PROCUREMENT PLAN Project information: Jordan- Strengthening Reform Management in Jordan P171965 Project Implementation agency: Ministry of Planning and International Cooperation Date of the Procurement Plan: Jan. 22, 2020 Period covered by this Procurement Plan: six months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Ministry of Planning and International Cooperation (MoPIC) has clear regulations in place with regards to procurement responsibility. The majority of procurement activities of MoPIC is supply of goods and consultancy services with estimated cost not exceeding JD 20,000., such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. PROCUREMENT Jordan : Strengthening Reform Management in Jordan PLAN General Information Country: Jordan Bank’s Approval Date of the Original Procurement Plan: 2020-01-22 2021-07-12 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171965 GPN Date: Project Name: Strengthening Reform Management in Jordan Loan / Credit No: TF / B1168 Ministry of Planning and International Cooperation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1.1-CS-25 / Heath 1. Support to reform Single Stage - One TF / B1168 Post Request for Bids Open - National 29,250.00 0.00 Canceled 2020-01-27 2020-01-26 2020-02-01 2020-03-14 2020-02-11 2020-04-13 2020-02-23 2020-05-18 2020-11-14 insurance management Envelope C2-GO-3 / IT Equipment for 2. Strengthening the PIM-PPP Single Stage - One TF / B1168 Post Request for Bids Open - National 10,000.00 3,385.05 Completed 2020-01-28 2020-01-26 2020-02-02 2020-03-15 2020-02-11 2020-04-14 2020-02-18 2020-05-19 2020-03-02 2020-11-15 2020-04-30 PPP Unit framework and function Envelope C2-GO-4 / laptops for PPP 2. Strengthening the PIM-PPP Request for Single Stage - One TF / B1168 Post Limited 15,000.00 5,227.08 Completed 2020-03-07 2020-02-26 2020-05-02 2020-05-04 2020-10-29 2021-01-13 unit framework and function Quotations Envelope C2-GO-5 / Design, Supply and Installation of the 2. Strengthening the PIM-PPP Single Stage - One TF / B1168 Post Request for Bids Open - International 650,000.00 589,810.34 Signed 2020-05-05 2020-05-07 2020-05-10 2020-05-07 2020-06-21 2020-07-01 2020-07-21 2020-09-27 2020-08-25 2020-12-08 2021-02-21 National Registry of framework and function Envelope Investment Projects (NRIP) C1.1-GO-26 / Laptops and IT 1. Support to reform Single Stage - One TF / B1168 Post Request for Bids Open - National 28,600.00 0.00 Canceled 2020-06-30 2020-07-05 2020-08-16 2020-09-15 2020-10-20 2021-04-18 Equipment management Envelope C1.1-GO-28 / Laptops and IT 1. Support to reform Request for Single Stage - One TF / B1168 Post Limited 28,600.00 33,723.55 Signed 2020-08-15 2020-08-11 2020-10-10 2020-09-14 2021-04-08 Equipment management Quotations Envelope C1.1-GO-29 / Equip 1. Support to reform Single Stage - One Conference room-video TF / B1168 Post Request for Bids Open - National 98,870.00 0.00 Canceled 2020-10-13 2020-10-18 2020-11-29 2020-12-29 2021-02-02 2021-08-01 management Envelope conferencing at MoPIC 2. Strengthening the PIM-PPP Single Stage - One C2-GO-6 / PIM equipment TF / B1168 Post Request for Bids Open - National 19,800.00 0.00 Canceled 2020-12-13 2020-12-10 2020-12-18 2021-01-29 2021-02-28 2021-04-04 2021-10-01 framework and function Envelope C1.2-GO-18 / IT Equipment 1. Support to reform Single Stage - One TF / B1168 Post Request for Bids Open - National 7,000.00 3,996.42 Signed 2021-03-22 2021-03-14 2021-03-27 2021-03-24 2021-05-08 2021-04-04 2021-06-07 2021-04-18 2021-07-12 2021-05-20 2022-01-08 for FCCL- MoF management Envelope Under C2-GO-7 / Laptops and 2. Strengthening the PIM-PPP Request for Single Stage - One TF / B1168 Post Limited 19,800.00 0.00 Implementati 2021-07-06 2021-06-27 2021-08-31 2022-02-27 Printers for PIM unit framework and function Quotations Envelope on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2-CS-2 / PPP Regulations - Project Cycle Regulation/ Project Procurement and Tendering Procedures For projects under a certain Consultant 2. Strengthening the PIM-PPP threshold + Regulations for TF / B1168 Post Qualification Limited 200,000.00 359,348.69 Signed 2020-01-29 2020-02-04 2020-02-12 2020-03-03 2020-03-13 2020-06-03 2020-04-17 2020-06-08 2020-10-14 framework and function Direct proposals,PDF Selection regulations and Common Clause Regulations, PIM Regulations/ FCCL Regulations INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual 1. Support to reform C1.1-CS-4 / M&E Specialist TF / B1168 Post Consultant Direct 20,873.00 56,684.78 Signed 2019-09-16 2020-03-24 2019-09-26 2019-09-01 2019-10-17 2019-08-01 2019-11-21 2019-09-12 2020-05-19 management Selection Individual C1.1-CS-7 / Administrative 1. Support to reform TF / B1168 Post Consultant Direct 7,035.00 17,766.74 Signed 2019-09-02 2020-03-24 2019-09-12 2019-08-14 2019-10-03 2019-08-14 2019-11-07 2019-09-12 2020-05-05 Assistant management Selection Individual C1.1-CS-16 / Financial 1. Support to reform TF / B1168 Post Consultant Direct 2,461.00 44,005.64 Signed 2019-12-02 2020-03-24 2019-12-12 2020-04-09 2020-01-02 2020-08-17 2020-02-06 2020-10-01 2020-08-04 Manager management Selection Page 1 Individual C1.1-CS-17 / Procurement 1. Support to reform TF / B1168 Post Consultant Direct 2,101.00 38,928.07 Signed 2020-01-02 2020-03-24 2020-01-12 2020-04-09 2020-02-02 2020-08-17 2020-03-08 2020-11-01 2020-09-04 Manager management Selection C1.1-CS-19 / Legal/Policy Individual 1. Support to reform Consultant for the Reform TF / B1168 Post Consultant Limited 24,000.00 0.00 Canceled 2020-01-28 2020-01-23 2020-02-02 2020-02-23 2020-03-29 2020-09-25 management Secretariat Selection Individual 1. Support to reform C1.1-CS-24 / Consultant TF / B1168 Post Consultant Direct 14,124.00 0.00 Canceled 2020-02-03 2020-02-13 2020-03-05 2020-04-09 2020-10-06 management Selection Individual 1. Support to reform C1.1-CS-5 / Researcher 1 TF / B1168 Post Consultant Direct 10,369.00 27,360.77 Signed 2019-09-16 2020-03-24 2019-09-26 2019-08-14 2019-10-17 2020-09-01 2019-11-21 2019-09-12 2020-05-19 management Selection Individual 1. Support to reform C1.1-CS-8 / Logestic Officer TF / B1168 Post Consultant Direct 13,466.00 34,687.21 Signed 2019-09-16 2020-03-24 2019-09-26 2020-08-02 2019-10-17 2019-08-14 2019-11-21 2019-09-12 2020-05-19 management Selection Individual C1.1-CS-20 / Monitering and 1. Support to reform TF / B1168 Post Consultant Open 49,435.00 0.00 Canceled 2020-04-01 2020-03-02 2020-05-20 2020-06-10 2020-07-15 2021-01-11 Evaluation Manager management Selection Individual 1. Support to reform C1.1-CS-9 / Analyst 1 TF / B1168 Post Consultant Open 31,780.00 18,550.07 Completed 2020-04-01 2020-03-02 2020-05-20 2020-05-17 2020-06-10 2020-05-26 2020-07-15 2020-06-01 2021-01-11 2021-06-01 management Selection C1.1-CS-11 / Individual 1. Support to reform Communication and Reporting TF / B1168 Post Consultant Open 49,435.00 0.00 Canceled 2020-04-01 2020-03-02 2020-05-20 2020-06-10 2020-07-15 2021-01-11 management Manager Selection Individual C1.1-CS-12 / Sectoral 1. Support to reform TF / B1168 Post Consultant Open 42,373.00 0.00 Canceled 2020-04-01 2020-03-02 2020-05-20 2020-06-10 2020-07-15 2021-01-11 Reform Lead management Selection C1.1-CS-13 / Individual 1. Support to reform Macroeconomic and Fiscal TF / B1168 Post Consultant Open 33,898.00 0.00 Canceled 2020-05-01 2020-03-02 2020-06-19 2020-07-10 2020-08-14 2021-02-10 management Reform Lead Selection Individual C1.1-CS-14 / Business 1. Support to reform TF / B1168 Post Consultant Open 38,136.00 55,853.31 Signed 2020-04-01 2020-03-02 2020-05-20 2020-05-18 2020-06-10 2020-06-03 2020-07-15 2020-10-03 2021-01-11 Environment Lead management Selection C1.1-CS-15 / Labor, Gender Individual 1. Support to reform and Social Protection Reform TF / B1168 Post Consultant Open 42,373.00 0.00 Canceled 2020-04-01 2020-03-02 2020-05-20 2020-06-10 2020-07-15 2021-01-11 management Lead Selection Individual 1. Support to reform C1.1-CS-6 / Researcher 2 TF / B1168 Post Consultant Direct 14,124.00 0.00 Canceled 2020-03-02 2020-03-03 2020-03-12 2020-04-02 2020-05-07 2020-11-03 management Selection C1.2-CS-1 / Business analyst 1 to assist the Ministry of Industry, Trade, and Supply Individual 1. Support to reform (MoITS) to complete reforms TF / B1168 Post Consultant Open 19,500.00 0.00 Canceled 2020-05-05 2020-06-10 2020-06-23 2020-07-14 2020-08-18 2021-02-14 management on the Investor Journey (From Selection Registration, Licensing, and closure of business) C1.2-CS-2 / Business analyst 2 to assist the Ministry of Industry, Trade, and Supply Individual 1. Support to reform (MoITS) to complete reforms TF / B1168 Post Consultant Open 19,500.00 0.00 Canceled 2020-05-05 2020-06-10 2020-06-23 2020-07-14 2020-08-18 2021-02-14 management on the Investor Journey (From Selection Registration, Licensing, and closure of business) Individual C1.1-CS-21 / Environmental 1. Support to reform TF / B1168 Post Consultant Open 10,000.00 43,200.00 Signed 2020-06-30 2020-06-10 2020-08-18 2020-08-13 2020-09-08 2020-08-16 2020-10-13 2020-09-01 2021-04-11 Safeguard Specialist-part time management Selection C1.1-CS-22 / Social Individual 1. Support to reform Safeguards Specialist and TF / B1168 Post Consultant Open 28,000.00 0.00 Canceled 2020-06-30 2020-06-10 2020-08-18 2020-09-08 2020-10-13 2021-04-11 management Consultation Lead Selection Individual 2. Strengthening the PIM-PPP C2-CS-4 / ICT expert TF / B1168 Post Consultant Open 20,000.00 13,440.00 Completed 2020-06-30 2020-06-10 2020-08-18 2020-06-30 2020-09-08 2020-06-30 2020-10-13 2020-07-15 2021-04-11 2020-12-08 framework and function Selection Individual C1.2-CS-3 / Labor Market 1. Support to reform TF / B1168 Post Consultant Open 20,000.00 0.00 Canceled 2020-06-30 2020-06-10 2020-08-18 2020-09-08 2020-10-13 2021-04-11 Researcher management Selection Individual C1.2-CS-4 / Project 1. Support to reform TF / B1168 Post Consultant Open 26,000.00 0.00 Canceled 2020-06-30 2020-06-10 2020-08-18 2020-09-08 2020-10-13 2021-04-11 Management Specialist management Selection C1.2-CS-5 / Individual 1. Support to reform Communications and TF / B1168 Post Consultant Direct 17,500.00 59,097.32 Signed 2020-06-30 2020-07-01 2020-07-10 2020-06-20 2020-07-31 2020-06-21 2020-09-04 2020-06-24 2021-03-03 management Reporting coordinator Selection Individual C1.2-CS-6 / Value Chain 1. Support to reform TF / B1168 Post Consultant Direct 13,000.00 48,237.27 Signed 2020-06-01 2020-06-10 2020-06-11 2020-04-12 2020-07-02 2020-05-26 2020-08-06 2020-06-01 2021-02-02 Analysts (CRI)-1 management Selection Individual C1.2-CS-7 / Value Chain 1. Support to reform TF / B1168 Post Consultant Direct 8,000.00 29,195.50 Signed 2020-06-01 2020-06-10 2020-06-11 2020-04-12 2020-07-02 2020-05-25 2020-08-06 2020-06-01 2021-02-02 Analysts (CRI)-2 management Selection Individual C1.1-CS-20-2 / monitoring 1. Support to reform TF / B1168 Post Consultant Open 49,435.00 0.00 Canceled 2020-08-10 2020-09-01 2020-09-28 2020-10-19 2020-11-23 2021-05-22 and evaluation manager management Selection Individual C1.1-CS-12-2 / Sectoral 1. Support to reform TF / B1168 Post Consultant Open 42,373.00 47,813.82 Signed 2020-08-10 2020-09-01 2020-09-28 2021-05-26 2020-10-19 2021-05-26 2020-11-23 2021-06-01 2021-05-22 reform lead management Selection Page 2 C1.1-CS-13-2 / Individual 1. Support to reform Macroeconomic and fiscal TF / B1168 Post Consultant Open 33,898.00 0.00 Canceled 2020-08-10 2020-09-01 2020-09-28 2020-10-19 2020-11-23 2021-05-22 management reform lead Selection C1.1-CS-11-2 / Individual 1. Support to reform COMMUNICATION AND TF / B1168 Post Consultant Open 49,435.00 42,076.16 Signed 2020-08-10 2020-09-01 2020-09-28 2020-12-29 2020-10-19 2020-12-27 2020-11-23 2021-03-01 2021-05-22 management REPORTING MANAGER Selection C1.1-CS-15-2 / Labor, Individual 1. Support to reform gender, and social protection TF / B1168 Post Consultant Open 42,373.00 56,420.31 Signed 2020-08-10 2020-09-01 2020-09-28 2020-12-29 2020-10-19 2020-12-31 2020-11-23 2021-03-01 2021-05-22 management reform lead Selection C1.1-CS-22-2 / social Individual 1. Support to reform safeguards specialist and TF / B1168 Post Consultant Open 28,000.00 0.00 Canceled 2020-08-10 2020-09-01 2020-09-28 2020-10-19 2020-11-23 2021-05-22 management consultation lead Selection Individual C1.2-CS-1-2 / business 1. Support to reform TF / B1168 Post Consultant Open 19,500.00 21,994.36 Signed 2020-08-10 2020-09-01 2020-09-28 2020-12-29 2020-10-19 2021-03-14 2020-11-23 2021-04-15 2021-05-22 analyst 1 -MoITS management Selection Individual C1.2-CS-2-2 / Business 1. Support to reform TF / B1168 Post Consultant Open 19,500.00 24,863.19 Signed 2020-08-10 2020-09-01 2020-09-28 2020-12-29 2020-10-19 2020-12-31 2020-11-23 2021-03-01 2021-05-22 analyst 2 for MoITS management Selection Individual C1.2-CS-3-2 / labor market 1. Support to reform TF / B1168 Post Consultant Open 20,000.00 0.00 Canceled 2020-08-10 2020-09-01 2020-09-28 2020-10-19 2020-11-23 2021-05-22 researcher management Selection Individual C1.2-CS-4-2 / project 1. Support to reform TF / B1168 Post Consultant Open 26,000.00 0.00 Canceled 2020-08-10 2020-09-01 2020-09-28 2020-10-19 2020-11-23 2021-05-22 management specialist-MoL management Selection Individual C1.2-CS-8 / Graphic 1. Support to reform TF / B1168 Post Consultant Direct 3,600.00 2,800.00 Signed 2020-08-10 2020-06-24 2020-08-20 2020-08-13 2020-09-10 2020-08-16 2020-10-15 2020-09-01 2021-04-13 Designer management Selection Individual 1. Support to reform C1.2-CS.8 / Graphic Designer TF / B1168 Post Consultant Direct 3,600.00 0.00 Canceled 2020-08-01 2020-08-11 2020-09-01 2020-09-23 2021-03-22 management Selection Individual C1.2-CS.9 / Senior Economic 1. Support to reform TF / B1168 Post Consultant Open 28,776.00 0.00 Canceled 2020-08-25 2020-09-01 2020-10-13 2020-11-03 2020-12-08 2021-06-06 Policy Analyst 1-MOF management Selection C1.2-CS.10 / Senior Individual 1. Support to reform Economic Policy Analyst 2- TF / B1168 Post Consultant Open 28,776.00 0.00 Canceled 2020-08-25 2020-09-01 2020-10-13 2020-11-03 2020-12-08 2021-06-06 management MOF Selection C1.2-CS.11 / Senior Individual 1. Support to reform Economic Policy Analyst 3- TF / B1168 Post Consultant Open 28,776.00 0.00 Canceled 2020-08-25 2020-09-01 2020-10-13 2020-11-03 2020-12-08 2021-06-06 management MOF Selection C1.2-CS.12 / Senior Individual 1. Support to reform Economic Policy Analyst 4- TF / B1168 Post Consultant Open 28,776.00 0.00 Canceled 2020-08-25 2020-09-01 2020-10-13 2020-11-03 2020-12-08 2021-06-06 management MOF Selection Individual C1.2-CS.13 / Sustainable 1. Support to reform TF / B1168 Post Consultant Direct 24,000.00 29,000.00 Signed 2020-08-25 2020-08-24 2020-09-04 2020-09-02 2020-09-25 2020-09-16 2020-10-30 2020-09-20 2021-04-28 Development Advisor- MEMR management Selection Individual C2-CS-3 / Deputy Director of 2. Strengthening the PIM-PPP TF / B1168 Post Consultant Open 59,322.00 0.00 Canceled 2020-10-01 2020-09-29 2020-11-19 2020-12-10 2021-01-14 2021-07-13 PIM framework and function Selection Individual C2-CS-6 / Project 2. Strengthening the PIM-PPP TF / B1168 Post Consultant Open 27,119.00 23,906.91 Signed 2020-10-01 2020-09-29 2020-11-19 2021-03-15 2020-12-10 2021-03-15 2021-01-14 2021-03-22 2021-07-13 Management Specialist framework and function Selection Individual C1.2-CS-14 / international 1. Support to reform TF / B1168 Post Consultant Direct 27,119.00 29,619.18 Signed 2020-10-01 2020-10-07 2020-10-11 2020-11-03 2020-11-01 2020-12-03 2020-12-06 2020-12-15 2021-06-04 cooperation advisor management Selection Individual C2-CS-7 / ICT expert 2-full 2. Strengthening the PIM-PPP TF / B1168 Post Consultant Direct 50,000.00 37,235.54 Signed 2020-11-25 2020-10-20 2020-12-05 2020-11-29 2020-12-26 2020-12-01 2021-01-30 2020-12-15 2021-12-30 time framework and function Selection C1.2-CS-16 / Drafting of 1. Support to reform Investemnet law and TF / B1168 Post Direct Selection Direct 50,000.00 68,716.50 Signed 2020-12-13 2020-11-26 2020-12-23 2020-12-15 2021-02-26 2021-05-16 2021-08-25 management regulations C1.2-CS-17 / upgrading 1. Support to reform Under TF / B1168 Post Direct Selection Direct 141,250.00 0.00 2021-01-20 2021-03-01 2021-01-30 2021-03-02 2021-04-05 2021-10-02 ISTD system management Implementation Individual C1.2-CS-19 / Financial 1. Support to reform TF / B1168 Post Consultant Open 34,000.00 0.00 Canceled 2021-01-20 2021-03-24 2021-03-10 2021-03-31 2021-05-05 2022-05-01 Specialist-FCCL-MoF management Selection Individual C1.2-CS.20 / 1. Support to reform TF / B1168 Post Consultant Open 34,000.00 0.00 Canceled 2021-01-20 2021-03-24 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Macroeconomist-FCCL-MoF management Selection Individual 1. Support to reform C1.1-CS.6 / Researcher 2 TF / B1168 Post Consultant Open 14,124.00 1,191.82 Completed 2020-04-01 2020-03-01 2020-05-20 2020-05-17 2020-06-10 2020-05-17 2020-07-15 2020-05-18 2021-01-11 2021-05-31 management Selection Individual C2-CS-5 / Economic and 2. Strengthening the PIM-PPP TF / B1168 Post Consultant Open 37,288.00 0.00 Canceled 2020-10-01 2020-09-29 2020-11-19 2020-12-10 2021-01-14 2021-07-13 Financial Specialist framework and function Selection Individual C1.2-CS.21 / Senior Legal 1. Support to reform Under TF / B1168 Post Consultant Open 16,950.00 15,300.42 2021-03-30 2021-03-24 2021-05-18 2021-05-27 2021-06-08 2021-05-30 2021-07-13 2022-01-09 Researcher management Implementation Selection Individual C1.2-CS.22 / Legal Research 1. Support to reform Under TF / B1168 Post Consultant Open 22,000.00 19,125.53 2021-03-30 2021-03-24 2021-05-18 2021-05-27 2021-06-08 2021-06-13 2021-07-13 2022-01-09 Officer management Implementation Selection Page 3 Individual C2-CS-5-2 / Economic and 2. Strengthening the PIM-PPP Under TF / B1168 Post Consultant Open 37,288.00 0.00 2021-04-01 2021-03-24 2021-05-20 2021-06-10 2021-07-15 2022-01-11 Financial Specialist-Relaunch framework and function Implementation Selection Individual C1.1-CS-30 / Program 1. Support to reform TF / B1168 Post Consultant Open 15,740.00 16,256.70 Signed 2021-04-15 2021-04-06 2021-06-03 2021-06-06 2021-06-24 2021-06-07 2021-07-29 2021-06-14 2022-01-25 Coordinator management Selection C1.1-CS-31 / Economic and Individual 1. Support to reform Business Environment Reform TF / B1168 Post Consultant Open 40,620.00 47,813.82 Signed 2021-04-15 2021-04-06 2021-06-03 2021-05-27 2021-06-24 2021-05-27 2021-07-29 2021-06-01 2022-01-25 management Lead Selection Individual C1.1-CS-32 / Monitoring and 1. Support to reform Under TF / B1168 Post Consultant Open 18,620.00 0.00 2021-05-20 2021-05-26 2021-07-08 2021-07-29 2021-09-02 2022-03-01 Evaluation Officer management Implementation Selection Individual 1. Support to reform C1.2-CS-23 / Researcher TF / B1168 Post Consultant Direct 18,000.00 17,461.61 Signed 2021-06-01 2021-06-01 2021-06-11 2021-05-31 2021-07-02 2021-05-31 2021-08-06 2021-05-31 2022-02-02 management Selection Individual C2-CS-8 / Education Sector 2. Strengthening the PIM-PPP Under TF / B1168 Post Consultant Open 48,000.00 0.00 2021-06-25 2021-06-14 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Specilalist framework and function Implementation Selection Individual C2-CS-9 / Energy Sectoral 2. Strengthening the PIM-PPP Under TF / B1168 Post Consultant Open 48,000.00 0.00 2021-06-25 2021-06-14 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Specilaist framework and function Implementation Selection Individual C2-CS-10 / Environement 2. Strengthening the PIM-PPP Under TF / B1168 Post Consultant Open 48,000.00 0.00 2021-06-25 2021-06-14 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Sectoral Specilaist framework and function Implementation Selection Individual C2-CS-11 / Health Sectoral 2. Strengthening the PIM-PPP Under TF / B1168 Post Consultant Open 48,000.00 0.00 2021-06-25 2021-06-14 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Specialist framework and function Implementation Selection Individual C2-CS-12 / Tourism Sectoral 2. Strengthening the PIM-PPP Under TF / B1168 Post Consultant Open 48,000.00 0.00 2021-06-25 2021-06-14 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Specilaist framework and function Implementation Selection Individual C2-CS-13 / Transport 2. Strengthening the PIM-PPP Under TF / B1168 Post Consultant Open 48,000.00 0.00 2021-06-25 2021-06-14 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Sectoral Specilaist framework and function Implementation Selection Individual C2-CS-14 / Agriculture 2. Strengthening the PIM-PPP Under TF / B1168 Post Consultant Open 48,000.00 0.00 2021-06-25 2021-06-14 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Sectoral Specilaist framework and function Implementation Selection C1.2-CS-24 / Fccl Training- 1. Support to reform TF / B1168 Post Direct Selection Direct 3,000.00 2,820.87 Signed 2021-06-01 2021-05-03 2021-06-11 2021-05-23 2021-08-15 2021-06-05 2022-02-11 Capacity Building (Excel VBA) management C1.2-CS-25 / Upgrade the 1. Support to reform Under CRM system to include the TF / B1168 Post Direct Selection Direct 32,500.00 0.00 2021-07-01 2021-06-20 2021-07-11 2021-09-14 2022-03-13 management Implementation IGM module Individual C1.1-CS-33 / Social 1. Support to reform Under TF / B1168 Post Consultant Open 19,000.00 0.00 2021-07-01 2021-06-24 2021-08-19 2021-09-09 2021-10-14 2022-04-12 Safeguards Officer management Implementation Selection C2-CS-15 / Capacity Building 2. Strengthening the PIM-PPP Under for PPP unit in PPP TF / B1168 Post Direct Selection Direct 22,500.00 0.00 2021-07-01 2021-06-24 2021-07-11 2021-09-14 2022-03-13 framework and function Implementation Procurement and Financing Individual C1.1-CS-34 / Labor, Gender 1. Support to reform Under TF / B1168 Post Consultant Open 20,000.00 0.00 2021-07-01 2021-06-24 2021-08-19 2021-09-09 2021-10-14 2022-04-12 and Social Protection Analyst management Implementation Selection Individual C2-CS-16 / PPP Project 2. Strengthening the PIM-PPP Under TF / B1168 Post Consultant Open 30,000.00 0.00 2021-07-05 2021-07-08 2021-08-23 2021-09-13 2021-10-18 2022-04-16 Finance Associate framework and function Implementation Selection Individual C2-CS-17 / PPP Economic 2. Strengthening the PIM-PPP Under TF / B1168 Post Consultant Open 30,000.00 0.00 2021-07-05 2021-07-08 2021-08-23 2021-09-13 2021-10-18 2022-04-16 Associate framework and function Implementation Selection Individual C1.2-CS-26 / Economic 1. Support to reform TF / B1168 Post Consultant Open 25,000.00 0.00 Under Review 2021-07-20 2021-07-12 2021-09-07 2021-09-28 2021-11-02 2022-05-01 Analyst management Selection Individual 1. Support to reform C1.2-CS-27 / Researcher TF / B1168 Post Consultant Open 19,200.00 0.00 Under Review 2021-07-20 2021-07-12 2021-09-07 2021-09-28 2021-11-02 2022-05-01 management Selection Individual C1.2-CS-19-2 / Financial 1. Support to reform Pending TF / B1168 Post Consultant Open 34,000.00 0.00 2021-07-30 2021-09-17 2021-10-08 2021-11-12 2022-05-11 Analyst-FCCL management Implementation Selection Individual C1.2-CS.20-2 / 1. Support to reform Pending TF / B1168 Post Consultant Open 34,000.00 0.00 2021-07-30 2021-09-17 2021-10-08 2021-11-12 2022-05-11 Macroeconomist-FCCL management Implementation Selection Page 4