Large Scale Irrigation Modernization Project
                                  Procurement Plan

I. General

1.     Bank’s approval Date of the procurement Plan [Original: 5 may 2015]: Revision 2 of
       Updated Procurement Plan, March 28, 2017
2.     Date of General Procurement Notice: Dec 24, 2006
3.     Period covered by this procurement plan: First 18 months


II. Goods and Works and non-consulting services.

1.     Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as
       stated in Appendix 1 to the Guidelines for Procurement:

                        Procurement Method           Prior Review Threshold        Comments
                                                              US$
          1.    Works                                Above US$ 15 million              All
          2.    Goods                                Above US$ 4 million               All
          3.    Non-Consultant Services              Above US$ 4 million               All

2.     Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with
       the provisions of paragraphs 2.9 and 2.10 of the Guidelines.

3.     Proposed Procedures for CDD Components (as per paragraph. 3.17 of the
       Guidelines:

4.     Reference to (if any) Project Operational/Procurement Manual:

5.     Any Other Special Procurement Arrangements:

6.     Summary of the Procurement Packages planned during the first 18 months after project
       effectiveness ( including those that are subject to retroactive financing and advanced
       procurement)


III. Selection of Consultants

1.     Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated
       in Appendix 1 to the Guidelines Selection and Employment of Consultants:

                           Selection Method          Prior Review Threshold        Comments
          1.    Competitive Methods (Firms)            Above US$ 2 million
          2.    Single Source                                  All
          3.    Individual                             Above US$ 400,000

July 9, 2010
2.     Short list comprising entirely of national consultants: Short list of consultants for
       services, estimated to cost less than $_equivalent per contract, may comprise entirely of
       national consultants in accordance with the provisions of paragraph 2.7 of the Consultant
       Guidelines.
3.     Any Other Special Selection Arrangements:

4.     Consultancy Assignments with Selection Methods and Time Schedule




July 9, 2010
PROCUREMENT
                                Morocco : MA-Large Scale Irrigation Modernization Project
PLAN
General Information
Country:                        Morocco                           Bank’s Approval Date of the Original Procurement Plan:                  2017-03-31
                                                                                                                             2019-01-07
                                                                  Revised Plan Date(s): (comma delineated, leave blank if none)
Project ID:                     P150930                           GPN Date:
Project Name:                   MA-Large Scale Irrigation Modernization Project
Loan / Credit No:               IBRD / 85140
Executing Agency(ies): Office Regionale de Mise en Valeur Agricole de TADLA (ORMVA TADLA



WORKS
                                                                                                                                                                                                                                                                                                                                      Bid Evaluation
Activity Reference No. /                                                                                                                                                                                                                      Draft Bidding
                                Loan / Credit                                                           Market         Procurement        Prequalification Actual Amount       Process     Draft Pre-qualification     Prequalification                         Specific Procurement   Bidding Documents   Proposal Submission /        Report and
         Description                               Component        Review Type        Method                                                                                                                                                  Document /                                                                                                  Signed Contract     Contract Completion
                                      No.                                                              Approach           Process             (Y/N)           (US$)             Status          Documents             Evaluation Report                          Notice / Invitation       as Issued        Opening / Minutes      Recommendation for
                                                                                                                                                                                                                                              Justification
                                                                                                                                                                                                                                                                                                                                           Award
                                                                                                                                                                                            Planned      Actual       Planned    Actual   Planned      Actual   Planned      Actual    Planned    Actual    Planned     Actual     Planned      Actual   Planned      Actual   Planned      Actual


 REF-14/2016/TA-DA /
Travaux du laboratoire pour
                                                                                                                     Single Stage - One
le contrôle de qualité pour     IBRD / 85140                      A posteriori    Appel d'offres   Open - National                                             215,224.65    Signé                                                        2016-03-16            2016-03-28                                 2016-04-21              2016-04-21            2016-04-21            2016-04-21
                                                                                                                     Envelope
secteur M et G et travaux
bassin




 REF-28/2016/TA-DA /
Travaux d'exécution des
conduites du réseau de                                                                                               Single Stage - One
                                IBRD / 85140                      A posteriori    Appel d'offres   Open - National                                           10,333,713.35   Signé                                                        2016-06-28            2016-07-12                                 2016-09-06              2016-09-06            2016-09-06            2016-09-06
distribution   y compris                                                                                             Envelope
ouvrage annexes des secteurs
M10-M18 ( L1 )




 REF-29/2016/TA-DA /
Travaux d'exécution de la                                                                                            Single Stage - One
                                IBRD / 85140                      A posteriori    Appel d'offres   Open - National                                            7,025,507.78   Signé                                                        2016-06-28            2016-07-12                                 2016-09-06              2016-09-06            2016-09-06            2016-09-06
conduite d'adducteur A5 des                                                                                          Envelope
secteurs M10-M18 ( L2 )




 REF-10/2017/TA-DA /
Travaux de réalisation des
prises bornes,prises
                                                                                                                     Single Stage - One
propriétés et les conduite de   IBRD / 85140                      A posteriori    Appel d'offres   Open - National                                            4,909,254.84   Signé                                                        2017-01-03            2017-01-17                                 2017-02-28              2017-02-28            2017-02-28            2017-02-28
                                                                                                                     Envelope
raccordement y compris la
télégestion des secteurs M10-
M13 (Lot 1)




 REF-15/2017/TA-DA /
Travaux d'exécution des                                                                                              Single Stage - One
                                IBRD / 85140                      A posteriori    Appel d'offres   Open - National                                            7,211,688.62   Signé                                                        2017-02-07            2017-02-17                                 2017-03-14              2017-03-14            2017-03-14            2017-03-14
conduites d'adducteur A6 des                                                                                         Envelope
secteurs G13-G18




 REF-11/2017/TA-DA /
Travaux de réalisation des
prises bornes,prises
                                                                                                                     Single Stage - One
propriétés et les conduite de   IBRD / 85140                      A posteriori    Appel d'offres   Open - National                                            4,047,710.58   Signé                                                        2017-01-03            2017-01-17                                 2017-02-28              2017-02-28            2017-02-28            2017-02-28
                                                                                                                     Envelope
raccordement y compris la
télégestion des secteurs
M14-M18 (Lot 2)




 REF-40/2015/TA-DA /
Travaux d'exécution des
conduites des adducteurs A5,
                                                                                                                     Single Stage - One                                      En attente
A6-1 et A6-2 de la partie       IBRD / 85140                      A posteriori    Appel d'offres   Open - National                                                    0.00                                                                2015-11-10            2015-11-23                                 2015-12-17              2015-12-17            2015-12-17            2015-12-17
                                                                                                                     Envelope                                                d'exécution
amont sur 5.3 km y compris
les ouvrages de prises
principaux




 REF-30/2017/TA-DA /
Fourniture et installation du
matériel d'équipement de la                                                                                          Single Stage - One                                      En attente
                                IBRD / 85140                      A posteriori    Appel d'offres   Open - National                                                    0.00                                                                2017-03-24            2017-03-29                                 2017-05-10              2017-06-09            2017-07-14            2018-01-10
station de filtration du                                                                                             Envelope                                                d'exécution
secteur M10/M18 y compris
génie civil.




                                                                                                                                                                                                             Page 1
 REF-32/2017/TA-DA /
Travaux de construction d'un                                                                                     Single Stage - One                                      En attente
                                 IBRD / 85140                A posteriori    Appel d'offres    Open - National                                                    0.00                                                                2017-05-25            2017-05-30                                 2017-07-11              2017-08-10            2017-09-14            2018-03-13
bassin de régulation                                                                                             Envelope                                                d'exécution
hydraulique ( 1ère Tranche )




 REF-40/2017/TA-DA /
Travaux de génie civil, de
fourniture,transport et pose
de conduites   et
                                                                                                                 Single Stage - One                                      En attente
équipements nécessaires,         IBRD / 85140                A posteriori    Appel d'offres    Open - National                                                    0.00                                                                2018-01-22            2018-01-27                                 2018-03-10              2018-04-09            2018-05-14            2018-11-10
                                                                                                                 Envelope                                                d'exécution
pour la réalisation des
réseaux de distribution d'eau
d'irrigation des secteurs G15
Bis- G18




 REF-41/2017/TA-DA /
Travaux de génie civil, de
fourniture,transport et pose
de conduites   et
                                                                                                                 Single Stage - One                                      En attente
équipements nécessaires,         IBRD / 85140                A posteriori    Appel d'offres    Open - National                                                    0.00                                                                2018-01-22            2018-01-27                                 2018-03-10              2018-04-09            2018-05-14            2018-11-10
                                                                                                                 Envelope                                                d'exécution
pour la réalisation des
réseaux de distribution d'eau
d'irrigation des secteurs G13-
G15




 REF-16/2018/TA-DA /
                                                                                                                 Single Stage - One                                      En attente
Fourniture et installation       IBRD / 85140                A posteriori    Appel d'offres    Open - National                                                    0.00                                                                2018-11-06            2018-11-11                                 2018-12-23              2019-01-22            2019-02-26            2019-08-25
                                                                                                                 Envelope                                                d'exécution
des stations de filtration




 REF-03/2019/TA-DA /
Travaux d'execution des                                                                                          Single Stage - One                                      En attente
                                 IBRD / 85140                A posteriori    Appel d'offres    Open - National                                                    0.00                                                                2019-03-01            2019-03-06                                 2019-04-17              2019-05-17            2019-06-21            2019-12-18
prises bornes et prises                                                                                          Envelope                                                d'exécution
propriétés secteur G




 REF-02/2019/TA-SMG /
Aménagement et équipement                                                                                        Single Stage - One                                      En attente
                                 IBRD / 85140                A posteriori    Demande de prix   Limited                                                            0.00                                                                                      2019-03-20                                                                               2019-05-15            2019-11-11
des locaux administratifs                                                                                        Envelope                                                d'exécution
dans la zone de reconversion




GOODS
                                                                                                                                                                                                                                                                                                                                  Bid Evaluation
Activity Reference No. /                                                                                                                                                                                                                  Draft Bidding
                                 Loan / Credit                                                      Market         Procurement        Prequalification Actual Amount       Process     Draft Pre-qualification     Prequalification                         Specific Procurement   Bidding Documents   Proposal Submission /        Report and
        Description                              Component     Review Type        Method                                                                                                                                                   Document /                                                                                                  Signed Contract     Contract Completion
                                       No.                                                         Approach           Process             (Y/N)           (US$)             Status          Documents             Evaluation Report                          Notice / Invitation       as Issued        Opening / Minutes      Recommendation for
                                                                                                                                                                                                                                          Justification
                                                                                                                                                                                                                                                                                                                                       Award
                                                                                                                                                                                        Planned      Actual       Planned    Actual   Planned      Actual   Planned      Actual    Planned    Actual    Planned     Actual     Planned      Actual   Planned      Actual   Planned      Actual


 REF-37/2016/TA-DGRID /
Fournitures de materiel pour
le suivi des paramètres de                                                                                       Single Stage - One                                      En attente
                                 IBRD / 85140                A posteriori    Appel d'offres    Open - National                                                    0.00                                                                2017-01-22            2017-01-27                                 2017-03-10              2017-04-09            2017-05-14            2017-11-10
la nappe au niveau des                                                                                           Envelope                                                d'exécution
secteurs M10/M18 et
G13/G18




 REF-58/2017/TA-SMG /
                                                                                                                 Single Stage - One                                      En attente
Aménagement et équipement        IBRD / 85140                A posteriori    Demande de prix   Limited                                                            0.00                                                                                      2017-12-20                                                                               2018-02-14            2018-08-13
                                                                                                                 Envelope                                                d'exécution
des locaux administratifs




 REF-59/2017/TA-SMG /                                                                                            Single Stage - One                                      En attente
                                 IBRD / 85140                A posteriori    Demande de prix   Limited                                                            0.00                                                                                      2017-12-11                                                                               2018-02-05            2018-08-04
Mobilier de bureau                                                                                               Envelope                                                d'exécution




 REF-08/2016/TA-SMG /                                                                                            Single Stage - One                                      En attente
                                 IBRD / 85140                A posteriori    Demande de prix   Limited                                                            0.00                                                                                      2016-04-11                                                                               2016-06-06            2016-12-03
Acquisition micro ordinateurs                                                                                    Envelope                                                d'exécution




 REF-17/2016/TA-SMG /                                                                                            Single Stage - One                                      En attente
                                 IBRD / 85140                A posteriori    Demande de prix   Limited                                                            0.00                                                                                      2016-05-21                                                                               2016-07-16            2017-01-12
Acquisition tablette tactile                                                                                     Envelope                                                d'exécution




                                                                                                                                                                                                         Page 2
 REF-66/2017/TA-SMG /
Aménagement et équipement                                                                                        Single Stage - One                                             En attente
                               IBRD / 85140                A posteriori    Demande de prix     Limited                                                                   0.00                                                                                              2018-01-12                                                                                           2018-03-09                2018-09-05
des locaux administratifs                                                                                        Envelope                                                       d'exécution
dans la zone de reconversion




 REF-12/2017/TA-SMG /
                                                                                                                 Single Stage - One                                             En attente
Achat de matériel              IBRD / 85140                A posteriori    Demande de prix     Limited                                                                   0.00                                                                                              2017-05-15                                                                                           2017-07-10                2018-01-06
                                                                                                                 Envelope                                                       d'exécution
informatique




 REF-01/2019/TA-SMG /
Aménagement et équipement                                                                                        Single Stage - One                                             En attente
                               IBRD / 85140                A posteriori    Demande de prix     Limited                                                                   0.00                                                                                              2019-04-06                                                                                           2019-06-01                2019-11-28
des locaux administratifs                                                                                        Envelope                                                       d'exécution
dans la zone de reconversion




NON CONSULTING SERVICES
                                                                                                                                                                                                                                                                                                                                                         Bid Evaluation
Activity Reference No. /                                                                                                                                                                                                                              Draft Bidding
                               Loan / Credit                                                        Market         Procurement        Prequalification Actual Amount              Process     Draft Pre-qualification       Prequalification                               Specific Procurement      Bidding Documents      Proposal Submission /          Report and
         Description                           Component     Review Type        Method                                                                                                                                                                 Document /                                                                                                                 Signed Contract         Contract Completion
                                     No.                                                           Approach           Process             (Y/N)                  (US$)             Status          Documents              Evaluation Report                                 Notice / Invitation          as Issued           Opening / Minutes        Recommendation for
                                                                                                                                                                                                                                                      Justification
                                                                                                                                                                                                                                                                                                                                                              Award
                                                                                                                                                                                               Planned      Actual        Planned     Actual      Planned      Actual       Planned      Actual      Planned    Actual       Planned      Actual      Planned       Actual      Planned       Actual      Planned      Actual


 REF-29/2017/TA-DGRID /
Mise à niveau de la station
                                                                                                                 Single Stage - One                                             En attente
des éxpérimentations hydro     IBRD / 85140                A posteriori    Demande de prix     Limited                                                                   0.00                                                                                              2017-02-19                                                                                           2017-04-16                2017-10-13
                                                                                                                 Envelope                                                       d'exécution
agricoles de Oulad Gnaou (
Expertise + Etude)




 REF-21/2017/DGRID /
Réalisation de la situation
                                                                                                                 Single Stage - One                                             En cours
de référence des paramètres    IBRD / 85140                A posteriori    Appel d'offres      Open - National                                                           0.00                                                                     2017-05-08               2017-05-11                                       2017-06-20                2017-06-30                2017-08-09                2018-02-05
                                                                                                                 Envelope                                                       d'exécution
environnenomentaux et mise
en place d'un PGES




 REF-04/2019/TA-DGRID /
Assistance technique et
accompagnement pour                                                                                              Single Stage - One                                             En attente
                               IBRD / 85140                A posteriori    Appel d'offres      Open - National                                                           0.00                                                                     2019-10-01               2019-10-06                                       2019-11-17                2019-12-17                2020-01-21                2020-07-19
l'exploitation et la                                                                                             Envelope                                                       d'exécution
maintenance des
équipements hydro-agricoles




CONSULTING FIRMS
Activity Reference No. /                                                                                                                                                                                                                                                                                                                 Combined Evaluation
                               Loan / Credit                                                        Market        Contract Type       Actual Amount                                                       Expression of Interest Short List and Draft Request for Proposals Opening of Technical                     Evaluation of
         Description                           Component     Review Type        Method                                                                   Process Status           Terms of Reference                                                                                                                                      Report and Draft            Signed Contract        Contract Completion
                                     No.                                                           Approach                               (US$)                                                                    Notice           Request for Proposals             as Issued         Proposals / Minutes     Technical Proposal
                                                                                                                                                                                                                                                                                                                                         Negotiated Contract
                                                                                                                                                                                  Planned       Actual     Planned        Actual      Planned      Actual      Planned       Actual     Planned      Actual    Planned       Actual      Planned       Actual      Planned       Actual      Planned       Actual


 MOF-REF-23 / Assistance
                                                                           Sélection fondée
technique pour le suivi et                                                                     Open -
                               IBRD / 85140                A priori        sur la qualité et                                              1,407,946.04   Signé                   2015-04-23                2015-05-24                2015-07-07                                         2016-03-10             2016-04-07                2016-05-04                2016-08-08                2020-08-21
contrôle des travaux des                                                                       International
                                                                           le coût
secteurs M10-M18




 MOF-REF-24 / Assistance
                                                                           Sélection fondée
technique pour le suivi et                                                                     Open -
                               IBRD / 85140                A priori        sur la qualité et                                              1,095,553.21   Signé                   2016-07-26                2016-08-16                2016-09-29                                         2016-10-27             2016-11-26                2016-12-31                2017-02-04                2018-02-04
contrôle des travaux des                                                                       International
                                                                           le coût
secteurs G13-G18




 REF-01/2017/DDA / Appuis
                                                                           Sélection fondée
aux agriculteurs pour la                                                                       Open -                                                    En cours
                               IBRD / 85140                A priori        sur la qualité et                                                      0.00                           2016-08-27                2016-09-17                2016-10-31                                         2016-11-28             2016-12-28                2017-02-01                2017-03-08                2018-03-08
valorisation de l'eau                                                                          International                                             d'exécution
                                                                           le coût
d'irrigation




INDIVIDUAL CONSULTANTS