The World Bank                                                                                                                                             Report No: ISR9137


                                                                                                    Implementation Status & Results
                                                                                                    Philippines
                                                           National Program Support for Environment and Natural Resources Management Project (P096174)
Public Disclosure Copy




                         Operation Name: National Program Support for Environment and Natural              Project Stage:   Implementation         Seq.No: 11      Status: ARCHIVED    Archive Date:    12-Feb-2013
                                          Resources Management Project (P096174)
                                                                             Country: Philippines                                   Approval FY:        2007
                         Product Line: IBRD/IDA                              Region: EAST ASIA AND PACIFIC                          Lending Instrument: Sector Investment and Maintenance Loan
                         Implementing Agency(ies):

                         Key Dates
                         Board Approval Date      26-Jun-2007         Original Closing Date 31-Dec-2012             Planned Mid Term Review Date 30-Jun-2010               Last Archived ISR Date 07-Aug-2012
                         Effectiveness Date       27-Nov-2007         Revised Closing Date 31-Dec-2013              Actual Mid Term Review Date     28-May-2010

                         Project Development Objectives
                         National Program Support for Environment and Natural Resources Management Project (P096174)
                         Project Development Objective (from Project Appraisal Document)
                         The program's overall development objective is to assist the Department of Environment and Natural Resources to improve efficiency and effectiveness in its service
                         delivery. More specifically, the project would aim to strengthen the allocative efficiency of DENR's limited budget resources through better prioritization and partnership
                         arrangements, facilitating scaling-up and better linking of plans and budgets.
                         Has the Project Development Objective been changed since Board Approval of the Program?

                            Yes           No

                         GEF Program supporting the National Program for Environment and Natural Resources Management Project (P091147)
                         Global Environmental Objective (from Project Appraisal Document)
                         Global Environment objective Ref. PAD B.2, Technical Annex 3
                          The global environment objective of the program would be to enhance ecosystem services for global and local benefits. Specific global objectives would be addressed
                         through GEF financing in strategic areas to enhance ecosystem services for global and local benefits. The global environment objective would be achieved by applying
                         an integrated ecosystem management (IEM) approach in priority watershed areas and selected sites of global significance.
Public Disclosure Copy




                         Has the Global Environmental Objective been changed since Board Approval of the Program?

                            Yes           No


                         Component(s)
                         Component Name                                                                                                           Component Cost
                         Policy, Planning, Monitoring and Evaluation                                                                                      38.14
                         Integrated Ecosystem Management                                                                                                  14.09
                         Strengthening Environment and Natural Resources Management                                                                        4.77



                                                                                                                                                                                                          Page 1 of 10
                             The World Bank                                                                                                                                        Report No: ISR9137



                         Overall Ratings
                                                                Previous Rating                           Current Rating
                         Progress towards achievement of PDO    Moderately Satisfactory                   Satisfactory
Public Disclosure Copy




                         Progress towards achievement of GEO    Moderately Satisfactory                   Satisfactory
                         Overall Implementation Progress (IP)   Moderately Satisfactory                   Satisfactory
                         Overall Risk Rating                    High                                      High

                         Implementation Status Overview
                         During the past six months the project has made commendable progress towards achieving its development objectives with most of its 15 outcome and intermediate level indicators
                         having been fully or partially achieved. For the Development Objective indicators, the targets for reduction in particulate matter and ecosystems investments have already been fully
                         achieved; the rationalization plans for the Department of Environment and Natural Resources (DENR's) Bureaus have been prepared and now await approval by the Department of
                         Budget and Management (DBM); and a follow up to the baseline survey is to be completed in June of 2013 which will determine the change in public satisfaction with DENR's
                         services. Both Global Environmental Indicators have already been achieved. Other major achievements include: (a) completion of forest boundary delineation including production of
                         maps; (b) significant progress on the cadastral surveys; (c) advances in the Manila Bay clean-up activity; (d) institutionalization of the Management Effectiveness Tracking Tool at all
                         protected areas being supported by the project; (e) standardized procedures for the issuance of tenure instruments; and (f) approaches for the rehabilitation of abandoned mines
                         tested and piloted. Given this improved performance, including accelerated disbursement (82% of loan funds and 78% of the grant) together with satisfactory performance on
                         procurement and financial management, the Bank has agreed to government's request for a one year extension for the ENRMP loan and grant from December 31, 2012 to December
                         31, 2013 in order to fully utilize the project funds. During this extended period the major activities under the loan would be: a) the National Greening Program, b) Comprehensive
                         cadastral surveying, c) The Manila Bay & Inland Waterway “clean-up�? program; and d) Installation and operationalization of the MIS; while for the GEF grant on-going activities in
                         integrated ecosystems management would be completed, with increased attention given to livelihood activities.


                         Locations
                         Country                                                  First Administrative Division              Location                                    Planned              Actual
                         Philippines                                              Zamboanga Peninsula                        Province of Zamboanga del Sur

                         Philippines                                              Zamboanga Peninsula                        Province of Zamboanga del Norte

                         Philippines                                              Not Entered                                Zamboanga City

                         Philippines                                              Central Luzon                              Province of Zambales

                         Philippines                                              Autonomous Region in Muslim Mindanao       Province of Tawi-Tawi
Public Disclosure Copy




                         Philippines                                              Central Luzon                              Province of Tarlac

                         Philippines                                              Calabarzon                                 Tanza

                         Philippines                                              Caraga                                     Province of Surigao del Sur

                         Philippines                                              Caraga                                     Province of Surigao del Norte

                         Philippines                                              Autonomous Region in Muslim Mindanao       Province of Sulu

                         Philippines                                              Soccsksargen                               Province of Sultan Kudarat



                                                                                                                                                                                                       Page 2 of 10
                             The World Bank                                                                                 Report No: ISR9137



                         Country              First Administrative Division      Location                         Planned             Actual
                         Philippines          Davao                              Province of South Cotabato
Public Disclosure Copy




                         Philippines          Bicol                              Province of Sorsogon

                         Philippines          Central Visayas                    Province of Siquijor

                         Philippines          Davao                              Sarangani

                         Philippines          Eastern Visayas                    Province of Samar

                         Philippines          Eastern Visayas                    Province of Samar

                         Philippines          Mimaropa                           Province of Romblon

                         Philippines          Calabarzon                         Province of Rizal

                         Philippines          Cagayan Valley                     Province of Quirino

                         Philippines          Not Entered                        Province of Quezon

                         Philippines          Ilocos                             Province of Pangasinan

                         Philippines          Central Luzon                      Province of Pampanga

                         Philippines          Mimaropa                           Province of Palawan

                         Philippines          Central Luzon                      Province of Nueva Ecija

                         Philippines          Central Luzon                      Province of Nueva Ecija

                         Philippines          Eastern Visayas                    Province of Northern Samar

                         Philippines          Soccsksargen                       Province of North Cotabato

                         Philippines          Central Visayas                    Province of Negros Oriental
Public Disclosure Copy




                         Philippines          Western Visayas                    Province of Negros Occidental

                         Philippines          Cordillera Administrative Region   Mountain Province

                         Philippines          Northern Mindanao                  Province of Misamis Oriental

                         Philippines          Northern Mindanao                  Province of Misamis Occidental

                         Philippines          Mimaropa                           Province of Mindoro Oriental

                         Philippines          Mimaropa                           Province of Mindoro Oriental

                         Philippines          Mimaropa                           Province of Mindoro Oriental


                                                                                                                                               Page 3 of 10
                             The World Bank                                                                        Report No: ISR9137



                         Philippines          Bicol                                  Province of Masbate

                         Philippines          Mimaropa                               Province of Marinduque
Public Disclosure Copy




                         Philippines          Autonomous Region in Muslim Mindanao   Province of Maguindanao

                         Philippines          Autonomous Region in Muslim Mindanao   Province of Maguindanao

                         Philippines          Eastern Visayas                        Province of Leyte

                         Philippines          Ilocos                                 Province of La Union

                         Philippines          Autonomous Region in Muslim Mindanao   Province of Lanao del Sur

                         Philippines          Soccsksargen                           Province of Lanao del Norte

                         Philippines          Calabarzon                             Province of Laguna

                         Philippines          Cagayan Valley                         Province of Isabela

                         Philippines          Western Visayas                        Province of Iloilo

                         Philippines          Ilocos                                 Province of Ilocos Sur

                         Philippines          Ilocos                                 Province of Ilocos Norte

                         Philippines          Cordillera Administrative Region       Province of Ifugao

                         Philippines          Eastern Visayas                        Province of Eastern Samar

                         Philippines          Caraga                                 Dinagat Island

                         Philippines          Davao                                  Province of Davao Oriental

                         Philippines          Davao                                  Province of Davao del Sur

                         Philippines          Davao                                  Province of Davao del Norte
Public Disclosure Copy




                         Philippines          Central Visayas                        Province of Cebu

                         Philippines          Calabarzon                             Province of Cavite

                         Philippines          Bicol                                  Province of Catanduanes

                         Philippines          Western Visayas                        Province of Capiz

                         Philippines          Northern Mindanao                      Province of Camiguin

                         Philippines          Bicol                                  Province of Camarines Sur




                                                                                                                                    Page 4 of 10
                             The World Bank                                                                                           Report No: ISR9137



                         Philippines                                Bicol                              Province of Camarines Norte

                         Philippines                                Cagayan Valley                     Province of Cagayan
Public Disclosure Copy




                         Philippines                                Central Luzon                      Province of Bulacan

                         Philippines                                Northern Mindanao                  Province of Bukidnon

                         Philippines                                Western Visayas                    Buenavista

                         Philippines                                Central Visayas                    Province of Bohol

                         Philippines                                Eastern Visayas                    Biliran

                         Philippines                                Cordillera Administrative Region   Province of Benguet

                         Philippines                                Calabarzon                         Province of Batangas

                         Philippines                                Cagayan Valley                     Province of Batanes

                         Philippines                                Zamboanga Peninsula                Province of Basilan

                         Philippines                                Central Luzon                      Province of Aurora

                         Philippines                                Western Visayas                    Province of Antique

                         Philippines                                Bicol                              Province of Albay

                         Philippines                                Western Visayas                    Province of Aklan

                         Philippines                                Caraga                             Province of Agusan del Sur

                         Philippines                                Caraga                             Province of Agusan del Norte

                         Philippines                                Cordillera Administrative Region   Province of Abra

                         Philippines                                Cordillera Administrative Region   Kalinga
Public Disclosure Copy




                         Philippines                                Cordillera Administrative Region   Apayao


                         Results
                         Project Development Objective Indicators




                                                                                                                                                       Page 5 of 10
                             The World Bank                                                                                                                                   Report No: ISR9137



                         Indicator Name                                    Core Unit of Measure              Baseline                          Current                        End Target
                         Implementation of DENR's reform agenda,                 Text             Value      Reform Agenda agreed for          partlially achieved            Key milestones have been
                         which includes timely actions on the dated                                          NPS-ENRMP in line with                                           met Dated loan covenants
Public Disclosure Copy




                         covenants, achievement of the key milestones                                        Rationalization Plan. Dated                                      complied with and under
                         andcontinued progress in implementing the                                           covenants provided in the                                        implementation.
                         Rationalization Plan                                                                loan for key actions.
                                                                                                  Date       27-Nov-2007                       13-Dec-2012                    31-Dec-2012
                                                                                                  Comments                                     Partially Achieved: EMB,
                                                                                                                                               MGB, NAMRIA & DENR Rat
                                                                                                                                               Plan still pending DBM
                                                                                                                                               approval, but reforms
                                                                                                                                               generally in line with plan
                                                                                                                                               Rationalization Plan because
                                                                                                                                               its approval is beyond its
                                                                                                                                               control
                         30% improvement in overall client satisfaction          Text             Value      60% - 70% range on                survey not yet done            30%
                         with DENR service delivery by type of client e.                                     satisfaction indicatorys
                         g. LGU/communities.                                                      Date       15-Dec-2008                       13-Dec-2012                    30-Dec-2012
                                                                                                  Comments                                     Follow up survey to be
                                                                                                                                               conducted in June 2013
                         80% of the Project's investment targets in              Text             Value      Zero                              88%                            80%
                         rehabilitation, ecosystem development and                                Date       27-Nov-2007                       13-Dec-2012                    30-Dec-2012
                         assessments being met
                                                                                                  Comments                                     Achieved: LGUs have CAF for
                                                                                                                                               88% of $4m GEF gran

                         Global Environmental Objective Indicators
                         Indicator Name                                    Core Unit of Measure              Baseline                          Current                        End Target
                         35% of ecologically sensitive forests (outside          Text             Value                                        35%+                           35%
                         protected areas) under effective protection as                           Date       15-Dec-2008                       13-Dec-2012                    30-Dec-2012
                         identified in each WMP
                                                                                                  Comments   Baseline being estimated as       Achieved: 125,377 ha under
Public Disclosure Copy




                                                                                                             part of the Client Satisfaction   effective protection
                                                                                                             Survey that is being
                                                                                                             implemented.
                         106,000 hectares of protected areas, protection         Text             Value                                        achieved                       106,000
                         forest and wetlands in GEF supported sites                               Date       27-Nov-2007                       13-Dec-2012                    30-Dec-2012
                         under effective management by PY5 as
                                                                                                  Comments   Baseline being estimated as       Core indicator equivalent
                         measured by the PA management
                         effectiveness tool                                                                  part of the Client Satisfaction   (forest area brought under
                                                                                                                                               effective management) METT




                                                                                                                                                                                               Page 6 of 10
                             The World Bank                                                                                                                                   Report No: ISR9137



                                                                                                             Survey that is being            implemented in PAs in all
                                                                                                             implemented.                    GEF sites though only 9525
                                                                                                                                             ha. covered
Public Disclosure Copy




                         Intermediate Results Indicators
                         Indicator Name                                    Core Unit of Measure              Baseline                        Current                          End Target
                         Framework for the rationalization of NRM&E              Text             Value      Various studies available       Achieved                         Action plan being
                         policies and legislation developed and under                                        highlighting inconsistencies in                                  implemented to rationalize the
                         implementation                                                                      legislation, policy and                                          ENR policies and legislation
                                                                                                             implementation
                                                                                                  Date       27-Nov-2007                     13-Dec-2012                      30-Dec-2012
                                                                                                  Comments                                   Framework developed and
                                                                                                                                             being updated in line with new
                                                                                                                                             priorities
                         Forward planning and budgeting strategy                 Text             Value      DBM instruction has been        Achieved                         Close linkage between Plans
                         started to be implemented which inter alia                                          isused requiring OPIFs to be                                     and Budgets
                         provides a vision and benchmarks for key                                            prepared by all departments
                         reformsin DENRs operations                                               Date       27-Dec-2007                     13-Dec-2012                      30-Dec-2012
                                                                                                  Comments                                   2010-2012 Medium Term
                                                                                                                                             Expenditure Program by
                                                                                                                                             sector was completed.
                         Procedures and responsibilities for issuance of         Text             Value      Lack of clarity in procedures   Achieved                         Increases in issuance of
                         tenure instruments standardized and                                                 for CBRMA/CBFMA and                                              CBRMA/CBFMAs and
                         streamlined                                                                         NIPAS has virtually resulted                                     NIPAS-IRR
                                                                                                             in a cessation of this
                                                                                                             instrument
                                                                                                  Date       27-Dec-2007                     13-Dec-2012                      30-Dec-2012
                                                                                                  Comments                                   NIPAS-IRR updated,
                                                                                                                                             streamlined & policy issued
                         30% of degraded forest in GEF supported sites           Text             Value      64,000 ha                       14%                              30%
                         rehabilitated with native species representing                           Date       31-Jul-2010                     13-Dec-2012                      30-Dec-2012
Public Disclosure Copy




                         the bio-geographic region as identified in the
                                                                                                  Comments                                   Core indicator: area restored.
                         WMP
                                                                                                                                             Rehab. Of 9525 ha
                                                                                                                                             (planned target may have
                                                                                                                                             been over estimated)
                         100% of GEF supported protected areas (PA)              Text             Value      Tools not in use at any sites   100%                             100%
                         mainstreamed PA management effectiveness                                 Date       27-Dec-2007                     13-Dec-2012                      30-Dec-2012
                         tool
                                                                                                  Comments                                   Core indicator equivalent
                                                                                                                                             (Forest area brought under




                                                                                                                                                                                                Page 7 of 10
                             The World Bank                                                                                                                Report No: ISR9137



                                                                                                                          management plans) Tool in
                                                                                                                          use at all sites
                         60% of targeted communities in GEF                 Text   Value      None                        82%                              60%
                         supported sites implementing micro-catchment
Public Disclosure Copy




                                                                                   Date       27-Dec-2007                 13-Dec-2012                      30-Dec-2012
                         plans by the end of the Project
                                                                                   Comments                               All targeted municipalities
                                                                                                                          have micro catchment plans
                         75 % of funded activities (by $ value) in GEF      Text   Value      Zero                        75%                              75%
                         supported sites implemented by the LGUs and/              Date       27-Dec-2007                 13-Dec-2012                      30-Dec-2012
                         or other stakeholders
                                                                                   Comments                               Core indicator equivalent
                                                                                                                          (people in targeted forest and
                                                                                                                          adjacent communities with
                                                                                                                          increased monetary and non-
                                                                                                                          monetary benefits from
                                                                                                                          forests)
                         10% per annum increase in companies                Text   Value      Year 1 level                27% air; water 6%                Year 1 plus 10%
                         complying with environmental standards                    Date       30-Dec-2008                 13-Dec-2012                      30-Dec-2012
                         compared to baseline
                                                                                   Comments                               Core indicator equivalent
                                                                                                                          (Particulate matter reduction
                                                                                                                          under the project (microgram/
                                                                                                                          m3))
                         Designation and operationalization of at least 3   Text   Value      Zero                        3                                3
                         water quality management areas                            Date       27-Dec-2007                 13-Dec-2012                      30-Dec-2012
                                                                                   Comments                               3 WQMAs established i)
                                                                                                                          Meycauayan-Marilao-
                                                                                                                          Obando- R3, Jaro-Tigum-
                                                                                                                          Aganan R-6 & Saranggani
                                                                                                                          Bay-R12. Each has a
                                                                                                                          Governing Board and 10-
                                                                                                                          year WQMA action plan.
                         128 LGUs are implementing three aspects of         Text   Value      Number of LGUs: 48 (2006)   112                              128
                         ecological solid waste management
Public Disclosure Copy




                                                                                   Date       27-Dec-2007                 13-Dec-2012                      30-Dec-2012
                                                                                   Comments                               Core indicator equivalent
                                                                                                                          (Industrial or municipal solid
                                                                                                                          waste reduced or recycled
                                                                                                                          under the project) Out of 112
                                                                                                                          LGUs, 88% implementing
                                                                                                                          segregation at source; 84%
                                                                                                                          practice segregated
                                                                                                                          collection, and 78% operate




                                                                                                                                                                             Page 8 of 10
                             The World Bank                                                                                                                                            Report No: ISR9137



                                                                                                                                                   MRFs. 3 LGUs exempted
                                                                                                                                                   due to impact of disasters
Public Disclosure Copy




                         Data on Financial Performance (as of 23-Dec-2012)
                         Financial Agreement(s) Key Dates
                         Project              Ln/Cr/Tf               Status              Approval Date              Signing Date           Effectiveness Date        Original Closing Date      Revised Closing Date
                         P096174              IBRD-74700             Effective           26-Jun-2007                29-Aug-2007            27-Nov-2007               31-Dec-2012                31-Dec-2013
                         P091147              TF-90073               Effective           29-Aug-2007                29-Aug-2007            27-Nov-2007               31-Dec-2012                31-Dec-2013

                         Disbursements (in Millions)
                         Project              Ln/Cr/Tf               Status              Currency        Original             Revised           Cancelled          Disbursed            Undisbursed          % Disbursed
                         P096174              IBRD-74700             Effective           USD                          50.00             50.00               0.00               41.25                  8.75         83.00
                         P091147              TF-90073               Effective           USD                           7.00              7.00               0.00                5.33                  1.67         76.00


                         Disbursement Graph
Public Disclosure Copy




                         Key Decisions Regarding Implementation
                         A formal request submitted through the Department of Finance for a one year extension of the project from December 31. 2012 to December 31, 2013 was approved by the Bank.

                         Restructuring History
                         Level two Approved on 21-Dec-2012


                                                                                                                                                                                                             Page 9 of 10
                            The World Bank                                                                                              Report No: ISR9137



                         Related Projects
                         P091147-GEF Program supporting the National Program for Environment and Natural Resources Management Project
Public Disclosure Copy
Public Disclosure Copy




                                                                                                                                                         Page 10 of 10