The World Bank Implementation Status & Results Report China: Gansu Rural-Urban Integration Project (P132775) China: Gansu Rural-Urban Integration Project (P132775) EAST ASIA AND PACIFIC | China | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2015 | Seq No: 11 | ARCHIVED on 22-Sep-2020 | ISR41809 | Implementing Agencies: Gansu Provincial Project Coordination Office, People’s Republic of China Key Dates Key Project Dates Bank Approval Date: 31-Mar-2015 Effectiveness Date: 14-Aug-2015 Planned Mid Term Review Date: 22-Oct-2018 Actual Mid-Term Review Date: 17-Nov-2017 Original Closing Date: 30-Jun-2021 Revised Closing Date: 30-Jun-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to provide residents in Wuwei Municipality and Linxia Prefecture with improved connectivity between rural and urban areas. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component A: Wuwei Road Network Improvement:(Cost $132.02 M) Component B: Linxia Road Network Improvement:(Cost $68.28 M) Component C: Technical Assistance and Project Management:(Cost $3.31 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The project continues to make steady progress towards its Project Development Objective of providing residents in Wuwei Municipality and Linxia Prefecture with improved connectivity between rural and urban areas. Civil works for eight out of ten roads have been completed, with one under construction and one to be dropped in Wuwei; five of six project roads have been completed in Linxia and the remaining one under construction. Completed project roads are playing important role in Wuwei and Linxia in facilitating urban-rural integration and poverty alleviation. The capacity building activities are progressing well, with a focus on road safety and road maintenance. 9/22/2020 Page 1 of 6 The World Bank Implementation Status & Results Report China: Gansu Rural-Urban Integration Project (P132775) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Low Low Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Low Low Technical Design of Project or Program -- Substantial Moderate Institutional Capacity for Implementation and -- Moderate Moderate Sustainability Fiduciary -- Moderate Moderate Environment and Social -- Substantial Substantial Stakeholders -- Moderate Moderate Other -- -- -- Overall -- Moderate Moderate Results PDO Indicators by Objectives / Outcomes More people have access to an all-season road connecting rural and urban areas in Wuwei and Linxia IN00844183 ►1. Share of rural population with access to an all-season road in Wuwei and Linxia (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 62.00 79.00 81.00 83.00 Date 23-Sep-2014 10-Jan-2020 12-Aug-2020 30-Jun-2021 This indicator measures the coverage aspect of the connectivity improvement between rural and urban areas. The definition and detailed method of calculation for this indicator is further clarified at the restructuring in October 2018. Baseline and target numbers and percentages are updated accordingly. Comments: This indicator does not count the additional population with access to all-season road because of road constructed outside the project, to ensure proper attribution. IN00844185 1.1 Number of rural people with access to an all-season road in Wuwei and Linxia (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 1,121,751.00 1,420,887.00 1,463,102.00 1,510,000.00 IN00844306 1.2 Share of rural women with access to an all-season road in Wuwei and Linxia (Number, Custom Breakdown) 9/22/2020 Page 2 of 6 The World Bank Implementation Status & Results Report China: Gansu Rural-Urban Integration Project (P132775) Baseline Actual (Previous) Actual (Current) End Target Value 62.00 79.00 81.00 83.00 Date 23-Sep-2014 10-Jan-2020 12-Aug-2020 30-Jun-2021 People save significant time travelling between rural and urban areas in Wuwei and Linxia IN00844184 ►2. Average travel time savings on selected key project roads connecting rural and urban areas in Wuwei and Linxia (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 28.00 35.00 38.00 Date 23-Sep-2014 10-Jan-2020 12-Aug-2020 30-Jun-2021 This indicator measures the efficiency aspect of the connectivity improvement between rural and urban areas. The definition and detailed method of calculation for this indicator is further clarified at the Comments: restructuring in October 2018. Baseline and target numbers and percentages are updated accordingly. Overall Comments PDO Completion of A10 and A11 allowed the progress in the two PDO indicators. Intermediate Results Indicators by Components Wuwei Road Network Improvement IN00844307 ►1. Length of roads rehabilitated or constructed in Wuwei (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 45.20 57.60 63.40 Date 23-Sep-2014 10-Jan-2020 12-Aug-2020 30-Jun-2021 This intermediate indicator is revised at project restructuring in October 2018 to reflect the implementation progress in Component 1 Wuwei Road Network Improvement. Therefore the current value (length of Comments: roads rehabilitated or constructed in Wuwei) is not comparable to the previous indicator value before the project restructuring (length of rural road rehabilitated). Linxia Road Network Improvement IN00844308 ►2. Length of roads rehabilitated or constructed in Linxia (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 34.70 34.70 47.90 9/22/2020 Page 3 of 6 The World Bank Implementation Status & Results Report China: Gansu Rural-Urban Integration Project (P132775) Date 23-Sep-2014 10-Jan-2020 12-Aug-2020 30-Jun-2021 This intermediate indicator is revised at project restructuring in October 2018 to reflect the implementation progress in Component 2 Linxia Road Network Improvement. Therefore the current value (length of roads Comments: rehabilitated or constructed in Linxia) is not comparable to the previous indicator value before the project restructuring (length of non-rural road constructed). Technical Assistance and Project Management IN00844309 ►3. Preparation of long term maintenance strategies (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 23-Sep-2014 10-Jan-2020 12-Aug-2020 30-Jun-2021 Linxia County has completed a long-term road maintenance and management strategy. Comments: IN00844310 ►4. Number of counterpart staff who attended training and study tours (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 373.00 381.00 535.00 Date 23-Sep-2014 10-Jan-2020 12-Aug-2020 30-Jun-2021 IN00844311 ►5. Length of ChinaRAP assessments undertaken with commitment to address road safety recommendations (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 33.30 60.00 100.00 Date 23-Sep-2014 10-Jan-2020 12-Aug-2020 30-Jun-2021 ChinaRAP has carried out assessment on all project roads and reviewed construction drawings of A5, A10, A11, and A12 in Wuwei, and B6 in Linxia. The design consultant has incorporated the road safety Comments: recommendations by ChinaRAP team in the engineering design of B6, A5, A10, A11, and A12. Overall Comments IR Progress due to the completion of A10 and A11, as well as road safety improvement made on project roads in Gulang. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) 9/22/2020 Page 4 of 6 The World Bank Implementation Status & Results Report China: Gansu Rural-Urban Integration Project (P132775) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P132775 IBRD-84800 Effective USD 150.00 150.00 0.00 129.90 20.10 87% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P132775 IBRD-84800 Effective 31-Mar-2015 25-May-2015 14-Aug-2015 30-Jun-2021 30-Jun-2021 Cumulative Disbursements PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History Level 2 Approved on 12-Oct-2018 Related Project(s) 9/22/2020 Page 5 of 6 The World Bank Implementation Status & Results Report China: Gansu Rural-Urban Integration Project (P132775) There are no related projects. 9/22/2020 Page 6 of 6