The World Bank                                                                                      Implementation Status & Results Report
            China: Gansu Rural-Urban Integration Project (P132775)



China: Gansu Rural-Urban Integration Project (P132775)


 EAST ASIA AND PACIFIC | China | Transport Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2015 | Seq No: 11 | ARCHIVED on 22-Sep-2020 | ISR41809 |


 Implementing Agencies: Gansu Provincial Project Coordination Office, People’s Republic of China



 Key Dates


  Key Project Dates

   Bank Approval Date: 31-Mar-2015                                              Effectiveness Date: 14-Aug-2015
   Planned Mid Term Review Date: 22-Oct-2018                                    Actual Mid-Term Review Date: 17-Nov-2017
   Original Closing Date: 30-Jun-2021                                           Revised Closing Date: 30-Jun-2021
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The project development objective is to provide residents in Wuwei Municipality and Linxia Prefecture with improved connectivity between rural and
  urban areas.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Component A: Wuwei Road Network Improvement:(Cost $132.02 M)
 Component B: Linxia Road Network Improvement:(Cost $68.28 M)
 Component C: Technical Assistance and Project Management:(Cost $3.31 M)

 Overall Ratings

 Name                                                                         Previous Rating                           Current Rating

 Progress towards achievement of PDO                                          Satisfactory                             Satisfactory
 Overall Implementation Progress (IP)                                         Satisfactory                             Moderately Satisfactory
 Overall Risk Rating                                                          Moderate                                 Moderate


 Implementation Status and Key Decisions

  The project continues to make steady progress towards its Project Development Objective of providing residents in Wuwei Municipality and Linxia
  Prefecture with improved connectivity between rural and urban areas. Civil works for eight out of ten roads have been completed, with one under
  construction and one to be dropped in Wuwei; five of six project roads have been completed in Linxia and the remaining one under
  construction. Completed project roads are playing important role in Wuwei and Linxia in facilitating urban-rural integration and poverty alleviation.
  The capacity building activities are progressing well, with a focus on road safety and road maintenance.




9/22/2020                                                                                                                       Page 1 of 6
            The World Bank                                                                                      Implementation Status & Results Report
            China: Gansu Rural-Urban Integration Project (P132775)




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                              Rating at Approval              Previous Rating                Current Rating

  Political and Governance                                   --                              Low                           Low
  Macroeconomic                                              --                              Moderate                      Moderate
  Sector Strategies and Policies                             --                              Low                           Low
  Technical Design of Project or Program                     --                              Substantial                   Moderate
  Institutional Capacity for Implementation and
                                                             --                              Moderate                      Moderate
  Sustainability
  Fiduciary                                                  --                              Moderate                      Moderate
  Environment and Social                                     --                              Substantial                   Substantial
  Stakeholders                                               --                              Moderate                      Moderate
  Other                                                      --                              --                             --
  Overall                                                    --                              Moderate                      Moderate



  Results


 PDO Indicators by Objectives / Outcomes



   More people have access to an all-season road connecting rural and urban areas in Wuwei and Linxia

    IN00844183
    ►1. Share of rural population with access to an all-season road in Wuwei and Linxia (Percentage, Custom)

                                       Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                              62.00                         79.00                        81.00                     83.00

    Date                               23-Sep-2014                   10-Jan-2020                  12-Aug-2020              30-Jun-2021
                                       This indicator measures the coverage aspect of the connectivity improvement between rural and urban
                                       areas. The definition and detailed method of calculation for this indicator is further clarified at the
                                       restructuring in October 2018. Baseline and target numbers and percentages are updated accordingly.
   Comments:
                                       This indicator does not count the additional population with access to all-season road because of road
                                       constructed outside the project, to ensure proper attribution.

     IN00844185
     1.1 Number of rural people with access to an all-season road in Wuwei and Linxia (Number, Custom Supplement)

                                     Baseline                     Actual (Previous)           Actual (Current)             End Target

     Value                           1,121,751.00                 1,420,887.00                1,463,102.00                 1,510,000.00

     IN00844306
     1.2 Share of rural women with access to an all-season road in Wuwei and Linxia (Number, Custom Breakdown)


9/22/2020                                                                                                                        Page 2 of 6
            The World Bank                                                                                      Implementation Status & Results Report
            China: Gansu Rural-Urban Integration Project (P132775)




                                     Baseline                     Actual (Previous)             Actual (Current)            End Target

     Value                           62.00                        79.00                         81.00                       83.00

     Date                            23-Sep-2014                  10-Jan-2020                   12-Aug-2020                 30-Jun-2021


   People save significant time travelling between rural and urban areas in Wuwei and Linxia

    IN00844184
    ►2. Average travel time savings on selected key project roads connecting rural and urban areas in Wuwei and Linxia (Percentage, Custom)

                                       Baseline                      Actual (Previous)            Actual (Current)           End Target

    Value                              0.00                          28.00                        35.00                      38.00

    Date                               23-Sep-2014                   10-Jan-2020                  12-Aug-2020               30-Jun-2021
                                       This indicator measures the efficiency aspect of the connectivity improvement between rural and urban
                                       areas. The definition and detailed method of calculation for this indicator is further clarified at the
   Comments:
                                       restructuring in October 2018. Baseline and target numbers and percentages are updated accordingly.


 Overall Comments PDO

  Completion of A10 and A11 allowed the progress in the two PDO indicators.




 Intermediate Results Indicators by Components



   Wuwei Road Network Improvement

    IN00844307
    ►1. Length of roads rehabilitated or constructed in Wuwei (Kilometers, Custom)

                                       Baseline                      Actual (Previous)            Actual (Current)           End Target

    Value                              0.00                          45.20                        57.60                      63.40

    Date                               23-Sep-2014                   10-Jan-2020                  12-Aug-2020               30-Jun-2021
                                        This intermediate indicator is revised at project restructuring in October 2018 to reflect the implementation
                                       progress in Component 1 Wuwei Road Network Improvement. Therefore the current value (length of
   Comments:                           roads rehabilitated or constructed in Wuwei) is not comparable to the previous indicator value before the
                                       project restructuring (length of rural road rehabilitated).



   Linxia Road Network Improvement

    IN00844308
    ►2. Length of roads rehabilitated or constructed in Linxia (Kilometers, Custom)

                                       Baseline                      Actual (Previous)            Actual (Current)           End Target

    Value                              0.00                          34.70                        34.70                      47.90


9/22/2020                                                                                                                       Page 3 of 6
            The World Bank                                                                                     Implementation Status & Results Report
            China: Gansu Rural-Urban Integration Project (P132775)




    Date                               23-Sep-2014                   10-Jan-2020                 12-Aug-2020                30-Jun-2021
                                       This intermediate indicator is revised at project restructuring in October 2018 to reflect the implementation
                                       progress in Component 2 Linxia Road Network Improvement. Therefore the current value (length of roads
   Comments:                           rehabilitated or constructed in Linxia) is not comparable to the previous indicator value before the project
                                       restructuring (length of non-rural road constructed).



   Technical Assistance and Project Management

    IN00844309
    ►3. Preparation of long term maintenance strategies (Yes/No, Custom)

                                       Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                              No                            Yes                         Yes                        Yes

    Date                               23-Sep-2014                   10-Jan-2020                 12-Aug-2020                30-Jun-2021

                                       Linxia County has completed a long-term road maintenance and management strategy.
   Comments:

    IN00844310
    ►4. Number of counterpart staff who attended training and study tours (Number, Custom)

                                       Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                              0.00                          373.00                      381.00                     535.00

    Date                               23-Sep-2014                   10-Jan-2020                 12-Aug-2020                30-Jun-2021

    IN00844311
    ►5. Length of ChinaRAP assessments undertaken with commitment to address road safety recommendations (Kilometers, Custom)

                                       Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                              0.00                          33.30                       60.00                      100.00

    Date                               23-Sep-2014                   10-Jan-2020                 12-Aug-2020                30-Jun-2021
                                       ChinaRAP has carried out assessment on all project roads and reviewed construction drawings of A5,
                                       A10, A11, and A12 in Wuwei, and B6 in Linxia. The design consultant has incorporated the road safety
   Comments:
                                       recommendations by ChinaRAP team in the engineering design of B6, A5, A10, A11, and A12.



 Overall Comments IR

  Progress due to the completion of A10 and A11, as well as road safety improvement made on project roads in Gulang.




 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)


9/22/2020                                                                                                                       Page 4 of 6
            The World Bank                                                                                    Implementation Status & Results Report
            China: Gansu Rural-Urban Integration Project (P132775)




 Project        Loan/Credit/TF    Status       Currency        Original   Revised     Cancelled     Disbursed       Undisbursed                % Disbursed


 P132775        IBRD-84800        Effective    USD             150.00      150.00           0.00         129.90           20.10                       87%


 Key Dates (by loan)

 Project         Loan/Credit/TF    Status      Approval Date       Signing Date     Effectiveness Date      Orig. Closing Date      Rev. Closing Date

 P132775         IBRD-84800        Effective   31-Mar-2015         25-May-2015      14-Aug-2015             30-Jun-2021             30-Jun-2021


Cumulative Disbursements




 PBC Disbursement

                                                                                         Achievement       Disbursed amount in         Disbursement %
 PBC ID                     PBC Type    Description             Coc       PBC Amount
                                                                                         Status            Coc                         for PBC




  Restructuring History


  Level 2 Approved on 12-Oct-2018


  Related Project(s)




9/22/2020                                                                                                                        Page 5 of 6
            The World Bank                                           Implementation Status & Results Report
            China: Gansu Rural-Urban Integration Project (P132775)




 There are no related projects.




9/22/2020                                                                           Page 6 of 6