REPUBLIC OF KENYA



MINISTRY OF TRANSPORT, INFRASTRUCTURE, HOUSING AND URBAN
                      DEVELOPMENT




                                                PY
       ABBREVIATED RESETTLEMENT ACTION PLAN FOR
            KAMBI MOTO INFORMAL SETTLEMENT




                                             CO
                     RE
            NAIROBI CITY COUNTY GOVERNMENT
                  SU


                       MAY, 2020
               LO



                     PREPARED BY
            SC
         DI
D IS CLO SU RE
                 C OP Y
                    Abbreviated Resettlement Action Plan for Kambi Moto

    ABBREVIATIONS

 AFD           French Development Agency
 GoK           Government of Kenya
 EMAT          External Monitoring Assistance team
 GRC           Grievance Redress Committee
 GRM           Grievances Redress Mechanism
 KISIP         Kenya Informal Settlements Improvement Project
 LP&LUDP       Local Physical & Land Use Development Plan
 MTIH&UD Ministry of Transport, Infrastructure, Housing and Urban Development
 NLC           National Land Commission
 O.P           Operational Policy




                                                                       PY
 PAI           Project Affected Institutions
 PAP           Project Affected Person
 PCT           Project Coordinating team




                                                                    CO
 RAP           Resettlement Action Plan
 RIC           Resettlement Implementation Committee
 SEC           Settlement Executive Committee
                               RE
 SGRC          Settlement Grievance Redress Committee
 SIDA          Swedish International Development Cooperation Agency
 WB            World Bank
                            SU
                         LO
                      SC
                   DI




Abbreviated Resettlement Action Plan for Kambi Moto|ABBREVIATIONS
Page ii of 130
                      Abbreviated Resettlement Action Plan for Kambi Moto

    DEFINITION OF TERMS

Abbreviated Resettlement Action Plan is a resettlement document prepared to mitigate
impacts that has affected less than 200 Project affected persons in accordance to World Bank OP
4.12.

Adoptive Planning: is a physical planning approach applied in this project that entailed
application of practical planning interventions that suit the realities, challenges and
characteristics of the project informal settlements. This was achieved through moderating of
conventional planning standards that would otherwise have been applied. This approach helped
to create responsive conditions that support the informal settlement’s capacity to respond to
changes towards securing tenure security without necessarily disintegrating the settlement and
at the same time sustaining the spatial functions at the minimum possible level.

Facilitation means payments made in cash in recognition of loss of assets and livelihoods
resulting from impacts caused by planning and surveying of the settlement.




                                                                          PY
Complete Displacement: means the displacement of a structure owner or institution PAP etc.
from one parcel of land to a different parcel of land outside the settlement due to the planning
and survey activities including demarcation of internal access paths.




                                                                       CO
Cut-off date is the date of start of the socio-economic survey/census and asset inventory of
PAPs. Persons entering and/or occupying land in the project area after this date and not included
in the inventory of PAPs will not be considered eligible for facilitation. Similarly, fixed assets such
as structures, established after the cut-off date will not be compensated/facilitated.

Formalization: This refers to the political and administrative acknowledgement or recognition
                                 RE
of informal settlements and their subsequent absorption into the formal fold.

Joint tenancy: is a concurrent form of property ownership where two or more persons share
equal, undivided interests in property.
                              SU


Legalization: This refers to the process of providing some legal backing to the tenure systems
operating within informal settlements. This is achieved through the recordation and maintenance
of legal rights to land at the community or municipal level.
                           LO



Market rate: The selling price of a commodity in the open competitive market.

Multiple ownership: This is the kind of ownership where a person or group of people own more
than one parcel of land.
                        SC




Project Affected Person(s) (PAPs) are persons, enterprises, and public or private
institutions affected because they may lose, be denied, or be restricted access to economic assets;
lose occupancy/shelter, income sources, or means of livelihood. These persons are affected
                     DI




whether or not they must move to another location.

Rehabilitation Assistance is the additional support, over and above compensation accorded
to the vulnerable or at-risk members of the affected community during implementation of the
ARAP e.g. labour support.



Abbreviated Resettlement Action Plan for Kambi Moto|DEFINITION OF TERMS
Page iii of 130
                      Abbreviated Resettlement Action Plan for Kambi Moto

Relocation/Localized displacement means displacement of a structure owner or institution
PAP etc. from one parcel of land to a different parcel of land (within the settlement) due to the
planning and survey activities including demarcation of roads.

Replacement cost means the market cost of the materials to build a replacement structure with
an area and quality similar to or better than those of the affected structure, or to repair a partially
affected structure, plus the cost of transporting building materials to the construction site, plus
the cost of any labour and contractors' fees, plus the cost of any registration and transfer taxes. In
determining the replacement cost, depreciation of the asset and the value of salvage materials are
not taken into account, nor is the value of benefits to be derived from the project deducted from
the valuation of an affected asset.

Resettlement Action Plan (RAP) or Resettlement Plan is a resettlement instrument
(document) to be prepared when program locations are identified. In such cases, planning and
survey activities including demarcation of roads lead to loss of structures and sources of
livelihood. RAPs are prepared by the party impacting on the people and their livelihoods. RAPS
contain specific and legal binding requirements to resettle and compensate/facilitate the affected
party before implementation of the project activities.




                                                                          PY
Resettlement Assistance means the measures to ensure that Project Affected Persons who
may require to be physically relocated are provided with assistance during relocation, such as
moving/shifting allowances for ease of resettlement, residential housing or rentals, rental




                                                                       CO
allowance whichever is feasible and as required, for ease of resettlement.

Resettlement Policy Framework (RPF) has been prepared as an instrument to be used
throughout the informal settlements improvement project implementation. The RPF will be
disclosed to set out the resettlement and compensation policy, organizational arrangements and
design criteria to be applied to meet the needs of the people who may be affected by the project.
                                 RE
The Resettlement Action Plans (“RAPs”) for the project will be prepared in conformity with the
provisions of this RPF.

Survey means a 100% field assessment carried out to identify and determine the number of
                              SU

Project Affected Persons (PAP).

Squatters are those who have extended their settlements into Government lands and have no
formal right or claim to the portion of the lands.
                           LO



Tenancy-in-common: Tenancy in common is a form of concurrent ownership of land in which
two or more persons possess the land simultaneously where each person holds an individual,
undivided interest in the property and each party has the right to alienate, or transfer their
interest.
                        SC




Tenure Regularization is a deliberate process aimed at bringing the informal and
unauthorized (not formerly planned) settlements within the official, legal, and administrative
system of land management.
                     DI




Titling: This refers to formal adjudication, cadastral survey and registration of individual or
group rights to land in the legal land register; and the concomitant issuance of certificates of title.

Valuation: is the art or science of establishing the worth of a particular interest in property for
a specific purpose and at a particular moment in time, considered all the features of the property,
demographics, topography as well as the underlying market drivers.

Abbreviated Resettlement Action Plan for Kambi Moto|DEFINITION OF TERMS
Page iv of 130
                    Abbreviated Resettlement Action Plan for Kambi Moto

Vulnerable Groups include all those affected by the project that are below the poverty line, the
elderly, women and children headed households, indigenous people, ethnic minorities or other
Project Affected Person who may not be protected through national land compensation
legislation.




                                                                     PY
                                                                  CO
                               RE
                            SU
                         LO
                      SC
                   DI




Abbreviated Resettlement Action Plan for Kambi Moto|DEFINITION OF TERMS
Page v of 130
                              Abbreviated Resettlement Action Plan for Kambi Moto

        EXECUTIVE SUMMARY

Project Description
The Kenya Informal Settlements Improvement Project (KISIP) is a five-year project of the
Government of Kenya (GOK) with support from the World Bank, through the International
Development Association, (IDA), the Swedish International Development Cooperation Agency
(Sida) and the Agence Française de Development (AFD). It is an initiative of the GoK, through the
Ministry of Transport, Infrastructure, and Housing and Urban Development. The overall project
strategic objective is to improve living conditions of people living and working in informal
settlements in Kenya’s fourteen (14) selected counties, of which Nairobi County - where Kambi
Moto informal settlement is located.

Land Titling Process
The process of enhancing tenure security in Kambi Moto Informal settlement, through planning
and surveying, commenced in February 2019. The key objective was to facilitate provision of
security of tenure to the residents of the settlement who occupied the present land upon signing




                                                                           PY
memorandum of Understanding (M.O.U) with the defunct Nairobi City Council (now Nairobi City
County Government). At the time KISIP initiated the project in the settlement, there were no
official records of any Local Physical and Land Use Development Plan (LP&LUDP). However, the
settlement exhibits a regular grid-layout pattern.




                                                                        CO
The project commenced with introduction to the settlement SEC and Community members.
Thereafter, a detailed base map prepared was used for physical mapping which subsequently was
used for socio-economic survey. The socio-economic survey formed a key aspect for generation of
preliminary List of Beneficiaries (LOB) and the findings informed/guided the community
participatory planning. Following the community participatory planning activity, the process
                                         RE
involved preparation of two planning models, namely, Adoptive planning model and nil
intervention models incorporating the vision, the needs and aspirations of the community. The
two alternatives were thereafter presented to the community, while highlighting the pros and cons
of each option. The Adoptive planning model was unanimously adopted by the Kambi Moto
Community, owing to its flexibility and minimal number of PAPs generated.
                                      SU


This was also informed by the existing settlement pattern that is generally well defined and with
most structures built to multi-storey level. The approved plan; together with the community
endorsed LOB formed the basis for the preparation of survey data and subsequent amendment of
                                   LO



the Registry Index Map (RIM) with the area list. The whole process culminated to preparation of
sectional titles1 for the beneficiaries in Kambi Moto. The following table shows number of parcels
and beneficiaries:
                                SC




Table E1: number of parcels and beneficiaries in Kambi Moto Settlement
    Category                      Total Number Males        Females     Institution   Community
                                  of                                    s             Groups
                                  Beneficiaries
                             DI




    Total no of                   157           89          63          2             3
    beneficiaries
    Total number of               145
    sectional titles



1   Details on Sectional Title provided under Section 2.3
Abbreviated Resettlement Action Plan for Kambi Moto|EXECUTIVE SUMMARY
Page vi of 130
                            Abbreviated Resettlement Action Plan for Kambi Moto

 Total Number of                145
 Parcels

During Implementation of this ARAP, the Nairobi City County Government will officially transfer
the land from public to individual beneficiaries through issuance of title deeds as per Kenyan Land
Laws.

Approach and Methodology

This ARAP for Kambi Moto Informal Settlement has been developed in compliance with the
World Bank's Operational Policy 4.12 on Involuntary Resettlement, and Government of Kenya
legal framework. Section 40 (Protection of right to property) in the Constitution of Kenya 2010 is
most relevant in protecting people’s right to property. The World Bank OP 4.1 2 which requires
that Project Affected Persons be consulted and assisted/facilitated before temporary
displacement from road way leaves as in the case of the KISIP Tenure regularization project. The
policy also provides that negative resettlement impacts should be avoided and where possible,
they should be minimized and mitigated or compensated/offset.




                                                                                               PY
The ARAP approach was also guided by KISIP’s Resettlement Policy Framework (RPF) 2014.
Therefore, in order to comply with the provisions of the World Bank OP4.12 and Kenya’s Land
Act 2012, below listed activities were undertaken during preparation of the ARAP report.




                                                                                            CO
     i.   Socio-economic survey and census of the PAPs and assets;
    ii.   Community, PAPs and an all-inclusive stakeholder consultation;
   iii.   Valuation of affected assets
   iv.    PAPs Meeting/consultations
    v.    Preparation of PAP and Asset register and;
                                       RE
   vi.    Sectional titling sensitization meetings2.

Grievance Redress Mechanism
This ARAP provides for a three tier Grievances Redress Mechanism (GRM) at no cost to the PAPs.
                                    SU


The first tier is the Settlement Grievance Redress Committee (SGRC), which already exists within
the Settlement; this committee will be the first level of grievance redress. The second level will be
the Resettlement Implementation Committee (RIC), which will comprise of KISIP National PCT
and Nairobi City County KISIP representative and the local administration, while the third tier
                                 LO



will be the Courts of Law, which will be adopted as the last resort.

All written/verbal grievances will be lodged through the chair of the SGRC. The SGRC will then
convene, with presence of complainant; within one week (14 days) to address the registered
                              SC




grievances. Where the complainant is satisfied and accepts the decision, corrective action will be
taken and verified by the SGRC. However, in case the SGRC is not able to resolve a complaint, it
will escalate the grievance to the RIC who will within two weeks (14 days) from the date the
complaint endeavour to resolve the grievance. Where an aggrieved party is not satisfied with the
resolution by the RIC, the party will be at liberty to appeal to the Courts of Law at any given time
                           DI




and at his/her own cost.

A grievance log will document all grievances and their status and will be used to monitor GRM
progress.

2Emphasis   of the sensitization was on sectional titling option given the settlement structural plinth areas were too small to allow
for individual titling
Abbreviated Resettlement Action Plan for Kambi Moto|EXECUTIVE SUMMARY
Page vii of 130
                            Abbreviated Resettlement Action Plan for Kambi Moto

Tenure Regularization impacts

Prior to intervention by KISIP, the settlement was already developed with permanent buildings,
without necessarily observing development control guidelines. Therefore, through the re-
planning of the settlement, the adoptive Local Physical and Land Use Development Plan
recommended that all the blocked accesses be opened up to create better connectivity and
accessibility within the settlement. This resulted to creation of the 11 PAPs composed of 4 females
and 5 males with 2 being vulnerable (1 male and 1 female), 1 religious Institution and 1 community
group documented herein this report. This information is presented in the PAP diagram below:
Figure 0-1: PAPs Diagram
                                                               PAPs- 11

                               PAPs-9                                                           PAI/PAG-2
         Male                                                  Female -
          5                                                       4
                           Vulnerable- 2




                                                                                             PY
   Vulnerable - 1                                            Vulnerable-1


Impact mitigation




                                                                                          CO
Given the settlement is already built-up, the approved land use plan adopted to the existing
settlement situation and gave proposals based on the practicality of their implementation and in
response to the World Bank Social safeguards that require generation of zero PAPs or minimal
numbers. This avoided the conventional planning standards that would have seen a significantly
high impact on structures in the settlement.
                                      RE
At the same time, cut-off date preventing any further developments and alterations in the
settlement was set as 26/7/2019 during the plan adoption meeting with the community.
                                   SU


The full implementation of Kambi Moto ARAP will be guided by the following:
     i. Ensure all PAPs are fully facilitated before any issuance of titles. Where possible, the two
         processes can be concurrent.
     ii. Involvement of the County Government of Nairobi through the Department of Physical
                                LO



         Planning and Urban Development in implementation of the ARAP e.g. in development
         control.
In addressing grievances, this ARAP has proposed a two-tier Grievance Redress Mechanism at no
cost to the PAPs. However, the third level of legal redress carries cost implications for the PAPs.
The design of the GRM will enable timely resolution of grievances at settlement level as well as
                             SC




provide for escalation mechanisms to KISIP and Courts of Law 3. A grievance log will document
all grievances and their status and will be used to monitor GRM progress.
An institutional framework, a conclusive implementation schedule and monitoring and
evaluation mechanism will be applied in implementation of the ARAP, as documented in later
                          DI




sections of this ARAP. KISIP will adopt an internal M&E framework while external monitoring
and ARAP completion audit will be conducted by a specialized firm.




3 This is a community led process and escalation of grievances to the Courts of Law is highly unlikely
Abbreviated Resettlement Action Plan for Kambi Moto|EXECUTIVE SUMMARY
Page viii of 130
                     Abbreviated Resettlement Action Plan for Kambi Moto

Costs and Budget

The total cost for implementation of this ARAP is KES. 803, 195.00 (Read Kenya Shillings Eight
hundred and three thousand, One hundred and ninety five only).

Institutional and implementation Framework
The overall responsibility for the implementation of this ARAP is vested in KISIP. The specific
implementation tasks will however be carried out by the Resettlement Implementation
Committee (RIC) consisting of KISIP National PCT and Nairobi City County KISIP team.

The ARAP implementation activities anticipated will consist of approval and disclosure of this
ARAP by the World Bank via the website info shop and further disclosure on the ground by RIC
and KISIP. The PAPs will open bank accounts prior to disbursement of compensation funds. After
compensation funds have been disbursed, they will also be required to self-demolish their
structures within 3 months of notification and salvage construction materials. These activities will
be undertaken as detailed in the implementation schedule.
Grievance redress as well as monitoring and evaluation will be continuous activities throughout
the ARAP implementation phase while final audit will be undertaken at the end of the




                                                                        PY
implementation process. This audit will be done by firms hired by KISIP for that purpose.
This ARAP also provides for continuous sensitization of beneficiaries through KISIP PCT and
Registrar of Titles on joint accounts for spouses and the use of funds and prevention of Gender




                                                                     CO
Based Violence. Gender empowerment and sensitisation will be adequately conducted by
stakeholders including: KISIP, Chief Land Registrar and Nairobi City County; Gender
Department; local women and men-based organizations; SEC; and local community will
participate. The vulnerable also on case-by-case basis will be assisted to demolish and reconstruct
their structures by KISIP County team and the SEC.
Monitoring and Evaluation
                                RE
Monitoring will ensure that the resettlement plan is well implemented and the affected persons
are facilitated. Internal monitoring will be conducted by KISIP and the SGRC – the latter with
reference to grievances they handled, but with the RIC having an oversight role over them. Also,
monitoring will be done on a continuous basis to ensure that all responsible implementing
                             SU


agencies follow the schedule and comply with the principles of this ARAP.

External resettlement monitoring which will cover compliance and impact monitoring will be
conducted by an independent External consultant selected by KISIP.
                          LO



Conclusion and commitments
This ARAP Report is prepared to mitigate impacts arising from the planning and surveying in
readiness for tenure regularization and issuance of Title Documents for Kambi Moto informal
settlement located in Nairobi City County.
                       SC




The ARAP presents an inventory (register) of PAPs, an Asset register of affected assets and the
proposed compensation package. The process for preparation of this ARAP involved various
stakeholders’ notably SEC members, the Kambi Moto community, local community leadership,
                    DI




and KISIP National and County representatives. The meetings and discussions held were
conducted in languages that the community would easily understand Ownership of the ARAP
was internalized by the affected persons through a rigorous and adequate consultation process.
Commitments
In order to ensure that this ARAP is fully implemented, KISIP commits to undertake the
following:

Abbreviated Resettlement Action Plan for Kambi Moto|EXECUTIVE SUMMARY
Page ix of 130
                     Abbreviated Resettlement Action Plan for Kambi Moto

   •   KISIP RIC in collaboration with the Registrar of Titles will organize and carry out
       Sensitization exercises aimed at enhancing women land rights as documented in this
       ARAP.
   •   Facilitate all the affected persons according to provisions of this ARAP within 3 months
       after approval of this ARAP.
   •   Ensure Grievances raised are addressed and resolved on a timely manner during
       implementation of the ARAP.
   •   All vulnerable persons enumerated in this ARAP will be promptly facilitated in accordance
       with the provisions of this ARAP
   •   Through the National Land Commission, KISIP will undertake issuance of sectional titles
       within three months after approval of the ARAP through the Ministry of Transport
       Infrastructure Housing and Urban Development (MoTIH&UD), and NLC to beneficiaries
       and PAPs concurrently with compensation payment.
   •   Issue a three months’ notice to PAPs to enable them Self Demolish and salvage their assets.
   •   Undertake Monitoring and Evaluation of this ARAP during and after implementation




                                                                      PY
                                                                   CO
                                RE
                             SU
                          LO
                       SC
                    DI




Abbreviated Resettlement Action Plan for Kambi Moto|EXECUTIVE SUMMARY
Page x of 130
                             Abbreviated Resettlement Action Plan for Kambi Moto

    TABLE OF CONTENTS


ABBREVIATIONS……………………………………………………………………………………………………. ii
DEFINITION OF TERMS…………………………………………………………………………………………. iii
EXECUTIVE SUMMARY…………………………………………………………………………… … vi
LIST OF FIGURES………………………………………………………………………………………………….. xv
LIST OF MAPS…………………………………………………………………………………… …….. xvi
LIST OF TABLES… ………………………………………………………………………………….                                                                                           xvii
CHAPTER 1: INTRODUCTION…………………………………………………………………………………..1
  1.1    Background Information ............................................................................................ 1
  1.1    Project Location .......................................................................................................... 1
  1.2    Background of Kambi Moto Informal Settlement ...................................................... 3




                                                                                                            PY
  1.3    Project Description - KISIP’s Intervention in Kambi Moto Settlement ..................... 3
  1.4    Objectives of the Abbreviated Resettlement Action ................................................... 4
CHAPTER 2: LAND TITLING AND TENURE REGULARIZATION………………………………. 5




                                                                                                         CO
  2.1    Introduction ................................................................................................................ 5
  2.2    The Planning Process. ................................................................................................. 9
    2.2.1      Plan Preparation……………………………………………………………………………………………………..                                                                      9
  2.3    Sectional Titling in the Settlement ........................................................................... 12
                                        RE
    2.3.1      Community sensitization on Land tenure Options…………………………………………………….. 12
    2.3.2      Selection of the best titling option……………………………………………………………………………… 13
    2.3.3      Application of Sectional Titles………………………………………………………………………………..                                                              14
                                     SU


  2.4    Validation of Plan and List of Beneficiaries .............................................................. 15
  2.5    Plan Approval............................................................................................................ 15
  2.6    Surveying Phase ........................................................................................................ 15
                                  LO



  2.7    Preparation of Abbreviated Resettlement Action Plan for Kambi Moto .................. 15
  2.8    Continuous Sensitization on Title Registration ........................................................ 16
CHAPTER 3: POLICY AND LEGAL FRAMEWORK…………………………………………………….17
                               SC




  3.1    Introduction ...............................................................................................................17
  3.2    Relevant Policies and Laws of Kenya .........................................................................17
  3.3    The Constitution of Kenya of 2010 ............................................................................17
                            DI




  3.4    The Land Act (2012) and National Land Policy (2017) ............................................ 18
  3.5    Land Registration Act (2012) .................................................................................... 18
  3.6   Prevention, Protection and Assistance to Internally Displaced Persons and Affected Communities
  No. 56 of 2012 (Large Scale Development Projects) ........................................................... 18
  3.7    National Land Commission Act 2012 ....................................................................... 19
  3.8    The Valuer’s Act Cap 532 .......................................................................................... 19
Abbreviated Resettlement Action Plan for Kambi Moto|TABLE OF CONTENTS
Page xi of 130
                             Abbreviated Resettlement Action Plan for Kambi Moto

  3.9    Sectional Properties Act, 1987 (Rev. 2012) ............................................................... 19
  3.10   KISIP’s Resettlement Policy Framework .................................................................. 20
  3.11   The World Bank’s Involuntary Resettlement Policy OP 4.12 ................................... 20
  3.12   Analysis of the Gaps between National Legal Frameworks and the World Bank Policies….21
CHAPTER 4: APPROACH AND METHODOLOGY…………………………………………………….26
  4.1    Introduction .............................................................................................................. 26
  4.2    Review of relevant documents .................................................................................. 26
  4.3    Socio-economic interviews and Census Survey of PAPs .......................................... 26
  4.4    Stakeholder consultation .......................................................................................... 27
  4.5    Identification and Valuation of affected assets ......................................................... 27
  4.6    Valuation Parameters ............................................................................................... 28
  4.7    Cut-off date ............................................................................................................... 28
CHAPTER 5: PUBLIC CONSULTATION AND PARTICIPATION…………………………………. 29




                                                                                                             PY
  5.1    Introduction .............................................................................................................. 29
  5.2    Categories of stakeholders ........................................................................................ 29
  5.3    PAPs consultations.................................................................................................... 29




                                                                                                          CO
  5.4    Stakeholder meetings and issues raised ................................................................... 29
CHAPTER 6: PROJECT IMPACTS……………………………………………………………………………. 34
  6.1    Introduction .............................................................................................................. 34
  6.2    The Project Affected Persons .................................................................................... 34
                                        RE
  6.3    Impact on structures ................................................................................................. 35
  6.4    Impacts on Community Facilities (PAI) ................................................................... 37
  6.5    Impact on vulnerable Groups ................................................................................... 37
                                     SU

  6.6    Tenure Security Impact: Sectional Titles .................................................................. 37
CHAPTER 7: SOCIO-ECONOMIC PROFILE OF THE PAPS…………………………………………..38
  7.1    Household identification .......................................................................................... 38
  7.2    Structural details ....................................................................................................... 38
                                  LO




  7.3    Age of PAPS............................................................................................................... 38
  7.4    Marital Status of PAPs .............................................................................................. 39
  7.5    Education level of PAPS ............................................................................................ 39
                               SC




  7.6    Health........................................................................................................................ 39
  7.7    Social issues .............................................................................................................. 39
  7.8    Economic Occupation ............................................................................................... 40
                            DI




  7.9    PAPS Expenditure Patterns ...................................................................................... 40
  7.10   Willingness to get the affected structure removed ................................................... 41
CHAPTER 8: MITIGATION OF IMPACTS…………………………………………………………………. 42
  8.1    Introduction .............................................................................................................. 42
  8.2    Planning and Survey Impact Mitigation Measures .................................................. 42
Abbreviated Resettlement Action Plan for Kambi Moto|TABLE OF CONTENTS
Page xii of 130
                               Abbreviated Resettlement Action Plan for Kambi Moto

  8.3      Mitigation and Entitlements ..................................................................................... 42
  8.4      Entitlement Matrix ................................................................................................... 43
CHAPTER 9: GRIEVANCE REDRESS MECHANISM………………………………………………….. 44
  9.1      Introduction .............................................................................................................. 44
  9.2      Grievance Redress Management Mechanism........................................................... 44
  9.3      Settlement Grievance Redress Committee (SGRC) .................................................. 44
  9.4      RAP Implementation Committee (RIC) ................................................................... 45
  9.5      Legal Redress ............................................................................................................ 45
  9.6      Procedures for Receiving and Resolving Grievances ................................................ 45
CHAPTER 10: INSTITUTIONAL AND IMPLEMENTATION ARRANGEMENTS ………………48
  10.1     Overview ................................................................................................................... 48
  10.2     Resettlement Implementation Institutions .............................................................. 48
  10.3     ARAP implementation at KISIP ............................................................................... 50




                                                                                                              PY
     10.3.1       KISIP Project Coordination Team…………………………………………………………………………….. 50
     10.3.2       KISIP ARAP Implementing Committee…………………………………………………………………….. 50
     10.3.3       County KISIP teams………………………………………………………………………………………………… 51




                                                                                                           CO
     10.3.4       Settlement Executive Committee (SEC)…………………………………………………………………….. 52
     10.3.5       The Settlement Grievance Redress Committee…………………………………………………………… 52
  10.4     ARAP Implementation Process Flow ........................................................................ 52
  10.5     Other Supporting Institutions .................................................................................. 55
                                          RE
  10.6     Gender Empowerment during ARAP implementation ............................................ 55
  10.7     Implementation procedures ..................................................................................... 55
  10.8     ARAP Schedule ......................................................................................................... 57
  10.9     Costs and Budget ...................................................................................................... 59
                                       SU


CHAPTER 11: MONITORING AND EVALUATION AND IMPLEMENTATION OF THE
ARAP………………………………………………………………………………………………………………….. 60
  11.1     Introduction .............................................................................................................. 60
                                    LO



  11.2     Monitoring and Evaluation Framework ................................................................... 60
     11.2.1       ARAP Monitoring Plan                                                                                                       60
     11.2.2       ARAP Monitoring Framework                                                                                                  61
                                 SC




  11.3     Resettlement Completion Audit ............................................................................... 63
CHAPTER 12: CONCLUSION AND COMMITMENTS……………………………………………………64
  12.1     Conclusion................................................................................................................. 64
                              DI




  12.2     Commitments ........................................................................................................... 64
  REFERENCES ................................................................................................................... 66
ANNEXES…………………………………………………………………………………………………………….. 67
  Annex 1: Minutes of the PAPs Consultation Meeting Held on 21 st August 2019 at the Muungano Kambi
  Moto Social Hall, Kambi Moto from 10:55 am. ................................................................... 67

Abbreviated Resettlement Action Plan for Kambi Moto|TABLE OF CONTENTS
Page xiii of 130
                            Abbreviated Resettlement Action Plan for Kambi Moto

  Annex 2: Minutes of the Final Stakeholders Meeting Held on 4th of November 2019 at the New Mathare
  Church Hall, Kambi Moto from 2:00 pm. ........................................................................... 74
  Annex 3: Minutes of the Presentation and Adoption of Proposed Kambi Moto Settlement Draft
  LP&LUDP, Final Verification Exercise of the List of Beneficiaries & Launch RAP meeting Held on 26th
  of July 2019 at New Mathare Church Hall, Kambi Moto from 10:20am. ........................... 86
  Annex 4: Minutes of Stakeholder Engagement Meeting (Presentation of Socio Economic Survey
  Findings, Validation of Base maps, Visioning and Community Participatory Planning) Held on 30th May
  2019 at Kambi Moto from 10: 30 am. .................................................................................. 94
  Annex 5: Minutes of the Project Launch Workshop Held on 27th March 2019 at 2: 23 Pm in Kambi Moto
  Settlement, Nairobi ............................................................................................................ 102
  Annex 6: Minutes of the Project Introduction Meeting Held on 27 th February 2019 at the Muungano
  Kambi Moto Hall, Kambi Moto from 11:55 am. ................................................................. 109




                                                                                               PY
                                                                                            CO
                                       RE
                                    SU
                                 LO
                              SC
                           DI




Abbreviated Resettlement Action Plan for Kambi Moto|TABLE OF CONTENTS
Page xiv of 130
                                Abbreviated Resettlement Action Plan for Kambi Moto

      LIST OF FIGURES

Figure 0-1: PAPs Diagram ......................................................................................................................... viii
Figure 6-1: Kambi Moto PAPs Diagram ..................................................................................................... 34
Figure 7-1: Years when PAPs moved to Kambi Moto ................................................................................. 38
Figure 7-2: Education level of PAPS ........................................................................................................... 39
Figure 7-3: PAPS Expenditure ..................................................................................................................... 41
Figure 9-1: Grievance Redress Procedure ...................................................................................................47
Figure 10-1: ARAP Implementing Institutions............................................................................................53
Figure 10-2: Stakeholder Engagement Strategy ........................................................................................54




                                                                                                           PY
                                                                                                        CO
                                           RE
                                        SU
                                     LO
                                  SC
                               DI




Abbreviated Resettlement Action Plan for Kambi Moto|LIST OF FIGURES
Page xv of 130
                               Abbreviated Resettlement Action Plan for Kambi Moto

      LIST OF MAPS

Map 1-1 : Location of Kambi Moto Settlement ............................................................................................. 2
Map 2-1: Kambi Moto LP&LUDP ................................................................................................................ 11
Map 6-1: Impacted Structures .................................................................................................................... 36




                                                                                                         PY
                                                                                                      CO
                                          RE
                                       SU
                                    LO
                                 SC
                              DI




Abbreviated Resettlement Action Plan for Kambi Moto|LIST OF MAPS
Page xvi of 130
                                 Abbreviated Resettlement Action Plan for Kambi Moto

      LIST OF TABLES

Table 2-1: Tenure Regularization Process .....................................................................................................5
Table 2-2: Analysis of planning alternatives in Kambi Moto Informal settlement..................................... 10
Table 2-3: Comparison of title options explored and discussed with the community ................................ 12
Table 2-4: Main Concerns raised by community and responses given during the Plan Adoption Meeting
Held on 26th July 2019 ............................................................................................................................... 13
Table 3-1: Comparative Analysis of World Bank OP 4.12 and Kenya constitution and GAP filling
Measures……………… .................................................................................................................................... 21
Table 4-1: Stakeholder participation during the PAPs meeting ................................................................. 28
Table 5-1: Stakeholder involvement ........................................................................................................... 30
Table 5-2: Main Issues raised by PAPs and responses given ..................................................................... 32
Table 6-1: Summary of the impacted structures .........................................................................................35
Table 8-2: Entitlement Matrix.................................................................................................................... 43




                                                                                                            PY
Table 10-1: National and County Government ARAP Implementing Institutions .................................... 49
Table 10-2: RAP implementation schedule ................................................................................................. 57
Table 10-3: Summary of ARAP Implementation budget for Kambi Moto settlement ................................59




                                                                                                         CO
Table 11-1: Monitoring Plan ........................................................................................................................ 60
Table11-2: Monitoring Indicators ................................................................................................................ 61
                                           RE
                                        SU
                                     LO
                                  SC
                               DI




Abbreviated Resettlement Action Plan for Kambi Moto|LIST OF TABLES
Page xvii of 130
                Abbreviated Resettlement Action Plan for Kambi Moto


CHAPTER 1: INTRODUCTION


1.1    Background Information

The Kenya Informal Settlements Project (KISIP) is a five-year project of the
Government of Kenya (GOK) with support from the World Bank, through the
International Development Association, (IDA), the Swedish International
Development Cooperation Agency (Sida) and the Agence Française de Development
(AFD). KISIP is an initiative of the GoK, through the Ministry of Transport,
Infrastructure, Housing and Urban Development (MTIH&UD). The overall project
strategic objective is to improve living conditions of people living and working in
informal settlements in Kenya’s fourteen (14) selected counties, of which Nairobi City
County - where Kambi Moto informal settlement is located is one of the beneficiary
counties. The Kenya Informal Settlements Improvement Programme (KISIP) aims at
addressing inequality and disparities in livelihoods and quality of life in informal




                                                                  PY
settlements through four key components namely: -
1.    Institutional strengthening/development and program management
      to assist in strengthening the capacity of the Ministry of Transport,
      Infrastructure, Housing and Urban Development and the participating counties.




                                                               CO
      This finances program management activities (including preparation of a
      baseline platform and systems for monitoring and evaluation).
2.    Enhancing tenure security to scale-up and process systematization of
      ongoing efforts to regularize tenure in urban slums. It includes financing for the
      following types of activities: community organization and mobilization,
                            RE
      identification and demarcation of settlement boundaries, preparation of Part
      Development Plans, and issuance of letters of offer/allotment to
      individuals/groups.
3.    Investing in settlement restructuring and infrastructure to support
                         SU


      implementation of settlement upgrading plans developed at the community
      level, investment in settlement level infrastructure and, where necessary,
      extension of trunk infrastructure to settlements.
4.   Planning for growth: Supporting delivery of affordable housing and serviced
                      LO



     land supporting proactive planning to dampen the growth of new slums and
     mechanisms for delivery of land and housing that can enhance affordability for
     middle- and low- income households.
For this particular assignment, the project aimed at improving security of land tenure
                   SC




based on Local Physical and Land Use Development Plans developed through a
community participatory process with the local Kambi Moto community.

1.1 Project Location
                DI




Kambi-Moto settlement is located in Mathare North Constituency near the northern
boundary of Moi Forces Academy across Juja road in Huruma. It is approximately 12
Km from Nairobi City and North East of Nairobi City (1o 15’S, 36o 52’E). It is also in
in close proximity to Outering road on the eastern side, 300m from the famous
‘Rounda’ landmark in the area. It covers 0.43 Ha. The settlement has a uniqueness

Page 1 of 130
                Abbreviated Resettlement Action Plan for Kambi Moto


since upgrading efforts through improvement of houses to permanent multi-storey
structures (up to 3rd floor) has already been done.




                                                             PY
                                                          CO
                            RE
                         SU
                      LO
                   SC
                DI




Map 1-1 : Location of Kambi Moto Settlement



Page 2 of 130
                Abbreviated Resettlement Action Plan for Kambi Moto


1.2 Background of Kambi Moto Informal Settlement

The settlement started in early 2000s. The settlers occupied the land, which was
initially designated for car parking of the adjacent defunct Huruma ‘D’ and ‘E’ Nairobi
City Council (now Nairobi City County Government) residential housing estates, and
put up one-roomed “mabati” structures. With the increasing population and
expanding families, extensions were made onto the initial access ways leading to
congestion. The settlement was thereafter characterized by incessant infernos. This
resulted to the name ‘Kambi Moto’ a Kiswahili phrase meaning –a camp of fire.
Through the intervention of NGOs (Pamoja Trust and Muungano wa Wanavijiji) and
Nairobi City Council in collaboration with the local community, they sought applicable
and affordable approaches for upgrading of the informal settlement.
With the community members being the source of labour, they upgraded the informal
settlement in-situ using blocks. The community opted for incremental construction of
these structures. As a result, this enabled the creation of through access paths with
some open space squares also provided for.




                                                                  PY
Currently, most of the settlement is built-up and occupied, with characteristic high-
rise structures (3 floors high), with rooms measuring 16x14 ft. This, according to the
community, is a perfect example of successful informal settlement upgrading model
driven by the community.




                                                               CO
However, despite improvement of the housing conditions, the settlement still ails from
insecurity of tenure, which still makes the community live with uncertainty and fear of
imminent evictions. It is for this reason that KISIP in collaboration with the Nairobi
City county government undertook to provide security of tenure to the inhabitants,
through this project.
                            RE
1.3 Project Description - KISIP’s Intervention in Kambi Moto
    Settlement
                         SU


At the time of starting the KISIP project in the settlement, the occupants were on
public land under the Nairobi City County government. KISIP’s component 2
interventions in Kambi Moto informal settlement entailed physical planning and
                      LO



surveying of the informal settlement, which led to the development of a local physical
and land use development plan. The plan was implemented through surveying process
and eventually led to the beneficiaries being issued with sectional properties title
deeds.
                   SC




The project is being executed through collaboration with various actors at the national,
county and community level. The national government organs include; Ministry of
Transport, Infrastructure, Housing and Urban Development, Ministry of Lands and
                DI




Physical Planning, and National Land Commission (NLC). Nairobi City County is
represented by the department of Lands, Housing and Physical Planning, KISIP
county coordination team, Sub county and ward administration. The community is
represented by the Settlement Executive Committee (SEC) selected from residents in
the settlement and the Local administration / leadership as ex-officials (in particular
the chief). As a result of this planning and surveying process, 11 temporary structures
belonging to 11 PAPS were affected and all of them were surveyed and valued. This
Page 3 of 130
                Abbreviated Resettlement Action Plan for Kambi Moto


then triggered the preparation of this Abbreviated Resettlement Action Plan to
mitigate the resultant impacts.

1.4 Objectives of the Abbreviated Resettlement Action

The objective of this Abbreviated Resettlement Action Plan (ARAP) is to identify,
document and mitigate the impacts arising from implementation of the approved
LP&LUDP which led to physical effects (loss of shelter/occupancy) in accordance with
the provisions of World Bank Operational Policy 4.12 - Involuntary Resettlement, and
the national legal framework. The ARAP provides Projected Affected Persons with
facilitation for their affected assets at full replacement cost while at the same time
providing support for vulnerable groups. The specific objectives of the ARAP are to:

   • Enumerate project affected persons in order to determine those affected by the
     project, the severity and extent of the impacts;
   • Generate list of the vulnerable groups so as to develop strategy to ensure that




                                                                PY
     they proactively benefit from the project;
   • Adequately consult and actively involve all the PAPs and other stakeholders
   • Guide on the legal and other institutional frameworks governing resettlement
     as outlined in the World Bank policies and Kenyan law;




                                                             CO
   • Develop mitigation measures in consultation with the affected people;
   • Prepare detailed entitlement matrix and an implementation plan;
   • Prepare a ARAP budget and;
   • Put in place a Monitoring and Evaluation and reporting system for the
     Resettlement Plan.
                            RE
The Kambi Moto ARAP was triggered by the planning and surveying of the informal
settlement through the KISIP Intervention, which affected 11 structures.
                         SU
                      LO
                   SC
                DI




Page 4 of 130
                Abbreviated Resettlement Action Plan for Kambi Moto


CHAPTER 2:                       LAND TITLING AND TENURE
     REGULARIZATION

2.1 Introduction

Land tenure refers to the manner in which individual/ groups of people within a
particular community enjoy rights of access to land. There are three types of land
tenure according to the constitution of Kenya (2010); Private, communal and public
land. For this project, the intervention is meant to transfer the land from public to
private ownership.

The tenure regularization process, in this project defined by planning, surveying,
preparation of ARAP and Titling Processes was therefore organized around 5 phases
as shown in table 2-1 below;




                                                                    PY
Table 2-1: Tenure Regularization Process
 Stage              Activities        Primary    Seconda    Indicators     Timelines
                                      Actor      ry Actor
1) Mobilizati •       Communit        SEC        County  ⎯ Gender          Undertaken
                      y




                                                                 CO
   on Stage                                      Governm    representati
                      Mobilizatio     KISIP
                                                 ent        ve      SEC
                      n               Consulta              compositio
                •     Introductio     nt                    n
                      n of KISIP      working            ⎯ Community
                      activities in   under                 welcomed
                            RE
                      Kambi           KISIP                 the project
                      Moto
                                                            as they have
                      Informal
                                                            been
                      Settlement
                                                            waiting on
                •     Outlining                             title   deed
                         SU


                      the                                   for a long
                      objective of                          time.
                      Planning
                                                         ⎯ Community
                      and Survey
                                                           committed
                      which will
                      LO



                                                           to embrace
                      lead       to
                                                           and support
                      issuance of
                                                           the project
                      title deeds.
                                                           until
                                                           completion
                   SC




2) Planning Stage

i.   Base Map •       Transect        Commun     KISIP   ⎯ Base map of     Undertaken
                DI




     Preparati        walks           ity
                                                 County    Kambi
     on    and        guided by
                                      SEC        Governm   Moto
     physical         SEC
                                                 ent       Informal
     Mapping •        157             Consulta             Settlement
                      Beneficiari     nt                 ⎯ Every
                      es              working              Beneficiary
                      identified.

Page 5 of 130
                   Abbreviated Resettlement Action Plan for Kambi Moto


 Stage                 Activities         Primary    Seconda      Indicators       Timelines
                                          Actor      ry Actor
ii. Socio-         •     Existing         under                   was
                         settlement       KISIP                   enumerated
    economic
    Survey               boundaries                             ⎯ Participatio
                         and                                      n of SEC
                         developed                                ensured
                         structure                                that    only
                         layout form                              members of
                         basis    for                             Kambi
                         Planning                                 Moto
                         and                                      Informal
                         surveying                                settlement
                   •     100       %                              were       the
                         Socioecono                               registered
                         mic survey                               beneficiarie
                         of       the                             s
                         settlement                             ⎯ Beneficiary




                                                                            PY
                         Beneficiari                              list
                         es                                       representati
                                                                  ve          of
                                                                  women
                                                                  beneficiarie




                                                                         CO
                                                                  s as well.

i.   Presentati        Community          Commun     Nairobi      Active           Undertaken
     on of the         adoption     of    ity        County       Women
     socio-            the findings as               Governm      participation
                                          SEC
                       the        true               ent          in       every
                            RE
     economic
     findings          reflection of      Consulta                planning
     to      the       the settlement     nt                      stakeholder
     communit                             working                 meeting.
                       A community
     y                                    under
                       led visioning                              Community
                         SU

ii. Visioning                             KISIP
                       process                                    adopts    the
     and Plan                             KISIP                   pedestrianisa
     preparati         Community
                                                                  tion of the
     on                prioritizes
                                                                  existing
iii. Prelimina         accessibility
                      LO



                                                                  internal
     ry                Community                                  accesses to
     verificatio       involved     in                            avoid
     n of the          preparation of                             creation   of
     List     of       plan that best                             high number
     beneficiar
                   SC




                       represents                                 of PAPs
     ies               their interests.
                       Preliminary
                       confirmation
                DI




                       of          the
                       beneficiaries
                       details on list
                       of
                       beneficiaries




Page 6 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


 Stage            Activities        Primary     Seconda    Indicators       Timelines
                                    Actor       ry Actor
i.  Plan          A community       Commun      KISIP      Community        Undertaken
    Validation    led validation    ity                    adoption of
                                                Nairobi
    and           of        plan                           the plan
                                    SEC         County
    Approval      ensured                                                   Nairobi County
                                                Governm    County
ii. Final         community         Consulta                                Government
                                                ent        approval of
    Verificati    vision       is   nt                                      approved the
                                                           Plan      step
    on of List    represented       working                                 plan
                                                           towards
    of                              under
                  Community                                tenure
    Beneficiar                      KISIP
                  endorsed Plan                            regularizatio
    ies                                                    n         and
                  Discussion on
                                                           issuance of
                  the     titling
                                                           titles
                  options
                  (community
                  adopted the
                  sectional




                                                                     PY
                  properties
                  titles)
                  Final
                  confirmation




                                                                  CO
                  of    list   of
                  beneficiaries
                  w          and
                  Issuance     of
                  project     ID
                  cards        to
                            RE
                  beneficiaries
                         SU

3) Surveying stage

 Surveying        Settlement        Commun      KISIP      Impacts and      Undertaken/
 and              Boundary          ity                    PAPs
                                                Nairobi
 Computatio       Beaconed and                             documented
                      LO



                                    SEC         County
 n   of    the
                  Each                          Governm
 structure                          Consulta
                  beneficiaries’                ent
 areas                              nt
                  structural
                                    working
                  area         is
                                    under
                   SC




                  computed and
                                    KISIP
                  coordinates
                  picked
 Approval of      Survey            Survey of   KISIP      New      RIM     undertaken
                DI




 Survey Plan      approval and      Kenya                  forwarded to
                  adjustment of                            Ministry of
                  Registry Index                           Land      for
                  Map (RIM) to                             Titling
                  include                                  process.
                  settlement
                  surveyed

Page 7 of 130
                   Abbreviated Resettlement Action Plan for Kambi Moto


    Stage           Activities         Primary       Seconda       Indicators        Timelines
                                       Actor         ry Actor
                    boundary
                    number
4) ARAP Preparation

    ARAP            Identified         Commun        KISIP         Entitlements      Undertaken
    Preparation     impacts are as     ity                         are given to
                                                     County
                    a result of                                    mitigate
                                       SEC           Governm
                    planning and                                   impacts
                                                     ent
                    survey      are    Consulta
                    identified,        nt
                    documented         working
                    and mitigated      under
                                       KISIP
    ARAP            Ensure client      World         Consulta      Approved          Ongoing
    Approval        commitment         Bank          nt            ARAP        to




                                                                              PY
                    to                               working       guide
                    implementati                     under         implementati
                    on of ARAP.                      KISIP         on     process
                                                                   and issuance
                    All safeguards
                                                                   of Titles




                                                                           CO
                    provisions are
                    met       and
                    addressed
    ARAP            Implementing       KISIP         Consulta      Facilitation      Not        yet
    implementa      ARAP                             nt            of PAPs           undertaken
                                       Commun
    tion            activities  as                   working
                              RE
                                       ity                         GRM
                    per                              under
                    implementati       County        KISIP         Issuance of
                    on schedule                                    Title Deeds
                                                                   (undertaken
                           SU

                                                                   after
                                                                   facilitation)
5) Land Titling
                        LO



    Sensitizatio    Registrar of       Registrar     County        Men allow for     Undertaken/
    n on Title      Titles             of Titles     Governm       joint titling     more
    owner ship4     Sensitizes                       ent           with spouses.     sensitization to
                                       Commun
                    Beneficiaries                                                    be carried out
                                       ity           Consulta      Beneficiaries
                    on                                                               during
                                                     nt            aware        of
                     SC




                    (i)Benefits of     SEC                                           implementatio
                                                     working       Benefits     of
                       the Titles      KISIP                                         n of the ARAP
                                                     under         the title being
                    (ii)     Condit
                                                     KISIP         issued.
                       ions to be
                       granted on                                  Beneficiary
                  DI




                       sectional                                   grievances
                       Titles                                      adequately
                                                                   addressed


4 The Community was Sensitized on the available tenure options out of which Sectional Titles was the most
appropriate for the settlement

Page 8 of 130
                Abbreviated Resettlement Action Plan for Kambi Moto


 Stage           Activities          Primary     Seconda    Indicators         Timelines
                                     Actor       ry Actor
                 (iii)   Law
                    requiremen
                    ts        in
                    Regulation
                    of      land
                    transaction
                    s
 Titles          The         final   Ministry               Signed Titles      Not        yet
 Printing and    beneficiary         of Lands-              are handed         undertaken
 Signing         list is the basis   Chief                  over       to
                 of printing of      Land                   National
                 Titles              Registrar              Land
                                                            Commission
                                                            for Approval.
 Gazzetemen      The       NLC       National               The names of       Not        yet




                                                                       PY
 t               approves            Land                   Beneficiaries      undertaken
                 transfer     of     Commiss                is    officially
                 Public land to      ion                    published in
                 individual                                 the      Kenya
                 beneficiaries                              Gazette      as




                                                                    CO
                 in      Kambi                              individual
                 Moto                                       title holders
                                                            securing their
                                                            tenure
 Issuance of     Upon                NLC         County     Beneficiaries      Not        yet
                            RE
 Title           facilitation of                            finally have       undertaken
                                     KISIP
                 All       PAPs,                            individual
                 Titles      are                            sectional
                 issued       to                            titles to their
                 respective                                 land. Tenure
                         SU


                 beneficiaries                              regularizatio
                 in a public                                n is complete
                 event.
                      LO



2.2 The Planning Process

The following section details the planning process in Kambi Moto informal Settlement.
                   SC




2.2.1 Plan Preparation
A notice of intention to prepare local physical and land use development plan for
Kambi Moto informal settlement was published in the print media, by the Director of
physical planning, as stipulated in the repealed Physical Planning Act Cap 286 so as to
                DI




pave way for the planning process. Following the community participatory planning
activity, the process involved preparation of two planning models, namely, Adoptive
planning model and nil intervention models incorporating the vision, the needs and
aspirations of the community. The two alternatives were thereafter presented to the
community, while highlighting the pros and cons of each option. The Adoptive
planning model was unanimously selected, owing to its flexibility and minimal number

Page 9 of 130
                    Abbreviated Resettlement Action Plan for Kambi Moto


of PAPs. This was also informed by the existing settlement pattern that is generally
well defined and with most structures built to multi-storey level. Table 2-2 below
shows a summary of the analysis of the two models.

Table 2-2: Analysis of planning alternatives in Kambi Moto Informal settlement
      Planning                     Advantages                                    Disadvantages
     Alternative
    Alternative 1: • No demolition of existing                     • No planning intervention
    Nil              structure/developments or                     • Can only achieve a community title
    intervention     relocation of people.                           against the community preference to
                                                                     individual titles
                                                                   • Sustained encroachment onto existing
                                                                     foot path reserves/wayleaves

    Alternative:        • Would enhance attainment of              • The structures blocking the access ways
    Adoptive              sectional properties titles to             have to be removed creating PAPs.




                                                                                   PY
    Planning              each beneficiary Allows for
    Approach              mixed-use developments
                        • Provides Guidelines for
                          futuristic development




                                                                                CO
                          dynamics
                        • Adopts the pedestrian internal
                          access paths
                              RE
The community chose the Adoptive planning alternative5 due to its flexibility. The
adoptive plan alternative would:

      i. Result in minimal interruptions as its implementation was likely to cause
           minimal PAPs. None of the beneficiaries would experience complete or
                           SU


           localized displacement.
      ii. Lead to a realization of the vision of the settlement residents such as improved
           circulation and accessibility.
      iii. The Adoptive approach borrowed heavily from the community proposals and
                        LO



           aspirations obtained from the visioning and participatory planning exercise.
                     SC
                  DI




5Full impact is applying since the structures are just temporary and they will be removed to open up the blocked
accesses.



Page 10 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


   Map 2.1 presents LP&LUDP prepared for the settlement




                                                              PY
                                                           CO
                             RE
                          SU
                       LO
                    SC
                 DI




Map 2-1: Kambi Moto LP&LUDP



Page 11 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


2.3 Sectional Titling in the Settlement

2.3.1 Community sensitization on Land tenure Options

The community was sensitized on the two tenure options (community & sectional
titles) during the community participatory planning exercise held on 30th May and on
26th July 2019 (see annex 4). Although a majority of the community members (54%)
had opted for one community title during the socio-economic survey exercise, they had
a change of mind after sensitization of the two options (community and sectional
properties title) upon the realization that individual titling was a possibility through
sectional titles. Apart from ensuring security of tenure for individual beneficiaries,
Sectional Titles will achieve a greater sense of communal lifestyle, maintaining the
social networks and interactions within the community.

The Settlement is comprised of individual structures of a footprint area of 4m by 4m
with a 3 vertical levels(sections) with a total plinth area is 48m2. This settlement




                                                                  PY
pattern, coupled with the World Banks’s provisions on zero or minimum generation of
PAPs, greatly influenced the choice of sectional titles tenure option. The following
table provides a comparison between the two tenure options presented to the
community.




                                                               CO
Table 2-3: Comparison of title options explored and discussed with the community
 No    Subject           Community Title                 Sectional Titles

 1.    Form of           One title issued to the         Unit titles are issued to individual
       Tenure            community                       beneficiaries
                             RE
 2.    Ownership         The property is owned           Sections(units) are owned by the
                         jointly by the community as     respective individuals
                         co-tenants                      Common properties are owned
                                                         jointly as tenants in common.
                          SU


 3.    Management        Managed through a               Community forms a corporation as
                         corporation                     per the provisions of Sectional
                                                         properties Act-process will be
                       LO



                                                         facilitated fully by KISIP
 4.    Disposition of    Depending on the type of        The individual owner can dispose off
       property          shares ownership, it is         his/her property with approval of
                         possible to transfer shares     the corporation
                         between parties, with
                    SC




                         approval of the group
 5.    Loan              It is not possible to use the   The individual owner can use their
       application       property for application of a   property to apply for loans
                         loan at an individual’s
                 DI




                         capacity
 6.    Alterations of    The community title relates     Owners lack freedom to alter,
       buildings         to land and not buildings; it   renovate or expand their sections
                         is therefore possible to        without the approval of the body
                         impose changes on               corporate
                         individual buildings

Page 12 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


 7.    Community         Both options achieve a greater sense of communal lifestyle
       Interactions



2.3.2 Selection of the best titling option

Based on the above analysis that was also presented to the community, during a
meeting held on 26th July, 2019, the sectional titles option was unanimously adopted
by the Kambi Moto community.

To foster legitimacy and acceptability of the LP&LUDP and the entire process of tilting
thereof, community participation and engagements was central throughout the
planning and surveying process. This comprehensive and inclusive planning process
brought stakeholders including community members; (SEC members,
landlords/structure owners, tenants, youths, the minority groups, community elders,
business community, CBOs, NGOs, and religious leaders; technical staff (KISIP




                                                                 PY
County and National Teams, the Consultant) and other key stakeholders including the
area chief and area MCA. Details of the Meetings provided under Section 4.0. Out of
the stakeholders’ engagement meetings, the key sensitization messages revolved
around:
 • Progress of each project output accompanied by presentations to the community




                                                              CO
    for comments and concurrence
 • Selection and adoption of most preferred planning option that would ensure
    minimum disruption of the community set-up
 • Formulation of plan proposals including community-led decisions on
    beneficiaries who had blocked the access ways. The community members
                             RE
    expressed their willingness to relocate throughout the project period.
 • Selected provisions from the Constitution of Kenya on rights of ownership of Land
    and property, inclusion of women, the minority groups and vulnerable groups, and
    protection of the Environment. Protection of Children’s rights was also
                          SU


    encouraged.
 • The community was also sensitized on possible grievances that would arise during
    the process and ensuring amicable resolution of disputes through the community
    led mechanism, that is the SEC and Grievance Redress committee
                       LO



 • Ensuring that they do not interfere with the beacons, but rather, they were
    encouraged to protect them.
 • Cut-off date of 26th July 2019 during plan adoption stakeholders meeting.

Table 2-4: Main Concerns raised by community and responses given during the Plan
                    SC




Adoption Meeting Held on 26th July 2019
 Concern                                  Response
 There are beneficiaries within the       It was made clear that sectional property titling
 settlement who have not yet              can be taken to any level of development. Unbuilt
                 DI




 developed their parcels. How will        parcels will be taken as plot numbers and upon
 they be considered under the             development of structures, the owners will be
 sectional titling option?                forced to adhere to the existing building plan




Page 13 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


 What name can best be adopted              The beneficiaries were informed that they were
 by the residents for the Sectional         free to choose their most preferred name for the
 Title option during                        title. They were advised to convene a meeting for
 establishment of the                       the same.
 corporation?
 What will happen to the                    It was made clear that individual titling was not
 residents occupying only one               achievable in the settlement due to the small sizes
 floor with regards to sectional            of land occupied by the residents (16m2).
 property titling option?                   However, it can be achieved through sectional
 Residents need to be issued titles         properties titling where during the survey
 basing on the land they occupy             process, structure coordinates will be picked by
 and not the structures.                    the project surveyor. KISIP will bear all the costs
                                            of the titling process. Moreover, it was also made
                                            clear that beneficiaries seeking to develop their
                                            structures further after completion of the KISIP




                                                                   PY
                                            project will be forced to undertake further survey
                                            at their own cost




                                                                CO
2.3.3 Application of Sectional Titles

On operationalization of the sectional properties, the community was informed on the
following;
   i.  Sectional Titles will be issued for each unit (against the total plinth area of the
                             RE
       structure). Certificates will also be issued to show the share in the common
       property apportioned to each unit owner.
  ii.  After registration of the Unit, as stipulated in subsection (1) of the Sectional
       Properties Act of 1987, the unit may devolve or be transferred, leased, charged
                          SU

       or otherwise dealt with in the same manner and form as land held under the
       Registered Land Act (Land Act).
 iii.  In the case of Kambi Moto where there are shared property walls, one registered
       unit can effect minimal alterations in case of change in desired design
 iv.   As provided by the Sectional Properties Act of 1987 the community is required
                       LO



       to form a corporation for all the 145 beneficiaries to facilitate registration of
       sectional Plan. The community was guided on the formation of the corporation,
       and the community already undertook this activity during the planning phase,
       including election of officials and formulation of the requisite constitution that
                    SC




       dictates the rules and regulations of their administrating and managing their
       community henceforth. The community officials and the constitution
       formulated by the community was presented and discussed during the final
       stakeholders meeting held on 4th of November 2019 (See Annex 2). However,
                 DI




       more sensitization will be done by KISIP in collaboration with the department
       of lands, Ministry of Lands and Physical Planning in subsequent steps of
       registration of the sectional titles. All costs accruing to the formation,
       registration and training on the corporation on their mandates in tenure
       management will be borne for by KISIP
  v.   The Corporation shall have perpetual succession and a common seal.


Page 14 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


 vi.   The Corporation formulated by the 145 Kambi Moto beneficiaries shall be
       regulated in accordance with the provisions of the Sectional Properties Act, and
       the bylaws specified in the regulations shall subject thereto, have effect in
       relation to the corporation and its board. However, the provisions of Company’s
       Act shall not be applicable to the corporation.
vii.   The corporation shall be required to make by laws to ensure control,
       management and regulation of the units as well as utilization of shared property


2.4 Validation of Plan and List of Beneficiaries
The Kambi Moto community validated and endorsed the LP&LUDP on 26 th of July
2019 (see annex 3) in the presence of the project’s consultant, KISIP National and
County teams and local Member of County Assembly representative. The community
confirmed that the Adoptive plan was their best choice and it had been prepared with
their inputs.

The final verification and validation of list of beneficiaries was necessary to ensure that
only the legitimate structure owners were enumerated in the list of beneficiaries. This




                                                                    PY
exercise was conducted twice during the project period – (Preliminary Verification and
the Final Verification). Verification of the Final list of beneficiaries was done between
26th and 27thJuly 2019. It involved issuance of project ID cards to the beneficiaries and
those signing in the List of beneficiaries confirming their details were correctly




                                                                 CO
captured.
To safeguard the legitimate beneficiaries against imposters, the following measures
were undertaken;
           • The SEC was involved and they played a key role in ascertaining the
               actual structure owners in the settlement
                             RE
           • Involvement of local leadership / administration (including the area
               chief, Deputy County Commissioner, village elders)
           • To avoid any ownership disputes, all the beneficiaries would identify
               their close neighbours thus preventing people from outside the
               settlement claiming structure ownership in the settlement.
                          SU


           • The exercises of verification of the List of beneficiaries was done publicly

2.5 Plan Approval
                       LO



The Kambi Moto LP&LUDP was approved by the Nairobi City County Government
under the plan approval reference - UP/UPR&S/ZONE 17/182/01/20.

2.6 Surveying Phase
                    SC




The surveying phase involved boundary picking, pickings and computing the
structural areas for registration of the sectional titles, approval process of the survey
plans and amendment of the RIM.
                 DI




2.7 Preparation of Abbreviated Resettlement Action Plan for
    Kambi Moto
The preparation of the Local Physical and Land Use Development Plan and surveying
for Kambi Moto Settlement, which aims at achieving tenure regularization, resulted to
11 PAPs. This was as a result of the proposed opening up of all the foot path access
within the settlement, which led to removal of the blocking structures.
Page 15 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto



With the community adopted plan and the expected no change in the plan layout, it
formed the basis of the process of preparing this report. Considering that, the impact
was minimal, and the affected beneficiaries are less than 200, an Abbreviated
Resettlement Action Plan has been prepared, as per the World Bank’s OP 4.12 and
specifications in the KISIP Resettlement Policy Framework.

2.8 Continuous Sensitization on Title Registration
There has been a continuous community sensitization on land ownership rights. It was
encouraged that everyone (male, female, institutions and vulnerable groups) had equal
rights to be registered as the rightful landowners of their parcels they occupy in the
settlement. Additional Sensitization will be undertaken during implementation of this
ARAP.

The community was sensitized on the two possible tenure options, which included
community titles and sectional titles. Due to the semi-autonomous nature and other
benefits associated with sectional titles, the community preferred this option against




                                                                  PY
the alternative of one community title. This is backed up with the fact that before KISIP
intervention, the Nairobi City County had approved the building plans that were used
to construct the structures in the settlement albeit their small sizes.




                                                               CO
Additional sensitization meeting on the subsequent registration of the sectional titles,
rules and regulations will be done by KISIP during the RAP implementation to
enlighten the beneficiaries on dynamics such as transfer of ownerships and
management of the common areas.
                             RE
                          SU
                       LO
                    SC
                 DI




Page 16 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


CHAPTER 3:                  POLICY AND LEGAL FRAMEWORK


3.1 Introduction
Preparation of the Local Physical & Land Use Development Plan (LP&LUDP) for
tenure regularization may trigger Project impacts to people’s assets and livelihoods
sources. KISIP’s RPF, anticipates minimal displacement impacts of the project
activities which could be occasioned by:
      i.   Partial demolition of structures to expand / realign road reserves and;
     ii.   Reclamation of encroached way-leaves,

The RPF has been prepared in conformity with OP 4.12 of the World Bank and is
anchored in the policy and legal provisions of the GoK pertinent to Involuntary
Resettlement. However insignificant the impacts may be, this ARAP observes that
negative impacts of displacements, resulting from tenure regularization in Kambi




                                                                  PY
Moto informal settlement, has to be mitigated through observance of appropriate legal
guidelines stipulated in the Kenya constitution 2010 and the World Bank Operational
Policy 4.12 and where the Kenyan Laws conflict with the World Bank policy, the Bank
policies takes precedence.




                                                               CO
Provisions of both GoK Laws and OP 4.12 of the World Bank will apply in the KISIP
project and where gaps are encountered, gap filling measures have been provided.
Additionally, project development has been firmly anchored on principles aimed at
mitigating displacement impact as follows:
                             RE
      i.   Involuntary Resettlement should be avoided where feasible
     ii.   Minimization of displacement
    iii.   Ensure all PAPs are adequately compensated for all losses they suffer as a
           result of the project intervention.
     iv.   Assistance to vulnerable groups.
                          SU


      v.   Gender Empowerment and Inclusivity.
     vi.   Continuous Community Consultation and engagement

3.2 Relevant Policies and Laws of Kenya
                       LO




In order to mitigate the negative impacts of the affected persons, relevant national and
local laws, regulations and guidelines on resettlement have been adopted for this
ARAP. These regulations and guidelines are as follows:
                    SC




3.3 The Constitution of Kenya of 2010
The Constitution of Kenya 2010 recognizes individuals’ right to matters of owning
property including land, and displacement. Chapter Five of the Constitution, entitled
                 DI




"Land and Environment,” articles 60 – 68, describes the principles of land policy.
Land should be held, used and managed in a manner that is equitable, efficient,
productive and sustainable and in accordance with security of land rights, sound
conservation and protection of ecologically sensitive areas.



Page 17 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


3.4 The Land Act (2012) and National Land Policy (2017)
Land Act (2012) guides the implementation and harmonisation of the National Land
Policy and the Constitution by regulating land management and administration to
increase the security of tenure The National Land Policy classifies land in Kenya as
public, community or private land. The public land is held by the state and used for
public purposes. Community land refers to land lawfully held, managed and used by a
given community as defined in article 63 of the constitution. Private land refers to land
lawfully held, managed and used by an individual or other entity under statutory
tenure.

3.5 Land Registration Act (2012)
In public land management, the Commission is required in section 10(1) to prescribe
guidelines for the management of public land by all public agencies, statutory bodies
and state corporations in actual occupation or use. In these guidelines management
priorities and operational principles for management of public land resources for
identified uses shall be stated. The land occupied by Kambi Moto informal settlement




                                                                  PY
is classified as Public land thereby invoking some sections of this Act.


3.6 Prevention, Protection and Assistance to Internally



                                                               CO
    Displaced Persons and Affected Communities No. 56 of
    2012 (Large Scale Development Projects)
In terms of large-scale development projects, the Act defines Internally Displaced
Persons as a person or group of persons who have been forced to leave their homes or
                             RE
places of habitual residence as a result of large scale development projects. Hence this
project triggers the Act. According to article 5(2) and 6(3), the government shall
prevent such displacements except where it is justified by overriding public interests.
Article 22(1-5) explains the procedures for displacement induced by development
                          SU


projects, which should take into considerations the following:
           • Seek the free consent and informed consent of the affected persons;
           • Hold public hearings on the project planning
           • Give justification for displacement and demonstrate that the
                       LO



              displacement is unavoidable and no feasible alternative exist
           • Give reasonable time to the persons affected to review the decision and
              challenge it if need be
           • the displacement to be carried out in a manner that is respectful of the
                    SC




              human rights of those affected, taking in particular into account the
              protection of community land and the special needs of women, children
              and persons with special needs
           • The process to incorporate information for those affected and their
                 DI




              effective participation, including by women, in planning, management
              of the displaced, and in defining suitable durable solutions;
           • Provisions of safe, adequate and habitable sites and to the greatest
              practicable extent, of proper accommodation; and
           • Creation of satisfactory conditions of safety, nutrition, health and
              hygiene and the protection of family unity.

Page 18 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


           •   Ensure the presence of government official when the displacement and
               relocation is effected and the monitoring by the independent body.

3.7 National Land Commission Act 2012
The National Land Commission (NLC) 2012 under Article 67(2) of the Constitution is
mandated to alienate public land on behalf of, and with the consent of the national and
county governments, monitor the registration of all rights and interests in land; ensure
that public land and land under the management of designated state agencies are
sustainably managed, manage and administer all unregistered trust and community
land.

3.8 The Valuer’s Act Cap 532
The Act establishes a board (Valuers Registration Board-VRB) with the responsibility
of registering the valuers and regulating their activities according to the provision of
the Act. In this project, the Act is triggered since a registered valuer is required to carry




                                                                     PY
out valuation estimates for the project according to the regulations in the Act. All
affected assets under this ARAP has therefore been valued by a qualified and registered
valuer.




                                                                  CO
3.9 Sectional Properties Act, 1987 (Rev. 2012)
It is an Act of Parliament that provides for the division of buildings into units to be
owned by individual proprietors and common property to be owned by proprietors of
the units as tenants in common and to provide for the use, management of the units
and for common property and connected Purposes. Section 4 of this Act, stipulates
                             RE
that the Provisions of Land use planning, relating to subdivision of land, do not apply
under a sectional plan.
In this form of tenure, each beneficiaries’ unit shall be registered and issued with a
title.
The requirements of sectional plans are as follows;
                          SU


   a) The heading of the plan shall be described as a sectional plan;
   b) Delineation of the external surface boundaries of the parcel and the location of
      the building in relation to them;
                       LO



   c) Bear a statement containing those particulars as may be necessary to identify
      the title to the parcel;
   d) Include a drawing illustrating the units and distinguishing the units by numbers
      or other symbols;
                    SC




   e) Define the boundaries of each unit;
   f) Show the approximate floor area of each unit;

Section 17 of the act requires that a corporation is registered to facilitate the
                 DI




registration process:

   1) On the registration of a sectional plan there shall be constituted a Corporation under
      the name “The Owners, Sectional Plan No. (the number to be specified being the
      number given to the plan on registration)”.
   2) A Corporation shall consist of all those persons—


Page 19 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


                   (a) who are the owners of units in the parcel to which the sectional
                       plan relates; or
                   (b) who are entitled to the parcel when the sectional arrangement
                       is terminated under this Act.
   3) The Corporation shall have perpetual succession and a common seal.
   4) The Corporation shall be regulated in accordance with this Act and the bylaws
      specified in the regulations shall subject thereto, have effect in relation to the
      corporation and its board.
   5) The provisions of the Companies Act (Cap. 486) shall not apply to the Corporation.


3.10 KISIP’s Resettlement Policy Framework

KISIP’s RPF conforms to OP 4.12 of the World Bank and is guided by the legal
provisions of the Kenya constitution 2010 as relates to Involuntary Resettlement
namely; - The National Constitution, Sessional Paper No. 3 of 2009 on National Land
Policy. The OP 4.12 of the World Bank requires that an RPF be prepared for all projects




                                                                   PY
that anticipate displacement of both settlements and livelihoods. Under KISIP’s
activities, minimal displacements are anticipated and therefore, the RPF:

   i. Provides for a policy, legal and institutional framework for responding to all




                                                                CO
        direct economic and social displacement impacts occasioned by activities
        undertaken under KISIP:
             • the involuntary taking of land resulting in relocation or loss of shelter;
                 loss of assets or access to assets; or loss of income sources or means of
                 livelihood, whether or not the affected persons must move to another
                 location; or
                             RE
             • The involuntary restriction of access to legally designated parks and
                 protected areas resulting in adverse impacts on the livelihoods of the
                 affected persons.
   ii. Offers choices among, and identify technically and economically feasible
                          SU


        resettlement alternatives; and,
   iii. Puts in place modalities for providing prompt and effective compensation at full
        replacement cost for loss of assets attributable directly to the project and
        provide support during the transitional period to enable the affected people to
                       LO



        improve or at least restore their pre-impact living standards.

3.11 The World Bank’s Involuntary Resettlement Policy OP 4.12
                    SC




The World Bank’s Involuntary Resettlement Policy OP 4.12 requires that social
impacts of all project it supports be mitigated according to operational polices that
spell out the principles and planning methods for mitigation work. The World Bank’s
IRP applies whenever property must be acquired, or its use modified, for a project, and
                 DI




that acquisition or modification results in the loss of income, residence or access to
resources, either permanent or temporary and whether the occupation is legal or
illegal. World Bank Involuntary Resettlement (OP 4.12) states that:
    • Avoiding or minimizing involuntary resettlement where feasible, exploring all
        viable alternative project design; where it is not feasible to avoid resettlement,
        resettlement activities should be conceived and executed as sustainable

Page 20 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


       development programs, providing sufficient investment resources to give the
       persons displaced by the project the opportunity to share in project benefits;
    • Displaced persons should be meaningfully consulted and have opportunities to
       participate in planning and implementing resettlement programs;
    • Displaced persons should be assisted in their efforts to improve their
       livelihoods and standards of living or at least to restore them, in real terms, to
       pre-displacement levels or to levels prevailing prior to beginning of project
       implementation, whichever is higher and;
    • The production/livelihood systems of a community are safeguarded to the
       extent that guarantees their livelihoods and that their skills base remain
       relevant regardless of the resettlement site. The policy objectives are also
       designed to minimize kinship group dislocation that might subject the affected
       persons to unfair competition when mutual help is diminished or lost.
World Bank’s (OP 4.12) allows that “for projects in which the number of people to be
displaced with a loss of assets or restriction of access to assets is less than 200 persons
will experience resettlement effects, and abbreviated resettlement plan (ARAP) should
be prepared. The displacement of 11 assets in Kambi Moto meets these conditions.




                                                                    PY
3.12 Analysis of the Gaps between National Legal Frameworks
    and the World Bank Policies




                                                                 CO
The principles behind the national legal framework and World Bank Policies are to
ensure that the affected persons are not disadvantaged due to involuntary
resettlement. Where there is a gap between Kenya law and the World Bank policy, the
World Bank policy shall apply in this ARAP.
                             RE
Table 3-1: Comparative Analysis of World Bank OP 4.12 and Kenya
constitution and GAP filling Measures
         OP 4.12                  Kenyan        Gap filling
                                Legislation     Measures
                          SU


 GENERAL REQUIREMENTS
 World Bank OP 4.12 has           1.    The Land Act,           1. Ensure        that
 overall policy objectives,             2012          Act          resettlement
 requiring that:                        outlines                   issues        are
                       LO



    1. Involuntary                      procedures for             considered at the
        resettlement should be          sensitizing the            design stage of
        avoided         wherever        affected                   the project to
        possible, or minimized,         population     to          avoid/ minimize
                    SC




        exploring             all       the project and            resettlement.
        alternatives.                   for consultation           this     includes
    2. Resettlement programs            on implications            minimum
        should be sustainable,          and grievance              planning
                 DI




        include      meaningful         procedures.                standards
        consultation        with 2.     The Land Act               adopted       for
        affected parties, and           2012 guarantees            KISIP
        provide benefits to the         the right to fair       2. Implement
        affected parties.               and          just          World Bank OP
    3. Displaced         persons        compensation in            4.12 policy –
        should be assisted in                                      affected persons
Page 21 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


           OP 4.12                      Kenyan                  Gap filling
                                       Legislation              Measures

        improving livelihoods         case             of      should          be
        etc.,    or     at  least     relocation.              assisted        in
        restoring      them    to 3. The Land Act              improving their
        previous levels.              does           not       livelihood to pre-
                                      stipulate     that       project status.
                                      resettlement
                                      should           be
                                      avoided
                                      wherever
                                      possible; on the
                                      contrary, as long
                                      as a project is for
                                      public interest,
                                      involuntary




                                                               PY
                                      resettlement is
                                      considered to be
                                      inevitable.
                                  4. Just and fair
                                      compensation as




                                                            CO
                                      outlined in the
                                      Land Act 2012 is
                                      not clear and can
                                      only             be
                                      determined by
                             RE
                                      NLC, which can
                                      be subjective. It
                                      is does not talk
                                      about improving
                          SU

                                      livelihood       or
                                      restoring them
                                      to     pre-project
                                      status.
 PROCESS REQUIREMENTS
                       LO



 Consultation: Displaced          The Land Act              Implement
 persons should be                outlines procedures       consultation
 meaningfully consulted and       for consultation          procedures as
 should have opportunities        with affected             outlined in both
                    SC




 to participate in planning       population by the         Kenyan legislation
 and implementing                 NLC and grievance         and World Bank.
 resettlement programs, the       management                For involvement of
 policy is particular on          procedures.               vulnerable and
                 DI




 involving vulnerable and                                   women, the OP 4.12
 marginalized as well as                                    will be applicable.
 women in the process.




Page 22 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


           OP 4.12                     Kenyan                  Gap filling
                                      Legislation              Measures

 Grievance: For physical           Land Act 2012           Adopt both by
 resettlement, appropriate         clearly outline the     providing for
 and accessible grievance          steps and process       alternative
 mechanism will be                 for grievance           grievance
 established.                      redress that            mechanism that are
                                   includes alternative    project based.
                                   dispute resolution,     Affected persons
                                   re-negotiation with     also free to seek
                                   NLC and is backed       legal redress if not
                                   by the judicial         satisfied.
                                   system through
                                   Environmental and
                                   Land Court
                                   Kenyan legislation




                                                               PY
                                   meets OP4.12
                                   requirements.
 Eligibility Criteria              The Land Act 2012       Ensure ALL users
 Defined as:                       provides that           (including squatters,
 (a) those who have formal         written and             laborers, rights of




                                                            CO
 legal rights to land              unwritten official or   access) of affected
 (including customary and          customary land          lands are included
 traditional rights recognized     rights are              in the census survey
 under the laws of the             recognized as valid     or are paid.
 country);                         land right. The Law
                             RE
 (b) those who do not have         provides that           Implement cut-off
 formal legal rights to land at    people eligible for     procedures as
 the time the census begins        compensation are        outlined in the RPF
 but have a claim to such land     those holding land      and Kenyan Law.
                          SU

 or assets—provided that           tenure rights.
 such claims are recognized        Land Act also
 under the laws of the country     recognizes those
 or become recognized              who have interest
 through a process identified      or some claim in
                       LO



 in the resettlement plan.         the land such
 (c) Those who have no             pastoralist or who
 recognizable legal right or       use the land for
 claim to the land they are        their livelihood.
                    SC




 occupying.                        The constitution
 To determine eligibility:         recognizes
 Carry out resettlement            ‘occupants of land
 census. Cut-off date for          even if they do not
                 DI




 eligibility is the day when the   have titles’ and
 census begins.                    payment made in
                                   good faith to those
                                   occupants of land.
                                   However, this does
                                   not include those


Page 23 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


           OP 4.12                     Kenyan                 Gap filling
                                      Legislation             Measures

                                  who illegally
                                  acquired land.
                                  Land Act 2012
                                  provides for census
                                  through NLC
                                  inspection and
                                  valuation process
                                  but is not clear on
                                  cut-off date.
 Measures: Preference             Land Act 2012           Ensure that all
 should be given to land-         appears to prefer       alternative options are
 based resettlement               cash for cash as the    considered before
 strategies for displaced         mode of                 providing cash
 persons whose livelihoods        compensation by         compensation.




                                                              PY
 are land-based.                  the Government to
 Cash based compensation          the affected            OP 4.12 Prevails.
 should only be made where        population.
 (a) land taken for the
 project is a small fraction of   Land Act talks of




                                                           CO
 the affected asset and the       prompt, just            OP 4.12 Prevails.
 residual is economically         compensation            Implement prompt
 viable; (b) active markets       before the              and effective
 for lost assets exist and        acquisition of land.    compensation at full
 there is sufficient supply of    However,                replacement cost for
                             RE
 land and housing; or (c)         interpretation of       the losses of the
 livelihoods are not land-        just compensation       assets. Ensure that
 based.                           is yet to be clearly    ALL resettlement
                                  outlined through a      options are agreed
                                                          on with PAPs and
                          SU

 World Bank OP4.12 Article        specific schedule.
 6(a) requires that displaced     Attorney’s fees, cost   put in place
 persons are provided with        of obtaining advice     BEFORE
 prompt and effective             or cost incurred in     displacement of
 compensation at full             preparing and           affected persons.
                       LO



 replacement cost for losses      making written
 of assets attributable           claim not in the
 directly to the project.         Land Act.
  If physical relocation is an
                    SC




 impact, displaced persons        The Act does not
 must be provided with            out rightly stipulate
 assistance during                assistance for
 relocation and residential       relocation but
                 DI




 housing, housing sites           rather that is left
 and/or agricultural sites to     subject to
 at least equivalent              interpretation.
 standards as the previous
 site. Replacement cost does
 not take depreciation into
 account. In terms of
Page 24 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


           OP 4.12                     Kenyan                 Gap filling
                                      Legislation             Measures

 valuing assets, if the
 residual of the asset being
 taken is not economically
 viable, compensation and
 assistance must be
 provided as if the entire
 asset had been taken.
 Valuation: With regard to        Valuation is            Apply the World
 houses        and        other   covered by the          Bank
 structures, it is the market     Land Act 2012 and       OP4.12valuation
 cost of the materials to build   stipulates, as          and compensation
 a replacement structure          already mentioned,      measures.
 with an area and quality         that the affected
 similar to or better than        person receive just




                                                              PY
 those of the affected            compensation, but
 structure, or to repair an       it is not specific of
 affected structure, the cost     the exact amount or
 of transporting building         procedures on the
 materials         to       the   same.




                                                           CO
 construction site, cost of any
 labour and contractors’ fees,
 cost of any registration and
 transfer taxes.
                             RE
                          SU
                       LO
                    SC
                 DI




Page 25 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


CHAPTER 4:                  APPROACH AND METHODOLOGY


4.1 Introduction

The Abbreviated Resettlement Action Plan for tenure regularisation of Kambi Moto
informal settlement was developed within a method consistent with the WB OP 4.12
and the Government of Kenya legal framework. The affected assets were valued by a
qualified and registered land valuer as guided by this Abbreviated Resettlement Action
Plan. The PAP census and consultations were led by an experienced sociologist. The
ARAP process included review of relevant documents, field visits, public consultations,
and PAP household surveys. Specifically, the various activities undertaken to prepare
the ARAP were as follows:

4.2 Review of relevant documents




                                                                  PY
This involved reviewing of relevant documents including:
  i.   KISIP Resettlement Policy Framework (RPF) which provides a framework
       consistent with the World Bank’s OP 4.12 for mitigating physical and livelihood




                                                               CO
       displacement impacts.
 ii.   World Bank policies on Involuntary Resettlement
iii.   Nairobi City County Integrated Urban Development Plan.
 iv.   KISIP Environmental and Social Management Framework (EMSF) which
       provides a framework for identification and mitigation of potential
                             RE
       environmental and social impacts arising from any KISIP project intervention.
 v.    Socio Economic Report for Kambi Moto Informal settlement 2019 (prepared as
       part of this consultancy) to provide baseline information for design and
       monitoring project interventions.
                          SU


 vi.   Survey Plans, Registry Index Maps (RIMs) and Local Physical & Land Use
       Development Plans (LP&LUDPs). The maps provided for the main settlement
       access from the existing (12m Ndingi Mwanzeki Road) and internal circulation
                       LO



       footpaths of minimum width of 1.5m.

Literature review was aimed at understanding the socio-economics of the project area;
harmonizing differences in resettlement and compensation guidelines between the
Kenya constitution and the World Bank Operational Policies, notably O.P 4.12 and
                    SC




establishing land tenure systems in the project area.

4.3 Socio-economic interviews and Census Survey of PAPs
                 DI




Field visits were undertaken to identify the properties affected by the project. The
analysis of the settlement’s high-resolution imagery combined with ground Physical
measuring was used to establish the extent of the property affected. In addition,
observation of social and physical setting of the area as well as economic activities was
undertaken.


Page 26 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


Interviews were held with each of the 11 affected PAPs using pre-designed semi-
structured questionnaires. A 100% census of all PAPs was undertaken. Using a GPS,
affected properties were identified and measurements and photographs taken. During
the household interviews, the following aspects were covered:
             •    Contact details and demographic data of the affected household,
             •    Vulnerability of PAPs
             •    Culture and social networks
             •    Livelihoods and income sources,
             •    Access to facilities and services’
             •    Land tenure/ownership and structures in the homestead,
             •    Perceptions of the titling programme and clearance from ROW for
                  infrastructure provision and,
             •    Anticipated impacts of the project




                                                                  PY
Analysis of the data collected for the socio-economic survey, was done using MS-
EXCEL and presenting the analysis results in charts and graphs into the ARAP report
for Kambi Moto informal settlement.




                                                               CO
4.4 Stakeholder consultation

Public participation is a key principle in the Kenyan Constitution (2010)-article 10.
This was achieved through various community meetings that were held from the time
of project initiation to the culmination of the ARAP report preparation.
                             RE
4.5 Identification and Valuation of affected assets

Valuation, which is the art or science of establishing the worth of a particular interest
                          SU


in property for a specific purpose and at a particular moment in time, considered all
the features of the property, demographics, topography as well as the underlying
market drivers. The valuation exercise was undertaken as per the Valuers Act Cap 532,
which provides for a Valuers Registration Board that regulates the activities and
                       LO



conduct of registered valuers. The Act governs the formation and guidelines of
valuation practice including the annual licensing and gazettement of valuers. The
Board also deals with ethics of the profession as well as registering complaints,
disciplining and deregistering of unethical members.
                    SC




The dates of inspection or survey were on 21st August 2019, which was the last day of
the exercise. During the PAP census survey, the type of structures affected ranging
from semi-permanent to temporary structures were documented. The amount of
compensation for individual PAPs was arrived at after computation of what he/she
                 DI




owned based on the asset inventory. A detailed breakdown of the affected assets is
appended to this report.

The valuation method adopted was full replacement cost method or contractor’s
method for asset valuation. This method of valuation is based on an estimate of the
current market value of the asset and other considerations. Valuation was based on

Page 27 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


detailed field data, description on type of property, condition, plinth/built-up area and
replacement cost value. Through these methods, the assets valued were basically
temporary structures within the project area boundaries.
A detailed valuation report has been presented as an annex to this report.


4.6 Valuation Parameters

Different parameters were used in this valuation depending on the specific item under
valuation, their nature, their use, and intervening circumstances that may have effect
on the value. In this case, the items were categorized as: Plants, temporary structures,
and semi-permanent structures.

4.7 Cut-off date

In the KISIP Resettlement Policy Framework, the cut-off date is described as the date




                                                                  PY
of start of the socio-economic survey/census and asset inventory of PAPs. Following
declaration of the cut-off date on 26th July 2019 during community plan
validation/adoption meeting. It was made clear that new persons entering and/or
occupying land in the project area after the cut-off date will not be included in the




                                                               CO
inventory of PAPs and not eligible for any facilitation or displacement assistance. In
addition, assets including structures established or modified after the cut-off date
could not be considered for compensation.

The affected properties were identified and valuation carried out to assess
commensurable values. In this process, only PAPs registered during the baseline
                             RE
survey were considered eligible for facilitation. The PAP’s census survey, a consultative
sensitization meeting with all PAPs and valuation of properties was undertaken and
completed on 21stAugust, 2019. The meeting was attended by 25 stakeholders
(including the Nairobi City County government representatives and local community
                          SU


project affected persons, the PAPs were again sensitised on the cut-off date
implications if anyone would have gone against the cut-off date directions.
Participation during the PAPs consultative meetings is presented in the following table
4-1:
                       LO



 Table 4-1:     Stakeholder participation during the PAPs meeting
Purpose       of Date         Category                of Number of Participants by   Subjects   of
Meeting                       Stakeholders               Gender                      Discussion
                                                         Male    Female Total
Consultative      21.8.2019   Community PAPs             11       14        25       Community
                    SC




RAP meeting                   Consultant, Nairobi City                               appraisal on the
Undertaking a                 County Representatives and                             RAP process
mobilization                  SEC official                                           Sensitization on
                                                                                     social safeguards
and                                                                                  (Gender,
sensitization
                 DI




                                                                                     vulnerable groups,
for PAPs                                                                             GRC/M etc.) and
                                                                                     entitlement
                                                                                     Recap of cut-off
                                                                                     date




Page 28 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


CHAPTER 5:                  PUBLIC CONSULTATION AND
    PARTICIPATION


5.1 Introduction

Community participation in the ARAP process was critical to ensure that the needs,
priorities and aspirations of the PAPs provided guidance for effective participatory
planning. Through this process, the community ultimately owned the project.
The main objectives of Consultation and Participation were to:
         i.   Create awareness among the affected persons on the impact
        ii.   Have an all-inclusive process involving all the stakeholders –
              community, county government, and other stakeholders with interests
              on the settlement;
       iii.   Provide an opportunity for PAPs in the proposed project area to raise




                                                                 PY
              issues and concerns pertaining to the project;
        iv.   Facilitate collection and collation of PAPs and other stakeholders’ views
              as well as incorporating them into the ARAP procedures and structures
              and;




                                                              CO
5.2 Categories of stakeholders

The main stakeholders involved included; Primary stakeholders: Structure owners,
SEC, Institutions within the settlement; Secondary stakeholders: persons living in the
settlement/local community leadership and elected leaders; Key stakeholders: KISIP
                             RE
national team, relevant national line ministries and county department.
5.3 PAPs consultations
                          SU

The participatory forums provided an opportunity to the PAPS to be sensitized and
informed on many issues among them; planning and survey process, Kenyan legal and
policies including World Bank OP 4.12 on Involuntary Resettlement provision on
resettlement and informing PAPs on the planned census schedule in the settlement.
                       LO



5.4 Stakeholder meetings and issues raised

A total of four planning meetings were held where a number of RAP issues were
discussed. These issues included among others; possible project impacts and available
                    SC




grievance redress mechanisms available to PAPS as detailed in table 5.2. Also, one
PAP consultative meeting was held with the Kambi Moto PAPs on 21st August 2019.
During this meeting, the following areas were covered;
    • Appraisal of the community members about the entire RAP process
                 DI




    • Briefing of the PAPs of the enumeration exercise that was set to be undertaken
       immediately after the meeting
    • The PAPs were informed that the guidelines that the RAP process is based on
       included i) The Kenyan Constitution (2010) chapter five on land and
       environment, which has three classifications on land ownership rights; public,
       private and communal. For the case of Kambi Moto, the residents had settled
       on public land on which the project was meant to undertake adjudication to give
Page 29 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


      them private rights. ii) Kenyan land laws legal framework and iii) World Bank
      Safeguard Policies (Operation Policy 4.12). He added that the policies governing
      land in Kenya would continue to exist even after issuance of the title deeds.


The schedule of the consultative stakeholder meetings including number of
participants is presented in table 5-1 below.

Table 5-1: Stakeholder involvement
 PURPOSE          DATE      PARTICIPA       NUMBER OF                  IN
 OF                         NTS             PARTICIPANTS               DISCUSSI
 MEETING                                    MAL FEMAL TOTA             ON
                                            E    E     L
 Introductio 27/3/2019 Community            42   37     79             • Sensitizati
 n to the              Members                                           on on the
 community             KISIP                1       1         2          project
 meeting &             National                                        • Introductio
 project               Nairobi              1       2         3




                                                                PY
                                                                         n of
 launch                County                                            consultant
                       Government                                        to the
                       Consultant           3       3         6          community
                       working under




                                                             CO
                       KISIP
                       Local                4       0         4
                       administration
                       Total                51      43        94
 Presentatio 30/05/201 SEC &                50      29        79       • Presentatio
                             RE
 n of Socio- 9         Community                                         n          &
 economic              members                                           confirmati
 findings              Nairobi County       2       1         3          on        of
 -Validation           Government                                        socioecono
 of base
                          SU

                       Consultant           3       2         5          mic
 maps                  working under                                     findings
 -                     KISIP                                           • Validation
 Community                                  2       1         3          and
 Visioning             KISIP                                             endorseme
                       LO



 &participat           Local                2       1         3          nt of the
 ory                   Administratio                                     Basemap
 planning              n                                                 by       the
                       Total                59      34        93         community
                    SC




                                                                       • Communit
                                                                         y visioning
                                                                         for      the
                                                                         settlement
                 DI




                                                                       • Communit
                                                                         y
                                                                         participato
                                                                         ry planning
                                                                       • Sensitizati
                                                                         on on the

Page 30 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


                                                                         tenure
                                                                         options
                                                                         (communit
                                                                         y&
                                                                         sectional
                                                                         titles
 Technical        19/7/201 KISIP         9         9         18        • Discussion
 Meeting          9        Nairobi                                       on the
                           County                                        proposed
                           Government                                    Adoptive
                           Local                                         planning
                           Administratio                                 model
                           n
                                                                       • Discussion
                           Consultant
                                                                         on possible
                           working under
                                                                         tenure
                           KISIP
                                                                         options




                                                              PY
 Presentatio 26/07/201 SEC &                56     43        99        • Presentation
 n of draft   9        Community                                        and
 Final                 members                                          discussion of
 LP&LUDP               Nairobi              2      5         7          the




                                                           CO
 to the                County                                           conventional
 Community             Government                                       and adoptive
 for                   KISIP                1      1         2          planning
 adoption              Consultant           2      2         4          models,
                       working under                                    based on the
 Final
                             RE
                       KISIP                                            community
 verification          Local                1      0         1          proposals
 of LoB                Administratio
                                                                        arrived at
                       n
                                                                        during the
                          SU


                                                                        community
                                                                        participatory
                                                                        planning.
                                                                       • Sensitizatio
                       LO



                                                                        n on the
                                                                        tenure
                                                                        options
                                                                        (community
                    SC




                                                                        & sectional
                                                                        titles
                                                                       • Setting of
                                                                        cut-off date
                 DI




                            Total           62     51        113

                 21/8/2019 Community        3      11        14        Community
                           members (11                                 appraisal on

Page 31 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


 Consultativ                PAPs and 3                                 the RAP
 e meeting                  SEC reps.)                                 process
 with PAPs                  KISIP            0      0          0       Sensitization
                            Nairobi          2      0          2       on social
                            County                                     safeguards
                            Government                                 (Gender,
                            Local            0      0          0       vulnerable
                            Administratio                              groups,
                            n                                          GRC/M etc.)
                            Consultant       6      3          9       and
                            working under                              entitlement
                            KISIP                                      Recap of cut-
                            Total            11     14         25      off date


The consultative RAP meeting held at Kambi Moto Social Hall on 21st August 2019 was
targeted for consultation with PAPs only. During this meeting various issues on the




                                                                PY
ARAP process being undertaken were raised by the PAPs and responded to as
documented under Annexed minutes of the final Abbreviated Resettlement Action
Plan. In summary ARAP issues raised by PAPs and responses provided are presented
in table 5-2 below;




                                                             CO
Table 5-2: Main Issues raised by PAPs and responses given
 Issue                               Response
 What is the fate of the social      All stakeholders including the Nairobi City
 hall which is above the sewer       County were involved in responding to this
 line                                question
                             RE
                                     The members were informed that the social hall
                                     was not impacted by the KISIP plan proposals,
                                     therefore did not qualify as an affected structure
                          SU


                                     under the project.

 What are guidelines that are        They were informed that KISIP project was not
 to be followed if the local         involved in structures building including that of
                       LO



 church members wanted to            the church. However, they were advised that they
 continue building their             should follow the county government regulations.
 church hall which already
 had ongoing construction
 works?
                    SC




 Can a structure owner’s             No representatives or tenants would be
 representative be                   interviewed except with consent from the owner
 interviewed on his behalf?
 what would happen to the            These errors would be addressed during
                 DI




 errors in the cards that were       surveying and beaconing phase
 issued
 The community member                Project team present assured the PAPs and
 asked the project team to           settlement committee present that they will
 implement the project               follow KISIP timelines.


Page 32 of 130
                     Abbreviated Resettlement Action Plan for Kambi Moto


    speedily as they have waited
    for long
    Sought to know from the                      The Consultant working under KISIP confirmed
    Consultant team, whether                     this will be considered during filling of beacon
    the survey team will be                      certificates in the upcoming week and
    coming to ground to                          sensitization will be done on a continuous basis.
    sensitize members who have
    issues with interpretation of
    beacons

COMMUNITY CONSULTATION ON SECTIONAL TITLES
 The community was sensitized on the two tenure options (community & sectional
titles) during the community participatory planning exercise held on 30th May and on
26th July 2019 (see annex 3 and 2 respectively). Although a majority of the community
members (54%) had opted for one community title during the socio-economic survey
exercise, they had a change of mind after sensitization of the two options6 (community
and sectional properties title) upon the realization that individual titling was a




                                                                            PY
possibility through sectional titles. Apart from ensuring security of tenure for
individual beneficiaries, Sectional Titles will achieve a greater sense of communal
lifestyle, maintaining the social networks and interactions within the community.
Section 2.2 of this ARAP report has a detailed coverage on the administration and




                                                                         CO
management of sectional titles. RE
                             SU
                          LO
                       SC
                    DI




6   This is documented in Section 2.3 and 2.8 of this Report.

Page 33 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


CHAPTER 6:                  PROJECT IMPACTS


6.1 Introduction

The prepared and approved LP&LUDP generated positive and negative impacts. These
impacts resulted from planning and surveying; specifically, the proposed clearance of
access paths within the settlement. The impacts led to PAPs losing structures.

Positive impacts include secure Land Tenure that enhance land ownership security
and hence an impetus for improvement of the settlement to a better place. With secure
land tenure, those living in the informal settlement can make long – term investment
commitment on the land. Issuance of title deeds guarantees permanency of property.
This will in turn improve the livelihoods of the beneficiaries in form of permanency
and access to finances by using the titles as collateral. There will also be improved ways
as encroaching structures will be cleared.




                                                                   PY
Negative impacts will result from the plan implementation that will require removal
of structures that had encroached into the settlement accesses/passages as provided
for by the plan proposals and persons being affected thereof would require facilitation
to effect the necessary adjustments as per the approved plan proposals.




                                                                CO
6.2 The Project Affected Persons
This KISIP project (on tenure regularisation) intervention in the Kambi Moto informal
settlement was done post- development, after some earlier remedial interventions of
upgrading (building of permanent structures with common and uniform designs)
                             RE
which were facilitated by an NGO-Pamoja Trust, Nairobi City Council and the
Community- even though the redevelopment models were not done to conventional
planning standards due to space limitations. To achieve the key project objective of
enhancing tenure security in the settlement, it required preparation and approval of
                          SU

the physical and land use development plan. Therefore, through the re-planning of
settlement, there were incidences where some structures happened to be affected by
the plan proposals of reopening blocked access paths and proposing some
complementary support land uses-open/green spaces. Through the plan, it was
recommended that all the blocked accesses needed to be cleared to create better
                       LO



connectivity and accessibility within the settlement. This resulted to creation of the 11
PAP/Is composed of 4 females, 5 males, 1 Institution-church and 1 community self-
help group) as documented herein this report. This information is presented in the
PAP diagram below:
                    SC




Figure 6-1: Kambi Moto PAPs Diagram
                                                PAPs- 11
                 DI




                        PAPs-9                                            PA/I/G-2
       Male                                     Female -
        5                                          4
                     Vulnerable- 2



Page 34 of 130
                     Abbreviated Resettlement Action Plan for Kambi Moto

    Vulnerable - 1                                       Vulnerable-1



6.3 Impact on structures

The Kambi Moto ARAP is triggered by the planning and surveying of the settlement,
which affected 11 structures which have been impacted by approved LP&LDP
proposals e.g. Opening up of blocked access paths. All the structures are fully affected.
The breakdown of the affected structures is indicated in the table below.

Table 6-1:       Summary of the impacted structures

 Description of affected property                                                         Number         and/or
                                                                                          Unit               of
                                                                                          Measurement
 Veranda extension                                                                        1 (full impact7)




                                                                                  PY
 20 feet Container laid on concrete blocks                                                1(full impact)
 Semi-permanent structures /Temporary stores                                              7(full impact)
 Empty Temporary poultry house                                                            1 (full impact)




                                                                               CO
 Semi-permanent structures extensions (church structure is 1(full impact)
 temporary one used as a store, religious activities will not be
 affected since they have an alternative main structure adjacent)
 Total                                                                                    11
                              RE
                           SU
                        LO
                     SC
                  DI




7Fullimpact is applying since the structures are just temporary and they will be removed to open up the blocked
accesses.

Page 35 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                              PY
                                                           CO
                             RE
                          SU
                       LO
                    SC
                 DI




Map 6-1: Impacted Structures


Page 36 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


6.4 Impacts on Community Facilities (PAI)

The church structure affected is a semi-permanent house made of iron-sheet walls and
roof which was temporarily put up to act as a store. However, they have an adjacent
permanent structure which is the main hall. Therefore, the removal of the temporary
structure will not interrupt any religious activities.
6.5 Impact on vulnerable Groups
The KISIP RPF recognises the need for an inventory of vulnerable persons so as to
ensure provision of additional support so as to cushion them from impacts associated
with the project and to facilitate faster adjustment after effects caused by planning and
survey.

There are two vulnerable PAPs of which one is both aged and widowed, and the other
is aged. The vulnerable PAPs will be given a financial assistance of KES. 2,000 per
month for two months. In addition, they will be given priority in disbursement of
compensation funds. KISIP will share details of the 2 Elderly PAPs to the County




                                                                  PY
Government Department of Social Services for enlisting to government social
programme such as the "Inua Jamii 70 years and above cash transfer programme for
aged PAPs.




                                                               CO
6.6 Tenure Security Impact: Sectional Titles
The sectional property titling option resulted from the Adoptive Local Physical and
Land Use development plan for Kambi Moto settlement to achieve the main objective
of enhancing tenure security for identified beneficiaries. The impacts generated from
                             RE
the titling option include; (i) Sectional ownerships and (ii) formation of a corporation
to manage the sections as stipulated by the Sectional Properties Act (1987). To ensure
this impact is adequately mitigated, KISIP will ensure provision of adequate
sensitization of the beneficiaries during implementation of the ARAP and facilitate the
                          SU


formation, registration and training of the corporation to be formed.
                       LO
                    SC
                 DI




Page 37 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


CHAPTER 7: SOCIO-ECONOMIC PROFILE OF THE
    PAPS


7.1 Household identification

There are 11 PAPS in Kambi Moto composed of (Individuals; 4 female and 5 males 1
institution-Catholic church and 1 self-help group (Muungano wa Kambi Moto). All
PAPS are from Kambi moto Settlement in Kiamaiko Sub- location.

7.2 Structural details
From the survey, 56% of the PAPS mentioned to have moved to Kambi Moto for
residential purposes while 44% mentioned to have moved for work purposes. The table
below indicates the years when the PAPS moved to Kambi Moto




                                                               PY
Figure 7-1: Years when PAPs moved to Kambi Moto

                      0%




                                                            CO
          2010-2019
             22%             1970- 1989
                                33%
                             RE
            1990-2009
               45%
                          SU
                       LO




From the survey, 78% of the structures affected are used as temporary structures, 11%
are used as a personal storage facility and the remaining 11% is a veranda extension.
All the affected structures were constructed between 1992 and 2017. All the affected
                    SC




structures are temporary where majority are constructed with iron sheets for walling
and roofing with a concrete floor except for two structures that have stone walls and
are tiled floor. With regards to sources of capital for construction, 78% of the PAPs
mentioned they sourced from their personal saving and 22% used loans from
economic organizations to construct their structures.
                 DI




7.3 Age of PAPS

The PAPS are aged between 36 to 68 years with an average age of 49 years. The female
PAPS are aged between 46-68 years with an average age of 52 years while the male
PAPS are aged between 36-63 years with an average age of 46 years.

Page 38 of 130
                  Abbreviated Resettlement Action Plan for Kambi Moto


7.4 Marital Status of PAPs

Of the PAPs interviewed 67 % (5 males and 1 female) were married, 11 % (1 female)
mentioned to be widowed while 22% (2 females) mentioned to be single.

7.5 Education level of PAPS

The PAPs recorded different levels of education attained; 67% of the mentioned to
have attained primary level of education, 22% mentioned to have attained secondary
level of education and 11% have attained college of education as illustrated below;

Figure 7-2: Education level of PAPS
 80%

 70%        67%




                                                                PY
 60%

 50%

 40%




                                                             CO
 30%
                             22%
 20%
                                               11%
 10%
                             RE
  0%
       Primary level of Seconadry level   College level of
          education      of education       education

Majority of the PAPS (55%) mentioned to have been trained on several courses such
                          SU


as driving, tailoring and geographical information system. 44% have not received any
training and one female PAP has received training on tailoring; the other three female
PAPs have not received any training.
                       LO



7.6 Health

Majority (78%) of the PAPS mentioned not to have suffered from any illness for the
last six months on the other hand22% mentioned to have suffered from several
                    SC




illnesses over the last six months that ranged from Malaria to respiratory illnesses.

7.7 Social issues
                 DI




In terms of social groups and integration; under religion, 89% of the PAPS are
Christians while 11% are Muslim.
The PAPs also indicated they joined various socio-economic groups such as Milimani
SACCO, Maelewano Welfare, Eclof Kenya, Jirani Mzee welfare, Nduru- Runo and
Kariobangi welfare. The main activities of the organizations where PAPs are members


Page 39 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


include table banking, savings and loan and help in social activities. Just 33% of the
PAPS mentioned that they did not belong to any socio-economic welfare/group.

PAPS indicated to receive social services such as health, education, water, energy,
sanitation, sports and market from within the area with an average distance of 3km.
The main energy source for the PAPS was mentioned to be cooking gas for cooking and
electricity for lighting purposes.

7.8 Economic Occupation

Project affected persons are involved in a number of economic activities including
Livestock rearing, business, casual jobs and renting of houses. Two PAPS mentioned
to be rearing poultry with average units of 14 and KES 2500 income per month. Seven
PAPS mentioned to be running businesses such as grocery, hair dressing, sand sale, oil
sale and water sale. The average income from the business per month is KES 14,571.
Two PAPs were engaged in casual jobs such as farming and construction with an
average monthly income of KES 8,500. The economic Activities do not take place in




                                                                PY
the Affected Structures.

67% of the PAPS are engaged in businesses, 22% are casual workers and 11% are
unemployed. Three of the four female PAPs are involved in businesses while one




                                                             CO
female PAP is unemployed. All male PAPS are either in businesses or in casual works.
Two PAPS mentioned to have rented houses out with an average monthly income of
KES 5,500. Four PAPS mentioned to have obtained loans from different institutions.
The average amount of loans is KES 105,000.
                             RE
Majority (67%) of the PAPS work within the settlement, while 33% work outside the
settlement.
All female PAPS work from within the settlement except one. 56% of the PAPS use
Bus/ Matatu as a mode of transport, 33% go on foot while 11% use private means.
                          SU


7.9 PAPS Expenditure Patterns

PAP’s income is spent on various needs including education, food, hiring business
                       LO



premises/labour, transportation, house rent and maintenance. The figure below
summarises the distribution of PAP’s income expenditures in various items:
                    SC
                 DI




Page 40 of 130
                    Abbreviated Resettlement Action Plan for Kambi Moto

Figure 7-3: PAPS Expenditure
               Medication        Water           Sanitation
                  3%              3%                1%

                               Energy…


                       House Rent and
                       Maintenance…                       Education
                                                            34%

                    Transportation
                         11%


                            Hiring busines
                              premises        Food
                                 16%          20%




7.10 Willingness to get the affected structure removed




                                                                                     PY
Majority of the PAPS 77.8% are willing to have the affected structures removed and
preferred to be given an opportunity to remove the structures by themselves after
facilitation. Those willing to have the structures removed mentioned to require




                                                                                  CO
support to remove the structure which they quoted compensation (cash or kind) of the
affection structure. On the other hand, 22.2% of the PAPS mentioned to be unwilling
to have the structures removed. They cited such reasons as loss of a place to reside and
loss of storage space8for declining removal of their structures.
                               RE
The average monthly income from the affected structures is KES 10,500 while the
average monthly profit from the affected business is KES 4,875. PAPS mentioned
impacts of the removal of the structures to be: loss of storage space, loss of residence
for a child and vulnerable child.
                            SU
                         LO
                      SC
                   DI




8This has been mitigated as PAPs will be Given enough facilitation to enable then relocate their Structures as well
as 3 months self-demolition, salvaging of materials and reconstruction of affected Assets

Page 41 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


CHAPTER 8:                   MITIGATION OF IMPACTS

8.1 Introduction

The Kenya Informal Settlements Improvement Project (KISIP) Resettlement Policy
Framework (RPF) defines Project Affected Persons (PAPs) as persons affected because
they may lose, be denied, or be restricted access to shelter and/or economic assets thus
losing income sources, or means of livelihoods. These persons are affected whether or
not they must move to another location.

The World Bank’s Operational Policy O.P. 4.12 on ‘Involuntary Resettlement’ states
that the Project affected persons should be compensated at full relocation cost prior to
the actual move. Further, the PAPs should be supported during the transition period,
and/or their incomes restored to pre-impact or better status (in case of a commercial
structure affected) and also advocates for support to vulnerable groups.




                                                                    PY
One of the objectives of this ARAP is to ensure that the PAPs conditions are improved
or restored to the project pre-impact levels. The negative impacts that are to be
mitigated, result from impacts on structures by the plan proposals in the approved
LP&LUDP. Consequently, the PAPs will require facilitation to remove these structures.




                                                                 CO
8.2 Planning and Survey Impact Mitigation Measures

During the planning of Kambi Moto Informal Settlement, the application of adoptive
planning approach saw the settlement planning done based on the existing situation.
Given the built-up structures were already storeyed and permanent, there was no
intervention that would be done to widen internal accesses. This informed the
                             RE
adoption of the existing internal access ways as foot-paths with only recommendations
of opening up the sections that had been blocked.

Also given the smallness of the settlement (measuring 135m x 32m), it was considered
                          SU


to be a walkable settlement across direction thus the adoption of the pedestrianized
internal accesses.
On the other hand, rather than demolishing of the built structures in order to achieve
registrable parcel sizes for tenure regularization, the plan proposed for the alternative
                       LO



Sectional properties titling option to allow the beneficiaries be entitled to the total
areas of their constructed structures. This was adequately done through community
consultations. At the time of RAP implementation, KISIP will enhance sensitization of
beneficiaries during the community meeting on management of sectional titles (see
also annex 2, 3)
                    SC




8.3 Mitigation and Entitlements

Opening up of accesses as a result of planning and surveying resulted to partial or full
                 DI




impact on structures therefore generation of PAPs. All those persons who are affected
by these activities regardless of their legal tenure status are eligible for facilitation if
they had assets at the affected sites before the project cut-off date of 26th July, 2019.

Sectional titles is not a common property registration option, necessitating adequate
sensitization to the beneficiaries. Although the process of sensitization commenced

Page 42 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


during the planning phase, further sensitization especially on subsequent titles
registration and operational modalities (post registration) will be done by KISIP
during the ARAP implementation phase, in collaboration with the department of
Lands, Ministry of Lands and Physical Planning. Formulation of a constitution that
dictates the rules and regulations of the beneficiaries and subsequent submission of
the same to the chief land registrar will be well ensure the beneficiaries aligns and
adheres to the spirit of this form of tenure security.

The entitlement matrix outlined in table 8-2 below defines the type of facilitation and
assistance provided to the different categories of Project Affected Persons.

8.4 Entitlement Matrix
Table 8-2 below shows the entitlement matrix that was used to determine the
compensation for the PAPs.
Table 8-1: Entitlement Matrix
 NO TYPE OF          PAP            ENTITLEMENTS
       LOSS          CATEGORY




                                                                       PY
  A. Loss of structures
  1. Fully           Squatter       • Cash facilitation at replacement cost without depreciation
       affected/part




                                                                    CO
       affected and                 • Right to salvage materials.
       remaining
       structure is
       non-viable

  B. Support to vulnerable groups (Elderly, widowed, female heads etc.)
                             RE
                                    • Additional cash support of Kshs 2000/month for the first three
                                      months.
                                    • Assistance on a case by case basis in self-demolition, salvaging
                                      of Materials and rebuilding of fully affected structures.
                                    • Forwarding of names of Elderly PAPs through county
                          SU


                                      government for consideration for the unconditional cash
                                      transfer programme "Inua Jamii 70 years and above cash
                                      transfer programme’ administered by the national government’s
                                      Ministry of Labour and Social Protection.
                       LO



  C. Formation and Registration of a Corporation
                                    KISIP shall undertake to foot all the statutory costs for formation,
                                    registration and training on operationalization of the corporation
                    SC
                 DI




Page 43 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


CHAPTER 9:                  GRIEVANCE REDRESS
    MECHANISM

9.1 Introduction

Grievance redress mechanisms are essential tools for facilitating PAPs to voice their
concerns about the compensation processes as they arise and, where necessary, for
corrective action to be taken promptly. Such mechanisms are fundamental to
achieving transparency in compensation processes.

The key grievance subject matters likely to arise in case of the planning and execution
for the Kambi Moto settlement include:
    i. Mistakes on inventory of the affected assets that might have occurred during
       the census survey;




                                                                 PY
    ii. Dispute over ownership of given assets between two or more affected
        individual(s);
    iii. Disagreements on structure valuation where the PAP feels that his/her asset
         have been undervalued;




                                                              CO
    iv. Delays in facilitation payment;
    v. Extent and values for the resettlement and disturbance assistance
    vi. Grievances arising from the titling process.
                             RE
These grievances necessitate the setting up of appropriate grievance and appeals
redress mechanisms to address the grievances and disputes that may arise from time
to time.
                          SU


9.2 Grievance Redress Management Mechanism

This ARAP has established procedures and mechanisms through which complaints
and disagreements can be resolved without costs and in a timely manner. The
                       LO



grievance redress mechanism (GRM) is simple and transparent; accessible to all the
affected persons irrespective of their location and/or socio-economic status; flexible
and open to scrutiny and; speedy, just and fair. The grievance redress mechanism
adopted in this ARAP. The proposed GRM is at 3 levels namely the settlement, the RIC
and the court of law. Each of the levels is discussed below:
                    SC




9.3 Settlement Grievance Redress Committee (SGRC)
                 DI




This Settlement Grievance Redress Committee (SGRC) was established at the onset of
the planning and surveying process, constituting of three members of the Settlement
Executive Committee with representation of a woman member, the Area Chief and the
ward Administrator. Its organizational structure comprises of the chair, vice chair and
three members. The grievances are received by the chair of the SGRC and entered into
the grievance logbook. The SGRC for Kambi Moto settlement is already functional. The

Page 44 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


Settlement Grievance Redress Committees (SGRC) will continue to operate during
implementation of this ARAP including times of disclosure and issuance of titles.
During community consultation forums, PAPs were continuously sensitized on the
available grievance redress mechanisms provided by this ARAP.

9.4 RAP Implementation Committee (RIC)
In case the grievance is not resolved at first tier, they will be forwarded to the proposed
ARAP Implementation Committee (RIC). At this level, county officials from the
County Government (as a key component of the RIC) are occasionally involved in
intricate land ownership disputes. In case of Kambi Moto settlement, this ARAP
recommends the RIC members to be composed of:

From KISIP National PCT:
  a) Head of Component 1
  b) Head of Component 2
  c) Project Liaison Officer




                                                                    PY
  d) Social safeguard specialist
  e) Community Development specialist
  f) 3 members from Component 2 – Surveyor, Land Administrator and Valuer
  g) KISIP Finance Officer




                                                                 CO
From the County:
  a) County KISIP Coordinator who will be the chairman
  b) Community Development Officer
  c) County Surveyor
  d) County Physical Planner
                             RE
  e) County Land Officer
  f) Representative from NLC

9.5 Legal Redress
                          SU


In cases where PAPs are not satisfied with the decision of the Grievance Redress
committee of KISIP, the PAPs will be at liberty to seek legal redress at courts of law.
                       LO




9.6 Procedures for Receiving and Resolving Grievances
The proposed step-by-step procedures for receiving and resolving grievances are as
                    SC




follows:

9.6.1 Step 1: Receipt and Redress of complaint/grievance by SGRC
                 DI




All grievances whether verbal or written by a PAP or community member will be
lodged at any time directly through the chair of the SGRC. During receipt of the
grievances, the chair will interview the complainant and enter responses into a
grievance form (if the PAP cannot read/write). The chair will record the complaint in
a register while the complainant will fill the grievance receipt form for which s/he will
take a copy home.

Page 45 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto



The SGRC will then meet within two weeks (14 days), based on the frequency of
grievances received by the chair, hold site level meetings to address the registered
grievances. The SGRC may opt to call the complainant or pass judgement/make
decision. If the SGRC is not able to resolve the complaint, it escalates the grievance to
the RIC. Whichever the case, the decision arrived at by the SGRC will be
communicated to the complainant not more than two days following the decision. If
satisfied, the complainant signs the satisfaction form and the same is entered into the
register. But if dissatisfied, the complainant will appeal to the RIC. Where the
complainant is satisfied and accepts the decision, corrective action will be taken and
verified by the SGRC.

9.6.2 Step 2: Escalation of the complaint to RIC

Where the SGRC is not able to resolve a complaint, it will escalate the grievance to the
RIC. The RIC will hold meetings to address grievances escalated to this level, these
meetings will be held at settlement level on case by case basis when required.




                                                                   PY
Following redress decisions reached, the RIC will communicate the same to the
complainant through the SGRC. Decisions by the RIC will be taken within two weeks
(14 days) from the date the complaint is escalated.




                                                                CO
9.6.3 Step 3: Alternative Action/Judicial Recourse

Where an aggrieved party is not satisfied with the resolution by the RIC, the party will
be at liberty to appeal to the courts of law at any given time and at his/her cost. The
proposed schematic diagram of the grievance redress mechanism is presented in the
                             RE
following figure:
                          SU
                       LO
                    SC
                 DI




Page 46 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                   Level 1
            Registration of the grievance with GO and resolution by
                                 SGRC (14 days)


                                                                            Level 2
                                                                      Forward findings
                                                                              and
                                                                      recommendation
                          Complainan                                  s to Resettlement
     YES                                                NO
                           t satisfied                                 Implementation
                            with the                                         (RIC)
                           outcome                                      Committee




                                                                         PY
                                                                          Grievance
      Final closure                YES                                    processing




                                                                      CO
                                                    Complainant
                                                      satisfied               by
                                                        with
                                                                          Mediation
                                                     outcome
                                                                          committee
                                                                           (14days)
                             RE
                                                         NO
                          SU


                                                       Level 3
                                                  Complainant seeks
                       LO



                                                    legal redress


Figure 9-1: Grievance Redress Procedure
                    SC
                 DI




Page 47 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


CHAPTER 10:                 INSTITUTIONAL AND
    IMPLEMENTATION ARRANGEMENTS


10.1 Overview
The overall responsibility for the implementation of the ARAP is vested in KISIP - the
Project Coordinator and staff of the Project Coordinating team (PCT). The PCT
consists of Component heads, planners, social safeguards experts, Monitoring and
Evaluation, procurement officer etc.
The main objectives of resettlement and compensation are to ensure that the PAPs
get fair and prompt compensation. In this way it is expected that their income,
productivity and standards of living will be improved, or at least restored to their
previous levels or even better.




                                                                PY
The guiding principles for the implementation of the ARAP will be as follows:
     a. Resettlement or relocation has been minimised by taking into consideration
         all possible alternative measures.
     b. Compensation will be paid concurrently with issuance of titles in a manner
         that does not curtail the livelihoods of the PAPs in terms of access and




                                                             CO
         utilisation of such compensation.
     c. The compensation values awarded are fair.
     d. All other activities related to the ARAP will be communicated in advance to
         the PAPs using the preferred channels of communication.
     e. Where grievances arise, the respective PAPs/beneficiaries who lodged the
                             RE
         grievance will be given an opportunity to be heard, fairly and promptly.
     f. Measures will be taken to ensure that vulnerable PAPs get special assistance
         and support as documented in the entitlements of this ARAP.
10.2 Resettlement Implementation Institutions
                          SU


This ARAP will be implemented within a period of not more than 90 days upon
approval from the World Bank. At implementation phase, KISIP will ensure all PAPs
are adequately facilitated according to the provisions of this ARAP before Title Deeds
                       LO



are issued to all beneficiaries. The implementation tasks will be carried out by KISIP
Resettlement Implementation Committee (RIC) for Nairobi City County whose
composition is outlined in this ARAP. Table 10-1 below indicates the County and
National Government role in this ARAP implementation:
                    SC
                 DI




Page 48 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


Table 10-1: National and County Government ARAP Implementing
Institutions
 No.         Institution            Role                     Capacity
    1.       Ministry of Transport, It houses the KISIP •The Ministry has the
             Infrastructure,         project and provides      capacity              for
             Housing and Urban for policy direction.           implementation of this
             Development.             Preparation of Title     ARAP
                                      deeds      for     the •The Ministry has the
                                      settlement               capacity              for
                                                               infrastructure
                                                               improvement in the
                                                               planned settlements
                                                              •The Ministry has experts
                                                               in the necessary key
                                                               areas: land management,
                                                               land administration and
                                                               physical planning.




                                                                      PY
    2.       Ministry of Finance    •Financial management    Capacity  exists and funds
                                     on behalf of the        will be made available.
                                     Borrower (GoK).
                                    •Provision of




                                                                   CO
                                     counterpart funding –
                                     part of which is used
                                     to settle compensation
                                     claims by PAPs.
      3.         National            Land   •Custodian of all public   The commission has the
                             RE
                 Commission                  land on behalf of the     capacity on this mandate.
                                             County Governments.
                                            •Ensures Issuance of
                                             Title Deeds to
                          SU


                                             beneficiaries.

      4.         County Government          •Ensures that all PAP’s    •The county has capacity
                                             are authentic              in the enforcement
                                            •Ensures that there is      department.
                       LO




                                             no re encroachment or     •The county has a
                                             any new development        functional social
                                             after cut-off date and     development office that
                                             before compensation        has been collaborating
                    SC




                                             process is completed.      with KISIP national
                                                                        office.
                                                                       •There is a functional
                                                                        KISIP County office
                 DI




                                                                        existing.

 5.              Ministry of Lands          •Processing of title       •Exist capacity to handle
                                             deeds                      the tasks



Page 49 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


In addition to the above government institutions, several structures have been
established to ensure effective implementation of this ARAP

10.3 ARAP implementation at KISIP
10.3.1 KISIP Project Coordination Team
The overall coordination of the whole process is provided by the KISIP Project
Coordinating Team (PCT). The National KISIP Coordinating Unit has the following
roles:
   a. Coordinate the effective implementation of the RAP as provided for by the
       RPF.
   b. Prepare Progress Reports on the implementation of the Social Safeguards.
   c. Procure and supervise consultants for Social safeguards.
   d. Build the capacity at all levels to implement the RAP.
   e. Supervise RAP implementation during and after project implementation.
   f. Ensure integration of RAPs into Contract and Bid Documents.




                                                               PY
   g. Ensure adequate community participation.

The Project Coordinator is the overall technical coordinator in the Project
Coordinating Team (PCT) and implementation of KISIP. She/he will supervise the




                                                            CO
project team and ensure that project implementation activities and reports are done
on schedule and in compliance with the financing agreement. The coordinator will
report to the Principal Secretary in the Ministry of Infrastructure, Transport
Housing and Urban Development and will from time to time draw the attention of
the PS to all emerging policies issues for decision at that level or a higher level.
                             RE
The PCT is responsible for routine implementation and technical aspects of the
KISIP project and comprises of a Safeguards Team which has Social Safeguard
                          SU


Specialists responsible for ensuring that the Social Safeguards are implemented.

10.3.2 KISIP ARAP Implementing Committee
A Resettlement Implementations Committee, appointed by the Project Coordinator
                       LO



is has been incorporated in the GRM and has the overall responsibility of Monitoring
and Evaluation of the resettlement process. The following are the recommended
members:
                    SC




From KISIP National PCT:
  a. Head of Component 1.
  b. Social Safeguard Specialist.
  c. Community Development Specialist.
                 DI




  d. 3 members from Component 2 – Surveyor, Land Administrator and Valuer.
  e. KISIP Finance Officer.

From the County
  a. County KISIP Coordinator who will be the chairman.
  b. Assistant County Commissioner.

Page 50 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


   c. Community Development Officer.
   d. County Surveyor.
   e. A representative from enforcement department.
   f. Town Administrator.
The committee works with the Project Affected Persons for each settlement. The
committees’ roles are as presented below.
a. The Resettlement Implementation Committee shall ensure the list of all PAPs has
   been verified and documented in the PAP register. The register shall have, among
   other parameters, (1) the name of the person, (2) type of loss (structure /
   Livelihood) (3) identification number of the PAP, (3) Compensation Amount (3)
   Bank Details or M-Pesa details of the PAP.
b. The Resettlement Implementation Committee will verify the identity of each PAP
   as stated in the register and ascertain that every identity card holder is correctly
   documented in the register.
c. Resettlement Implementation Committee will support KISIP in carrying out




                                                                 PY
   sensitization about opening of joint accounts and appropriate use of compensation
   funds for households. RIC will support PAPs in opening individual and joint
   accounts with financial institutions of their choice. RIC will support KISIP in
   following up on PAPs to ensure they have received their compensation.




                                                              CO
d. On completion of the PAP Audit and resolution of any grievance, the committee
   shall recommend compensation. Payments will be made according to locations and
   adequate information will be made available to all affected persons prior to
   payment. Such information will include: dates and locations of payment, list of
   eligible people and mode of payment, etc.
                             RE
10.3.3 County KISIP teams
For effective implementation of the project, Counties have established County KISIP
Teams whose composition is a replica of the national team. The county team was
                          SU

crucial in development of this ARAP and they will also be important during
implementation of the ARAP prior to commencement of civil works.

The role of the County KISIP Team includes:
  a. Validation of assets and PAPs before compensation.
                       LO




  b. Formation of the Grievance Redress Committee.
  c. Capacity building of ARAPs committee.
  d. Sensitization of PAPs on bank accounts and use of compensation funds.
                    SC




  e. Monitoring of ARAP activities.
  f. Oversight and supervision of rebuilding of structures owned by vulnerable
     PAPs who need assistance.
  g. Nairobi City County Government
                 DI




The county’s role includes:
  i. Facilitate implementation of ARAP and ensuring project success.
 ii. Delivery of other assistance to PAPs will be the responsibility of County
     Government under the coordination of respective RIC.


Page 51 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


iii.   Responsibility for appropriate and suitable measures to prevent further
       encroachments after the cut-off date and before facilitation is made.
 iv.   Oversight and quality control of rebuilding of structures for vulnerable PAPs
       identified for this additional assistance.
 v.    Clearance of structures after expiry of self-demolition period and
       compensation.
 vi.   Part of Grievance Redresses Mechanism through County KISIP office.
vii.   Maintaining roads and safeguarding them from encroachment after ARAP
       Implementation.


10.3.4 Settlement Executive Committee (SEC)

This was instrumental in mobilizing the community and providing a link between
KISIP, the Consultants, and the community. The Committee has been involved in all
stages of ARAP development and is expected to continue playing an active role in
monitoring its implementation.




                                                               PY
The Settlement Executive Committee role in the ARAP process as follows:
   h. It provides an entry point into the informal settlement.
   i. It is the crucial link between the community and other institutions.
   j. Plays an important role in the formulation of the community resettlement




                                                            CO
       committee and other engagement structures.
   k. Will play a crucial role in additional assistance to vulnerable PAPs during
       Implementation e.g. rebuilding of structures, and movement.

10.3.5 The Settlement Grievance Redress Committee
                             RE
This will be formed to address all grievances related to the development and
implementation of this ARAP at settlement level.

10.4 ARAP Implementation Process Flow
                          SU


The ARAP provides for coordination of relevant institutions discussed above during
ARAP implementation, figure 10-1 below presents a flow chart which illustrates roles
of institutions involved in ARAP implementation while figure 10-2 presents
                       LO



information sharing and Stakeholder Engagement Strategy.
                    SC
                 DI




Page 52 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto

Figure 10-1: ARAP Implementing Institutions


      KISIP Project Coordination
                  Team
           Overall coordination
      Overall responsibility of ARAP
             implementation
    Ensure budget for implementation is
                 available




           Resettlement
    Implementation Committee
    Monitoring and Coordination of




                                                                PY
        resettlement process
         Grievance redress




       Nairobi City County
       KISIP Team
          Validation of Assets                               CO
                                                Nairobi City County
                                              Ensure sustainability of the
                                                       project
                             RE
         Handling grievances                     ARAP implementation
                          SU


   The SEC and Settlement
   Grievance Redress Committee
   First tier of grievance redress
                       LO
                    SC
                 DI




Page 53 of 130
                                            Abbreviated Resettlement Action Plan for Kambi Moto

Figure 10-2:     Stakeholder Engagement Strategy



        What                                 Why                                          Areas                                            Whom                                How

                                - Avert Disputes/conflicts and GBV    - Benefits of Title Deed                       - Chief Registrar of Titles   - All            Community
                                - Enhance/safeguard Women’s           - Types of Registrations                       - KISIP                        beneficiaries   meetings
   Titles Sensitization          Land Rights                          - Joint Registration of Titles                 - NLC                         - Spouses with
                                                                      - Regulation of land transactions              - Land Control Board           Joint
                                                                       (mandatory spousal consent)                                                  Ownership
                                                                      - Relevant land related institutions
                            W
                                - Allow PAPs to self-demolish,        - Entitlements                                 - RIC                         PAPS             Community
                            O
                                 salvage and rebuild affected         - PAP register                                 - Nairobi City County                          meetings
                            M    structures in time                   - Notice for self-demolish and implications     (NCC)
     Notification &         E   - Ensure PAPs use compensation         of failure to do so within time               - Area Chief
      Disclosure            N    for right purpose
                                - Ensure grievances are directed      - Unilateral Grievance Redress Mechanism        RIC                          PAPS             Community




                                                                                                 PY
                            C    towards the right institutions for    for ARAP implementation                                                                      meetings
                            O    timely resolution                    - Procedures and processes in GRM

    Sensitization on        N
                                - Avert conflicts and GBV over        - Full disclosure of facilitation payment to   - RIC                         PAPS             - Community
                            C
         GRM                     compensation                          both spouses                                  - CGM                                           meetings
                            E   - Ensure PAPs use funds for right     - Opening of Joint Accounts                    - Area Chief                                   - Individuals/S
                            R




                                                                                              CO
                                 purpose                              - Utilization of funds, GBV                    - SGRC                                          pouses
                            N                                                                                                                                        meetings
                            S
   Compensation &
    Joint Accounts
     Sensitization




                                           E                                                   Guiding Principles
                                         UR
                                                       Proactive Engagement Clear and Open Information Sharing Learning & Modifying performance



                                                                                       Overall Coordination by KISIP PCT
                                       OS
                                    CL



Page 54 of 130
                       Abbreviated Resettlement Action Plan for Kambi Moto



 10.5 Other Supporting Institutions

 In addition, several agencies and institutions are to be involved in the ARAP
 implementation process as well as monitoring and evaluation.
 These institutions include:
       i.    Ministry of Lands and Physical Planning – For registration of the corporation,
             preparation and issuance of titles
   ii.       The National Land community mission – As a custodian of public land, key in the
             process of issuance of titles.


 10.6 Gender Empowerment during ARAP implementation

 In implementing this ARAP, gender empowerment and sensitisation will be adequately




                                                                       PY
 conducted by stakeholders including: KISIP, Chief Land Registrar and Nairobi County;
 Gender Department; local women and men based organizations; SEC; and local
 community will participate. These Sensitization exercises will include but not limited to:




                                                                    CO
  i.        Women’s landownership rights enhancement through recommendations such as
            joint spousal registration and titling.
 ii.        Enhancing women’s decision-making on land use and Land Laws. For example,
            women will be sensitized to know that a spouse cannot sell land without their
            consent
iii.        Sensitization on land transfer processes e.g. in the event of a spouse’s death or
                                  RE
            transfer to children.
iv.         Educating community on the benefits of recognizing promoting women’s land
            rights.
                               SU

 10.7 Implementation procedures

 The key activities anticipated prior to, during and after implementation of the ARAP are
                            LO



 outlined under the implementation schedule namely Abbreviated Resettlement Action
 Plan Activity Schedule (ARAPAS). Implementation of the Abbreviated Resettlement
 Action plan will consist of the following main interlinked activities:
                         SC




                i.    ARAP approval and Disclosure will be undertaken on the ground by RIC,
                      KISIP, in conjunction with SEC. This will be done in Kiswahili for better
                      comprehension by the community. KISIP and The World Bank will also
                      disclose via their website and Info Shop respectively.
                      DI




                ii.   KISIP shall oversee and bear full costs on formation, registration and
                      training of the corporation on operationalization of the sectional


 Page 55 of 130
                  Abbreviated Resettlement Action Plan for Kambi Moto

                 properties titles as stipulated by the Sectional Properties Act (1987) during
                 implementation of the ARAP

          iii.   Validation of asset valuation/values will be undertaken by KISIP RIC.

          iv.    Capacity building for Grievance Redress Committee will be undertaken by
                 KISIP. The training will cover topics including grievance collection and
                 documentation, strategies for settling complaints and escalation of
                 grievances to RIC including types of grievances to escalate to RIC. Dispute
                 /grievances resolution will be a continuous process and undertaken by
                 KISIP, RIC, SGRC.

          v.     PAPs mobilization and sensitization will be undertaken by RIC. This will
                 include sensitization on how to use the compensation amounts and the
                 importance of joint spousal involvement.

          vi.    Bank account opening by each of the affected PAPs so as to facilitate




                                                                    PY
                 smooth payment process will then happen.

          vii. Offering of awards by RIC. The PAPs will then choose to accept or reject
               the award. Where the PAP rejects the award, s/he will explain the reasons




                                                                 CO
               and can launch a grievance. For those who sign the award, they will wait
               for payment.

          viii. Issuance of titles will be undertaken by Ministry of Lands, at the same
                time as offering of compensation.
                             RE
          ix.    Following payment of facilitation, the PAPs will be issued with notice for
                 self-demolition, so as to salvage the building materials, which will be 1
                 month. For PAPs who will not Self-demolish, the County Government is
                 mandated to undertake development control. Therefore, demolition of
                          SU

                 any structures that have not been demolished at the expiry of the notice
                 period by the Nairobi County Development Control Section.

          x.     Monitoring and evaluation will be undertaken on a continuous basis by
                       LO



                 KISIP/RIC

          xi.    Evaluation and final audit will be undertaken following completion of
                 implementing the ARAP by KISIP, MoTIH&UD & World Bank. This is
                    SC




                 discussed in detail in Chapter 10.
                 DI




Page 56 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto

10.8 ARAP Schedule

The Abbreviated Resettlement Action Plan Activity Schedule (ARAPAS) is spread over a
period of Six months. Table 10-2 below summarizes the Abbreviated Resettlement Action
Plan Activity Schedule (ARAPAS).

Table 10-2: RAP implementation schedule
                                             Actor                       Implementation to
                                                                         begin immediately
                                                                          after approval of
    TASK NAME                                                                   ARAP
                                                                         Period in Months

                                                                     1      2   3   4   5     6
 1. Approval of ARAP                         World Bank




                                                                PY
 2. Formation of a corporation               KISIP
    Sensitization on Title Registration KISIP, RIC, PAPs,
    (including Gender Empowerment on Beneficiaries
 3.
    land ownership), sectional Title




                                                             CO
    Management
                                           KISIP,        PAPs,
 4. Disclosure of ARAP
                                           Beneficiaries
                                           KISIP, RIC, GRC,
    Capacity building of Grievance Redress PAPs
 5.
    Committee
                             RE
                                             KISIP,         County
 6. Validation of asset valuation/values
                                             Government,
                                             KISIP, RIC, PAPs,
                                             Beneficiaries, GRC
                          SU

 7. Grievance Redress


                                           KISIP, PAPs, RIC,
    Sensitization of PAPs on bank accounts County Government,
                       LO



    and use of compensation funds Women                  Based
 8.                                        Organizations    (if
    including joint spousal management of
    cash, GBV in use of funds              present), SEC
                    SC




 9. Payment of compensation                  KISIP, RIC
                                             KISIP, RIC
 10.Issuance of notice for self-demolition
                 DI




 11. Self-Demolition                          PAPs
     Demolition of any structures that have Nairobi County
 12. not been demolished at the expiry of the
     notice period

Page 57 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto

                                            Actor                    Implementation to
                                                                     begin immediately
                                                                      after approval of
    TASK NAME                                                               ARAP
                                                                       Period in Months

                                                                 1       2   3   4   5    6
                                            KISIP
 13.Monitoring activities
                                            MoTIH&UD
                                            KISIP, Ministry of
    Formation, Registration and training of Lands & Physical
 14.
    the Corporation                         Planning
                                            MoTIH&UD




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 58 of 130
                  Abbreviated Resettlement Action Plan for Kambi Moto

10.9 Costs and Budget
The budget for this project has been prepared considering that the compensation will be
in the form of cash. Any administrative expenses e.g. costs of facilitation transfer, logistics
for committees etc. will be incurred by the project. The values projected in the budget
have also been estimated with consideration of the market trends in the project area
taking into consideration the expected immediate changes in the short-term future.

In this ARAP, the cost for implementation amounted to KES. 803,195.00 (Read Kenya
Shillings Eight hundred and Three thousand, one hundred and ninety-five only). This is
inclusive of a total of KES. 633,460 for Vulnerability support, corporation registration,
supervision, implementation, disturbance allowance and monitoring/evaluation fund for
the project. These costs are summarized in the following table:
Table 10-3: Summary of ARAP Implementation budget for Kambi Moto settlement
 S/        DESCRIPTION                                                      VALUE
 N




                                                                      PY
      1. Loss of assets (structures)                                        169, 735.00

      2. Vulnerability Support and assistance                               8,000.00




                                                                   CO
      3. Formation,      registration      and     training     of    the 50,000.00
           corporation
      4. Awareness raising and sensitization of Beneficiaries 120,000.00
           and PAPs
           -
                             RE
      5.   Training and Capacity Building for GRM                           80,000.00
           -
      6.   Operational & Administrative Costs                 of     RAP 100,000.00
           Committees
           -
                          SU

      7.   Monitoring and Evaluation                                        250,000.00
           -
      8.   Disturbance allowance                                            25,460
                       LO



           GRAND TOTAL                                                      803,195.00
                    SC
                 DI




Page 59 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto

CHAPTER 11:                MONITORING AND EVALUATION
    AND IMPLEMENTATION OF THE ARAP


11.1 Introduction

Monitoring and evaluation for implementation of this ARAP will be undertaken on a
continuous basis to ensure that the resettlement plan is smoothly implemented and PAPs
have been adequately assisted before implementation of component two of the project;
and whether the PAPs enjoy the same or higher standard of living than before. Monitoring
will also ensure that attention is given to the 2 vulnerable persons affected by the plan.
Monitoring will provide both as a warning system for the project proponent and a channel
for the affected persons to make known their needs and their reactions to resettlement
activities.




                                                                 PY
Monitoring and evaluation activities and programs will be adequately funded and staffed.
In-house monitoring will need to be supplemented by independent monitors to ensure
complete and objective information gathering. The primary responsibility for monitoring




                                                              CO
rests with proponent i.e. KISIP which already has a Social Safeguards Team which will
work in collaboration with the RIC, and other external actors, where needed.


11.2 Monitoring and Evaluation Framework
                             RE
11.2.1 ARAP Monitoring Plan

The ARAP Monitoring Plan and Framework involves internal monitoring by KISIP,
impact monitoring commissioned to specialized firms and Resettlement Completion
                          SU

Audit. The ARAP Monitoring Plan to be adopted is presented below:

Table 11-1:   Monitoring Plan
   Activity        Monitoring           Means of         Responsibility Frequency
                       LO



                   Parameters         verification
 Impact          Tracking           Quarterly or         Project            Frequently
 Monitoring      effectiveness of   semi-annual          safeguards and     as required
                 inputs against     quantitative and     RIC or             by the
                 baseline           qualitative          contracted         (KISIP)
                    SC




                 indicators         surveys              external
                                                         monitoring
                 Assessment of      Regular public       agency
                 PAP satisfaction   meetings and
                 DI




                 compensation       other
                 proposals of the   consultation with
                 affected assets    people affected by
                                    the project;

Page 60 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto

                                      review of
                                      grievance
                                      mechanism
                                      outputs
 Completion Measurement of            External            Contracted      On
 Audit      output                    assessment of       external        completion
            indicators such           ARAP                auditing and    of the ARAP
            as productivity           implementation,     evaluation      time table
            gains and                 independent         agency
            developmental             surveys and
            impact against            consultation with
            baseline                  affected persons


11.2.2 ARAP Monitoring Framework




                                                                  PY
ARAP Implementation Reports will be verified by a field check of the following:

      i.   Payment of compensation
     ii.   Stakeholder engagement
    iii.   Formation and Registration of a corporation for titles Management




                                                               CO
    iv.    Adequacy of training and other developmental inputs.
     v.    Infrastructure repair, relocation or replacement.
    vi.    Transition allowances.

The mechanism of the above shown field check includes the following:
                             RE
      i. Public Consultations with affected people at the community level will be
         observed.
     ii. The resettlement operation at all levels will be observed to assess its
         effectiveness and compliance with the ARAP.
   iii. The type of grievance issues and the functioning of Grievance Redress
                          SU

         Mechanisms will be checked by reviewing the processing of appeals at all
         levels and interviewing aggrieved PAP’s.
    iv. The standards of living of the PAP’s before and after implementation of
         resettlement will be surveyed to assess whether the standards of living of the
                       LO



         PAP’s have improved or been maintained.
     v. Project management will be advised regarding necessary improvements in
         the implementation of the ARAP, if any.
    vi. Functional corporation able to manage issues related to sectional titles
                    SC




The Table 11-2 below shows Internal Monitoring Indicators that will be checked during
Internal Performance Monitoring by KISIP:
                 DI




Table11-2: Monitoring Indicators
   Activity/Parameters              Indicators
   Compensation       for          • Number of PAPs promptly paid disaggregated by gender
   loss of structures              • Number and amounts of payments made to PAPs

Page 61 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto

                               • Number of PAPs with restored assets disaggregated by type
                                 of structure
                               • Number of restored structures disaggregated by type,
                                 building/construction material, asset use/purpose and
                                 standard
                               • Average income level by source
                               • Employment status of household head
                               • Use of compensation cash
                               • Development of settlement triggered by land tenure process
                               • Changes in land values and plot ownership
   Access to services          • Number of PAPs with access to water services disaggregated
                                 by type of water source
                               • Number of PAPs with access to sanitation services
                                 disaggregated by type of water source
                               • Number, type of educational establishments and proximity
                                 to PAPs




                                                               PY
                               • Number, type of health facilities establishments and
                                 proximity to PAPs
                               • Length of roads that are newly constructed or expanded
   Vulnerability               • Status of “vulnerable” homesteads




                                                            CO
                               • Structures constructed to PAPs through Additional
                                 Assistance
   Community                   • Number of local consultative meetings held
   participation   and         • Type of issues raised at public consultation meetings
   public engagement           • Number of participants attending public consultation
                             RE
                                 meetings related to displacement disaggregated by gender
   Training         and        • Number of trainings held disaggregated by target
   Capacity Building             group/institutions and issues
                               • Number and type of participants disaggregated by gender
                          SU

                               • Themes discussed in various trainings
                               • Perception of PAPs on usefulness and timing of these issues
                                 discussed
   Gender Concerns             • Number of women with land titles disaggregated by type
                       LO



                                 (e.g. sole owners, joint owners)
                               • Number of Cases of GBV
                               • Participation of women and men in trainings
                               • Number of Joint accounts opened for facilitation funds
                    SC




   Grievance                   • Number of grievances received
   management                  • Number of grievances resolved promptly (within the
                                 duration allowed in the grievance redress mechanism)
                               • Number of outstanding grievances not resolved
                 DI




                               • Average timelines for resolution of grievances
                                 disaggregated by the various levels of grievance redress
                                 mechanism/institutions
                               • Number of grievances referred to Level 3 (Courts of Law)

Page 62 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto

                                • Number of complaints referred to World Bank
   Awareness            and     • Type of information disclosed to PAPs during each meeting
   Access                to     • Accessibility of the ARAP document at the local level
   Information                  • Accessibility of the ARAP document on the Ministry’s
                                  website and the Bank’s Info shop
                                • Awareness on ARAP/Entitlement information
                                • Number of people seeking information on displacement
                                  and compensation
   Process Management           • Formation of proposed institutions or better alternatives
                                • Census and asset verification/quantification procedures in
                                  place
                                • Effectiveness of compensation delivery system by KISIP
                                • Efficiency of compensation delivery system by KISIP
                                • Co-ordination between KISIP national, KISIP, County
                                  Government and the community
                                • Availability of adequate funds for the process




                                                                 PY
   Sectional           Title    • Formation and registration of a corporation (facilitated by
   Management                     KISIP)
                                • Training of the corporation membership on sectional titles
                                  management




                                                              CO
                                • Gender mainstreaming in the corporation leadership.
11.3 Resettlement Completion Audit

The purpose of the completion audit will be to verify and ascertain that the resettlement
                             RE
process at the end of ARAP implementation has complied with resettlement
commitments as defined by the ARAP. This audit will be done at end of ARAP
implementation either internally by KISIP PCT or by an external audit firm to be hired by
KISIP. Reference document for the completion audit will be this ARAP Report and the
legal framework lay therein.
                          SU


The Completion Audit will have following specific objectives:
      i. Assessment of compliance of implementation with laws, regulations and
                       LO



         safeguard policies.
     ii. Assessment of the adequacy and promptness of the compensation and
         resettlement procedures as implemented.
    iii. Evaluation of the impact of the compensation and resettlement program
         measured through incomes and standards of living, with an emphasis on the
                    SC




         “no worse-off if not better-off” requirement; and
    iv.  Identification of potential corrective actions necessary to mitigate the
         negative impacts of the program, if any, and to enhance its positive impacts.
                 DI




The Completion Audit will be based on documents and materials generated by internal
and external monitoring persons. In addition, auditors will make their own assessments,
surveys and interviews in the field and with Project Affected Persons.


Page 63 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto

CHAPTER 12:                 CONCLUSION AND COMMITMENTS


12.1 Conclusion

This ARAP Report is prepared to mitigate impacts arising from the planning and
surveying in readiness for tenure regularisation and issuance of Sectional Title Deeds for
beneficiaries in Kambi Moto informal settlement located in Nairobi City County. The
planning and Surveying activity is undertaken by the Kenya Informal Settlements
Improvement Project (KISIP).

The Kambi Moto ARAP has been prepared in compliance with the applicable Kenyan
Legal Framework and the provisions of the World Bank's Safeguard Policy on
Involuntary Resettlement (OP 4.12). Under the World Bank’s OP 4.12, for all projects
that anticipate displacement of persons including shelter, livelihood and associated




                                                                  PY
impacts, a RAP has to be prepared.

World Bank’s (OP 4.12) allows that “for projects in which the number of people to be
displaced with a loss of assets or restriction of access to assets is small (less than 200
persons will experience resettlement effects), an abbreviated resettlement plan (ARAP)




                                                               CO
should be prepared. The displacement of economic activities in Kambi Moto informal
settlement meets these conditions.

The ARAP presents an inventory (register) of PAPs, an Asset register of affected assets
and the proposed compensation package. The process for preparation of this ARAP
                             RE
involved all stakeholders notably the SEC members, the Kambi Moto community, KISIP
National and County Teams, NLC and the Consultant under KISIP. Ownership of the
ARAP has been internalised by all the affected persons through a rigorous and adequate
consultations.
                          SU

12.2 Commitments

   •   KISIP RIC in collaboration with the Registrar of Titles will organize and carry out
                       LO



       Sensitization exercises aimed at enhancing women land rights as documented in
       this ARAP.
   •   Facilitate all the affected persons according to provisions of this ARAP within 3
       months after approval of this ARAP.
                    SC




   •   KISIP will Ensure Grievances raised are addressed and resolved on a timely
       manner during implementation of the ARAP.
   •   All vulnerable persons enumerated in this ARAP will be promptly facilitated in
       accordance with the provisions of this ARAP
                 DI




   •   KISIP through the Ministry of Lands and Physical Planning and NLC will
       immediately begin issuance of title deeds to beneficiaries, concurrently with
       compensation.

Page 64 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto

   •   Issue a three months’ notice to PAPs to enable them Self Demolish and salvage
       their assets.
   •   To undertake thorough community engagement and sensitization on Sectional title
       during implementation.
   •   KISIP will incur all costs associated in management of the Sectional Title from
       formation of the cooperation up until handover to beneficiaries
   •   Undertake Monitoring and Evaluation of this ARAP during and after
       implementation
   •   KISIP will work with the County Government of Nairobi in ensuring the RAP is
       successfully implemented. The County Government will be part of the RIC and
       GRM committees. The County Government will also enforce development
       controls, clearance of structures on road reserves after the expiry of self-demolition
       period
   •   Facilitate and assist in formation, registration and training on the cooperation




                                                                   PY
                                                                CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 65 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto



REFERENCES
1. Socio-economic survey of Kambi Moto Settlement, Nairobi 2019.
2. Local Physical and Land Use Development Plan for Kambi Moto Settlement, Nairobi
   2019.
3. International Finance Corporation; Handbook for Preparing a Resettlement Action
   Plan
4. Resettlement Policy Framework (RPF) for KISIP, October, 2014




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 66 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto

    ANNEXES

     Annex 1: Minutes of the PAPs Consultation Meeting Held on
     21st August 2019 at the Muungano Kambi Moto Social Hall,
     Kambi Moto from 10:55 am.




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 67 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 68 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 69 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 70 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 71 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                             PY
                                                          CO
A photograph of the RAP meeting in session
                             RE
                          SU
                       LO
                    SC




The RAP Expert appraising the community on resettlement policies and
guidelines
                 DI




Page 72 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




A photograph of the valuer taking measurements of an affected structure.




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 73 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto


     Annex 2: Minutes of the Final Stakeholders Meeting Held on
     4th of November 2019 at the New Mathare Church Hall, Kambi
     Moto from 2:00 pm.




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 74 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 75 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 76 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 77 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 78 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 79 of 130
                 Abbreviated Resettlement Action Plan for Kambi Moto




                                                             PY
                                                          CO
                             RE
                          SU
                       LO
                    SC
                 DI




Page 80 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                               PY
                            CO
      RE
   SU

                                                      Page 81 of 130
LO
Abbreviated Resettlement Action Plan for Kambi Moto




                               PY
                            CO
      RE
   SU

                                                      Page 82 of 130
LO
Abbreviated Resettlement Action Plan for Kambi Moto




                               PY
                            CO
      RE
   SU

                                                      Page 83 of 130
LO
Abbreviated Resettlement Action Plan for Kambi Moto




                               PY
                            CO
      RE
   SU

                                                      Page 84 of 130
LO
Abbreviated Resettlement Action Plan for Kambi Moto




                               PY
                            CO
      RE
   SU

                                                      Page 85 of 130
LO
       Abbreviated Resettlement Action Plan for Kambi Moto




Annex 3: Minutes of the Presentation and Adoption of
Proposed Kambi Moto Settlement Draft LP&LUDP, Final
Verification Exercise of the List of Beneficiaries & Launch
RAP meeting Held on 26th of July 2019 at New Mathare
Church Hall, Kambi Moto from 10:20am.




                                                   PY
                                                 CO
                 RE
              SU
            LO
         SC
      DI




                                                             Page 86 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 87 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 88 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 89 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 90 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 91 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 92 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 93 of 130
      Abbreviated Resettlement Action Plan for Kambi Moto


Annex 4: Minutes of Stakeholder Engagement Meeting
(Presentation of Socio Economic Survey Findings,
Validation of Base maps, Visioning and Community
Participatory Planning) Held on 30th May 2019 at Kambi
Moto from 10: 30 am.




                                                  PY
                                                CO
                 RE
              SU
            LO
         SC
      DI




                                                            Page 94 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 95 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 96 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 97 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 98 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 99 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 100 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                          CO
           RE
        SU
      LO
   SC
DI




                                                      Page 101 of 130
       Abbreviated Resettlement Action Plan for Kambi Moto


Annex 5: Minutes of the Project Launch Workshop Held on
27th March 2019 at 2: 23 Pm in Kambi Moto Settlement,
Nairobi




                                                   PY
                                                CO
                  RE
               SU
            LO
         SC
      DI




                                                             Page 102 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                         CO
            RE
         SU
      LO
   SC
DI




                                                      Page 103 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                         CO
            RE
         SU
      LO
   SC
DI




                                                      Page 104 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                         CO
            RE
         SU
      LO
   SC
DI




                                                      Page 105 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                         CO
            RE
         SU
      LO
   SC
DI




                                                      Page 106 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                         CO
            RE
         SU
      LO
   SC
DI




                                                      Page 107 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                            PY
                                         CO
            RE
         SU
      LO
   SC
DI




                                                      Page 108 of 130
           Abbreviated Resettlement Action Plan for Kambi Moto


Annex 6: Minutes of the Project Introduction Meeting Held on 27th
February 2019 at the Muungano Kambi Moto Hall, Kambi Moto from
11:55 am.




                                                        PY
                                                     CO
                      RE
                   SU
                LO
             SC
          DI




                                                                 Page 109 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                             PY
                                          CO
            RE
         SU
      LO
   SC
DI




                                                      Page 110 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                             PY
                                          CO
            RE
         SU
      LO
   SC
DI




                                                      Page 111 of 130
Abbreviated Resettlement Action Plan for Kambi Moto




                                             PY
                                          CO
            RE
         SU
      LO
   SC
DI




                                                      Page 112 of 130