The World Bank Implementation Status & Results Report PMGSY Rural Roads Project (P124639) PMGSY Rural Roads Project (P124639) SOUTH ASIA | India | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2011 | Seq No: 16 | ARCHIVED on 13-Jun-2019 | ISR36506 | Implementing Agencies: National Rural Road Development Agency, Republic of India, National Rural Roads Development Agency, Ministry of Rural Development Key Dates Key Project Dates Bank Approval Date: 20-Dec-2010 Effectiveness Date: 18-Feb-2011 Planned Mid Term Review Date: 30-Jun-2013 Actual Mid-Term Review Date: 18-Feb-2014 Original Closing Date: 30-Nov-2015 Revised Closing Date: 15-Dec-2020 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective is to strengthen the systems and processes of the national PMGSY rural roads program for the expansion and maintenance of all- season rural access roads. The result will enhance the road connectivity to economic opportunities and social services for beneficiary communities in the participating states. Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Project Development Objective (If project is formally restructured) The objective is to strengthen the systems and processes of the national PMGSY rural roads program for the expansion and maintenance of all-season rural access roads. The result will enhance the road connectivity to economic opportunities and social services for beneficiary communities in the participating states. Components Table Name PMGSY Program Financing:(Cost $970.00 M) Institutional Strengthening:(Cost $30.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Highly Satisfactory Highly Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions 6/13/2019 Page 1 of 8 The World Bank Implementation Status & Results Report PMGSY Rural Roads Project (P124639) The implementation progress is as below: Component One: PMGSY Program Financing: The balance work of already sanctioned works during original Project (RRP-II) is under progress. Meanwhile, new sanctions of Road & bridge works of 6080 Km under environmentally optimized designs and 2660 Km under Green & Climate resilient roads with an estimated value of US$ 748.77 million including pilot under innovative technologies in Tamil Nadu & Orissa . Component Two: Institutional Strengthening: NIRDA has made progress on institutional strengthening activities such as GIS based road network data, E-Marg platform being adopted in all states for maintenance management system based on the experience of the state of Madhya Pradesh and training and capacity building of 3,500 staff in the last fiscal year. However, NRIDA also needs to enhance implementation of other activities such as asset management plan, rural road safety action plans, vulnerability assessment, green and climate-resilient strategy etc., many of them are critical to achieve the Disbursement Linked Indicators. 6/13/2019 Page 2 of 8 The World Bank Implementation Status & Results Report PMGSY Rural Roads Project (P124639) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Moderate Moderate Macroeconomic -- Low Low 6/13/2019 Page 3 of 8 The World Bank Implementation Status & Results Report PMGSY Rural Roads Project (P124639) Sector Strategies and Policies -- Low Low Technical Design of Project or Program -- Substantial Substantial Institutional Capacity for Implementation and Sustainability -- Substantial Substantial Fiduciary -- Moderate Moderate Environment and Social -- Moderate Moderate Stakeholders -- Moderate Moderate Other -- -- -- Overall -- Substantial Substantial Results PDO Indicators by Objectives / Outcomes Number of habitations benefitted with all-weather roads IN00686457 ►Improved condition of core rural road network (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 55.00 64.00 64.00 68.00 Date 31-Mar-2018 30-Apr-2018 30-Apr-2018 15-Dec-2020 Not Due Yet Comments: IN00686458 ►Number of habitations benefitted with all-weather roads (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,000.00 Date 31-Jan-2018 30-Nov-2018 30-Apr-2019 15-Dec-2020 Data being collected Comments: IN00686459 ►Improved effectiveness of public expenditure - Km of roads used green and climate resilient designs and new technologies (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,000.00 Date 31-Mar-2018 31-Mar-2021 30-Apr-2018 15-Dec-2020 NRIDA has sanctioned 8,060 km of road works which are under different stages of implementation. Comments: IN00686460 ►Improved asset management - number of districts implementing performance and/or community based maintenance contracts (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 6/13/2019 Page 4 of 8 The World Bank Implementation Status & Results Report PMGSY Rural Roads Project (P124639) Value 10.00 10.00 2.00 50.00 Date 31-Mar-2018 31-Mar-2021 30-Apr-2019 15-Dec-2020 Not due yet Comments: Intermediate Results Indicators by Components Institutional Strengthening IN00686631 ►Effectiveness of Public Expenditures - improved planning systems (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Adoption of the Value To be drafted -- Being Finalised Manual Date 31-Mar-2018 30-Jun-2016 30-Apr-2019 15-Dec-2020 IN00686632 ►Effectiveness of Public Expenditures - Number of districts establishing GIS based road and bridge inventory and condition database (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 2.00 2.00 2.00 20.00 Date 31-Mar-2018 26-Dec-2017 30-Apr-2019 15-Dec-2020 IN00686633 ►Effectiveness of Public Expenditure - vulnerability assessment (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5,000.00 Date 31-Mar-2018 30-Jun-2016 30-Apr-2019 15-Dec-2020 Terms of Reference under finalisation Comments: IN00686634 ►Effectiveness of Public Expenditures –award of civil works within 45 days of bids submission (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 77.00 77.00 77.00 90.00 Date 31-Mar-2018 30-Nov-2018 30-Apr-2019 15-Dec-2020 Data being collected Comments: IN00686635 ►Effectiveness of public expenditure - Number of states having prepared road safety action plan (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.00 2.00 10.00 6/13/2019 Page 5 of 8 The World Bank Implementation Status & Results Report PMGSY Rural Roads Project (P124639) Date 31-Mar-2018 30-Nov-2018 30-Apr-2019 15-Dec-2020 IN00686636 ►Effectiveness of Public Expenditures – procurement and contract management manual (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Draft under preparation -- Being Finalised Adopted Date 31-Mar-2018 30-Nov-2018 30-Apr-2019 15-Dec-2020 Draft Procurement and Contract Management Manual has been prepared already and will be finalized Comments: after the finalization of the harmonized bidding document. IN00686637 ►Effective Execution of Maintenance Works - Number of states with asset management plans adopted (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2.00 2.00 10.00 Date 31-Mar-2018 30-Nov-2018 30-Apr-2019 15-Dec-2020 Under preparation in other states Comments: IN00686638 ►Effective Execution of Maintenance Works - Number of districts that publicly disclose annual maintenance plans (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 31-Mar-2018 30-Nov-2018 30-Apr-2019 15-Dec-2020 Data being collected Comments: IN00686639 ►Improved Institutional Effectiveness - Number of staff accredited after completing training (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 20.00 3,500.00 2,000.00 Date 31-Mar-2018 30-Nov-2018 30-Apr-2019 15-Dec-2020 3,500 already undertaken training in at least one course in FY18-19 Comments: IN00686640 ►Improved Institutional Effectiveness - Number of districts with disclosure of annual performance reports (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 31-Mar-2018 30-Nov-2018 30-Apr-2019 15-Dec-2020 Data being collected Comments: IN00686641 ►Improved Institutional Effectiveness - Number of workshops organized for Gender based capacity enhancement (Number, Custom) 6/13/2019 Page 6 of 8 The World Bank Implementation Status & Results Report PMGSY Rural Roads Project (P124639) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 30-Mar-2018 30-Nov-2018 30-Apr-2019 15-Dec-2020 data being collected Comments: IN00686642 ►Improved Institutional Effectiveness - Number of women benefitted through self-help groups engaged in post-construction maintenance contracts (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 100.00 0.00 0.00 2,000.00 Date 30-Mar-2018 30-Nov-2018 30-Apr-2019 15-Dec-2020 Data being compiled and will be shared after finalization of MOUs in States with Women Self-help Groups. Comments: IN00686643 ►Improved Institutional Effectiveness - Effective citizen feedback mechanism (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 85.00 Date 30-Mar-2018 30-Nov-2018 30-Apr-2019 15-Dec-2020 Data being compiled Comments: Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P124639 IBRD-79950 Closed USD 500.00 500.00 0.00 500.00 0.00 100% P124639 IBRD-88640 Effective USD 500.00 500.00 0.00 51.93 448.07 10% P124639 IDA-48480 Closed USD 379.40 279.40 100.00 246.58 0.00 100% P124639 IDA-48490 Closed USD 620.60 620.60 0.00 607.49 0.00 100% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P124639 IBRD-79950 Closed 20-Dec-2010 14-Jan-2011 18-Feb-2011 30-Nov-2015 30-Jun-2018 P124639 IBRD-88640 Effective 25-May-2018 31-May-2018 18-Jun-2018 15-Dec-2020 15-Dec-2020 P124639 IDA-48480 Closed 20-Dec-2010 14-Jan-2011 18-Feb-2011 30-Nov-2015 30-Jun-2018 6/13/2019 Page 7 of 8 The World Bank Implementation Status & Results Report PMGSY Rural Roads Project (P124639) P124639 IDA-48490 Closed 20-Dec-2010 14-Jan-2011 18-Feb-2011 30-Nov-2015 30-Jun-2018 Cumulative Disbursements Restructuring History Level 2 Approved on 20-Jan-2014 ,Level 2 Approved on 03-Dec-2014 ,Level 2 Approved on 04-Nov-2015 ,Level 2 Approved on 08-Jun-2016 ,Level 2 Approved on 29-Jun-2017 ,Level 2 Approved on 27-Oct-2017 ,Level 2 Approved on 12-Apr-2018 Related Project(s) P165402-Additional Financing for PMGSY Rural Roads Project 6/13/2019 Page 8 of 8