Public Disclosure Copy The World Bank Implementation Status & Results Report Financial Sector Rapid Response Project (P119047) Financial Sector Rapid Response Project (P119047) SOUTH ASIA | Afghanistan | Finance & Markets Global Practice | IBRD/IDA | Specific Investment Loan | FY 2012 | Seq No: 9 | ARCHIVED on 07-Feb-2017 | ISR26880 | Implementing Agencies: Key Dates Key Project Dates Bank Approval Date:25-Aug-2011 Effectiveness Date:06-Sep-2011 Planned Mid Term Review Date:04-Oct-2014 Actual Mid-Term Review Date:25-Apr-2015 Original Closing Date:30-Jun-2014 Revised Closing Date:31-Oct-2019 Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project's development objective is to assist DAB to develop actions plans for improved banking supervision and implementamodernnational payment system for efficient and transparent payment transactions. Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Project Development Objective (If project is formally restructured)PHRPDODEL To assist DAB to develop action plans for improved banking supervision and to establish key building blocks of financial sector infrastructure: payment system, movable collateral registry, and public credit registry. Components Name Strengthening the DAB's capacity:(Cost $9.00 M) Development of the financial sector infrastructure:(Cost $29.70 M) DAB Skill Development; Technical Assistance and project implementation:(Cost $7.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory 2/7/2017 Page 1 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Financial Sector Rapid Response Project (P119047) Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions Two implementation support missions were conducted during (July 21 –August 4, 2016) and (January 13 –28, 2017) to assess implementation progress, finalize pending procurement issues. DAB's leadership demonstrated strong support to achieving the project's development objective. The new Additional Financing (AF) was approved by the World Bank’s Board on October 27, 2016. The legal agreement was signed by the Minister of Finance on January 4th 2017 and the agreement is currently being reviewed by Ministry of Justice as the final step towards effectiveness. On another front, the parent project’s progress has been maintained during the past six months. Many developments have taken place that are expected to improve project performance in the coming months. Component 1: Strengthening of DAB Financial Supervision Department’s (FSD) capacity: 1 . Under this component a firm would be recruited to provide TA to strengthen the capacity of the Financial Supervision Department in the areas of banking regulation and supervision. The technical evaluation report (TER) was submitted to the task team for no objection on June 26, 2016 identifying two shortlisted firms to be considered for the next step. The TER was reviewed and the go-ahead was granted on July 12, 2016 to proceed to reviewing the financial proposals as the final step towards awarding the contract and implementation. NPA advised the team on January 7th 2017 that the contract negotiations process has not yet been finalized which requires further extension of the proposals validity period for the 4th time January 24, 2017 up to March 21, 2017. The team discussed with DAB’s leadership the need to expedite the negotiation process and move forward with this critical component and will be closely following up. 1 . Once on board, the consultancy firm will be tasked with the following important activities: (i) stock taking on capacity building efforts on financial supervision over the last 10 years and development and implementation of a capacity building plan to sustainably strengthen the Financial Supervision Department, (ii) diagnostic review of the current legal and regulatory landscape and identify the key regulatory reform areas and regulations in need of an update/development. This is to be followed by a timed action plan that prioritizes / sequences regulations that need to be updated or developed; and (iii) development and implementation of action plans following audits of commercial banks. Component 2: Development of the financial sector infrastructure: Support to establishment of Collateral Registry (CR) and Public Credit Registry (PCR): 1 . The Collateral Registry (CR) and the Public Credit Registry (PCR) remains a significant achievement. Since it officially started operations in 2013 and 2014 respectively, CR is now utilized by DAB’s FSD, 15 commercial banks, 4 microfinance institutions as well as the Revenue’s department. The implementation of the PCR has been undertaken in partnership with IFC Advisory Services. As per a DAB circular issued on November 18, 2014, all commercial banks are mandated to make an inquiry to the PCR and obtain a Credit Report before issuing a loan. 2 . As of end-November 2016 (after almost three years of operations), DAB indicated that the total number of active contracts in the PCR system reached 62357. The PCR has been well received in the Afghan financial sector as a significant step forward to circumventing bureaucracy within financial institutions, as well as reducing the cost of access to credit and systematic risk. Stakeholders also recognized the role of the CR and PCR in bridging the credit information gap in the country. Although much more needs to be done in enhancing financial intermediation on the lending side by banks, the establishment of the CR and PCR is fundamental to sound financial market development and as economic activity picks up, will serve to establish a valuable service that can greatly facilitate the development of credit markets over time. On the other hand, the public searches on CR by end November 2016 has reached 14609 with total value of active credit limits 24 billion AFN . 3 . CR/PCR is now playing a more active role to scale up its operations, in this respect a meeting was held on 22nd August 2016 with Large and Medium Tax Payers Directorate at Ministry of Finance in order to increase the registration of Tax Lien notices into CR system. Besides, the CR team has conducted training on Collateral Registry system for a responsible employee of Medium Tax Payer Directorate on 20th September 2016. Recently, a new user of CR system has been created for Revenue Collection Department Staff at Ministry of Finance on 20th September 2016. CR/PCR is also in touch with Afghanistan Independent Land Authority (Arazi) organization on 23rd August 2016 regarding the registry of securing charges on immovable property. The January 2017 ISM discussed CR/PCR requests for build capacity of its staff and the team will coordinate with IFC advisory in this respect. 4 . Modernization of National Payment Systems: including setting up an Automated Transfer System (ATS), National Card and Mobile Payment Switch (Afghanistan Payment System) and an Interbank Communication Network: The Modernization of National Payment Systems included financing the setup of ATS which entails the Real Time Gross Settlement System (RTGS), Automated Clearing House (ACH) and Centralized Securities Depository (CSD). It is meant to modernize the national payment system for efficient and transparent payment transactions. The ATS and its subcomponents will support enhancing financial intermediation and enabling safety and efficiency of the financial system. It will also facilitate financial inclusion and service delivery and outreach through 2/7/2017 Page 2 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Financial Sector Rapid Response Project (P119047) building the required infrastructure for more efficient payment services. 5 . The procurement of the ATS was finalized in April 2016 with the signature of the contract between DAB and CMA (the awarded firm). The kickoff meeting was held in May 2016 and DAB had a detailed technical discussion with CMA on implementation arrangements. The functional specification document (FSD) was finalized and signed with CMA on December 19th 2016. It was communicated to commercial banks to start preparation to connect their core banking systems to the ATS as soon as it is operational. The FSD will be published on DAB’s website shortly. The duration of the contract is 13 months and the warranty and post warranty periods will be eight years after the operational acceptance of the system. 6 . The national card and mobile payment switch is a key component of the modernization of the national payment system. Once fully operational, it will serve its potential participants in terms of being able to bring their Automated Teller Machines (ATMs), Point of Sale (POS) terminals, agents, mobile money accounts and cards on to the Afghanistan Payment System (APS) platform that is anchoring this infrastructure. APS is aimed to enhance the efficiency of electronic payments, reducing transaction costs and fostering financial intermediation through offering interoperability to financial intermediaries and retailers to facilitate electronic and card payments. All technical operational requirements and testing were concluded by APS team and it was officially inaugurated by DAB’s Governor on April 26, 2016. There are currently 6 participating banks in APS and another bank and a mobile operator are in discussion to join the platform. Support to the development of the Afghanistan Institute of Banking and Finance (AIBF) 1 . AIBF’s management reported that it adopted 90% of the Organizational Capacity Assessment since January 2016. It is now the sole provider accredited ACCA courses in Afghanistan and currently acquiring the required accreditation to provide certified internal audit courses. AIBF signed a MoU in December 2016 with the Indian Institute of Banking and Finance to share expertise, provide specialized quality training courses and facilitate accreditation of training programs. 2 . During the past year, AIBF offered training courses for 1027 professional employees from the banking industry of which around 95 were women professionals. Component 3: Technical assistance and training for project implementation: 1 . This component focuses on providing technical assistance to support the implementation capacity of APS and DAB. It is meant to complement the investment in physical equipment financed under component 2 for the modernization of the national payment system. A payment system consultant has been providing technical inputs to APS, for the switch, and DAB for the RTGS/& ACH (collectively ATS) and /CSD, while a legal consultant has completed: (i) the assessment of the legal and regulatory framework for the NPS; (ii) the review, with proposed amendments, of APS bye-laws against the requirements under the financing agreement; and (iii) recommendations for addressing the gaps identified in the legal and regulatory framework (revisions of Electronic Fund Transfer and Money Service Providers regulations). Support was also provided to ensure that the movable Collateral Registry managed by DAB is continuing to operate satisfactorily. Finally, this component also covered training for key stakeholders of the project and operating costs for the Project Implementation Cell. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- High High Macroeconomic -- High High Sector Strategies and Policies -- High High Technical Design of Project or Program -- Substantial Substantial Institutional Capacity for Implementation and Sustainability -- Substantial Substantial Fiduciary -- Substantial Substantial Environment and Social -- Low Low Stakeholders -- Substantial Substantial Other -- -- -- 2/7/2017 Page 3 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Financial Sector Rapid Response Project (P119047) Overall -- Substantial Substantial Results Project Development Objective Indicators PHINDPDOTBL Actions plans developed, with initial implementation monitored,for the ten banks audited (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Targeted TA on Targeted TA on banking Action plans Value No action plan banking supervision supervision under under under procurement procurement implementation Date 01-Aug-2011 07-Oct-2015 30-Dec-2016 31-Oct-2019 PHINDPDOTBL Payment system conforms to international norms (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Substantially Value Not conform Not conform Not conform Conform Date 01-Aug-2011 07-Oct-2015 31-Dec-2016 31-Oct-2019 Overall Comments Intermediate Results Indicators PHINDIRITBL Audit reports completed highlighting strengths and weaknesses of each bank (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target No audit reports to Audits Value Audits completed Audits completed international standards completed Date 01-Aug-2011 07-Oct-2015 30-Dec-2016 30-Jun-2016 2/7/2017 Page 4 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Financial Sector Rapid Response Project (P119047) PHINDIRITBL RTGS operational and transactions settled in real time by end of project (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value No RTGS No RTGS No RTGS RTGS goes live Date 01-Aug-2011 07-Oct-2015 31-Dec-2016 31-Oct-2019 PHINDIRITBL Number of commercial banks? staff trained in AIBF reaches 4,500 by end of project (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 1,017.00 4,850.00 5,000.00 6,000.00 Date 01-Aug-2011 16-Aug-2016 31-Dec-2016 31-Oct-2019 PHINDIRITBL Increased transparency through the adoption of international central bank accounting and auditing standards (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target DAB financial statements for the year ended Financial statements Financial statements in 2018 Value prepared based on local -- prepared based on local prepared in accounting standards accounting standards accordance with IFRS (as applicable in 2016) Date 16-Aug-2016 -- 30-Dec-2016 31-Oct-2019 Comments This is related to the new additional financing project that is not yet effective 2/7/2017 Page 5 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Financial Sector Rapid Response Project (P119047) PHINDIRITBL Effective Financial Supervision Department (FSD) organization with training processes in place to ensure sustainable capacity development (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Procurement of TA for Procurement of TA for Continuous Revised FSD organization Financial Supervision Value Financial Supervision implementation approved by DAB Department Under NPA Department underway of action plan review Date 01-Nov-2013 02-Jun-2015 30-Dec-2016 31-Oct-2019 PHINDIRITBL Percentage increase in the number of on-site and off-site examinations by the department (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 10.00 PHINDIRITBL Approval by DAB of financial sector regulations ensuring consistency with international standards (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target A new banking law and A new banking law and Afghanistan financial AML/CFT regulations AML/CFT regulations sector regulations not fully were approved. TA for were approved. TA for Key regulations Value aligned with international Financial Supervision Financial Supervision approved standards Department under Department under procurement procurement Date 01-Nov-2013 16-Aug-2016 30-Dec-2016 31-Oct-2019 PHINDIRITBL Interbank payment (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Same day all T+1 for Kabul area and T+1 for Kabul area and T+1 for Kabul area and Value over T+3 for other areas T+3 for other areas T+3 for other areas Afghanistan Date 01-Aug-2011 16-Aug-2016 30-Dec-2016 31-Oct-2019 2/7/2017 Page 6 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Financial Sector Rapid Response Project (P119047) PHINDIRITBL Card payment system (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target System goes Implementation of Implementation of live and, on an interbank card system interbank card system ongoing basis, underway. The Afghan underway. The Afghan processes over Payment system Payment system 80% of platform was platform was domestic Value No interbank card system inaugurated on April inaugurated on April 26, interbank/inter- 26, 2016. Discussions 2016. Discussions institution ongoing to increase ongoing to increase payment card number of participants number of participants and mobile (6 banks) (6 banks) money transactions Date 01-Aug-2011 16-Aug-2016 30-Dec-2016 31-Oct-2019 PHINDIRITBL Rating of national payment system (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Med-High: a, b, Low: a, e, f; Med-low: d; Low: a, e, f; Med-low: Low: a, e, f; Med-low: d; Value d, f; Med-Low: n.a. b, c d; n.a. b, c n.a. b, c c, e Date 01-Aug-2011 16-Aug-2016 30-Dec-2016 31-Oct-2019 PHINDIRITBL Increase in the number of creditreports sent by the Public Credit Registry to commercial banks (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 115,000.00 128,648.00 250,000.00 Date 01-Nov-2013 31-Mar-2016 30-Sep-2016 31-Oct-2019 Comments This is the latest figure received Jan 20th 2017 2/7/2017 Page 7 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Financial Sector Rapid Response Project (P119047) PHINDIRITBL Increase in the number of items of collateral registered in the Collateral Registry (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 815.00 5,828.00 6,207.00 10,000.00 Date 01-Nov-2013 30-Jun-2016 30-Sep-2016 31-Oct-2019 Comments This is the latest figure received Jan 20th 2017 PHINDIRITBL Enhanced operational efficiency of DAB staff : percentage reduction in time spent to prepare DAB balance sheet (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80% Date 16-Aug-2016 -- 30-Dec-2016 31-Oct-2019 Comments This is related to the new additional financing project that is not yet effective PHINDIRITBL DAB training - Number of key DAB staff trained (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1,443.00 Date 16-Aug-2016 -- 30-Dec-2016 31-Oct-2019 Comments This is related to the new additional financing project that is not yet effective 2/7/2017 Page 8 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Financial Sector Rapid Response Project (P119047) PHINDIRITBL Number of DAB staff who have completed or enrolled into a Bachelor or Masters program (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 88.00 -- 0.00 250.00 PHINDIRITBL DAB training - Percentage of eligible staff in critical functions who completed specialized, professional training sessions (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 PHINDIRITBL Number of key DAB female staff trained under the project (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 172.00 Date 16-Aug-2016 -- 30-Dec-2016 31-Oct-2019 PHINDIRITBL Improved sustainability of APS and AIBF (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 50.00 Date 16-Aug-2016 -- -- 31-Oct-2019 Comments This is related to the new additional financing project that is not yet effective Overall Comments 2/7/2017 Page 9 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Financial Sector Rapid Response Project (P119047) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed Not P119047 IDA-D1400 XDR 14.40 14.40 0.00 0.00 14.40 0% Effective P119047 IDA-H7320 Effective XDR 11.90 11.90 0.00 7.43 4.47 62% P119047 IDA-H8930 Effective XDR 4.40 4.40 0.00 1.83 2.57 42% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P119047 IDA-D1400 27-Oct-2016 -- -- 31-Oct-2019 31-Oct-2019 Effective P119047 IDA-H7320 Effective 25-Aug-2011 27-Aug-2011 06-Sep-2011 30-Jun-2014 30-Jun-2018 P119047 IDA-H8930 Effective 26-Nov-2013 10-Mar-2014 04-Jun-2014 30-Jun-2016 30-Jun-2018 Cumulative Disbursements 2/7/2017 Page 10 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Financial Sector Rapid Response Project (P119047) Restructuring History Level 2 Approved on 26-Jan-2015 ,Level 2 Approved on 25-May-2016 Related Project(s) P147624-Additional Financing to Financial Sector Rapid Response Project ,P160073-Financial Sector Rapid Response - Additional Financing 2/7/2017 Page 11 of 11 Public Disclosure Copy