NILE EQUATORIAL LAKES SUBSIDIARY ACTION PROGRAM (NELSAP PROCUREMENT PLAN 1st May 2017 to April 2018 I. General 1. Project information: - Country borrower: Nile Basin Initiative/Nile Equatorial Lakes Subsidiary Action Program - Project Name: Nile Cooperation for Results Project - Loan/Credit No:- TF13766 - Project Implementing Agency (PIA): Nile Equatorial Lakes Subsidiary Action Program 2. Bank’s approvalDate of the procurement Plan: 3. Date of General Procurement Notice: N/A 4. Period covered by this procurement plan: 12 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] No Procurement Method Threshold Prior Review Comments (Goods and Works) in US Dollars Threshold in US Dollars 1 ICB (Goods) N/A N/A 2 LIB (Goods) N/A N/A 3 NCB (Goods and Non Consultants N/A N/A Services) 4 Shopping (Goods and Non ≤100,000 ≤100,000 Consultants Services) 5 ICB (Works) N/A 6 NCB (Works) N/A 7 Shopping (Works) N/A 8 ICB(Non-Consultant Services) N/A 2. Prequalification. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: : Guidelines for procurement under IBRD loans and IDA credits, NBI Procurement and Disposal Manual 5. Any Other Special Procurement Arrangements: N/A 6. Procurement Packages with Methods and Time Schedule: N/A III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: III. Selection of Consultants 2. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Ceiling Prior Review Comment Method Threshold 1. QCBS >= 1,000,000 2. QBS N/A 3. LCS ≤200,000 4. CQS N/A 5. SSS ≥ 100,000 6. IC ≥300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule PROCUREMENT Africa : AFCC2/RI-Nile Cooperation for Results Project PLAN General Information Country: Africa Bank’s Approval Date of the Original Procurement Plan: 2017-08-01 2018-10-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P130694 GPN Date: Project Name: AFCC2/RI-Nile Cooperation for Results Project Loan / Credit No: TF / 13767 Executing Agency(ies): Nile Basin Initiative/Nile Equatorial Lakes Subsidiary Program - Coordination Unit, Eastern Nile Technical Regional Office, Nile Basin Initiative Secretariat WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-ENTRO-23627-GO-RFQ / Service and supply of goods i.e network cable re- Pending Request for Single Stage - One installation & maintenance TF / 13767 Post Limited 0.00 Implementati 2017-08-20 2017-10-15 2018-02-12 Quotations Envelope For Upgrading the existing on network and electrical system ET-ENTRO-23630-GO-RFQ / Maintenance of backup Pending power supply equipment and Request for Single Stage - One TF / 13767 Post Limited 0.00 Implementati 2017-08-20 2017-10-15 2018-02-12 standardized installation Quotations Envelope on including supply of spare parts ET-ENTRO-23633-GO-RFQ / Supply and replacement of Pending old network equipment, Request for Single Stage - One TF / 13767 Post Limited 0.00 Implementati 2017-08-20 2017-10-15 2018-02-12 software and servers Quotations Envelope on including maintenance service ET-ENTRO-23658-GO-RFQ / Application software for Pending Request for Single Stage - One Strengthen National Dam TF / 13767 Post Limited 0.00 Implementati 2018-01-20 2018-03-17 2018-05-16 Quotations Envelope Safety Units and Developing on Human Resources Capacity ET-ENTRO-23659-GO-RFQ / Pending Dam safety monitoring and Request for Single Stage - One TF / 13767 Post Limited 0.00 Implementati 2018-02-20 2018-04-17 2018-06-16 inspection Quotations Envelope on instrument/equipment UG-NBI-24732-GO-DIR / Pending software tools for TF / 13767 Post Direct Selection Direct 0.00 Implementati 2018-02-05 2018-02-10 2018-03-17 2018-09-13 maintaining user community on portal and helpdesk UG-NBI-24733-GO-RFQ / Pending Request for Single Stage - One Printing the Corporate TF / 13767 Post Limited 0.00 Implementati 2017-10-10 2017-12-05 2018-06-03 Quotations Envelope Brochure on Page 1 UG-NBI-24734-GO-RFQ / Pending Request for Single Stage - One Printing the NBI Corporate TF / 13767 Post Limited 0.00 Implementati 2017-10-25 2017-11-24 2017-11-28 Quotations Envelope Report on ET-ENTRO-23640-GO-RFQ / High performance Workstations,laptops,ups,... Pending Single Stage - One to enhance and strengthen TF / 13767 Post Request for Bids Open - National 0.00 Implementati 2017-12-15 2017-12-20 2018-01-31 2018-03-02 2018-04-06 2018-06-05 Envelope Eastern Nile Seasonal on Forecasting and Flood Forecasting- Early Warning UG-NBI-24249-GO-RFQ / Pending Request for Single Stage - One 5.1.1 - High end computing TF / 13767 Post Limited 0.00 Implementati 2018-01-10 2018-02-22 2018-03-16 Quotations Envelope facility (server) on RW-NELSAP-CU-21626-GO- Request for Single Stage - One RFQ / Supply of Bulk Files TF / 13767 Post Limited 0.00 Canceled 2018-02-05 2018-03-10 2018-04-30 Quotations Envelope Archiving System RW-NELSAP-CU-21630-GO- Pending Request for Single Stage - One RFQ / Printing of RATP TF / 13767 Post Limited 0.00 Implementati 2018-02-01 2018-03-06 2018-04-05 Quotations Envelope Manuals on UG-NBI-24552-GO-RFQ / Request for Single Stage - One Printing 2018 NBI TF / 13767 Post Limited 4,500.00 Signed 2017-11-25 2018-01-19 2019-01-05 Quotations Envelope Secretariat Calendars UG-NBI-24221-GO-DIR / 1.10.1.1 - Software tools for Request for Single Stage - One TF / 13767 Post Limited 0.00 Canceled 2017-11-24 2017-11-29 2018-01-10 2018-02-09 2018-03-16 2018-09-12 developing the integrated Proposals Envelope website and databases Pending UG-NBI-24247-GO-RFQ / Request for Single Stage - One TF / 13767 Post Limited 0.00 Implementati 2017-12-02 2018-01-21 2018-02-18 5.1.1.1 - Laptops Quotations Envelope on Pending UG-NBI-37577-GO-RFQ / Request for Single Stage - One TF / 13767 Post Limited 0.00 Implementati 2018-01-15 2018-03-12 2018-09-08 Printing of the NBI Strategy Quotations Envelope on UG-NBI-37654-GO-RFQ / Pending Request for Single Stage - One Printing of the State of TF / 13767 Post Limited 0.00 Implementati 2018-01-09 2018-03-06 2018-09-02 Quotations Envelope knowledge brochure on ET-ENTRO-78513-GO-DIR / Pending Dam Safety Reference TF / 13767 Prior Direct Selection Direct 0.00 Implementati 2018-10-01 2018-10-06 2018-11-10 2019-01-09 Books/Journals on UG-NBI-24553-GO-RFQ / Request for Single Stage - One Printing the NBI Success TF / 13767 Post Limited 0.00 Canceled 2018-01-20 2018-02-12 2018-03-09 Quotations Envelope Stories UG-NBI-37655-GO-RFQ / Request for Single Stage - One Procurement of Computer TF / 13767 Post Limited 0.00 Canceled 2018-01-07 2018-03-04 2018-08-31 Quotations Envelope workstation/laptop UG-NBI-80192-GO-RFQ / Pending Activity 6.4.1.2 Printing of Request for Single Stage - One TF / 13767 Post Limited 0.00 Implementati 2018-10-23 2018-11-28 2018-12-20 communication products Quotations Envelope on (production cost, printing) NON CONSULTING SERVICES Page 2 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-ENTRO-23651-NC-RFQ / Pending Printing for Documentation Request for Single Stage - One TF / 13767 Post Limited 0.00 Implementati 2018-01-20 2018-03-17 2018-05-16 and dissemination (training Quotations Envelope on and scaling up manuals) ET-ENTRO-23656-NC-RFQ / Pending Production of Eastern Nile Request for Single Stage - One TF / 13767 Post Limited 0.00 Implementati 2018-01-20 2018-03-17 2018-06-15 Ground Water preliminary Quotations Envelope on Atlas Under UG-NBI-22127-NC-RFB / Single Stage - One TF / 13767 Post Request for Bids Limited 0.00 Implementati 2017-11-29 2017-12-04 2018-04-08 2018-04-15 2018-05-06 2018-09-15 IFMIS Software Envelope on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RW-NELSAP-CU-21811-CS- CQS / Consultancy Services for Finalization of Preparation of Environmental Consultant and Social Impact Open - Under TF / 13767 Post Qualification 0.00 2017-07-25 2017-08-15 2017-09-28 2017-10-14 2017-11-11 2018-05-10 Assessment (ESIA) and International Implementation Selection Resettlement Action Plan (RAP) for the Sio Sango Irrigation and Watershed Management Project RW-NELSAP-CU-21857-CS- CDS / Consultancy Services for the External Audit of the Financial Statements of Least Cost Pending TF / 13767 Post Open - National 0.00 2018-07-02 2018-07-23 2018-09-05 2018-10-03 2018-11-02 2018-12-07 2019-01-11 2019-07-10 the NELSAP/NCORE Project Selection Implementation CIWA Grant for the Period 1 July 2017 to 30 June 2018 RW-NELSAP-CU-21813-CS- CQS / Consultancy Services for Finalization of the Environmental and Social Consultant Open - Pending Impact Assessment (ESIA) TF / 13767 Post Qualification 0.00 2017-07-25 2017-08-15 2017-09-28 2017-10-13 2017-11-03 2018-05-02 International Implementation and Resettlement Action Selection Plan (RAP) for the Kabuyanda Water Resources Development Project ET-ENTRO-52179-CS-QCBS / Development of the Nile Quality And Cost- Open - Under TF / 13767 Prior 0.00 2018-04-26 2018-05-04 2018-06-17 2018-07-15 2018-08-14 2018-09-18 2018-10-23 2019-10-23 Basin Initiative Integrated Based Selection International Implementation Knowledge Portal (NBI-IKP) INDIVIDUAL CONSULTANTS Page 3