Details of the project procurement activities published under GPN.
GENERAL PROCUREMENT NOTICE (GPN)
Government of the Islamic Republic of Afghanistan
Eshteghal Zaiee – Karmondena Project (EZ-Kar)
Project ID No.: P166127
Implementing Agencies:

 1.   Ministry of Foreign Affairs (MoFA)
 2.   Independent Directorate of Local Governance (IDLG)
 3.   Kabul Municipality (KM)
 4.   Ministry of Economy (MoEc)

Procurement of Goods, Works, Consultancy and Non-Consultancy Services for the EZ-Kar Project
The Government of the Islamic Republic of Afghanistan (GoIRA) has been provided with a grant (US$ 50
million) from the Afghanistan Reconstruction Trust Fund (ARTF) and a grant (approximately US$ 150
million) from the International Development Association (IDA) of the World Bank Group, thus totaling
grants of US$ 200 million, towards the cost of the Eshteghal Zaiee- Karmondena Project (EZ-Kar), and it
intends to apply part of the proceeds of these grants to payments for goods, works, related non-
consulting and consulting services to be procured under this project.
PROJECT INFORMATION
Since 2016, there have been a significant number of Afghan refugees returning to the country. The
number of internally displaced within Afghanistan due to conflicts, droughts and mounting insecurity has
also risen significantly. Together the returnees and IDPs have concentrated in some provinces and
especially in some cities. The high influx of displaced populations in some areas has also added to the
pressures on the host communities on limited resources, public infrastructure and economic and
employment opportunities. The Project Development Objective (PDO) of the EZ-Kar is to strengthen the
enabling environment for economic opportunities in cities where there is a high influx of displaced people.
The EZ-Kar duration is from 2019 to 2023 (5 years), and includes a coverage/ target area of Afghan
refugees in Pakistan, and the cities of Kabul City (Kabul Province), Jalalabad (Nangarhar), Kandahar City
(Kandahar Province), Herat City (Herat Province), Puli Khumri (Baghlan), Maimana (Faryab), Ferozkoh/
Chaghcheran (Ghor), Khost Matun (Khost province), Asadabad (Kunar), Kunduz City (Kunduz Province),
Mehtarlam (Laghman), Parun (Nuristan), and Taloqan (Takhar). The EZ-Kar essentially includes the
following core components:
Component #1: Regional and National Integration of Displaced Persons, to be implemented by the
Ministry of Foreign Affairs (MOFA). It provides technical assistance, institutional support and training,
necessary equipment, and operational assistance to MoFA to: (a) enhance its capacity to provide
consular services (such as issuance of passports and verification of certificates); (b) develop and
implement a joint communication strategy for MoFA and MoRR to disseminate information to Afghan
refugees in Pakistan in order to facilitate their access to economic opportunities and social services
through information centers at MoFA missions in selected cities of Pakistan, in collaboration with MoRR;
and (c) support day-to-day implementation of this Component. Total budget = US$ 4.5 million.
Component #2: Short Term Employment Opportunities, Reforms and Market-Based Infrastructure, to be
implemented by the Independent Directorate of Local Governance (IDLG), via its urban Citizens’ Charter
Afghanistan Project’s Project Implementation Unit (CCAP PIU). This component includes essentially a
labor intensive, cash-for-work program (Maintenance and Construction Cash Grants) that targets poor
households as beneficiaries, providing enough labor and payments to sustain the poor households
through one lean season. Around 1,100 urban communities will be targeted with these MCCG grants of
US$ 27,000 each. This Component also includes the establishment of urban Gozar Assemblies (GAs)
and parallel Business Gozars (BGAs), each of which will receive a sum of US$ 200,000 for prioritized
market-based infrastructure development/support. This Component will cover 12 of the 13 prioritized
cities, except Kabul. Municipal-level regulatory reforms also fall under this Component. Total budget =
US$ 120.5 million.
Component #3: Prioritized Urban Investments in Four Provincial Capital Cities (PCCs), to be
implemented by the IDLG, via its City Investment Project’s Project Implementation Unit (CIP PIU). This
component will cover the cities of Jalalabad, Kandahar, Herat and Khost Matun. Performance grant
allocations for prioritized urban investments will be awarded against achievement of specific performance
criteria in three cycles. Four participating PCCs will receive 5 percent of the formula-based allocation
investment financing amount following the submittal of a “Municipal Investment Platform” (Cycle-1). The
remaining financing for investments will be distributed in two subsequent budgetary cycles awarded
based on the level of compliance by the municipality with the public financial management triggers. Total
budget =US$ 25 million.
Component #4: Market Based Infrastructure and Regulatory Reforms, to be implemented by the Kabul
Municipality (KM) for within its own coverage area. The KM will develop and implement several regulatory
reforms with the immediate focus on simplification of construction permits. Other reforms relevant to
Doing Business (DB) indicators will also be supported. The KM will identify “Priority Project” investments
through consultations with businesses. The funding for these investments will be released in three
tranches and will be conditional on meeting the regulatory reform triggers for this component. Total
budget = US$ 40 million.
Component #5: Red Carpet and Program Coordination, to be implemented by the Ministry of Economy
(MoEc). The first of its sub-components seeks to move the government from providing “red tape”
(bureaucratic/difficult processes) to providing a “red carpet” (an investor friendly way of operating) through
the provision of technical and operational assistance to MoEC for supporting national regulatory reforms
and feasibility assessment of business service centers in selected cities. Its second sub-component
mandates MoEC as responsible for inter-ministerial coordination within GoIRA for overall management
and project oversight across the IAs, for all aspects of the EZ-Kar. Total budget = US$ 10 million
PROCUREMENT NOTICE
This General Procurement Notice (GPN) is being issued by the MoEc (on behalf of all
Implementing Agencies) of the EZ-Kar, with regard to all procurement that will be undertaken
under the EZ-Kar Project.
All goods, works, non-consulting services and consulting services required for the Project and to be
financed out of the proceeds of the IDA/ARTF Grant(s) for EZ-Kar shall be procured in accordance with
the requirements set forth or referred to in the “World Bank Procurement Regulations for IPF Borrowers”
dated July 2016, revised November 2017 (“Procurement Regulations”), and the provisions of the
Recipient’s procurement plan for the Project (“Procurement Plan”) dated November 18, 2018 and the
same may be updated from time to time in agreement with the World Bank.
Specific procurement notices will be announced, as they become available, in the following websites: UN
Development Business, dgMarket, NPA website www.ppu.gov.af and in the local Newspapers. These
specific procurement notices will also be available in the website for the EZ-Kar that is expected to be set-
up shortly, and the websites of the relevant implementation agency:
MoEc: www.moec.gov.af; IDLG: www.idlg.gov.af; MOFA: www.mofa.gov.af; and KM: www.km.gov.af
At the time of publication of this GPN, the planned and approved major procurement activities for the EZ-
Kar include the following:
Consultancy Services:

 1. Firm: Feasibility Assessment for Business Service Support Centers in Select EZ-Kar Cities – MoEc
 2. Firm: Preparation of Communication/ Media Products for the EZ-Kar Visibility and Branding – MoEc
 3. Firm: Design, set-up, pilot and training of staff in a Project specific Management Information System
     (MIS)– MoEc
 4. Firm: Development of a National Regulatory Reform Plan
 5. Firm: Phased Impact Evaluation (baseline, mid-term, post-project completion) for select sub-
     components
 6. Firm: Independent Monitoring and Approving Agents
 7. Firm(s): NGOs to serve as Facilitating Partners (FPs) for EZ-Kar’s Component 2; total 5 packages
     proposed for 13 cities – IDLG
 8. Firm: Developing web-based GRM system – MoFA
 9. Firm: Developing and implementing a communication strategy targeting Afghan refugees in
     Pakistan – MoFA
 10. Firm: Managing helpline and manual development for the same – MoFA
 11. Firm: Development and training in municipal level construction permit reform plan – IDLG
 12. Firm: Identification, selection and screening of Component 3 projects – IDLG
 13. Firm: Feasibility and design of Component 3 projects – IDLG
 14. Firm: Construction supervision – IDLG
 15. _____________________________

Goods:

 1.   Office furniture: Varying packages by all IAs
 2.   IT and Office Equipment and Accessories: Varying packages by all IAs
 3.   Passport production equipment: MoFA
 4.   Fuel (vehicles and generators): Varying packages by all IAs
 5.   _________________________

Works:

 1. Market based infrastructure for gozar assemblies (GAs) and business gozar assemblies (BGAs) in
    12 cities– to be procured by the GAs and BGAs themselves using community based procurement
    method or by the IDLG if larger subprojects.
 2. Priority city investment infrastructure projects in 4 cities – IDLG
 3. Priority Kabul-based infrastructure projects – Kabul Municipality
 4. _________________________________________

Non-Consulting Services

 1.   Internet services: Varying packages by all IAs
 2.   Website-hosting: MoEC
 3.   Vehicle rentals: Varying packages by all IAs
 4.   Office space rentals: IDLG
PROCUREMENT
                              Afghanistan : Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project
PLAN
General Information
Country:                      Afghanistan                                  Bank’s Approval Date of the Original Procurement Plan:                    2019-08-28
                                                                                                                                      2020-09-16
                                                                           Revised Plan Date(s): (comma delineated, leave blank if none)
Project ID:                   P166127                                      GPN Date:                                                                 2018-12-22
Project Name:                 Afghanistan: Eshteghal Zaiee - Karmondena (EZ-Kar) Project
Loan / Credit No:             IDA / D4160
Executing Agency(ies): EZ-Kar KMDP-PIU




WORKS
                                                                                                                                                                                                                                                                                                                                                                                                          Bid Evaluation
Activity Reference No. /                                                                                                                                                                  Procurement       Estimated        Actual                                                                       Draft Bidding
                              Loan / Credit                                                                        Market         Procurement        Prequalification   High SEA/SH                                                       Process      Draft Pre-qualification    Prequalification                              Specific Procurement    Bidding Documents      Proposal Submission /        Report and                                      Contract
         Description                                 Component               Review Type       Method                                                                                      Document          Amount         Amount                                                                         Document /                                                                                                              Signed Contract
                                    No.                                                                           Approach           Process              (Y/N)             Risk                                                           Status           Documents            Evaluation Report                               Notice / Invitation         as Issued          Opening / Minutes      Recommendation for                                 Completion
                                                                                                                                                                                             Type                (US$)       (US$)                                                                        Justification
                                                                                                                                                                                                                                                                                                                                                                                                               Award
                                                                                                                                                                                                                                                        Planned      Actual      Planned     Actual   Planned       Actual      Planned      Actual     Planned     Actual      Planned     Actual     Planned       Actual      Planned      Actual   Planned


 EZ-KAR/W-02-MU /                             Market Enabling                                                                                                                                                                            Pending
                                                                                                                                Single Stage - One
Upgrading of Mandawi          IDA / D4160     Infrastructure and Reforms   Post            Request for Bids   Open - National                                                                               1,000,000.00         0.00    Implementat                                                  2020-04-01                2020-04-06                                     2020-05-18              2020-06-17                2020-07-22            2021-01-18
                                                                                                                                Envelope
Kabul                                         for Kabul Municipality                                                                                                                                                                     ion




 EZ-KAR/W-03-MU / Women                       Market Enabling                                                                                                                                                                            Pending
                                                                                                                                Single Stage - One
for Women Market (District-   IDA / D4160     Infrastructure and Reforms   Post            Request for Bids   Open - National                                                                               2,500,000.00         0.00    Implementat                                                  2020-04-30                2020-05-05                                     2020-06-16              2020-07-16                2020-08-20            2021-02-16
                                                                                                                                Envelope
2)                                            for Kabul Municipality                                                                                                                                                                     ion




 EZ-KAR/W-07-MU / Women                       Market Enabling                                                                                                                                                                            Pending
                                                                                                                                Single Stage - One
for Women Market (District-   IDA / D4160     Infrastructure and Reforms   Post            Request for Bids   Open - National                                                                               2,500,000.00         0.00    Implementat                                                  2020-09-30                2020-10-05                                     2020-11-16              2020-12-16                2021-01-20            2021-07-19
                                                                                                                                Envelope
8)                                            for Kabul Municipality                                                                                                                                                                     ion




 EZ-KAR/W-10-MU / Women                       Market Enabling                                                                                                                                                                            Pending
                                                                                                                                Single Stage - One
for Women Market (District-   IDA / D4160     Infrastructure and Reforms   Post            Request for Bids   Open - National                                                                               2,500,000.00         0.00    Implementat                                                  2020-09-05                2020-09-10                                     2020-10-22              2020-11-21                2020-12-26            2021-06-24
                                                                                                                                Envelope
11)                                           for Kabul Municipality                                                                                                                                                                     ion




 EZ-KAR/W-12-MU / Women                       Market Enabling                                                                                                                                                                            Pending
                                                                                                                                Single Stage - One
for Women Market (District-   IDA / D4160     Infrastructure and Reforms   Post            Request for Bids   Open - National                                                                               2,500,000.00         0.00    Implementat                                                  2020-09-10                2020-09-15                                     2020-10-27              2020-11-26                2020-12-31            2021-06-29
                                                                                                                                Envelope
12)                                           for Kabul Municipality                                                                                                                                                                     ion




GOODS
                                                                                                                                                                                                                                                                                                                                                                                  Bid Evaluation
Activity Reference No. /                                                                                                                                                                                                                                                            Draft Bidding
                              Loan / Credit                                                                        Market         Procurement        Prequalification    Estimated       Actual Amount           Process   Draft Pre-qualification        Prequalification                            Specific Procurement      Bidding Documents      Proposal Submission /        Report and
         Description                                 Component               Review Type       Method                                                                                                                                                                               Document /                                                                                                           Signed Contract         Contract Completion
                                    No.                                                                           Approach           Process              (Y/N)         Amount (US$)         (US$)               Status         Documents                Evaluation Report                             Notice / Invitation            as Issued         Opening / Minutes      Recommendation for
                                                                                                                                                                                                                                                                                    Justification
                                                                                                                                                                                                                                                                                                                                                                                       Award
                                                                                                                                                                                                                            Planned        Actual       Planned      Actual      Planned     Actual   Planned       Actual      Planned      Actual     Planned     Actual      Planned     Actual     Planned       Actual      Planned      Actual


 EZ-KAR/G-7 / Procurement
of IT Equepment for EZ-Kar                    Market Enabling                                                                                                                                               Under
                                                                                           Request for                          Single Stage - One
(Printer, Router Board,       IDA / D4160     Infrastructure and Reforms   Post                               Open - National                                                18,751.00               0.00   Implementati                                                                              2019-11-14   2019-11-20                                                                          2019-11-26                2019-12-06
                                                                                           Quotations                           Envelope
SUNKTAK Online UPS,                           for Kabul Municipality                                                                                                                                        on
Monitor...)




                                              Market Enabling
 EZ-KAR/G-4 / Office                                                                       Request for                          Single Stage - One
                              IDA / D4160     Infrastructure and Reforms   Post                               Open - National                                                 4,193.50          1,293.13    Signed                                                                                    2020-02-28                                                                                       2020-03-11   2020-07-14   2020-03-25
Furniture for EZ-Kar Team                                                                  Quotations                           Envelope
                                              for Kabul Municipality




 EZ-KAR/G-9 / IT                              Market Enabling
                                                                                           Request for                          Single Stage - One
Equipment requirement for     IDA / D4160     Infrastructure and Reforms   Post                               Open - National                                                12,910.00         11,391.85    Signed                                                                                    2020-03-03                                                                                       2020-04-28   2020-06-06   2020-10-25
                                                                                           Quotations                           Envelope
EZ-Kar staff                                  for Kabul Municipality




                                              Market Enabling
 EZ-KAR/G-11 / Wifi Router                                                                 Request for                          Single Stage - One
                              IDA / D4160     Infrastructure and Reforms   Post                               Open - National                                                 2,240.00          2,364.81    Signed                                                                                    2020-06-24                                                                                       2020-07-10   2020-07-08   2020-07-20
for EZ-Kar                                                                                 Quotations                           Envelope
                                              for Kabul Municipality




                                                                                                                                                                                                                                Page 1
                                              Market Enabling                                                                                                                                                  Pending
 EZ-KAR/G-14 / Survey                                                                      Request for                         Single Stage - One
                              IDA / D4160     Infrastructure and Reforms   Post                              Open - National                                                  908.01                    0.00   Implementati                                                                                 2020-07-30                                                                                      2020-09-03                2020-09-18
Equipment Requirements                                                                     Quotations                          Envelope
                                              for Kabul Municipality                                                                                                                                           on




NON CONSULTING SERVICES
                                                                                                                                                                                                                                                                                                                                                                                       Bid Evaluation
Activity Reference No. /                                                                                                                                                                                                                                                               Draft Bidding
                              Loan / Credit                                                                       Market         Procurement        Prequalification    Estimated         Actual Amount             Process   Draft Pre-qualification        Prequalification                               Specific Procurement      Bidding Documents      Proposal Submission /       Report and
        Description                                  Component               Review Type       Method                                                                                                                                                                                  Document /                                                                                                             Signed Contract         Contract Completion
                                    No.                                                                          Approach           Process              (Y/N)         Amount (US$)            (US$)                Status         Documents              Evaluation Report                                  Notice / Invitation          as Issued           Opening / Minutes      Recommendation for
                                                                                                                                                                                                                                                                                       Justification
                                                                                                                                                                                                                                                                                                                                                                                           Award
                                                                                                                                                                                                                               Planned       Actual      Planned       Actual      Planned      Actual       Planned      Actual      Planned    Actual       Planned     Actual     Planned    Actual      Planned       Actual      Planned      Actual


 EZ-KAR/G-8 / Request for
Quotation for Geo-Technical                   Market Enabling
                                                                                           Request for                         Single Stage - One
Soil Investigation of Women   IDA / D4160     Infrastructure and Reforms   Post                              Open - National                                                15,272.00               7,563.62   Signed                                                                                       2019-12-14   2020-01-05                                                                         2019-12-27   2020-03-05   2020-02-25
                                                                                           Quotations                          Envelope
for Women Market of                           for Kabul Municipality
District-12 Kabul City




CONSULTING FIRMS
Activity Reference No. /                                                                                                                                                                                                                                                                                                                                                Combined Evaluation
                              Loan / Credit                                                                       Market        Contract Type         Estimated           Actual                                                            Expression of Interest Short List and Draft Request for Proposals Opening of Technical                    Evaluation of
        Description                                  Component               Review Type        Method                                                                                    Process Status        Terms of Reference                                                                                                                                        Report and Draft         Signed Contract       Contract Completion
                                    No.                                                                          Approach                           Amount (US$)       Amount (US$)                                                                 Notice           Request for Proposals             as Issued         Proposals / Minutes     Technical Proposal
                                                                                                                                                                                                                                                                                                                                                                         Negotiated Contract
                                                                                                                                                                                                                Planned         Actual       Planned      Actual       Planned     Actual      Planned        Actual     Planned      Actual    Planned       Actual     Planned     Actual    Planned       Actual      Planned       Actual


 EZ-KAR/CS-01/QCBS /
                                              Market Enabling
Hiring firm for Preparation                                                                Quality And Cost- Open -                                                                       Pending
                              IDA / D4160     Infrastructure and Reforms   Post                                                                           234,000.00               0.00                         2020-06-30                  2020-07-21                2020-09-03                                         2020-10-01             2020-10-31              2020-12-05             2021-01-09                2021-05-24
of Detailed Design                                                                         Based Selection   International                                                                Implementation
                                              for Kabul Municipality
Documentation




INDIVIDUAL CONSULTANTS
Activity Reference No. /                                                                                                                                                                                                                        Invitation to
                              Loan / Credit                                                                       Market        Contract Type         Estimated           Actual                                                                                        Draft Negotiated
        Description                                  Component               Review Type        Method                                                                                    Process Status        Terms of Reference            Identified/Selected                                Signed Contract         Contract Completion
                                    No.                                                                          Approach                           Amount (US$)       Amount (US$)                                                                                         Contract
                                                                                                                                                                                                                                                 Consultant
                                                                                                                                                                                                                Planned         Actual       Planned      Actual       Planned     Actual      Planned        Actual     Planned      Actual