The World Bank Report No: ISR16512 Implementation Status & Results China China-Second Liaoning Medium Cities Infrastructure Project (P092618) Public Disclosure Copy Operation Name: China-Second Liaoning Medium Cities Infrastructure Project Project Stage: Implementation Seq.No: 9 Status: ARCHIVED Archive Date: 08-Dec-2014 (P092618) Country: China Approval FY: 2007 Product Line: IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Lioning Urban Construction and Renewal Project Office Key Dates Board Approval Date 26-Jun-2007 Original Closing Date 31-Dec-2013 Planned Mid Term Review Date Last Archived ISR Date 25-Jun-2014 Effectiveness Date 04-Dec-2007 Revised Closing Date 31-Dec-2014 Actual Mid Term Review Date 18-Oct-2010 Project Development Objectives China-Second Liaoning Medium Cities Infrastructure Project (P092618) Project Development Objective (from Project Appraisal Document) The project development objective is to improve the performance and sustainability of water supply, wastewater, and solid waste services in the LMC-2 cities. Enhanced wastewater and solid waste services will also help reduce pollution into the Bohai Sea and contribute to improving Bohai Sea water quality. Has the Project Development Objective been changed since Board Approval of the Program? Yes No China-GEF-Liaoning (P090375) Global Environmental Objective (from Project Appraisal Document) The global environmental objective of the LMC-2 project with the GEF enhancements is the reduction of land-based pollution into the Bohai Sea through investments in wastewater and solid waste infrastructure and improved utility regulation, planning and management in the LMC-2 cities and throughout Liaoning Province. Has the Global Environmental Objective been changed since Board Approval of the Program? Yes No Public Disclosure Copy Component(s) Component Name Component Cost Wastewater Infrastructure 157.44 Water Supply Infrastructure 172.24 Solid Waste Management Infrastructure 84.39 Institutional Development 6.70 Overall Ratings Page 1 of 7 The World Bank Report No: ISR16512 Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Progress towards achievement of GEO Moderately Satisfactory Moderately Satisfactory Public Disclosure Copy Overall Implementation Progress (IP) Moderately Satisfactory Moderately Unsatisfactory Overall Risk Rating Implementation Status Overview A significant percentage (64%) of the physical works has been satisfactorily completed, and currently operational and delivering benefits to target population. Another 23% are substantially complete and will be operational before the current closing date of December 31, 2104. An extension of the closing date to April 30, 2015 would be needed to complete the remaining 13%. Some of the key achievements to date include: (i) increasing clean water supply by 190,000 tons per day for Yingkou and Anshan, benefiting a population of approximately 1.1 million; (ii) completing three new wastewater treatment plants with a combined capacity of 250,000 tons per day in Yingkou, Panjin and Gaizhou, benefiting nearly 1.8 million with nearly 15,600 tons of biochemical oxygen pollution load reduction in 2013 that otherwise would have gone into the Bohai Sea; (iii) increasing modern sanitary landfill capacity by 1,400 ton per year in Fushun. These achievements far exceed the project targets. In addition the project successfully completed: (i) upgrading and installing 580 km of water supply networks; (iii) upgrading and installing about 130 km of main sewers lines; (iv) implementing active Non-Revenue Water programs in five cities; and (v) improving cost recovery trends and installing satisfactory asset management plans in all participating water utilities. The project is also piloting a program that extends and integrates solid waste collection and disposal services into peri-urban communities around Panjin. With respect to the GEF Grant, three activities have been satisfactorily completed. The remaining 7 activities are progressing satisfactorily and expected to be completed before the closing date of December 31, 2014. Locations Country First Administrative Division Location Planned Actual China Liaoning Yingkou Shi ✔ ✔ China Liaoning Xingcheng Shi ✔ ✔ China Liaoning Panjin Shi ✔ ✔ China Liaoning Haicheng Shi ✔ ✔ China Liaoning Gaizhou Shi ✔ ✔ Public Disclosure Copy China Liaoning Fushun Shi ✔ ✔ China Liaoning Anshan Shi ✔ ✔ Results Project Development Objective Indicators Page 2 of 7 The World Bank Report No: ISR16512 Indicator Name Core Unit of Measure Baseline Current End Target Wastewater Utility Cost Recovery Ratio for 4 Text Value Yingkou 1.0 Panjin 0.6 Yingkou 0.99; Panjin 0.88; Yingkou 1.0; Panjin 1.0; cities Fushun 0.5 Gaizhou 0.0 Gaizhou 1.0 Fushun 1.0; Gaizhou 1.0 Public Disclosure Copy Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data from the June 2014 semi- annual progress report. The next update will be in December 2014. Water Supply Utility Cost Recovery Ratio for 5 Text Value Yingkou 0.9 Panjin 0.8 Yingkou 0.77; Panjin 0.09; Yingkou 1.0; Panjin 1.0; cities Anshan 1.0 Haicheng 0.8 Anshan 0.84; Haicheng 0.8 Anshan 1.0; Haicheng 1.0 Xingcheng 0.9 Xingcheng 1.0; Fushun 1.0 Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data from the June 2014 semi- annual progress report. The next update will be in December 2014. Solid Waste Disposed in Landfill (tons/day) in 3 Text Value Yingkou ETZ 0 Panjin 0 Panjin 550; Fushun 1150 Panjin 450 Fushun 600 cities Fushun 0 Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data Panjin’s landfill was financed from the June 2014 semi- with alternative funds so it will annual progress report. The be dropped; Yingkou is next update will be in dropping its SWM component. December 2014. Direct project beneficiaries Number Value 0.00 2900000.00 5100000.00 Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data The total urban population in from the June 2014 semi- target cities (in the PAD). annual progress report. The Public Disclosure Copy next update will be in December 2014. Female beneficiaries Percentage Value 0.00 46.10 50.00 Sub Type Supplemental Global Environmental Objective Indicators Page 3 of 7 The World Bank Report No: ISR16512 Indicator Name Core Unit of Measure Baseline Current End Target New Wastewater Treatment Plant BOD Text Value 0 15643 5750 removal (tons/year) in 4 cities Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Public Disclosure Copy Comments The values above reflect data Target was revised in the from the June 2014 semi- April 2014 restructuring. annual progress report. The next update will be in December 2014. New wastewater treatment plant total nitrogen Tones/year Value 0.00 3596.00 1100.00 (TN) removal (ton/year) in 4 cities Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data Target was revised in the from the June 2014 semi- April 2014 restructuring. annual progress report. The next update will be in December 2014. New wastewater treatment plant total Tones/year Value 0.00 532.00 210.00 phosphorus (TP) removal (ton/year) in 4 cities Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data from the June 2014 semi- annual progress report. The next update will be in December 2014. Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target WWTP Capacity (m3/day) Text Value 450000 700000 650000 Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data from the June 2014 semi- annual progress report. The Public Disclosure Copy next update will be in December 2014. Total new or rehabilitated drainage pipelines Text Value 0 130 145 (km) Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data from the June 2014 semi- annual progress report. The next update will be in December 2014. Page 4 of 7 The World Bank Report No: ISR16512 Number of new or rehabilitated pipelines for Kilometers Value 0.00 5875.00 440.00 water supply Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data Target was revised in the Public Disclosure Copy from the June 2014 semi- April 2014 restructuring. annual progress report. The next update will be in December 2014. Number of Water Meters installed (each) Text Value 0 82568 145000 Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data Target was revised in the from the June 2014 semi- April 2014 restructuring. annual progress report. The next update will be in December 2014. Industrial and municipal waste disposal Metric ton Value 0.00 2000.00 1050.00 capacity created under the project Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data Yingkou is dropped out of the from the June 2014 semi- project’s solid waste annual progress report. The component. next update will be in December 2014. Training for Public Utility Program (Man-days) Text Value 0 49 100 Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data from the June 2014 semi- annual progress report. The next update will be in December 2014. Solid Waste Master Plans completed Text Value 0 0 Fushun, Yingkou, Gaizhou and Panjin Public Disclosure Copy Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data from the June 2014 semi- annual progress report. The next update will be in December 2014. Solid Waste and Wastewater Master Plans Text Value 0 0 Panjin and Gaizhou Completed Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data from the June 2014 semi- Page 5 of 7 The World Bank Report No: ISR16512 annual progress report. The next update will be in December 2014. Number of water utilities that the project is Number Value 0.00 6.00 6.00 Public Disclosure Copy supporting Date 31-Dec-2006 30-Sep-2014 31-Dec-2014 Comments The values above reflect data from the June 2014 semi- annual progress report. The next update will be in December 2014. Data on Financial Performance (as of 19-Jun-2014) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P092618 IBRD-48640 Effective 26-Jun-2007 19-Sep-2007 04-Dec-2007 31-Dec-2013 31-Dec-2014 P090375 TF-57757 Effective 19-Sep-2007 19-Sep-2007 19-Sep-2007 31-Dec-2013 31-Dec-2014 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P092618 IBRD-48640 Effective USD 173.00 173.00 0.00 114.29 58.71 66.00 P090375 TF-57757 Effective USD 173.00 5.00 0.00 2.49 2.51 50.00 Disbursement Graph Public Disclosure Copy Page 6 of 7 The World Bank Report No: ISR16512 Public Disclosure Copy Key Decisions Regarding Implementation The extension of the closing date is under consideration by the Bank management. Restructuring History Level 2 CD Decision on 30-Dec-2013, Level 2 CD Decision on 04-Apr-2014 Related Projects P090375-China-GEF-Liaoning Public Disclosure Copy Page 7 of 7