Procurement Plan (Text Part) Bangladesh Weather and Climate Services Regional Project (BWCSRP) Agency: Bangladesh Meteorological Department (BMD) Bangladesh Water Development Board Department of Agricultural Extension I. General 1. Bank’s approval Date of the procurement Plan: June 15, 2017 2. Date of General Procurement Notice: July 10, 2017 3. Period covered by this procurement plan: The procurement period of project covered from July 2016 to June 2022. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank: Procurement Prior Review Thresholds (US$ millions) (Procurement Activity) Type of Procurement High risk Substantial risk Moderate risk Low risk Works (including turnkey, supply & 5 10 15 20 installation of plant and equipment, and PPP) Goods, information technology and non- 1.5 2 4 6 consulting services Notes: 1. All contracts at or above the mandatory procurement prior review thresholds are subject to international advertising; 2. Use of Standard Procurement Documents: For all procurements under the project, the Bank’s Standard Procurement Documents (or other documents agreed with the Bank) shall be used; 3. Request for Bids (Open-National), if allowed in the Procurement Plan, will be carried out under the Bank’s Procurement Guidelines following procedures for Open Tendering Method (OTM) of the People’s Republic of Bangladesh (Public Procurement Act 2006 – PPA, 1st amendment to PPA (2009) and The Public Procurement Rules 2008, as amended in August 2009) using standard/model bidding documents satisfactory to the Bank. For the purpose of Request for Bids (Open-National) the following shall apply: a. Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; b. Bids should be submitted and opened in public in one location immediately after the deadline for submission; c. Lottery in award of contracts shall not be allowed; d. Bidders’ qualification/experience requirement shall be mandatory; e. Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost and contract award shall be based on the lowest evaluated bid price of compliant bid from eligible and qualified bidder; and f. Single-stage two-envelope procurement system shall not be allowed. 2. Prequalification. Not Applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable. 4. Reference to (if any) Project Operational/Procurement Manual: A Project Operational Manual will be prepared. 5. Any Other Special Procurement Arrangements: Not Applicable. 6. Summary of the Procurement Packages: [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Estimated Domestic Review Ref. Description Cost Packages Preference by Bank Comments No. US$ million (yes/no) (Prior / Post) Summary of contracts 55.51 12 Yes/ No Prior that will be let under RFB (Goods, Works and Non-Consulting Services) (Prior Review) Summary of contracts 31.67 63 Yes/ No Post that will be let under RFB (Goods, Works and Non-Consulting Services) (Post Review) Summary of contracts 0.04 7 No Post that will be let under RFQ (Goods, Works and Non-Consulting Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank: Procurement Prior Review Thresholds (US$ millions) (Procurement Activity) Type of Procurement High risk Substantial risk Moderate risk Low risk Consultants: firms 0.5 1 2 4 Consultants: 0.2 0.3 0.4 0.5 Individual 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ (Prior / million Post) Summary of number 1.64 1 Prior of contracts that will be let under QCBS (Prior Review) Summary of number 2.54 9 Post of contracts that will be let under QCBS (Post Review) Summary of number 3.29 1 Prior of contracts that will be let under other methods (QBS, FBS, CQS, LCS, Direct Selection) (Prior Review) Summary of number 2.51 19 Post of contracts that will be let under other methods (QBS, FBS, CQS, LCS, Direct Selection) (Post Review) Summary of number 1.53 7 Prior of contracts that will be let under SIC (Prior Review) Summary of number 1.55 15 Post of contracts that will be let under SIC (Post Review) PROCUREMENT Bangladesh : Bangladesh Weather and Climate Services Regional Project PLAN General Information Country: Bangladesh Banks Approval Date of the Original Procurement Plan: 2017-03-29 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-11-21 Project ID: P150220 GPN Date: 2017-07-10 Project Name: Bangladesh Weather and Climate Services Regional Project Loan / Credit No: IDA / Q9970, IDA / 58370 Executing Agency(ies): Bangladesh Meteorological Department, Department of Agricultural Extension, Bangladesh Water Development Board WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component C- Agro- DAE-W1 / Refurbishing and Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 150,000.00 0.00 2017-07-02 2017-07-07 2017-08-06 2017-09-25 2017-11-06 2018-05-05 setting up of VC Room Envelope Implementation Systems Development DAE-W2 / Refurbishment of Component C- Agro- Single Stage - One Pending district level agrometerological IDA / 58370 Meteorological Information Post Request for Bids Open - National 150,000.00 0.00 2017-07-02 2017-08-01 2017-09-30 2017-10-30 2017-12-11 2018-06-09 Envelope Implementation service room (64 districts) Systems Development Component C- Agro- Single Stage - One Pending DAE-W3 / Lighting and wiring IDA / 58370 Meteorological Information Post Request for Bids Open - National 121,343.17 0.00 2017-04-21 2017-04-26 2017-06-07 2017-07-07 2017-08-11 2018-02-07 Envelope Implementation Systems Development Component C- Agro- DAE-W4 / Office premises repair Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 103,027.22 0.00 2017-04-20 2017-04-25 2017-06-06 2017-07-06 2017-08-10 2018-02-06 and maintenance Envelope Implementation Systems Development Component C- Agro- DAE-W5 / Other repair and Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 14,614.60 0.00 2017-04-14 2017-04-19 2017-05-31 2017-06-30 2017-08-04 2018-01-31 maintenance Envelope Implementation Systems Development BMD-W1 / Refurbishing Component A- Strengthening Single Stage - One Pending meteorology offices at HQ and 6 IDA / 58370 Meteorological Information Post Request for Bids Open - National 1,600,000.00 0.00 2017-12-11 2017-12-16 2018-01-27 2018-02-26 2018-04-02 2020-03-22 Envelope Implementation divisional offices (P1) Services Component B- Strengthening BWDB-W1 / Procurement of Hydrological Information Single Stage - One Pending Refurshibing HQ and Division IDA / 58370 Post Request for Bids Open - National 1,671,025.00 0.00 2017-11-23 2017-11-28 2017-12-26 2018-01-16 2018-02-27 2019-02-27 Services and Early Warning Envelope Implementation level hydrology offices Work Systems BWDB-W2 / Procument of Component B- Strengthening Supply and installation of New Hydrological Information Single Stage - One Pending Ground water nests in coastal IDA / 58370 Post Request for Bids Open - National 830,000.00 0.00 2018-02-08 2018-02-13 2018-03-27 2018-04-26 2018-05-31 2019-05-31 Services and Early Warning Envelope Implementation region and hotspot areas Systems including Dhaka Work Component B- Strengthening BWDB-W3 / Construction of Hydrological Information Single Stage - One Pending Training center for Hydrological IDA / 58370 Post Request for Bids Open - National 1,000,000.00 0.00 2018-07-02 2018-07-07 2018-08-18 2018-09-17 2018-10-22 2019-10-22 Services and Early Warning Envelope Implementation Equipment operation Systems GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A- Strengthening BMD-PPF-G1 / Supply of Request for Single Stage - One Under IDA / Q9970 Meteorological Information Post Open - National 2,544.00 2,400.24 2016-08-21 2016-09-12 2016-09-26 Stationery Quotations Envelope Implementation Services BMD-PPF-G2 / Supply of Office Component A- Strengthening Request for Single Stage - One Under Equipment (Computer, Printer, IDA / Q9970 Meteorological Information Post Open - National 5,724.00 0.00 2016-08-21 2016-09-12 2016-09-26 Quotations Envelope Implementation Scanner & Photocopier) Services Component A- Strengthening BMD-PPF-G3 / Procurement of Request for Single Stage - One Under IDA / 58370 Meteorological Information Post Open - National 3,816.00 0.00 2016-09-04 2016-09-26 2016-10-10 Furniture Quotations Envelope Implementation Services DAE-G1 / ICT Equipment for Component C- Agro- Single Stage - One Pending Bangladesh Agrometeorological IDA / 58370 Meteorological Information Post Request for Bids Open - International 921,063.34 0.00 2017-06-26 2017-07-01 2017-08-12 2017-10-11 2017-11-22 2018-05-21 Envelope Implementation Information System (BAMIS) Systems Development DAE-G3 / Purchase of Agromet Component C- Agro- Single Stage - One Pending Display boards for 4051 Union IDA / 58370 Meteorological Information Post Request for Bids Open - National 977,995.42 0.00 2017-04-30 2017-05-05 2017-06-04 2017-07-14 2017-08-25 2018-02-21 Envelope Implementation Parishads Systems Development Component C- Agro- DAE-G4 / Purchase of handheld Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - International 977,995.42 0.00 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 ARGs for Union Parishads Envelope Implementation Systems Development Component C- Agro- DAE-G5 / Agrometeorological Single Stage - One Pending IDA / 58370 Meteorological Information Prior Request for Bids Open - International 3,000,000.00 0.00 2017-02-28 2017-03-05 2017-04-16 2017-06-15 2017-07-27 2018-01-23 kiosks for the 487 Upzillas Envelope Implementation Systems Development Component C- Agro- DAE-G6 / Procurement of 6664 Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 15,988.30 0.00 2016-12-05 2016-12-10 2017-01-09 2017-02-08 2017-03-22 2017-09-18 SIM cards Envelope Implementation Systems Development Component C- Agro- DAE-G7 / BARI/BRRI/BSRI/BJRI Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 96,769.27 0.00 2017-03-30 2017-04-04 2017-05-04 2017-06-23 2017-08-04 2018-01-31 Instrumentation Envelope Implementation Systems Development Component C- Agro- DAE-G8 / ICT Equipment for Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 4,324.60 0.00 2017-03-22 2017-03-27 2017-04-26 2017-05-26 2017-07-07 2018-01-03 office (camera) Envelope Implementation Systems Development Page 1 DAE-G9 / ICT Equipment for Component C- Agro- Single Stage - One Pending Office (desktop computer, printer, IDA / 58370 Meteorological Information Post Request for Bids Open - National 15,136.10 0.00 2017-03-30 2017-04-04 2017-05-02 2017-06-01 2017-07-13 2017-09-11 Envelope Implementation Laptop) Systems Development Component C- Agro- DAE-G12 / Instant Power Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 24,026.97 0.00 2017-04-18 2017-04-23 2017-05-23 2017-06-22 2017-08-03 2017-10-02 Supply (IPS) System etc. Envelope Implementation Systems Development Component C- Agro- Single Stage - One Pending DAE-G11 / Office Furniture IDA / 58370 Meteorological Information Post Request for Bids Open - National 45,840.75 0.00 2017-03-14 2017-03-19 2017-04-18 2017-05-18 2017-06-29 2017-08-28 Envelope Implementation Systems Development DAE-G10 / Equipment for Component C- Agro- Single Stage - One Pending district offices (64 districts and IDA / 58370 Meteorological Information Post Request for Bids Open - National 148,639.02 0.00 2017-04-05 2017-04-10 2017-05-10 2017-06-09 2017-07-21 2017-11-18 Envelope Implementation HQ) Systems Development Component C- Agro- DAE-G13 / Procurement of Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 1,017,145.76 0.00 2017-04-05 2017-04-10 2017-05-10 2017-06-29 2017-08-10 2018-02-06 Tablet Computer for 6664 SAAOs Envelope Implementation Systems Development Component C- Agro- Single Stage - One Pending DAE-G14 / Data for Tabs IDA / 58370 Meteorological Information Post Request for Bids Open - National 508,572.88 0.00 2017-05-08 2017-05-13 2017-06-24 2017-07-24 2017-08-28 2018-02-24 Envelope Implementation Systems Development BMD-G3 / Supply and Component A- Strengthening Installation of Coastal Marine Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - International 660,000.00 0.00 2018-03-04 2018-03-09 2018-04-20 2018-05-20 2018-06-18 2018-12-11 Automated Network (CMAN) Envelope Implementation Services including softwares BMD-G6 / Procurement of Component A- Strengthening Single Stage - One Pending calibration system for IDA / 58370 Meteorological Information Post Request for Bids Open - International 360,000.00 0.00 2018-03-06 2018-03-11 2018-04-22 2018-05-22 2018-06-26 2018-12-23 Envelope Implementation Meteorological Sensors Services Component A- Strengthening BMD-G9 / Procurement of GIS Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 120,000.00 0.00 2018-03-05 2018-04-04 2018-05-04 2018-07-03 2018-09-16 2019-03-15 software Envelope Implementation Services BMD-G10 / Procurement of data Component A- Strengthening Single Stage - One Pending sharing software to share info IDA / 58370 Meteorological Information Post Request for Bids Open - National 240,000.00 0.00 2018-03-05 2018-03-10 2018-04-21 2018-05-21 2018-06-27 2018-12-24 Envelope Implementation between BMD and stakeholders Services BMD-G11 / Procurement of Component A- Strengthening Common Alerting Protocol (CAP) Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 240,000.00 0.00 2018-03-06 2018-03-11 2018-04-22 2018-05-22 2018-06-28 2018-12-25 hardware for Disaster Envelope Implementation Services Management BMD-G13 / Supply and Component A- Strengthening Single Stage - One Pending Installation of Nowcasting IDA / 58370 Meteorological Information Post Request for Bids Open - International 840,000.00 0.00 2018-03-07 2018-03-12 2018-04-23 2018-05-23 2018-06-28 2018-12-25 Envelope Implementation workstations and softwares Services Component A- Strengthening BMD-G14 / Procurement of High Single Stage - One Pending IDA / 58370 Meteorological Information Prior Request for Bids Open - International 3,512,400.00 0.00 2018-07-01 2018-07-06 2018-08-19 2018-09-18 2018-10-29 2019-04-27 Performance Computer Envelope Implementation Services Component A- Strengthening Single Stage - One Pending BMD-G15 / Office Furniture IDA / 58370 Meteorological Information Post Request for Bids Open - National 540,000.00 0.00 2017-07-02 2017-07-07 2017-08-18 2017-09-17 2017-10-22 2018-04-20 Envelope Implementation Services BMD-G1 / Supply and Component A- Strengthening Installation of Automatic Weather Single Stage - One Pending IDA / 58370 Meteorological Information Prior Request for Bids Open - International 7,800,000.00 0.00 2018-07-15 2018-07-19 2018-08-30 2018-09-30 2018-11-05 2019-05-02 Stations (AWS) and Automatic Envelope Implementation Services Raingauges Component A- Strengthening Single Stage - One Pending BMD-G16 / Consumable Stores IDA / 58370 Meteorological Information Post Request for Bids Open - National 152,632.92 0.00 2018-04-15 2018-04-19 2018-05-31 2018-07-01 2018-08-05 2019-01-31 Envelope Implementation Services BMD-G8 / Procurement of ICT, Component A- Strengthening Single Stage - One Pending Data Center and IDA / 58370 Meteorological Information Prior Request for Bids Open - International 5,800,000.00 0.00 2019-07-15 2019-07-21 2019-09-01 2019-10-01 2019-11-05 2020-05-03 Envelope Implementation Communications Equipment Services BMD-G12 / Supply and Component A- Strengthening Single Stage - One Pending installation of Weather IDA / 58370 Meteorological Information Post Request for Bids Open - International 1,176,000.00 0.00 2018-03-06 2018-04-05 2018-05-20 2018-07-19 2018-10-17 2019-04-15 Envelope Implementation Workstations and softwares Services BMD-G2 / Supply and Component A- Strengthening Single Stage - One Pending Installation of Aviation Weather IDA / 58370 Meteorological Information Post Request for Bids Open - International 1,620,000.00 0.00 2018-04-15 2018-04-22 2018-06-03 2018-07-03 2018-08-07 2019-02-03 Envelope Implementation Observing System (AWOS) Services BMD-G4 / Supply and Component A- Strengthening Single Stage - One Pending Installation of Moored Buoy IDA / 58370 Meteorological Information Post Request for Bids Open - International 1,440,000.00 0.00 2018-03-04 2018-03-08 2018-04-19 2018-05-20 2018-06-24 2018-12-20 Envelope Implementation System Services BMD-G5 / Supply and Component A- Strengthening Single Stage - One Pending Installation of Portable Hydrogen IDA / 58370 Meteorological Information Post Request for Bids Open - International 1,320,000.00 0.00 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 Envelope Implementation Generators Services BMD-G7 / Supply and Component A- Strengthening Installation of XC-Band Weather Single Stage - One Pending IDA / 58370 Meteorological Information Prior Request for Bids Open - International 9,000,000.00 0.00 2018-04-15 2018-04-22 2018-06-03 2018-07-03 2018-08-07 2019-02-03 Radar including software and Envelope Implementation Services training Component A- Strengthening BMD-G19 / Stationery Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 152,632.92 0.00 2017-08-07 2017-08-13 2017-09-24 2017-10-24 2017-11-27 2021-06-30 (Framework Agreement) Envelope Implementation Services BWDB-G1 / Procurement of Component B- Strengthening Upgrade ground water stations Hydrological Information Single Stage - One Pending IDA / 58370 Prior Request for Bids Open - International 3,631,773.00 0.00 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-08-06 2019-08-06 and nests from manual to Services and Early Warning Envelope Implementation automatic and new stations Systems BWDB-G2 / Procurement of Component B- Strengthening Automatic Water Level Stations Hydrological Information Single Stage - One Pending and Upgrade existing 3 climate IDA / 58370 Prior Request for Bids Open - International 9,411,930.81 0.00 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-08-06 2019-08-06 Services and Early Warning Envelope Implementation stations and 257 rain guages to Systems automatic and real time. Page 2 Component B- Strengthening BWDB-G3 / Procurement of Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 743,996.44 0.00 2017-09-28 2017-10-03 2017-10-31 2017-11-15 2017-12-20 2018-02-18 Catamarans and Survey Boats Services and Early Warning Envelope Implementation Systems Component B- Strengthening BWDB-G4 / Procurement of Hydrological Information Single Stage - One Pending Equipment s for hydrological IDA / 58370 Post Request for Bids Open - National 1,200,000.00 0.00 2017-09-28 2017-10-03 2017-10-31 2017-11-14 2017-12-19 2018-02-17 Services and Early Warning Envelope Implementation survey Systems BWDB-G5 / Procurement of Component B- Strengthening Systems for Morphological Hydrological Information Single Stage - One Pending survey ( Ecosounder,Total IDA / 58370 Post Request for Bids Open - International 1,800,000.00 0.00 2017-09-28 2017-10-03 2017-11-14 2017-12-14 2018-01-18 2018-03-19 Services and Early Warning Envelope Implementation Station,DGPS,Real Time Systems Kinematic GPS etc.) Component B- Strengthening BWDB-G6 / Coastal Flood Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - International 959,997.46 0.00 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2019-04-03 Monitoring Stations Services and Early Warning Envelope Implementation Systems Component B- Strengthening BWDB-G7 / Procurement of Lab Hydrological Information Single Stage - One Pending and field equipment and IDA / 58370 Post Request for Bids Open - National 240,002.50 0.00 2018-10-04 2018-10-06 2018-11-03 2018-11-17 2018-12-22 2019-02-05 Services and Early Warning Envelope Implementation accessories Systems Component B- Strengthening BWDB-G8 / Procurement of Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 60,000.00 0.00 2018-06-14 2018-06-19 2018-07-19 2018-07-29 2018-09-02 2018-10-02 Supply of Calibration goods Services and Early Warning Envelope Implementation Systems BWDB-G9 / procurement of Component B- Strengthening nowcasting workstations for short Hydrological Information Single Stage - One Pending lead time events and IDA / 58370 Post Request for Bids Open - International 360,000.00 0.00 2018-02-08 2018-02-13 2018-03-27 2018-04-26 2018-05-31 2018-11-27 Services and Early Warning Envelope Implementation development of flash flood Systems forecasts BWDB-G10 / Procurement of Component B- Strengthening ICT and communication Hydrological Information Single Stage - One Pending hardware: including, computers, IDA / 58370 Post Request for Bids Open - National 1,202,111.00 0.00 2018-04-05 2018-04-10 2018-05-08 2018-05-22 2018-07-03 2018-09-01 Services and Early Warning Envelope Implementation related systems for 13 VC Systems stations Component B- Strengthening BWDB-G11 / Procurement of Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 311,994.40 0.00 2017-09-28 2017-10-03 2017-10-31 2017-11-11 2017-12-09 2018-01-23 Cross country vehicle Services and Early Warning Envelope Implementation Systems Component B- Strengthening BWDB-G12 / Procurement of Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 89,939.00 0.00 2017-09-28 2017-10-03 2017-10-14 2017-11-11 2017-12-09 2018-01-23 Double cabin pick-up Services and Early Warning Envelope Implementation Systems Component B- Strengthening BWDB-G13 / Procurement of Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 102,060.00 0.00 2017-09-28 2017-10-03 2017-10-31 2017-11-14 2017-12-26 2018-02-09 Motorcycles Services and Early Warning Envelope Implementation Systems Component B- Strengthening BWDB-G14 / Procurement of Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 60,000.00 0.00 2018-02-15 2018-02-20 2018-03-13 2018-03-23 2018-04-27 2018-06-11 GIS software Services and Early Warning Envelope Implementation Systems Component B- Strengthening BWDB-G15 / Procurement of Hydrological Information Single Stage - One Pending Purchase of GIS/Satellite images IDA / 58370 Post Request for Bids Open - National 523,764.00 0.00 2018-02-08 2018-02-13 2018-03-13 2018-03-27 2018-05-08 2018-06-22 Services and Early Warning Envelope Implementation and DEM Systems BWDB-G16 / procurement of Component B- Strengthening data and information sharing Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - International 180,000.00 0.00 2018-02-08 2018-02-13 2018-03-27 2018-04-26 2018-05-31 2018-11-27 software to share info between Services and Early Warning Envelope Implementation BWDB and stakeholders Systems Component B- Strengthening BWDB-G20 / Procurement of Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 104,300.00 0.00 2017-09-14 2017-09-19 2017-10-10 2017-10-17 2017-11-21 2017-12-06 IPS & Electrical equipments Services and Early Warning Envelope Implementation Systems Component B- Strengthening BWDB-G18 / Procurement of Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 72,717.00 0.00 2017-12-17 2017-12-21 2018-01-11 2018-01-18 2018-02-01 2018-02-16 Office Equipment Services and Early Warning Envelope Implementation Systems Component B- Strengthening BWDB-G19 / Procurement of Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 46,744.00 0.00 2017-12-17 2017-12-21 2018-01-11 2018-01-18 2018-02-01 2018-02-16 Office Furniture Services and Early Warning Envelope Implementation Systems Component C- Agro- DAE-G2 / Vehicles: Two double Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 143,233.27 0.00 2017-11-15 2017-11-20 2018-01-01 2018-01-31 2018-03-14 2018-04-10 cabin pickup with canopy Envelope Implementation Systems Development NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A- Strengthening BMD-PPF-NS1 / Hiring of Request for Single Stage - One Under IDA / Q9970 Meteorological Information Post Open - National 3,816.00 0.00 2016-08-21 2016-09-15 2016-12-31 Vehicle Quotations Envelope Implementation Services Component A- Strengthening BMD-PPF-NS2 / Basic Request for Single Stage - One Under IDA / Q9970 Meteorological Information Post Open - National 6,360.00 0.00 2016-08-28 2016-09-20 2016-10-06 Database Training (SQL/Oracle) Quotations Envelope Implementation Services Page 3 Component A- Strengthening BMD-PPF-NS3 / Basic Request for Single Stage - One Under IDA / Q9970 Meteorological Information Post Open - National 6,360.00 0.00 2016-08-28 2016-09-20 2016-10-06 Networking Training (Cisco) Quotations Envelope Implementation Services BMD-PPF-NS4 / Microsoft Component A- Strengthening Request for Single Stage - One Under Office, C, Paython,and Matlab IDA / Q9970 Meteorological Information Post Open - National 6,360.00 0.00 2016-08-28 2016-09-20 2016-10-06 Quotations Envelope Implementation Programing language Training Services DAE-NS1 / Data digitization of Component C- Agro- Single Stage - One Pending historical and currently generated IDA / 58370 Meteorological Information Post Request for Bids Open - National 500,000.00 0.00 2017-11-02 2017-11-07 2017-12-19 2018-01-18 2018-03-01 2018-05-30 Envelope Implementation data of agromet databases Systems Development DAE-NS2 / Development of Component C- Agro- Single Stage - One Pending content for media and IDA / 58370 Meteorological Information Post Request for Bids Open - National 100,000.00 0.00 2018-06-07 2018-06-12 2018-07-24 2018-08-23 2018-10-04 2021-06-15 Envelope Implementation communication Systems Development Component A- Strengthening BMD-NS1 / Data Digitization Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 250,000.00 0.00 2017-12-03 2017-12-08 2018-01-19 2018-02-18 2018-03-25 2018-10-21 and Rescue Envelope Implementation Services BMD-NS2 / Media and sector Component A- Strengthening Single Stage - One Pending user outreach (publications, TV, IDA / 58370 Meteorological Information Post Request for Bids Open - National 50,000.00 0.00 2017-11-20 2017-11-25 2018-01-06 2018-02-05 2018-03-12 2018-09-09 Envelope Implementation videos, etc) Services BMD-NS5 / Community Based Early Warning System for quick Component A- Strengthening Single Stage - One Pending Onset Hazards and drought and IDA / 58370 Meteorological Information Prior Request for Bids Open - International 3,000,000.00 0.00 2017-12-17 2017-12-22 2018-02-02 2018-03-04 2018-04-08 2019-05-05 Envelope Implementation extreme meteorological events in Services NW Bangladesh BMD-NS6 / Survey of Component A- Strengthening Bathymetry and coastal elevation Single Stage - One Pending IDA / 58370 Meteorological Information Prior Request for Bids Open - International 2,800,000.00 0.00 2018-07-22 2018-07-27 2018-09-07 2018-10-07 2018-11-19 2019-05-19 monitoring for modeling tropical Envelope Implementation Services cyclone associated storm surge Component A- Strengthening BMD-NS3 / Internet Connectivity Single Stage - One Pending IDA / 58370 Meteorological Information Post Request for Bids Open - National 1,100,000.00 0.00 2017-10-10 2017-10-15 2017-11-26 2017-12-26 2018-01-30 2018-07-29 in BMD offices Envelope Implementation Services Component B- Strengthening BWDB-NS7 / Hiring of Vehicles Hydrological Information Single Stage - One Pending for project office and field works( IDA / 58370 Post Request for Bids Open - National 457,898.75 0.00 2017-09-21 2017-09-26 2017-10-24 2017-11-03 2017-12-08 2021-07-03 Services and Early Warning Envelope Implementation 6 double cabin pickup) Systems Component B- Strengthening BWDB- NS1 / Hiring Media and Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 40,000.00 0.00 2019-10-24 2019-10-29 2019-11-26 2019-12-06 2020-01-10 2021-06-30 Communication outreach Work Services and Early Warning Envelope Implementation Systems BWDB-NS2 / Hiring Facilitation of Regional: data Component B- Strengthening sharing,collaboration on Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 1,300,000.00 0.00 2019-01-17 2019-01-22 2019-03-05 2019-04-04 2019-05-09 2020-05-08 identifying transboundary Services and Early Warning Envelope Implementation risk,cooperation on mitigating Systems transboundary risk works BWDB-NS3 / Hiring Community based EWS in 2 flood prone Component B- Strengthening districts (Nethrkona and Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 1,450,000.00 0.00 2019-02-07 2019-02-12 2019-03-26 2019-04-25 2019-05-30 2020-05-29 Sunamganj) in collaboration with Services and Early Warning Envelope Implementation DDM, incl community Systems participation Work Component B- Strengthening BWDB-NS4 / Hiring Internet Hydrological Information Single Stage - One Pending Connectivity serivces at 13 IDA / 58370 Post Request for Bids Open - National 50,000.00 0.00 2020-03-18 2020-03-23 2020-05-04 2020-06-03 2020-07-08 2021-06-30 Services and Early Warning Envelope Implementation locations Systems BWDB-NS5 / Hiring of Sampling Component B- Strengthening and Analysis of Groundwater Hydrological Information Single Stage - One Pending Samples for Water Quality (20 IDA / 58370 Post Request for Bids Open - National 570,000.00 0.00 2018-01-04 2018-01-09 2018-02-20 2018-03-22 2018-04-26 2018-10-23 Services and Early Warning Envelope Implementation physico-chemical parameters) Systems services Component B- Strengthening BWDB-NS6 / Hiring of Survey, Hydrological Information Single Stage - One Pending IDA / 58370 Post Request for Bids Open - National 169,994.90 0.00 2017-09-12 2017-09-17 2017-10-15 2017-10-29 2017-12-03 2018-12-03 Study & Investigation services Services and Early Warning Envelope Implementation Systems CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component C- Agro- DAE-C1 / BAMIS technical Quality And Cost- Under IDA / 58370 Meteorological Information Post Open - International 328,567.79 0.00 2017-03-30 2017-07-09 2017-04-20 2017-06-03 2017-07-01 2017-08-30 2017-10-04 2017-11-15 2019-10-15 design consultancy Based Selection Implementation Systems Development DAE-C2 / Consultancy for Component C- Agro- Consultant Pending Agromet data analysis and IDA / 58370 Meteorological Information Post Qualification Open - National 246,425.85 0.00 2017-04-04 2017-04-25 2017-06-08 2017-07-08 2017-08-12 2018-02-08 Implementation development of products Systems Development Selection Component B- Strengthening Consultant DAE-C4 / Risk mapping for Hydrological Information Pending IDA / 58370 Post Qualification Open - National 164,283.90 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-18 2020-08-17 climate vulnerabiltiy Services and Early Warning Implementation Selection Systems DAE-C10 / Technical consultancy on Baseline survey and two monitoring surveys to Component C- Agro- assess user satisfaction of Quality And Cost- Pending IDA / 58370 Meteorological Information Post Open - National 127,779.19 0.00 2017-04-11 2017-05-02 2017-06-15 2017-07-13 2017-08-12 2017-09-16 2017-10-21 2018-10-21 agrometeorological advisories Based Selection Implementation Systems Development and products,mid-term and end- term evaluations and Training need assesment Page 4 DAE-C11 / Dissemination of Agrometeorological advisories Component C- Agro- and products to farming Quality And Cost- Pending IDA / 58370 Meteorological Information Post Open - National 95,828.03 0.00 2017-05-16 2017-06-13 2017-07-27 2017-08-24 2017-10-13 2017-11-17 2017-12-29 2021-06-15 communities in different Based Selection Implementation Systems Development Upazillas and feedback from farmers Component A- Strengthening BMD-C1 / Meteorology Systems Quality Based Under IDA / 58370 Meteorological Information Prior Open - International 3,285,780.00 0.00 2017-07-11 2017-08-04 2017-08-01 2017-09-25 2017-09-14 2017-10-12 2017-11-11 2017-12-11 2018-01-15 2019-01-15 and Services Integrator (MSSI) Selection Implementation Services Component A- Strengthening BMD-C8 / Technical Quality And Cost- Pending IDA / 58370 Meteorological Information Post Open - National 166,109.45 0.00 2017-08-01 2017-08-22 2017-10-05 2017-11-02 2017-11-30 2018-01-04 2018-02-08 2019-02-10 consultancy on M&E Based Selection Implementation Services Component A- Strengthening Consultant BMD-C9 / Building - Structural Pending IDA / 58370 Meteorological Information Post Qualification Open - National 63,888.25 0.00 2017-12-05 2017-12-26 2018-02-08 2018-03-08 2018-04-12 2019-04-07 assessment and design options Implementation Services Selection Component A- Strengthening Consultant BMD-C10 / Development of a Pending IDA / 58370 Meteorological Information Post Qualification Open - National 63,888.25 0.00 2017-12-05 2017-12-26 2018-02-08 2018-03-11 2018-04-15 2019-04-10 national data sharing policy Implementation Services Selection BMD-C11 / Develop roadmap for Component A- Strengthening Consultant regional collaboration (including Pending IDA / 58370 Meteorological Information Post Qualification Open - National 127,776.50 0.00 2018-07-15 2018-08-05 2018-09-18 2018-10-18 2018-11-22 2019-11-17 twinning plan), technical support Implementation Services Selection and facilitation for BMD BMD-C12 / Design and implementation of dissemination Component A- Strengthening Consultant of forecasts, weather and climate Pending IDA / 58370 Meteorological Information Post Qualification Open - National 164,289.00 0.00 2017-12-06 2017-12-27 2018-02-08 2018-03-11 2018-04-15 2019-04-15 reports and data to users through Implementation Services Selection mobile applications (both push and pull technology) BMD-C13 / Multiple technical Component A- Strengthening Quality And Cost- Pending studies (regional collaboration IDA / 58370 Meteorological Information Post Open - National 292,065.50 0.00 2019-05-01 2019-05-22 2019-07-07 2019-08-04 2019-09-03 2019-10-08 2019-11-12 2021-11-11 Based Selection Implementation and others) Services BMD-C14 / Design, Component A- Strengthening Consultant Pending implementation and training on IDA / 58370 Meteorological Information Post Qualification Open - National 82,144.50 0.00 2018-02-05 2018-02-26 2018-04-11 2018-05-13 2018-06-17 2019-06-12 Implementation Common Alerting Protocal (CAP) Services Selection BMD-C15 / Develop software of Component A- Strengthening Consultant Pending Common Alerting Protocol (CAP) IDA / 58370 Meteorological Information Post Qualification Open - National 164,289.00 0.00 2018-08-19 2018-09-09 2018-10-23 2018-11-22 2018-12-27 2019-12-22 Implementation for Disaster Management Services Selection BMD-C17 / Technical Consultants for meteorology Component A- Strengthening Consultant Pending training including general IDA / 58370 Meteorological Information Post Qualification Open - National 164,289.00 0.00 2017-09-03 2017-09-24 2017-11-07 2017-12-07 2018-01-11 2021-12-21 Implementation meteorology training and NWP Services Selection product interpretation Component A- Strengthening Consultant BMD-C18 / Install, configure and Pending IDA / 58370 Meteorological Information Post Qualification Open - National 164,289.00 0.00 2018-07-04 2018-07-25 2018-09-06 2018-10-07 2018-11-11 2019-11-06 train on WRF model Implementation Services Selection BMD-C19 / Install, configure and Component A- Strengthening Consultant Pending training on storm surge and wave IDA / 58370 Meteorological Information Post Qualification Open - National 246,433.50 0.00 2018-07-10 2018-07-31 2018-09-13 2018-10-14 2018-11-18 2019-11-13 Implementation models Services Selection BMD-C20 / Design, installation, Component A- Strengthening Consultant Pending training on climate modeling and IDA / 58370 Meteorological Information Post Qualification Open - National 246,433.50 0.00 2018-07-15 2018-08-05 2018-09-18 2018-10-18 2018-11-22 2019-11-17 Implementation prediction Services Selection BMD-C16 / Consultancy for BMD Climate Services Product Component A- Strengthening Quality And Cost- Pending generation and communication IDA / 58370 Meteorological Information Post Open - International 657,156.00 0.00 2017-12-18 2018-01-08 2018-02-21 2018-03-21 2018-04-19 2018-05-24 2018-06-28 2019-06-23 Based Selection Implementation and outreach to sectoral users Services and stakeholders BWDB-C2 / Hiring of expanding flood forecasting model (whole Component B- Strengthening country), Improve inundation Hydrological Information Quality And Cost- Pending IDA / 58370 Post Open - National 328,580.51 0.00 2018-09-09 2018-09-30 2018-11-13 2018-12-11 2019-01-10 2019-02-14 2019-03-31 2021-06-30 model in coastal and hotspot Services and Early Warning Based Selection Implementation areas (depth and area of Systems inundation) services. Component B- Strengthening BWDB-C1 / Hiring Water Hydrological Information Quality And Cost- Pending Resources System Integrator IDA / 58370 Prior Open - International 1,351,961.44 0.00 2017-09-14 2017-10-12 2017-11-25 2017-12-23 2018-01-22 2018-02-26 2018-04-02 2021-06-30 Services and Early Warning Based Selection Implementation (WRSI) Consultancy services Systems Component B- Strengthening BWDB-C8 / Hiring project Hydrological Information Quality And Cost- Pending Technical Consultant (PTC) in IDA / 58370 Post Open - National 146,947.00 0.00 2017-09-28 2017-10-19 2017-12-02 2017-12-30 2018-01-29 2018-03-05 2018-04-09 2020-10-07 Services and Early Warning Based Selection Implementation PIU services Systems BWDB-C14 / Hiring Technical studies on mitigatiing transboundary disaster risks, Component B- Strengthening regional collaboration, Risk Hydrological Information Quality And Cost- Pending analysis and Mitigation - Hazard, IDA / 58370 Post Open - National 410,722.46 0.00 2018-09-20 2018-12-20 2019-02-02 2019-03-02 2019-04-01 2019-05-06 2019-06-10 2021-06-09 Services and Early Warning Based Selection Implementation vulnerability, risk assessment, Systems development of feasibility studies for mitigation measures of flood and disaster BWDB-C15 / Hire BWDB hydrological services and product generation consultancy (development of hydrological Component B- Strengthening services products such as hyd. Hydrological Information Quality And Cost- Pending IDA / 58370 Post Open - National 205,367.59 0.00 2018-08-23 2018-09-13 2018-10-27 2018-11-24 2018-12-24 2019-01-28 2019-03-04 2021-03-03 drought rediction, basin wise Services and Early Warning Based Selection Implementation flood forecast, sediment Systems prediction, salinity intrusion forecast,ground water outlook and forecast Page 5 BWDB-C16 / Hiring of Component B- Strengthening consultancy for Development of Hydrological Information Quality And Cost- Pending IDA / 58370 Post Open - National 51,106.58 0.00 2018-08-16 2018-09-06 2018-10-20 2018-11-17 2018-12-17 2019-01-21 2019-02-25 2020-02-25 Institutional Analysis of Dept of Services and Early Warning Based Selection Implementation Hydrology Systems INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A- Strengthening BMD-C7 / Senior M&E Individual Consultant Pending IDA / 58370 Meteorological Information Post Open - National 68,147.46 0.00 2018-05-01 2018-06-19 2018-07-10 2018-08-14 2019-08-11 specialist for PIU (National) Selection Implementation Services BMD-C3 / Senior Financial Component A- Strengthening Individual Consultant Pending Management Specialist for PIU IDA / 58370 Meteorological Information Post Open - National 196,616.64 0.00 2017-09-03 2017-10-22 2017-11-12 2017-12-17 2021-06-30 Selection Implementation (National consultant) Services BMD-C4 / Senior Project Component A- Strengthening Individual Consultant Pending Technical Coordinator (National IDA / 58370 Meteorological Information Post Open - National 138,424.54 0.00 2017-09-07 2017-10-29 2017-11-19 2017-12-24 2019-12-15 Selection Implementation Consultant) Services BMD-C5 / International Component A- Strengthening Individual Consultant Under Procurement Consultant (Bid IDA / 58370 Meteorological Information Prior Open - National 168,532.00 0.00 2017-08-10 2017-08-03 2017-09-28 2017-10-19 2017-11-23 2018-05-22 Selection Implementation Evaluation) Services BMD-C6 / International Component A- Strengthening Individual Consultant Under Technical Consultant (Bid IDA / 58370 Meteorological Information Prior Open - National 168,532.00 0.00 2017-10-15 2017-08-03 2017-12-03 2017-12-24 2018-01-28 2018-07-29 Selection Implementation Evaluation) Services BMD-C2 / Sr. Procurement Component A- Strengthening Individual Consultant specialist for PIU (National IDA / 58370 Meteorological Information Prior Open - National 196,196.90 0.00 Canceled 2016-08-01 2016-09-19 2016-10-10 2016-11-14 2017-05-13 Selection consultant) Services BMD-C-2 / Sr. Procurement Component A- Strengthening Individual Consultant Under Specialist for PIU (National IDA / 58370 Meteorological Information Prior Open - National 196,196.90 0.00 2017-07-23 2017-07-27 2017-09-10 2017-10-18 2017-10-01 2017-11-21 2017-11-12 2021-06-30 Selection Implementation Consultant) Services Component B- Strengthening BWBD-C3 / Hiring project Hydrological Information Individual Consultant Pending Coordination Consultant PCU IDA / 58370 Post Open 138,476.00 0.00 2017-09-12 2017-10-31 2017-11-21 2018-01-02 2020-01-01 Services and Early Warning Selection Implementation services Systems BWDB-C4 / Hiring Senior Social Component B- Strengthening safeguards and communitcations Hydrological Information Individual Consultant Pending IDA / 58370 Post Open 47,914.00 0.00 2019-09-08 2019-10-27 2019-11-17 2019-12-22 2020-12-21 specialist for PCU (National) Services and Early Warning Selection Implementation serivces Systems BWDB-C5 / Hiring Senior Component B- Strengthening Environmental safeguards Hydrological Information Individual Consultant Pending IDA / 58370 Post Open 47,914.00 0.00 2019-09-08 2019-10-27 2019-11-17 2019-12-22 2020-12-21 specialist for PCU (National) Services and Early Warning Selection Implementation services Systems Component B- Strengthening BWDB-C9 / Hiring Senior M&E Hydrological Information Individual Consultant Pending specialist for PIU (National) IDA / 58370 Post Open 121,381.00 0.00 2017-09-28 2017-11-16 2017-12-07 2018-01-11 2020-01-11 Services and Early Warning Selection Implementation services Systems Component B- Strengthening BWDB-C10 / Hiring ground Hydrological Information Individual Consultant Pending Water Specialist(National) IDA / 58370 Post Open 69,918.00 0.00 2017-09-28 2017-11-16 2017-12-07 2018-01-11 2020-01-11 Services and Early Warning Selection Implementation services Systems Component B- Strengthening BWDB-C11 / Hiring Hydrological Information Individual Consultant Pending Administrative Associate IDA / 58370 Post Open 44,880.25 0.00 2017-09-12 2017-10-31 2017-11-21 2017-12-26 2021-06-30 Services and Early Warning Selection Implementation services Systems Component B- Strengthening BWDB-C12 / Hiring Logistic Hydrological Information Individual Consultant Pending IDA / 58370 Post Open 44,880.25 0.00 2017-09-12 2017-10-31 2017-11-21 2017-12-26 2021-06-29 Associate Services Services and Early Warning Selection Implementation Systems BWDB-C13 / Hiring Technical Component B- Strengthening consultancy on M&E:Develop Hydrological Information Individual Consultant Pending M&E framework and survey IDA / 58370 Post Open 127,779.00 0.00 2017-09-28 2017-11-16 2017-12-07 2018-01-11 2021-01-10 Services and Early Warning Selection Implementation instruments,Conduct Baseline Systems survey etc. Component B- Strengthening BWDB-C17 / Hiring of Hydrological Information Individual Consultant Pending consultancy for Development of IDA / 58370 Post Open 82,142.00 0.00 2018-07-15 2018-09-02 2018-09-23 2018-10-28 2019-10-28 Services and Early Warning Selection Implementation Mobile apps services Systems Component B- Strengthening BWDB-C19 / Hiring of design, Hydrological Information Individual Consultant Pending implementation and training on IDA / 58370 Post Open 82,142.00 0.00 2018-09-20 2018-11-08 2018-11-29 2019-01-06 2019-11-02 Services and Early Warning Selection Implementation CAP services Systems Component B- Strengthening BWDB-C20 / Hiring of Upgrading Hydrological Information Individual Consultant Pending IDA / 58370 Post Open 63,889.00 0.00 2019-01-24 2019-03-14 2019-04-04 2019-05-12 2020-01-07 webportal services Services and Early Warning Selection Implementation Systems BWDB-C21 / Hiring performance Component B- Strengthening auditing of 3 Project Hydrological Information Individual Consultant Pending IDA / 58370 Post Open 69,257.00 0.00 2020-09-01 2020-10-20 2020-11-10 2020-12-15 2021-06-13 Implementation Units by PCU Services and Early Warning Selection Implementation services. Systems Component B- Strengthening BWDB-C18 / Hiring Consultancy Hydrological Information Individual Consultant Pending IDA / 58370 Post Open 51,106.60 0.00 2019-01-10 2019-02-28 2019-03-21 2019-04-25 2020-04-24 on Data Sharing Policy Services Services and Early Warning Selection Implementation Systems Page 6 Component B- Strengthening BWDB-C6 / Hiring of Senior Hydrological Information Individual Consultant Pending Procurement specialist for PIU ( IDA / 58370 Post Open 209,296.62 0.00 2017-12-17 2018-02-04 2018-02-25 2018-04-01 2021-09-12 Services and Early Warning Selection Implementation National ). Systems Component B- Strengthening BWDB-C7 / Hiring of Senior Hydrological Information Individual Consultant Pending Financial Management specialist IDA / 58370 Post Open 209,296.62 0.00 2017-12-17 2018-02-04 2018-02-25 2018-04-01 2021-09-12 Services and Early Warning Selection Implementation for PIU ( national ) Systems Component C- Agro- DAE-C3 / Senior International Individual Consultant IDA / 58370 Meteorological Information Prior Open 354,451.79 0.00 Canceled 2017-04-06 2017-05-09 2017-06-08 2017-07-08 2017-08-19 2020-08-18 Agromet Technical consultant Selection Systems Development DAE C6 / Selection of Senior Component C- Agro- Individual Consultant Pending National Procurement Consultant IDA / 58370 Meteorological Information Post Open 95,828.08 0.00 2017-10-31 2017-12-19 2018-01-09 2018-02-13 2021-02-12 Selection Implementation for PIU Systems Development Component C- Agro- DAE-C6 / Senior National Individual Consultant IDA / 58370 Meteorological Information Prior Open 95,828.03 0.00 Canceled 2017-03-30 2017-05-09 2017-05-18 2017-06-08 2017-07-20 2020-06-20 Procurement Consultant for PIU Selection Systems Development Component C- Agro- DAE C9 / Senior National M&E Individual Consultant Pending IDA / 58370 Meteorological Information Post Open 47,914.02 0.00 2017-11-02 2017-12-21 2018-01-11 2018-02-15 2019-08-17 Consultant Selection Implementation Systems Development Component C- Agro- DAE C8 / National Individual Consultant Pending IDA / 58370 Meteorological Information Post Open 31,938.44 0.00 2017-11-02 2017-12-21 2018-01-11 2018-02-15 2019-02-15 Communications Consultant Selection Implementation Systems Development Component C- Agro- DAE C7 / Senior National FM Individual Consultant Pending IDA / 58370 Meteorological Information Post Open 122,665.99 0.00 2017-11-05 2017-12-24 2018-01-14 2018-02-18 2021-06-30 Consultant Selection Implementation Systems Development Component C- Agro- DAE C5 / Senior National Individual Consultant Pending IDA / 58370 Meteorological Information Post Open 92,000.00 0.00 2017-11-05 2017-12-24 2018-01-14 2018-02-18 2021-02-17 Agromet Technical Consultant Selection Implementation Systems Development Component C- Agro- DAE-C9 / Senior National M&E Individual Consultant IDA / 58370 Meteorological Information Post Open 47,914.02 0.00 Canceled 2017-07-12 2017-09-04 2017-09-06 2017-09-27 2017-11-08 2019-11-08 Consultant for PIU Selection Systems Development DAE-C8 / National Component C- Agro- Individual Consultant Communications Consultant for IDA / 58370 Meteorological Information Post Open 31,938.44 0.00 Canceled 2017-05-24 2017-08-27 2017-07-19 2017-08-09 2017-09-20 2018-09-20 Selection PIU Systems Development DAE-C5 / Senior National Component C- Agro- Individual Consultant Agromet Technical Consultant for IDA / 58370 Meteorological Information Post Open 92,000.00 0.00 Canceled 2017-04-07 2017-08-27 2017-05-26 2017-06-16 2017-07-28 2020-07-27 Selection PIU Systems Development Component C- Agro- DAE-C7 / Senior National FM Individual Consultant IDA / 58370 Meteorological Information Post Open 122,665.99 0.00 Canceled 2017-04-12 2017-09-04 2017-05-31 2017-06-21 2017-08-02 2021-07-02 Consultant for PIU Selection Systems Development DAE C3 / Selection of Senior Component C- Agro- Individual Consultant Pending International Agromet Technical IDA / 58370 Meteorological Information Prior Open 354,451.79 0.00 2017-10-31 2017-12-19 2018-01-09 2018-02-13 2020-02-13 Selection Implementation Consultant Systems Development Page 7