Public Disclosure Copy

        The World Bank                                                            Implementation Status & Results Report
        Gansu Cultural and Natural Heritage Protection and Development Project (P091949)


Gansu Cultural and Natural Heritage Protection and Development Project (P091949)

EAST ASIA AND PACIFIC | China | Urban Development Global Practice |
IBRD/IDA | Specific Investment Loan | FY 2008 | Seq No: 8 | ARCHIVED on 26-Nov-2014 | ISR16372 |


Implementing Agencies: GANSU PMO




Key Dates

  Key Project Dates

  Board Approval date:20-Mar-2008                                           Effectiveness Date:11-Aug-2008
  Planned Mid Term Review Date:21-Oct-2011                                  Actual Mid-Term Review Date:19-Mar-2012
  Original Closing Date:31-Dec-2013                                         Revised Closing Date:31-Dec-2014




Project Development Objectives

 Project Development Objective (from Project Appraisal Document)
 The project development objective is to generate benefits for local communities from the development of sustainable cultural tourism in Gansu
 Province.


 Has the Project Development Objective been changed since Board Approval of the Project Objective?
 No

 PHRPDODEL



Components

Name
Protection and Development of Priority Sites:(Cost $46.07 M)
Institutional Strengthening and Capacity Building:(Cost $1.38 M)



Overall Ratings
Name                                                                      Previous Rating                          Current Rating

Progress towards achievement of PDO                                        Moderately Unsatisfactory               Moderately Unsatisfactory
Overall Implementation Progress (IP)                                       Moderately Unsatisfactory               Moderately Satisfactory
Overall Risk Rating                                                        --                                      Substantial


Implementation Status and Key Decisions


11/26/2014                                                                                                                             Page 1 of 8
                                                          Public Disclosure Copy
                                                            Public Disclosure Copy

           The World Bank                                                            Implementation Status & Results Report
           Gansu Cultural and Natural Heritage Protection and Development Project (P091949)



 Of the seven cultural heritage sites being upgraded under the project, six have culture conservation plans approved by the Gansu Cultural Relic Bureau
 and the State Administration of Cultural Heritage (SACH), with the seventh and final approval for Maijishan Scenic Area expected by end December
 2014. Works carried out under the project have improved site access and tourist facilities and services at all nine sites. Project improvements in
 Maijishan and Suoyang contributed to their being listed as Silk Road World Heritage sites UNESCO in 2014, which could, in turn, increase their visibility
 to international tourists as well as domestic tourists. Visitor satisfaction with the sites and visitor spending levels are exceeding expectations as seen in
 the Results Framework. The project management office has been recently strengthened and is increasing attention to operations and maintenance of
 the infrastructure and facilities constructed. Taken together these bode well for sustainable tourism. Benefits generated by the project for local
 communities include increased tourist purchasing of local private tourism services, increased awareness and knowledge of the significance of the
 cultural site, increased access to basic services such as water, sanitation, roads, power and solid waste management. Economic benefits generated by
 the project may be difficult to isolate given the influx of development funding in Gansu over the course of project implementation but may include
 increased employment opportunities and livelihood diversification from provision of tourism related services (home stays, restaurants, shops,
 transportation, guided tours).
 With only a few weeks left before the revised closing date, the client and Bank are considering extending the closing date to allow extra time to complete
 the Maijishan Scenic Area works, to rehabilitate two roads damaged by recent severe flooding, and to enhance operations and maintenance planning.
 Considering the importance of completing key works in Maijishan, a ten month extension of the Loan Closing date is being considered. Additional time
 would also be useful in completing damaged roads, improving operations and maintenance plans and carrying out socio-economic work. The next
 mission is scheduled for March, 2014.




Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                               Rating at Approval                Previous Rating              Current Rating

 Political and Governance                                     --                               --                          Substantial
 Macroeconomic                                                --                               --                          Low
 Sector Strategies and Policies                               --                               --                          Substantial
 Technical Design of Project or Program                       --                               --                          Substantial
 Institutional Capacity for Implementation and
 Sustainability
                                                              --                               --                          Substantial
 Fiduciary                                                    --                               --                          Low
 Environment and Social                                       --                               --                          Moderate
 Stakeholders                                                 --                               --                          Low
 Other                                                        --                               --                          --
 Overall                                                      --                               --                          Substantial


Results

 Project Development Objective Indicators




11/26/2014                                                                                                                                  Page 2 of 8
                                                            Public Disclosure Copy
                                                           Public Disclosure Copy

               The World Bank                                                            Implementation Status & Results Report
               Gansu Cultural and Natural Heritage Protection and Development Project (P091949)

 PHINDPDOTBL




          Number of people participating in the provision of tourism services at the project sites (Text, Custom)


                                             Baseline                    Actual (Previous)        Actual (Current)       End Target

         Value                               3,130                       7197                     7998                   3,740

         Date                                31-Dec-2007                 10-Jun-2014              31-Oct-2014            31-Dec-2013


         Comments

 PHINDPDOTBL




          Percentage of tourists who purchase private tourism services when visiting the project sites (%) (Text, Custom)


                                             Baseline                    Actual (Previous)        Actual (Current)       End Target

         Value                               34%                         60%                      64%                    60%

         Date                                31-Dec-2007                 10-Jun-2014              31-Oct-2014            31-Dec-2013


         Comments

 PHINDPDOTBL




      Percentage of local community members with awareness and knowledge of the significance of the cultural site (%) (Text,
     Custom)

                                             Baseline                    Actual (Previous)        Actual (Current)       End Target

         Value                               63%                         84%                      88%                    80%

         Date                                31-Dec-2007                 10-Jun-2014              31-Oct-2014            31-Dec-2013


         Comments



 Overall Comments

 Intermediate Results Indicators




11/26/2014                                                                                                                       Page 3 of 8
                                                           Public Disclosure Copy
                                                                  Public Disclosure Copy

                  The World Bank                                                            Implementation Status & Results Report
                  Gansu Cultural and Natural Heritage Protection and Development Project (P091949)

 PHINDIRITBL




              Number of heritage sites in project with approved cultural conservation plans (#) (Text, Custom)

                                                    Baseline                     Actual (Previous)            Actual (Current)   End Target

               Value                                1                            6                            6                  7

               Date                                 31-Dec-2007                  10-Jun-2014                  31-Oct-2014        31-Dec-2013


               Comments

 PHINDIRITBL




              Level of visitor satisfaction with access to site (% fully satisfied) (Text, Custom)

                                                    Baseline                     Actual (Previous)            Actual (Current)   End Target

               Value                                37                           86%                          87%                60

               Date                                 31-Dec-2007                  10-Jun-2014                  31-Oct-2014        31-Dec-2013


               Comments

 PHINDIRITBL




              Level of visitor satisfaction with interpretation of site (% fully satisfied) (Text, Custom)

                                                    Baseline                     Actual (Previous)            Actual (Current)   End Target

               Value                                24                           79%                          90%                60

               Date                                 31-Dec-2007                  10-Jun-2014                  31-Oct-2014        31-Dec-2013


               Comments

 PHINDIRITBL




              Level of visitor satisfaction with management of site (% fully satisfied) (Text, Custom)

                                                    Baseline                     Actual (Previous)            Actual (Current)   End Target

               Value                                21%                          75%                          85%                60%

               Date                                 31-Dec-2008                  04-Dec-2013                  31-Oct-2014        31-Dec-2013


               Comments




11/26/2014                                                                                                                              Page 4 of 8
                                                                  Public Disclosure Copy
                                                                 Public Disclosure Copy

                  The World Bank                                                            Implementation Status & Results Report
                  Gansu Cultural and Natural Heritage Protection and Development Project (P091949)

 PHINDIRITBL




              Level of visitor satisfaction with environment of site (% fully satisfied) (Text, Custom)

                                                   Baseline                    Actual (Previous)           Actual (Current)   End Target

               Value                               15%                         72%                         84%                50%

               Date                                31-Dec-2007                 10-Jun-2014                 31-Oct-2014        31-Dec-2013


               Comments

 PHINDIRITBL




              Average expenditure per tourist visit at Maijishan Scenic Area (RMB/visitor/visit) (Text, Custom)

                                                   Baseline                    Actual (Previous)           Actual (Current)   End Target

               Value                               400                         513                         564                480

               Date                                31-Dec-2007                 10-Jun-2014                 31-Oct-2014        31-Dec-2013


               Comments

 PHINDIRITBL




              Average expenditure per tourist visit at Yellow River Stone Forest Geological Park (RMB/visitor/visit) (Text, Custom)

                                                   Baseline                    Actual (Previous)           Actual (Current)   End Target

               Value                               335                         600                         625                430

               Date                                31-Dec-2007                 10-Jun-2014                 31-Oct-2014        31-Dec-2013


               Comments

 PHINDIRITBL




              Average expenditure per tourist visit at Jiayuguan Great Wall Scenic Area (RMB/visitor/visit) (Text, Custom)

                                                   Baseline                    Actual (Previous)           Actual (Current)   End Target

               Value                               625                         820                         830                800

               Date                                31-Dec-2007                 10-Jun-2014                 31-Oct-2014        31-Dec-2013


               Comments




11/26/2014                                                                                                                             Page 5 of 8
                                                                 Public Disclosure Copy
                                                               Public Disclosure Copy

                  The World Bank                                                            Implementation Status & Results Report
                  Gansu Cultural and Natural Heritage Protection and Development Project (P091949)

 PHINDIRITBL




              Average expenditure per tourist visit at Yadan National Geological Park (RMB/visitor/visit) (Text, Custom)

                                                 Baseline                   Actual (Previous)        Actual (Current)       End Target

               Value                             350                        500                      543                    425

               Date                              31-Dec-2007                10-Jun-2014              31-Oct-2014            31-Dec-2013


               Comments

 PHINDIRITBL




            Participation of communities in sustainable tourism regarding cumulative number of local people trained in sustainable tourism-
           related activities (#) (Text, Custom)

                                                 Baseline                   Actual (Previous)        Actual (Current)       End Target

               Value                             0                          9,828                    10,506                 9,000

               Date                              31-Dec-2007                10-Jun-2014              31-Oct-2014            31-Dec-2013


               Comments

 PHINDIRITBL




            Participation of communities in sustainable tourism regarding number of community persons with improved road access to
           main touristareas within Maijishan and Qingcheng (#) (Text, Custom)

                                                 Baseline                   Actual (Previous)        Actual (Current)       End Target

               Value                             0                          13,495                   20,217                 27,000

               Date                              31-Dec-2007                10-Jun-2014              31-Oct-2014            31-Dec-2013


               Comments

 PHINDIRITBL




              Direct project beneficiaries (Number, Core)

                                                 Baseline                   Actual (Previous)        Actual (Current)       End Target

               Value                             0.00                       0.00                     0.00                   0.00

               Date                              31-Dec-2007                04-Dec-2013              04-Dec-2013            31-Dec-2013


               Comments




11/26/2014                                                                                                                           Page 6 of 8
                                                               Public Disclosure Copy
                                                                  Public Disclosure Copy

                  The World Bank                                                            Implementation Status & Results Report
                  Gansu Cultural and Natural Heritage Protection and Development Project (P091949)

 PHINDIRITBL




              Female beneficiaries (Percentage, Core Supplement)

                                                    Baseline                   Actual (Previous)         Actual (Current)             End Target

               Value                                55.00                      55.00                     55.00                        55.00

               Date                                 31-Dec-2007                04-Dec-2013               04-Dec-2013                  31-Dec-2013


               Comments



 Overall Comments



 Data on Financial Performance

Disbursements (by loan)

 Project               Loan/Credit/TF   Status        Currency      Original   Revised     Cancelled    Disbursed      Undisbursed                  Disbursed

 P091949               IBRD-75420       Effective     USD             38.40      38.40           0.00         33.89            4.51                         88%


Key Dates (by loan)
 Project               Loan/Credit/TF   Status        Approval Date    Signing Date      Effectiveness Date    Orig. Closing Date     Rev. Closing Date

 P091949               IBRD-75420       Effective     20-Mar-2008      28-May-2008       11-Aug-2008           31-Dec-2013            31-Dec-2014



Cumulative Disbursements




11/26/2014                                                                                                                                    Page 7 of 8
                                                                  Public Disclosure Copy
                                                Public Disclosure Copy

        The World Bank                                                            Implementation Status & Results Report
        Gansu Cultural and Natural Heritage Protection and Development Project (P091949)



 Restructuring History

 Level 2 Approved on 09-Aug-2013




 Related Project(s)

There are no related projects.




11/26/2014                                                                                                     Page 8 of 8
                                                Public Disclosure Copy