Updated Procurement Plan of GEF Green Freight Demonstration Project unit:USD 10,000 Reviewed by Description of Estimated Ratio of Preparation of Cont. # Selection Method Bank Note Assignment Cost GEF Grant TOR (Prior / Post) Procurement Agent C1 5 QCBS Prior 100% Dec. 2010 signed Service for the Project Commercial and C2 Technology Agent 16 CQ Post 100% Nov. 2011 signed Service Study on demonstration C3 scheme of drop-and-pull —— —— —— —— —— transport moved to Design of demonstration corresponding scheme for logistics incentive scheme C4 —— —— —— —— —— transaction information platform Development of Green C5 Freight information 10 SSS Prior 100% Jun..2011 signed platform Study on green freight C6 9 CQ Post 100% Jun.2012 signed policy Development of C7 Teaching Materials for 7 CQ Post 100% Sep.2013 signed Green Freight Training Planning and Organizing of Guangdong C8 15 CQ Post 100% Jun.2011 signed International Green Freight Fair Planning and Organizing of Achievement newly added; C8-2 Exhibition of Guangdong 8 CQ Post 100% Aug.2014 contract signed Green Freight Demonstration Project Prior , as the first Design of green freight C9 2 CQ contract to adopt 100% Mar.2011 signed logo CQ method Technical experts (To C11 employ technical experts —— —— —— —— —— cancelled based on the needs) update the Preparation of Project budget and the C12 3 IC Post 100% Apr.2015 Completion Report time needed for preparing ToR Study on Guangdong Green Freight C13 Sustainable Development 8 CQ Post 100% Apr. 2015 newly added under the Strategy of the “Belt and Road� �计 83 Note: IC-Individual Consultant; SSS-Single Source Selection; CQS-Selection Based on Consultants’ Qualifications; QCBS- Quality and Cost-Based Selection; SOE—Statement of Expenditure, based on actual expenditure. Updated Procurement Plan of GEF Green Freight Demonstration Project P119654 unit:USD 10,000 Estimated Ratio of GEF Cont. # Description of Assignment Selection Method Implementing Period Note Cost Grant Domestic Studies and Training (for the staff from T1 the project coordinating 7 SOE 100% Jan.2011-Dec.2015 group, relevant transport departments and the PMO) Overseas Studies and Training (for the staff from T2 the project coordinating 18 SOE 100% Jan.2011-Dec.2015 group, relevant transport Implementing departments and the PMO) period Project Evaluation changed (Evaluation of the project’s M1 5 SOE 100% Jun.2014 and Dec. 2015 medium period and the completion) incremental operating cost M2 2 SOE 100% Jan.2011-Apr.2016 (IOC) Dissemination and P1 Promotion of Green Freight 9 SOE 100% Jan.2011-Dec.2015 Demonstration Project Total 41 Note: IC-Individual Consultant; SSS-Single Source Selection; CQS-Selection Based on Consultants’ Qualifications; QCBS-Quality and Cost-Based Selection; SOE—Statement of Expenditure, based on actual expenditure.