The World Bank                                                                                          Implementation Status & Results Report
         Saint Lucia - Caribbean Regional Air Transport Connectivity Project (P170860)



Saint Lucia - Caribbean Regional Air Transport Connectivity Project (P170860)


 LATIN AMERICA AND CARIBBEAN | St. Lucia | Transport Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2020 | Seq No: 1 | ARCHIVED on 13-Nov-2020 | ISR43415 |


 Implementing Agencies: Saint Lucia, Saint Lucia Air and Sea Ports Authority



 Key Dates


  Key Project Dates

   Bank Approval Date: 28-May-2020                                                Effectiveness Date: 16-Oct-2020
   Planned Mid Term Review Date: --                                               Actual Mid-Term Review Date:
   Original Closing Date: 30-Jun-2027                                             Revised Closing Date: 30-Jun-2027
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The Project Development Objectives (PDO) are to (i) improve operational safety and navigation efficiency of air transport and (ii) enhance resilience
  of Saint Lucia’s airport infrastructure to natural disasters.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Component 1: Improvement of UVF Runway Safety and Resilience:(Cost $32.50 M)
 Component 2: Modernization of Air Navigation Systems:(Cost $4.00 M)
 Component 3: Institutional Strengthening:(Cost $4.50 M)
 Component 4: Project Management:(Cost $4.00 M)
 Component 5: Contingent Emergency Response

 Overall Ratings

 Name                                                                        Previous Rating                            Current Rating

 Progress towards achievement of PDO                                         --                                         Satisfactory
 Overall Implementation Progress (IP)                                        --                                         Satisfactory
 Overall Risk Rating                                                         --                                         Substantial


 Implementation Status and Key Decisions

  The Project was approved on May 28, 2020. The Financing Agreement was signed on July 31, 2020 and the project was declared effective on
  October 16, 2020. The Project Implementing Entity has finalized the terms of reference for the recruitment of key personnel. The terms of reference
  for the elaboration of key studies are being finalized, including the vulnerability assessment and airfield resilience plan and the design study for
  Hewanorra International Airport’s airfield improvements.




11/13/2020                                                                                                                      Page 1 of 9
            The World Bank                                                                                          Implementation Status & Results Report
            Saint Lucia - Caribbean Regional Air Transport Connectivity Project (P170860)




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                                Rating at Approval                Previous Rating                Current Rating

  Political and Governance                                     Moderate                         --                             Moderate
  Macroeconomic                                                Substantial                      --                             Substantial
  Sector Strategies and Policies                               Moderate                         --                             Moderate
  Technical Design of Project or Program                       Moderate                         --                             Moderate
  Institutional Capacity for Implementation and
                                                               Substantial                      --                             Substantial
  Sustainability
  Fiduciary                                                    Substantial                      --                             Substantial
  Environment and Social                                       Moderate                         --                             Moderate
  Stakeholders                                                 Moderate                         --                             Moderate
  Other                                                        --                                --                             --
  Overall                                                      Substantial                      --                             Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   Improve operational safety and navigation efficiency of air transport

    IN00891181
    ►UVF runway in compliance with additional ICAO standards/requirements (Number, Custom)

                                        Baseline                     Actual (Previous)                Actual (Current)          End Target

    Value                               0.00                         --                               0.00                      4.00

    Date                                31-Mar-2020                  --                               10-Sep-2020              30-Jun-2027
                                        UVF runway improved to meet additional ICAO standards and requirements. This will be assessed by the
                                        following elements: (i) rehabilitation of the runway pavement, (ii) construction of 7.5 meter wide shoulders
   Comments:
                                        in both sides, (iii) installation of LED lighting, and (iv) new runway marking. These will be defined while the
                                        designs are finalized.
    IN00891183
    ►Modernization of air navigation systems and oversight (Number, Custom)

                                        Baseline                     Actual (Previous)                Actual (Current)          End Target

    Value                               0.00                         --                               0.00                      3.00

    Date                                31-Mar-2020                  --                               10-Sep-2020              30-Jun-2027



11/13/2020                                                                                                                           Page 2 of 9
           The World Bank                                                                                         Implementation Status & Results Report
           Saint Lucia - Caribbean Regional Air Transport Connectivity Project (P170860)



                                        Air traffic monitoring and control capacity upgraded to the international standards at UVF and SLU through
                                        (i) installation of ILS at UVF, (ii) installation of ADS-B monitors at UVF and SLU, and installation of ADS-B
   Comments:
                                        on Saint Lucia-based aircraft, and (iii) modernization of UVF aeronautical charts. The target will be
                                        assessed and revised after the final designs for Component 2 are finalized.
    IN00891184
    ►Regional change in airspace area covered by globally standardized air traffic monitoring system (Percentage, Custom)

                                       Baseline                      Actual (Previous)              Actual (Current)            End Target

    Value                              0.00                          --                             0.00                        100.00

    Date                               31-Mar-2020                   --                             10-Sep-2020                 30-Jun-2027
                                        Change in area of airspace covered by ADS-B which will be installed by the CATCOP program in the
                                        Caribbean region. The target value will be re-defined once the feasibility studies identify of the additional
                                        ADS-B coverage area in each CATCOP participating country. The indicator will be estimated as a change
   Comments:
                                        of the total coverage area in the region. The ADS-B is the globally standardized air traffic monitoring
                                        system which will benefit not only to flights taking off/landing tin the installed countries, but to all flights
                                        passing through the airspace covered by the system.
    IN00891185
    ►Regional capacity building program on air traffic control and management prepared and endorsed (Yes/No, Custom)

                                       Baseline                      Actual (Previous)              Actual (Current)            End Target

    Value                              No                            --                             No                          Yes

    Date                               31-Mar-2020                   --                             10-Sep-2020                 30-Jun-2027

                                        Regional capacity building program for all the SOP participants on air traffic control and management
   Comments:
                                        prepared and endorsed.


   Enhance resilience of Saint Lucia’s airport infrastructure to natural disasters

    IN00891182
    ►Change in discharge capacity of the runway drainage system at UVF (Percentage, Custom)

                                       Baseline                      Actual (Previous)              Actual (Current)            End Target

    Value                              0.00                          --                             0.00                        100.00

    Date                               31-Mar-2020                   --                             10-Sep-2020                 30-Jun-2027
                                        Change in discharge capacity of the runway drainage system at UVF due to the drainage improvement
   Comments:                            works in the airfield. The baseline value of the discharge capacity will be set by the design study. If
                                        necessary, the target will be updated.


 Intermediate Results Indicators by Components



   Improvement of UVF Runway Safety and Resilience

    IN00891186
    ►UVF runway rehabilitated (Percentage, Custom)

                                       Baseline                      Actual (Previous)              Actual (Current)            End Target

    Value                              0.00                          --                             0.00                        100.00


11/13/2020                                                                                                                         Page 3 of 9
           The World Bank                                                                                   Implementation Status & Results Report
           Saint Lucia - Caribbean Regional Air Transport Connectivity Project (P170860)




    Date                               22-Oct-2019                 --                         10-Sep-2020              30-Jun-2027

   Comments:                           Percentage of the UVF runway pavement rehabilitated.

    IN00891190
    ►Shoulders constructed along the UVF runway (Percentage, Custom)

                                       Baseline                    Actual (Previous)          Actual (Current)          End Target

    Value                              0.00                        --                         0.00                      100.00

    Date                               31-Mar-2020                 --                         10-Sep-2020              30-Jun-2027

   Comments:                           Construction work of installing the new shoulders along the UVF runway

    IN00891194
    ►LED lighting system installed for UVF runway (Yes/No, Custom)

                                       Baseline                    Actual (Previous)          Actual (Current)          End Target

    Value                              No                          --                         No                        Yes

    Date                               31-Mar-2020                 --                         10-Sep-2020              30-Jun-2027

   Comments:                           LED lighting system installed for UVF runway

    IN00891197
    ►Runway End Safety Areas constructed on the UVF runway (Percentage, Custom)

                                       Baseline                    Actual (Previous)          Actual (Current)          End Target

    Value                              0.00                        --                         0.00                      100.00

    Date                               31-Mar-2020                 --                         10-Sep-2020              30-Jun-2027

   Comments:                           Construction of Runway End Safety Areas (RESA) in the both end of the runway at UVF

    IN00891200
    ►Airfield drainages improved at UVF (Yes/No, Custom)

                                       Baseline                    Actual (Previous)          Actual (Current)          End Target

    Value                              No                          --                         No                        Yes

    Date                               31-Mar-2020                 --                         10-Sep-2020              30-Jun-2027

   Comments:                           Improvement of airfield drainage system at UVF

    IN00891202
    ►Airfield resilience plan prepared for UVF (Yes/No, Custom)

                                       Baseline                    Actual (Previous)          Actual (Current)          End Target

    Value                              No                          --                         No                        Yes

    Date                               31-Mar-2020                 --                         10-Sep-2020              30-Jun-2027



11/13/2020                                                                                                                 Page 4 of 9
           The World Bank                                                                                      Implementation Status & Results Report
           Saint Lucia - Caribbean Regional Air Transport Connectivity Project (P170860)




   Comments:                           Airfield resilience plan for UVF is prepared.

    IN00891204
    ►Firefighters control room upgraded at UVF (Yes/No, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                              No                           --                           No                        Yes

    Date                               31-Mar-2020                  --                           10-Sep-2020              30-Jun-2027

   Comments:                           Firefighters control room at UVF is upgraded.

    IN00891205
    ►Annual passenger volume of UVF (Number, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                              830,000.00                   --                           830,000.00                1,000,000.00

    Date                               31-Dec-2018                  --                           31-Dec-2018              30-Jun-2027

                                       Number of annual passenger volume of UVF who will be benefited by the safer and more resilient UVF
   Comments:
                                       airport once the project interventions are completed.


   Modernization of Air Navigation Systems

    IN00891187
    ►ILS approach installed for UVF Runway (Yes/No, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                              No                           --                           No                        Yes

    Date                               31-Mar-2020                  --                           10-Sep-2020              30-Jun-2027

   Comments:                           ILS approach system is installed for UVF Runway for arrival flights.

    IN00891191
    ►ADS-B monitors installed for UVF and SLU (Yes/No, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                              No                           --                           No                        Yes

    Date                               31-Mar-2020                  --                           10-Sep-2020              30-Jun-2027

   Comments:                           Installation of ADS-B monitors at UVF and SLU.

    IN00891195
    ►Number in Saint Lucia-based aircraft equipped with ADS-B (Number, Custom)

                                       Baseline                     Actual (Previous)            Actual (Current)          End Target

    Value                              0.00                         --                           0.00                      3.00




11/13/2020                                                                                                                    Page 5 of 9
           The World Bank                                                                                      Implementation Status & Results Report
           Saint Lucia - Caribbean Regional Air Transport Connectivity Project (P170860)




    Date                               31-Mar-2020                 --                            10-Sep-2020              30-Jun-2027

                                       Number in Saint Lucia-based aircraft equipped with ADS-B technology. As of March 2020, 3 helicopters
   Comments:
                                       are registered in Saint Lucia as a whole.
    IN00891198
    ►UVF Aeronautical Charts updated (Yes/No, Custom)

                                       Baseline                       Actual (Previous)          Actual (Current)          End Target

    Value                              No                          --                            No                        Yes

    Date                               31-Mar-2020                 --                            10-Sep-2020              30-Jun-2027

   Comments:                           UVF Aeronautical Charts is updated



   Institutional Strengthening

    IN00891188
    ►Air Traffic Controllers trained on updated equipment and aeronautical charts (Yes/No, Custom)

                                       Baseline                       Actual (Previous)          Actual (Current)          End Target

    Value                              No                          --                            No                        Yes

    Date                               31-Mar-2020                 --                            10-Sep-2020              30-Jun-2026

   Comments:                           Air Traffic Controllers trained on updated equipment and aeronautical charts

     IN00891193
     Percentage of female participants of training (Percentage, Custom Supplement)

                                     Baseline                    Actual (Previous)              Actual (Current)          End Target

     Value                           0.00                        --                             0.00                      50.00

    IN00891196
    ►Gap analysis conducted on airport operational capacity (Yes/No, Custom)

                                       Baseline                       Actual (Previous)          Actual (Current)          End Target

    Value                              No                          --                            No                        Yes

    Date                               31-Mar-2020                 --                            10-Sep-2020              30-Jun-2027

   Comments:                           Gap analysis conducted on airport operational capacity

    IN00891199
    ►Change in number of women hired for middle-skilled jobs by SLASPA (Percentage, Custom)

                                       Baseline                       Actual (Previous)          Actual (Current)          End Target

    Value                              0.00                        --                            0.00                      50.00

    Date                               31-Mar-2020                 --                            10-Sep-2020              30-Jun-2027

                                       Change in number of women hired for middle-skilled jobs by SLASPA. The definition of middle-skilled job
   Comments:
                                       will be determined during the implementation.


11/13/2020                                                                                                                    Page 6 of 9
           The World Bank                                                                                      Implementation Status & Results Report
           Saint Lucia - Caribbean Regional Air Transport Connectivity Project (P170860)



    IN00891201
    ►Semi-annual meetings held with stakeholders to discuss their suggestions and related actions taken by the project (Number, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                        --                            0.00                       12.00

    Date                               31-Mar-2020                 --                            10-Sep-2020                30-Jun-2027

                                       Number of meeting minutes documenting the discussion on decisions and/or actions taken based on
   Comments:
                                       stakeholders' focus group's feedback
    IN00891203
    ►Share of women included in the medium-skills training (Percentage, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                        --                            0.00                       30.00

    Date                               31-Mar-2020                 --                            10-Sep-2020                30-Jun-2027
                                       The project will finance training by a certified agency for SLASPA and ECCAA capacity building for
                                       development of medium skills, including those related to air traffic controllers, supervisors, and public
   Comments:
                                       safety and security screening staff. The indicator will measure how many women will participate in this
                                       training


   Project Management

   IN00891189
   ►Percentage of grievances received by project staff that are addressed according to the agreed GRM procedures and the results
   communicated back to the involved stakeholders (Percentage, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                        --                            0.00                       100.00

    Date                               31-Mar-2020                 --                            10-Sep-2020                30-Jun-2027
                                       The indicator will monitor the claims submitted to the GRM and follow-up actions. PIU under SLASPA will
                                       ensure that the GRM will receive claims from stakeholders and respond in accordance to the agreed GRM
   Comments:
                                       procedures. Stakeholders include neighboring communities, airport passengers, civil society
                                       organizations, airlines, cargo handlers, ECCAA, relevant governmental agencies, etc.
    IN00891192
    ►Number of stakeholder meetings held to discuss the decisions and/or actions taken based on beneficiaries’ feedback. (Number, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                        --                            0.00                       12.00

    Date                               31-Mar-2020                 --                            10-Sep-2020                30-Jun-2027

                                       Number of stakeholder meetings held to discuss the decisions and/or actions taken based on
   Comments:
                                       beneficiaries’ feedback. At least semi-annually during the project implementation period.


 Performance-Based Conditions



 Data on Financial Performance



11/13/2020                                                                                                                      Page 7 of 9
           The World Bank                                                                                   Implementation Status & Results Report
           Saint Lucia - Caribbean Regional Air Transport Connectivity Project (P170860)




 Disbursements (by loan)

 Project       Loan/Credit/TF     Status       Currency        Original   Revised     Cancelled     Disbursed     Undisbursed                % Disbursed


 P170860       IDA-66530          Effective    USD               45.00      45.00            0.00        0.00           45.00                         0%


 Key Dates (by loan)

 Project        Loan/Credit/TF     Status      Approval Date       Signing Date     Effectiveness Date    Orig. Closing Date      Rev. Closing Date

 P170860        IDA-66530          Effective   28-May-2020         31-Jul-2020      16-Oct-2020           30-Jun-2027             30-Jun-2027


Cumulative Disbursements




 PBC Disbursement

                                                                                           Achievement   Disbursed amount in         Disbursement %
 PBC ID                     PBC Type    Description             Coc       PBC Amount
                                                                                           Status        Coc                         for PBC




11/13/2020                                                                                                                     Page 8 of 9
         The World Bank                                                                  Implementation Status & Results Report
         Saint Lucia - Caribbean Regional Air Transport Connectivity Project (P170860)




  Restructuring History


  There has been no restructuring to date.


  Related Project(s)


 There are no related projects.




11/13/2020                                                                                              Page 9 of 9