Procurement Plan, RRP-II: H.P. June 13 Revised Procurement Plan for the project Rural Roads Project -II (PMGSY) For Himachal Pradesh Effective 7 Aug 2013 This is an indicative plan prepared by the Project for the period of 18 months starting June 2013. The Project shall update the Procurement Plan annually or as needed throughout the duration of the project in agreement with the Bank to reflect the actual project implementation needs and improvements in institutional capacity. The Project shall implement the Procurement Plan in the manner in which it has been approved by the Bank. This plan has been reviewed during negotiations I. General 1. Bank’s approval Date of the procurement Plan November 24, 2010 2. Date of General Procurement Notice issued for Consultancies only: September 14, 2010. Updated GPN for the complete project is to be issued. 3. Period covered by this procurement plan: For the entire project period II. Goods and Works 1. Procurement Methods and Prior Review Threshold: Procurement Decisions shall be subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. Expenditure Category Procurement Method Prior Review Threshold Comments US$ GOODS, EQUIPMENT & MACHINERY 1. Goods and Equipment ICB All contracts World Bank SBD will be used and the estimated to cost equivalent of procurement will be as per procedures US$ 300,000 or more per described in World Bank Guidelines contract Page 1 of 31 Procurement Plan, RRP-II: H.P. June 13 2. Goods and Equipment NCB First contract for goods for The NCB bidding document agreed with estimated to cost less than each state , irrespective of GOI will be used and the procurement will US$ 300,000 and greater than value and all contracts be as per procedures described in the US$ 100,000 equivalent per estimated to cost more than Procurement and Contract Management contract US$ 200,000 equivalent per Manual. contract 3. Goods and Equipment Shopping procedure with at All post review estimated to cost less than least three quotations from US$ 100,000 equivalent per qualified bidders in contract accordance with the provisions of paragraph 3.5 of procurement Guidelines. Procurement through DGS&D rate contracts will be considered equivalent to shopping procedure. 4. Goods and Equipment that Direct Contracting Upto US$ 10000 post review meet the requirements of and balance prior review paragraph 3.6 and 3.7 of Procurement Guidelines. ct CIVIL WORKS 5. Civil works contracts ICB * All contracts World Bank SBD will be used and the . estimated to cost more than procurement will be as per procedures US$ 10,000,000 equivalent described in World Bank Guidelines. per contract Civil works contracts NCB First contract for works for The procurement will be done as per 6. estimated to cost up to US$ each state, irrespective of procedures described in the Procurement 10,000,000 equivalent per value and all contracts cum Contract Management Manual and contract estimated to cost more than using the « Model Bidding Document » Page 2 of 31 Procurement Plan, RRP-II: H.P. June 13 US$ 5,000,000 equivalent cleared by the Bank per contract will be subject to prior review by the Bank. All other works contracts will be subject to post review. * As per current planning, no ICB contracts are envisaged for civil works. 2. Pre-qualification. Not Applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: A Procurement cum contract Management Manual is already circulated by NRRDA after taking WB into confidence. All procurement in the project will be done as per procedures described in it. . 5. Any Other Special Procurement Arrangements: The following provisions constitute additional provisions applicable for purposes of National Competitive Bidding (NCB). NCB will be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines and the following provisions:  Only the model bidding documents for procurement of works through NCB agreed with the Bank (and as amended for time to time), shall be used for bidding;  No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small scale enterprises or enterprises from any given State;  Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; Page 3 of 31 Procurement Plan, RRP-II: H.P. June 13   The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project;  However, as an exception in this project, two part bidding for NCB works (as described in the model bidding document) has been agreed by the Bank subject to appropriate fiduciary safeguards(e- procurement system and complaint handling mechanism acceptable to the Bank)  All procurement of works through NCB in the seven participating states will be done through a standardized e-procurement system acceptable to the Bank.  As per paragraph 1.14(e) of the World Bank's Procurement Guidelines, the Association's right to inspect the accounts and records of bidders, suppliers and contractors will be included in the bidding documents. III. Selection of Consultants 1. Selection Methods and Prior Review Threshold: Selection decisions shall be subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Expenditure x Selection Method Prior Review Threshold Category Value threshold per contract Consultancy -Quality and Cost Based (QCBS) method All prior review. contracts to be Each contract estimated to cost -REOI to be published in UNDB on line awarded to US$ 200,000 equivalent or Consultant firms more per contract including -Quality and Cost Based (QCBS) method All single source selection of selection of Each contract estimated to cost -Quality Based (QBS) method of selection consultants with estimated cost Page 4 of 31 Procurement Plan, RRP-II: H.P. June 13 training institutes less than US$ 200,000 in accordance with the provisions of of more than US$ 30,000 by equivalent per contract paragraph 3.1 to 3.4 of Consultant’s equivalent per contract will be NRRDA/SRRDAs Guidelines. subject to prior review. All -Consultant’s Qualifications (CQS) method. other contracts will be subject to -Least Cost Method (LCS). post review but with TORs -Fixed BudgetMethod. subject to prior review by the -Single Source Selection Bank Individual Consultant -Through comparison of qualifications of at All cases subject to post review estimated to cost less than US$ least three candidates. but with TORs subject to prior 30,000 or equivalent per review by the Bank. contract All contracts for single source -Sole Source Selection d\selection of individual consultant will be subject to prior review. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. Any Other Special Selection Arrangements: NIL Page 5 of 31 Procurement Plan, RRP-II: H.P. June 13 Rural Roads Project II (P124639) Procurement Packages with Methods and Time Schedule Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 1 HP-08-237 Maloh to Saryun road 3.000 97.03 NCB Post Awarded In Progress 2 HP-08-242 Shanan to Arthi road 5.775 154.06 NCB Post Awarded In Progress 3 HP-09-255 Mehli to Gusan road 5.420 177.22 NCB Post Completed 4 HP-09-272 Link road to vill. Dhanoti. 3.000 132.36 NCB Post Awarded In Progress 5 HP-11-57 Pater Bhonku to Hatra road 2.600 44.35 NCB Post Completed Changar Ghumaran to 6 HP-11-58 4.110 182.22 NCB Post Awarded In Progress Nissal road. Kumsu Bahwa to Kathanda 7 HP-06-97 4.000 118.69 NCB Post Awarded In Progress road 8 HP-01-112 Ghyal to Dabar road. 11.000 502.61 NCB Post Awarded In Progress Link road from Sirmani to 9 HP-04-01 2.585 87.89 NCB Post Awarded In Progress Mandhu. Link road from Rulehar to 10 HP-04-02 3.880 351.94 NCB Post Awarded In Progress Lam Page 6 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 11 HP-04-19 Manai to Bharuplahar road 2.130 151.42 NCB Post Awarded In Progress 12 HP-04-155 Bhatoli to Bhalun road 4.930 430.54 NCB Post Awarded In Progress 13 HP-04-154 Bharwain to Gural road 3.520 158.30 NCB Post Awarded In Progress 14 HP-04-172 Dehra to Kuhru road 2.825 178.22 NCB Post Awarded In Progress 15 HP-04-177 Mandeli to Narwari road. 1.675 56.26 NCB Post Awarded In Progress 16 HP-04-170 Hatli to Mohli khas road. 3.430 161.78 NCB Post Awarded In Progress 17 HP-04-180 Bathra to Swanta road. 4.045 225.00 NCB Post Awarded In Progress Damtal Kandwal road to 18 HP-04-162 2.690 85.32 NCB Post Awarded In Progress vill. Jangal Thapkaur. 19 HP-04-178 Gangath to Dadoh-II- road. 2.900 146.24 NCB Post Awarded In Progress 20 HP-04-176 Chougan to Gudli-II- road. 1.000 38.40 NCB Post Awarded In Progress 21 HP-01-115 Jhabola to Goacher road 6.000 73.85 NCB Post Awarded In Progress 22 HP-01-113 Fish farm to vill. Deoli. 1.195 16.81 NCB Post Awarded In Progress 23 HP-01-114 Badaghat to Kassaru road. 1.600 22.48 NCB Post Awarded In Progress Gaila Barodi Kaiga road 24 HP-02-163 (portion Bhamuin to 2.400 48.16 NCB Post Awarded In Progress Barodi). 25 HP-02-147 Mohri to Kuthar road 2.900 54.92 NCB Post Awarded In Progress 26 HP-02-171 Bhanota to Bharara road 7.500 222.69 NCB Post Awarded In Progress 27 HP-02-169 Link road to Vill. Shikari. 3.000 81.91 NCB Post Awarded In Progress 28 HP-02-133 Guila to Devikothi road 2.500 41.90 NCB Post Awarded In Progress Colony Mod to Tissa sawa 29 HP-02-165 Saranger road (portion 5.500 182.60 NCB Post Awarded In Progress Madan salancha to Padher). 30 HP-02-134 Rajindoo to Kureel road. 2.000 32.19 NCB Post Awarded In Progress Page 7 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 31 HP-02-161 Link road to vill. Ohli. 1.300 18.28 NCB Post Awarded In Progress 32 HP-02-146 Gugoi to Jambal road 2.825 46.86 NCB Post Awarded In Progress 33 HP-02-130 Kakira to Chalma road 4.300 48.20 NCB Post Awarded In Progress 34 HP-02-150 Mandhiar to Baloh road 4.700 64.99 NCB Post Awarded In Progress 35 HP-02-172 Samote to Surpura road 5.000 137.87 NCB Post Awarded In Progress 36 HP-02-128 Godra to Siuni road 3.195 53.09 NCB Post Awarded In Progress 37 HP-02-174 Bariangala to Taragarh road. 3.490 72.28 NCB Post Awarded In Progress T-01 to Gowahla road 38 HP-02-157 1.480 33.31 NCB Post Awarded In Progress (section Tooh to Gowari ) Bounkharimour to Nagali 39 HP-02-167 8.250 155.26 NCB Post Awarded In Progress road. 40 HP-02-144 Tunnuhatti to Rohni road 2.800 45.35 NCB Post Awarded In Progress 41 HP-02-139 Balley to Khaddi road 4.200 53.83 NCB Post Awarded In Progress 42 HP-02-154 Lader to Chihi road 10.350 231.66 NCB Post Awarded In Progress 43 HP-02-155 Kalog to Sudla road 6.300 140.87 NCB Post Awarded In Progress 44 HP-02-149 Hutta to Ligga Ladwah road. 7.040 145.53 NCB Post Awarded In Progress 45 HP-02-129 Link road to vill. Simni. 2.570 39.46 NCB Post Awarded In Progress 46 HP-02-143 Link road to vill. Kuthed. 6.000 93.74 NCB Post Awarded In Progress 47 HP-02-173 Bharari to Fagla road. 1.300 33.10 NCB Post Awarded In Progress 48 HP-03-48 Link road to vill. Sapahal 1.500 40.40 NCB Post Awarded In Progress 49 HP-03-05 Link road to vill. Darogan 1.700 40.18 NCB Post Completed 50 HP-03-03 Herata Bhaloo road. 3.760 99.54 NCB Post Awarded In Progress 51 HP-03-02 Link road to vill. Sai. 1.500 47.66 NCB Post Awarded In Progress 52 HP-03-02 Link road to vill. Galol. 0.890 22.94 NCB Post Awarded In Progress 53 HP-04-11 Icchi to Kalandlehar road. 1.710 33.42 NCB Post Awarded In Progress Page 8 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 54 HP-04-16 Bhatlahru to Pathiyar road 3.550 72.31 NCB Post Awarded In Progress Uperla Odder to Bangrehr 55 HP-04-13 1.435 28.01 NCB Post Completed road. 56 HP-04-12 Charri to Bhitlu road. 5.780 135.52 NCB Post Awarded In Progress Jhikli Bhatoli to Tikkar 57 HP-04-88 6.000 62.04 NCB Post Completed road. 58 HP-04-173 Totru to Alloh road 3.150 58.25 NCB Post Completed 59 HP-04-111 Jagnoli to Nigal road. 13.000 250.16 NCB Post Awarded In Progress Jadhaman to Upper Balwal 60 HP-04-152 1.750 30.52 NCB Post Awarded In Progress road. 61 HP-04-174 Chalali to Sukar road. 2.150 72.51 NCB Post Awarded In Progress Masroor to Dhanger khas 62 HP-04-164 7.000 152.14 NCB Post Awarded In Progress road Link road afrom Paliyar to 63 HP-04-169 NCB Post Awarded In Progress Garna road 3.585 48.53 Link road afrom Paliyar to 64 HP-04-169 NCB Post Awarded In Progress Garna road 65 HP-04-165 Kandredi to Chandua road 4.000 66.35 NCB Post Awarded In Progress 66 HP-04-167 Bagga to Tharoo road. 1.210 19.26 NCB Post Completed 67 HP-04-18 Link road to village Gadiara. 1.540 43.81 NCB Post Awarded In Progress 68 HP-04-23 Tamber to Majhoti road. 1.510 33.99 NCB Post Awarded In Progress Chadhiar to Matial Khurd 69 HP-04-04 1.780 37.49 NCB Post Awarded In Progress road. 70 HP-04-05 Link road to vill. Dhaneri. 0.900 18.10 NCB Post Awarded In Progress 71 HP-04-157 Link road to village Paniala. 2.555 47.13 NCB Post Awarded In Progress Page 9 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 72 HP-06-05 Bharai to Peej road 7.855 200.44 NCB Post Awarded In Progress Neoli ( Rogimour) to 73 HP-06-22 3.850 166.89 NCB Post Awarded In Progress Larikot road Bari Padharu to Tharku 74 HP-06-03 3.500 154.97 NCB Post Awarded In Progress Pechha road 75 HP-08-56 Cholthara to Kothi road. 13.500 177.81 NCB Post Awarded In Progress 76 HP-08-20 Tihra to Kot road 4.000 70.73 NCB Post Awarded In Progress Dharampur to Chapanu 77 HP-08-70 4.000 67.24 NCB Post Awarded In Progress road. 78 HP-08-19 Chalali to Reyur road 2.500 42.20 NCB Post Awarded In Progress 79 HP-08-19 Longni to Sari road 6.210 106.00 NCB Post Awarded In Progress 80 HP-08-19 Baroti to Chowki road 3.000 52.67 NCB Post Awarded In Progress 81 HP-09-35 Kacholi Kandi Odda road. 4.000 115.33 NCB Post Awarded In Progress Khoronwala (Shyampur 82 HP-10-130 Bhood) to Manpur Deora 1.700 36.34 NCB Post Awarded In Progress road. Link road to village 83 HP-10-148 14.250 380.91 NCB Post Awarded In Progress Chhacheti. 84 HP-12-91 Makrer to Chaukhat road 7.000 202.90 NCB Post Awarded In Progress 85 HP-12-89 UAM road to vill. Sasan. 1.510 35.10 NCB Post Completed Una Basoli road to vill. 86 HP-12-90 5.630 140.01 NCB Post Completed Lamlehri Nichli road Jablanda to Kiarkoti up to In Progress 87 HP-09-293 8.200 284.07 NCB Post Awarded Village Parni road 88 HP-09-294 Kogi to Seon road 3.700 153.27 NCB Post Awarded In Progress Page 10 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 89 HP-04-153 Bathu to Jalera road 3.500 89.19 NCB Post 17th June 2013 Under Process 90 HP-02-162 Ludera Sungal Paluin road. 7.500 179.56 NCB Post 16.09.13 Recalled Ludera Suri Kaila road upto 91 HP-02-132 5.540 81.73 NCB Post 16.09.13 Recalled vill. Suri. 92 HP-02-170 Trella to Bunreri road 4.500 132.74 NCB Post 16.09.13 Recalled Link road to vill. Chhapa 93 HP-02-136 2.250 35.95 NCB Post 16.09.13 Recalled (Dob Darkund to Nera) Ludera Suri Kaila road 94 HP-02-175 10.000 279.66 NCB Post 16.09.13 Recalled (Portion Suri to Kaila). 95 HP-02-184 Bairagarh to Chanju road. 7.500 218.47 NCB Post 17th June 2013 Under Process Bairagarh Devikothi road 96 HP-02-176 (Portion Devikothi to 5.900 166.25 NCB Post 16.09.13 Recalled Teppa). 97 HP-02-135 Rori Gaila Gatyanu road. 5.000 73.80 NCB Post 16.09.13 Recalled 98 HP-02-137 Link road to vill. Rajindoo. 3.000 46.20 NCB Post 17th June 2013 Under Process 99 HP-02-140 Gehra to Marour road. 3.500 87.76 NCB Post 16.09.13 Recalled 100 HP-02-138 Rajera to Dhullara road. 1.600 25.84 NCB Post 16.09.13 Recalled 101 HP-02-166 Link road to vill. Sunara. 3.000 89.04 NCB Post 16.09.13 Recalled Bhanara Pariungal Jatkari 102 HP-02-164 road (portion Bhanara to 5.370 136.84 NCB Post 16.09.13 Recalled kolka). Page 11 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 103 HP-02-145 Panjla to Koid road 4.000 65.37 NCB Post Awarded In Progress 104 HP-02-148 Link road to vill. Jantra. 5.000 121.09 NCB Post 16.09.13 Recalled 105 HP-02-141 Link road to vill. Mindhal. 2.890 51.03 NCB Post 16.09.13 Recalled 106 HP-02-142 Dhakog to Thalla road. 7.000 149.62 NCB Post 16.09.13 Recalled Killar to Hudan Bhatori 107 HP-02-179 14.600 420.33 NCB Post 16.09.13 Recalled road. Mahllu Nallah to Seri kothi 108 HP-02-183 8.000 208.04 NCB Post 16.09.13 Recalled Kariyuni road. 109 HP-02-160 Link road to vill. Rei. 3.690 66.38 NCB Post 16.09.13 Recalled 110 HP-02-181 GREF road to vill. Luj road. 2.500 47.47 NCB Post 16.09.13 Recalled 111 HP-02-182 Sach Kumar to Parmar road. 11.280 332.89 NCB Post 16.09.13 Recalled 112 HP-02-180 Saichu to Shoon Leo road. 6.400 177.78 NCB Post 16.09.13 Recalled Lahar to Sangrahian 113 HP-02-168 5.500 99.83 NCB Post Awarded In Progress (Section Lahar to Kurla). 114 HP-02-156 Jalaot to Panjei road 11.410 240.24 NCB Post 16.09.13 Recalled 115 HP-02-152 Kuther to Khandwara road 12.100 259.42 NCB Post 16.09.13 Recalled Sundla Girjindoo road to 116 HP-02-158 6.255 133.05 NCB Post 16.09.13 Recalled Kund Suila road. Page 12 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 117 HP-02-153 Salooni to Ghal road 7.500 155.00 NCB Post 16.09.13 Recalled Likely to be Bid Opened on 118 HP-03-01 Nara to Chhaproh road. 1.500 24.72 NCB Post awarded by 14th 25th April 2013 August 13 Likely to be Bid Opened on 119 HP-03-01 Dugwar to Changar road. 1.375 22.41 NCB Post awarded by 14th 25th April 2013 August 13 Bid Opened on 120 HP-04-171 Link road to village Pukhru 2.450 31.83 NCB Post Under Process 25th April 2013 121 HP-04-168 Koke dhatti to Parmala road 3.500 59.38 NCB Post 16.09.13 Under Process 122 HP-04-17 Thehar Uperli to Kudang. 0.900 15.25 NCB Post 16.09.13 Under Process 123 HP-04-07 Chadhiar to Rupehr road. 0.600 12.38 NCB Post 16.09.13 Under Process 124 HP-04-24 Majheen to Sialkhar road. 2.800 56.99 NCB Post Awarded In Progress 125 HP-06-04 Bhuin to Shillihar road. 6.100 183.20 NCB Post Awarded In Progress 126 HP-06-23 Bhekhali to Bastori road 6.075 141.54 NCB Post 09.09.13 Recall 127 HP-06-23 Fozal to Flain road. 5.600 169.83 NCB Post 09.09.13 Recall 128 HP-06-02 Benchi to Manjhlihar road. 7.340 245.31 NCB Post 09.09.13 Recall 129 HP-06-31 Mansari to Soil road 1.800 42.92 NCB Post Awarded In Progress 130 HP-06-26 Kais to Kotadhar road. 7.650 211.39 NCB Post Awarded In Progress Page 13 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 131 HP-06-16 Dohra nallah to Khariar road 8.660 266.26 NCB Post 09.09.13 Recall 132 HP-06-24 Banala to Ninu road. 3.690 175.81 NCB Post Awarded In Progress Khora Age to Bhallan -II- 133 HP-06-18 10.862 359.98 NCB Post Awarded In Progress road. 134 HP-06-07 Bhuinka pul to Kotla road 10.800 376.85 NCB Post 09.09.13 Recall 135 HP-06-20 Damothi to Bharthidhar road 10.000 391.71 NCB Post Awarded In Progress 136 HP-06-21 Salwar to Kanon road 5.880 311.72 NCB Post 06.08.13 Recall Bids Opened on 137 HP-06-14 Brow to Poshana road 13.180 411.91 NCB Post Under Process 26th April 13 Bids Opened on 138 HP-06-13 Nainavati to Kared road 11.800 250.52 NCB Post Under Process 26th April 2013 Bids Opened on 139 HP-06-27 Soidhar to beungal road 9.855 266.28 NCB Post Under Process 26th April 2013 Bids Opened on 140 HP-06-09 Ranabag to Karshaigad 14.510 327.31 NCB Post Under Process 26th April 2013 Avera (Devidhank) to Bids Opened on 141 HP-06-15 10.600 267.95 NCB Post Under Process Ghattu road 26th April 2013 Bids Opened on 142 HP-06-12 Bagipul to Jaon road 11.000 275.34 NCB Post Under Process 26th April 2013 143 HP-08-11A Lahri to Chhanchher road. 3.000 65.71 NCB Post 06.08.13 Recall Page 14 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS Link road to gram panchayat 144 HP-08-25 1.640 38.97 NCB Post 06.08.13 Recall Pipli. 145 HP-08-11 Arla to Bhaila road. 4.000 93.68 NCB Post Awarded In Progress 146 HP-08-24 Bajrour to Ropri road. 1.640 31.03 NCB Post Awarded In Progress 147 HP-08-50 A Nandal to Arnehar road. 11.510 279.56 NCB Post 09.09.13 Recall Bids Opened on 148 HP-09-287 Shillaroo to Reog road 13.500 220.60 NCB Post Under Process 22nd May 2013 Bids Opened on 149 HP-09-286 Guthan to Sharmala road 4.270 68.21 NCB Post Under Process 22nd May 2013 150 HP-09-289 Koti to Piran road 28.020 585.15 NCB Post Awarded In Progress 151 HP-09-290 Anandpur to Kot road 8.500 183.46 NCB Post Awarded In Progress 152 HP-09-288 Bhawana to Cheri road 4.330 76.43 NCB Post Awarded In Progress Shoghi to Goro Kanwan 153 HP-09-291 5.500 91.31 NCB Post Awarded In Progress road Bid opened on 154 HP-09-292 Bharari to Bhont road 4.000 61.98 NCB Post Under Process 17th June 2013 Bids Opened on 155 HP-09-300 Sangti to Neri road. 7.300 164.60 NCB Post Under Process 22nd May 2013 Bangora to Basti Gunana 156 HP-09-299 12.500 333.13 NCB Post Awarded In Progress road. Page 15 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS Bids Opened on 157 HP-09-296 Machoti to Bhoot road. 9.000 236.59 NCB Post Under Process 22nd April 2013 158 HP-09-298 Bhaloon to Kui road. 9.000 258.22 NCB Post Awarded In Progress 159 HP-09-297 Samarkot to Shalawat road. 3.500 94.67 NCB Post Awarded In Progress Bid opened on 160 HP-09-19 Link road to vill. Shakrori. 1.087 23.36 NCB Post Under Process 17th June 2013 Bid opened on 161 HP-09-17 Link road to vill. Dharogra. 8.100 174.02 NCB Post Under Process 17th June 2013 Bid opened on 162 HP-09-09 Link road to vill. Mandyalu. 2.820 60.50 NCB Post Under Process 17th June 2013 T-04 to Puruwala 163 HP-10-147 1.000 22.57 NCB Post Awarded In Progress Kanshipur road. T-04 to Kishanpura 164 HP-10-146 1.420 34.56 NCB Post Awarded In Progress Bainkuan road. Link road from NH-72 to 165 HP-10-149 3.000 107.89 NCB Post Awarded In Progress Harijan Basti Sainwala. Link road to village 166 HP-10-150 4.150 135.03 NCB Post Awarded In Progress Lohgarh. Katasan to Uttamwala Bid opened on 167 HP-10-145 2.300 69.34 NCB Post Under Process Baraban road. 17th June 2013 Bids Opened on 168 HP-10-144 Kun to Nehrla road. 3.200 109.88 NCB Post Under Process 16th March 13 169 HP-11-62 Dame site to Bissa road. 8.000 173.38 NCB Post Awarded In Progress Page 16 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 170 HP-11-61 Link to vill. Wakna. 2.000 36.75 NCB Post Awarded In Progress Jaunaji to Dharo ki Dhar 171 HP-11-68 6.720 83.56 NCB Post Awarded In Progress road. 172 HP-11-66 Kanwala to Bughar road. 8.720 171.25 NCB Post Awarded In Progress Bid opened on 173 HP-11-63 Arki to Jalana road. 4.823 76.56 NCB Post Under Process 17th June 2013 174 HP-11-64 Link road to vill. Kotla. 1.256 22.51 NCB Post Awarded In Progress Bid opened on 175 HP-11-65 Link road to vill. Turu. 2.726 39.55 NCB Post Under Process 17th June 2013 Bid opened on 176 HP-11-60 Link to vill. Ghai. 6.300 119.12 NCB Post Under Process 17th June 2013 Bid opened on 177 HP-11-59 Link to vill. Kiyard. 6.000 114.45 NCB Post Under Process 17th June 2013 Sanctioned on 178 HP-02-177 Lachori to Seri road. 8.000 216.98 NCB Post 25th June 2013 09-04-13 Sundla to Bachuni (Sundla 179 HP-02-178 4.600 107.71 NCB Post Awarded In Progress to Pukhri) Bid received 180 HP-02-185 Hutta to Darakeri road. 1.450 59.61 NCB Post 25th June 2013 Under Process Bid received 181 HP-02-190 Kuthar to Mouwa road. 3.400 76.05 NCB Post 25th June 2013 Under Process Kuther (Kainthly) to Bid received 182 HP-02-195 6.570 153.79 NCB Post 25th June 2013 Malunda road Under Process Page 17 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS Bid received 183 HP-02-186 Rajain to Dungru road. 1.500 29.50 NCB Post 25th June 2013 Under Process 184 HP-02-187 Banoon to Awan road. 3.000 58.17 NCB Post Awarded In Progress 185 HP-02-197 Kalam bridge to Banet road 2.900 96.05 NCB Post 25th June 2013 Awarded Bid received 186 HP-02-191 Thala to Mando road 8.000 70.96 NCB Post 9th July 2013 Under Process Bid received 187 HP-02-193 Mando to Serkao road 5.500 49.19 NCB Post 9th July 2013 Under Process Bid received 188 HP-02-192 Dinka to Barai road 3.180 44.13 NCB Post 25th June 2013 Under Process Bid received 189 HP-03-19 Gadhiara to Kuthera road. 2.000 55.08 NCB Post 5th July 2013 Under Process Bid received 190 HP-04-51 Simbal to Mehala road. 1.660 65.11 NCB Post 9th July 2013 Under Process Palampur to Tanda Parla Bid received 191 HP-04-52 1.550 49.51 NCB Post 9th July 2013 road. Under Process Bid received 191 HP-04-53 Sungal to Matt road. 1.400 44.36 NCB Post 29th June 2013 Under Process Bid received 193 HP-04-54 Aweri to Lachhun road. 1.150 33.65 NCB Post 29th June 2013 Under Process Bid received 194 HP-04-56 Aweri to Aweri khas road. 1.430 54.61 NCB Post 29th June 2013 Under Process 195 HP-04-14 Oddar to Lanjhani road. 2.200 67.18 NCB Post Awarded In Progress Page 18 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 196 HP-04-06 Loharkar to Ruhru road. 1.510 119.40 NCB Post Awarded In Progress Bid received 197 HP-04-55 Pihar to Duhak Kunni road. 1.730 57.42 NCB Post 29th June 2013 Under Process Bid received 198 HP-04-57 Barot to Nalotha road. 15.225 454.29 NCB Post 29th June 2013 Under Process Link road to vill. Bid received 199 HP-04-22 1.000 36.15 NCB Post 9th July 2013 Jamwalkhar Under Process Bid received 200 HP-04-186 Saprialu to Chhount road. 1.225 62.58 NCB Post 9th July 2013 Under Process Bid received 201 HP-04-03 Palera to Tilla road. 1.900 133.87 NCB Post 9th July 2013 Under Process Kotla Bassi to Malot Seul Bid received 202 HP-04-190 4.825 216.81 NCB Post 25th June 2013 road. Under Process Bid received 203 HP-04-181 Bagli to Mandwara road. 1.800 118.19 NCB Post 25th June 2013 Under Process Karoa Kalan to Mawa Bid received 204 HP-04-182 3.915 167.92 NCB Post 25th June 2013 Kundli road. Under Process Bid received 205 HP-04-189 Balghar to Landyara road. 4.250 109.71 NCB Post 25th June 2013 Under Process 206 HP-04-15 Baldhar to Jassour road. 4.000 172.51 NCB Post Awarded In Progress Bid received 207 HP-04-27 Sunhi Khas Pandol road. 2.600 54.57 NCB Post 25th June 2013 Under Process Sanctioned on 208 HP-04-32 Nihargalu to Barana road. 4.600 130.39 NCB Post 25th June 2013 09-04-13 Page 19 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS 209 HP-04-163 Larth to Banoli Khas road. 4.000 53.71 NCB Post Awarded In Progress Tikka Nagrota to Hathidhar 210 HP-04-187 9.120 312.53 NCB Post Awarded In Progress road. Sanctioned on 211 HP-04-20 Matehar to Baluhi road. 2.060 55.09 NCB Post 5th Sept 2013 09-04-13 Sanctioned on 212 HP-04-33 Longni to Bhagun road. 3.210 105.52 NCB Post 5th Sept 2013 09-04-13 Sanctioned on 213 HP-04-29 Thural to Bharanta road. 3.000 88.59 NCB Post 5th Sept 2013 09-04-13 Kangain to Garh Jamula 214 HP-04-28 1.405 30.14 NCB Post Awarded In Progress road. Bids Under 215 HP-05-08 Leo bridge to hango road. 16.000 436.57 NCB Post 2nd July 2013 Process Bids Under 216 HP-05-07 Lippa to Asrang road. 10.100 264.01 NCB Post 2nd July 2013 Process Bids Under 217 HP-05-06 NH-22 to Dubling road. 5.000 126.27 NCB Post 2nd July 2013 Process Bids Under 218 HP-06-95 Shroo to Kapti road. 8.000 568.26 NCB Post 8th July 2013 Process Bids Under 219 HP-06-96 Glad to Boong road. 3.120 213.16 NCB Post 8th July 2013 Process Bids Under 220 HP-06-119 Panasha to Badgai road. 3.000 130.31 NCB Post 8th July 2013 Process Bids Under 221 HP-06-41 Sharni to Pinni road. 15.180 604.80 NCB Post 8th July 2013 Process Page 20 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS Bids Under 222 HP-06-13 Churla to Khanipandh road. 7.500 282.16 NCB Post 28th June 2013 Process Bids Under 223 HP-06-69 Bhekhali to Sari road. 6.000 213.97 NCB Post 8th July 2013 Process Bids Under 224 HP-06-64 Ratocha to Dhara road. 5.000 256.43 NCB Post 28th June 2013 Process Bids Under 225 HP-07-03 Kiato to Chicham road. 18.810 422.52 NCB Post 2nd July 2013 Process Bids Under 226 HP-07-06 Chicham to Kibber road. 5.065 115.25 NCB Post 2nd July 2013 Process Bids Under 227 HP-07-04 Lidang to Damul road. 18.000 370.66 NCB Post 2nd July 2013 Process Bids Under 228 HP-07-05 Attargu to Lulang road. 14.000 313.89 NCB Post 2nd July 2013 Process Ghanganoo to Khanokhar Bids Under 229 HP-08-27 A 4.650 153.90 NCB Post 28th June 2013 road. Process Bids Under 230 HP-08-23 A Chambi to Kangar road. 3.600 95.20 NCB Post 28th June 2013 Process Bids Under 231 HP-08-48 Ladruhin to Khalai road. 1.780 61.76 NCB Post 24th July 2013 Process Sainthal to Bhala-Ka-Rihra Bids Under 232 HP-08-14 6.300 248.13 NCB Post 24th July 2013 road. Process Bids Under 233 HP-08-69 Khaddar to Khuddi road. 4.780 161.54 NCB Post 24th July 2013 Process Bids Under 234 HP-08-13 Lad Bharol to Triambli road. 4.250 132.15 NCB Post 24th July 2013 Process Page 21 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS Bids Under 235 HP-08-12 Gagal to Bhaghar road. 7.000 198.27 NCB Post 24th July 2013 Process Bids Under 236 HP-08-54 Darabil to Langara road. 3.080 64.39 NCB Post 29th June 2013 Process Bids Under 237 HP-08-15 Kunduni to Kass road. 3.030 107.50 NCB Post 29th June 2013 Process Bids Under 238 HP-08-34 A Gohar to Kanda road. 14.000 318.39 NCB Post 24th July 2013 Process Bids Under 239 HP-08-36 A Link road to village Shilnoo. 5.100 210.02 NCB Post 24th July 2013 Process Bids Under 240 HP-08-30 Nehra to Badharnu road. 2.570 80.52 NCB Post 28th June 2013 Process Bids Under 241 HP-08-116 Karsog to Bagaila road. 5.000 199.20 NCB Post 24th July 2013 Process Bids Under 242 HP-08-09 Kotlu to Nanj road. 5.000 135.24 NCB Post 28th June 2013 Process Bids Under 243 HP-08-10 Haylog to Pehad road. 10.000 223.34 NCB Post 5th July 2013 Process Bids Under 244 HP-08-33 Lakhrehar to Kujjabalh road. 5.855 133.79 NCB Post 5th July 2013 Process Dharampur to Saraskan Bids Under 245 HP-08-22 4.420 99.13 NCB Post 5th July 2013 road. Process Bids Under 246 HP-08-130 A Kuklah to Bagi road. 8.000 476.92 NCB Post 8th July 2013 Process Matiana Guthan to Dhar Bids Under 247 HP-09-295 5.485 219.65 NCB Post 24th July 2013 road. Process Page 22 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS Bids Under 248 HP-09-301 Kanur Nallah to Jau road. 2.570 122.23 NCB Post 24th July 2013 Process Rahighat to Kiartoo road up Bids Under 249 HP-09-303 4.000 170.18 NCB Post 24th July 2013 to vill. Balowa. Process Bhekhalty to Majhar Bids Under 250 HP-09-302 6.400 272.97 NCB Post 24th July 2013 (Khalashi ) road. Process Bids Under 251 HP-09-304 Kot to Barar road. 4.000 161.45 NCB Post 24th July 2013 Process Bids Under 252 HP-09-305 Kanda to Moolkoti road 9.240 361.62 NCB Post 20th July 2013 Process Elysium devidhar to Pagog Bids Under 253 HP-09-311 5.345 199.26 NCB Post 20th July 2013 road. Process Bids Under 254 HP-09-306 Koti Rohalti to Satlai road. 15.000 543.04 NCB Post 20th July 2013 Process Bids Under 255 HP-09-310 Tipra to Patgair road. 8.045 310.24 NCB Post 20th July 2013 Process Bids Under 256 HP-09-307 Satlai to Chikhar road. 1.600 61.69 NCB Post 31st July 2013 Process Bids Under 257 HP-09-308 Longwood to Barmu road. 3.190 96.05 NCB Post 31st July 2013 Process Bids Under 258 HP-09-309 Powabo to Dumi road. 3.270 116.34 NCB Post 31st July 2013 Process Bids Under 259 HP-09-314 Pujarli to Matal road 18.500 1048.07 NCB Post 31st July 2013 Process Bids Under 260 HP-09-312 Kuthar to Manu road 5.000 160.14 NCB Post 31st July 2013 Process Page 23 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS Bids Under 261 HP-09-313 Manu to Irra road 8.200 250.66 NCB Post 31st July 2013 Process Bids Under 262 HP-09-318 Dhadu to Dochi Deiya road 11.705 406.90 NCB Post 31st July 2013 Process Bids Under 263 HP-09-315 Nerwa to Bijmal road. 6.510 232.50 NCB Post 31st July 2013 Process Bids Under 264 HP-09-316 Belog to Rushlah road 7.855 260.72 NCB Post 31st July 2013 Process Bids Under 265 HP-09-20 Sunda to Jaguni road 5.550 188.11 NCB Post 31st July 2013 Process Ghanvi to Labana Sadana Bids Under 266 HP-09-33 8.000 231.37 NCB Post 31st July 2013 road Process Bids Under 267 HP-09-23 Ghanvi to Keo road 4.180 131.52 NCB Post 31st July 2013 Process Bids Under 268 HP-09-51 Ghanvi to Jagori road 9.545 251.26 NCB Post 31st July 2013 Process Bids Under 269 HP-09-21 Nankhari to Addu road 4.500 155.81 NCB Post 31st July 2013 Process Railla to Karoli (Khanog) Bids Under 270 3.000 120.41 NCB Post 31st July 2013 road. Process Railla (Karoli) to Dharunja Bids Under 271 HP-09-264 1.745 110.12 NCB Post 31st July 2013 road. Process Bids Under 272 HP-09-015 Nog to Kirti road 9.165 268.52 NCB Post 31st July 2013 Process Page 24 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS Bids Under 273 HP-09-58 Jimmu Nallah to Jal road 5.000 137.52 NCB Post 31st July 2013 Process Bids Under 274 HP-09-55 Kangal to Mogra road 4.765 193.94 NCB Post 31st July 2013 Process Bids Under 275 HP-09-135 Pharbuna to Pauchi road 3.900 157.47 NCB Post 31st July 2013 Process Bids Under 276 HP-09-43 Link road to vill. Kanthru 4.650 150.51 NCB Post 31st July 2013 Process Link road to vill. Bids Under 277 HP-09-124 1.280 51.77 NCB Post 31st July 2013 Madhawani Process Link road to vill. Baragaon Bids Under 278 HP-09-36 4.500 184.75 NCB Post 31st July 2013 Bargal Process Bids Under 279 HP-09-15 Link road to vill. Kupri 2.600 88.87 NCB Post 31st July 2013 Process Bids Under 280 HP-09-016 Link road to vill. Pharal 7.645 221.79 NCB Post 31st July 2013 Process Bids Under 281 Link road to vill. Bai. 0.690 20.04 NCB Post 31st July 2013 Process Bids Under 282 HP-09-56 Dargi to Judlu road. 7.900 190.75 NCB Post 31st July 2013 Process Bids Under 283 HP-09-319 Sharog to Bahli road 4.000 157.89 NCB Post 31st July 2013 Process Bids Under 284 HP-09-321 Link road to Kanda 4.000 174.91 NCB Post 31st July 2013 Process Bids Under 285 HP-09-320 Chirgaon to Chillala road 5.450 257.32 NCB Post 31st July 2013 Process Page 25 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS Km. 30/430 of Birla Gatu Bids Under 286 HP-10-142 4.000 203.05 NCB Post 31st July 2013 navi road to Purli. Process Kolar to Phandi Bodiwala Bids Under 287 HP-10-169 3.600 294.18 NCB Post 31st July 2013 road Process Mehat Gawana Khali Bids Under 288 HP-10-151 12.000 270.66 NCB Post 31st July 2013 Achhaun Kando Naddi road Process Bids Under 289 HP-10-166 Chandni to Kathwar road. 13.480 488.18 NCB Post 31st July 2013 Process Manal to Kanti Mashwa Bids Under 290 HP-10-165 13.350 490.62 NCB Post 31st July 2013 road. Process Bids Under 291 HP-10-124 Uttri Mour to Uttri road 2.600 122.90 NCB Post 31st July 2013 Process Baila Gujon to Kotapab Bids Under 292 HP-10-164 10.165 399.75 NCB Post 31st July 2013 road. Process Bids Under 293 HP-10-115 Jar Drabil to Kotion road 6.705 352.59 NCB Post 31st July 2013 Process Bids Under 294 HP-10-160 Thian bag to Gahal road. 10.500 568.48 NCB Post 31st July 2013 Process Bids Under 295 HP-10-161 Link road to vill. Choakar. 3.700 263.16 NCB Post 31st July 2013 Process Bids Under 296 HP-10-156 Link road to vill. Sainj. 2.915 185.25 NCB Post 31st July 2013 Process Bids Under 297 HP-10-157 Kharkoli to Ganog road. 9.170 553.20 NCB Post 31st July 2013 Process Bids Under 298 HP-10-163 Bhajond to Gatlog road. 8.000 503.13 NCB Post 15th July 2013 Process Page 26 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS Bids Under 299 HP-10-159 Jarog to Khood road. 9.000 412.15 NCB Post 15th July 2013 Process Bids Under 300 HP-10-162 Kharan to Deori road. 4.975 337.40 NCB Post 15th July 2013 Process Bids Under 301 HP-10-104 Khajurna to Dhakwali road. 3.435 262.43 NCB Post 15th July 2013 Process Bids Under 302 HP-10-158 NH-72 to Satiwala road. 1.120 66.78 NCB Post 15th July 2013 Process Neripul Dhamandu Tharu Bids Under 303 HP-10-154 road upto vill. Deothi 12.000 506.16 NCB Post 15th July 2013 Process Majhgaon. Giankot to Bhujjal via Matal Bids Under 304 HP-10-153 5.300 218.88 NCB Post 15th July 2013 road. Process Churwadhar Gadol Pirag Bids Under 305 HP-10-155 10.750 538.13 NCB Post 15th July 2013 road. Process Bids Under 306 HP-11-69 Manjholi to Lakhanpur road. 4.395 166.73 NCB Post 15th July 2013 Process Bids Under 307 HP-11-72 Bairchha to Gholowal road. 1.650 41.77 NCB Post 15th July 2013 Process Bids Under 308 HP-11-75 Bhini Johari to Lunas road. 7.000 290.65 NCB Post 15th July 2013 Process Bids Under 309 HP-11-70 Malonkhas to Jobi road 2.750 32.69 NCB Post 15th July 2013 Process Bids Under 310 HP-11-71 Link road to vill. Sauri. 2.250 53.54 NCB Post 15th July 2013 Process Page 27 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated Length Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments (Km) Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 1. HIMACHAL PRADESH - CIVIL WORKS Bids Under 311 HP-11-74 Kanswala to Damras road. 1.750 95.19 NCB Post 15th July 2013 Process Bids Under 312 HP-11-73 Ghagar to Manjhiat road 1.761 27.19 NCB Post 15th July 2013 Process Bids Under 313 HP-11-67 Kaithlighat to Basha road 6.600 175.44 NCB Post 15th July 2013 Process Bids Under 314 HP-11-78 Joharji to Kaba Kalan road. 5.270 138.29 NCB Post 15th July 2013 Process Bids Under 315 HP-11-77 Bhojnagar to Banasar road. 12.720 337.99 NCB Post 15th July 2013 Process Bids Under 316 HP-12-95 Up Mohal Joh to Saloh road. 4.000 63.08 NCB Post 15th July 2013 Process NH-70 at km.78/420 to vill. Bids Under 317 HP-12-96 6.000 141.53 NCB Post 15th July 2013 Duhki. Process Bids Under 318 HP-12-92 Chani Devi to Gurat road 5.420 78.79 NCB Post 15th July 2013 Process Total 1700.58 51392.12 Page 28 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated No.s/qua Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments ntity Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 2. HIMACHAL PRADESH - GOODS Quality Control Equipment 1 TOTAL STATION 3 18.00 Shopping Post 19th August 2013 2 AUTO LEVEL 10 12.50 Shopping Post 19th August 2013 3 LAB EUIPMENT SET 10 78.10 NCB Post 19th August 2013 Condition survey Approved by Approval of equipment( Modified 4 5 1.10 Shopping Post 19th August 2013 NRRDA vide Roughness Indicating NRRDA Machine (MERLIN) its mail dated received on July NCC BM cetied Concrete 5 13July 2013 5 1.5 Shopping Post 13, 2013 Test Hammer (BIS 1311- 19th August 2013 1992 (Part-2) Bump Integrator (CRRI 6 Design) supplied with 2 15.50 Post Shopping 19th August 2013 Transportation wheel and CRRI Calibration Certificate 7 Lump sum for field Lump 2.00 Post Shopping 19th August 2013 Page 29 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Review by Reference Estimated No.s/qua Procurement Bank Expected bid Sl. no Package Contract (Description) Cost (Rs. Comments ntity Method (Prior / opening date No. In Lakh) Post) * * First contract of each State will be subject to prior review by the Bank 2. HIMACHAL PRADESH - GOODS equipments sum Total 128.50 Computer and IT Equipment 1 Laptops 5 2.645 Shopping Post 19th August 2013 Model HP-4440 2 Desktop Computers 10 4.389 Shopping Post 19th August 2013 Model HP-8200 3 A3 Laserjet Printers 10 6.250 Shopping Post 19th August 2013 Model HP-5200 Total 13.284 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Sl. No. Ref. No. Description of Assignment Estimated Selection Review by Award position Comments cost Method Bank (Prior / Post)6 3. HIMACHAL PRADESH - CONSULTANCY PW/WBP/RFP 1 /PMC/2011/59 Appointment of Project INR QCBS Prior Awarded to M/s In Progress Page 30 of 31 Procurement Plan, RRP-II: H.P. June 13 Procurement Plan with Methods & Time Schedule for 18 Months period starting June 13 - for CIVIL WORKS Sl. No. Ref. No. Description of Assignment Estimated Selection Review by Award position Comments cost Method Bank (Prior / Post)6 3. HIMACHAL PRADESH - CONSULTANCY 6-601 Management Consultant 63,431,714- (Time Based) Meinhardt (Selection ) under PMGSY 00 Singapore Pte. Rural Roads Project-II ( Including Ltd., NOIDA Service Tax) Road Maintenance US $ 327,000 QCBS Prior Procurement yet 2 Management System and road condition inventories. to be started Road Maintenance Policy US $ 100,000 QCBS Post Procurement yet 3 formulation to be started Chief Engineer(PMGSY) HPPWD, Nirman Bhawan Himachal Pradesh Page 31 of 31