Page 1 ESMF for IPFF DRAFT BANGLADESH BANK Investment Promotion and Financing Facility (IPFF) ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK ESMF FOR IPFF 05 December 2009 Prepared by: Infrastructure Investment Facilitation Center Dhaka, Bangladesh E2314 V1 Page 2 ESMF for IPFF Page 3 ESMF for IPFF i TABLE OF CONTENT ACRONYMS..................................................................................................................................................V EXECUTIVE SUMMARY.........................................................................................................................VII PART – A GENERAL...............................................................................................................................1 1 THE ESMF DOCUMENT....................................................................................................................1 1.1 O VERVIEW OF ESMF......................................................................................................................1 1.2 S TRUCTURE OF THE DOCUMENT..................................................................................................1 1.3 M ETHODOLOGY ..............................................................................................................................2 1.4 P URPOSE OF ESMF.........................................................................................................................4 1.5 U SERS OF ESMF.............................................................................................................................4 2 IPFF PROJECT DESCRIPTION........................................................................................................4 2.1 B ACKGROUND O F IPFF P ROJECT ....................................................................................................4 2.2 O BJECTIVES & AIMS OF IPFF..........................................................................................................5 2.3 C OMPONENTS OF IPFF....................................................................................................................5 2.3.1 I NFRASTRUCTURE D EVELOPMENT S UB -L OANS ...............................................................................5 2.3.2 T ECHNICAL A SSISTANCE .................................................................................................................6 2.4 A NTICIPATED P ROJECT T YPES UNDER IPFF....................................................................................6 2.5 T HE IPFF P ROJECT C YCLE ..............................................................................................................7 3 SUB-PROJECTS OF IPFF - APPROVAL AND MONITORING....................................................9 3.1 IPFF P ROJECTS M ANAGEMENT .......................................................................................................9 3.2 P ROJECT D OCUMENT P REPARATION ...............................................................................................9 3.3 A PPRAISAL AND A PPROVAL ..........................................................................................................10 3.3.1 Environmental and Social Assessment Process.......................................................................11 3.3.2 Approval Process of Loan.......................................................................................................12 3.4 P ROJECT S R EPORT ING UNDER IPFF............................................................................................13 3.5 A NNUAL R EVIEWS FOR IPFF ........................................................................................................13 4 CAPACITY BUILDING, TRAINING ON ESMF............................................................................14 4.1 I NSTITUTIONAL C APACITY A SSESSMENT ......................................................................................14 4.2 C APACITY B UILDING .....................................................................................................................14 4.3 T RAINING NEEDS AND P LANS ........................................................................................................15 4.4 T ECHNICAL A SSISTANCE FOR C APACITY B UILDING I MPLEMENTATION ........................................15 Page 4 ESMF for IPFF ii P ART – B ENVIRONMENTAL MANAGEMENT FRAMEWORK.................................................17 5 GENERAL ENVIRONMENTAL MANAGEMENT .......................................................................17 5.1 OVERVIEW ................................................................................................................................17 5.2 TARGET AREAS OF ENVIRONMENTAL MANAGEMENT.................................................17 5 .2.1 P hysiographic and Land Use Pattern.......................................................................................17 5.2.2 Hydrology................................................................................................................................18 5.2.3 Ground Water..........................................................................................................................18 5.2.4 Ecology....................................................................................................................................18 5.2.5 Climate....................................................................................................................................19 5.2.6 Environmentally and Ecologically Sensitive Areas.................................................................19 5.3 M AIN E NVIRONMENTAL C ONCERNS .............................................................................................19 6 LEGAL AND INSTITUTIONAL FRAMEWORK (ENVIRONMENTAL) ..................................20 6.1 OVERVIEW ................................................................................................................................20 6.2 ENVIRONMENT RELATED POLICIES IN BANGLADESH..................................................20 6.2.1 National Environmental Policy, 1992......................................................................................20 6.2.2 National Environmental Management Action Plan, 1995.......................................................21 6.2.3 National Conservation Strategy, 1992.....................................................................................21 6.2.4 National Water Policy, 2000 ...................................................................................................21 6.2.5 National Water Management Plan, 2001.................................................................................22 6.3 RELEVANT LAWS AND REGULATIONS IN BANGLADESH.............................................22 6.4 ENVIRONMENTAL GUIDELINES FOR PROJECTS IN BANGLADESH.............................25 6.4.1 Green Category........................................................................................................................25 6.4.2 Orange A and B Category .......................................................................................................25 6.4.3 Red Category...........................................................................................................................26 6.5 INSTITUTIONAL ORGANIZATIONS......................................................................................26 6.5.1 Department of Environment (DoE).........................................................................................26 6.5.2 Department of Forest...............................................................................................................27 6.6 DOE REQUIREMENTS ON ENVIRONMENTAL ASPECTS..................................................27 6.7 WORLD BANK SAFEGUARD POLICIES................................................................................27 6.8 CATEGORIES OF PROJECTS ACCORDING TO THE WORLD BANK ...............................28 6.8.1 Category A:.............................................................................................................................28 6.8.2 Category B...............................................................................................................................28 6.8.3 Category C...............................................................................................................................29 6.9 COMPARISON BETWEEN GOB AND WB GUIDELINES.....................................................29 7 ENVIRONMENTAL IMPACT AND MITIGATION MEASURES...............................................31 Page 5 ESMF for IPFF iii 7.1 OVERVIEW ................................................................................................................................31 7.2 POTENTIAL IMPACTS..............................................................................................................31 7.2.1 Pre-Construction (Planning and Design) Phase.......................................................................31 7.2.2 Construction Phase..................................................................................................................32 7.2.3 Operation and Maintenance Phase ..........................................................................................33 7.3 MAJOR ENVIRONMENTAL IMPACTS...................................................................................34 7.4 ASSESSMENT OF IMPACTS....................................................................................................35 7.4.1 Cumulative Impacts.................................................................................................................36 7.5 MITIGATION MEASURES........................................................................................................36 PART – C SOCIAL MANAGEMENT FRAMEWORK.....................................................................40 8 LEGAL AND INSTITUTIONAL FRAMEWORK (SOCIAL) .......................................................40 8.1 OVERVIEW ................................................................................................................................40 8.2 RELEVANT NATIONAL LEGISLATION................................................................................40 8.3 ACQUISITION AND REQUISITION ORDINANCE, 1982......................................................41 8.4 WORLD BANK’S SAFEGUARD POLICIES............................................................................42 8.4.1 OP 4.12 Requirements (Involuntary Resettlement).................................................................42 8.4.2 OP 4.10 Requirements (Indigenous Peoples)..........................................................................43 8.5 COMPARISON OF REQUIREMENTS OF GOB AND WB .....................................................44 8.6 ADDRESSING WORLD BANK SAFEGUARD POLICIES .....................................................45 9 SOCIAL MANAGEMENT PROCESS..............................................................................................47 9.1 G ENERAL ......................................................................................................................................47 9.2 STAGES IN PROJECT DEVELOPMENT .................................................................................47 9.3 FLOWCHART FOR SMF...........................................................................................................48 9.4 SOCIAL COMPLIANCE MATRIX............................................................................................49 9.5 SOCIAL SCREENING................................................................................................................51 9.6 PUBLIC INFORMATION CAMPAIGN AND CONSULTATION.............................................51 9.6.1 Involvement of the Host Populations ......................................................................................51 9.6.2 Formal Consultation Process...................................................................................................51 9.6.3 Informal Consultation Process.................................................................................................52 9.7 R ECORD OF C ONSULTATION .........................................................................................................52 9.8 SOCIAL IMPACT ASSESSMENT (SIA)...................................................................................52 9.8.1 Identifying Social Impact Assessment Variables....................................................................52 9.8.2 Combining Social Impact Assessment Variables, Project Stage, and Setting.........................54 9.8.3 Steps in the Social Impact Assessment Process.......................................................................54 9.9 IDENTIFICATION OF IMPACT................................................................................................58 9.10 IMPACT MITIGATION..............................................................................................................59 Page 6 ESMF for IPFF iv 9.11 LAND ACQUISITION FOR PROJECTS ...................................................................................59 9.11.1 Steps in Land Acquisition...................................................................................................60 9.12 RESETTLEMENT ACTION PLAN (RAP)................................................................................61 9.12.1 Land Acquisition Plan ........................................................................................................61 9.12.2 Resettlement Types.............................................................................................................61 9.12.3 Resettlement Action Plan (RAP) Preparation.....................................................................63 9.12.4 Abbreviated Resettlement Plan...........................................................................................68 9.13 I NDIGENOUS P EOPLES D EVELOPMENT P LAN (IPDP).....................................................................68 9.14 G RIEVANCE R EDRESS M ECHANISM ..............................................................................................69 PART-D OPERATIONAL MANUAL ................................................................................................70 10 OPERATIONAL MANUAL...............................................................................................................70 10.1 SEQUENCE OF TASKS OF THE ESMF IN DIFFERENT PHASES OF IPFF PROJECT.......70 10.1.1 Pre-Construction Phase Activities......................................................................................72 10.1.2 Criteria For Site Clearance Of Projects/Industries..............................................................74 10.1.3 Procedure for Issuing Environmental Clearance Certificate...............................................75 10.1.4 Land Acquisition Phase......................................................................................................76 10.1.5 Financing Phase..................................................................................................................76 10.1.6 Construction Phase .............................................................................................................76 10.1.7 Post-Construction Operation Phase ....................................................................................76 10.2 INSTITUTIONAL FRAMEWORK FOR ESMF IMPLEMENTATION....................................76 10.2.1 Environment and Social Cell (ESC) of IPFF......................................................................76 10.2.2 The Project Management Unit (PMU) in Sub-project........................................................77 10.2.3 Project Environmental and Social Cell (PESC) under sub-project.....................................77 10.2.4 Resettlement Unit (RU) under PESC..................................................................................78 10.3 ESMF IMPLEMENTATION BUDGET......................................................................................78 10.4 MONITORING OF ESMF...........................................................................................................78 10.4.1 Construction Phase Monitoring..........................................................................................79 10.4.2 Operational Phase Monitoring............................................................................................79 10.4.3 Monitoring Plan..................................................................................................................79 10.5 ESMF AUDITING FRAMEWORK............................................................................................80 10.6 PERIODIC REPORTING ON ESMF..........................................................................................80 Page 7 ESMF for IPFF v ACRONYMS APO Annual Plan Operation BB Bangladesh Bank BECA Bangladesh Environment Conservation Act BMP Best Management Practices BP Bank Procedures BRTA Bangladesh Road Transport Authority CO Carbon Monoxide CUL Compensation under Law DCs District Commissioners DLAC District Land Acquisition Committee DoE Department of Environment EA Environmental Assessment ECA Environment Conservation Act, 1995 ECC Environmental Clearance Certificate ECR Environment Conservation Rules, 1997 EIA Environmental Impact Assessment EMP Environmental Management Plan EMMP Environmental Mitigation and Management Plan ERD Economic Relations Division ESA Environmental and Social Assessment ESMF Environmental and Social Management Framework ESMP Environmental and Social Management Plan FCD Flood, Control and Drainage FGD Focus Group Discussion FI Financial Intermediary FIL Financial Intermediary Loan GoB Government of Bangladesh GRC Grievance Resolution Committee ICT Information and Communication Technology IDA International Development Association IEE Initial Environmental Examination IIFC Infrastructure Investment Facilitation Centre IPFF Investment Promotion Financing Facility IPDP Indigenous People Development plan LAP Land Acquisition Proposal MoEF Ministry of Environment & Forest Page 8 ESMF for IPFF vi NEMAP National Environmental Management Action plan NGO Non-Government Organization NOx Oxides of Nitrogen OD Operational Directives OP Operational Policies PAD Project Appraisal Document PAP Project Affected Person PFI Participatory Financing Institution PI Public Involvement PICOM Private Infrastructure Committee PPP Public-Private Partnership PRA Participatory Rural Appraisal RAP Resettlement Action Plan RDP Regional Development Plan SCC Site Clearance Certificate SIA Social Impact Assessment SMP Social Management Plan SOx Oxides of Sulphur TA Technical Assistance WB World Bank WARPO Water Resources Planning Organization WQS Water Quality Standard Page 9 ESMF for IPFF vii EXECUTIVE SUMMARY This ESMF has been prepared to serve as a guideline for the stakeholders of the IPFF project: the intending project sponsors; the financial intermediaries; the executing agency and relevant line ministries, etc. For the intending project sponsor, the ESMF gives the sequence of activities that should be followed in conforming to the environmental and social aspects of a project seeking IPFF funding. Page 10 ESMF for IPFF viii Page 11 ESMF for IPFF 1 PART – A GENERAL THE ESMF DOCUMENT OVERVIEW OF ESMF Environmental and Social Management Framework (ESMF) is a safeguard instrument which establishes a mechanism to determine and assess future potential environmental and social impacts of different projects and other activities associated with the projects regardless of funding agency. The framework sets out mitigation, monitoring and institutional measures to be taken during design, implementation and operation of the project activities to eliminate adverse environmental and social impacts, offset them, or reduce them to acceptable levels. This instrument has been prepared as a separate and stand-alone document to be used for IPFF project. This framework is a diagnostic tool to support decision-making but is not a substitute for decision making either at the strategic or detailed implementation levels. It is important to recognize that the World Bank Operational Policies require that the Environmental and Social Assessments (ESA) of private sector projects, financed by Financial Intermediary Loan (FIL) institutions undergo the same rigorous treatment, as in case of regular public sector investment projects. However, it is practically unachievable. In public sector projects, the Bank is involved from the inception of the project and goes along in all the stages from project identification, feasibility study, tendering, evaluation, award of contract, financing and construction (from Stages 0 to 6, in the continuum of project development stages, as given in Bangladesh Private Sector Investment Guidelines, BPSIG 2004). But in Private Public Partnership (PPP) projects, the Bank or a Participatory Financial Institute (PFI) comes in the project scene only at the time of financing (Stage 5). The The Bank or the PFI enters in the project life when much of the Environmental and Social Assessment (ESA) activities have been completed. As such it cannot control these activities and can only make a due diligence in the past activities, to ensure compliance. For projects in which the World Bank finances are involved since the inception, all the WB requirements for environmental and social issues are to be followed. But in case where the sponsor purchases the land for the project through voluntary negotiations or the land has been acquired by the government earlier, all the Bank guidelines for land acquisition and resettlement issues cannot be followed. In such cases the IPFF will take appropriate measure that may be possible at that stage. This matter has been discussed in detail, in the Operational Manual of this document. STRUCTURE OF THE DOCUMENT The ESMF is a large and an important document. It has been divided into four parts with total ten chapters for the convenience of the users of this document. Here, the ‘Environmental Management Framework’ and the ‘Social Management Framework’ are dealt separately, so that users can easily go through the both frameworks without any perplexity. The four parts are named as, 1. Part A: General includes chapters 1, 2, 3 and 4. 2. Part B: Environmental Management Framework includes chapters 5, 6 and 7. 3. Part C: Social Management Framework includes chapters 8 and 9 4. Part D: Operational Manual includes chapter 10 Page 12 ESMF for IPFF 2 The contents of these ten chapters are stated below. i) Chapter One gives an overview of ESMF including its purpose, users and environmental and social assessment process. ii) Chapter Two gives a brief idea on the IPFF project including its objective, nature, components and the project cycle. iii) Chapter Three gives a brief idea on IPFF sub-projects management and its monitoring and auditing framework. iv) Chapter Four discusses the capacity building and training needs and plans of the ESMF . This chapter also discusses the technical assistance required for capacity building implementation and ESMF implementation budget. v) Chapter Five describes the relevant available environmental resources of Bangladesh , which are important for environmental management. vi) Chapter Six provides the legal and institutional basis for establishing the environmental standards/guidelines for IPFF projects. It also includes the World Bank guidelines and the comparison between GoB and WB guidelines. vii) Chapter Seven outlines the possible environmental impacts and their mitigation measures during pre-construction, construction and operation phases of the sub-projects. viii) Chapter Eight provides the legal and institutional basis for establishing the social standards/guidelines for IPFF sub-projects. It also includes the World Bank guidelines and the comparison between GoB and WB guideline ix) Chapter Nine gives a brief idea on social management process , relating their risk to their management, and impact identification and mitigation measures, including land acquisition and resettlement issues for IPFF sub-projects. . x) Chapter Ten gives an operational manual including sub project implementation arrangements; and management plans. METHODOLOGY The following steps were followed in the methodology for preparation of this ESMF document. The whole report preparation consists of following seven steps. 1. Review the ToR of ESMF 2 2 . . Literature review 3. Selection of experts and stakeholders 4. Consultation with experts and stakeholders 5. Compilation and analysis of information 6. Preparation of Draft Final Report 7 7 . . Preparation of the Final Report incorporating the comments of concerned agencies on Draft Final Report These steps are detailed in the Flowchart shown on the following page. Page 13 ESMF for IPFF 3 Fig 1. 1 : Methodology of Preparing ESMF R R e e v v i i e e w w t t h h e e T T o o R R o o f f E E S S M M F F L L i i t t e e r r a a t t u u r r e e R R e e v v i i e e w w S S e e l l e e c c t t i i o o n n o o f f E E x x p p e e r r t t s s a a n n d d S S t t a a k k e e h h o o l l d d e e r r C C o o n n s s u u l l t t a a t t i i o o n n w w i i t t h h E E x x p p e e r r t t s s a a n n d d S S t t a a k k e e h h o o l l d d e e r r s s C C o o m m p p i i l l a a t t i i o o n n a a n n d d A A n n a a l l y y s s i i s s o o f f I I n n f f o o r r m m a a t t i i o o n n P P r r e e p p a a r r a a t t i i o o n n o o f f D D r r a a f f t t F F i i n n a a l l R R e e p p o o r r t t P P r r e e p p a a r r a a t t i i o o n n o o f f F F i i n n a a l l R R e e p p o o r r t t Before preparing ESMF it is necessary to go through the ToR very carefully. Because ToR includes the structure of the repot, its component and other important issues. A number of ESMF documents of different organizations both local and international are studied for clear understanding on ESMF. Policy guidelines of World Bank are also studied. As ESMF is prepared for Bangladesh context, both local and international experts and stakeholders are selected for their valuable advices. After that, a consultation is held with the selected experts and stakeholders. As information is collected from both primary and secondary sources, all information is organized for further analysis. After all the above stages, a draft report is prepared and is sent to World Bank and IPFF cell of Bangladesh for their comments After considering all the comments of World Bank and IPFF cell of BB, a final report was prepared. Page 14 ESMF for IPFF 4 PURPOSE OF ESMF The Environment and Social Management Framework (ESMF) details the agreed policies, guidelines, and procedures to be integrated into the implementation of IPFF projects. The main purposes of the ESMF are, · To understand the process of undertaking ESAs for IPFF sub-projects, which are usually PPP projects · To establish clear procedures and methodologies for the environmental and social assessment, review, approval and implementation of investments to be financed under the project; · To specify appropriate roles and responsibilities, and outline the necessary reporting procedures, for managing and monitoring environmental and social concerns related to project investments; · To determine the training, capacity building and technical assistance needed to successfully implement the provisions of the ESMF; · To provide practical information, resources for implementing the ESMF. As a detailed guide on principles and procedures for incorporating environmental and social issues into project preparation, the ESMF would be a useful reference to potential project sponsors and other financing agencies likely to participate in future stage of an IPFF projects. USERS OF ESMF As a core policy and procedural document for the IPFF projects, the ESMF is designed for use by the following actors: · IPFF Project Staff: As a document enshrining operating principles and guidelines to ensure that projects are adequately assessed to ensure compliance with environmental and social standards. · Project Sponsor: As a document that spells out requirements with respect to environmental and social issues that need to be met, for obtaining finances for IPFF project. · Project Associates (Bangladesh Bank, other shareholders, consultants, lenders, etc.): As a document that explains the compliance requirements for environmental and social requirements for projects that receive financing for IPFF projects. · Other relevant government agencies, including DOE, for reference. IPFF PROJECT DESCRIPTION 2.1 BACKGROUND OF IPFF PROJECT The Government of Bangladesh (GoB) with support from World Bank has taken the Investment Promotion and Financing Facility (IPFF) Project to open a new window for infrastructure financing through private sector participation. The IPFF has made available partial debt financing through private sector financial intermediaries for eligible, government-endorsed infrastructure projects to be developed by private sector. Projects developed solely by the private sector but identified by the Government to be in the public interest are also being eligible for financing. The project also seeks to assist the Government of Bangladesh in facilitating new infrastructure projects with potential for Page 15 ESMF for IPFF 5 private sector participation and in developing the capacity of the financial institutions for the ongoing provisions of infrastructure finance. The IPFF project has exhausted its first phase allocation amount of $50.00 million ($47.5 million investment and $2.50 million TA for capacity building) in its third year of operation, and considerable excess demand still exists. The initial funds have been used exclusively in the power sector as a matter of priority. However, other sectors also require a boost in infrastructure financing, as well as in familiarization with the PPP framework. The objectives of the additional financing for IPFF project are: · To supplement the resources of the Bangladesh financial markets to provide term finance for infrastructure and other investment projects beyond the capacity of local financial institutions; and · To scale up the financing of public-private partnership (PPP) ventures in infrastructure already started in the project. The proposed operation will support Bangladesh Bank (BB), the implementing agency, to scale up the financing of PPP ventures in infrastructure. The proposed operation is expected to increase additional financing of infrastructure by over $400 million, leveraging about 100% private resources. It is expected to increase infrastructure supply in the power sector - renewable energy and energy savings - as well as bridges, ports, container terminals, water treatment plants, waste disposal projects, and others. The increased provision of infrastructure will create (or help maintain) jobs during the economic slowdown, and remove bottlenecks in economic growth caused by existing infrastructure shortages. The proposed amount of US$257 million equivalent is divided into $7 million for capacity building (technical assistance) and US$250 million for the lending pipeline. 2.2 OBJECTIVES & AIMS OF IPFF The objectives of the IPFF Project are to accelerate private sector-led growth by providing term finance for infrastructure development and promoting domestic infrastructure finance capacity. The project aims to: a) Supplement the resources of the Bangladesh financial markets to provide term finance, in Taka and foreign currency, for infrastructure and other investment projects beyond the capacity of local financial institutions; b) Promote the role of private sector entrepreneurs in the development of capital projects, especially infrastructure. 2.3 COMPONENTS OF IPFF The IPFF Project consists of two components: A. Infrastructure Development Sub-loans B. Technical Assistance 2.3.1 Infrastructure Development Sub-Loans This component aims to develop a funding mechanism that adds transparent levels of control and market-based incentives to the existing methodology for allocating public funds to priority infrastructure projects identified by the government and developed on the basis of PPP. Page 16 ESMF for IPFF 6 The funding mechanism is not created for any newly licensed financial institutions but it operates following the regulation of BB for the existing regulated local financial institutions. Funds are allocated to local financial institutions for on-lending to private sector infrastructure projects selected by the government. Financing comes from the government but is administered by BB. The private sector infrastructure promoters operate under incentive-based contractual arrangements designed to align their interests with those of the GOB. Sub-loans to PFIs for investment projects eligible for financing from the facility are approved by the BB as agent of GOB subject to World Bank “No Objection”. Projects are supported on market terms and require at least a 30 percent equity component from the private infrastructure promoter and a further minimum of 14 percent of third- party funding, which may come from the PFIs. The PFIs are required to co-invest as well as assume all commercial credit risk to reinforce alignment of their interests and those of the government. Syndication amongst PFIs and with non participating institutions is permitted but the PFIs are responsible for credit administration and recovery. BB has carried the selection of PFIs on a transparent basis. Eligibility is restricted to local financial institutions licensed by BB. World Bank provided its “No Objection” for the selected PFIs. The interest rate for funds available under the facility is market-determined, using a process that references the risk free rate (typically Government bonds) for financings of a comparable maturity and interest period. Sub-loans made to promoters of infrastructure projects are made at market offered rates to be determined by the PFIs. 2.3.2 Technical Assistance a. Strengthening the management and operation of the Facility. b. Strengthening the capacity of PFIs in the areas of business planning, resource mobilization and management information system. c. Provision of technical advisory services to Bangladesh Bank to carry out the Project d. Provision of technical advisory services by IIFC to facilitate the development of a framework for building capacity to manage private-public partnership in infrastructure, and for fostering policy, regulatory, and institutional reforms. e. Provision of technical assistance by IIFC: (i) To assess infrastructure investment projects; (ii) To carry out training and dissemination activities to promote infrastructure finance; and (iii) To carry out environmental assessments. f. Provision of technical advisory services to PICOM: (i) in the area of policy and regulatory reform, awareness creation, capacity building, project pipeline monitoring and evaluation, and preparation of standard contract documentation; and (ii) in assisting the Recipient’s ministries and sectoral agencies to implement the Private Sector Infrastructure Guidelines. 2.4 ANTICIPATED PROJECT TYPES UNDER IPFF Under the project different infrastructure sectors will be financed. Infrastructure Projects from the power sector will be given special emphasis, however under the Private Sector Infrastructure Guidelines, infrastructure projects from the following sectors or sub sectors may be implemented as Private Infrastructure Projects: (a) power generation, transmission, distribution, renewable energy and services. Page 17 ESMF for IPFF 7 (b) port development( sea, river and land) including inland container terminals, inland container depot and other services; (c) environmental, industrial and solid waste management projects (d) highways and expressways including mass-transit , bridges, tunnels, flyovers, interchanges, city roads, bus terminals, commercial car parking, etc; (e) airports, terminals and related aviation facilities; (f) water supply and distribution, sewerage and drainage; (g) industrial estates and parks development; 2.5 THE IPFF PROJECT CYCLE A project appraisal document (PAD) had been prepared for the IPFF project in April 2005 that details out the arrangements under which the project will support lending functions as well as TA functions. The project cycle is illustrated in the figure provided on the next page. Page 18 ESMF for IPFF 8 Page 19 ESMF for IPFF 9 SUB-PROJECTS OF IPFF - APPROVAL AND MONITORING IPFF PROJECTS MANAGEMENT The IPFF is structured and implemented through signing agreements between the parties and institutions involved in implementation of the facility. The World Bank has provided funds for IPFF through signing a financing agreement with the Government of Bangladesh. The Government of Bangladesh has engaged Bangladesh Bank as the executing agency of the facility through signing an administration agreement. However, the fund will not be directly provided to the project promoter by the BB. Rather, some selected PFIs will provide the loan to the project promoter. A part of the loan will be financed from IPFF through BB. BB will treat the fund provided against a particular loan proposal as the loan extended to the PFI by Bangladesh Bank, with obligations irrespective of loan repayment performance of the project promoter. Bangladesh Bank has signed Master Facility Agreements with the selected PFI for extending such loan. Bangladesh Bank has signed a Technical Services Agreement with Infrastructure Investment Facilitation Centre (IIFC) to assist BB in administering the facility. The agreements are listed as follows: (a) Financing Agreement between World Bank and GoB (b) Administration Agreement between GoB and BB (c) Master Facility Agreement between BB and the PFIs (d) Technical Services Agreement between BB and IIFC Bangladesh Bank needs to follow a document “Operational Directives (OD)” to administer the facility on a day-to-day basis. PROJECT DOCUMENT PREPARATION The Operational Directives of IPFF provides a Documentation Checklist, which needs to be followed by the PFIs before submitting a loan application to BB. This is reproduced below, for clear understanding. Table 3. 1 Documentation Checklist 1. Application Letter from PFI stating amount of funding requested and a precise description of the project cost Yes No 2. A copy of the summary details of Investment Project. Yes No 3. Confirmation that PFI has agreed with IE in writing. Yes No 4. Copy of investment project/Request from IE to PFI Yes No 5. Copy investment project appraisal which states, inter alia, the benefits to derived from IE, project cost and financial plan Yes No 6. Copy of PFI’s draft Sanction Letter, which includes the proposed terms and conditions of the Investment Project Yes No 7. Copy of the Draft Agreement to be made between the PFI and the Investment Enterprise Yes No 8. Investment Project Payment/ Amortization Schedule (tentative) Yes No 9. Arrangement of Insurance policy for usual risks (e.g. fire, theft, flood, riot, public liability etc., as applicable) in the name of PFI as lender or payable to PFI Yes No Page 20 ESMF for IPFF 10 10. Whether EIA done or not Yes No 11. PFI’s own Environmental Assessment available or not Yes No 12. Clearance certificate of DOE enclosed or not Yes No 13. Clean, current Credit Information Bureau Report on IE (no more than 90 days old from submission of the proposal), all local shareholder directors and associated companies Yes No 14. Undertaking of PFI and IE that the assets will be procured as per procedures described in the OD under the proposed financing (copies of appropriate documents will be provided in due course) Yes No 15. Copy of evidence that the proposed Investment Loan does not include activities of a military or paramilitary nature or activities in the SITC groups or subgroups as described in 6(e) of Schedule 5 of the Financing Agreement between GOB and WORLD BANK Yes No 16. Arrangement of utilization of 30% equity of the IE and contribution from PFI’s own resources and other institutions Yes No 17. Procurement Plan of the IE’s enclosed or not Yes No 18. Whether the Investment Project located inside a protected area or not Yes No 19. Whether the Investment Enterprise owns the land where the Investment Project will be developed Yes No 20. Confirmation of PFI that repayments on existing other Loans/Leases to the IE and its Group members are up to date Yes No 21. Inspection Report regarding utilization of 2 nd installment/3 rd installment Yes No The above checklist is maintained, to ascertain that key documents about the project have been obtained from the PFI. A sub-project cannot be finally approved and funded until such reports are received and approved. APPRAISAL AND APPROVAL For determining eligibility for financing by IPFF, the processing of loan application needs to be understood. The OD provides the following process from the project promoter making application for loan upto financing as follows: The project promoter approaches the PFI for financing a project. After conducting due diligence on the viability of the project, the PFI decides whether to finance an infrastructure project. Then the PFI forwards the loan file to BB for approval of the requested IPFF financing (which shall be at maximum 80% of the debt). BB does initial scrutiny of the proposal as per the documentation checklist and forwards to the Technical Advisor (IIFC in this case), for review. IIFC provides technical assistance to BB during this review process. Upon receipt of loan application along with necessary documents from BB, IIFC reviews whether the investment project meets the following criteria: · Acceptable procurement process · Sufficient equity participation (minimum 30% of the project cost) · Completion of EIA etc. After the review by IIFC, BB provides approval, if the technical criteria contained in the check-list provided in Annex B of this report are fulfilled. Then it forwards the loan application to World Bank for no-objection. After receiving World Bank's clearance regarding the loan application, the Project Director of IPFF sanctions the loan amount. The Page 21 ESMF for IPFF 11 PFI should ensure at least 30% equity participation of the entrepreneurs along with the PFI’s own lending. Environmental and Social Assessment Process The ESMF will establish a unified process for addressing all the environmental and social safeguard issues. It will help to systematically identify, predict, and evaluate beneficial and adverse environmental and social impacts of development activities, designing enhancement measures for beneficial impacts, and implement mitigation measures for the adverse impacts. Tab 1.1 describes the steps in environmental and social assessment process at different stages of a project cycle. Table 3. 2: Steps in the Environmental and Social Assessment Process EIA and SIA Steps in indifferent Stages of Project Cycle A Project Identification & Pre-Feasibility Studies (Pre-Construction) Phase 1. Environmental and Social screening 2. Social performance frameworks for projects not requiring specific resettlement and land acquisition studies B Project Design Phase 3. Initial Environmental Examination (IEE): assess environmental impacts to determine if EIA is required; its recommendations are incorporated into the project design. 4. Scoping: identify significant potential impacts and project alternatives, and propose terms of reference for the EIA and SIA. 5. Baseline Data Collection, as part of SIA: identify current environmental and socio- economic conditions without the project and update it during the project in accordance with changes in the project. 6. Public consultation and participation of stakeholders of different level at various stages in the assessment process to ensure quality, comprehensiveness and effectiveness, and that stakeholders’ views are adequately addressed. 7. Prepare EIA Report and SIA Report: summarizes all information obtained, analyzed and interpreted in a report form; should contain a non-technical summary including methods used, results, interpretations and conclusions. The report should also include recommendations for mitigation of negative impacts, enhanced opportunities and relevant policy and regulatory actions. The report should be shared with stakeholders participating in the consultation process and affected by the recommendations and time for feedback should be allowed. 8. Prepare Environmental and Social Management Plan (ESMP) of the project to determine specific actions to be taken during the designing of the project that includes plans for land acquisition, engineering design and construction stages to minimize or mitigate adverse environmental and social impacts. 9. Preparation of Resettlement Action Plan (RAP) and Indigenous People’s Development Plan (IPDP) on the basis of SIA and update them in accordance with changes in the project requiring land acquisition. 10. Design mitigation measures: to avoid, reduce and minimize adverse environmental and social impacts and enhance beneficial impacts. Page 22 ESMF for IPFF 12 EIA and SIA Steps in indifferent Stages of Project Cycle C Project Appraisal/ Approval (Financing) Phase 11. Review and Approval of EIA and SIA Report: review report to assess if all issues have been adequately addressed and to facilitate the decision-making process; decide if project should proceed, or if further alternatives must be examined. D Construction Phase 12. Implementation of Environmental Management Plan (EMP) and RAP to address adverse environmental and social impacts and update it in accordance with changes in the project 13. Environmental and Social Monitoring: determines compliance with ESMP 14. Mid- term independent evaluation to assess the continued relevance of the mitigation plans and need for any alterations based on actual developments during the construction phase E Post-Construction Phase 15. Environmental and social Audit: As per the recommendations of EIA and SIA study. 16. Regular monitoring arrangements to record and evaluate progress against initial plans and potential new challenges and opportunities. Approval Process of Loan The 5-step approval process of Loan Applications under IPFF as per OD is as follows. Steps in IPFF Process Activity (Investor/PFI/BB/World Bank) Step1: Procurement of private sector promoter by the government agency A private sector promoter is selected to undertake a government sponsored infrastructure project following International Competitive Bidding (ICB) or other competitive bidding or the investor is selected through an open licensing process etc. Step 2: Proposal to PFI from promoter · The promoter approaches a PFI to finance the Investment Project. · The PFI conducts due diligence on the proposed investment project. · If satisfied with the project, the PFI decides to co-finance the project and determines the applicable interest rate. Step 3: Loan application to BB from PFI The PFI then approaches BB with the proposed project and requests co-financing under IPFF. Step 4: Review of loan application by Technical Advisor The Technical Advisor reviews the proposed investment project and provides its advice also to World Bank. On the basis of its own assessment for adherence to project objectives, the Financing Agreement and government policies, World Bank will also review on the basis of “No Objection”. Page 23 ESMF for IPFF 13 Step 5: Approval from World Bank After “No Objection” of World Bank, BB sanctions loan for the PFI against the project. Bangladesh Bank will have the responsibility for selecting the PFIs, deciding whether to finance the loan proposals submitted by the PFIs, based on a list of pre-determined criteria and providing capacity building to financial institutions in infrastructure finance and related themes, eligibility criteria will be followed to select PFIs under IPFF. The IPFF is open to both bank and non-bank financial institutions. PROJECTS REPORTING UNDER IPFF BB will maintain a computerized financial management, accounting, disbursement and reporting system for the project in accordance with generally accepted accounting principles and practices. The accounts and records will be capable of disclosing a true and fair view of the financial position and of facilitating progress monitoring. BB will prepare quarterly and annual accounts and generate quarterly reports, to ensure consistency with World Bank’s requirements under OP/BO 10.02. Annual financial statements will be audited by Foreign Aided Project Audit Directorate. Internal controls will include a separate Project Audit Committee, proper segregation of functional responsibilities, signing of checks, verification of procurement proposals, monthly reconciliation of bank accounts, and regular detailed reporting. Assess whether procurement have been made as per procurement plan. ANNUAL REVIEWS FOR IPFF The scope of work and its procedures for implementation of the subprojects will be reviewed periodically (annual/ every two years). It is expected that these reviews will be carried out by an authorized person or a group of persons not involved in the subproject implementation. The purpose of the reviews is two-fold: ƒ to assess compliance with ESMF procedures, learn lessons, and improve future ESMF performance; and ƒ to assess the occurrence of, and potential for, cumulative impacts due to project- funded and other development activities. The third-party annual reviews will be a principal source of information to project management for improving performance, and to the World Bank supervision missions. Thus, they should be undertaken after the annual report has been prepared and should be available for Bank supervision of the Project. Page 24 ESMF for IPFF 14 CAPACITY BUILDING, TRAINING ON ESMF The environmental sustainability of the IPFF that involve funding of multiple, small-scale subprojects is highly dependent on the capacity of implementing agencies to carry out the associated design, planning, approval and implementation work. Thus, to ensure that capacity, it is vital that that IPFF allocates sufficient resources to training and capacity building. INSTITUTIONAL CAPACITY ASSESSMENT An understanding of the institutional needs for implementing the ESMF includes a review of the authority and capability of institutions at different levels, and their capacity to manage and monitor ESMF implementation. The capacity building assessment and the plan should include: ƒ the institutional structure, and its authorities at all relevant levels, to address environmental management issues; ƒ the number and qualifications of staff to carry out their ESMF responsibilities; ƒ resources to support staff in their work; and ƒ knowledge and experience relevant to carrying out environmental analyses and designing mitigation measures for infrastructure. The BB has limited institutional capacity to implement the ESMF. The expert personnel/consultant may be utilized to conduct awareness-building type training for BB, PFIs, and private investors those who would be involved in the implementation process. Although general awareness on environmental issues exists among BB staff, focused training and capacity building would enhance the ESMF implementation capacity substantially on their part. CAPACITY BUILDING All environmental assessments (EAs) that will be carried out (and cleared by the Bank) for all subprojects in the IPFF pipeline (e.g. power plants, renewable energy and energy savings investments, bridges, ports, container terminals, water treatment plants, and waste disposal projects) along with detailed surveys and designs must be in accordance with the ESMF. Internal capacity in the BB is limited in respect of the management of environmental and social issues. As such a program of capacity building for BB and the PFIs implementing sub-projects will be put in place to ensure that, over time, capacity to conduct due diligence on social and environmental aspects of infrastructure projects on PPP basis is built. IPFF envisages capacity building to BB, PFIs and investment enterprises to ensure that the ESMF is effectively operationalised. The IPFF personnel will be exposed to formal training in the management of environmental and social issues. The training program for various role players will include · an orientation program on the ESMF, · Environmental Assessment Processes, · Environmental Management Plan Page 25 ESMF for IPFF 15 · Social Impact Assessment (SIA), Resettlement Action Plan (RAP), Indigenous People Development Plan (IPDP) · Project Management. The ESMF will help improve the effectiveness in the management of environmental and social impacts during planning, implementation and operation of proposed investments. Capacity building will enhance the subprojects ’ ESMF management capacity by allowing real application of the critical practices such as the following: (a) Basic practices: screening impacts, scoping assessments, planning mitigation options, public consultation to assess feasibility and acceptability options; (b) Environment: site selection and route alignment to minimize environmental impacts and social disruption; restoration of drainage patterns, land use etc; including mitigation measures in contracts; management of impacts during construction; monitoring of effectiveness of measures; (c) Monitoring and grievance redress: transparency and public administration in planning, reporting and supervision responsibilities and formats during implementation, documenting land transactions, complaint response record keeping and procedures; TRAINING NEEDS AND PLANS A plan is to be designed for a comprehensive training programme that aims at enhancing capacity of relevant implementing agencies. The technical adviser of IPFF (IIFC) and/ or any other consultant will play the key role in the initial phase in conducting the trainings. A panel of experts will be developed so that suitable expert/s can be chosen from a list as a resource person for providing training, as and when required for a particular training event. The objectives of the training under the ESMF are to: (a) to identify, prepare, implement and manage the environmental and social aspects of their sub-projects; (b) ensure that investors have the capacity to assist in preparing sub-project proposals, mitigation plans and (c) ensure that BB have the capacity to appraise, approve and supervise the implementation of subprojects; and training plans will be prepared accordingly. Different groups involved in IPFF implementation have different training needs in terms of raised awareness, sensitization to the issues, and detailed technical training: TECHNICAL ASSISTANCE FOR CAPACITY BUILDING IMPLEMENTATION The capacity building and training constitute a separate component of IPFF and adequate resources for this component should be allocated to ensure effective implementation of the ESMF. The resources are needed to implement the following items. · Institutional development activities Page 26 ESMF for IPFF 16 · The training program for BB, PFIs and private investors, who will directly involved in the planning, design and implementation of the project to implement the ESMF o to understand and appreciate the ESMF requirements, o to prepare and review the IEE/ EIA, o to prepare and review EMP/ SMP, o To understand, prepare and review RAP and IPDP o to monitor the implementation of the sub-project specific ESMPs · Annual reviews and audits Page 27 ESMF for IPFF 17 PART – B ENVIRONMENTAL MANAGEMENT FRAMEWORK GENERAL ENVIRONMENTAL MANAGEMENT OVERVIEW An Environmental Management Plan (EMP) is an implementation plan for mitigation, protection and/or enhancement measures, which are recommended in the EIA. It details: (a) The measures to be taken during the implementation and operation of a project to eliminate or offset adverse environmental impacts, or to reduce them to acceptable level. (b) The actions needed to implement these measures. EMP documents key elements of environmental management including the environmental policy, responsibilities, applicable standard operating procedures and best management practices (BMP), record keeping, reports, communication, training, monitoring, and corrective action. It features the “PLAN, DO, CHECK, ACT” model for future and ongoing improvement of environment. Plan Planning, including identifying environmental impacts and establishing environmental goals. Do Implementing, including employee training and establishing operational controls. Check Checking, including auditing, monitoring and taking corrective action. Act Reviewing, including progress reviews and taking action to make needed changed to the EMP. Before preparing Environmental Management Plan, it is necessary to get a brief idea on available environmental resources of Bangladesh. TARGET AREAS OF ENVIRONMENTAL MANAGEMENT The IPFF projects are expected to be located all over Bangladesh. Therefore, it is necessary to keep in mind the general variation in the environmental conditions expected in different parts of the country. A brief description of the important environmental resources and issues are discussed in this section. Physiographic and Land Use Pattern Bangladesh is located between 20 0 34´ and 26 0 38´ N, and 88 0 01´ and 92 0 41´ E. The area of the country is 1, 47,570 square km with a coastline of about 700 km in length. The land is flat to the extent of about 80% intersected by numerous rivers and their distributaries. The rest 20% of the area consists of uplands (~8%) and hill areas (~12%). The hill areas consist of Chittagong Hill Tracts, hill ranges of northeastern Sylhet and hills along the narrow strip of Sylhet and Mymensingh Districts. Most of the land is used for agriculture. Land use is generally classified into five categories as agricultural, forest, cultivable waste, current fallow and as ‘not available for Page 28 ESMF for IPFF 18 cultivation’. The category of ‘not available for cultivation’ consists of mainly of urban, rural settlements and industrial land. Hydrology Bangladesh is characterized by an exceptional hydro-geographical setting. It is one of the largest deltas in the world and is criss-crossed by numerous rivers, their tributaries and distributaries. There are about 700 rivers, canals, and streams in Bangladesh, with a total length of approximately 22,155 km, which occupy a riverine area of about 9,384 sq km. A vast amount of water flows through Bangladesh mostly during June-October. The rivers of Bangladesh also carry huge amounts of sediment, an estimated 24 billion tons/year. The ultimate result is additional new land in some places due to accretion, forming islands called chars, and loss of land in some other places due to erosion. Hydrology of a given area is extremely important for any sub-project, which may have impact upon water bodies. Impact on water flow by any subproject should be carefully considered in subproject planning. Ground Water Groundwater is a vital natural resource for the reliable and economic provision of potable water supply in both the urban and rural environment. Presently about 80% of the people in rural Bangladesh depend on groundwater for drinking. Urban water supply is also largely dependent on groundwater. Until the emergence of the Arsenic problem, groundwater was hailed for providing the access to clean drinking water in Bangladesh. Groundwater in Bangladesh occurs at a very shallow depth where the recent river-borne sediments form prolific aquifers in the floodplains. The main component of discharge is the withdrawal of groundwater by different types of tube wells. A minor component of discharge is natural flow towards lower gradient. The groundwater level is at or very close to the surface during the monsoon whereas it is at maximum depth during the months of April and May. Because of uneven distribution of water resources, dry season demand for water in Bangladesh is mainly met by groundwater. Ecology The most important terrestrial ecosystem in Bangladesh is forest. The total land under forest in Bangladesh is about 2.56 million hac. A significant part of the existing forest area is designated as State Forest; most of this land is actually barren of tree vegetation. Again, Bangladesh has an enormous area of seasonal wetland. In fact, half of the country could be delineated as such. The area under perennial wetlands is much smaller and is principally permanent rivers and streams, shallow freshwater lakes and marshes, fish ponds and estuarine systems in the extensive mangrove swamps. Wetland resources are crucial to the environment of Bangladesh. Both perennial and seasonal wetlands provide habitats to a large variety of flora and fauna. Wetlands also provide subsistence for a significant proportion of the population through their fishery resources. But the wetlands of Bangladesh are being drastically affected by the impacts of the increasing human population. The wetlands are being lost to flood control, drainage and irrigation development. Severe erosion in the catchments areas is causing increased siltation, and having major impacts on the key wetland areas. Page 29 ESMF for IPFF 19 Climate Bangladesh has a subtropical monsoon climate characterized by wide seasonal variations in rainfall, moderately warm temperatures, and high humidity. Regional climatic differences in this flat country are minor. Three seasons are generally recognized: a hot, humid summer from March to June; a cool, rainy monsoon season from June to October; and a cool, dry winter from October to March. Heavy rainfall is characteristic of Bangladesh. About 80% rainfall occurs during the monsoon season. The monsoons result from the contrasts between low and high air pressure areas that result from differential heating of land and water. Environmentally and Ecologically Sensitive Areas Environmentally sensitive areas are those having significant value in their natural state, or having socio-cultural significance or sensitivity. Cultural or historical sites and densely populated urban centers are examples of the later category. Ecologically Sensitive Areas can be defined as areas that may contain unique features, maintain key natural processes, support endangered, endemic or threatened plants or animals and their habitats, or provide important breeding areas for wildlife. In sensitive areas, environmental and ecological impacts tend to be more severe than elsewhere, and therefore, extra precautions must be taken to avoid significant environmental impacts. In many cases, this will mean extra investments in mitigation measures, while in some cases these areas will simply have to be avoided, resulting, for example, in the abandonment of a subproject or there-alignment of a section of road. The list of ecologically critical areas declared by DoE is attached in Annex 5.1 MAIN ENVIRONMENTAL CONCERNS The key environmental concerns in Bangladesh include the following and special care needs to be taken for preparing an EMP: · Flooding · Drainage · River bank erosion · Surface water quality · Seasonal fluctuations in ground water table · Groundwater quality · Arsenic Contamination of Aquifers · Saline intrusion (coastal areas) · Wetland deterioration · Land degradation · Ambient Air Pollution · Indoor Air Pollution · Forestry management · Biodiversity conservation · Fish and fisheries resource management Page 30 ESMF for IPFF 20 LEGAL AND INSTITUTIONAL FRAMEWORK (ENVIRONMENTAL) OVERVIEW The institutional and legal setting in Bangladesh provides the context within which the environmental assessment procedure for IPFF projects was developed. It is imperative that the project sponsors for IPFF projects are aware of and comply with the legal and institutional requirements of the GOB. ENVIRONMENT RELATED POLICIES IN BANGLADESH The following section will discuss the relevant policies, which regulate environmental management in Bangladesh and are also relevant to projects that may be financed by IPFF. The relevant laws are, 1. National Environmental Policy,1992 2. National Environmental Management Action Plan, 1995 3. National Conservation Strategy, 1992 4. National Water Policy, 2000 5. National Water Management Plan, 2001 National Environmental Policy, 1992 The Bangladesh National Environmental Policy sets out the basic framework for environmental action together with a set of broad sectoral action guidelines. Key elements of the policy are: · Maintenance of the ecological balance and overall progress and development of the country through protection and improvement of the environment; · Protection of the country’s assets, properties and resources against natural disasters; · Identification and regulation of all types of activities which pollute and degrade the environment; · Ensuring sustainable utilization of all natural resources; · Promoting active association with all environment related international initiatives. The Environmental Policy requires the following specific actions with respect to the ‘Industrial’ sector: · To phase in corrective measures in polluting industries; · To conduct Environmental Impact Assessment (EIAs) for all new public and private industrial developments; · To ban, or find environmentally sound alternatives for, the production of goods that cause environmental pollution; and · To minimize waste and ensure sustainable use of resources by industry. Under the National Environmental Policy, Department of Environment is directed to Page 31 ESMF for IPFF 21 review and approve all Environmental Impact Assessments . National Environmental Management Action Plan, 1995 The National Environmental Management Action plan (NEMAP) is a wide-ranging and multi-faceted plan, which builds on and extends the statements set out in the National Environmental Policy. NEMAP was developed to address issues and management requirements and set out the framework within which the recommendations of the National Conservation Strategy are to be implemented. NEMAP has the following broad objectives: · Identification of key environmental issues affecting Bangladesh; · Identification of actions necessary to halt or reduce the rate of environmental degradation; · Improvement of the natural environment; · Conservation of habitats and bio-diversity; · Promotion of sustainable development; and · Improvement of the quality of life of the people. National Conservation Strategy, 1992 The National conservation strategy provides recommendations for sustainable development in the industrial sector as follows: · All industries shall be subject to EIA and adoption of pollution prevention/control technologies shall be enforced; · Hazardous or toxic materials/wastes shall not be imported as raw materials for industry; · Import of appropriate and environmentally sound technology shall be ensured; and · Dependence on imported technology and machinery should gradually be reduced in favor of sustainable local skills and resources. National Water Policy, 2000 The National water policy recognizes that continued development and management of the nation’s water resources is essential and includes protection, restoration and preservation of the environment and biodiversity including wetlands, mangrove and other natural forests, endangered species and water quality. It also states objectives for all agencies and departments entrusted with water management in regards to their responsibilities for regulation, planning, construction, operation and maintenance. Pollution of surface and ground water around various industrial centers from untreated effluent discharge into water courses is a critical water management issue. The Policy of the Government in this regard is that: Page 32 ESMF for IPFF 22 · Zoning regulations will be established for location of new industries in consideration of safe water availability and suitable effluent discharge possibilities; · Effluent disposal will be monitored by relevant government agencies to prevent water pollution; · Standards of effluent disposal into common watercourses will be set by Water Resources Planning Organization (WARPO) of the Ministry of Water Resources in consultation with DoE; · Industrial polluters will be required by law to pay for remedial clean up of water bodies polluted by them. National Water Management Plan, 2001 The National Water Management Plan addresses options for water quality, considerations behind measures to clean up industrial pollution, where effluent discharge monitoring and zoning regulations for new industries are emphasized RELEVANT LAWS AND REGULATIONS IN BANGLADESH A large number of laws related to environmental issues, some dating back to 19 th century exist in Bangladesh. The most important of these are the Environmental Conservation Act, 1995 (ECA 1995) and the Environmental Conservation Rules (under the ECA, 1995) 1997, (ECR 1997). Many of the other laws are cross sectoral and are only partially related to environmental issues. Tab 0 presents an outline of the National legal instruments along with a list of key governmental institutions that have regulatory power over environmental aspects associated with the projects financed by IPFF. Page 33 ESMF for IPFF 23 Table 6. 1 Environment Related Laws and Regulations Laws/ Regulations Enforcing Agencies - Ministry/ Authorities 1. The Environment Conservation Act, 1995 and subsequent amendments in 2000 and 2002 Department of Environment, Ministry of Environment and Forest Regulated/ Enforced Items · Declaration of Ecologically Critical Areas; · Obtaining Environmental Clearance Certificate; Regulation with respect to vehicles emitting smoke harmful for the environment; · Regulation of development activities from environmental perspective; Promulgation of standards for quality of air, water, noise, and soils for different areas and for different purposes; · Promulgation of acceptable limits for discharging and emitting waste; · Formulation of environmental guidelines relating to control and mitigation of environmental pollution, conservation and improvement of environment. 2. Environment Conservation Rules, 1997 and subsequent amendments in 2002 and 2003 Department of Environment, Ministry of Environment and Forest Regulated/ Enforced Items · Declaration of ecologically critical Area; · Requirement of Environmental Clearance Certificate for various categories of projects; Requirement for IEE/EIA according to the appropriate category of the project; Renewal of the environmental clearance certificate within 30 days after the expiry; · Provision of standards for quality of air, water & sound and acceptable limits for emission/discharges from vehicles and other sources. 3. Environment Court Act, 2000 and subsequent amendments in 2002 Judiciary Ministry of Environment & Forest Regulated/ Enforced Items GOB has given highest priority to environment pollution and passed ‘Environment Court Act, 2000’ for completing environment related legal proceedings effectively. 4. The Vehicle Act, 1927 The Motor Vehicles Ordinance, 1983 The Bengal Motor Vehicle Rules, 1940 Bangladesh Road Transport Authority (BRTA) Regulated/ Enforced Items Exhaust emission; Vehicular air and noise; Road safety; Licensing. 5. The Brick Burning (Control) Act, 1989 The Brick Burning (Control) Amendment Act, 1992 Ministry of Environment & Forest Page 34 ESMF for IPFF 24 Regulated/ Enforced Items Control of brick burning requires a license from the MoEF; Restricts brick burning with fuel wood. 6. The Removal of Wrecks and Obstructions in inland Navigable Water Ways Rules 1973 Bangladesh Inland Water Transport Authority Regulated/ Enforced Items Removal of wrecks and obstructions in inland Navigable Waterways. 7. Water Supply and Sanitation Act, 1996 Ministry of Local Government, Rural Development and Cooperatives Regulated/ Enforced Items Management and Control of water supply and sanitation in urban areas. 8. The Ground Water Management Ordinance 1985 Upazila Parishad Regulated/ Enforced Items Management of ground water resources; Tube well shall not be installed in any place without the license granted by Upazila Parishad. 9. The Forest Act, 1927 and subsequent amendments in 1982 and 1989 Ministry of Environment and Forest Regulated/ Enforced Items Reserve Forests; Protected Forests; Village Forests. 10. The Private Forests Ordinance Act, 1959 Regional Forest Officer, Forest Department Regulated/ Enforced Items Conservation of private forests and for the aforestation on wastelands. 11. Bangladesh Wild Life (Preservation) Act, 1974 Ministry of Environment and Forest Bangladesh Wild Life Advisory Board Regulated/ Enforced Items Preservation of Wildlife Sanctuaries, parks, reserves. 12. The Protection and Conservation of Fish Act 1950 subsequent amendments in 1982 Ministry of Fishery Regulated/ Enforced Items Protection and Conservation of fishes in Government owned water bodies. 13. Natural Water Bodies Protection Act 2000 RAJUK/Town Development Authority/Municipalities Regulated/ Enforced Items According to this Act, the character of water bodies i.e. rivers, canals, tanks, or floodplains identified as water bodies in the master plans or in the master plans formulated under the laws establishing municipalities in division and district towns shall not be changed without approval of the concerned ministry. Page 35 ESMF for IPFF 25 14. The Embankment and Drainage Act 1952 Ministry of Water Resources and FCD . Regulated/ Enforced Items An Act to consolidate the laws relating to embankment and drainage and to make better provision for the construction, maintenance, management, removal and control of embankments and water courses for the better drainage of lands and for their protection from floods, erosion and other damage by water. (Source: Different Laws and Regulation of GoB) ENVIRONMENTAL GUIDELINES FOR PROJECTS IN BANGLADESH As pointed out earlier, the most important laws/rules in table 6.1 are the ECA 1995 and the ECR 1997. The ECA1995 is primarily an instrument for the Department of Environment (DoE) and for controlling industrial pollution. The ECR, 1997 was promulgated under ECA, 1995 to operationalize the enforcement of the Act. Depending on the extent of impact on the environment, industries the Department of Environment classifies all the projects in four categories. These are: i) Green; ii) Orange- A; iii) Orange- B; and iv) Red Green Category Projects, which do not have any negative impact on the environment, belong to Green category. For this category of projects, no Initial Environmental Examination (IEE) or Environmental Impact Assessment (EIA) is required. However, the project proponent will have to submit an application in a prescribed format to DOE for Site Clearance Certificate and Environmental Clearance Certificate. Examples · Bamboo and cane goods; · Candle, watches etc. assembling and manufacturing; and · Cork (excluding metallic item). Orange A and B Category Orange category includes those projects that produce such wastes that can produce moderate or significant impacts on environment but the impacts could be mitigated easily if proper action is undertaken. Depending on the nature and extent of impacts the projects under Orange category has been sub-divided into two sub-categories-Orange A and Orange B. The projects/industries likely to produce some wastes but those are not harmful for su rrounding environment and can be managed easily are categorized under “Orange- A”. Example · Small hotel/restaurant business; · Weaving factory; · Handloom industry; Page 36 ESMF for IPFF 26 The “Orange-B” category projects/industries are those likely to produce adverse environmental impacts but not to any significant level and that the impacts can be easily mitigated with no residual adverse impacts. Examples · Mineral water, soft drink, etc., manufacturing and bottling; · Processing of fish; · Meat and other food items; Red Category This category includes industries, first requiring IEE for the purpose of obtaining site clearance, and then EIA, for obtaining environmental clearance. In this case also an application has to be made in a prescribed format along with an IEE report, on the basis of which site clearance may be granted with suitable conditions or the project may be rejected, on grounds of unsuitable location. If the site clearance is granted the project proponent can go ahead with implementation of the project subject to the conditions as may be stipulated while granting the site clearance. Examples · Port development including container terminals, island container depot etc.; · Telecommunication systems, networks and services including information and · Communication technology (ICT); and · Power generation, transmission, distribution and services. INSTITUTIONAL ORGANIZATIONS Department of Environment (DoE) The primary institution for environmental management in Bangladesh is the Department of Environment (DoE), working under the Ministry of Environment and Forest (MoEF). The Department was created in 1989 to ensure sustainable development and to conserve and manage the environment of Bangladesh. The following Policy, Acts and Rules facilitate the activities of the Department · Environment Policy, 1992; · Environmental Conservation Act, 1995 and subsequent amendments in 2000 and 2002; · Environmental Conservation Rules, 1997 and subsequent amendments in 2002 and 2003; · Environment Court Act, 2000 and subsequent amendments in 2002 The principal activities of DoE are: · Defining Environmental Impact Assessment (EIA) procedures and issuing environmental clearance permits - the latter being legal requirements before proposed projects can proceed to implementation stage; · Providing advice or taking direct action to prevent degradation of the environment; · Pollution control, including the monitoring of effluent sources and ensuring mitigation of environmental pollution; · Setting the Water Quality Standard (WQS) for particular uses of water and for discharges to water bodies; and Page 37 ESMF for IPFF 27 · Declaring Ecologically Critical Areas (ECAs) where the ecosystem has been degraded to a critical state. Department of Forest The Department of Forest is responsible for sensitive area protection in four types of legally protected areas- wildlife sanctuaries, game reserves, reserved forests, and natural forests. DOE REQUIREMENTS ON ENVIRONMENTAL ASPECTS For any projects, the sponsor needs to obtain the clearance from the DOE in two stages: a. Initial Stage: Site Clearance Certificate (SCC) b. Advanced Stage: Environmental Clearance Certificate (ECC) a) Initial Stage For obtaining the SCC, the following two documents need to be submitted to the DOE: · An Initial Environmental Examination (IEE) Report and · A TOR for detailed Environmental Impact Assessment (EIA) (with a process flow diagram) Without the SCC, the sponsor cannot apply for approval of the civil design of the project to the local authorities. After the SCC is obtained, the sponsor can proceed for land development and other primary civil works. b) Advanced Stage After receiving the SCC, the sponsors need to proceed for ECC. The EIA has to be submitted to DOE for clearance. After EIA approval, construction of super-structure and erection of capital machinery can be done. ECC needs to be obtained before commercial operation. c) Validity Period of Environmental Clearance Certificate Categories of Project Validity Renewal Period Green 1 year Orange A & B 1 year Red 3 year 30 days before expiry of the validity period WORLD BANK SAFEGUARD POLICIES Safeguard policies, incorporating environmental principles, are designed to protect the interests of third parties from adverse impacts of World Bank-assisted projects. The objective of these policies is to prevent and mitigate undue harm to people and their environment in the development process. The Safeguards are designed to protect the environment from possible adverse effects of its projects. The World Bank’s Safeguard Policies are available with World Bank and on Internets. Table 6. 2: The Safeguard Policies of World Bank on Environmental Issues Page 38 ESMF for IPFF 28 Sl. World Bank Policy Reasons of Applicability Addressed by 1 Environmental Assessment OP 4.01 Project is likely to have impact on natural environments. Particularly, air, water land, human safety, natural habitats, forestry. Preparation of detailed environmental management framework and participation framework to address the environmental issues. 2 Natural Habitats OP 4.04 Project passes through or is adjacent to national parks and / or protected forests. Preparation of an environmental management plan to address impacts, if any, on biodiversity (flora and fauna) 3 Forestry OP 4.36 Project passes through or is adjacent to major forest areas Preparation of the environmental management plan to address impacts, if any, on forest areas (Source: World Bank Documents) CATEGORIES OF PROJECTS ACCORDING TO THE WORLD BANK Based on project type and scale, project location, sensitivity of issues, nature of impacts and magnitude of impacts, World Bank has classified all projects into three categories, viz: Category A, Category B and Category C. These are described in the following sections. Category A: A project is classified as Category A if it is likely to have significant adverse environmental impacts that are sensitive, diverse, or unprecedented. These impacts may affect an area broader than the sites or facilities subject to physical works. EA for a Category A project examines the project's potential negative and positive environmental impacts, compares them with those of feasible alternatives (including the "without project" situation), and recommends any measures needed to prevent, minimize, mitigate, or compensate for adverse impacts and improve environmental performance. For a Category A project, the borrower is responsible for preparing a report, normally an EIA (or a suitably comprehensive regional or sectoral EA) Category B A project is classified as Category B if its potential adverse environmental impacts on human population or environmentally important areas--including wetlands, forests, grasslands, and other natural habitats--are less adverse than those of Category A projects. These impacts are site-specific; few if any of them are irreversible; and in most cases mitigatory measures can be designed more readily than for Category A projects. The scope of EA for a Category B project may vary from project to project, but it is narrower than that of Category A EA. Like Category A EA, it examines the project's potential negative and positive environmental impacts and recommends any measures needed to prevent, minimize, mitigate, or compensate for adverse impacts and improve environmental performance. Page 39 ESMF for IPFF 29 Category C A project is classified as Category C if it is likely to have minimal or no adverse environmental impacts. Beyond screening, no further EA action is required for a Category C project. COMPARISON BETWEEN GOB AND WB GUIDELINES After reviewing the law of GoB and World Bank guidelines, it is necessary to identify the similarities and differences between those so that the more stringent requirements can be applied for the sub projects. In general OP 4.01 requirements are more comprehensive when compared with the requirements of Bangladesh legal system. Table 6.3 lists some key comparisons between GoB and World Bank guidelines. Table 6. 3 : Comparison between GoB and World Bank Guidelines Sl Criteria Requirements as per GoB law Requirements as per OP 4.01 1 Type of Environmental Analysis Project specific Project specific, regional and sectoral 2 Basis for Categorization Currently, screening criteria available only for industrial projects, where assessment is done based on: · Level of pollution emission · Type of project and location · Scale of project · Operational activities Non –industrial projects are reviewed on a case by case basis by DOE Detailed screening criteria for all projects based on · Sensitivity · Nature and magnitude of potential impacts 3 EA Outputs Since detailed rules and regulations for EA have not been prescribed, EA outputs are not specified. However, the industrial sector guidelines, the water sector guidelines and the road sector guidelines have specific EA output requirements, such as: · Baseline survey · IEE/EIA Report · Site clearance · Risk analysis and management · Analysis of alternatives · EA Report · Analysis of alternatives · Environmental Management Plan 4 Public Consultation No special mention is made for public consultation in BECA. Sectoral guidelines mentioned above have prescribed consultation. Mandatory at the stage of · Preparation of EA · Project appraisal · Project design · Project implementation and monitoring Page 40 ESMF for IPFF 30 5 Disclosure of Information BECA makes no reference to disclosure. The Sectoral guidelines prescribe some provisions for disclosure Mandatory at · Summary of project description an potential adverse impact · Summary of EA report and conclusion · EA report (Source: ESF, IDCOL, 1997) Page 41 ESMF for IPFF 31 ENVIRONMENTAL IMPACT AND MITIGATION MEASURES OVERVIEW The analysis of the environmental impacts is an important tool in determining the appropriate mitigation measures to be employed. Identifying the related impacts is an exhaustive process that always has to be updated. The most important impact for the projects is the activities and its associated effects on the environment. This section gives a broad overview of the probable impacts that might occur during the project implementation and execution, including a general indication to the seriousness or significance of potential impacts. It also discusses the possible mitigation measures that can be put in place to mitigate any negative impacts and enhance the positive ones. POTENTIAL IMPACTS Considering the interaction between engineering operations and activities and the environment, the potential impacts occurring in the following three phases are considered: i) Pre – Construction (Planning and Design) ii) Construction iii) Operation & Maintenance It is recommended that the impact assessment measures the performance during all the three phases against the baseline position. Pre-Construction (Planning and Design) Phase The location of industry in an environmentally sensitive area such as a wildlife sanctuary, game reserve, protected wetland, forest or area of cultural importance has the potential to cause adverse impacts. Table 7. 1 Site Location and Sensitivity presents the framework for assessing the sensitivity of a sub-project depending upon its location. Table 7. 1 Site Location and Sensitivity SL Environmental Issues Low Sensitivity Medium Sensitivity High Sensitivity 1 Natural Habitats No critical natural habitats; no other natural habitats No critical natural habitats; other non- forest natural habitats present Critical natural habitats [Critical natural habitats are defined as existing and proposed protected areas] along with unprotected natural habitats of known high importance for biodiversity conservation. 2 Induced Development Area or region is well consolidated; dense road network Medium density road network; open lands are still available Area or region is undeveloped; road network is incipient or non-existent 3 Soil Stability / Erosion Flat terrain; no potential erosion problems. Medium slopes; some erosion potential Mountainous terrain; high slopes; unstable soil formations; high erosion t tial Page 42 ESMF for IPFF 32 SL Environmental Issues Low Sensitivity Medium Sensitivity High Sensitivity potential (Source: ESMF, PSDSP Economic Zone Project, 2009) Construction Phase Generally, construction impacts are expected to affect the environment for a relatively short time period and these are expected to cease soon after the completion of construction. The potential major impacts are described herein: a) Impact on Flora and Fauna The construction of buildings and other infrastructure could result in clearing and depletion of vegetation that will result in loss of plant cover, disturbance and loss of fauna habitats, weakening and degradation of soils, disturbance of the natural landscape and disfiguring of the natural morphology. b) Impact on Soil and Land Degradation Earthmoving equipments such as excavators are likely to be used in cutting/excavation works. These equipments may expose the soil to erosion and also compact it and may break down the soil structure, which may potentially decrease the drainage of the areas. Furthermore, the risks of accidental discharge of hazardous products, leakage of hydrocarbons, oils or grease from construction machinery also constitute potential sources of soil and water pollution. c) Impact on Vehicular Traffic Construction work may result in a high traffic volume within the area. Wastes generated from project activities such as cement bags, paint drums and debris may result in pollution and constitute obstructions to vehicular traffic. d) Impact on Waste Management Activities at construction sites may produce construction wastes such as excavated soils and debris. In addition, unmanaged waste can have a significant indirect economic impact by reducing the price of properties nearby and in general, by affecting the aesthetics, child- friendliness and overall condition of the environment. e) Impact on Slope, Erosion and Drainage If the topography of the project area is hilly, erosion problems during construction are likely to be more severe, as compared to a flat area. However, if the area is flat, water may not drain away easily, in general, and stagnant pools of water may get created. These pools, if not drained regularly may provide favorable breeding grounds for mosquitoes. f) Impact on Air Quality Page 43 ESMF for IPFF 33 Air quality will be impacted by emissions from vehicles, earthmoving equipment and released particulate matter. g) Impact on Water Quality Water quality may be impacted by wastewater discharge from construction activities. These will include discharge from onsite sewage system and rainwater run-off. The discharge of this wastewater into surface water may impact water quality by causing changes to its physical, chemical and biological properties. Given the high anticipated volume of waste/spoil that may be generated, it is likely that the waste may get stockpiled on road sides. If it is not properly contained, rains could carry it along with runoff into other surface waters, leading to increased turbidity and siltation. This could affect aquatic resources such as fisheries etc. Operation and Maintenance Phase Operational impacts continue during the life of the project after the completion of construction phase and may last for a longer time. Operation of industries emits a number of pollutants that need to be carefully mitigated and monitored. Main pollutants during the operation phase are as follows: a) Liquid Wastes ƒ Process Water from the industries ƒ Domestic Sewage ƒ Oils & Grease ƒ Contaminated Water ƒ Solvents b) Solid Wastes ƒ Packaging materials ƒ Raw material residues ƒ Container residues ƒ Scrap metals ƒ Sludge containing various toxic metals c) Air Emission ƒ Smoke ƒ Volatile organic compounds ƒ Particulates ƒ Oxides of Nitrogen ƒ Sulphur dioxide ƒ Carbon Dioxide d) Noise ƒ Use of machineries e) Health & Safety ƒ Water pollution hazards Page 44 ESMF for IPFF 34 ƒ Potential Fire Hazards ƒ Handling of Chemicals ƒ Heat Generation ƒ Air pollution hazards f) Smell ƒ Effluent discharge ƒ Use of chemicals g) Visual impact ƒ Construction of industries and buildings ƒ Smoke MAJOR ENVIRONMENTAL IMPACTS Table 7.2: Major Environmental Impacts gives an overview of the major environmental impacts resulting from the preconstruction, construction and operation of IPFF Projects. Table 7.2: Major Environmental Impacts SL Parameters Impacts 1 Soil ƒ Possible increase in soil erosion as a result of the construction activities (clearing of vegetation and soil excavation) ƒ Loss of productive topsoil resulting from site clearance ƒ Soil contamination resulting from the release of chemicals (lubricant, fuel, paint) from the machinery 2 Water ƒ Run-off erosion may occur from unprotected excavated areas during heavy rain resulting to sedimentation of the nearby water-bodies ƒ Potential pollution of the water bodies through run-off of hazardous construction waste (lubricants, cements, paint and fuels) ƒ Contamination of surrounding water bodies through improper disposal of industrial effluent and sewage during operation ƒ Possible run off from the temporary solid waste storage site into the drainage system (during the project operational phase) 3 Ecosystem ƒ Destruction of vegetation, loss of habitat and loss of biodiversity ƒ Possible loss of endangered and rare species ƒ Change in land use and disturbance of ecosystem ƒ Contamination of biota 4 Air ƒ Particulate matters emission from construction activities ƒ Emission of pollutants (NOx, SOx, CO) from the construction ƒ Machineries ƒ Possible release of micro organisms to the air during the operational phase of the project 5 Noise ƒ Construction equipment will generate noise above the usual level 6 Landscape ƒ Change in natural drainage pattern ƒ Destruction of vegetation and trees ƒ Deforestation and desertification ƒ Visual impact Page 45 ESMF for IPFF 35 ASSESSMENT OF IMPACTS This section contains a discussion of the possible environmental effects of the IPFF sub- projects for the specific issue areas that were identified as having the potential to experience significant impacts. “Significant effect” can be defined as ‘a substantial, or potentially substantial, adverse change in any of the physical conditions within the area affected by the project including land, air, water, minerals, flora, fauna, ambient noise, and objects of historic or aesthetic significance.’ An economic or social change by itself shall not be considered a significant effect on the environment, but may be considered in determining whether the physical change is significant.” In the impact analysis, significance thresholds are those criteria which are universally recognized, or are developed specifically for a single project analysis to determine whether potential effects are significant. Environmental impacts of the sub-projects can broadly be classified as those taking place during pre-construction, construction and operational phases. The overall strategy has the following sequence: Types of Impacts are grouped into four classes. These are: i) Class I Significant and Unavoidable: An impact that cannot be reduced to below the threshold level given reasonably available and feasible mitigation measures. Significance thresholds are those criteria which are developed specifically to determine whether potential effects are significant. ii) Class II Significant but Mitigable: An impact that can be reduced to below the threshold level given reasonably available and feasible mitigation measures. iii) Class III Not Significant: An impact that may be adverse, but does not exceed the threshold levels and does not require mitigation measures. However, mitigation measures that could further lessen the environmental effect may be suggested if readily available and easily achievable. iv) Class IV Beneficial: An effect that would reduce existing environmental problems or hazards. In those cases where the mitigation measure for an impact could have a significant environmental impact in another issue area, this impact is discussed as a residual effect. The impact analysis concludes with a discussion of cumulative impacts, which evaluates the impacts associated with the proposed project in conjunction with other future development in the area. Significant and Unavoidable (I) Significant but Mitigable (II) Beneficial (IV) IMPACTS Page 46 ESMF for IPFF 36 Cumulative Impacts Cumulative impacts can be defined as impacts, which potentially develop from the combined impacts of more than one project or large scale program occurring within the same area of influence and time span. In such cases, cumulative impacts will have to be assessed based on the combined effects of potential impacts from the various program inputs. The cumulative impacts may occur due to the following environmental parameters: · Change in Land use · Traffic · Industrial Wastewater Effluent · Solid Waste Disposal · Noise MITIGATION MEASURES This section includes the principles, procedures and mitigation measures that are relevant and suitable to the project for ensuring the most appropriate environmental mitigation and enhancement plans applicable during different stages of project implementation. To avoid and minimize the impacts resulting from the activities of different sub-projects, measures/management plans, which are essential to mitigate the impacts as discussed, are based upon appropriate technological design, improvements or adjustments, policy including good site operational practices etc. Therefore, the mitigation plan has been adopted to highlight the action procedures to avoid/minimize / control the resultant impacts arising out of the different project phases i.e. pre-construction, construction and operation which are elaborately described in the following Table 7. 3 Mitigation Measures. Table 7. 3 Mitigation Measures Responsibility Issue Mitigation Measure Time Frame Implementation. Supervision /Monitoring A. CONSTRUCTION PHASE a) Soil Disposal from excavated earthworks · Earthwork cuts will be used where possible · Residual spoil will be disposed of according to the erosion prevention plan During Construction Project Sponsor IPFF Loss of Top Soil · Topsoil from all areas to be permanently covered shall be stripped, stored and used for re- vegetation works; · Construction vehicles, During Construction Project Sponsor IPFF Fig 7. 1 Impact Structure Page 47 ESMF for IPFF 37 machinery, and equipment shall move or be stationed in designated areas. Access to adjacent agricultural land will be minimized Soil erosion and Water Pollution · Measures as per design or as directed by the Consultants to control soil erosion. Earth materials and stone will be properly disposed of so as not to block rivers, resulting in adverse impact on water quality. · Measures will be taken to prevent earth works · Mitigation measures will be taken to prevent the untreated wastewater produced in construction from entering into creek and streams During Construction Project Sponsor IPFF b) Water Resources Siltation of water bodies · Measures to prevent erosion will be taken in accordance with the erosion prevention plan During Construction Project Sponsor IPFF Contaminated runoff from inappropriately stored hazardous materials · Solid hazardous and non hazardous wastes will be appropriately stored to prevent contaminated runoff to adjacent waterways During Construction Project Sponsor IPFF c) Air Quality Generation of Dust · Water will be sprayed on construction sites, exposed sites and earth roads to minimize dust; · Concrete batching plants and crushing plants will be sited at least 500 m from the nearest habitation and fitted with dust extraction units in compliance with national air quality standards During Construction Project Sponsor IPFF Emissions from construction vehicles, equipment and machinery · All emissions will meet standards. · Developer will submit dust suppression program before construction During Construction Project Sponsor IPFF d) Noise Quality Page 48 ESMF for IPFF 38 Noise from vehicles, plant, and earth moving equipment · Within 200 m of the nearest habitation, construction work will be restricted to between 0600 to 2100 hours. · Maintenance of machinery and vehicles should be enhanced to keep their noise within acceptable level During Construction Project Sponsor IPFF e) Impact on Flora Loss of or damage to Vegetation · Minimum damage or disruption to the flora. Trees or shrubs will be removed that impinge directly on the permanent works or necessary temporary works. During Construction Project Sponsor IPFF f) Impact on Fauna Loss or Damage or Disruption of Fauna · All works are to be carried out in such a fashion that the damage or disruption of the fauna is minimum. During Construction Project Sponsor IPFF g) Waste Management Generation of Solid wastes · Solid waste generated to be accumulated at one place and treated. During Construction Project Sponsor IPFF B. OPERATION & MAINTENANCE PHASE Industrial Effluent · All recommendations on ESMP shall be implemented. · All industrial effluent will be directed to central effluent treatment plant before disposal · Industrial Effluent will be treated to applicable standards Throughout Operation Period Project Operator IPFF Air Emission · All recommendations of ESMP shall be implemented. · Suitable dust collectors (bag filters) shall be provided at all major emission source. · For dispersion of the hot air from boiler stack, it is recommended that the height of the stack chimney should be at least 2.5 times of the nearest height of the building Project Operator IPFF Page 49 ESMF for IPFF 39 · The effluents will be treated to applicable standards Noise · All recommendations of ESMP shall be implemented. · Proper design and sound management practice will be adopted · The noise emission shall conform to applicable standards · Green belts as sound barriers shall be established. · Monitoring will be conducted during the operational phase to confirm noise-modeling results. Throughout Operation Period Project Operator IPFF Solid Waste · All materials will be disposed through central solid waste management system Throughout Operation Period Project Operator IPFF Occupational Health · Occupational, Health and Safety Program will be adopted. · Review and evaluate to improve the effectiveness of Environmental Health and Safety Program Throughout Operation Period Project Operator IPFF Page 50 ESMF for IPFF 40 PART – C SOCIAL MANAGEMENT FRAMEWORK LEGAL AND INSTITUTIONAL FRAMEWORK (SOCIAL) OVERVIEW The World Bank – the financer of the IPFF project), requires the project sponsors to identify, review and abide by all laws of the host country that are applicable to land acquisition and involuntary resettlement including: · The scope of the power of eminent domain and the nature of compensation associated with it, both the procedures for assessing compensation values and the schedule for making compensation payments · The legal and administrative procedures applicable, including the appeals process and the normal time for such procedures · Land titling and registration procedures · Laws and regulations relating to agencies responsible for implementing resettlement and those related to land compensation, consolidation, land use, environment, water use, and social welfare The table below lists the relevant National laws relevant for the project sponsor to comply with and the government agencies responsible for different aspects of the social management for sub-project to be funded by IPFF. RELEVANT NATIONAL LEGISLATION Table 8. 1 : Relevant National Legislation Laws/Regulations Enforcing Agencies- Ministry/Authorities 1. Antiquities Act 1968 Ministry of Cultural Affairs Regulated/ Enforced Items This legislation governs preservation of the national cultural heritage, protects and controls ancient monuments, regulates antiquities as well as the maintenance, conservation and restoration of protected sites and monuments, controls planning, exploration and excavation of archaeological sites. 2. The Building Construction Act 1952 (with amendments) Ministry of Works Regulated/ Enforced Items An Act to provide for the prevention of haphazard construction of building and excavation of tanks which are likely to interfere with the planning of certain areas in Bangladesh. 3. · The Land Acquisition Act, 1894 · The Acquisition and Requisition of Immovable Property Ordinance 1982 and subsequent amendments in 1994, 1995 and 2004 Revenue Department Page 51 ESMF for IPFF 41 Laws/Regulations Enforcing Agencies- Ministry/Authorities 4. Regulated/ Enforced Items Current GoB Act & guidelines, relating to acquisition of land 5. The Factories Act, 1965 and Bangladesh Labor Law, 2006 Ministry of Labor 6. Regulated/ Enforced Items This Act pertains to the occupational rights and safety of factory workers and the provision of a comfortable work environment and reasonable working conditions. ACQUISITION AND REQUISITION ORDINANCE, 1982 In 1982, the Acquisition and Requisition of Immovable Property Ordinance, came in force. This law replaced the earlier law, The Land Acquisition Act, 1894 (I of 1894) and others that have been in force between 1947 and 1982, and is the major basis for all the present actions regarding acquisition, resettlement and rehabilitation. The relevant and salient points of the 1982 law are as follows: "Property" means only immovable property (land and building) and includes any right in such property and "Owner" includes the occupiers. Matters to be considered in determining compensation include o the market value of property o damage to standing crops or trees due to acquisition o damage due to severance of acquired property from other property at the time of actual taking of permission by concerned authorities o damage to other properties or earnings o expenses for relocation of residence o damage due to lowering of profit of the property to be acquired between the serving of acquisition notice and actual acquisition. While the rules under the Act 'appear' fairly generous, problems often arise in implementing the provisions of the Act. Determining market value and damage to property or income are difficult to establish in normal circumstances. It becomes more so in an emotion charged situation such as acquisition of land in a land-scarce and agricultural- dependent society. Arbitrariness is almost certainly likely to result. The situation is not helped by assigning by the government to itself sweeping powers in matters of acquisition. Read with the Article 42, sub clause (2) of the Constitution referred to above, there is every chance that the acquisition may not be entirely necessary, that compensation may be rather inadequate or paid such later than actual acquisition. To sum-up the legal context, while there are constitutional and legal provisions for acquisition and payment of compensation for acquisition of land and other immovable property for state-determined purposes, there are also uncertainties in the actual practice because of lack of clear guidelines, sweeping power given to Deputy Commissioners who actually serve notice and take possession of acquired property and the denial of legal instruments to citizens against such actions. The present laws, acts, regulations and rules are not very explicit regarding resettlement and rehabilitation of project-affected people (PAP). One can, however, as indicated earlier interpret the spirit and letter of these laws (including constitutional provisions) and rules to Page 52 ESMF for IPFF 42 imply that resettlement and rehabilitation of people adversely affected due to the project is the responsibility of the project authorities. As a result, in recent years there have been several instances where attempts have been made and are being made to take affirmative action. In all such cases the core idea is to prepare an entitlement matrix based upon an entitlement policy. Entitlement here means the rights of the persons adversely affected by the project to receive certain benefits from the project authorities to compensate for their losses that may include land and other immovable property, income, standing crops, occupation etc. The compensation is often in terms of cash grants but also includes training and credit facilities and other necessary facilities in resettlement and rehabilitation. WORLD BANK’S SAFEGUARD POLICIES OP 4.12 Requirements (Involuntary Resettlement) The primary objective of the World Bank policy on is to explore all alternatives to avoid or minimize involuntary resettlement. Where resettlement is unavoidable, the resettlement activities should be conceived and executed as sustainable development programs, providing sufficient resources to enable affected persons to share in project benefits and to assist in their efforts to improve their livelihood and standard of living, or at least to restore them to pre-project level. The policy also requires that affected people are meaningfully consulted and should have opportunities to participate in planning and implementing resettlement programs. Measures required to ensure that resettlement has a positive outcome are as follows: · Providing project-affected persons with options; permitting their participation in planning and selecting these options; prompt compensation at full replacement cost for losses; choosing relocation sites that provide, at a minimum, the same benefits as the sites that are replaced; · Providing allowances and other assistance to make a smooth transition after displacement · Identifying vulnerable groups and providing special assistance to these groups · Implementing an institutional structure that supports the process to a successful end. World Bank's policy on Involuntary Resettlement requires payment of compensation and other assistance to project affected people before they are displaced from their existing locations. Further, the policy requires income rehabilitation assistance to those affected due to the loss of their productive assets or loss of incomes and livelihood. Absence of legal title does not exclude affected individuals from the eligibility to receive compensation and or other assistance. The Policy also requires that those without a legal title should be given assistance to meet the objectives of the policy. The genesis of these rights may come from continued possession of public land where the government has not sought eviction. The Bank's policy also recognizes that stakeholders who illegally occupy project-affected areas after established cut-off-date for any components are not eligible for compensation. Institutional or project specific policies are being prepared to address these gaps and to meet the requirements of multilateral agencies and best practices. Page 53 ESMF for IPFF 43 The principles for World Bank OP 4.12, involuntary resettlement are ƒ Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project plans ƒ Where it is not feasible to avoid resettlement, resettlement activities should be conceived and executed as sustainable development programs. ƒ Displaced persons should be assisted in their efforts to improve their livelihoods and standards or at least restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher. OP 4.10 Requirements (Indigenous Peoples) This policy contributes to the WB’s mission of poverty reduction and sustainable development by ensuring that the development process fully respects the dignity, human rights, economies, and cultures of. The Bank recognizes that the identities and cultures of Indigenous Peoples are inextricably linked to the lands on which they live and the natural resources on which they depend. These distinct circumstances expose Indigenous Peoples to different types of risks and levels of impacts from development projects, including loss of identity, culture, and customary livelihoods, as well as exposure to disease. As social groups with identities that are often distinct from dominant groups in their national societies, Indigenous Peoples are frequently among the most marginalized and vulnerable segments of the population. A project proposed for Bank financing that affects Indigenous Peoples requires: · Screening by the Bank to identify whether Indigenous Peoples are present in, or have collective attachment to, the project area · A social assessment by the borrower · A process of free, prior, and informed consultation with the affected Indigenous Peoples’ communities at each stage of the project, and particularly during project preparation, to fully identify their views and ascertain their broad community support for the project. · The preparation of an Indigenous Peoples Plan (IPP) or an Indigenous Peoples Planning Framework (IPPF). · Disclosure of the draft Indigenous Peoples Plan or draft Indigenous Peoples Planning Framework The borrower makes the social assessment report and draft IPP/IPPF available to the affected Indigenous Peoples’ communities in an appropriate form, manner, and language. Before project appraisals, the borrower sends the social assessment and draft IPP/IPPF to the Bank for review. Once the Bank accepts the documents as providing an adequate basis for project appraisal, the Bank makes them available to the public in accordance with The World Bank Policy on Disclosure of Information, and the borrower makes them available to the affected Indigenous Peoples’ communities in the same manner as the earlier draft documents. Page 54 ESMF for IPFF 44 COMPARISON OF REQUIREMENTS OF GOB AND WB While Bangladesh law provides for land acquisition, the regulations and rules are not very explicit regarding the resettlement and rehabilitation of Project Affected People (PAP). The World Bank OPs, on the other hand, are more comprehensive requiring the following: · Payment of adequate compensation for various losses at replacement value. · Rehabilitation to ensure improvement/or at least restoration of lost economic activities, income and standard of living. · Public consultation during the entire process of social assessment and disclosure of information (where ensuring that the information available to stakeholders is adequate and accessible is key) · A grievance procedure that is accessible and adequately responsive (time for processing claims, etc) A Resettlement Action Plan, and where appropriate, an Indigenous Peoples’ Development Plan While Bangladesh law (Ordinance 1982) provides for land acquisition, the regulations and rules are not very explicit regarding the resettlement and rehabilitation of PAPs. The World Bank ODs, on the other hand, are more comprehensive and stringent, requiring, among other things, the following: · Payment of compensation for various losses at replacement value · Rehabilitation to ensure improvement/restoration of the standard of living · Public consultation during the entire process of social assessment and disclosure of information. · A Resettlement Action Plan, and where appropriate, an Indigenous Peoples Development Plan Tables below lists some key comparisons between Bangladesh Law and WB policy regarding land acquisition and compensation. Table 8. 2 : Comparison: Bangladesh law and World Bank OP 4.12 Issue 1982 ORDINANCE OP 4.12 Coverage Legal owners Share-croppers Tenants All affected parties, including squatters and illegal occupants Compensation Based on market values over previous 12 months Replacement cost at current market price Requires livelihood restoration component. Uses of material from dismantled structures Material is to be auctioned after being compensated for it Material can be taken and re-used by affected party Page 55 ESMF for IPFF 45 Minimization of impacts Discourages unnecessary acquisition but no mechanism to monitor Alternative analysis required to justify avoidance and/or mitigation of impacts Cut-off dates Not addressed Important to ensure that squatters are included in compensation and to prevent rent-seeking behavior of additional squatters settling onto project land Consultation No consultation required Consultation as core issue in RAP preparation and implementation Relocation assistance No assistance provided Relocation assistance required Livelihood restoration Not addressed Livelihood restoration component and attention to post-resettlement required ADDRESSING WORLD BANK SAFEGUARD POLICIES Table 8. 3 : Addressing World Bank Safeguard Policies World Bank Policy Reasons of Applicability Addressed by Physical Cultural Resources OP 4.11 Project may pass through culturally significant areas – including areas that are an integral part of a people’s cultural identity and practices Usually avoided by Govt. authorities while selecting the site Involuntary Resettlement OP 4.12 Project may require physical relocation of people or entire communities and/or private property acquisition (land, commercial, residential and other structures) leading to resettlement. A process of consultation, including adequate and accessible disclosure of any resettlement information. Preparation of a Resettlement Framework and compensation plan and entitlement policy and updating them in accordance with changes in the Project involving land acquisition. This includes an accessible grievance procedure. Indigenous Peoples OP 4.10 Project affecting the dignity, human rights, economic and cultures of Indigenous Peoples because of acquisition of land and common resources on which they depend for their social, economic and cultural needs and also their homesteads requiring relocation. Preparation of Indigenous Peoples’ Development Plan (IPDP) based on Social Impact Assessment that involved free, prior and informed consultations and updating it in accordance with changes in the Project that involves Indigenous Peoples. Page 56 ESMF for IPFF 46 Page 57 ESMF for IPFF 47 SOCIAL MANAGEMENT PROCESS GENERAL Social issues are usually common to all sectors with the degree of effect of any issue varying on an individual basis. The major social issues related to infrastructure projects include: (i) site planning (ii) involuntary resettlement; (iii) protection of marginalized and vulnerable groups; and (iv) public consultation, participation, and consensus building. All proposed investments in the IPFF, based on the significance of impact, would fall in three categories using WB policies, as classified in Section 6.8. · Category “A” projects involve land acquisition, resettlement, or indigenous peoples. These will require the project sponsor to prepare appropriate plans in compliance with WB policy criteria OP 4.12 and OP 4.10. · Category “B” projects will require preparation of a Social Management and Monitoring Plan as needed to address salient social risks. · Category “C” projects have minimal or no adverse environmental or social effect and need no further action beyond screening. STAGES IN PROJECT DEVELOPMENT All projects and policies go through a series of steps or stages, starting with initial planning, then implementation and construction, carrying through to operation and implementation. It is imperative for the project sponsor to understand that Social impacts will be different for each stage; therefore it is essential to define the stages in project development: a) Pre-Construction This refers to all activity that takes place from the time a project or policy is conceived to Stage 1. Pre-Construction Stage 2. Construction/Implementation Stage 3. Operation/Maintenance Page 58 ESMF for IPFF 48 the point of construction activity or policy implementation. Examples include project design, revision, public comment, licensing, the evaluating of alternatives, and the decision to go ahead. b) Construction/Implementation This stage begins when a decision is made to proceed, a permit is issued or a law or regulation takes place. This involves clearing land, building access roads, developing utilities, displacement and relocation of people. The build-up of a migration work force may occur creating social stresses. c) Operation/Maintenance This stage occurs after the construction is complete. It is during this stage that communities seeking industrial development will focus their attention on the long-term economic benefits that accrue from a development. FLOWCHART FOR SMF The flow chart is prepared to illustrate the social compliance activities for preparation of an infrastructure project for obtaining IPFF loan. The flow chart given below, in Fig. 8.1, provides a guideline to the project sponsor in carrying out the necessary steps to address social requirements of a sub-project for IPFF funding. A Social Impact Assessment (SIA) of the project, with a socio-economic sample survey of the project and influence area is a must for assessment of the project. This SIA will determine if any RAP or IPDP will be required to be done. If the land is procured by the project sponsor through voluntary negotiation or the land has been acquired by the government beforehand, then no RAP etc, will be required. Page 59 ESMF for IPFF 49 Fig 9. 1: Social Management Flowchart SOCIAL COMPLIANCE MATRIX The matrix below has been designed considering OP 4.12 and OP 4.10 of World This will assist the project sponsor to comply with the requirement for social aspects for IPFF funding. Table 9. 1: Social Compliance Matrix Project Stage Action required Applicable standards and institutional responsibility Pre-feasibility studies Social screening For projects not requiring specific resettlement and land acquisition studies social performance frameworks will be designed OP 4.12 para 27 For FIL projects requiring involuntary resettlement, the financial intermediary (FI) screens sub-projects to ensure consistency with OP 4.12. If the initial screening identifies indigenous peoples present, screening as stated in OP 4.10 will be undertaken. Public information campaign/communication, consultation and participation The project sponsor will carry out a public information campaign (which may be monitored by the relevant implementing agency) that will comply with OP 4.12 Project Design Scoping: Identify significant potential impacts and project WB OP 4.12 The project sponsor will identify the Socio-economic census Survey, in Project footprint area, for RAP preparation. Project Affected People (PAP) list and ID card distribution Consultation with different level stakeholders Social Screening by the project area, by the sponsor Disclosure of Project information to and Consultations with potential affected persons. Socio-Economic (sample) Survey, PRA and FGD in Project and Surrounding Area, Social Impact Assessment (SIA) and Social Management Plan (SMP) RAP preparation (No. of PAP will decide the extent of RAP) Disclosure of RAP information to the people only the social issues and policies. Engagement of RAP Implementation Agency (Consulting Company or NGO) Grievances and Redress Mechanism management RAP approved by WB Payment of Additional Entitlement to PAP, by the project Relocation and Rehabilitation Activities Monitoring of SMP If RAP is required If IPDP is required (refer OP 4.1) If RAP is not required, Social Performance Framework will be prepared Page 60 ESMF for IPFF 50 Project Stage Action required Applicable standards and institutional responsibility alternatives and propose terms of reference for SIA presence of significant potential impacts and assess against project alternatives and then propose terms of reference for the SIA Baseline Data Collection (SIA): Identify current socio-economic conditions without the project and update it during the project with changes The project sponsor will carry out a sample socio-economic survey of both proposed project area as well as surrounding areas of the project that would have impacts. The socio- economic survey would have to comply to OP 4.12 Annex A Estimate social impacts The project sponsor will estimate impacts based on OP 4.12 For IPDP, OP 4.10 Annex A will be considered. Preparation of SMP The project sponsor to design plan for specific actions during land acquisition, engineering design and construction stages to conform to GoB requirement (Acquisition & Requisition of Property Ordinance 1982) as well as World Bank’s requirements OP 4.12 Preparation of RAP on the basis of SIA The project sponsor will prepare a RAP following OP 4.12 Annex A Preparation of IPDP on the basis of SIA The project sponsor will prepare IPDP (if indicated by the SIA) following OP 4.10 Annex B Design mitigation measures The project sponsor will design mitigation measure in line with OP 4.12. For Indigenous peoples OP 4.10 will be consulted. Project Appraisal/ Approval Review and Approval of RAP PFI is to review report to assess compliance with WB 4 OP.12 and if relevant OP 4.10. Also to check for compliance with GoB’s requirements for compensation for LA. Implementation Plan Implement SMP Appointed Agency (Consulting company or NGO) to implement Engineering Design & Construction Works Social Monitoring of SMP Appointed Agency (Consulting company or NGO) to implement Post-Construction Social Audit and regular monitoring arrangements and evaluation Selected Agency (Consulting company or NGO)to audit Page 61 ESMF for IPFF 51 SOCIAL SCREENING To assess the precise nature and magnitude of social impacts, social screening may be conducted as part of the feasibility study for each subproject. To ensure consistency in the application of social screening criteria, a standard field level social screening checklist needs to be used. To the extent possible, social and environment screening should be carried out together with technical and economic screening. Social screening will identify the probability for loss of land assets/structures, livelihoods, willingness of the community to donate land to the project, and other significant social impacts. Social screening also enables the categorization of subprojects based on the level of social impacts. Where the extent of adverse social impacts is minor and no displacement or loss of assets or livelihoods is expected, no further action is required. However, where the social screening indicates that land acquisition and/or loss of assets are unavoidable, appropriate resettlement plans are of paramount importance PUBLIC INFORMATION CAMPAIGN AND CONSULTATION The World Bank requires participation by interested parties and PAPs in the assessment of social effects of a project. The public Involvement takes two forms: a formal and an informal process. The primary purposes of the consultation and participation process are: dissemination of information to the participants; solicitation of information relative to the interests of the participants; and solicitation of comments, concerns and suggestions for inclusion in the development of the project. The first step is the identification of who will actually be involved in the social assessment process. In general, the participants will include all governmental agencies and ministries that have statutory responsibility for management of resources affected by the project. A second group of potential participants are the NGOs including national organizations and CBOs. The third group includes the local population that will be directly or indirectly affected by project implementation. Involvement of the Host Populations The population living in the areas identified as hosts for a relocated population also needs to be integrally involved in the planning and implementation of a resettlement plan. Formal Consultation Process Frequently, the initial contact with participants by the project sponsor is achieved through distribution of the Scoping Document. Included in the scooping document is an invitation to participate in a workshop to discuss the project and its objectives and to discuss the particular social concerns of the agencies and the local population. A second workshop is advised, especially for larger, more complex projects to review the status of the studies being conducted are obtaining the information necessary. Upon completion of a draft RAP and IPDP, a final workshop is recommended to obtain oral Page 62 ESMF for IPFF 52 comments and suggestions from the various stakeholders. The formal consultation process should also include the solicitation and receipt of written comments and suggestions on all social documents. Informal Consultation Process Informal consultation like Focus Group Discussion (FGD) with various stakeholders throughout the Social Assessment process is strongly encouraged. This consultation includes discussions with the various governmental organizations involved and interactions with NGOs and local populations to discuss various social issues pertinent to the planning and implementation of the project. A record of the informal discussions with agencies and/or other participants should be included in the SMP. RECORD OF CONSULTATION A record of the formal and informal consultation with participants is an important component of the SMP. The record will verify that PI requirements of WB have been met satisfactorily. The PI record should include for workshops: an agenda of workshops, minutes of the workshop proceedings, issues discussed, responses to issues, a list of attendees, for written comments: actual letter containing comments and suggestions, the project sponsors responses to the comments and suggestions with rationale; for informal discussions with Agencies: brief memoranda describing topics discussed, information obtained from agencies, issues and suggestions raised and responses; for informal discussions: brief memoranda describing persons and situations of the discussions, issues discussed, information obtained and responses of the Project sponsor to issues and concerns raised. SOCIAL IMPACT ASSESSMENT (SIA) The SIA is one of the primary requirements of the project sponsor in order to comply with social requirements for a World Bank-assisted project. The project sponsor should use social impact assessment specialists for the SIA. Identifying Social Impact Assessment Variables. This is another important consideration before conducting the SIA, as this incorporates the local characteristics of the project affected areas and establishes a baseline for variables that would be used to collect data. A general list of social variables is given below: a) Population Characteristics : present population and expected change, ethnic and racial diversity, and influxes and outflows of temporary residents as well as the arrival of seasonal or leisure residents. b) Community and Institutional Structures: the size, structure, and level of organization of local government including linkages to the larger political system c) Political and Social Resources : distribution of power authority, the interested and affected publics, and the leadership capability and capacity within the community. d) Individual and Family changes : factors, which influence the daily life of the individuals and families, including attitudes, perceptions, family characteristics and friendship networks. Page 63 ESMF for IPFF 53 e) Community Resources: patterns of natural resource and land use; the availability of housing and community services. The figure below gives a matrix relating project stage to Social Impact Assessment Variables. Table 9. 2: Social Impact Assessment Variables Matrix Social Impact Assessment Variable Pre- Construction Implementation/ Construction Operation/ Maintenance Population Characteristics Population change Ethnic and racial distribution Relocated populations Influx or outflows or temporary workers Seasonal residents Community and Institutional Structures Voluntary association Interest group activity Size and structure of local government Historical experience with change Employment/income characteristics Employment equity of minority groups Local/regional/national linkages Political and Social Resources Distribution of power and authority Identifications of stakeholders Interested and affected publics Leadership capability and characteristics Individual and Family Changes Perceptions of risk, health, and safety Displacement/relocation concerns Page 64 ESMF for IPFF 54 Social Impact Assessment Variable Pre- Construction Implementation/ Construction Operation/ Maintenance Trust in political and social institutions Residential stability Community Resources Change in community infrastructure Land use patterns Effects on cultural, historical, and archaeological sites Combining Social Impact Assessment Variables, Project Stage, and Setting Social impact specialists engaged by the project sponsor will construct a matrix to that will serve as a guide for their assessing of significant social impacts. For each project stage, the assessor should identify potential impacts on each social variable identified in the matrix. This approach ensures that no critical areas are overlooked. The analytical procedures would be repeated for each of the SIA variable for each stage of the project . The procedures for accomplishing these tasks are outlined below: Steps in the Social Impact Assessment Process The process in the social assessment is described below in 10 steps. i) Public Involvement ii). Identification of Alternatives iii). Baseline Conditions iv) Scoping v). Projection of Estimated Effects-Investigate the probable impacts vi). Predicting responses to impacts vii). Indirect and Cumulative Impacts viii). Changes in Alternatives ix). Mitigation x.) Monitoring i) Public Involvement- Develop an effective public Involvement plan to involve all potentially affected publics. Requires identifying and working with all potentially affected groups starting at the very beginning of planning for the proposed action. ii). Identification of Alternatives - Describe the proposed action of policy change and reasonable alternatives. The proposed action is described in detail to begin to identify the data requirements needed from a project proponent (World Bank) to frame the SIA iii). Baseline Conditions : Describe the relevant human environment/area of influence and baseline conditions. These are the existing conditions and past trends associated with human environment in which the proposed activity is to take place. Page 65 ESMF for IPFF 55 The Base conditions would include the following set aspects of human environment: ƒ Relationship with the biophysical environment ƒ Historical background: including initial settlement and subsequent shifts in population ƒ Political and social resources ƒ Culture, attitudes and social-psychological conditions ƒ Population characteristics including the demographics of relevant groups (including all significant stakeholders and groups) iv) Scoping : Identify the full range of probable social impacts that will be addressed based on discussion or interviews with numbers of al potentially affected. After initial scoping, the social impact assessor (social impact specialist engaged by the project sponsor) selects the SIA variables for further assessment situations. Considerations need to be given to both the impacts perceived by the project sponsor/executing agency (as the case may be) and to those perceived by the affected groups and communities through consultations. The principal methodology employed here is reviews of the existing social science literature, public scoping, public surveys, and public participation techniques. It is a requirement of OP 4.12 that views of affected people are taken into consideration. Relevant criteria for selecting impacts include: ƒ Probability of the event occurring ƒ Number of people including indigenous populations that will be affected ƒ Duration of impacts (long-term vs. short-term) ƒ Value of benefits and costs to impacted groups (intensity of impacts) ƒ Extent that the impact is reversible or can be mitigated ƒ Likelihood of causing subsequent impacts ƒ Relevance to present and future policy decisions ƒ Uncertainty over possible effects ƒ Presence or absence of controversy over the issue. v). Projection of Estimated Effects-Investigate the probable impacts The probable social impacts will be formulated in terms of predicted conditions without the actions (baseline projection); predicted conditions with the actions; and predicted impacts which can be interpreted as the differences between the future with and without the proposed action. Investigation of the probable impacts involves five major sources of information: ƒ Data from project proponents ƒ Records of previous experience with similar actions as represented in reference literature as well as other SIA’s. ƒ Census and vital statistics ƒ Documents and secondary sources ƒ Field research, including informant interviews, hearing, group meetings, and surveys of the general population. The record of previous experience is very important to the estimation of future impacts. Expert knowledge of the social impact specialists is used to enlarge this knowledge base and to judge how the study case is likely to deviate from the typical patterns. vi). Predicting responses to impacts Page 66 ESMF for IPFF 56 This determines the significance of the identified social impacts. After direct impacts have been estimated the Social Impact Specialist must next estimate how the affected people will respond in terms of attitude and actions. The actions of affected groups are to be estimated using comparable cases and interviews with affected people about what they expect to do. vii). Indirect and Cumulative Impacts This estimates subsequent impacts and cumulative impacts. Indirect impacts are those caused by the direct impacts; they often occur later than the direct impacts, or further away. Cumulative impacts are those impacts which result from the incremental impacts of an action added to other past, present, and reasonably foreseeable future actions regardless of which agency or person undertakes them. viii). Changes in Alternatives Recommend new or changed alternatives and estimate or project their consequences. Each new alternative or recommended change should be assessed separately. Here more innovative alternatives and changes probably should be presented in an experimental structure. ix). Mitigation Develop a mitigation plan. A SIA should identify means to mitigate adverse impacts. These measures include avoiding the impact by not taking or modifying an action; minimizing, rectifying, or reducing the impacts through the design or operation of the project; or compensation for the impact by providing substitute facilities, resources, or opportunities x.) Monitoring Develop a monitoring plan. A monitoring program should be developed for identifying deviations from the proposed action and any important unanticipated impacts. A monitoring plan should be developed to track project and program development and compare real impacts with projected areas. A flowchart of the Steps in the Social Impact Assessment Process is provided in the next page. Page 67 E S M F f o r I P F F 5 7 F i g 9 . 2 : S t e p s i n t h e S o c i a l I m p a c t A s s e s s m e n t P r o c e s s D e v e l o p p u b l i c s c o p i n g p r o g r a m ( p u b l i c i n v o l v e m e n t I d e n t i f y p r o b a b l e i m p a c t s ( b a s e d o n s c o p i n g ) D e s c r i b e p r o p o s e d a c t i o n a n d a l t e r n a t i v e s ( i d e n t i f i c a t i o n o f a l t e r n a t i v e s D e s c r i b e r e l e v a n t h u m a n e n v i r o n m e n t a n d a r e a o f i n f l u e n c e ( b a s e l i n e c o n d i t i o n s ) D e t e r m i n e p r o b a b l e r e s p o n s e o f a f f e c t e d p u b l i c s I n v e s t i g a t e p r o b a b l e i m p a c t s ( p r o j e c t i o n o f e s t i m a t e d e f f e c t s ) R e c o m m e n d c h a n g e s i n p r o p o s e d a c t i o n o r a l t e r n a t i v e s ( c h a n g e s i n a l t e r n a t i v e s ) D e v e l o p m o n i t o r i n g p r o g r a m ( m o n i t o r i n g ) M i t i g a t i o n p l a n E s t i m a t e i n d i r e c t a n d c u m u l a t i v e i m p a c t s Page 68 58 IDENTIFICATION OF IMPACT Basic categories of issues/impacts those needed to be addressed under the entitlement framework are the following: · Loss of land · Loss of water source · Loss of structure · Loss of source of livelihood · Loss of access to common resources and facilities · Loss of standing crops, trees and perennial trees · Loss of public infrastructure · Loss of services (electricity, water, transport, etc) · Loss of or imperilled access to any of the above Table 9. 3: List of Probable Impacts during Various Phases of the Project Pre-Construction Construction Operation & Maintenance Site Surveys & Investigations · Inducement of uncertainties relating to land acquisition · Stimulation of new construction to obtain higher compensation Contractors' Camps. Employment · Employment opportunities for local population · Conflicts between the imported workers and local population · Risk of HIV/AIDS and other transmittable diseases · Inducement of traffic congestion & related road safety hazards Land & Property Acquisition · Loss of and displacement from homestead land · Loss of agricultural land and other productive assets · Loss of business/commercial land or premises · Loss of public buildings and facilities · Loss of cultural heritage/ Resources · Loss of sensitive habitats Clearance of Site · Interference with utility services · Increased employment opportunities · Increased economic activity Page 69 59 Construction Materials · Loss of and displacement from productive land · Waterborne disease risks/Safety hazard on abandonment · Visual alteration in landscape quality Construction Traffic · Damage to road pavement & structures · Increased traffic congestion & related road safety hazards. IMPACT MITIGATION Impact mitigation includes the principles, procedures and mitigation measures that are relevant and suitable to the project for ensuring the most appropriate environmental mitigation and enhancement plans applicable during different stages of project implementation. To avoid and minimize the impacts resulting from the activities of the different sub-projects, measures/management plans, which are essential to mitigate the impacts as discussed, are based upon appropriate technological design, improvements or adjustments, policy including good site operational practices etc. Environmental and social impacts of the subprojects can broadly be classified as those taking place during pre-construction, construction and operational phases. The overall strategy has the following sequence: · Impact avoidance: Changing project location, design and construction methods to avoid impacts. · Impact minimization: Where impacts cannot be avoided, implementing mitigation measures to reduce the impact to acceptable levels. · Compensation: Arranging compensation where impacts cannot be avoided or sufficiently mitigated. · Enhancement: measures, which, at insignificant cost to the project, give appreciable social or developmental benefits. The mitigation plan is adopted to highlight the action procedures to avoid/ minimize/ control the resultant impacts arising out of the different project phases i.e. pre- construction, construction and operation. LAND ACQUISITION FOR PROJECTS Land Acquisition is the action of acquiring private land by the state as per provisions of the law of the land. The earliest law on such land acquisition in the territory of present Bangladesh was the Bengal Regulation I of 1824 enacted to promote British commercial interests in salt manufacture. This law was repealed and replaced by Act I of 1850. By Act XLII of 1850, construction of railways was declared a public purpose and summary powers were assumed by the government to expedite acquisition of land as well as taking earth for construction of roads, canals, and railways. Page 70 60 Act VI of 1857 consolidated various laws on the subject. This act was made applicable to the whole of British India. But it did not provide for acquisition of land for private companies. A new law entitled Act XXII of 1863 was enacted to authorize the Governor General-in-Council to declare projects dealing with Irrigation, navigation, and improvement of docks and harbors as work of public utilities. This process of modification and consolidation continued till enactment of Act X of 1870. The Act of 1894 made the collector's award of compensation final, unless altered by a decree of the civil court in a regular suit. The object of the act was to provide a speedy method of determining the compensation to be followed for acquiring land. This was a comprehensive law, which also provided for emergency situations. To mitigate the hardships of those affected, the collector was put under legal obligation to pay compensation on the basis of provisional estimates as under: (a) 10% for structures and buildings; (b) 75% for households, overheads and orchards; and (c) 50% for vacant 'nal' lands. The Acquisition and Requisition of Immovable Property Ordinance 1982 (Ordinance 11 of 1982), now constitutes the sole instrument of land acquisition in Bangladesh (except in the 3 hill districts). This law provides for acquisition and requisition of immovable properties for a public purpose or in the public interest. Places of worship, graveyard or cremation ground, however, were exempted. Detailed procedures have been prescribed to ensure that a deputy commissioner proceeds systematically and on sound principles in such cases, leaving room for owners to raise objections which must be disposed of after due hearing. This delegation of decision-making power was dictated by the delay in the acquisition process under the previous law. Delay in acquisition of land caused delay in the implementation of development projects. Moreover, foreign financing agencies were insistent upon expeditious land acquisition. Accordingly, a time limit was fixed according to the following scheme: (a) if the quantity of land proposed to be acquired was up to 50 bighas and there was no objection - 45 days; and if objection was raised - 75 days; and (b) if the quantity was over 50 bighas and no objection was raised - 105 days; and if objection was raised - 135 days. An additional maximum time limit of 112 days was allowed for finalization of the award. Thus the maximum time of finalization of an acquisition case is now 187 days if the quantity of land is up to 50 bighas and 274 days if it is over 50 bighas. Laws, rules and procedures for land acquisition in the plain land districts of Bangladesh do not apply in the Chittagong Hill Tracts, which now comprise the three districts of Rangamati, Khagrachhari and Bandarban. Steps in Land Acquisition The following are the major steps of Bangladesh Government’s Immovable and Movable Properties / Land Acquisition (LA) after the finalization of the engineering designs: · Preparation of the land acquisition proposals (LAPs) · LAPs submitted to the Ministry for administrative approval · Administrative approval received from the Ministry Page 71 61 · LAPs submitted to the Deputy Commissioners (of respective Districts) · LAPs approved by the District Land Acquisition Committees (DLACs) · LAPs approval by the Ministry of Land · Notice-3 issued by the DCs · Notice-6 issued by the DCs · Notice-7 issued by the DCs · Compensation Budgets submitted by the DCs to project authority · Compensation Budgets forwarded to the concerned Line Ministry for approval · Compensation Budgets approved by the Ministry · Authority to place the Compensation funds with the DCs · DCs start the payment of the 'compensation under the law' (C UL) RESETTLEMENT ACTION PLAN (RAP) Land Acquisition Plan For any land acquisition a Land Acquisition Plan (LAP) is needed. Preparation of the land acquisition plans will include locating each of the components; sorting out the ownership status of the lands in which project shall be established; and preparing the schedules of plots (with ‘dag’ or Plot numbers and other information required by the acquiring body) from which lands are to acquired. These are the documents the relevant project authority will submit to DC along with a request to start the acquisition process. LAPs will be prepared for proposed site and will ensure that the total amount of land in the individual acquisition packages does not exceed 50 standard bighas, which the Divisional Commissioners can approve without referring to the Ministry of Land. Resettlement Types For acquisition of land, iIf the SIA indicates that a resettlement Action Plan (RAP) is required, then the project sponsor will engage a Social Specialist who will prepare a RAP considering all World Bank OPs. i) Short RAP : As per WB OP 4.12, where impacts on the entire displaced population are minor or fewer than 200 people are displaced, an is required. ii) Full RAP In other cases, a full RAP is to be prepared. Resettlement effects result from a wide range of project types envisaged under the IPFF. These range from small plots of land required for schools or health centers may create limited resettlement effects. Long alignments required for power lines, roads, railways, or canals may cause resettlement along a narrow right of way, or disrupt community networks, dividing roads, paths, irrigation systems, and landholdings. Most types of projects have the resettlement effects as set out in the table below: Table 9. 4: Resettlement in Different Project Types Sector Project Components Type of Resettlement Effect Power and Energy ƒ Transmission alignment ƒ Minor resettlement effects from construction of pylons. These might be Page 72 62 Sector Project Components Type of Resettlement Effect ƒ Power generation plants, transmission stations, substations, and access roads ƒ Hydroelectric power reservoirs severe if landholdings are small. Right- of-way restrictions, without land acquisition, might affect people’s land use along the transmission alignment. May require temporary land borrow during construction ƒ May cause severe localized effects, and temporary land borrow during construction. Power plants may cause resettlement effects through pollution of land, air, or water. ƒ Reservoir construction can have severe and often widespread effects, displacing whole communities from construction and inundation areas, and disrupting patterns of communication, landholdings, social and economic systems, and resource use. Temporary land borrow for construction. Transport ƒ Road or rail alignment ƒ Associated stations, terminals, bridges ƒ Airports, seaports, river ports ƒ Resettlement effects over alignment. Disruption can usually be addressed within existing community units because alignment is narrow. However, if the alignment is long, cutting across administrative boundaries, the distribution of responsibilities may be unclear and entitlements may vary between sections. Alignments might divide landholdings, local roads and paths, irrigation systems, economic and social networks, or access to resources. May require temporary land borrow for construction ƒ May cause localized resettlement effects, and necessitate temporary land borrow for construction ƒ Severe resettlement effects for communities currently occupying land are possible. Can displace whole communities, or disrupt patterns of communication, landholdings, social and economic systems and resource use. Temporary land borrow for construction Water supply and sanitation ƒ Reticulation systems ƒ Temporary land borrow. Use of existing rights-of-way (for example, roads) can minimize disruption. Narrow land corridors might be Page 73 63 Sector Project Components Type of Resettlement Effect ƒ Pumping stations, treatment sites ƒ Reservoirs for water supply acquired permanently with minor disruption. ƒ May cause more severe localized effects. Temporary land borrow for construction. ƒ Reservoir construction can have severe and often widespread effects Solid waste ƒ Transfer stations, landfill sites ƒ May cause severe localized effects Urban renewal ƒ Urban infrastructure sites ƒ May cause severe localized effects Health ƒ Sites for hospitals, clinics, teaching facilities ƒ May cause severe localized effects. Communities might be prepared to volunteer small sites for community services. Education ƒ Sites for schools, training institutions, etc ƒ May cause severe localized effects. Communities might be prepared to volunteer small sites for community services. Irrigation and Flood control ƒ Canal alignments, protective embankments, and associated works ƒ Dams ƒ Resettlement effects over a narrow alignment. ƒ Dam construction can have severe and widespread effects Mining operations ƒ Strip mining ƒ May cause severe localized effects, or resettlement effects due to severe loss of environmental quality (ex. Polluted land or water) Forestry developments ƒ Reforestation, industrial plantations, forest closure ƒ May cause loss of access to forest products for cash and subsistence. Loss of grazing rights. Displacements of communities. Parks, conservation sites ƒ National parks or biodiversity areas ƒ May cause loss of grazing rights, or disruption of grazing routes. May displace communities from park. Resettlement Action Plan (RAP) Preparation According to WB OP 4.12, the Resettlement Action Plan (RAP) for any project shall cover the following elements. a) Description of the project : General description of the project and identification of the project area b) Potential impacts: Identification of: · The project component or activities that give rise to resettlement · The zone of impact of such component or activities · The alternatives considered to avoid or minimize resettlement Page 74 64 · The mechanisms established to minimize resettlement, to the extent possible, during project implementation c) Objectives: The main objectives of the resettlement program d) Socio-economic studies: The findings of socio-economic studies to be conducted in the early stages of project preparation and with the involvement of potentially displaced people, to include: (a) The results of a census survey covering: (i) Current components of the affected area to establish a basis for the design of the resettlement program and to exclude subsequent inflows of people from eligibility for compensation and resettlement assistance (ii) Standard characteristics of displaced households, including a description of production systems, labor, and household organization; and baseline information on livelihoods (including, as relevant, production levels and income derived from both formal and informal economic activities) and standards of living (including health status) of the displaced population. Annex 9.1 is an illustration of the typical format of data collection for operation. (iii) the magnitude of the expected loss – total or partial – of assets, and the extent if displacement, physical or economic. Annex 9.2 is an illustration of the typical format of data collection for such an operation (iv) information on vulnerable groups or persons as provided for in OP 4.12, para. 8, for whom special provisions may have to be made (v) provisions to update information on the displaced people's livelihoods and standards of living at regular intervals so that the latest information is available at the time of their displacement. (b) Other studies describing the following (i) land tenure and transfer systems, including an inventory of common property natural resources from which people derive their livelihoods and sustenance, non-title-based usufruct systems (including fishing, grazing, or use of forest areas) governed by local recognized land allocation mechanisms, and any issues raised by different tenure systems in the project area; (ii) the patterns of social interaction in the affected communities, including social networks and social support systems, and how they will be affected by the project; (iii) public infrastructure and social services that will be affected; and (iv) social and cultural characteristics of displaced communities, including a description of formal and informal institutions (e.g., community organizations, ritual groups, nongovernmental organizations (NGOs)) that may be relevant to the consultation strategy and to designing and implementing the resettlement activities. e) Legal Framewor k: The findings of an analysis of the legal framework will cover the following: (a) the scope of the power of eminent domain and the nature of compensation associated with it, in terms of both the valuation methodology and the timing of payment Page 75 65 (b) the applicable legal and administrative procedures, including a description of the remedies available to displaced persons in the judicial process and the normal timeframe for such procedures, and any available alternative dispute resolution mechanisms that may be relevant to resettlement under the project; (c) relevant law (including customary and traditional law) governing land tenure, valuation of assets and losses, compensation, and natural resource usage rights; customary personal law related to displacement; and environmental laws and social welfare legislation; (d) laws and regulations relating to the agencies responsible for implementing resettlement activities; (e) gaps, if any, between local laws covering eminent domain and resettlement and the Bank's resettlement policy, and the mechanisms to bridge such gaps; and (f) any legal steps necessary to ensure the effective implementation of resettlement activities under the project, including, as appropriate, a process for recognizing claims to legal rights to land--including claims that derive from customary law and traditional usage (see OP 4.12, para.15 b). f) Institutional Framework . The findings of an analysis of the institutional framework will cover: (a) the identification of agencies responsible for resettlement activities and NGOs that may have a role in project implementation; (b) an assessment of the institutional capacity of such agencies and NGOs; (c) any steps that are proposed to enhance the institutional capacity of agencies and NGOs responsible for resettlement implementation. g) Eligibility. The definition of displaced persons and criteria for determining their eligibility for compensation and other resettlement assistance, including relevant cut-off dates. h) Valuation of and compensation for losses The methodology to be used in valuing losses to determine their replacement cost ; and a description of the proposed types and levels of compensation under local law and such supplementary measures as are necessary to achieve replacement cost for lost assets. i) Resettlement measures . A description of the packages of compensation and other resettlement measures that will assist each category of eligible displaced persons to achieve the objectives of the policy (see OP 4.12, para. 6). In addition to being technically and economically feasible, the resettlement packages should be compatible with the cultural preferences of the displaced persons, and prepared in consultation with them. j) Site selection, site preparation, and relocation. Alternative relocation sites considered and explanation of those selected, covering Page 76 66 (a) institutional and technical arrangements for identifying and preparing relocation sites, whether rural or urban, for which a combination of productive potential, locational advantages, and other factors is at least comparable to the advantages of the old sites, with an estimate of the time needed to acquire and transfer land and ancillary resources; (b) any measures necessary to prevent land speculation or influx of ineligible persons at the selected sites; (c) procedures for physical relocation under the project, including timetables for site preparation and transfer; and (d) legal arrangements for regularizing tenure and transferring titles to resettlers. k) Housing, infrastructure, and social services. Plans to provide (or to finance resettlers' provision of) housing, infrastructure (e.g., water supply, feeder roads), and social services (e.g., schools, health services); plans to ensure comparable services to host populations; any necessary site development, engineering, and architectural designs for these facilities. m) Environmental protection and management . A description of the boundaries of the relocation area; and an assessment of the environmental impacts of the proposed resettlement and measures to mitigate and manage these impacts (coordinated as appropriate with the environmental assessment of the main investment requiring the resettlement). n) Community participation. Involvement of resettlers and host communities This includes the following components: (a) A description of the strategy for consultation with and participation of resettlers and hosts in the design and implementation of the resettlement activities; (b) a summary of the views expressed and how these views were taken into account in preparing the resettlement plan; (c) a review of the resettlement alternatives presented and the choices made by displaced persons regarding options available to them, including choices related to forms of compensation and resettlement assistance, to relocating as individuals families or as parts of preexisting communities or kinship groups, to sustaining existing patterns of group organization, and to retaining access to cultural property (e.g. places of worship, pilgrimage centers, cemeteries) d Page 77 67 (d) institutionalized arrangements by which displaced people can communicate their concerns to project authorities throughout planning and implementation, and measures to ensure that such vulnerable groups as indigenous people, ethnic minorities, the landless, and women are adequately represented. o) Integration with host populations. Measures to mitigate the impact of resettlement on any host communities, including (a) consultations with host communities and local governments; (b) arrangements for prompt tendering of any payment due the hosts for land or other assets provided to resettlers; (c) arrangements for addressing any conflict that may arise between resettlers and host communities; and (d) any measures necessary to augment services (e.g., education, water, health, and production services) in host communities to make them at least comparable to services available to resettlers. p) Grievance procedures . Affordable and accessible procedures for third-party settlement of disputes arising from resettlement; such grievance mechanisms should take into account the availability of judicial recourse and community and traditional dispute settlement mechanisms. q) Organizational responsibilities . The organizational framework for implementing resettlement, including identification of agencies responsible for delivery of resettlement measures and provision of services; arrangements to ensure appropriate coordination between agencies and jurisdictions involved in implementation; and any measures (including technical assistance) needed to strengthen the implementing agencies' capacity to design and carry out resettlement activities; provisions for the transfer to local authorities or resettlers themselves of responsibility for managing facilities and services provided under the project and for transferring other such responsibilities from the resettlement implementing agencies, when appropriate. r) Implementation schedule . An implementation schedule covering all resettlement activities from preparation through implementation, including target dates for the achievement of expected benefits to resettlers and hosts and terminating the various forms of assistance. The schedule should indicate how the resettlement activities are linked to the implementation of the overall project. s) Costs and budget. Page 78 68 Tables showing itemized cost estimates for all resettlement activities, including allowances for inflation, population growth, and other contingencies; timetables for expenditures; sources of funds; and arrangements for timely flow of funds, and funding for resettlement, if any, in areas outside the jurisdiction of the implementing agencies. t) Monitoring and evaluation. Arrangements for monitoring of resettlement activities by the implementing agency, supplemented by independent monitors as considered appropriate by the Bank, to ensure complete and objective information; performance monitoring indicators to measure inputs, outputs, and outcomes for resettlement activities; involvement of the displaced persons in the monitoring process; evaluation of the impact of resettlement for a reasonable period after all resettlement and related development activities have been completed; using the results of resettlement monitoring to guide subsequent implementation. Abbreviated Resettlement Plan Where the impacts on the entire displaced population are minor, or fewer than 200 people are displaced, an abbreviated resettlement plan may be agreed with the project sponsor. This is in line with OP 4.12 para. 25. Information disclosure procedures set forth in para. 22 are applicable. An abbreviated plan covers the following minimum elements: (a) a census survey of displaced persons and valuation of assets; (b) description of compensation and other resettlement assistance to be provided (c) consultations with displaced people about acceptable alternatives; (d) institutional responsibility for implementation and procedures for grievance redress (e) arrangements for monitoring and implementation (f) a timetable and budget. INDIGENOUS PEOPLES DEVELOPMENT PLAN (IPDP) If the SIA indicates the need for an Indigenous Peoples Development Plan IPDP, then an IPDP is will be prepared by the project sponsor through social experts. The level of detail will vary depending on the nature of the sub-project and the nature of the effects to be addressed. The IPDP will include the following elements, as mentioned in the WB OP 4.10. (a) a summary of the information referred to in the OP. (b) A summary of the social assessment. (c) A summary of results of the free, prior, and informed consultation with the affected Indige nous Peoples’ communities that was carried out during project preparation (Annex A) and that led to broad community support for the project. Page 79 69 (d) A framework for ensuring free, prior, and informed consultation with the affected Indigenous Peoples’ communities during project implementation (see paragraph 10 of this policy). (e) An action plan of measures to ensure that the Indigenous Peoples receive social and economic benefits that are culturally appropriate, including, if necessary, measures to enhance the capacity of the project implementing agencies. (f) When potential adverse effects on Indigenous Peoples are identified, an appropriate action plan of measures to avoid, minimize, mitigate, or compensate for these adverse effects. (g) The cost estimates and financing plan for the IPP. (h) Accessible procedures appropriate to the project to address grievances by the affected Indigenous Peoples’ communities arising from project implementation. When designing the grievance procedures, the borrower takes into account the availability of judicial recourse and customary dispute settlement mechanisms among the Indigenous Peoples. (i) Mechanisms and benchmarks appropriate to the project for monitoring, evaluating, and reporting on the implementation of the IPP. The monitoring and evaluation mechanisms should include arrangements for the free, prior, and informed consultation with the affected Indigenous Peoples’ communities. GRIEVANCE REDRESS MECHANISM Despite best efforts to arrive at fair rewards in project involving involuntary resettlement, there will always be a few unsatisfied citizens. The relevant authority will make efforts at project level to resolve grievances through negotiations involving community leaders and PAP’s representatives. Grievance Resolution Committee: In case the dispute is not resolved at local level, the matter through submission of a relevant formal reference would be placed before a Grievance Resolution Committee. Grievance Resolution Committee (GRC) shall be constituted consisting of a panel of five (5) Members, one of whom shall be community relation officer, to be appointed by the concerned authority. Other members would include two (2) representatives from the PAPs community of the project area, those who are would publicly known to be persons of integrity, good judgment and command respect. Page 80 70 PART-D OPERATIONAL MANUAL OPERATIONAL MANUAL SEQUENCE OF TASKS OF THE ESMF IN DIFFERENT PHASES OF IPFF PROJECT The ESMF tasks have been grouped in five phases, as mentioned below. The activities, by a project sponsor, in different phases are described in detail in the subsequent sections. The phases are: i). Pre-Construction Phase ii). Land Acquisition Phase iii). Financing Phase iv). Construction Phase v). Post-Construction Operation Phase i). PRE-CONSTRUCTION PHASE 1. Environmental and Social Screening, report on Impact Identification and project alternatives (prepared by the sponsor) 2. Initial Environmental Examination IEE, (with TOR for EIA) Site Clearance Certificate (SCC) obtained for minor civil works. 3. Social Impact Assessment (SIA), after base line data collection, will include: o Social Management Plan (SMP), with Mitigation measures o Rehabilitation Plan (RP) 4. Environmental Impact Assessment EIA, will include: o Environmental Management Plan EMP Environmental Clearance Certificate (ECC) obtained and Project Construction may start, subject to availability of fund. ii). LAND ACQUISITION PHASE Case i) LAND PURCHASE BY SPONSOR (THROUGH NEGOTIATION) 1. Land is purchased directly by the Sponsor, through negotiation with the landowners. The usual policy is to pay the market price or the replacement value of the land and the structures. A ‘Land Acquisition Specialist’ engaged by the project sponsor (or requiring body, RB) and its representative works jointly, in collaboration with a Legal Advisor. No RAP is required in such cases and development may start immediately. Case ii) LAND ACQUISITION BY GOB (WITH GOB OR SPONSOR FUND) 1. Land Acquisition Plan (LAP), prepared by requiring body, RB. Includes: o Land plot schedule of the project foot-print area, along with Mouza maps Page 81 71 o Entitlement list and Compensation package prepared by joint verification survey, by representatives of RB and DC’s office 2. Estimated land compensation money deposited by RB and Compensation payment made by DC to the affected persons. Land acquired and handed over to RB and development starts Case iii) LAND ACQUISITION BY GOB (FOR AVAILING WORLD BANK FINANCES) 1. Disclosure (of Project information) and Consultations (with potential affected persons), by project sponsor and/or engaged consultants. 2. Socio-Economic (sample) Survey, PRA and FGD in Project and Surrounding Area, the methodology depending on pattern of livelihood and other parameters. 3. Resettlement Action Plan (RAP) preparation, after Socio-economic (census) Survey in the Project footprint area. The RAP will include: o Project Affected People (PAP) list o Compensation policy o Compensation Matrix and Entitlement Plan o Relocation Plan (RP), if any o Indigenous People Development Plan, IPDP (if required) [For projects not requiring specific resettlement and LA studies, a ‘Social Performance Framework’ will be sufficient] 4. Engagement of RAP Implementation Agency (Consulting Company or NGO) 5. Disclosure of RAP information and Consultations with PAP 6. Grievances and Redress Mechanism management 7. RAP approved by WB 8. Compensation Payment to PAP o Compensation as per GoB policy by DC o Additional Entitlement to PAP, by the project iii). FINANCING PHASE Loan Application is submitted to IPFF, by the private sector sponsor, at the stage when the project is awarded by the public sector and agreement signed between them. By the time most of the studies have been completed and the land is acquired. 1. Review of and due diligence on already completed EIA and SIA Reports. Assess if all issues have been adequately addressed. Decide if further alternatives are to be examined. iv). CONSTRUCTION PHASE 1. Implementation of Environmental Management Plan (EMP) and its monitoring 2. Monitoring of Management Plan (SMP), which includes RAP, Relocation, Livelihood restoration, Training activities, etc.) v). POST-CONSTRUCTION OPERATION PHASE 1. Environmental and Social Audit, as per recommendation of EIA and SIA. 2. Regular monitoring of environmental issues as per EMP, and keep records. Page 82 72 Pre-Construction Phase Activities After identification of an infrastructure project in PPP, the project sponsor will carry out the Environmental and Social screening of the project. After screening, sponsor will apply for site clearance certificate for stating the project at site. a) Procedure For Issuing Site Clearance Certificate For obtaining the SCC, the following two documents need to be submitted to the DOE; 1. an Initial Environmental Examination (IEE) Report and 2. a TOR for detailed Environmental Impact Assessment (EIA) with a process flow diagram. b) The Content of Initial Environmental Examination (IEE) Report IEE is an important tool which should be carried out as early as the project planning stage as part of feasibility thus it can assure that the project will be environmentally feasible. The contents of an IEE report are stated below; A Introduction B Description of the Project C Description of the Environment D Screening of Potential Environmental Impacts and Mitigation Measures E Institutional Requirements and Environmental Monitoring Plan F Public Consultation and Information Disclosure G Findings and Recommendation H Conclusions The detail of the contents is stated below. A Introduction This section usually includes the following: · Purpose of the report, including (a) identification of the project and project proponent; (b) brief description of the nature, size, and location of the project and of its importance to the country; and (c) any other pertinent background information; and · Extent of the IEE study: scope of study, magnitude of effort, person or agency performing the study, and acknowledgement. B Description of the Project Furnish sufficient details to give a brief but clear picture of the following (include only applicable items): · type of project; · category of Project; · need for project; · location (use maps showing general location, specific location, and project site); · size or magnitude of operation; · proposed schedule for implementation; and · descriptions of the project, including drawings showing project layout, and project components. This information should be of the same type and extent as is included in feasibility reports for proposed projects to give a clear picture of the project and its operations. C Description of the Environment Page 83 73 Furnish sufficient information to give a brief but clear picture of the existing environmental resources in the area affected by the project, including the following (to the extent applicable): (a) Physical Resources : (e.g.) · atmosphere (e.g. air quality and climate) · topography and soils, · surface water · groundwater · geology/ seismology. (b) Ecological Resources: (e.g.) · fisheries · aquatic biology · wildlife · forests · rare or endangered species · protected areas · coastal resources (c) Economic Development: (e.g.) · industries · infrastructure facilities (e.g. water supply, sewerage, flood control) · transportation (roads, harbors, airports, and navigation) · land use (e.g. dedicated area uses) · power sources and transmission · agricultural development, mineral development, and tourism facilities (d) Social and Cultural Resources: (e.g.) · population and communities (e.g. numbers, locations, composition, employment · health facilities · education facilities · socio-economic conditions (e.g. community structure, family structure, social well being) · physical or cultural heritage · current use of lands and resources for traditional purposes by Indigenous Peoples · structures or sites that are of historical, archaeological, pale ontological, or architectural significance. D Screening of Potential Environmental Impacts and Mitigation Measures Using the checklist of environmental parameters for projects, this section will screen out “no significant impacts” from those with significant adverse impact by reviewing each relevant parameter according to the following factors or operational stages. Mitigation measures, where appropriate, will also be recommended environmental problems due to project location, and related to project design, construction, and operations. Potential environmental enhancement measures and additional considerations will also be covered. E Institutional Requirements and Environmental Monitoring Plan This section should state the impacts to be mitigated, and activities to implement the mitigation measures, including how, when, and where they will be implemented. Institutional arrangements for implementation should be described. The environmental Page 84 74 monitoring plan will describe the impacts to be monitored, and when and where monitoring activities will be carried out, and who will carry them out. The environmental management and monitoring costs should also be described. F Public Consultation and Information Disclosure This section will describe the process undertaken to involve the public in project design and recommended measures for continuing public participation; summarize major comments received from beneficiaries, local officials, community leaders, NGOs, and others, and describe how these comments were addressed; list milestones in public involvement such as dates, attendance, and topics of public meetings; list recipients of this document and other project related documents; describe compliance with relevant regulatory requirements for public participation; and summarize other related materials or activities, such as press releases and notifications. This section will provide of summary of information disclosed to date and procedures for future disclosure. G Findings and Recommendations This section will include an evaluation of the screening process and recommendation will be provided whether significant environmental impacts need further detailed study or EIA. If there is no need for further study, the IEE itself, which at times may need to be supplemented by a special study in view of limited but significant impacts, becomes the completed environmental assessment for the project and no follow-up EIA will be needed. If an EIA is needed, then this section will include a brief terms of reference (TOR) for the needed follow-up EIA, including approximate descriptions of work tasks, professional skills required, time required, and estimated costs. The Bank's Environment Guidelines provides a guide for preparing the TOR for different projects. H Conclusions This section will discuss the result of the IEE and justification, if any, of the need for additional study or EIA. If an IEE, or an IEE supplemented by a special study, is sufficient for the project, then the IEE with the recommended institutional and monitoring program becomes the completed EIA. Criteria For Site Clearance Of Projects/Industries For establishing industrial plant, following criteria have been proposed to consider in the Industrial Guidelines prepared by DOE; (a) The location of an industry should be in the area, which is designated or likely to be designated as an industrial zone under the town and country planning regulations. (b) The sites for industries of the Orange and Red categories should be away from the following features by the minimum distance shown against them. 1. Environmentally or other sensitive areas 10 km (may extend sitting 25 km) 2. High tide line in coastal areas, or natural or modified flood plain boundary 0.5 km 3. Boundary of the nearest human settlement 1.5 to 10 km (depending upon the size of settlement) 4. Highway/ Railway boundary 0.5 km (c) No “forest land” or prime agricultural land shall be used as industrial sites. (d) The industrial premises should be adequately large to provide for; Page 85 75 (i) Storage of solid wastes; (ii) Treatment of waste water; (iii) Reuse of treated waste water, if feasible; and (iv) Green belt of 15 to 100 meter width around the site perimeter, depending upon the size and pollution potential of the industry. (e) Industrial plants with high potential for pollution should not be located in or near; (v) Catchments areas of public water supply reservoir; (vi) Recharge area of aquifer of present or possible water supply use; (vii) Areas known to suffer from frequent inversions; (viii) A habit of endangered species; (ix) Areas prone to flooding or earthquake. Other factors, which need to be taken into consideration from the point of view of potential impacts include, (a) Assimilative capacity of receiving body of water; (b) Effect on availability of existing infrastructure facilities to the local population like water supply, housing, power; (c) Likely induced growth around the industrial site; and (d) Views of the local people likely to be affected. Procedure for Issuing Environmental Clearance Certificate After receiving the SCC, the sponsors need to proceed for ECC. The EIA has to be submitted to DoE for clearance. The EIA will include the following documents; · No objection certificate from local authority · Outline of the plan for relocation and rehabilitation (if applicable · Feasibility report · Environmental Management Plan (including process flow diagram, layout plan, effluent treatment plant and its effectiveness) · Emergency Plan relating to adverse environmental impact and plan for mitigation of the effects of pollution · Detail Plan for addressing the DoE approved ToR Issuance of Environmental Clearance Certificate by DOE for the industrial units and projects depends on their site and impact on the environment. The procedures for each category are described in detail in ECA 1995. After ECC is obtained, project construction may start, subject to availability of fund. Table 10. 1Validity Period of Environmental Clearance Certificate Categories of Project Validity Renewal Period Green 1 year Orange A & B 1 year Red 3 year 30 days before expiry of the validity period Page 86 76 Land Acquisition Phase The land procurement for the project may happen in three different ways; 1. Land purchase by the sponsor through negotiation 2. Land acquisition by GoB, with GoB or sponsor fund 3. Land acquisition by GoB for availing World Bank finances In case 1, no RAP will be required as the purchase is done from willing seller, by directly paying the cost of land and structures. In case 2, the land acquisition will be done by the concerned Deputy Commissioner following the law of the land. In case 3, the land acquisition process must be in conformity with World Bank safeguard policies, as WB fund will be utilized for land acquisition or development of the project. All these have been described in relevant chapter of this framework. Financing Phase Loan Application is received by IPFF from the private sector sponsor, at the stage when the project is awarded by the public sector and agreement signed between them. At this stage, most of the studies have been completed and the land is acquired. The IPFF project will review already completed EIA and SIA Reports. IPFF project will assess if all issues have been adequately addressed and decide if further alternatives are to be examined. A checklist for due diligence by IPFF is given in Annexure 10.4. Construction Phase During the construction phase, IPFF project will monitor the implementation of Environmental Management Plan (EMP) and Social Management Plan (SMP).This will include monitoring of RAP, Relocation, Livelihood restoration, Training activities, etc. Post-Construction Operation Phase In the operation phase IPFF project will not have much activity with regards to ESMF. However, an Environmental and Social Audit is recommended as per EIA and SIA. INSTITUTIONAL FRAMEWORK FOR ESMF IMPLEMENTATION Environment and Social Cell (ESC) of IPFF To coordinate the environmental and social assessment processes and to ensure the effective implementation of the Environmental and Social Management Plan, the fund manager (the IPFF project) will establish an Environment and Social Cell (IPFF ESC). IPFF may also hire a consulting company for the purpose, who will work on behalf of the IPFF project. Page 87 77 This ESC (or the hired company) should have an ‘E & S Manager’ from the fund manager’s senior management who will assume responsibility for overseeing all environmental and social matters, ensure resources are made available for the E&S management. The E & S Manager may be supported by an Environment Coordinator (EC) and Social Coordinator (SC) who should be technically qualified, to implement and supervision activities. The E&S Manager and his Coordinators should ensure the investment teams and legal counsels are all trained on the E&S policy and procedures and can call for meetings to discuss any policy or project related issues. The fund manager should build and maintain a roaster of qualified E&S consultants who can be called upon to assist for E&S reviews. It is strongly recommended that E&S responsibilities and outcomes be included in fund employees’ performance measurement system. The Project Management Unit (PMU) in Sub-project Each sub-project will establish a Project Management Unit (PMU). Implementation of the ESMF will be the responsibility of this PMU and its monitoring would be the responsibility of the ESC of IPFF. Key responsibilities of PMU will include the following: · Procurement of works, goods and services as per Annual Plan Operation (APO) following World Bank and GOB rules. · To monitor and prepare reports on physical and financial progress of implementation · To maintain financial accounts · To conduct technical, financial and procurement audit. · To ensure implementation of Environmental and Social Management Plan (ESMP) as set out in the Environmental Assessment (EA). · To expedite the Land Acquisition process and provide compensation to the Project Affected Persons (PAPs) and implementation of Resettlement Action Plan (RAP) · To liaise with the ministries / planning commissions and other institutions / agencies / ministries etc., if required. · To make timely and efficient disbursements to all the parties working on the project. · To prepare Implementation Completion Report (ICR) and Operational Plan (OP). Project Environmental and Social Cell (PESC) under sub-project Each PMU will also establish a Project Environmental and Social Cell (PESC) The Functions of PESC will be: · Ensure implementation of the ESMP throughout the project implementation period, · Ensure integration of the ESA & resulting ESMP into the sub-project design and implementation plans (contract documents) · Monitor implementation of the mitigation measures by the Contractors, Page 88 78 · Assist the Engineers at site by providing appropriate environmental and social advice, and developing appropriate environmental and social mitigation measures for the sub-projects · Assist PMU to carry out participatory consultation during planning, design and implementation of the sub-projects · Prepare regular periodic progress reports on the implementation of the ESMP throughout the project implementation period. Resettlement Unit (RU) under PESC Every Project Environment and Social Cell (PESC) shall set up a Resettlement Unit (RU) to organize, manage and coordinate works related to preparation and implementation of the Resettlement Plan. It should be mentioned that this RU shall be formed only for implementation of the resettlement plan. The RU will be responsible for coordination, management and day to day monitoring of the resettlement work and all works related to RAP and to determine entitlement package for each affected person. ESMF IMPLEMENTATION BUDGET In view of the environmental and social management measures suggested above to be implemented, necessary budgetary provisions should be made for different components of individual projects. Tentative budget for each of the projects should include the environmental management costs other than the good engineering practices, cost of environmental and resettlement monitoring. It is assumed that each of the sub-projects involving civil works will involve environmental and resettlement costs. These costs do not involve administration costs of environment and social staff at PMU. A sample table for details of costs is provided in table below. Table 10. 1: ESMF Implementation Budget (sample) Project Name: _____________________________________________ Components, with Sub-Component Env. Monitor- ing R&R Monitor- ing Env. Manage- ment. RAP Budget Training/ Capacity Building Budget Total Cost MONITORING OF ESMF The objectives of ESMF monitoring are · To provide timely information about the success or otherwise of the Environmental and Social Management process outlined in the ESMF in such a manner that Page 89 79 changes can be made as required to ensure continuous improvement to the process; and · To evaluate the performance of the ESMF by determining whether the mitigation measures designed in the project have been successful in such a way that the pre- program environmental condition has been restored, improved upon or worse than before and to determine what further mitigation measures may be required. It is suggested that environmental monitoring studies should be conducted separately because different activities during construction and operation period of the Project will result in different possible environmental impacts. Monitoring plan of the project is presented in construction and operation phases, respectively. Construction Phase Monitoring Monitoring every environmental and social parameter continuously is not practical and necessary. Environmental and social monitoring functions according to the characteristics of existing environmental and social conditions and identifies unacceptable changes during construction period. In this context, monitoring plan is designed to commit that “project activities have no permanent negative effect on environmental resources”. For construction period, different components of Environment and social issues relevant to the project will be monitored and the results will be compared to legal limiting values. Operational Phase Monitoring In the operational phase of the project, fewer environmental and social impacts are expected than construction period. In addition, it is also recommended to carry out social survey prior to the operational phases in order to determine the needs of the local society and to develop social responsibility projects. Furthermore, in the operational phase of the project, there should be a routine social monitoring to follow up the development of the social responsibility projects and to record and resolve any complaint about the operations of project. Monitoring Plan Table 10.2: Monitoring Plan of ESMF Phase What is to be monitored Where is the parameter be Monitored How is the parameter to be monitored When is the parameter to be monitored frequency of measurement Monitor ing cost Responsibility Construction Operation Page 90 80 ESMF AUDITING FRAMEWORK Audit is the process to review the effectiveness of environmental and social management. Its objectives are to: · Determine whether a project complies with all regulatory and environmental and social performance standards or other management requirements for their operations. · Ensure conformity with environmental and social assessment requirements, and test the accuracy of the assessment. It entails a systematic, documented and periodic review of project implementation. Therefore, its results could be very useful to improve project management performance. The principal focus of the audit will be to assess the extent to which the ESMP has led to the implementation of the environmental codes of practices, appropriate mitigation measures in accordance with the ESMPs/ Specifications in the sub-projects. PERIODIC REPORTING ON ESMF The ESMF is not a static document. It may be improved with passage of time, based on experience gathered in execution of different sub-projects. The Fund Manager should require its environmental manager/ environmental coordinator along with the investment transaction leader/officer to prepare periodic reports on ESMF. The Fund Manager should also provide proper and periodic ESMFS reports to its investors and other stakeholders. These internal and external reports can also form the basis of the reports which the fund manager is required to prepare annually and periodically to World Bank. Internally and in addition to the annual external investor/stakeholder report, the fund manager should use all these opportunities to review and adjust its E&S policies and procedures and identify areas for improving their implementation Page 91 81