Procurement Plan General 1. Bank’s approval Date of the procurement Plan January 28, 2017 2. Date of General Procurement Notice: February 21, 2013 3. Period covered by this procurement plan: January to December, 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: No. Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 2,000,000 All 2. NCB (Goods) Above US$ 2,000,000 All 3. ICB (Works) Above US$ 10,000,000 All 4. NCB (Works) Not Applicable All 5. (Non-Consultant Services) Above US$ 2,000,000 All 2. Prequalification. Bidders when applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P114264 04/01/2013 issued by GCAP 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Estimated Domestic Review Ref. Description Cost Packages Preference by Bank Comments No. US$ million (yes/no) (Prior / Post) Summary of the ICB 1 (Goods) None None None None Summary of the NCB 2 (Goods) 0.615 7 No Post Summary of the ICB 3 (Non-Consultant None None None None Services) July 9, 2010 Summary of the NCB 4 (Non-Consultant 0.569 9 None Post Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 1,000,000 2. Single Source (Firms) All 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Assignment Estimated Review No. Cost Packages by Bank Comments US$ million (Prior / Post) Summary of number of 1 contracts that will be let 8.350 5 Prior under QCBS Summary of number of 2 contracts that will be let 1.5 15 Prior under other methods July 9, 2010 PROCUREMENT Ghana : Ghana Commercial Agriculture PLAN General Information Country: Ghana Bank’s Approval Date of the Original Procurement Plan: 2017-11-28 2020-06-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P114264 GPN Date: Project Name: Ghana Commercial Agriculture Loan / Credit No: IDA / 50770 Executing Agency(ies): Ministry of Food and Agriculture-GCAP WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 5: Investments GH-GCAP-37239-CW-RFB / in Physical Rehabilitation Rehabilitation and and Modernization of Open - Single Stage - One 32,012,453.1 IDA / 50770 Prior Request for Bids 30,000,000.00 Signed 2017-11-21 2017-11-30 2017-11-26 2017-12-04 2018-01-07 2017-10-18 2018-02-06 2018-01-04 2018-03-13 2018-02-07 2019-09-04 Completion of Kpong Left Selected Existing Public International Envelope 8 Bank Irrigation Project Irrigation and Drainage Infrastructure Component 5: Investments GH-GCAP-45400-CW-RFB / in Physical Rehabilitation Rehabilitation and and Modernization of Open - Single Stage - One 28,812,845.0 IDA / 50770 Prior Request for Bids 25,000,000.00 Signed 2018-01-30 2018-03-13 2018-02-04 2018-03-16 2018-03-18 2018-05-11 2018-04-17 2018-07-10 2018-05-22 2018-09-06 2019-11-23 Modernization of Tono Selected Existing Public International Envelope 0 Irrigation Scheme Irrigation and Drainage Infrastructure Component 5: Investments GH-GCAP-45730-CW-RFB / in Physical Rehabilitation Rehabilitation and and Modernization of Open - Single Stage - One 40,274,293.5 IDA / 50770 Prior Request for Bids 30,000,000.00 Signed 2018-02-12 2018-07-10 2018-02-17 2018-07-30 2018-03-31 2018-09-17 2018-04-30 2019-01-25 2018-06-04 2019-04-30 2019-12-06 Modernisation of Kpong Selected Existing Public International Envelope 0 Irrigation Scheme Irrigation and Drainage Infrastructure. Component 6: Support for GH-GCAP-45913-CW-RFB / the Restructuring and Rehabilitation ICOUR Main Single Stage - One IDA / 50770 Strengthening of Public Post Request for Bids Open - National 170,000.00 147,090.65 Signed 2018-02-16 2018-11-21 2018-02-21 2018-04-04 2018-12-17 2018-05-04 2018-12-17 2018-06-08 2019-04-12 2018-12-05 Office (Block A & C) at Envelope Irrigation and Drainage Tono Institutions Component 6: Support for GH-GCAP-46877-CW-RFB / the Restructuring and Single Stage - One Rehabilitation of ICOUR IDA / 50770 Strengthening of Public Post Request for Bids Open - National 85,000.00 77,513.02 Signed 2018-02-16 2018-12-10 2018-02-21 2018-04-04 2018-12-17 2018-05-04 2018-12-17 2018-06-08 2019-04-12 2018-12-05 Envelope Office at Vea Irrigation and Drainage Institutions Component 5: Investments GH-GCAP-37258-CW-RFB / in Physical Rehabilitation Rehabilitation and and Modernization of Open - Single Stage - One IDA / 50770 Prior Request for Bids 20,000,000.00 0.00 Canceled 2017-11-30 2018-01-16 2017-12-05 2018-01-16 2018-02-15 2018-03-22 2019-09-13 Modernization of Vea Selected Existing Public International Envelope Irrigation Scheme Irrigation and Drainage Infrastructure Component 6: Support for GH-GCAP-45908-CW-RFB / the Restructuring and Rehabilitation of GIDA Single Stage - One IDA / 50770 Strengthening of Public Post Request for Bids Open - National 400,000.00 0.00 Canceled 2018-04-17 2018-04-22 2018-06-03 2018-07-03 2018-08-07 2019-02-03 Zonal Offices at Tamale (Lot Envelope Irrigation and Drainage 1) Institutions Component 5: Investments GH-GCAP-96201-CW-RFB / in Physical Rehabilitation Construction of Temporary and Modernization of Single Stage - Two GIDA Head Office with Pre- IDA / 50770 Post Request for Bids Open - National 600,000.00 1,123,344.25 Signed 2019-01-30 2019-01-29 2019-02-04 2019-03-18 2019-02-28 2019-05-31 2019-03-11 2019-07-05 2019-07-17 2020-01-01 Selected Existing Public Envelope fabricated Materials and Irrigation and Drainage Furnishing Infrastructure Page 1 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-GCAP-96214-GO-RFQ / Production of 1000 Component 4: Project pesticides/agrochemical user Request for Single Stage - One IDA / 50770 management and monitoring Post Limited 20,000.00 9,762.40 Signed 2019-04-28 2019-04-10 2019-06-23 2019-05-21 2019-12-20 guide/manuals and TOT Quotations Envelope and evaluation Materials , IEC materials on out-grower management GH-GCAP-46073-GO-RFQ / Procurement of Office Equipment 12 No. Laptop Component 4: Project Computers and Accessories, Request for Single Stage - One IDA / 50770 management and monitoring Post Limited 60,000.00 0.00 Canceled 2018-03-08 2018-05-03 2018-10-30 2. No. Scanners and Quotations Envelope and evaluation printers, 2 No. Photocopiers and Softwares)for ICOUR & MED Component 5: Investments GH-GCAP-96211-GO-RFQ / in Physical Rehabilitation Supply of 2No. 4X4 Double Pending and Modernization of Request for Single Stage - One Cabin Pickup and 1No. mini IDA / 50770 Post Limited 120,000.00 0.00 Implementati 2019-06-03 2019-07-24 2019-09-17 Selected Existing Public Quotations Envelope Station wagon Vehicles for on Irrigation and Drainage ICOUR Infrastructure. Component 5: Investments GH-GCAP-96227-GO-RFQ / in Physical Rehabilitation Supply of Office Equipment Pending and Modernization of Request for Single Stage - One & furniture for the IDA / 50770 Post Limited 40,000.00 0.00 Implementati 2020-03-02 2020-04-27 2020-05-15 Selected Existing Public Quotations Envelope rehabilitated ICOUR Offices on Irrigation and Drainage in Tono & VEA Infrastructure. Component 5: Investments GH-GCAP-96207-GO-RFQ / in Physical Rehabilitation Pending Procurement of ArcGIS and and Modernization of Request for Single Stage - One IDA / 50770 Post Limited 45,000.00 0.00 Implementati 2020-03-31 2020-05-26 2020-07-25 EPANENT Software for Selected Existing Public Quotations Envelope on GIDA Irrigation and Drainage Infrastructure. GH-GCAP-96222-GO-RFQ / Print info-pack to attract Component 6: Support for investors to Nasia Nabogo the Restructuring and Pending PPP sites, Kpong Irrigation Request for Single Stage - One IDA / 50770 Strengthening of Public Post Limited 20,000.00 0.00 Implementati 2020-04-28 2020-06-23 2020-08-22 Scheme (KIS), Kpong Left Quotations Envelope Irrigation and Drainage on Bank Irrigation Project Institutions (KLBIP) and Tono Irrigation scheme Component 6: Support for GH-GCAP-46074-GO-RFQ / the Restructuring and Pending Supply and Installation of Request for Single Stage - One IDA / 50770 Strengthening of Public Post Limited 90,000.00 0.00 Implementati 2019-12-30 2020-04-30 2020-10-27 GIDA Drawing Office Quotations Envelope Irrigation and Drainage on Software and Digital Library Institutions GH-GCAP-96198-GO-RFQ / Procurement of Equipment Component 2: Securing Pending for GIDA Drawing Office Request for Single Stage - One IDA / 50770 PPPs and small-holder Post Limited 49,000.00 0.00 Implementati 2020-04-20 2020-06-15 2020-07-15 and 4no. Desktop computers, Quotations Envelope linkages in the Accra Plains on 3no. Laptop computers and 1no. Printers for MED) NON CONSULTING SERVICES Page 2 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-GCAP-45755-NC-RFQ / Produce IEC materials with Component 1: strengthening extracts from the Model investment promotion Request for Single Stage - One Lease Agreement - for IDA / 50770 infrastructure, facilitating Post Limited 50,000.00 0.00 Canceled 2018-04-13 2018-06-08 2018-12-05 Quotations Envelope community education secure access to land and activities & IEC materials project management. on agronomic practices GH-GCAP-46067-NC-RFQ / Print (100 copies each) all other completed GCAP investment related Component 3: securing PPPs information - National Request for Single Stage - One IDA / 50770 and small-holder linkages in Post Limited 50,000.00 0.00 Canceled 2018-03-05 2018-04-30 2018-10-27 Framework on Out-grower Quotations Envelope the SADA zone arrangements, PFAR on warehouses and Produce manuals, IEC materials on out-grower management GH-GCAP-46068-NC-RFQ / Component 1: strengthening Print Agric Investment investment promotion Request for Single Stage - One Guide & Brief (200 copies IDA / 50770 infrastructure, facilitating Post Limited 50,000.00 0.00 Canceled 2018-02-13 2018-04-10 2018-10-07 Quotations Envelope each) and Investors Profile secure access to land and (100 copies) project management. GH-GCAP-46070-NC-RFQ / Component 3: securing PPPs Request for Single Stage - One Print info-pack on proposed IDA / 50770 and small-holder linkages in Post Limited 20,000.00 0.00 Canceled 2018-08-27 2018-10-22 2019-04-20 Quotations Envelope Nasia- Nabogo PPP sites the SADA zone GH-GCAP-96240-NC-RFQ / Component 4: Project Request for Single Stage - One Produce Video Documentary IDA / 50770 management and monitoring Post Open - National 35,000.00 17,615.79 Signed 2019-03-25 2019-05-20 2019-05-21 2019-08-08 Quotations Envelope on the safe use of pesticides and evaluation GH-GCAP-46064-NC-RFQ / Component 4: Project Request for Single Stage - One Production and printing of IDA / 50770 management and monitoring Post Limited 25,000.00 0.00 Canceled 2018-05-21 2018-07-16 2019-01-12 Quotations Envelope 500 Pesticide User Manuals and evaluation GH-GCAP-46063-NC-RFQ / Component 4: Project Request for Single Stage - One Produce Video Documentary IDA / 50770 management and monitoring Post Limited 10,000.00 0.00 Canceled 2018-06-01 2018-07-27 2019-01-23 Quotations Envelope on the use of pesticides and evaluation GH-GCAP-45754-NC-RFQ / Component 4: Project Pending Produce Video Documentary Request for IDA / 50770 management and monitoring Post 90,000.00 0.00 Implementati 2019-10-16 2020-02-19 2020-08-17 for GCAP (Phase 2) and Quotations and evaluation on Three Irrigation Schemes GH-GCAP-45912-NC-RFQ / Produce signage and Component 4: Project Pending directional signs for Small Request for Single Stage - One IDA / 50770 management and monitoring Post Limited 25,000.00 0.00 Implementati 2018-05-21 2018-07-16 2019-01-12 Scale irrigation schemes and Quotations Envelope and evaluation on additional development at NNIV GH-GCAP-96238-NC-RFQ / Component 4: Project Pending Development of MIS Request for Single Stage - One IDA / 50770 management and monitoring Post Open - National 35,000.00 0.00 Implementati 2020-04-26 2020-06-21 2020-09-19 Database and training for Quotations Envelope and evaluation on MED GH-GCAP-45912-NC-RFQ-1 / Produce signage and Component 4: Project Pending directional signs for Small Request for Single Stage - One IDA / 50770 management and monitoring Post Limited 25,000.00 0.00 Implementati 2019-05-09 2019-07-30 2019-09-10 Scale irrigation schemes and Quotations Envelope and evaluation on additional development at NNIV Page 3 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 5: Investments GH-GCAP-45403-CS-QCBS / in Physical Rehabilitation Construction Supervision of and Modernization of Quality And Cost- Open - IDA / 50770 Prior 2,000,000.00 2,254,554.75 Under Review 2018-01-30 2018-02-07 2018-02-20 2018-04-05 2018-03-04 2018-05-03 2018-06-02 2018-06-18 2018-07-07 2018-08-20 2018-08-11 2018-09-03 2019-08-11 the Tono and Vea Irrigation Selected Existing Public Based Selection International Schemes Irrigation and Drainage Infrastructure. GH-GCAP-45733-CS-QCBS / Consultancy Service to provide Third Party Capacity Building for all Matching Component 3: securing PPPs Grant Beneficiaries to build Quality And Cost- Open - IDA / 50770 and small-holder linkages in Prior 600,000.00 0.00 Canceled 2018-02-09 2018-03-02 2018-04-15 2018-05-13 2018-06-12 2018-07-17 2018-08-21 2019-08-21 technical capacity of Based Selection International the SADA zone grantees and outgrowers (agronomy, management and operations, safeguards and community engagement GH-GCAP-45738-CS-QCBS / Consultancy Service for Component 2: Securing Quality And Cost- Open - Feasibility Studies of IDA / 50770 PPPs and small-holder Prior 2,000,000.00 0.00 Canceled 2018-03-13 2018-04-03 2018-05-17 2018-06-14 2018-07-14 2018-08-18 2018-09-22 2019-09-22 Based Selection International Irrigation Water linkages in the Accra Plains Transmission Pipeline Project GH-GCAP-52022-CS-CQS / Consultancy Service for ORGANISATIONAL Component 7: Support for TRANSFORMATION/ RE- the Development of Water Consultant STRUCTURING OF ICOUR IDA / 50770 Users’ Associations and Post Qualification Open - National 250,000.00 153,574.00 Signed 2019-02-01 2018-12-14 2019-02-22 2019-04-07 2019-03-01 2019-05-07 2019-05-20 2019-06-11 2019-05-29 2019-12-08 INTO A PRIVATE SME Private Scheme Management Selection AND FORMATION & Entities CAPACITY BUILDING OF WUAS IN TONO & VEA SCHEMES GH-GCAP-45746-CS-CQS / Consultancy to Provide Component 3: securing PPPs Consultant Technical Assistance in IDA / 50770 and small-holder linkages in Post Qualification Open - National 300,000.00 0.00 Canceled 2019-09-25 2019-10-16 2019-11-29 2019-12-29 2020-02-02 2020-07-31 Management of Centre Pivot the SADA zone Selection Systems and Greenhouses Component 7: Support for GH-GCAP-97526-CS-QCBS / the Development of Water Recruitment of Scheme Quality And Cost- Open - Pending IDA / 50770 Users’ Associations and Post 250,000.00 0.00 2020-06-19 2020-07-10 2020-08-23 2020-09-20 2020-10-20 2020-11-24 2020-12-29 2021-12-29 Management Entities to Based Selection International Implementation Private Scheme Management Manage KLBIP Entities Component 7: Support for GH-GCAP-97525-CS-QCBS / the Development of Water Recuritment of Scheme Quality And Cost- Open - Pending IDA / 50770 Users’ Associations and Post 250,000.00 0.00 2020-06-17 2020-07-08 2020-08-21 2020-09-18 2020-10-18 2020-11-22 2020-12-27 2021-12-27 Management Entities to Based Selection International Implementation Private Scheme Management Manage KIS Entities GH-GCAP-97527-CS-CQS / Consultancy for the Preparation of Component 4: Project Consultant Pending Implementation Completion IDA / 50770 management and monitoring Post Qualification Open - National 100,000.00 0.00 2019-10-31 2019-11-21 2020-01-04 2020-02-03 2020-03-09 2020-09-05 Implementation Report for GCAP and evaluation Selection MATCHING GRANT BENEFICIARIES Page 4 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-GCAP-45747-CS-INDV / Component 3: securing PPPs Individual Consultantancy to Build IDA / 50770 and small-holder linkages in Post Consultant Open 50,000.00 0.00 Canceled 2018-02-02 2018-02-08 2018-03-23 2018-04-13 2018-05-18 2018-11-14 Capacity of Grantees in the SADA zone Selection Warehouse Management GH-GCAP-49022-CS-INDV / Component 5: Investments CONSULTANCY SERVICES in Physical Rehabilitation FOR THE DESIGN OF A Individual and Modernization of FRAMEWORK FOR IDA / 50770 Post Consultant Limited 15,000.00 14,276.25 Signed 2018-02-28 2018-02-15 2018-03-05 2018-02-01 2018-03-26 2018-02-09 2018-04-30 2018-02-15 2018-10-27 Selected Existing Public MANAGING PROJECTS IN Selection Irrigation and Drainage THE MINISTRY OF FOOD Infrastructure AND AGRICULTURE GH-GCAP-49025-CS-INDV / CONSULTANCY SERVICE Component 2: Securing Individual TO UNDERTAKE SUB- IDA / 50770 PPPs and small-holder Post Consultant Open 100,000.00 99,927.50 Signed 2018-02-28 2018-02-15 2018-04-18 2018-03-05 2018-05-09 2018-03-15 2018-06-13 2018-03-19 2018-12-10 SECTOR STUDIES ON linkages in the Accra Plains Selection COTTON, COCONUT, CASHEW AND RUBBER GH-GCAP-46072-CS-INDV / Component 4: Project Individual Consultancy to baseline IDA / 50770 management and monitoring Post Consultant Limited 40,000.00 0.00 Canceled 2018-04-09 2018-04-14 2018-05-05 2018-06-09 2018-12-06 Study at Nasia-Nabogo and evaluation Selection Inland Valley GH-GCAP-45745-CS-INDV / Consultancy Services for Producing As-Built-Drawings Component 3: securing PPPs Individual and Final Accounts for IDA / 50770 and small-holder linkages in Post Consultant Open 60,000.00 0.00 Canceled 2018-03-04 2018-02-02 2018-04-22 2018-05-13 2018-06-17 2018-12-14 Warehouses under the First the SADA zone Selection Call for Matching Grants (2ICS) GH-GCAP-45748-CS-INDV / Engage a 3rd party consultant to assist GCAP Component 4: Project Individual develop and publish human IDA / 50770 management and monitoring Post Consultant Open 35,000.00 0.00 Canceled 2018-04-09 2018-05-28 2018-06-18 2018-07-23 2019-01-19 interest/ success stories and and evaluation Selection use existing M&E data to publish the success of GCAP GH-GCAP-96230-CS-INDV / Component 5: Investments Recruitment of Transaction in Physical Rehabilitation Individual Advisor to Develop ToR and and Modernization of IDA / 50770 Post Consultant Open 100,000.00 0.00 Canceled 2019-03-18 2019-05-06 2019-05-27 2019-07-01 2019-12-28 Assist in the procurement of Selected Existing Public Selection Scheme Management Entities Irrigation and Drainage (SMEs) Infrastructure. GH-GCAP-96232-CS-INDV / Provision of Technical Component 4: Project Individual Assistance to GCAP- IDA / 50770 management and monitoring Post Consultant Open 30,000.00 0.00 Canceled 2019-03-15 2019-05-03 2019-05-24 2019-06-28 2019-12-25 supported Farmers in Agric and evaluation Selection Machinery Management GH-GCAP-120522-CS-INDV Component 5: Investments / Recruitment of in Physical Rehabilitation Instrumentation Engineer for Individual and Modernization of Construction Supervision of IDA / 50770 Prior Consultant Open 45,000.00 0.00 Under Review 2019-07-01 2019-08-19 2019-09-09 2019-10-14 2020-04-11 Selected Existing Public the Rehabilitation and Selection Irrigation and Drainage Modernization of Kpong Infrastructure. Irrigation Scheme. Page 5 GH-GCAP-120524-CS-INDV Component 5: Investments / Recruitment of Social in Physical Rehabilitation Safeguards Specialist for Individual and Modernization of Construction Supervision of IDA / 50770 Prior Consultant Open 45,000.00 0.00 Under Review 2019-07-01 2019-07-22 2019-08-19 2019-08-06 2019-09-09 2019-10-14 2020-04-11 Selected Existing Public the Rehabilitation and Selection Irrigation and Drainage Modernization of Kpong Infrastructure. Irrigation Scheme GH-GCAP-120527-CS-INDV / Recruitment of Institutional Component 5: Investments & Organizational in Physical Rehabilitation Individual Development Expert for and Modernization of IDA / 50770 Prior Consultant Open 45,000.00 0.00 Under Review 2019-07-01 2019-07-22 2019-08-19 2019-08-06 2019-09-09 2019-10-14 2020-04-11 Construction Supervision of Selected Existing Public Selection the Rehabilitation and Irrigation and Drainage Modernization of Kpong Infrastructure. Irrigation Scheme GH-GCAP-45750-CS-INDV / Component 3: securing PPPs Individual Consultancy to Build Land IDA / 50770 and small-holder linkages in Post Consultant Open 35,000.00 0.00 Canceled 2019-08-06 2019-09-24 2019-10-15 2019-11-19 2020-05-17 Management Information the SADA zone Selection Database Component 6: Support for GH-GCAP-45753-CS-INDV / the Restructuring and Individual Consultancy for the Design IDA / 50770 Strengthening of Public Post Consultant Open 20,000.00 0.00 Canceled 2019-08-06 2019-09-24 2019-10-15 2019-11-19 2019-11-27 of Digital Library for GIDA Irrigation and Drainage Selection Institutions GH-GCAP-120516-CS-INDV / Recruitment of Senior Component 5: Investments Irrigation Engineer- Team in Physical Rehabilitation Individual Leader/Resident Engineer for and Modernization of Under IDA / 50770 Prior Consultant Open 140,000.00 0.00 2019-07-01 2019-07-23 2019-08-19 2019-08-01 2019-09-09 2020-06-15 2019-10-14 2021-04-06 Construction Supervision of Selected Existing Public Implementation Selection the Rehabilitation and Irrigation and Drainage Modernization of Kpong Infrastructure. Irrigation Scheme GH-GCAP-161958-CS-INDV / Consultancy Services for Component 4: Project Individual Pending Completion Report for Ghana IDA / 50770 management and monitoring Post Consultant Limited 80,000.00 0.00 2020-06-22 2020-06-27 2020-07-18 2020-08-22 2021-02-18 Implementation Commercial Agricultural and evaluation Selection Project GH-GCAP-174574-CS-INDV / TERMS OF REFERENCE TO HIRE AN INDIVIDUAL CONSULTANT TO PROVIDE LEGAL SERVICES TO THE GHANA Component 2: Securing Individual Pending COMMERCIAL IDA / 50770 PPPs and small-holder Prior Consultant Direct 30,000.00 0.00 2020-06-24 2020-07-04 2020-07-25 2020-08-29 2020-12-27 Implementation AGRICULTURE PROJECT linkages in the Accra Plains Selection (GCAP) & GHANA PERI- URBAN VEGETABLE VALUE CHAIN PROJECT (GPVVCP) UNDER A TIME- BASED AGREEMENT Page 6