Public Disclosure Copy

        The World Bank                                                                           Implementation Status & Results Report
        Rwanda Urban Development Project (P150844)


Rwanda Urban Development Project (P150844)

AFRICA | Rwanda | Social, Urban, Rural and Resilience Global Practice Global Practice |
IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 2 | ARCHIVED on 21-Dec-2016 | ISR26332 |


Implementing Agencies: Ministry of Infrastructure




Key Dates

  Key Project Dates

  Bank Approval Date:29-Mar-2016                                           Effectiveness Date:13-Jul-2016
  Planned Mid Term Review Date:12-Nov-2018                                 Actual Mid-Term Review Date:--
  Original Closing Date:30-Jun-2021                                        Revised Closing Date:30-Jun-2021




Project Development Objectives

 Project Development Objective (from Project Appraisal Document)
 The project development objective is to provide access to basic infrastructure and enhance urban management in selected urban centers of the
 participating districts.


 Has the Project Development Objective been changed since Board Approval of the Project Objective?
 No

 PHRPDODEL



Components

Name
Component 1: Provision of Basic Infrastructure in Secondary Cities:(Cost $80.00 M)
Component 2: Upgrading of Unplanned Settlements in the City of Kigali:(Cost $10.00 M)
Component 3: Technical Assistance for Sustainable Urban Management:(Cost $3.00 M)
Component 4: Support for Project Management:(Cost $2.00 M)



Overall Ratings
Name                                                                     Previous Rating                         Current Rating

Progress towards achievement of PDO                                       Satisfactory                           Satisfactory
Overall Implementation Progress (IP)                                      Satisfactory                           Satisfactory
Overall Risk Rating                                                       Substantial                            Substantial



12/21/2016                                                                                                                           Page 1 of 7
                                                         Public Disclosure Copy
                                                          Public Disclosure Copy

               The World Bank                                                                        Implementation Status & Results Report
               Rwanda Urban Development Project (P150844)




Implementation Status and Key Decisions

 The project became effective on July 13, 2016 and was officially launched on September 20, 2016, in the presence of key stakeholders in the national
 and district governments. The project launch was accompanied by a three-day training (September 20-22, 2016) with the RUDP teams, particularly for
 District Government officials, covering all aspects of project implementation. The detailed engineering designs (DEDs) for all six secondary cities and
 City of Kigali (COK) are currently being reviewed and finalized, and bidding documents are anticipated in January 2017.




Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                              Rating at Approval               Previous Rating             Current Rating

 Political and Governance                                    Low                             Low                        Low
 Macroeconomic                                               Low                             Low                        Low
 Sector Strategies and Policies                              Low                             Low                        Low
 Technical Design of Project or Program                      Moderate                        Moderate                   Moderate
 Institutional Capacity for Implementation and
 Sustainability
                                                             Substantial                     Substantial                Substantial
 Fiduciary                                                   Substantial                     Substantial                Substantial
 Environment and Social                                      Substantial                     Substantial                Substantial
 Stakeholders                                                Moderate                        Moderate                   Moderate
 Other                                                       --                              --                         --
 Overall                                                     Substantial                     Substantial                Substantial


Results

 Project Development Objective Indicators
 PHINDPDOTBL




      Number of people in urban areas provided with access to all-season roads within a 500 meter range under the project
     (Number, Core)

                                            Baseline                     Actual (Previous)           Actual (Current)            End Target

         Value                              36,299.00                    --                          36,299.00                   118,805.00

         Date                               31-Jan-2016                  --                          08-Dec-2016                 30-Jun-2021


 PHINDPDOTBL




          Land Area provided with drainage services financed under the project (Hectare(Ha), Custom)




12/21/2016                                                                                                                               Page 2 of 7
                                                          Public Disclosure Copy
                                                           Public Disclosure Copy

               The World Bank                                                                Implementation Status & Results Report
               Rwanda Urban Development Project (P150844)



                                             Baseline                   Actual (Previous)     Actual (Current)     End Target

         Value                               0.00                       0.00                  0.00                 3,479.00

         Date                                31-Jan-2016                28-Jun-2016           08-Dec-2016          30-Jun-2021


 PHINDPDOTBL




          Increase in share of maintenance expenditures of district budget (Percentage, Custom)


                                             Baseline                   Actual (Previous)     Actual (Current)     End Target

         Value                               6.50                       --                    6.50                 10.00

         Date                                31-Jan-2016                --                    08-Dec-2016          30-Jun-2021


 PHINDPDOTBL




          Direct project beneficiaries (Number, Core)


                                             Baseline                   Actual (Previous)     Actual (Current)     End Target

         Value                               0.00                       0.00                  0.00                 88,000.00

         Date                                31-Jan-2016                28-Jun-2016           08-Dec-2016          30-Jun-2021


 PHINDPDOTBL




          Female beneficiaries (Percentage, Core Supplement)



                                             Baseline                   Actual (Previous)     Actual (Current)     End Target

         Value                               0.00                       0.00                  0.00                 51.70




 Overall Comments

 Intermediate Results Indicators




12/21/2016                                                                                                                 Page 3 of 7
                                                           Public Disclosure Copy
                                                                Public Disclosure Copy

                  The World Bank                                                                   Implementation Status & Results Report
                  Rwanda Urban Development Project (P150844)

 PHINDIRITBL




              Urban roads rehabilitated or constructed (Kilometers, Custom)

                                                  Baseline                    Actual (Previous)    Actual (Current)        End Target

               Value                              0.00                        --                   0.00                    81.00

               Date                               31-Jan-2016                 --                   08-Dec-2016             30-Jun-2021




 PHINDIRITBL




              Standalone drains constructed or rehabilitated under the project (Kilometers, Custom)

                                                  Baseline                    Actual (Previous)    Actual (Current)        End Target

               Value                              0.00                        0.00                 0.00                    44.00

               Date                               31-Jan-2016                 28-Jun-2016          08-Dec-2016             30-Jun-2021




 PHINDIRITBL




              Unplanned settlement area upgraded (Hectare(Ha), Custom)

                                                  Baseline                    Actual (Previous)    Actual (Current)        End Target

               Value                              0.00                        --                   0.00                    86.00

               Date                               31-Jan-2016                 --                   08-Dec-2016             30-Jun-2021




 PHINDIRITBL




              District system for tracking business activity operational. (Text, Custom)

                                                  Baseline                    Actual (Previous)    Actual (Current)        End Target

                                                                                                                           System for
                                                                                                                           tracking
                                                  No standard system in                            No standard system in
               Value                                                          --                                           business
                                                  place                                            place
                                                                                                                           activity fully
                                                                                                                           operational

               Date                               31-Jan-2016                 --                   08-Dec-2016             30-Jun-2021




12/21/2016                                                                                                                           Page 4 of 7
                                                                Public Disclosure Copy
                                                               Public Disclosure Copy

                  The World Bank                                                                    Implementation Status & Results Report
                  Rwanda Urban Development Project (P150844)

 PHINDIRITBL




              Districts use GIS as key planning tool (Text, Custom)

                                                 Baseline                   Actual (Previous)       Actual (Current)        End Target

                                                                                                                            4 Districts
                                                                                                                            demonstrate
                                                                                                                            use of GIS in
                                                                                                                            strategic
               Value                             0.00                       --                      0.00
                                                                                                                            investment
                                                                                                                            planning and
                                                                                                                            annual planning
                                                                                                                            procedures

               Date                              31-Jan-2016                --                      08-Dec-2016             30-Jun-2021

 PHINDIRITBL




              District infrastructure management system for road and drainage assets operational (Text, Custom)

                                                 Baseline                   Actual (Previous)       Actual (Current)        End Target

                                                                                                                            2nd year O&M
                                                                                                                            plan
                                                 No standard system in                              No standard system in
               Value                                                        --                                              implemented in
                                                 place                                              place
                                                                                                                            at least 4
                                                                                                                            districts

               Date                              31-Jan-2016                28-Jun-2016             08-Dec-2016             30-Jun-2021

 PHINDIRITBL




              Participants in consultation activities during project implementation (number) (Number, Core)

                                                 Baseline                   Actual (Previous)       Actual (Current)        End Target

               Value                             0.00                       0.00                    0.00                    700.00

               Date                              31-Jan-2016                28-Jun-2016             08-Dec-2016             30-Jun-2021




 PHINDIRITBL




              Participants in consultation activities during project implementation - female (Number, Core Breakdown)

                                                 Baseline                   Actual (Previous)       Actual (Current)        End Target

               Value                             0.00                       --                      0.00                    350.00

               Date                              31-Jan-2016                --                      08-Dec-2016             30-Jun-2021




 Overall Comments

12/21/2016                                                                                                                           Page 5 of 7
                                                               Public Disclosure Copy
                                                         Public Disclosure Copy

           The World Bank                                                                        Implementation Status & Results Report
           Rwanda Urban Development Project (P150844)




 Data on Financial Performance

Disbursements (by loan)

 Project       Loan/Credit/TF     Status      Currency      Original   Revised      Cancelled   Disbursed    Undisbursed                   Disbursed

 P150844       IDA-57840          Effective   XDR             68.90      68.90           0.00         4.47           64.43                        6%


Key Dates (by loan)
 Project       Loan/Credit/TF    Status       Approval Date    Signing Date      Effectiveness Date   Orig. Closing Date     Rev. Closing Date

 P150844       IDA-57840         Effective    29-Mar-2016      06-Apr-2016       13-Jul-2016          30-Jun-2021            30-Jun-2021



Cumulative Disbursements




 Restructuring History

  There has been no restructuring to date.




12/21/2016                                                                                                                          Page 6 of 7
                                                         Public Disclosure Copy
                                             Public Disclosure Copy

        The World Bank                                                Implementation Status & Results Report
        Rwanda Urban Development Project (P150844)



 Related Project(s)

There are no related projects.




12/21/2016                                                                                         Page 7 of 7
                                             Public Disclosure Copy