The World Bank                                                                                   Implementation Status & Results Report
           Second Ho Chi Minh City Environmental Sanitation Project (P127978)



Second Ho Chi Minh City Environmental Sanitation Project (P127978)


 EAST ASIA AND PACIFIC | Vietnam | Water Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2015 | Seq No: 13 | ARCHIVED on 01-Feb-2021 | ISR45472 |


 Implementing Agencies: Socialist Republic of Vietnam, URBAN INFRASTRUCTURE CONSTRUCTION INVESTMENT PROJECTS MANAGEMENT
 UNIT



 Key Dates


  Key Project Dates

   Bank Approval Date: 23-Dec-2014                                            Effectiveness Date: 10-Jul-2015
   Planned Mid Term Review Date: 14-Jun-2019                                  Actual Mid-Term Review Date: 17-May-2019
   Original Closing Date: 30-Jun-2021                                         Revised Closing Date: 30-Jun-2021
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The Project Development Objective is to improve wastewater services in a sustainable manner in selected areas of Ho Chi Minh City (HCMC) and
  increase awareness on sanitation.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Component 1: Interceptor (Base Cost):(Cost $63.00 M)
 Component 2: Wastewater Treatment Plant (Base Cost):(Cost $220.00 M)
 Component 3: Sewerage in District 2 Area (Base Cost):(Cost $45.00 M)
 Component 4A: Construction and Supervision and Project Management (Base Cost):(Cost $29.00 M)
 Component 4B: Land Acquisition and Operating Cost of Investment Management Authority (Base
 Cost):(Cost $41.00 M)

 Overall Ratings

 Name                                                                       Previous Rating                         Current Rating

 Progress towards achievement of PDO                                        Moderately Unsatisfactory              Moderately Unsatisfactory
 Overall Implementation Progress (IP)                                       Moderately Satisfactory                Moderately Satisfactory
 Overall Risk Rating                                                        Substantial                            Substantial


 Implementation Status and Key Decisions

  Overall, there has been several positive developments and continued progress over the last 12 months. Key achievements include: (1)
  advancement of the interceptor tunnels (now around 85% completed), (2) good progress on most of the sewer line contracts and (3) progress of
  designs and commencement of on-site works under XL-02 – the Design-Build and Operate (DBO) contract for the large (480,000 m3/day)
  wastewater treatment plant (WWTP).
  All originally planned activities are progressing, completion of which will ensure the project development objectives are achieved with project
  benefits directly extending to more than 1.1 million residents of Ho Chi Minh City. However, as a result of start-up and procurement delays,


2/1/2021                                                                                                                     Page 1 of 6
            The World Bank                                                                                      Implementation Status & Results Report
            Second Ho Chi Minh City Environmental Sanitation Project (P127978)



  intermediate result targets have not been realized as planned, as many are linked to the infrastructure developments which are yet to be completed
  and operational. An extension of the project closing date is needed in order to allow for all project investments to be completed and the Project
  development objective fully achieved. This extension is being discussed between the national Government, City and World Bank.




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                              Rating at Approval               Previous Rating               Current Rating

  Political and Governance                                   --                               Moderate                     Moderate
  Macroeconomic                                              --                               Moderate                     Moderate
  Sector Strategies and Policies                             --                               Moderate                     Moderate
  Technical Design of Project or Program                     --                               Low                          Low
  Institutional Capacity for Implementation and
                                                             --                               Moderate                     Moderate
  Sustainability
  Fiduciary                                                  --                               Substantial                  Moderate
  Environment and Social                                     --                               High                         Substantial
  Stakeholders                                               --                               Moderate                     Moderate
  Other                                                      --                               Moderate                     Moderate
  Overall                                                    --                               Substantial                  Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   Improve wastewater services in a sustainable manner in selected areas of Ho Chi Minh City (HCMC)

    IN00952832
    ►Volume (mass) of BOD pollution load removed by treatment plant under the project (Tones/year, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                        0.00                          0.00                       3,883.00

    Date                               31-Dec-2014                 07-Jul-2020                   28-Jan-2021                30-Jun-2021
                                       This indicator will only be met once the wastewater treatment plant supported under the project is
                                       completed and operational. Originally targeted for June 2020, a delay in the procurement of the DBO
                                       contract for the wastewater treatment plant has pushed achievement of this indicator to about June 2024
   Comments:
                                       (a formal request to extend the project Closing Date to allow for construction completion of this plant has
                                       been discussed and is expected from the Borrower).

    IN00952834


2/1/2021                                                                                                                       Page 2 of 6
           The World Bank                                                                                      Implementation Status & Results Report
           Second Ho Chi Minh City Environmental Sanitation Project (P127978)




    ►Direct project beneficiaries (number), of which female (percentage) (Number, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)          End Target

    Value                              0.00                        0.00                          0.00                       1,125,000.00

    Date                               31-Dec-2014                 07-Jul-2020                   28-Jan-2021                30-Jun-2021

                                       Similar comment to the main indicator above.
   Comments:

     IN00952835
     Percentage female beneficiaries (%) (Number, Custom Breakdown)

                                      Baseline                    Actual (Previous)             Actual (Current)            End Target

     Value                          0.00                          0.00                          0.00                        50.00

     Date                           31-Dec-2014                   30-Apr-2019                   30-Apr-2019                 30-Jun-2021

    IN00952836
    ►Maintaining cost recovery for wastewater management in HCMC (Percentage, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)          End Target

    Value                              0.00                        37.00                         37.00                      100.00

    Date                               31-Dec-2014                 07-Jul-2020                   28-Jan-2021                30-Jun-2021
                                       A proposal to adopt an increased tariff schedule and related tariff implementation roadmap for wastewater
                                       and drainage services using the cost recovery approach set forth in Decree 80 (2014) had been submitted
                                       to the City’s People’s Committee. Following several rounds of internal comments by all relevant HCMC
                                       line agencies and completion of the poverty and social impact assessment, the updated report and
                                       proposals are in the final stages of review and public consultations (delayed due to COVID-19). The
                                       improvement in cost recovery ratio for wastewater management is expected to be seen after an increased
   Comments:
                                       tariff schedule commence implementation. The MTR report recommended adjustments to this indicator to
                                       clarify that this indicator will measure cost recovery from consumer tariff i.e., excluding any subsidy or
                                       budget support from HCMC, to better measure improving trend in financial sustainability. After
                                       adjustments, the end target is likely to be about 50% (also taking into account that the project only covers
                                       a portion of the total wastewater management area of the Steering Committee for Flood Control (SCFC).



   Increase awareness on sanitation

    IN00952833
    ►Percentage of respondents demonstrating an increase in awareness on sanitation issues (Percentage, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)          End Target

    Value                              0.00                        98.50                         98.50                      50.00

    Date                               31-Dec-2014                 07-Jul-2020                   28-Jan-2021                30-Jun-2021
                                       The baseline survey conducted by the IEC consultant in the areas covered by the project asked a series
                                       of questions related to sanitation. Findings indicate that that most people are aware of sanitation
                                       issues. In particular, almost all are cognizant of the benefits of sewer connections, citing reasons related
   Comments:
                                       to reducing pollution of groundwater/water sources and to water bodies, roads and nearby areas, as well
                                       as reducing odor. This indicator appears to be very broad.




2/1/2021                                                                                                                        Page 3 of 6
           The World Bank                                                                                    Implementation Status & Results Report
           Second Ho Chi Minh City Environmental Sanitation Project (P127978)



 Intermediate Results Indicators by Components



   Component 1: Interceptor

    IN00952837
    ►Length of interceptor installed (Kilometers, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                        4.10                         5.00                      8.00

    Date                              31-Dec-2014                 07-Jul-2020                  28-Jan-2021               30-Jun-2021
                                      Physical progress 85%. Of twenty shafts in total, 17 are now substantially completed and 3 are in
                                      progress. Pipe jacking is progressing, with a length of 4,966m of a total of 7,770m now completed. This
                                      includes completion of Stage 1 (Shafts S-0 to S-10) along with Shaft 11 to 15 in Stage 2. Pipe
   Comments:
                                      manufacturing is advanced with around 7,400m produced in total. Certified payment claims have reached
                                      around 75% of the awarded contract value.



   Component 2: Wastewater Treatment Plant

    IN00952838
    ►DBO Contractor activities in place (Yes/No, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             No                          Yes                          Yes                       Yes

    Date                              31-Dec-2014                 07-Jul-2020                  28-Jan-2021               30-Jun-2021
                                      The WWTP DBO contract was signed in March 2019 and became effective January 3, 2020. The
   Comments:                          contractor is working on design submittals and on-site preparatory works.



   Component 3: Sewerage in District 2 Area

    IN00952839
    ►District 2 sewers operational (Yes/No, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             No                          No                           No                        Yes

    Date                              31-Dec-2014                 07-Jul-2020                  28-Jan-2021               30-Jun-2021
                                      Construction works for all project supported District 2 sewer lines are ongoing, under five civil works
                                      contracts with cumulative physical progress greater than 60%. XL-04, XL-05 and XL-06 are under
   Comments:                          satisfactory implementation with progress between 75-85%. But contracts XL-03, XL-07 and XL-08 are
                                      lagging and are being closely monitored to ensure satisfactory completion.

    IN00952841
    ►New household sewer connections constructed under the project (Number, Custom)

                                      Baseline                    Actual (Previous)            Actual (Current)          End Target

    Value                             0.00                        0.00                         0.00                      7,153.00


2/1/2021                                                                                                                     Page 4 of 6
           The World Bank                                                                                        Implementation Status & Results Report
           Second Ho Chi Minh City Environmental Sanitation Project (P127978)




    Date                              31-Dec-2014                  07-Jul-2020                     28-Jan-2021              30-Jun-2021
                                      Surveys of households in the District 2 areas covered by the project has been done. Household
                                      connections will only be made in tandem with the completion of the associated secondary and tertiary
                                      sewer lines, currently under construction.
   Comments:                          The MTR recommended that the description of this indicator be adjusted to include households served by
                                      the sewer lines directly or indirectly. The sewer lines are designed to include interceptors that will serve to
                                      collect wastewater and thus indirectly serve households not directly connected to houses.

    IN00952842
    ►Number of poor people in the D2 area connected to the sewerage network (Number, Custom)

                                      Baseline                     Actual (Previous)               Actual (Current)          End Target

    Value                             0.00                         0.00                            0.00                      3,318.00

    Date                              31-Dec-2014                  07-Jul-2020                     07-Jul-2020              30-Jun-2021
                                      The MTR recommended that the description of this indicator be revised to clarify that it includes poor
   Comments:                          people served directly and indirectly by the sewer lines.



   Component 4A: Construction and Supervision and Project Management

    IN00952840
    ►Survey and IEC activities conducted (Yes/No, Custom)

                                      Baseline                     Actual (Previous)               Actual (Current)          End Target

    Value                             No                           Yes                             Yes                       Yes

    Date                              31-Dec-2014                  07-Jul-2020                     07-Jul-2020              30-Jun-2021
                                      Baseline survey has been completed. Several IEC activities (including posters, videos, IEC promoters'
                                      manual) have been completed and update to the context of COVID-19. A motivators' training workshops
   Comments:                          have been conducted along with house-to-house communications which are expected to be further rolled
                                      out in tandem with the sewer lines construction work.



 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF    Status      Currency        Original     Revised      Cancelled      Disbursed       Undisbursed             % Disbursed


 P127978       IBRD-84600        Effective   USD              250.00       250.00           0.00          39.47            210.53                       16%

 P127978       IDA-55680         Effective   USD              200.00       200.00           0.00          99.92             91.97                       52%


 Key Dates (by loan)




2/1/2021                                                                                                                        Page 5 of 6
           The World Bank                                                                               Implementation Status & Results Report
           Second Ho Chi Minh City Environmental Sanitation Project (P127978)




 Project        Loan/Credit/TF     Status      Approval Date    Signing Date    Effectiveness Date   Orig. Closing Date      Rev. Closing Date

 P127978        IBRD-84600         Effective   23-Dec-2014      12-Mar-2015     10-Jul-2015          30-Jun-2021             30-Jun-2021
 P127978        IDA-55680          Effective   23-Dec-2014      12-Mar-2015     10-Jul-2015          30-Jun-2021             30-Jun-2021


Cumulative Disbursements




 PBC Disbursement

                                                                                     Achievement     Disbursed amount in        Disbursement %
 PBC ID                     PBC Type    Description            Coc    PBC Amount
                                                                                     Status          Coc                        for PBC




  Restructuring History


  There has been no restructuring to date.


  Related Project(s)


  There are no related projects.