             The World Bank                                                                           Implementation Status & Results Report
             Sustainable Forest and Landscape Management Project (P129961)



Sustainable Forest and Landscape Management Project (P129961)

 EUROPE AND CENTRAL ASIA | Bosnia and Herzegovina | Environment & Natural Resources Global Practice |
 Global Environment Project | Investment Project Financing | FY 2014 | Seq No: 10 | ARCHIVED on 18-Dec-2018 | ISR35089 |


 Implementing Agencies: Ministry of Finance and Treasury, FBiH Ministry of Agriculture, Water Management and Forestry, RS Ministry of Agriculture,
 Forestry and Water Management



 Key Dates

   Key Project Dates

        Bank Approval Date: 15-Jan-2014                                       Effectiveness Date: 09-Jun-2014
        Planned Mid Term Review Date: 17-Apr-2017                             Actual Mid-Term Review Date: 24-Apr-2017
        Original Closing Date: 31-May-2019                                    Revised Closing Date: 31-May-2019

 pdoTable




 Project Development Objectives

   Project Development Objective (from Project Appraisal Document)
   A. Proposed Development Objective: To build capacity of forestry sector stakeholders and to demonstrate approaches for sustainable forest and
   land management through integrated management of vulnerable forest, scrub and pasture landscapes.

   Has the Project Development Objective been changed since Board Approval of the Project Objective?
   No


 Components            Table




 Name

 Enhanced Planning and Monitoring for SFLM:(Cost $1.07 M)
 Demonstration and Replication of SFLM Techniques in Vulnerable Areas:(Cost $4.23 M)
 Project Management:(Cost $0.28 M)


 Overall Ratings
 Name                                                                       Previous Rating                         Current Rating

 Progress towards achievement of PDO                                        Satisfactory                           Moderately Satisfactory

 Overall Implementation Progress (IP)                                       Satisfactory                           Moderately Satisfactory

 Overall Risk Rating                                                        Moderate                               Moderate


 Implementation Status and Key Decisions
   The overall progress in the project has been moderately satisfactory, and the project can still meet its Project Development Objective. Component
   1: Enhanced Planning and Monitoring for SFLM Substantial work has been invested in the past years in the activities supporting capacity
   building of forest sector stakeholders. These include FSC re-certification, progress on preparation of Forest Roads Master Plans, as well as
   strengthening decision-making through introducing selected key information relating to climate change into information systems and developing the
   systems themselves.


12/18/2018                                                                                                                   Page 1 of 6
                                                                  Public Disclosure Copy

           The World Bank                                                                                  Implementation Status & Results Report
           Sustainable Forest and Landscape Management Project (P129961)


             SFM Certification: The project supports efforts to increase certified area and maintain the certificate of already certified areas through re-
              certification in areas where the certifications had expired. The RS SUME has maintained its FSC certification. In FBiH, certified area has
              increased increasing the total area certified to 1.84 million ha. The end target is 1.85 million hectares.
             Forest Roads Master Plan - The RS has contracted a team of specialists to prepare the Forest Roads Master Plan. Baseline and
              background data has already been collected and the team has developed initial models for the road network. In FBiH, baseline data
              collection and other preparatory activities for the Forest Roads Master Plan Preparation have been completed and data entry into FMIS is
              almost completed. However, the expert team for preparing the plan has not been contracted yet. With only six months remaining of
              the project, the plan will likely not be as comprehensive as was originally planned.
             FMIS - In the RS, the RS Sume has an existing FMIS which is functioning, and information from the FMIS is used to make decisions on
              budgets, silvicultural activities, fire and pest management etc. The data from the FMIS is also used for national reporting to the
              international conventions. The FBiH FMIS has not yet fully resumed operations, while progress towards its establishment has been made.

  Component 2: Demonstration and Replication of SFLM Techniques in Vulnerable Areas Significant progress has been made in both entities
  during project implementation in demonstrating approaches for sustainable forest and landscape management through pilot sub-projects on
  re/afforestation, thinning, conversion, rehabilitation of fire affected areas, cleaning and removal of wild dump sites, production of seedlings etc. Total
  land area on which sustainable land management practices have been adopted is presently 3178 ha in both entities combined (1027 ha in RS and
  2151 ha in FBiH) and the PDO indicator value exceeds its end target value (3000 ha) already at this stage.

  The activities undertaken so far have already provided benefits to local communities (e.g., reforested areas will result in increased carbon stock and
  biodiversity, and will mitigate the negative effects from floods; rehabilitated forest fire roads, forest thinning activities, removal of unauthorized trash
  dumping sites and procurement of forest fire equipment will decrease forest fire risk). Additional benefits for the communities come from
  employment opportunities provided by these activities. Local communities have also participated in capacity building activities such as training in fire
  prevention, use of firefighting equipment, and other silvicultural activities.

  The Central Nursery Garden Doboj in RS has state of the art seedling production facilities and is in full operation. The project supported
  procurement of equipment for containerized covered root seedlings production. This modern nursery technology allows production of seedlings that
  are more resilient in worsening planting conditions caused by climate change. There have also been investments in staff training, as well as
  irrigation system. Another nursery for climate resilient Mediterranean species has been established in Trebinje.

  In FBiH, re/afforestation and restoration works – including rehabilitation of fire affected sites – have been completed in the area of 488 ha. There
  has also been an extensive effort to remove and clean illegal dumpsites in forest areas.

  The total area restored or re-/afforested under the project is 862 ha – of which re-/afforested is 766 ha. The area under enhanced production on
  state lands (2305 ha) already exceeds the project target. The project has completed 25 demonstration projects on sustainable forest and land
  management out of the end target of 28. In total, 29 sub-projects projects were related to fire control; well above the end target of 22.

  There have been savings from favorable currency rate developments and lower project costs. In RS, these savings have been used for equipment
  for the nursery in Trebinje and procurement of game management equipment. The Federation of BiH there will be an additional call for proposals for
  demonstration activities. The call has been delayed and is yet to be launched. The activities will need to be implemented under a tight time schedule
  and there is no room for additional delays.




  Risks


 Systematic Operations Risk-rating Tool

  Risk Category                                                  Rating at Approval               Previous Rating               Current Rating

  Political and Governance                                       --                               Moderate                     Moderate
  Macroeconomic                                                  --                               Moderate                     Moderate
  Sector Strategies and Policies                                 --                               Moderate                     Moderate
  Technical Design of Project or Program                         --                               Low                          Low
  Institutional Capacity for Implementation and
  Sustainability
                                                                 --                               Moderate                     Moderate
  Fiduciary                                                      --                               Moderate                     Moderate

12/18/2018                                                                                                                           Page 2 of 6
                                                                  Public Disclosure Copy

                 The World Bank                                                                                Implementation Status & Results Report
                 Sustainable Forest and Landscape Management Project (P129961)



  Environment and Social                                         --                               Low                         Low
  Stakeholders                                                   --                               Moderate                    Moderate
  Other                                                          --                               --                           --
  Overall                                                        --                               Moderate                    Moderate


  Results

 PDO Indicators by Objectives / Outcomes

   PDO
    IN00603135




    ►Land          area where sustainable land mgt. practices were adopted as a result of proj (Hectare(Ha), Corporate)
                                           Baseline                    Actual (Previous)               Actual (Current)        End Target
    Value                                  0.00                        3,178.00                        3,178.00                3,000.00

    Date                                   08-Nov-2013                 29-May-2018                     30-Nov-2018             31-May-2019



 Intermediate Results Indicators by Components


   Enhanced Planning and Monitoring for SFLM
    IN00603236




    ►IO          1.1 Forest Area Certified (million ha) (Hectare(Ha), Custom)
                                           Baseline                    Actual (Previous)               Actual (Current)        End Target
    Value                                  1.65                        1.76                            1.84                    1.85

    Date                                   08-Nov-2013                 29-May-2018                     30-Nov-2018             31-May-2019
                                           This reflects the total area certified in the country; some work been financed by resources outside the
    Comments:                              project.
    IN00603238




    ►IO 1.3 Key climate change mitigation and adaptation indicators included in FMIS (carbon stock, area lost to fire, area under
    insect/pest attack) (Text, Custom)
                                           Baseline                    Actual (Previous)               Actual (Current)        End Target
    Value                                  0.00                        2.00                            2.00                    3.00

    Date                                   08-Nov-2013                 29-May-2018                     30-Nov-2018             31-May-2019
                                           The indicator value indicates the number of topics covered by online reporting. In FBiH, the development
                                           of the main FMIS system is still ongoing and the climate change mitigation and adaptation indicators are
    Comments:                              reported online in annual reports outside FMIS. In RS, FMIS development is financed by the RS Sume's
                                           other resources and fire and pest/disease information is also provided online in Annual Reports.
    IN00603239




    ►Govt          institutions provided w/ capacity buildg to improve mgt of forest resources (Number, Custom)
                                           Baseline                    Actual (Previous)               Actual (Current)        End Target
    Value                                  0.00                        19.00                           19.00                   13.00




12/18/2018                                                                                                                          Page 3 of 6
                                                                               Public Disclosure Copy

                              The World Bank                                                                              Implementation Status & Results Report
                              Sustainable Forest and Landscape Management Project (P129961)



    Date                                                08-Nov-2013                 29-May-2018                   30-Nov-2018                31-May-2019
                                                        RS: RS Sume and MAFW; FBiH: MAWF; Federal Forest Institute and Forest Sector; Forest Faculty; 9
    Comments:                                           CFMC; 5 municipalities
    IN00603237




    ►IO                       1.2 Road Access Strategic Plan Completed (Text, Custom)
                                                        Baseline                     Actual (Previous)             Actual (Current)          End Target
    Value                                               0.00                        0.00                          0.00                       2.00

    Date                                                08-Nov-2013                 29-May-2018                   30-Nov-2018                31-May-2019
                                                        Both PIUs are currently working on the Master Plans. In RS good progress is made and timely finalization
                                                        of a high-quality master plan is expected. In FBiH there have been delays and achieving the result is not
    Comments:
                                                        as likely.


   Demonstration and Replication of SFLM Techniques in Vulnerable Areas
    IN00603241




    ►IO                       2.2 Area under enhanced production on state lands (Hectare(Ha), Custom)
                                                        Baseline                     Actual (Previous)             Actual (Current)          End Target
    Value                                               0.00                        2,305.00                      2,305.00                   2,000.00

    Date                                                08-Nov-2013                 23-May-2018                   30-Nov-2018                31-May-2019
    IN00603240




    ►Area                       restored or re/afforested (Hectare(Ha), Custom)
                                                        Baseline                     Actual (Previous)             Actual (Current)          End Target
    Value                                               0.00                        862.00                        862.00                     1,000.00

    Date                                                08-Nov-2013                 23-May-2018                   30-Nov-2018                31-May-2019
                 IN00603244




                 Area           re/afforested (Hectare(Ha), Custom Breakdown)

                                                       Baseline                    Actual (Previous)             Actual (Current)            End Target
                 Value                                0.00                         766.00                        766.00                      1,000.00

                 Date                                 08-Nov-2013                  23-May-2018                   30-Nov-2018                 31-May-2019
    IN00603242




    ►IO                       2.3 Demonstration subprojects completed relating to innovative SFLM methods (Text, Custom)
                                                        Baseline                     Actual (Previous)             Actual (Current)          End Target
    Value                                               0.00                        25.00                         25.00                      28.00

    Date                                                08-Nov-2013                 29-May-2018                   30-Nov-2018                31-May-2019
                                                        In RS, the actual number of individual project sites is 126; this indicator value (RS: 10; FBiH 15) covers
    Comments:                                           the type of activities and generic characteristics of the sites, not individual sites.
    IN00603243




    ►IO                       2.4 Demonstration subprojects completed relating to fire control (Text, Custom)
                                                        Baseline                     Actual (Previous)             Actual (Current)          End Target
    Value                                               0.00                        29.00                         29.00                      22.00

    Date                                                08-Nov-2013                 29-May-2018                   30-Nov-2018                31-May-2019



12/18/2018                                                                                                                                        Page 4 of 6
                                                             Public Disclosure Copy

           The World Bank                                                                        Implementation Status & Results Report
           Sustainable Forest and Landscape Management Project (P129961)




 Data on Financial Performance

 Disbursements (by loan)

 Project      Loan/Credit/TF    Status       Currency      Original   Revised    Cancelled    Disbursed     Undisbursed                 % Disbursed

 P129961      TF-16646          Effective    USD               5.58      5.58          0.00          3.92           1.66                       70%


 Key Dates (by loan)
 Project       Loan/Credit/TF    Status      Approval Date     Signing Date     Effectiveness Date   Orig. Closing Date      Rev. Closing Date

 P129961       TF-16646          Effective   01-Apr-2014       01-Apr-2014      09-Jun-2014          31-May-2019             31-May-2019


Cumulative Disbursements




  Restructuring History

  There has been no restructuring to date.




12/18/2018                                                                                                                Page 5 of 6
                                                  Public Disclosure Copy

          The World Bank                                                   Implementation Status & Results Report
          Sustainable Forest and Landscape Management Project (P129961)



  Related Project(s)

  There are no related projects.




12/18/2018                                                                                    Page 6 of 6