The World Bank                                                                                                                                                   Report No: ISR5774


                                                                                                     Implementation Status & Results
                                                                                                               Kenya
                                                                                       Kenya - Natural Resource Management Project (P095050)
Public Disclosure Copy




                         Operation Name: Kenya - Natural Resource Management Project (P095050)                 Project Stage:   Implementation         Seq.No: 16      Status: ARCHIVED      Archive Date:       23-Jan-2012
                                                                               Country: Kenya                                           Approval FY:        2007
                         Product Line: IBRD/IDA                                Region: AFRICA                                           Lending Instrument: Specific Investment Loan
                         Implementing Agency(ies): Ministry of Water & Irrigation, Ministry of Forestry & Wildlife, National Irrigation Board (NIB), Water Resources Management Authority (WRMA), Kenya Forest Service (KFS)

                         Key Dates
                         Board Approval Date      27-Mar-2007          Original Closing Date 30-Jun-2013              Planned Mid Term Review Date 22-Mar-2010                 Last Archived ISR Date 24-Dec-2011
                         Effectiveness Date       10-Dec-2007          Revised Closing Date 30-Jun-2013               Actual Mid Term Review Date       31-Mar-2010

                         Project Development Objectives
                         Kenya - Natural Resource Management Project (P095050)
                         Project Development Objective (from Project Appraisal Document)
                         The objective of the project is to improve management of water and forest resources in selected districts.

                         Has the Project Development Objective been changed since Board Approval of the Program?

                         �?   Yes          No


                         Component(s)
                         Component Name                                                                                                             Component Cost
                         Strengthening the Capacity of the Water Resources Management Authority (WRMA) with Direct                                             15.40
                         Investments in the Upper Tana Catchment
                         Consolidation of Irrigation Reforms and Investments                                                                                   28.40
                         Management of Forest Resources                                                                                                        22.60
                         Livelihood-based Investments in the Upper Tana Catchment                                                                               6.20
Public Disclosure Copy




                         Management and M&E                                                                                                                     4.90

                         Overall Ratings
                                                                   Previous Rating                        Current Rating
                         Progress towards achievement of PDO       Moderately Satisfactory                Moderately Satisfactory
                         Overall Implementation Progress (IP)      Moderately Satisfactory                Moderately Satisfactory
                         Overall Risk Rating                       Substantial                            Substantial

                         Implementation Status Overview
                         This ISR records (a) the findings of an Implementation Mission carried out for the Forest Component; as well as (b) the results of a field verification of the implementation progress of

                                                                                                                                                                                                                   Page 1 of 6
                             The World Bank                                                                                                                                                   Report No: ISR5774



                         sub-projects under the Livelihood Component of the Natural Resources Management Project (NRMP).

                         Management of Forest Resources Component:
                         The overall objective of the mission was together with the Government of Kenya to review (a) the implementation of safeguard instruments (advancing the IPPF into Vulnerable and
Public Disclosure Copy




                         Marginalized Group Plans (VMGPs), updating of the Process Framework); (b) the status of implementation of the procurement plan. Despite the delay in the start-up phase,
                         implementation progress has improved following the June 2011 restructuring of the Project.

                         Livelihood Investment Component:
                         The review of the implementation status of sub-projects was carried out for 14 out of 69 (20%) funded projects (through sample visits of randomly selected sub-projects). Focus was
                         given to the issues of procurement, financial management, and/or value for money as well as environmental compliance and the technical assistance and oversight provided by the
                         Livelihood Component Secretariat (established in the WRMA Regional Office) and associated Partner Agencies. The majority of the visited sub-projects have completed their
                         workplans and disbursed most of the funds they received.


                         Locations
                         Country                                                     First Administrative Division                    Location                                      Planned                Actual
                         Kenya                                                       Central Province                                 Thika District

                         Kenya                                                       Central Province                                 Murang'a District

                         Kenya                                                       Central Province                                 Kirinyaga District

                         Kenya                                                       Central Province                                 Aberdare Range

                         Kenya                                                       Central Province                                 Central Province

                         Kenya                                                       Western Province                                 Western Province                                                               ✔

                         Kenya                                                       Rift Valley Province                             Rift Valley Province                                                           ✔


                         Results

                         Project Development Objective Indicators
                         Indicator Name                                       Core      Unit of Measure                    Baseline                          Current                          End Target
Public Disclosure Copy




                         Community/User groups collaborating with                       Number                  Value      40.00                             318.00                           170.00
                         GoK institutions in water and/or forest activities
                         (% of which members are female)                                                        Date       14-Jan-2011                       30-Nov-2011                      28-Jun-2013
                                                                                                                Comments   Percentage of female              Percentage of female             Percentage of female
                                                                                                                           members = 42%                     members = 48%                    members = 50%
                         Increased revenue from water use charges                       Amount(USD)             Value      22000000.00                       25000000.00                      36000000.00
                         collected (in Kenya Shillings)
                                                                                                                Date       14-Jan-2011                       24-Jun-2011                      28-Jun-2013




                                                                                                                                                                                                                    Page 2 of 6
                             The World Bank                                                                                                                                   Report No: ISR5774



                                                                                                    Comments                                    No change, as revenues are
                                                                                                                                                being reported according to
                                                                                                                                                FYs (due by June 2012)
Public Disclosure Copy




                         Area of forests in project intervention areas            Hectare(Ha)       Value      0.00                             160000.00                     300000.00
                         managed according to approved forest
                         management plans.                                                          Date       20-Nov-2007                      01-Sep-2011                   30-Jun-2013
                                                                                                    Comments   Management plans are             Management plans of an
                                                                                                               outdated or not available,       estimated 160,000 hectares
                                                                                                               forest harvesting banned         have been finalized, with
                                                                                                                                                management of different
                                                                                                                                                stages of implementation.

                         Intermediate Results Indicators
                         Indicator Name                                    Core   Unit of Measure              Baseline                         Current                       End Target
                         Implementation of KFS Strategic Plan activities          Percentage        Value      0.00                             30.00                         60.00
                         supported
                                                                                                    Date       30-Jun-2009                      30-Nov-2011                   28-Jun-2013
                                                                                                    Comments   The KFS Strategic Plan is a
                                                                                                               five-year document (FY 2010
                                                                                                               to 2014), outlining 120
                                                                                                               activities under six strategic
                                                                                                               objectives.
                         Annual progress reports produced in time                 Number            Value      0.00                             3.00                          5.00
                         (cummulative)
                                                                                                    Date       20-Nov-2007                      30-Nov-2011                   28-Jun-2013
                                                                                                    Comments                                    no change
                         Technical staff from KFS trained in                      Number            Value      0.00                             60.00                         400.00
                         participatory forest management
                                                                                                    Date       20-Nov-2007                      30-Nov-2011                   30-Jun-2013
                                                                                                    Comments

                         Area brought under forest cover in project               Hectare(Ha)       Value      0.00                             1900.00                       3500.00
Public Disclosure Copy




                         intervention areas
                                                                                                    Date       20-Nov-2007                      30-Nov-2011                   28-Jun-2013
                                                                                                    Comments

                         Sub-projects implemented to improve                      Number            Value      0.00                             318.00                        500.00
                         livelihoods in Upper Tana Catchment
                                                                                                    Date       20-Nov-2007                      30-Nov-2011                   30-Jun-2013




                                                                                                                                                                                               Page 3 of 6
                             The World Bank                                                                                                                                  Report No: ISR5774



                         Indicator Name                               Core   Unit of Measure              Baseline                       Current                             End Target
                                                                                               Comments                                  Following the second call for
                                                                                                                                         proposals in May 2011, 1,209
Public Disclosure Copy




                                                                                                                                         proposal were received. 249
                                                                                                                                         proposals have been
                                                                                                                                         approved by the
                                                                                                                                         RegionalProject
                                                                                                                                         Implementation committee for
                                                                                                                                         funding. Cheques have been
                                                                                                                                         issued, implementation team
                                                                                                                                         is currently verifying/certifying
                                                                                                                                         outputs of the first batch of 69
                                                                                                                                         projects.
                         Production forests whose management has             Number            Value      0.00                           1.00                                5.00
                         been transferred to the private sector
                                                                                               Date       20-Nov-2007                    30-Nov-2011                         28-Jun-2013
                                                                                               Comments   All public forests are currently No change
                                                                                                          managed by KFS, no
                                                                                                          management responsibility ha
                                                                                                          s been transferred to the
                                                                                                          private sector.
                         Area provided with irrigation and drainage          Hectare(Ha)       Value      0.00                           0.00                                13420.00
                         services
                                                                                               Date       20-Nov-2007                    30-Nov-2011                         28-Jun-2013
                                                                                               Comments                                  Works contract for Mwea
                                                                                                                                         signed and contractor
                                                                                                                                         mobilized. Draft Design for
                                                                                                                                         the Lower Nzoia Scheme
                                                                                                                                         construction delayed.
                                                                                                                                         Discussionswith KfW
                                                                                                                                         (interested in co-financing) to
                                                                                                                                         address delays and develop a
                                                                                                                                         way forward.
Public Disclosure Copy




                         Improved area                                       Hectare(Ha)       Value      0.00                           0.00                                9420.00

                                                                             Sub Type          Date       20-Nov-2007                    30-Nov-2011                         28-Jun-2013
                                                                             Breakdown         Comments                                  Mwea rehabilitation works           This comprises (i) Mwea with
                                                                                                                                         contract signed and                 9,150 has and (ii) Bunyala
                                                                                                                                         contractor on site                  with 270 has (part of the new
                                                                                                                                                                             Lower Nzoia Scheme).
                         New area                                            Hectare(Ha)       Value      0.00                           0.00                                4000.00

                                                                             Sub Type          Date       20-Nov-2007                    30-Nov-2011                         28-Jun-2013



                                                                                                                                                                                               Page 4 of 6
                             The World Bank                                                                                                                                                Report No: ISR5774



                                                                                Breakdown           Comments                                           Lower Nzoia design delayed, Lower Nzoia Scheme
                                                                                                                                                       discussions with KfW as
                                                                                                                                                       potential co-financier ongoing.
                                                                                                                                                       Important to address capacity
Public Disclosure Copy




                                                                                                                                                       constraints of design
                                                                                                                                                       consultant and technical
                                                                                                                                                       issues with design as matter
                                                                                                                                                       of urgency considering project
                                                                                                                                                       closing date.
                         Microcatchment action plans developed by               Number              Value          0.00                                31.00                               30.00
                         WRUAs and approved by WRMA
                                                                                                    Date           20-Nov-2007                         30-Nov-2011                         30-Jun-2013
                                                                                                    Comments                                           58 WRUAs have been formed
                                                                                                                                                       in the Upper Tana Catchment
                                                                                                                                                       Area, of which 31 have
                                                                                                                                                       developed SCMPs, 27 are
                                                                                                                                                       developing SCMPs, and 12
                                                                                                                                                       are implementing SCMPs.


                         Data on Financial Performance (as of 02-Dec-2011)
                         Financial Agreement(s) Key Dates
                         Project             Loan No.               Status                          Approval Date                    Signing Date                Effectiveness Date             Closing Date
                         P095050             IDA-42770              Effective                       27-Mar-2007                      07-May-2007                 10-Dec-2007                    30-Jun-2013
                         P099628             TF-57564               Effective                       15-Nov-2006                      15-Nov-2006                 15-Nov-2006                    31-Dec-2018

                         Disbursements (in Millions)
                         Project             Loan No.               Status               Currency           Original             Revised            Cancelled          Disbursed            Undisbursed          % Disbursed
                         P095050             IDA-42770              Effective            USD                           68.50               68.50                0.00               30.89             40.04             45.00
                         P099628             TF-57564               Effective            USD                              1.58              1.58                0.00                0.00                  1.58          0.00
Public Disclosure Copy




                         Disbursement Graph




                                                                                                                                                                                                                 Page 5 of 6
                             The World Bank                                                                                                                                  Report No: ISR5774
Public Disclosure Copy




                         Key Decisions Regarding Implementation
                         The mission found that the development of Vulnerable and Marginalized Groups Plans (VMGPs) has further advanced, with VMGPs covering Cherangany Hills Forest Areas
                         finalized. These VMGPs are ready to be implemented following the completion of technical training of the community committees. With respect to the VMGP for Mt. Elgon, progress
                         has been delayed, following a request of the Ogiek community, considering the (independently) ongoing "Whakatane Assessment" led by IUCN and Forests Peoples Programme.
                         The updated Process Framework (PF) is currently being finalized and - following final editing - will be disclosed withing the first quarter of 2012.
                         Major works contracts (Investment Center at KFS HQ, office/lecture building for the Forestry Department at Moi University and a conference facility at Kenya Forest College) are
                         close to completion with hand-overs for the three sites expected before the end of January 2012.
                         The delay of important consultancies (e.g. the facilitation of a Inter-ministerial Task Force on Land issues, the REDD+ Coordination) has been recognized by the implementation
                         agency with a commitment to have the consultants on board by January 31, 2012.

                         Restructuring History
                         Level one Approved on 24-Jun-2011
Public Disclosure Copy




                         Related Projects
                         P099628-BioCF Kenya Greenbelt Movement




                                                                                                                                                                                               Page 6 of 6