RAMP -2: Procurement Plan – Jan. 2017. (RURAL ROADS AND MOBILTY PROJECT-2 PP:2017) I. General 1. Project Information: Country: Nigeria Borrower: Federal Government of Nigeria Project Name: Rural Road and Mobility Project 2 (RAMP2). Loan/Credit No.: P095003 PIA: Federal Project Management Unit (FPMU) 2. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision of Updated Procurement Plan, June 2010]. Updated January 2017 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by initial procurement plans: The procurement period of project covered from year June 2010 to December 2012; (Period covered by this current procurement plan: and January 2017 to December 2017 and or to June 2018). II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comment (US$ equivalent) 1. ICB and LIB (Goods and services other > 1,000,000.00 ALL than consultancy services) 2. NCB (Goods) 100,000.00 ≤ 1,000,000.00 NONE 3 IT System, and Non-Consulting Services > 1,000,000.00 (ICB). NCB: 100,000.00 ≤ 1,000,000.00 4. ICB (Works) > 10,000,000.00 ALL 5. NCB (Works) 300,000 ≤ 10,000,000.00 NONE 6 Shopping-Goods < 100,000.00 NONE 7 Shopping-Works < 300,000.00 NONE 8. Community Participation in All Values SSS of Community Procurement acceptable to the Maintenance Association and described in the PIM groups, etc. 9 Training, Workshops, Study Tours All Values Based on Annual Work Plans & Budgets July 9, 2010 2. Pre-qualification. Bidders for major works could be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Shall apply. 4. Reference to (if any) Project Operational/Procurement Manual: Shall apply 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the next 12 to18 (from January 2017). [ Packages which require Bank’s Prior review and Post Review packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 Yes Prior the ICB (Works) Summary of 43.77 15 Yes Prior the ICB (Goods) Summary of 64.53 18 No Post the NCB (Works) Summary of 1.86 4 No Post the NCB (Goods) Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2. Selection Method Prior Review Threshold Comment 1 Consultant Services-QCBS- All Values ALL International 2 Consultant Services-QCBS-National > 300,000.00 ALL 3 Consultant Services-CQS < 300,000.00 NONE 4 Consultant Services-lC > 200,000.00 ALL 5 Consultant Services-lC < 100,000.00 ToR only but ALL 6 Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior reviewed QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimated Packages Review Comments of Cost by Bank Assignment US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods (***This is the consolidated Procurement Plan for all the RAMP2 PIUs (Federal and States.). The individual PP submitted for review/ or already cleared for each SPIU is uploaded in the system). July 9, 2010 July 9, 2010 PROCUREMENT Nigeria : NG-RURAL ACCESS & MOBILITY PROJECT-Phase 2 PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2017-07-17 2020-06-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P095003 GPN Date: Project Name: NG-RURAL ACCESS & MOBILITY PROJECT-Phase 2 Loan / Credit No: IDA / 51540 Executing Agency(ies): Adamawa State RAMP 2 WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-ADAMAWA RAMP- Community-based Road Community Under 17035-CW-DIR / Routine IDA / 51540 Maintenance and Annual Post Driven Direct 20,903.22 0.00 Implementat 2017-01-31 2017-09-05 2017-01-31 2017-02-21 2017-08-20 maintenance (by maintenance Mechanized Maintenance Development ion Team) of 27km pilot road NG-ADAMAWA RAMP- Community-based Road Pending 17039-CW-RFQ / Annual Request for Single Stage - One IDA / 51540 Maintenance and Annual Post Limited 1,028,451.00 0.00 Implementat 2017-03-04 2017-03-04 2017-03-04 mechanized maintenance of Quotations Envelope Mechanized Maintenance ion 56.5km pilot Road NG-ADAMAWA RAMP- 17041-CW-RFP / Community-based Road Request for Single Stage - Two Construction of 16No River IDA / 51540 Maintenance and Annual Post Open - National 1,608,040.00 0.00 Canceled 2013-02-12 2017-11-10 2013-02-12 2013-02-12 Proposals Envelope Crossing across the State Mechanized Maintenance of Adamawa NG-ADAMAWA RAMP- 17265-CW-RFQ / Community-based Road Pending Request for Single Stage - One Rehabilitation /upgrading of IDA / 51540 Maintenance and Annual Prior Open - National 15,007,539.81 0.00 Implementat 2013-12-16 2013-12-16 2013-12-16 Quotations Envelope 201.4 km length of rural Mechanized Maintenance ion roads in three (3) lots NG-ADAMAWA RAMP- 47252-CW-CDD / Routine Community-based Road Community maintenance of 201.4km of IDA / 51540 Maintenance and Annual Post Driven Direct 193,975.00 0.00 Canceled 2018-03-15 2016-12-10 2018-03-20 2017-11-16 2018-04-24 2018-10-21 rural roads in Adamawa Mechanized Maintenance Development State NG-ADAMAWA RAMP- Community-based Road Pending 48446-CW-RFB / Annual Single Stage - One IDA / 51540 Maintenance and Annual Post Request for Bids Open - National 937,500.00 0.00 Implementat 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 mechanized maintenance of Envelope Mechanized Maintenance ion 57.7km pilot NG-ADAMAWA RAMP- 97583-CW-RFQ / Annual Community-based Road Request for Single Stage - One mechanized maintenance of IDA / 51540 Maintenance and Annual Post Limited 152,904.00 295,456.84 Signed 2019-03-02 2019-04-03 2019-04-27 2019-04-30 2019-10-24 Quotations Envelope Mayo Lamja - Gamlamja Mechanized Maintenance 20km (Lot1) Pilot road NG-ADAMAWA RAMP- 97590-CW-RFQ / Annual Community-based Road Request for Single Stage - One mechanized maintenance of IDA / 51540 Maintenance and Annual Post Limited 137,613.00 112,722.16 Completed 2019-03-02 2019-04-04 2019-04-27 2019-05-02 2019-10-24 Quotations Envelope Dasing Hausa/Radio Gotel Mechanized Maintenance 18km (Lot2) Pilot road NG-ADAMAWA RAMP- 97598-CW-RFQ / Annual Community-based Road Request for Single Stage - One mechanized maintenance of IDA / 51540 Maintenance and Annual Post Limited 151,884.00 229,386.96 Completed 2019-03-02 2019-04-10 2019-04-27 2019-05-08 2019-10-24 Quotations Envelope Pakka/Kirchinga/Bangshika Mechanized Maintenance 19.7km(Lot3) Pilot road Page 1 NG-ADAMAWA RAMP- 97618-CW-RFQ / Annual Community-based Road Request for Single Stage - One mechanized maintenance of IDA / 51540 Maintenance and Annual Post Limited 118,994.00 111,509.16 Completed 2019-03-02 2019-04-04 2019-04-27 2019-04-29 2019-10-24 Quotations Envelope Bille-W/Bobbo 15.5km (Lot3) Mechanized Maintenance Phase 1 road NG-ADAMAWA RAMP- 97621-CW-RFQ / Annual Community-based Road Pending Request for Single Stage - One mechanized maintenance of IDA / 51540 Maintenance and Annual Post Limited 193,459.00 0.00 Implementat 2019-03-02 2019-04-27 2019-10-24 Quotations Envelope /Namtari/Boggare 25.2km Lot Mechanized Maintenance ion 1 Phase 1 NG-ADAMAWA RAMP- 97774-CW-RFQ / Annual Community-based Road Under Request for Single Stage - One mechanized maintenance of IDA / 51540 Maintenance and Annual Post Limited 337,788.00 321,123.73 Implementat 2019-03-02 2019-04-03 2019-04-27 2019-05-07 2019-10-24 Quotations Envelope Njoboliyo/Borrong 44km Lot Mechanized Maintenance ion 2 Phase 1 NG-ADAMAWA RAMP- 97783-CW-RFQ / Access to Upgrading and Under Request for Single Stage - One 19No River Crossing IDA / 51540 Rehabilitation of Rural Post Limited 329,628.00 0.00 Implementat 2019-04-20 2019-10-03 2019-06-15 2019-12-12 Quotations Envelope Parda / Diyam Dadi 13.4km Transport Infrastructure ion (Lot 4) NG-ADAMAWA RAMP- 97785-CW-RFQ / Access to Upgrading and Under Request for Single Stage - One 19No River Crossing IDA / 51540 Rehabilitation of Rural Post Limited 188,153.00 0.00 Implementat 2019-04-20 2019-10-03 2019-06-15 2019-12-12 Quotations Envelope Sambang/Buwangal/ Yerima Transport Infrastructure ion 11.5km (Lot 5) NG-ADAMAWA RAMP- 98634-CW-RFB / Upgrading and Single Stage - One 16,735,000.8 Rehabilitation /upgrading of IDA / 51540 Rehabilitation of Rural Prior Request for Bids Open - National 13,451,885.00 Signed 2019-05-20 2019-04-22 2019-05-25 2019-07-24 2019-07-06 2019-06-10 2019-08-05 2019-10-02 2019-09-09 2019-10-15 2020-03-07 Envelope 0 361.7km length of rural Transport Infrastructure roads in Phase II NG-ADAMAWA RAMP- Upgrading and Under 97780-CW-RFQ / Access to Single Stage - One IDA / 51540 Rehabilitation of Rural Post Request for Bids Limited 286,484.00 0.00 Implementat 2019-04-15 2019-10-02 2019-04-20 2019-10-03 2019-06-01 2019-07-01 2019-08-05 2020-02-01 19No RC Kenya,Mbulirga Envelope Transport Infrastructure ion 11.6km (Lot 1) NG-ADAMAWA RAMP- 97779-CW-RFQ / Access to Upgrading and Under Single Stage - One 19No RC Dilwachira, IDA / 51540 Rehabilitation of Rural Post Request for Bids Limited 466,387.00 0.00 Implementat 2019-04-15 2019-10-02 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 Envelope Kwalita, Bolki-Dumne Transport Infrastructure ion 20.6km (Lot 2) NG-ADAMAWA RAMP- Upgrading and Under 97782-CW-RFQ / Access to Single Stage - One IDA / 51540 Rehabilitation of Rural Post Request for Bids Limited 171,145.00 0.00 Implementat 2019-04-15 2019-10-02 2019-04-20 2019-10-03 2019-06-01 2019-07-01 2019-08-05 2020-02-01 19No RC Shima, Kalambare Envelope Transport Infrastructure ion ,Dukkul 7.7km (Lot 3) NG-ADAMAWA RAMP- 97787-CW-RFQ / Re- Upgrading and Request for Single Stage - One construction/Rehabilitation of IDA / 51540 Rehabilitation of Rural Post Limited 402,117.00 322,751.49 Signed 2019-03-02 2019-02-11 2019-04-27 2019-04-05 2019-10-24 Quotations Envelope section of 4No road affected Transport Infrastructure by the 2018 flood NG-ADAMAWA RAMP- 17011-CW-RFB / Upgrading and Pending Rehabilitation /upgrading of Request for Single Stage - One IDA / 51540 Rehabilitation of Rural Post Limited 2,580,645.00 0.00 Implementat 2019-05-05 2019-06-30 2019-12-27 140 km length of rural Quotations Envelope Transport Infrastructure ion roads in three (3) lots under Phase 2 NG-ADAMAWA RAMP- 108292-CW-RFQ / Routine Community-based Road Pending Request for Single Stage - One maintenance of 201.4km of IDA / 51540 Maintenance and Annual Post Limited 193,975.00 0.00 Implementat 2019-04-05 2019-05-31 2019-11-27 Quotations Envelope rural roads in Adamawa Mechanized Maintenance ion State Page 2 NG-ADAMAWA RAMP- 47252-CW-RFQ / Routine Community-based Road Pending Request for Single Stage - One maintenance of 201.4km of IDA / 51540 Maintenance and Annual Post Limited 193,975.00 0.00 Implementat 2019-05-05 2019-06-30 2019-12-27 Quotations Envelope rural roads in Adamawa Mechanized Maintenance ion State NG-ADAMAWA RAMP- Community-based Road Pending 17041 / Construction of Single Stage - One IDA / 51540 Maintenance and Annual Post Request for Bids Open - National 1,608,040.00 0.00 Implementat 2019-03-31 2019-04-05 2019-05-17 2019-06-16 2019-07-21 2020-01-17 16No River Crossing across Envelope Mechanized Maintenance ion the State of Adamawa NG-ADAMAWA RAMP- 178758-CW-CDD / Community-based Road Community Pending Community Based IDA / 51540 Maintenance and Annual Post Driven Limited 207,161.11 0.00 Implementat 2020-06-30 2020-07-05 2020-08-16 2020-09-15 2020-10-20 2021-04-18 maintenance of 522.7km of Mechanized Maintenance Development ion rural roads in Adamawa State GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA RAMP- Project Management and 17016-GO-RFQ / Strengthening of State and Procurement of 6No laptops, Request for Single Stage - One IDA / 51540 Federal Road Sector Post Limited 8,065.00 8,786.25 Completed 2017-02-13 2017-02-13 2017-04-05 2017-02-13 2018-04-11 10No External Drive(500GB), Quotations Envelope Institutional, Policy and 1No A3 Printer, 2NoA4 Regulatory Framework printers NG-ADAMAWA RAMP- Project Management and 17023-GO-RFQ / Strengthening of State and Procurement of 2No Fire Request for Single Stage - One IDA / 51540 Federal Road Sector Post Limited 9,677.40 7,726.95 Completed 2017-02-06 2017-02-06 2017-12-12 2017-02-06 2018-01-18 proof file cabinet, 8No file Quotations Envelope Institutional, Policy and Cabinet, 3No tables, 8No Regulatory Framework Swive NG-ADAMAWA RAMP- Project Management and 17019-GO-RFQ / Strengthening of State and Procurement of 39 tri- Request for Single Stage - One IDA / 51540 Federal Road Sector Post Limited 87,097.00 80,279.72 Completed 2017-06-05 2017-06-05 2017-12-14 2017-06-05 2018-03-22 cycles, Shovels, Diggers, Quotations Envelope Institutional, Policy and Hand Rammers, Rainboot, Regulatory Framework Rain Coat NG-ADAMAWA RAMP- Project Management and 47199-GO-RFQ / Strengthening of State and Request for Single Stage - One Procurement of 1NO A3 IDA / 51540 Federal Road Sector Post Limited 21,875.00 19,206.21 Completed 2018-03-18 2018-04-19 2018-05-13 2018-05-18 2018-11-09 2018-05-22 Quotations Envelope Printer, Photocopy Machine Institutional, Policy and and anti virus software Regulatory Framework Project Management and NG-ADAMAWA RAMP- Strengthening of State and 47245-GO-RFQ / Request for Single Stage - One IDA / 51540 Federal Road Sector Post Limited 16,625.00 13,369.13 Completed 2018-03-12 2018-04-19 2018-05-07 2018-05-21 2018-11-03 2018-06-01 Procurement of 10No. Quotations Envelope Institutional, Policy and Laptops Regulatory Framework NG-ADAMAWA RAMP- 48447-GO-RFQ / Procurement of 20 tri-cycle , Project Management and shovels, diggers, had Strengthening of State and Pending Request for Single Stage - One rammers, boots, rain coat, IDA / 51540 Federal Road Sector Post Limited 62,500.00 0.00 Implementati 2018-03-10 2018-05-05 2018-11-01 Quotations Envelope wheel barrows, caution sign, Institutional, Policy and on reflective jacket, helmet, rain Regulatory Framework boot, cutlasses for maintenance team Page 3 NG-ADAMAWA RAMP- 97875-GO-RFP / Procurement Community-based Road Pending Request for Single Stage - One of 20 No tri-cycle , shovels, IDA / 51540 Maintenance and Annual Post Limited 76,452.00 0.00 Implementati 2019-07-03 2019-08-28 2020-02-24 Quotations Envelope diggers, had rammers, boots, Mechanized Maintenance on rain coat, wheel barrows etc Project Management and NG-ADAMAWA RAMP- Strengthening of State and Pending Request for Single Stage - One 97877-GO-RFQ / IDA / 51540 Federal Road Sector Post Limited 4,587.00 0.00 Implementati 2019-02-23 2019-04-20 2019-10-17 Quotations Envelope Procurement 4No Laptops Institutional, Policy and on Regulatory Framework Project Management and NG-ADAMAWA RAMP- Strengthening of State and 71825-GO-RFQ / Request for Single Stage - One IDA / 51540 Federal Road Sector Post Limited 312,500.00 242,327.04 Completed 2019-02-05 2018-07-16 2019-04-02 2018-08-06 2019-09-29 2018-09-26 Procurement 4No 4X4 Quotations Envelope Institutional, Policy and Hilux Regulatory Framework NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA RAMP- 16589-CS-QCBS / Detailed Engineering Design Studies Upgrading and for 300km of Prioritized Quality And Cost- Open - Under IDA / 51540 Rehabilitation of Rural Prior 1,000,000.00 0.00 2017-07-10 2017-07-31 2017-08-01 2017-09-13 2017-11-29 2017-10-11 2018-02-21 2017-11-10 2018-03-14 2017-12-15 2018-06-09 2018-01-19 2019-01-19 Roads and Supervision Based Selection International Implementation Transport Infrastructure Consultancy for Construction/Rehabilitation of 140km NG-ADAMAWA RAMP- 16878-CS-CQS / Engineering design study of the 16No Upgrading and Consultant Under River Crossings, IDA / 51540 Rehabilitation of Rural Post Qualification Open - National 114,829.00 0.00 2015-03-19 2014-11-13 2015-03-19 2015-03-19 2015-08-07 2015-03-19 2016-09-14 2015-03-19 2015-03-19 Implementation environmental and Transport Infrastructure Selection safeguards and other technical activities, NG-ADAMAWA RAMP- 17043-CS-QCBS / Upgrading and Quality And Cost- Open - Under Supervision of the IDA / 51540 Rehabilitation of Rural Prior 706,366.83 0.00 2013-02-12 2013-02-12 2013-02-12 2013-02-12 2013-02-12 2013-02-12 2013-02-12 2013-02-12 Based Selection International Implementation construction of 201.4km of Transport Infrastructure the designed Rural Roads in the 3 lots NG-ADAMAWA RAMP- Project Management and 17266-CS-CQS / Consultancy Strengthening of State and Consultant for rural roads inventories Open - Under IDA / 51540 Federal Road Sector Post Qualification 112,903.23 0.00 2016-09-27 2016-09-19 2016-09-27 2016-09-27 2017-01-10 2016-09-27 2017-03-21 2016-09-27 2016-09-27 and GIS based mapping International Implementation Institutional, Policy and Selection road asset management in Regulatory Framework the State NG-ADAMAWA RAMP- Project Management and 47200-CS-CQS / Consultancy Strengthening of State and Consultant for updating of GIS Pending IDA / 51540 Federal Road Sector Post Qualification Open - National 46,875.00 0.00 2018-09-28 2018-10-19 2018-12-02 2019-01-01 2019-02-05 2019-08-04 Database for Phase II Implementation Institutional, Policy and Selection RAMP roads in Adamawa Regulatory Framework State Page 4 NG-ADAMAWA RAMP- 47203-CS-CQS / Consultancy Upgrading and Consultant for the post documentary of Under IDA / 51540 Rehabilitation of Rural Post Qualification Open - National 46,875.00 0.00 2018-10-09 2018-04-17 2018-10-30 2018-08-06 2018-12-13 2018-12-18 2019-01-12 2019-02-16 2019-08-15 Phase I Roads, 19 No River Implementation Transport Infrastructure Selection Crossing and 300km rural rads in Phase II Project Management and NG-ADAMAWA RAMP- Strengthening of State and Consultant 97789-CS-CQS / Consultancy Pending IDA / 51540 Federal Road Sector Post Qualification Open - National 45,871.00 0.00 2019-06-03 2019-06-24 2019-08-07 2019-09-06 2019-10-11 2020-04-08 for socioeconomic basline of Implementation Institutional, Policy and Selection 2nd phase of rural roads Regulatory Framework NG-ADAMAWA RAMP- Project Management and 97793-CS-CQS / Technical Strengthening of State and Consultant Under Assistant (TA) for IDA / 51540 Federal Road Sector Post Qualification Open - National 18,348.00 0.00 2019-02-25 2019-01-02 2019-03-18 2019-05-01 2019-02-22 2019-05-31 2019-07-05 2020-01-01 Implementation Evironmental & safegaurd Institutional, Policy and Selection officers Regulatory Framework NG-ADAMAWA RAMP- 97887-CS-CQS / Technical Project Management and assistant (TA) on road asset Strengthening of State and Consultant management system Open - Pending IDA / 51540 Federal Road Sector Post Qualification 244,648.00 0.00 2019-06-26 2019-07-17 2019-08-30 2019-09-29 2019-11-03 2020-05-01 including planning and International Implementation Institutional, Policy and Selection maintenance policy and Regulatory Framework other studies/TA under the component INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA RAMP- Project Management and 16888-CS-INDV / Strengthening of State and Individual Under Revalidation/prioritization of IDA / 51540 Federal Road Sector Post Consultant Limited 71,664.32 0.00 2016-05-11 2016-01-25 2016-05-11 2016-05-11 2016-05-11 2016-05-11 Implementation 600km of rural roads in Institutional, Policy and Selection Adamawa State Regulatory Framework NG-ADAMAWA RAMP- 178754-CS-INDV / Upgrading and Individual Supervision of the Pending IDA / 51540 Rehabilitation of Rural Post Consultant Direct 16,666.67 0.00 2020-06-30 2020-07-10 2020-07-31 2020-09-04 2021-03-03 construction of 30km of Implementation Transport Infrastructure Selection Rural Roads in Madagali by Sapper Engineers Page 5