Public Disclosure Copy The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) Bihar Rural Roads Project (P155522) SOUTH ASIA | India | Transport & ICT Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 1 | ARCHIVED on 26-Apr-2017 | ISR27744 | Implementing Agencies: Key Dates Key Project Dates Bank Approval Date:21-Dec-2016 Effectiveness Date:-- Planned Mid Term Review Date:30-Apr-2020 Actual Mid-Term Review Date:-- Original Closing Date:31-Dec-2022 Revised Closing Date:31-Dec-2022 Project Development Objectives Project Development Objective (from Project Appraisal Document) The PDO is to improve rural road connectivity in project districts, and enhance management of rural roads in Bihar. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Rural Roads Improvement:(Cost $320.00 M) Asset Management and Institutional Effectiveness:(Cost $15.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  --  Satisfactory Overall Implementation Progress (IP)  --  Satisfactory Overall Risk Rating  --  Substantial Implementation Status and Key Decisions The Project is not yet effective. 4/26/2017 Page 1 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Moderate  --  Moderate Macroeconomic  Moderate  --  Moderate Sector Strategies and Policies  Moderate  --  Moderate Technical Design of Project or Program  Substantial  --  Substantial Institutional Capacity for Implementation and Sustainability  Substantial  --  Substantial Fiduciary  Moderate  --  Moderate Environment and Social  Moderate  --  Moderate Stakeholders  Moderate  --  Moderate Other  Low  --  Low Overall  Substantial  --  Substantial Results Project Development Objective Indicators PHINDPDOTBL  Increased road connectivity to habitations (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 60,280.00 -- -- 62,000.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. PHINDPDOTBL  Roads in good and fair condition as a share of total classified roads (Percentage, Core) Baseline Actual (Previous) Actual (Current) End Target 4/26/2017 Page 2 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) Value 40.00 -- -- 50.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. PHINDPDOTBL  Improved effectiveness of project expenditure - Project roads designed using cost-effective measures. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 50.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. PHINDPDOTBL  Improved asset management - number of districts that have developed and are using asset management system (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 10.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. Overall Comments Intermediate Results Indicators 4/26/2017 Page 3 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) PHINDIRITBL  Roads constructed, Rural (Kilometers, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 2,500.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. PHINDIRITBL  Improved quality of built Infrastructure - Project roads delivered with satisfactory quality certified through independent quality reviews (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 85.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. PHINDIRITBL  Length of roads subject to planned maintenance contracting (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4,600.00 -- -- 10,000.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. 4/26/2017 Page 4 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) PHINDIRITBL  Effective Citizen Feedback Mechanism (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 85.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. PHINDIRITBL  Road Safety improvement scheme related audits undertaken on priority roads (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 2,000.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. PHINDIRITBL  GIS based road and bridge inventory and condition database (including videography) established in project districts (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 50.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. 4/26/2017 Page 5 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) PHINDIRITBL  Network level climate vulnerability assessment undertaken with special focus on floods (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 2,000.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. PHINDIRITBL  RWD staff received at least six (6) weeks of professional training during the entire project duration. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 400.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. PHINDIRITBL  Gender-based capacity enhancement (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 30.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. 4/26/2017 Page 6 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) PHINDIRITBL  Direct project beneficiaries (Number, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 1,200,000.00 Date 30-Sep-2016 -- -- 30-Sep-2022 Comments The project is not yet effective. The actual results are yet to be measured. PHINDIRITBL  Female beneficiaries (Percentage, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 48.00 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed Not P155522 IDA-59380 USD 235.00 235.00 0.00 0.00 235.00 0% Effective Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date Not P155522 IDA-59380 21-Dec-2016 -- -- 31-Dec-2022 31-Dec-2022 Effective Cumulative Disbursements 4/26/2017 Page 7 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Bihar Rural Roads Project (P155522) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 4/26/2017 Page 8 of 8 Public Disclosure Copy