        The World Bank                                                                           Implementation Status & Results Report
        Ghana---Social Opportunities Project (P115247)


Ghana---Social Opportunities Project (P115247)

AFRICA | Ghana | Social Protection & Labor Global Practice |
IBRD/IDA | Specific Investment Loan | FY 2010 | Seq No: 13 | ARCHIVED on 17-May-2017 | ISR27543 |


Implementing Agencies:




Key Dates

  Key Project Dates

  Bank Approval Date:20-May-2010                                            Effectiveness Date:19-Oct-2010
  Planned Mid Term Review Date:12-Feb-2014                                  Actual Mid-Term Review Date:12-Feb-2014
  Original Closing Date:30-Jun-2016                                         Revised Closing Date:30-Jun-2017




Project Development Objectives

 Project Development Objective (from Project Appraisal Document)
 The objectives of the Project are to improve targeting in social protection spending, increase access to conditional cash transfers nationwide,
 increase access to employment and cash-earning opportunities for the rural poor during the agricultural off-season, and improve economic and
 social infrastructure in target districts.

 Has the Project Development Objective been changed since Board Approval of the Project Objective?
 Yes

 Board Approved Revised Project Development Objective (If project is formally restructured)PHRPDODEL
 The Project Development Objectives (PDO) of this Additional Financing is to improve targeting of social protection programs and provide income
 support to poor households through LEAP grants and LIPW infrastructure in targeted districts.




Components

Name
Component One: Social Protection Policy and Systems Strengthening:(Cost $9.00 M)
Component Two: Labor Intensive Public Works Implementation and Capacity Building.:(Cost $19.20 M)
Component Three: Livelihood Empowerment Against Poverty Implementation and Capacity Building:(Cost $15.70 M)
Component Four: Project Management and Coordination:(Cost $6.10 M)



Overall Ratings
Name                                                                      Previous Rating                         Current Rating

Progress towards achievement of PDO                                        Satisfactory                           Satisfactory


5/17/2017                                                                                                                           Page 1 of 12
                                                         Public Disclosure Copy
                                                           Public Disclosure Copy

        The World Bank                                                                               Implementation Status & Results Report
        Ghana---Social Opportunities Project (P115247)


Overall Implementation Progress (IP)                                         Satisfactory                             Satisfactory
Overall Risk Rating                                                          Low                                      Low


Implementation Status and Key Decisions

 The follow key activities and achievements were made during this ISR period:
 Project Component One: Social Protection Policy and Systems Strengthening. As part of system’s strengthening the Social Protection Directorate
 of the Ministry of Gender, Children and Social Protection, which leads the effort to coordinate and monitor Social protection efforts in Ghana has been
 fully staffed and has facilitated two National Social Protection Dialogues and 4 Social Protection Sector Working Groups which bring together key
 stakeholders within the SP sector. The Directorate has also begun to design a Monitoring and Evaluation Framework for Social Protection.
 The development of the Social Protection Implementation plan is underway and is expected to be completed by June 30, 2017. The draft Social
 Protection Bill was submitted to the Attorney General’s office in September 2016 and awaits final comments prior to being submitted to Parliament by
 June 30, 2017.
 A Single-Window case management system has been proposed for the five SP flagship interventions – the Livelihood Empowerment Against Poverty
 (LEAP) cash transfers program, the Labor-Intensive Public Works (LIPW) program, Ghana School Feeding Program (GSPS), Education Capitation
 Grant and the National Health Insurance Authority. The idea is to reduce the burden on the beneficiaries in terms of their ability to make complaints or
 ask questions about the SP programs, as well as update their family circumstances. Additionally, given that these interventions, for the most part, serve
 the same client, a common case management system reduces duplication and provides cost and operational efficiencies. As a first step, a concept note
 has been developed after consultations with call center service providers to develop a call center that will service beneficiaries for these interventions.
 Two toll-free hotline numbers have already been purchased. The call center is expected to be launched by June 30, 2017.
 Data collection for the Ghana National Household Registry (GNHR) was completed for 131,684 households in the Upper West Region by
 December 3, 2016. While data cleaning and analysis is being finalized, preliminary results indicate that approximately 57% of the households have been
 categorized as extreme poor, 23% poor, and 20% non-poor. Preparations are underway to collect data in the Upper East Region slated to begin in May
 2017. The development of data sharing protocols are underway, and once approved data will be shared beginning with the LEAP program by May 2017.
 The GNHR is also re-engaging with the National Identification Authority to discuss ways in which the two organizations can collaborate on the collection
 of biometric data.
 Project Component Two: Labor Intensive Public Works Implementation and Capacity Building. Since project inception, 166,725 unskilled
 persons have been employed out of which 60.9 percent are women A total of 615 subprojects have been completed with 11,644,043 person-days
 employment provided that has yielded an average earning of GHc451 per unskilled worker since inception. A total of 52 coaches, 183 client
 supervisors, 284 small scale construction firms, 673 contractor supervisors, and 179 Climate Change Focal Persons have been trained. LIPW
 practitioners’ manuals for small-earth-dams and dugouts and for feeder roads have been published and distributed. A total of 623 subprojects have
 been completed to date, comprising 110 climate change adaptation projects, 251 feeder roads, 214 small earth dams and dugouts and 40 social
 infrastructure projects.
 Project Component Three: Livelihood Empowerment Against Poverty (LEAP) Implementation and Capacity Building. The number of registered
 households from all districts in the country at the end of December 2016 was 213,048 made up of 943,842 direct beneficiaries with 56% female. The
 program disbursed cash grants to 212,919 households in November 2016 using the Ghana Interbank Payment and Settlement Systems (GhIPSS)
 electronic payment platform. The program also engaged stakeholders to review the Independent Monitoring Checks tools to reflect the current status
 (electronic) of the LEAP program. The objective of the IMC is to generate data on LEAP beneficiary’s satisfaction and understanding of the program by
 various stakeholders.
 Project component four: Project Management and Coordination. Monitoring and supervision visits were on-going throughout the period and
 technical reviews provided feedback to improve implementation. Closer process monitoring and reviews, and a shift towards electronic payments were
 pursued to enhance achievements of component objectives. Community Focal Persons were appointed and trained to facilitate speedy and transparent
 resolution of complaints and grievances at the local level. Major procurement activities were under the GNHR, including pickups, motorbikes, laptops,
 furniture. Additionally, assorted office supplies were procured for the SP directorate to enhance their program monitoring. By December 2016, a total of
 US$102,252,064.50 representing 73.77 percent of the total credit proceeds of US$ 138,600,000.00 had been spent.




5/17/2017                                                                                                                                Page 2 of 12
                                                           Public Disclosure Copy
                                                Public Disclosure Copy

        The World Bank                                                   Implementation Status & Results Report
        Ghana---Social Opportunities Project (P115247)




5/17/2017                                                                                            Page 3 of 12
                                                Public Disclosure Copy
                                                          Public Disclosure Copy

               The World Bank                                                                      Implementation Status & Results Report
               Ghana---Social Opportunities Project (P115247)




Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                             Rating at Approval              Previous Rating            Current Rating

 Political and Governance                                   --                             Moderate                  Moderate
 Macroeconomic                                              --                             Substantial               Substantial
 Sector Strategies and Policies                             --                             Low                       Low
 Technical Design of Project or Program                     --                             Low                       Low
 Institutional Capacity for Implementation and
 Sustainability
                                                            --                             Moderate                  Moderate
 Fiduciary                                                  --                             Low                       Low
 Environment and Social                                     --                             Low                       Low
 Stakeholders                                               --                             Low                       Low
 Other                                                      --                             Low                       Low
 Overall                                                    --                             Low                       Low


Results

 Project Development Objective Indicators
 PHINDPDOTBL




          Beneficiaries of social safety net programs (Number, Corporate)


                                            Baseline                   Actual (Previous)           Actual (Current)           End Target

         Value                              0.00                       778,729.00                  1,110,567.00               390,000.00

         Date                               05-Mar-2010                30-Jun-2016                 30-Dec-2016                30-Jun-2017


         Comments

5/17/2017                                                                                                                             Page 4 of 12
                                                          Public Disclosure Copy
                                                              Public Disclosure Copy

               The World Bank                                                                         Implementation Status & Results Report
               Ghana---Social Opportunities Project (P115247)



         LEAP targets households, but also collects information on number of individuals within the household. Therefore currently LEAP has
         213,000 households representing 943,842 individuals. LIPW targets individuals.




 PHINDPDOTBL




          Beneficiaries of Safety Nets programs - Female (number) (Number, Custom Breakdown)


                                               Baseline                     Actual (Previous)          Actual (Current)           End Target

         Value                                 0.00                         446,200.00                 611,220.00                 253,500.00

         Date                                  05-Mar-2010                  30-Jun-2016                30-Dec-2016                30-Jun-2017


 PHINDPDOTBL




      Beneficiaries of Safety Nets programs - Cash-for-work, food-for-work and public works (number) (Number, Custom
     Breakdown)

                                               Baseline                     Actual (Previous)          Actual (Current)           End Target

         Value                                 0.00                         160,627.00                 166,725.00                 190,000.00

         Date                                  05-Mar-2010                  30-Jun-2016                30-Dec-2016                30-Jun-2017


 PHINDPDOTBL




          Direct project beneficiaries (Number, Custom)


                                               Baseline                     Actual (Previous)          Actual (Current)           End Target

         Value                                 0.00                         778,729.00                 1,110,567.00               390,000.00

         Date                                  20-May-2010                  30-Jun-2016                30-Dec-2016                30-Jun-2017


         Comments
         LEAP targets households, but also collects information on number of individuals within the household. Therefore currently LEAP has
         213,000 households representing 943,842 individuals. LIPW targets individuals.




 PHINDPDOTBL




          Female beneficiaries (Percentage, Custom Supplement)




5/17/2017                                                                                                                                Page 5 of 12
                                                              Public Disclosure Copy
                                                                 Public Disclosure Copy

               The World Bank                                                                                Implementation Status & Results Report
               Ghana---Social Opportunities Project (P115247)




                                                 Baseline                        Actual (Previous)           Actual (Current)              End Target

         Value                                   0.00                            59.00                       55.00                         65.00




 PHINDPDOTBL




          Direct project beneficiaries under cash transfer component (Number, Custom Breakdown)


                                                 Baseline                        Actual (Previous)           Actual (Current)              End Target

         Value                                   0.00                            618,102.00                  943,842.00                    200,000.00

         Date                                    20-May-2010                     30-Jun-2016                 30-Dec-2016                   30-Jun-2017


 PHINDPDOTBL




          Direct project beneficiaries under LIPW component (Number, Custom Breakdown)


                                                 Baseline                        Actual (Previous)           Actual (Current)              End Target

         Value                                   0.00                            160,627.00                  166,725.00                    190,000.00

         Date                                    20-May-2010                     30-Jun-2016                 30-Dec-2016                   30-Jun-2017


 PHINDPDOTBL




          Average annual earnings of unskilled workers in LIPWs (cedi) (Number, Custom)


                                                 Baseline                        Actual (Previous)           Actual (Current)              End Target

         Value                                   0.00                            242.00                      458.90                        200.00

         Date                                    20-May-2010                     30-Jun-2016                 30-Dec-2016                   30-Jun-2017


         Comments
         This indicator is calculated as the total earnings of all Beneficiaries within the specified period - in this instance, January 1, 2016 through
         December 31, 2016, divided by the total number of persons whose names appeared in the payroll.




 PHINDPDOTBL




          Person days of unskilled workers (Number, Custom)




5/17/2017                                                                                                                                           Page 6 of 12
                                                                 Public Disclosure Copy
                                                                Public Disclosure Copy

               The World Bank                                                                             Implementation Status & Results Report
               Ghana---Social Opportunities Project (P115247)



                                                Baseline                       Actual (Previous)          Actual (Current)             End Target

         Value                                  0.00                           10,075,756.00              11,644,043.00                9,500,000.00

         Date                                   20-May-2010                    30-Jun-2016                30-Dec-2016                  30-Jun-2017


         Comments
         This indicator is calculated as the total count of person days of all unskilled beneficiaries under LIPW. A person day is defined as assigned
         task completed within a 6-hour day.




 PHINDPDOTBL




      Potential and actual beneficiaries in participating districts satisfied with subprojects, LIPW program and LEAP transfers (%)
     (Percentage, Custom)

                                                Baseline                       Actual (Previous)          Actual (Current)             End Target

         Value                                  0.00                           78.00                      78.00                        70.00

         Date                                   20-May-2010                    30-Jun-2016                30-Dec-2016                  30-Jun-2017


         Comments
         This indicator reported is only in relation to LIPW based on findings from the June 2016 independent Impact Evaluation Study by ISSER.
         The measurement is for actual beneficiary satisfactory results.




 PHINDPDOTBL




      Share of beneficiaries from the poorest 20% of population for LEAP and poorest 30% of the population for LIPW. (Percentage,
     Custom)

                                                Baseline                       Actual (Previous)          Actual (Current)             End Target

         Value                                  40.00                          86.90                      86.90                        50.00

         Date                                   31-Mar-2014                    30-Jun-2016                30-Dec-2016                  30-Jun-2017




 Overall Comments
 Note that data on the share of beneficiaries from the poorest 20% of population for LEAP and poorest 30% of the population for LIPW are
 reported separately, with break downs as follows: LIPW 30%: 86.9 (source ISSER June 2016 Independent Impact Assessment) and LEAP 20%:
 46.3 (Ning Report). The LIPW indicator is reported.




 Intermediate Results Indicators


5/17/2017                                                                                                                                      Page 7 of 12
                                                                Public Disclosure Copy
                                                                      Public Disclosure Copy

                   The World Bank                                                                               Implementation Status & Results Report
                   Ghana---Social Opportunities Project (P115247)

 PHINDIRITBL




              Targeting performance (share of LEAP beneficiaries from the poorest 20% of population) (Percentage, Custom)

                                                      Baseline                       Actual (Previous)          Actual (Current)             End Target

               Value                                  19.00                          46.30                      46.30                        50.00

               Date                                   31-Mar-2014                    30-Jun-2016                30-Dec-2016                  30-Jun-2017




 PHINDIRITBL




              Enrolled beneficiaries in the districts where LEAP pilot will be intensified (% increase) (Number, Custom)

                                                      Baseline                       Actual (Previous)          Actual (Current)             End Target

               Value                                  100.00                         507.00                     516.45                       270.00

               Date                                   20-May-2010                    30-Jun-2016                30-Dec-2016                  30-Jun-2017


               Comments
               There were 21 pilot districts in 2010. The number of beneficiaries was 1,654, representing 100%, the baseline. The number of beneficiaries
               as of December 2016 are 37,277, which represents 2,253.74%. Although 21 districts have been split (Now 30 districts), the geographic
               locations remain the same.




 PHINDIRITBL




              LEAP administrative costs compared to total costs (Percentage, Custom)

                                                      Baseline                       Actual (Previous)          Actual (Current)             End Target

               Value                                  15.00                          12.00                      12.00                        11.00

               Date                                   30-Sep-2013                    30-Jun-2016                30-Dec-2016                  30-Jun-2017




 PHINDIRITBL




              Total unskilled worker earnings as share of LIPW cost (Percentage, Custom)

                                                      Baseline                       Actual (Previous)          Actual (Current)             End Target

               Value                                  40.00                          58.00                      53.00                        62.00

               Date                                   20-May-2010                    30-Jun-2016                30-Dec-2016                  30-Jun-2017


               Comments
               This indicator measures the labor content, which is the total cost of unskilled labor for all subprojects under LIPW, expressed as a


5/17/2017                                                                                                                                             Page 8 of 12
                                                                      Public Disclosure Copy
                                                              Public Disclosure Copy

                   The World Bank                                                              Implementation Status & Results Report
                   Ghana---Social Opportunities Project (P115247)



               percentage of the total cost.




 PHINDIRITBL




            Original name: Maintenance program established for roads and dams. Revised name: District Assemblies with maintenance
           programs established for completed sub-projects (number) (Number, Custom)

                                                Baseline                   Actual (Previous)   Actual (Current)      End Target

               Value                            10.00                      10.00               31.00                 60.00

               Date                             20-May-2010                31-Dec-2015         30-Dec-2016           30-Jun-2017



 PHINDIRITBL




            Original name: Rehabilitated dams inspected annually by communities for dam safety concerns. Revised name: Completed
           subprojects inspected annually by Communities (under spn of district tech. spc). (Percentage, Custom)

                                                Baseline                   Actual (Previous)   Actual (Current)      End Target

               Value                            50.00                      51.00               62.00                 90.00

               Date                             20-May-2010                30-Jun-2016         30-Dec-2016           30-Jun-2017



 PHINDIRITBL




              Roads rehabilitated, Rural (Kilometers, Custom)

                                                Baseline                   Actual (Previous)   Actual (Current)      End Target

               Value                            0.00                       744.00              936.12                700.00

               Date                             20-May-2010                30-Jun-2016         30-Dec-2016           30-Jun-2017




5/17/2017                                                                                                                     Page 9 of 12
                                                              Public Disclosure Copy
                                                             Public Disclosure Copy

                  The World Bank                                                                  Implementation Status & Results Report
                  Ghana---Social Opportunities Project (P115247)

 PHINDIRITBL




              Payments to workers under LIPW program made within 20 days after the attendance at work sites (Percentage, Custom)

                                               Baseline                   Actual (Previous)         Actual (Current)       End Target

               Value                           0.00                       70.00                     66.67                  80.00

               Date                            20-May-2010                30-Jun-2016               30-Dec-2016            30-Jun-2017




 PHINDIRITBL




            Original name: Payments made to contractors after receipt of performance security. Revised name: Avg time lapse between
           submission of interim certificate by LIPW contractors and payments by DAs (Percentage, Custom)

                                               Baseline                   Actual (Previous)         Actual (Current)       End Target

               Value                           30.00                      --                        35.00                  20.00

               Date                            30-Sep-2013                31-Dec-2015               30-Dec-2016            30-Jun-2017



 PHINDIRITBL




            Original name: Working group to set priorities for social protection indicators to be set under MoFEP leadership. Revised
           name: Social Protection Policy drafted by MoGCSP and submitted to cabinet (Yes/No, Custom)

                                               Baseline                   Actual (Previous)         Actual (Current)       End Target

               Value                           N                          Y                         Y                      Y

               Date                            20-May-2010                30-Jun-2016               30-Dec-2016            30-Jun-2017



 PHINDIRITBL




              Area Planted for Fruit Trees and Multi-Purpose Woodlots (ha) (Hectare(Ha), Custom)

                                               Baseline                   Actual (Previous)         Actual (Current)       End Target

               Value                           672.00                     2,140.40                  2,166.40               2,360.00

               Date                            31-Mar-2014                30-Jun-2016               30-Dec-2016            30-Jun-2017




5/17/2017                                                                                                                          Page 10 of 12
                                                             Public Disclosure Copy
                                                                  Public Disclosure Copy

                  The World Bank                                                                         Implementation Status & Results Report
                  Ghana---Social Opportunities Project (P115247)

 PHINDIRITBL




              Small earth dams and dug-outs rehabilitated (number) (Number, Custom)

                                                    Baseline                   Actual (Previous)         Actual (Current)             End Target

               Value                                62.00                      184.00                    214.00                       300.00

               Date                                 31-Mar-2014                30-Jun-2016               30-Dec-2016                  30-Jun-2017




 PHINDIRITBL




              Private contractors techically capable of implementing and supervising LIPW. (Percentage, Custom)

                                                    Baseline                   Actual (Previous)         Actual (Current)             End Target

               Value                                74.00                      284.00                    284.00                       125.00

               Date                                 31-Mar-2014                30-Jun-2016               30-Dec-2016                  30-Jun-2017




 Overall Comments




 Data on Financial Performance

Disbursements (by loan)

 Project               Loan/Credit/TF   Status        Currency      Original   Revised     Cancelled    Disbursed      Undisbursed                  Disbursed

 P115247               IDA-47350        Effective     XDR             58.40      58.40           0.00         58.40            0.00                     100%

 P115247               IDA-54660        Effective     XDR             32.40      32.40           0.00         21.89           10.51                        68%


Key Dates (by loan)
 Project               Loan/Credit/TF   Status        Approval Date    Signing Date      Effectiveness Date    Orig. Closing Date     Rev. Closing Date

 P115247               IDA-47350        Effective     20-May-2010      08-Sep-2010       19-Oct-2010           30-Jun-2016            30-Jun-2017
 P115247               IDA-54660        Effective     27-May-2014      10-Apr-2015       28-May-2015           30-Jun-2017            30-Jun-2017



Cumulative Disbursements




5/17/2017                                                                                                                                  Page 11 of 12
                                                                  Public Disclosure Copy
                                                Public Disclosure Copy

        The World Bank                                                   Implementation Status & Results Report
        Ghana---Social Opportunities Project (P115247)




 Restructuring History

 There has been no restructuring to date.