Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: agreed upon at appraisal 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: first 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1000,000 First three packages 2. NCB (Goods) Above US$ 100,000 First contract 5. (Non-Consultant Services) Below US$ 1000,000 First three packages [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) G.Sev Several IT 1.35 No Prior (Goods) eral equipment million packages for establishin g Consumer Departmen t and Microfinan ce Unit III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 0.2 Million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million C.IND.Seve Several 0.25 1 Post ral Contracts million supporting developmen t of the institutional framework for microfinance C.QCBS.2 Enhance 0.35 1 Prior consumer million protection mechanism PROCUREMENT Egypt, Arab Republic of : Inclusive Regulations for Microfinance PLAN General Information Country: Egypt, Arab Republic of Bank’s Approval Date of the Original Procurement Plan: 2017-06-20 2021-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149677 GPN Date: Project Name: Inclusive Regulations for Microfinance Loan / Credit No: TF / 17864 Egyptian Financial Supervisory Authority Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FRA-18 / Update of the Personnel and Payroll Program TF / 17864 Post Direct Selection Direct 3,821.66 Completed 2018-09-30 2018-10-01 2018-11-13 2018-11-13 2018-12-02 2018-12-30 2021-12-01 2019-01-01 (HITS DNA) FRA-19 / Update the electronic archive program TF / 17864 Post Direct Selection Direct 1,751.59 Completed 2018-09-30 2018-10-01 2018-11-12 2018-11-13 2018-12-02 2018-12-30 2021-12-01 2019-03-03 (JUPITER) FRA-GO-SH-1 / Tech. facilities & Supplies ( Request for Single Stage - One TF / 17864 Post Limited 30,249.30 Completed 2019-05-01 2019-06-09 2019-06-05 2019-07-25 2019-12-02 2019-07-29 Conference System) for the Quotations Envelope new training center FRA-GO-SH-3 / Tech. facilities & Supplies ( Sound Request for Single Stage - One TF / 17864 Post Limited 12,377.93 Completed 2019-04-28 2019-06-09 2019-06-02 2019-07-28 2019-11-29 2019-07-31 Systems) for the new training Quotations Envelope center FRA-GO-SH-4 / Tech. facilities & Supplies ( Projector Request for Single Stage - One TF / 17864 Post Limited 30,543.42 Completed 2019-05-01 2019-06-09 2019-06-12 2019-06-26 2019-12-09 2019-07-11 System) for the new training Quotations Envelope center FRA-GO-SH-2 / MIS Software, Design and Single Stage - Two Implementation of EFSA TF / 17864 Post Request for Bids Limited 6,138.11 Completed 2016-03-01 2016-04-21 2016-10-24 2016-10-24 2016-12-21 2016-12-21 2017-05-23 2017-05-23 2017-06-22 2017-06-22 2019-09-30 2018-01-18 Envelope Microfinance Information and Reporting System FRA-GO-SH-5 / Furnitures Request for Single Stage - One TF / 17864 Post Limited 0.00 Canceled 2019-04-23 2019-05-30 2019-11-26 for the new training center Quotations Envelope EG-FRA-119037-GO-RFQ / Financial Inclusion Training Request for Single Stage - One Center Main Display Screen TF / 17864 Post Limited 80,000.00 Completed 2019-06-16 2019-06-16 2019-07-04 2019-07-07 2019-07-07 2019-07-11 Quotations Envelope with Video signal cabling & installation accessories FRA- GO-45 / FRA BACKUP INFRASTRUCTURE SOLUTIONS TF / 17864 Post Direct Selection Direct 0.00 Canceled 2020-04-13 2020-04-07 2020-04-15 2020-04-09 2020-04-19 2020-07-03 SYSTEM (Verits) FRA- GO-46 / RAM FOR Request for Single Stage - One TF / 17864 Post Limited 2,678.93 Completed 2020-05-25 2020-06-25 2020-06-30 2020-07-09 2020-12-27 2020-07-21 UPGRADING DELL SERVERS Quotations Envelope FRA-GO-49 / FRA BACKUP Single Stage - One INFRASTRUCTURE SOLUTIONS TF / 17864 Post Request for Bids Open - National 0.00 Canceled 2020-08-25 2020-08-30 2020-10-11 2020-11-10 2020-12-15 2021-06-13 Envelope SYSTEM NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LEASE-001 / Rent premises TF / 17864 Prior Direct Selection Direct 78,085.99 Signed 2015-04-01 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Consultant IC/EFSA/2015 / procurement TF / 17864 Prior Qualification Open - International 10,000.00 Terminated 2015-08-06 2015-08-10 consultant Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FRA-CS-INDV-25 / Mohamed Individual Mohamed Taha, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-25 2018-12-16 2019-08-01 2018-12-23 2018-12-23 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist Page 1 FRA-CS-INDV-26 / Hossam Individual Fathy Gamal El Din, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-23 2018-12-06 2018-12-23 2018-12-16 2019-01-01 2018-12-30 2020-06-30 Junior Inspections & Selection Compliance Specialist FRA-CS-INDV-27 / Reem Individual Issam Mohammed, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2018-12-30 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-28 / Sarah Individual Mohamed Morsy, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-06 2018-12-23 2018-12-23 2019-01-01 2018-12-31 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-29 / Hoda Individual Abdel-Hamid Hermach, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-16 2018-12-16 2018-12-24 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-30 / Individual Mohammed Ramadan Abdul TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2018-12-30 2020-06-30 Aziz, FRA's Inspections & Selection Compliance Specialist FRA-CS-INDV-31 / Mostafa Individual Said Ibrahim, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2019-10-06 2018-12-23 2018-12-23 2019-01-01 2018-12-31 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-32 / Amira Individual Karam Sabbak, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-06 2018-12-23 2018-12-16 2018-12-30 2018-12-31 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-33 / Individual Mohammed Reza Mohammed, TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2019-01-01 2020-06-30 FRA's Inspections & Selection Compliance Specialist Individual FRA-CS-INDV-34 / Mirna TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-16 2018-12-23 2018-12-23 2019-01-01 2019-01-01 2020-06-30 Ashraf Fathi Selection FRA-CS-INDV-35 / Fatima Individual Mohammed Jaber, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-16 2018-12-16 2018-12-16 2018-12-23 2018-12-23 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-36 / Amira Individual Fawzi Mohamed, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-16 2018-12-23 2018-12-23 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-37 / Alaa Individual Nasser Sayed, FRA's TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-06 2018-12-23 2018-12-19 2019-01-01 2018-12-31 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-38 / Bassam Individual Hussam El - Din Abdel - TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2018-12-31 2020-06-30 Hamd, FRA's Inspections & Selection Compliance Specialist FRA-CS-INDV-39 / Samar Individual Ibrahim Hefnawi, Junior TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-20 2018-12-20 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-40 / Israa Individual Abdel Azim Ahmed, Junior TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2018-12-31 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-41 / Fatima Al- Individual Zahra Abd Al-Badea, Junior TF / 17864 Post Consultant Limited 6,140.00 Completed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-12 2018-12-16 2019-01-01 2018-12-30 2020-06-30 2021-03-01 Inspections & Compliance Selection Specialist FRA-CS-INDV-42 / Shadwa Individual Alaa Eddin Mahmoud, Junior TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2019-01-01 2020-06-30 Inspections & Compliance Selection Specialist FRA-CS-INDV-43 / Aya Ali Individual Mohamed, Junior Inspections TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-16 2019-01-01 2019-01-01 2020-06-30 & Compliance Specialist Selection FRA-CS-INDV-44 / Sarah Individual Kamal Riad, Junior Inspections TF / 17864 Post Consultant Limited 6,140.00 Signed 2018-12-02 2018-12-02 2018-12-07 2018-12-06 2018-12-16 2018-12-07 2019-01-01 2018-12-31 2020-06-30 & Compliance Specialist Selection FRA-CS-INDV-1 / MF Project Individual deputy Manager (Ahmed TF / 17864 Post Consultant Limited 4,758.26 Signed 2016-08-01 2016-08-01 2016-08-06 2016-08-06 2016-08-21 2016-08-21 2016-09-01 2016-09-01 2020-06-30 Hussein Abdelgawad) Selection FRA-CS-INDV-4 / Specialist Individual of Analysis and Control TF / 17864 Post Consultant Limited 2,647.72 Signed 2015-06-01 2015-06-01 2015-06-06 2015-06-06 2015-06-16 2015-06-16 2015-07-12 2015-07-12 2020-06-30 (Ahmed Mohamed Ahmed Selection Abdel Aati) FRA-CS-INDV-5 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 2,283.61 Completed 2015-09-22 2015-09-22 2015-09-27 2015-09-27 2015-10-18 2015-10-18 2015-11-11 2015-11-11 2020-06-30 2019-10-31 Specialist (Hassan Mohamed Selection Abdel Latif Hassan) FRA-CS-INDV-6 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 1,734.26 Signed 2016-07-03 2016-07-03 2016-07-08 2016-07-08 2016-07-29 2016-07-29 2016-09-01 2016-09-01 2017-02-28 Specialist (Anas Sobhy Ahmed Selection El-Erian) Page 2 FRA-CS-INDV-7 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 1,737.53 Signed 2016-07-03 2016-07-03 2016-07-08 2016-07-08 2016-07-29 2016-07-29 2016-09-01 2016-09-01 2020-06-30 Specialist (Hisham Abdel- Selection Maleem Abdel-Kareem) FRA-CS-INDV-8 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 776.72 Signed 2018-10-01 2018-10-01 2018-10-06 2018-10-06 2018-10-16 2018-10-16 2018-11-01 2018-11-01 2020-06-30 Specialist (Mina Reda Nassif) Selection FRA-CS-INDV-9 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 1,040.39 Completed 2017-11-07 2017-11-07 2017-11-12 2017-11-12 2017-12-03 2017-12-03 2018-01-15 2018-01-15 2020-06-30 2019-12-31 Specialist (Assem Eid Selection Mahmoud) FRA-CS-INDV-10 / training Individual and awareness Specialist TF / 17864 Post Consultant Limited 962.94 Signed 2017-12-11 2017-12-11 2017-12-16 2017-12-07 2018-01-06 2018-01-06 2018-02-01 2018-02-01 2020-06-30 (Safaa Mohamed Abdoun Selection Hussein) FRA-CS-INDV-11 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 815.05 Signed 2018-05-27 2018-05-27 2018-06-01 2018-05-30 2018-06-17 2018-06-17 2018-07-01 2018-07-01 2020-06-30 Specialist (Abbas Abdel Selection Moneim Abbas Al - Saidi) FRA-CS-INDV-12 / Individual Compliance & Inspection TF / 17864 Post Consultant Limited 985.18 Signed 2018-02-01 2018-02-01 2018-02-06 2018-02-06 2018-02-19 2018-02-19 2018-03-01 2018-03-01 2020-06-30 Specialist (Mohammed Ayman Selection Kamal Al - Kurdi) FRA-CS-INDV-13 / Individual Procurment & Adm Specialist TF / 17864 Post Consultant Limited 7,000.00 Signed 2019-01-01 2019-01-01 2019-01-06 2019-01-08 2019-01-15 2019-01-15 2019-02-01 2019-02-01 2020-06-30 (Mohamed Nabil Zaki) Selection FRA-CS-INDV-14 / Individual Administrative Affairs Clerck TF / 17864 Post Consultant Limited 1,070.08 Signed 2015-02-26 2015-02-26 2015-03-03 2015-03-03 2015-03-24 2015-03-24 2015-04-26 2015-04-26 2020-06-30 (Hashem Ahmed Hashim) Selection FRA-CS-INDV-15 / Support Individual Services Assitant (Abdullah TF / 17864 Post Consultant Limited 540.00 Signed 2016-08-01 2016-08-01 2016-08-06 2016-08-07 2016-08-16 2016-08-16 2016-09-19 2016-10-19 2020-06-30 Abdulrahman Mohammed Al - Selection Sadawi) FRA-CS-INDV-16 / Support Individual Services Assitant (Alaa TF / 17864 Post Consultant Limited 640.00 Signed 2016-08-01 2016-08-01 2016-08-06 2016-08-07 2016-08-27 2016-09-11 2016-09-19 2016-09-19 2020-06-30 mahmood mahmood) Selection FRA-CS-INDV-17 / Support Individual Services Assitant (Mohammed TF / 17864 Post Consultant Limited 540.00 Signed 2016-08-01 2016-08-01 2016-08-06 2016-08-07 2016-08-27 2016-08-27 2016-09-19 2016-10-19 2020-04-30 Jnaidi Jad Amira) Selection FRA-CS-INDV-18 / M&E Individual Specialist (Ms. Sara TF / 17864 Post Consultant Limited 3,433.77 Signed 2017-10-01 2017-10-01 2017-10-06 2017-10-06 2017-10-16 2017-10-16 2017-11-01 2017-11-01 2020-06-30 Eldegheidi) Selection FRA-CS-CDS-1 / Senior Advisor Microfinance TF / 17864 Post Direct Selection Direct 2,158.73 Signed 2014-11-15 2014-11-15 2014-11-25 2014-11-25 2015-01-01 2015-01-01 2015-12-31 Regulatory Framework (Mr. Abdel Hamid Ibrahim) FRA-CS-CDS-11 / Insurance Advisor (Mr. Hesham Ibrahim) TA under our MF Project to cover specifically the insurance sector. EFSA TF / 17864 Post Direct Selection Direct 2,178.27 Completed 2017-10-01 2017-10-01 2017-10-11 2017-10-14 2017-10-27 2017-10-26 2017-12-31 2021-01-21 currently needs to work on the following: • Drafting a new insurance law taking into consideration all the recent developments FRA-CS-CDS-2 / FRA's Advisor for legislation and TF / 17864 Post Direct Selection Direct 191.69 Signed 2017-10-01 2017-10-01 2017-10-15 2017-10-15 2017-11-01 2017-11-01 2018-12-31 drafting of lawsJudge (Mr. Mohamed Abed Elkerim) FRA-CS-CDS-3 / Consumer Protection Advisor (Dr. Shahira Fawzy) Local consulatnt under MF project for the Consumer Protection to guidance FRA TF / 17864 Post Direct Selection Direct 767.75 Signed 2018-04-01 2018-04-01 2018-04-11 2018-04-07 2018-05-01 2018-05-02 2018-12-31 team and design the needed framwork to support FRA efforts which aim to develop non banking financial markets In Egypt FRA-CS-CDS-4 / MFI Financial Reporting quality TF / 17864 Post Direct Selection Direct 9,000.00 Signed 2018-05-16 2018-05-16 2018-05-28 2018-05-28 2018-07-01 2019-07-01 2018-12-31 assurance consultant (Dr. Mohamed Yehia) FRA-CS-CDS-5 / Information Technology Advisor Eng. TF / 17864 Post Direct Selection Direct 1,406.65 Signed 2018-01-21 2018-01-21 2018-01-31 2018-01-31 2018-03-01 2018-03-01 2018-12-31 Tarek Fathy FRA-CS-CDS-6 / Information Technology Advisor MIS TF / 17864 Post Direct Selection Direct 1,904.76 Signed 2018-12-02 2018-12-02 2018-12-16 2018-12-16 2019-01-01 2019-01-01 2019-12-31 Sysytem Eng. Nael Abdelwahab FRA-CS-INDV-2 / Finance Individual Planning & General Support TF / 17864 Post Consultant Limited 1,533.55 Signed 2015-02-01 2015-02-01 2015-02-11 2015-02-11 2015-02-25 2015-02-25 2015-04-01 2015-04-01 2015-12-31 Services Manager (Hossam Selection Bashir) FRA-CS-INDV-3 / Head of Individual Micro Finance (Mr. Gamal TF / 17864 Post Consultant Direct 3,192.08 Signed 2015-01-01 2015-01-01 2015-01-11 2015-01-11 2015-02-01 2018-02-01 2015-03-01 2015-03-01 2015-12-31 Khalifa) Selection Page 3 FRA-CS-CDS-7 / Digital Transformation Advisor (Mrs. TF / 17864 Post Direct Selection Direct 952.38 Signed 2018-12-02 2018-12-02 2018-12-12 2018-12-12 2019-01-01 2019-01-01 2019-12-31 Asmaa Mahmoud Hosny) EG-EFSA-201452-CS-CDS / a consultant for drafting the TF / 17864 Post Direct Selection Direct 0.00 Under Review 2020-10-25 2020-09-15 2020-10-27 2020-11-01 2021-04-30 law of Futures Contracts Exchange (Samah adel) Page 4 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, One WASH- Consolidated WASH Account (CWA) Project “Phase II”, P167794 Project Implementation agency: Water Development Commission (WDC) of the Ministry of Water, Irrigation and Energy (MoWIE) Date of the Procurement Plan: August 28, 2019 Period covered by this Procurement Plan: September 2019 to August 2020. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : One WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project (One WASH—CWA) PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2020-03-11 2021-05-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167794 GPN Date: 2019-12-06 Project Name: One WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project (One WASH—CWA) Loan / Credit No: IDA / 64450 T Executing Agency(ies): IGRAY WRDB WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-TIGRAY WRDB-151604- CW-RFB / Civil work construction with supply and installation of Pipes ,Fittings Urban Water Supply, Under Single Stage - One 2021-04- and electro-mechanical IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 0.00 Implementat 2020-03-04 2020-04-01 2020-03-19 2020-04-18 2020-05-04 2020-05-18 2020-09-08 2020-06-28 Envelope 24 equipment's) forAdi Daero (Urban WASH) ion Town. Implementing Agency-Tigray Water Resource Bureau ET-TIGRAY WRDB-155372- CW-RFB / Drilling and pumping test of one Deep Urban Water Supply, Single Stage - One 2020-07- borehole for Adi Nebried IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 30,670.14 Signed 2020-02-05 2020-04-13 2020-02-20 2020-03-21 2020-05-13 2020-04-20 2020-07-08 2020-05-25 2020-08-17 Envelope 24 Town. (Urban WASH) Implementing Agency-Tigray Water Resource Bureau ET-TIGRAY WRDB-151608- CW-RFB / Expansion of water Urban Water Supply, Under supply system at Nebelet Single Stage - One 2020-09- IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 0.00 Implementat 2020-02-12 2020-04-16 2020-02-27 2020-03-28 2020-05-15 2020-04-27 2020-07-21 2020-06-01 town. Envelope 29 (Urban WASH) ion Implimenting Agency-Tigray Water Resource Bureau ET-TIGRAY WRDB-151627- CW-RFB / Construction of RPS (Civil work construction , supply and installation of Pipes and Fittings and Rural Water Supply, Under Single Stage - One 2021-04- electromechanical equipment) IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 0.00 Implementat 2020-02-24 2020-05-19 2020-03-10 2020-04-21 2020-06-23 2020-05-21 2020-10-10 2020-07-01 Envelope 07 at Kilite Awlealo Woreda (Rural WASH) ion (Dinwale Village) Implementing Agency-Tigray Water Resource Bureau ET-TIGRAY WRDB-151638- CW-RFB / Drilling and pumping test of Five Deep borehole for (Laelay Maychew Rural Water Supply, Under Single Stage - One 2020-09- #1, Laelay Adiyabo #1 , IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 153,863.83 Implementat 2020-02-14 2020-04-10 2020-02-29 2020-04-11 2020-05-20 2020-05-11 2020-07-08 2020-06-21 Envelope 19 hintalo wojerat (Gonka) (Rural WASH) ion #1,Tsegede #1 and Welkait#1) Implementing Agency-Tigray Water Resource Bureau ET-TIGRAY WRDB-155368- CW-RFB / Drilling of shallow wells and supply and installation of Afredeve hand pump at lot-1 Atsbi Wonberta and ofla Rural Water Supply, Under Single Stage - One 2020-11- woredas #10Shallow wells IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 156,058.70 Implementat 2020-03-28 2020-04-08 2020-04-12 2020-05-12 2020-05-08 2020-06-11 2020-07-07 2020-07-16 Envelope 13 lot-2Welkayit woreda #10 (Rural WASH) ion shallow wells lot-3Tsegede Woreda#10SW Implementing Agency- Tigray Water Resource Bureau ET-TIGRAY WRDB-151601- CW-RFB / Civil work construction with supply and installation of Pipes ,Fittings Urban Water Supply, Under Single Stage - One 2021-06- and electromechanical IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 0.00 Implementat 2020-02-07 2020-04-01 2020-02-25 2020-03-26 2020-05-07 2020-05-05 2020-09-22 2020-06-15 Envelope 15 equipments) for Wukro Maray (Urban WASH) ion Town. Implementing Agency- Tigray Water Resource Bureau ET-TIGRAY WRDB-232288- National CW-DIR / Construction of Procurement Rural Water Supply, Pending RPSs including supply and Document - 1 2022-01- IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementat 2021-04-30 2021-05-05 2021-05-22 Installation of Pipes and Envelope 27 (Rural WASH) ion Fittings and EME for Dinwale process (Non village by Tigray WRB Bank-SPD) ET-TIGRAY WRDB-232291- National CW-DIR / Construction of WSS Procurement Urban Water Supply, Pending including supply and Document - 1 2021-12- IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementat 2021-04-30 2021-05-05 2021-05-22 Installation of Pipes and Envelope 08 (Urban WASH) ion Fittings and EME for Adi Daero process (Non Town by Tigray WRB Bank-SPD) ET-TIGRAY WRDB-232292- National CW-DIR / Construction of WSS Procurement Urban Water Supply, Pending including supply and Document - 1 2022-05- IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementat 2021-04-30 2021-05-05 2021-05-22 Installation of Pipes and Envelope 22 (Urban WASH) ion Fittings and EME for Wukro process (Non Maray Town by Tigray WRB Bank-SPD) ET-TIGRAY WRDB-232293- National CW-DIR / Construction of WSS Procurement Urban Water Supply, Pending including supply and Document - 1 2022-02- IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementat 2021-04-30 2021-05-05 2021-05-22 installation of pipes and Envelope 16 (Urban WASH) ion fittings and EME for Chercher process (Non Town by Tigray WRDB Bank-SPD) Page 1 National ET-TIGRAY WRDB-232299- Procurement CW-DIR / Drilling of 30 Rural Water Supply, Pending Document - 1 2021-09- shallow wells including supply IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementat 2021-04-30 2021-05-05 2021-05-22 Envelope 19 & installation of hand pump in (Rural WASH) ion process (Non 4 lots by Tigray RWB Bank-SPD) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-TIGRAY WRDB-232298- GO-DIR / Procurement of 7 Urban Water Supply, Pending generator and 6 pumps and 3 IDA / 64450 Sanitation, and Hygiene Post Direct Selection Direct 0.00 Implementati 2021-04-30 2021-05-05 2021-06-09 2021-09-07 switch boards by Tigray Water (Urban WASH) on Resources Bureau NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-TIGRAY WRDB-155393- CS-INDV / Selection and Individual Employment of Regional Institutional Strengthening Under IDA / 64450 Post Consultant Open 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2021-06-04 WASH Assistant coordinator and Project Management Implementation Selection by Tigray Water Resource Bureau. ET-TIGRAY WRDB-155455- CS-INDV / Recruitment of Individual Institutional Strengthening Under Monitoring and Evaluation IDA / 64450 Post Consultant Open 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2021-06-04 and Project Management Implementation Specialist by Tigray Water Selection Resource Bureau. ET-TIGRAY WRDB-155465- CS-INDV / Recuitement of Individual Institutional Strengthening Under Electromechanical Specialist IDA / 64450 Post Consultant Open 0.00 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2021-06-04 and Project Management Implementation by Tigray Water Resource Selection Bureau ET-TIGRAY WRDB-155475- CS-INDV / Recruitment of Individual Institutional Strengthening Technical Specialist (Engineer) IDA / 64450 Post Consultant Open 0.00 Canceled 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2021-06-04 and Project Management by Tigray Water Resource Selection Bureau ET-TIGRAY WRDB-155461- Individual CS-INDV / Recruitment of Institutional Strengthening IDA / 64450 Prior Consultant Open 0.00 Canceled 2020-04-20 2020-06-08 2020-06-29 2020-08-03 2023-08-03 Procurement specialist by and Project Management Selection Tigray Water Resource Bureau. ET-TIGRAY WRDB-191553- Individual CS-INDV / Recuitment of Institutional Strengthening Under IDA / 64450 Prior Consultant Open 0.00 2020-09-12 2020-10-31 2020-11-21 2020-12-26 2023-12-26 procurement specialist by and Project Management Implementation Selection Tigray Water Resource Bureau ET-TIGRAY WRDB-191557- CS-INDV / Recuitemnet of Individual Institutional Strengthening Under technical specialist (Engineer) IDA / 64450 Post Consultant Open 0.00 2020-09-12 2020-10-31 2020-11-21 2020-12-26 2021-12-26 and Project Management Implementation by Tigray Water Resource Selection Bureau ET-TIGRAY WRDB-232308- Individual CS-INDV / Recruitment of Institutional Strengthening Pending IDA / 64450 Post Consultant Limited 0.00 2021-05-05 2021-05-10 2021-05-25 2021-06-25 2022-06-25 Technical Specialist (Engineer) and Project Management Implementation Selection by Tigray WRB ET-TIGRAY WRDB-232310- Individual Institutional Strengthening Pending CS-INDV / Recruitment of IDA / 64450 Post Consultant Limited 0.00 2021-05-05 2021-05-10 2021-05-31 2021-07-05 2022-07-05 and Project Management Implementation Social Safeguard by Tigray Selection WRB ET-TIGRAY WRDB-232311- Individual CS-INDV / Recruitment of Institutional Strengthening Pending IDA / 64450 Post Consultant Limited 0.00 2021-05-05 2021-05-10 2021-05-31 2021-07-05 2022-07-05 Procurement specialist by and Project Management Implementation Selection Tigray WRB Page 2 Nigeria For APPEALSP PROCUREMENT PLAN (Textual Part) Project information: [Nigeria] [Agro-Processing, Productivity Enhancement and Livelihood Improvement Support Project] (P53390) Project Implementation agency: [Federal Ministry of Agriculture and Rural Development] Date of the Procurement Plan: [October 25, 2018] Period covered by this Procurement Plan: [October 25, 2018 to December 2018] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works).Not Applicable. Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable Other Relevant Procurement Information. The project will use the CDD procurement under this project. CDD manual will be produced by the project. PROCUREMENT Nigeria : Agro-Processing, Productivity Enhancement and Livelihood Improvement Support Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2019-04-26 2021-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148616 GPN Date: Project Name: Agro-Processing, Productivity Enhancement and Livelihood Improvement Support Project Loan / Credit No: IDA / 59930 LAGOS APPEALS Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned APPEALSP-LGSCO-CW-01 / Under Renovation of Office, Project Management and Request for Single Stage - One 2020-01- IDA / 59930 Post Limited 27,470.00 27,514.10 Implementat 2019-05-11 2019-05-07 2019-07-06 2019-06-13 Conference Room & Training Coordination Quotations Envelope 02 ion Hall NG-LAGOS APPEALS-158867- CW-RFB / Construction/rehabilitation of Infrastructure Support to Single Stage - Two 2021-07- IDA / 59930 Post Request for Bids Open - National 877,780.00 0.00 Canceled 2020-08-10 2020-08-15 2020-09-26 2020-12-09 2021-01-13 7.9 km Farm Access Roads Agribusiness Clusters Envelope 12 (3.8Km at Igbodu, Epe; 4.1 Km at Erikorodo -Phase 1) NG-LAGOS APPEALS-235890- Request for Bids - Pending CW-RFB / Infrastructure Support to Single Stage - One Small Works SPD 2022-03- IDA / 59930 Post Request for Bids Open - National 3,966,280.00 0.00 Implementat 2021-05-27 2021-06-01 2021-07-13 2021-08-12 2021-09-16 Construction/Rehabilitation of Agribusiness Clusters Envelope (1 envelope 15 ion Farm Access Road process) NG-LAGOS APPEALS-235891- Request for Bids - Pending CW-RFB / Infrastructure Support to Single Stage - One Small Works SPD 2022-03- IDA / 59930 Post Request for Bids Open - National 458,333.00 0.00 Implementat 2021-06-08 2021-06-13 2021-07-25 2021-08-24 2021-09-28 Construction/Rehabilitation of Agribusiness Clusters Envelope (1 envelope 27 ion 3 No.s of Aggregation Centers process) NG-LAGOS APPEALS-235893- Primary processing, Value Request for Bids - Pending CW-RFB / Establishment of 12 Addition, Post-Harvest Single Stage - One Small Works SPD 2022-03- IDA / 59930 Post Request for Bids Open - National 1,833,333.00 0.00 Implementat 2021-06-08 2021-06-13 2021-07-25 2021-08-24 2021-09-28 No.s Cottage Processing Management and Women & Envelope (1 envelope 27 ion Centers Youth Empowerment process) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual APPEALSP-LGSCO-GO-01 / Production of Information, Education &Communication Project Management and Request for Single Stage - One materials / Knowledge IDA / 59930 Post Limited 8,240.00 14,793.04 Signed 2019-05-12 2019-08-05 2019-07-07 2019-08-26 2020-01-03 2020-03-25 Coordination Quotations Envelope sharing materials (Fact sheets, Newsletters, leaflets, handbills, manuals, briefs etc APPEALSP-LGSCO-GO-02 / Procurement of Communication equipment; (1)High Megapixel photo Technical Assistance, Request for Single Stage - One camera, (2)HD Professional IDA / 59930 Knowledge Management and Post Limited 4,330.00 174,430.32 Signed 2019-05-11 2019-05-24 2019-07-06 2019-06-20 2020-01-02 2019-08-27 Quotations Envelope Camera, (3) Medium PAS Communication (1);(4) Big Movable PAS(1),(5) Projector and Screen, (6) Media Mobile device APPEALSP-LGSCO-GO-03 / Technical Assistance, Request for Single Stage - One Production of Promotional IDA / 59930 Knowledge Management and Post Limited 10,990.00 10,877.06 Signed 2019-05-12 2019-05-05 2019-07-07 2019-07-02 2020-01-03 2019-09-06 Quotations Envelope items & Bill Boards/Sign posts Communication APPEALSP-LGSCO-GO-04 / Procurement of Office Furniture: 20 Executive Chairs Project Management and Request for Single Stage - One IDA / 59930 Post Limited 13,740.00 13,713.66 Signed 2019-04-27 2019-05-03 2019-06-22 2019-06-11 2019-12-19 2019-07-19 and Tables; Office fittings (e.g Coordination Quotations Envelope curtains,window blind,railings etc) APPEALSP-LGSCO-GO-05 / Procurement of Electrical Equipment and Appliances, 6 Infrastructure Support to Request for Single Stage - One units of 2HP Airconditioners IDA / 59930 Post Limited 18,930.00 5,099.93 Completed 2019-04-29 2019-04-30 2019-06-24 2019-05-31 2019-12-21 2019-09-06 Agribusiness Clusters Quotations Envelope for the training Hall, 30 units of fanS, calculators and Casting machine. APPEALSP-LGSCO-GO-06 / Provision of Alternative Source Infrastructure Support to Request for Single Stage - One of Energy for SCO (Inverter IDA / 59930 Post Limited 27,470.00 50,374.63 Signed 2019-05-14 2019-05-10 2019-07-09 2019-07-02 2020-01-05 2020-05-08 Agribusiness Clusters Quotations Envelope System/ Battery Banks and accessories etc) APPEALSP-LGSCO-GO-07 / Procurement of computers and accessories: 20 Nos Computer Laptops with carrier bags for projects officers, Project Management and Request for Single Stage - One IDA / 59930 Post Limited 28,830.00 56,284.84 Signed 2019-04-30 2019-05-02 2019-06-25 2019-07-01 2019-12-22 2019-07-31 External hard drive(EHD) and Coordination Quotations Envelope Flash drives, 20 units of Modem, Printers and Scanners, Global Positioning System (GPS) APPEALSP-LGSCO-GO-08 / Procurement of the following soft wares: 10 units of Database tracking soft ware, Project Management and Request for Single Stage - One IDA / 59930 Post Limited 21,560.00 15,595.85 Completed 2019-04-30 2019-07-15 2019-06-25 2019-07-16 2019-12-22 2019-08-06 5 users Smart draw for Coordination Quotations Envelope excelent chart and reporting; Computer aided design CAD Soft wares Page 1 APPEALSP-LGSCO-GO-09 / Under Project Management and Request for Single Stage - One Procurement of 1 unit of IDA / 59930 Post Limited 71,430.00 0.00 Implementati 2019-05-20 2019-05-30 2019-07-15 2020-01-11 Coordination Quotations Envelope project Utility vehicle on NG-LAGOS APPEALS-158835- Primary processing, Value GO-RFQ / Procurement of Addition, Post-Harvest Request for Single Stage - One IDA / 59930 Post Limited 83,330.00 229,662.72 Signed 2020-04-28 2020-04-23 2020-06-23 2020-05-06 2020-12-20 2020-06-02 facilities for the Establishment Management and Women & Quotations Envelope of Farmers Markets Youth Empowerment NG-LAGOS APPEALS-158940- Project Management and Request for Single Stage - One GO-RFQ / Procurement of 2 IDA / 59930 Post Limited 154,000.00 138,069.27 Signed 2020-03-28 2020-03-30 2020-05-23 2020-04-24 2020-11-19 2020-04-28 Coordination Quotations Envelope Utility vehicles NG-LAGOS APPEALS-158738- Primary processing, Value GO-RFQ / Procurement of Addition, Post-Harvest Request for Single Stage - One IDA / 59930 Post Limited 27,780.00 0.00 Canceled 2020-09-26 2020-11-21 2021-05-20 facilities for the Establishment Management and Women & Quotations Envelope of One-Stop-Shop Youth Empowerment APPEALSP-LGSCO-GO-9C / Technical Assistance, Pending Procurement of (Furniture, Request for Single Stage - One IDA / 59930 Knowledge Management and Post Limited 27,778.00 0.00 Implementati 2021-08-08 2021-10-03 2022-04-01 Workstation etc)for the Quotations Envelope Communication on Establishment of Library APPEALSP-LGSCO-GO-08C / Technical Assistance, Pending Procurement of knowleged Request for Single Stage - One IDA / 59930 Knowledge Management and Post Limited 27,778.00 0.00 Implementati 2021-08-04 2021-09-29 2022-03-28 material repository for Quotations Envelope Communication on Development of e-library NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-LAGOS APPEALS-156950- Consultant CS-CQS / Feasibility study on Production and Productivity IDA / 59930 Post Qualification Open - National 40,280.00 0.00 Under Review 2020-04-30 2020-06-04 2020-05-21 2020-09-14 2020-07-04 2020-07-20 2020-08-03 2020-09-07 2021-03-06 the establishment of bird Enhancement Selection hatchery in the State NG-LAGOS APPEALS-162010- CS-CQS / Engagement of a Primary processing, Value Consultants for the facilitation Consultant Addition, Post-Harvest of all activities for the PWDs IDA / 59930 Post Qualification Open - National 33,330.00 0.00 Under Review 2020-03-09 2020-03-20 2020-03-30 2020-05-13 2020-06-12 2020-07-17 2021-01-13 Management and Women & (Training, Mentoring, Selection Youth Empowerment Monitoring etc) support under the WYEP NG-LAGOS APPEALS-162013- Primary processing, Value CS-CQS / Engagement of Consultant Addition, Post-Harvest Under Consultancy to facilitate IDA / 59930 Post Qualification Open - National 27,780.00 0.00 2020-05-25 2019-06-20 2020-06-15 2020-07-29 2020-08-28 2020-10-02 2021-03-31 Management and Women & Implementation International Market Selection Youth Empowerment Expectation for Aquaculture NG-LAGOS APPEALS-161811- Primary processing, Value Consultant CS-CQS / Feasibility Study on Addition, Post-Harvest Under IDA / 59930 Post Qualification Open - National 27,780.00 0.00 2020-04-20 2020-05-28 2020-05-11 2020-06-24 2020-07-24 2020-08-28 2021-02-24 production of Egg Powder Management and Women & Implementation Selection technology in the State. Youth Empowerment NG-LAGOS APPEALS-161999- CS-CQS / Technical Consultant Assistance for the conduct of Production and Productivity IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-03-31 2020-04-21 2020-06-04 2020-07-04 2020-08-08 2021-02-04 Need Assessment for the Enhancement Selection selected value chains of Poultry, Aquaculture and Rice. NG-LAGOS APPEALS-162000- CS-CQS / Consultancy to Consultant source for climate smart, Production and Productivity IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-05-18 2020-06-08 2020-07-22 2020-08-21 2020-09-25 2021-03-24 nutrition sensitive and Enhancement Selection improved technologies to enhance Farmers productivity NG-LAGOS APPEALS-162005- Technical Assistance, Consultant CS-CQS / Consultancy on IDA / 59930 Knowledge Management and Post Qualification Open - National 27,880.00 0.00 Canceled 2020-06-09 2020-06-30 2020-08-13 2020-09-12 2020-10-17 2021-04-15 Production of Project Communication Selection Documentary NG-LAGOS APPEALS-162001- Consultant CS-CQS / Technical Support Project Management and IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-04-28 2020-05-19 2020-07-02 2020-08-01 2020-09-05 2021-03-04 to strengthen the fiduciary Coordination Selection system of the Project NG-LAGOS APPEALS-162006- CS-CQS / Technical Technical Assistance, Consultant Assistance on Production of IDA / 59930 Knowledge Management and Post Qualification Open - National 41,670.00 0.00 Canceled 2020-04-29 2020-05-20 2020-07-03 2020-08-02 2020-09-06 2021-03-05 Knowledge and learning Communication Selection products NG-LAGOS APPEALS-162008- CS-CQS / Consultancy Consultant services for the Enviromental Project Management and IDA / 59930 Post Qualification Open - National 33,330.00 0.00 Canceled 2020-03-23 2020-04-13 2020-05-27 2020-06-26 2020-07-31 2021-01-27 and Social Impact Assesmemt Coordination Selection (including ESMP) for Rural Infrastructural support NG-LAGOS APPEALS-158859- Consultant CS-CQS / Engagement of Infrastructure Support to IDA / 59930 Post Qualification Open - National 36,105.55 0.00 Canceled 2020-04-15 2020-05-06 2020-06-19 2020-07-19 2020-08-23 2021-02-19 Consultant for the Design of Agribusiness Clusters Selection 14.66 Km Farm Access Road. Page 2 NG-LAGOS APPEALS-162012- CS-CQS / Consultancy on Primary processing, Value Market Sensitivity Analysis Consultant Addition, Post-Harvest and Determination of IDA / 59930 Post Qualification Open - National 27,780.00 0.00 Canceled 2020-04-30 2020-05-21 2020-07-04 2020-08-03 2020-09-07 2021-03-06 Management and Women & Consumer Preference for Selection Youth Empowerment Poultry, Aquaculture and Rice value chains INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual APPEALSP-LGSCO-CS-01 / Consultancy on the conduct of Primary processing, Value Individual Technical Feasibility Studies Addition, Post-Harvest IDA / 59930 Post Consultant Limited 13,740.00 13,793.10 Completed 2019-04-18 2019-06-26 2019-04-23 2019-05-03 2019-05-14 2019-07-04 2019-06-18 2019-08-23 2019-12-15 2019-12-06 on Market Information / Management and Women & Selection Opprtunities for the selected Youth Empowerment value chains in the State. APPEALSP-LGSCO-CS-02 / Consultancy for the Technical Assistance, Individual engagement of Technical IDA / 59930 Knowledge Management and Post Consultant Limited 13,740.00 0.00 Canceled 2019-05-19 2019-06-26 2019-05-24 2019-06-14 2019-07-19 2020-01-15 assistant to strengthen the Communication Selection financial management of the Project. APPEALSP-LGSCO-CS-03 / Technical Assistance, Individual Conduct of Survey on effective IDA / 59930 Knowledge Management and Post Consultant Limited 13,740.00 0.00 Canceled 2019-05-21 2019-06-26 2019-05-26 2019-07-30 2019-06-16 2019-07-21 2020-01-17 communication channels in Communication Selection Lagos State APPEALSP-LGSCO-CS-04 / Individual Engagement of consultant for Project Management and IDA / 59930 Post Consultant Limited 8,240.00 13,226.06 Under Review 2019-09-26 2019-06-26 2019-10-01 2019-08-01 2019-10-22 2019-09-26 2019-11-26 2019-09-13 2020-05-24 2020-01-22 the development of greivance Coordination Selection redress mechanism(GRM) APPEALSP-LGSCO-CS-05 / Technical Assistance, Individual Production & Airing of Jingles IDA / 59930 Knowledge Management and Post Consultant Limited 13,740.00 13,679.90 Under Review 2019-04-29 2019-06-26 2019-05-04 2019-06-27 2019-05-25 2019-07-26 2019-06-29 2019-08-05 2019-12-26 2020-03-02 (Yoruba, English, Pidgin on Communication Selection Radio NG-LAGOS APPEALS-162004- CS-INDV / Consultancy on Technical Assistance, Individual News feature of project IDA / 59930 Knowledge Management and Post Consultant Limited 19,440.00 0.00 Under Review 2020-03-31 2019-07-03 2020-04-05 2020-04-26 2020-05-31 2020-11-27 activities in print and Communication Selection electronic media NG-LAGOS APPEALS-158943- Technical Assistance, Individual CS-INDV / Conduct of Survey IDA / 59930 Knowledge Management and Post Consultant Limited 27,780.00 0.00 Under Review 2020-04-20 2020-07-07 2020-04-25 2020-05-16 2020-06-20 2020-12-17 on effective communication Communication Selection channels in Lagos State NG-LAGOS APPEALS-158856- Individual Project Management and CS-INDV / Consultancy for IDA / 59930 Post Consultant Limited 8,330.00 0.00 Canceled 2020-06-10 2020-06-15 2020-07-06 2020-08-10 2021-02-06 Coordination GBV mapping in the State Selection NG-LAGOS APPEALS-158845- CS-INDV / Engagement of Individual Infrastructure Support to Consultant for preparation of IDA / 59930 Post Consultant Limited 13,890.00 0.00 Canceled 2020-09-23 2020-09-28 2020-10-19 2020-11-23 2021-05-22 Agribusiness Clusters ESMP for 3NO Cottage Selection Industries NG-LAGOS APPEALS-158903- Individual CS-INDV / Consultancy on the Infrastructure Support to IDA / 59930 Post Consultant Limited 16,670.00 0.00 Canceled 2020-04-15 2020-04-20 2020-05-11 2020-06-15 2020-12-12 Design and Supervision of Agribusiness Clusters Selection Energy Interventions NG-LAGOS APPEALS-158889- CS-INDV / Engagement of Individual Infrastructure Support to consultant for the Design of 2 IDA / 59930 Post Consultant Limited 25,000.00 0.00 Canceled 2020-04-24 2020-04-29 2020-05-20 2020-06-24 2020-12-21 Agribusiness Clusters Nos of Jetties (Badagry; Selection Agbowa) NG-LAGOS APPEALS-158916- Individual CS-INDV / Engagement of Project Management and IDA / 59930 Post Consultant Limited 27,780.00 0.00 Canceled 2020-10-19 2020-10-24 2020-11-14 2020-12-19 2021-06-17 Technical Assistant on Coordination Selection Agricultural Production Survey Individual APPEALSP-LGSCO-CS-03C / Infrastructure Support to Pending IDA / 59930 Post Consultant Limited 19,444.00 0.00 2021-06-22 2021-06-27 2021-07-18 2021-08-22 2022-02-18 Design of Energy for Clusters Agribusiness Clusters Implementation Selection APPEALSP-LGSCO-CS-02C / Individual Infrastructure Support to Pending Engagement of consultant for IDA / 59930 Post Consultant Limited 20,834.00 0.00 2021-05-29 2021-06-03 2021-06-24 2021-07-29 2022-01-25 Agribusiness Clusters Implementation the design of Jetties Selection Individual NG-LAGOS APPEALS-158941- Project Management and IDA / 59930 Post Consultant Limited 13,890.00 0.00 Canceled 2020-04-02 2020-04-07 2020-04-28 2020-06-02 2020-11-29 CS-INDV / Market Price Survey Coordination Selection Page 3 Procurement Plan Community Development Program Support Project – Phase III (Programme National de Développement Participatif – Phase III) I. General 1. Bank’s approval Date of the procurement Plan [Original: February 2016]: Revision of Updated Procurement Plan, May 05, 2017 2. Date of General Procurement Notice: February 15, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year January to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) None 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million 5. DC (Non-Consultant Services) none 2. Prequalification. Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Procurement (works, goods and services) for subprojects of communes, such as small infrastructure, social infrastructure, classrooms, health centers, community halls, , minor works or rehabilitation, will be procured on the basis of community participation in accordance with the clause 3.19 of the World Bank Procurement Guidelines (Community Participation in Procurement), and the Guidelines for Simplified Procurement and Disbursement for Community-Based Investments (March 3, 1998) detailed in the specific manual or guidelines to communes approved by the bank. 4. Reference to (if any) Project Operational/Procurement Manual: Guide des Acteurs intervenant dans le processus de passation et de l’exécution des marchés communaux financés par le PNDP – Juin 2010, révisé en Janvier 2016 May 05, 2017 5. Any Other Special Procurement Arrangements: 5 ICB works packages will be financed under - retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packag Domesti Review Comments No. n d es c by Bank Cost Prefere (Prior / US$ nce Post) million (yes/no) Summary of 2.328 2 No Prior the ICB (Goods) Summary of 0.700 1 No Post 1st contract the NCB for Prior (Goods) Review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 500,000 Justification prior reviewed by bank 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule May 05, 2017 1 2 3 4 5 6 7 Ref Description of Estimate Selection Review Expecte Comment . Assignment d cost method by the d s/ No (US$ Bank proposal completio equivale (prior/po s n date nt) st) submissi on date For the Support for the 1 Post first year preparation of 20,000 IC 21/08/15 24/09/15 Statutory Instruments (30 days) 2 Study on the definition 40,000 Post 22/04/16 of a planning CQS 25/01/16 (03 methodology at months) regional level 3 Study on the planning 40,000 CQS Post 25/01/16 22/04/16 process in the (03 communes and urban months) communities 4 Study for the 20,000 IC Post 19/02/16 24/03/16 establishment of local (30 days) public service in communes 5 Study on the 40,000 CQS Post 11/04/16 18/07/16 sustainability of the (03 PNDP months) 6 Evaluation of the 40,000 CQS Post 13/07/16 18/10/16 decentralization (03 process in months) Cameroon/supports to the finalization of the national strategy for decentralization 7 Selection of a 20,000 IC Post 20/11/15 30/12/15 consultant to develop (30 days) the practitioner's manual for the 31 communes 8 Municipal staff training 100,000 SSS Prior NA Service provided by the CEFAM (Conventio n) 9 Training of 100,000 SSS Prior NA Service procurement provided commissions by ARMP (Conventio n) 10 Financial Audits of the 150,000 LCS Post 10/03/15 Contract project for the first 2 for 2 years years 11 legal advice 10,000 IC Post 28/12/15 Annual contract May 05, 2017 1 2 3 4 5 6 7 Ref Description of Estimate Selection Review Expecte Comment . Assignment d cost method by the d s/ No (US$ Bank proposal completio equivale (prior/po s n date nt) st) submissi on date 12 Design and 90,000 CQS Post 12/02/16 22/08/16 development of an (06 internet portal on the months) PNDP and communes 13 Translation of 90,000 CQS Post 11/05/16 20/08/16 documents (03 months) 14 Technical audit 80,000 QCBS Post 16/02/16 31/08/16 (06 months) 15 Beneficiary assessment 50,000 QCBS Post 15/11/16 22/05/17 (06 months) 16 Environmental and 70,000 QCBS Post 13/12/16 26/06/17 Social Assessment (06 months) 17 Service Follow-up of training SSS Prior NA provided deployment and by AIMF 70,000 technical assistance to expert Sim_ba software in (Conventio communes n) 18 IC Post 27/05/15 Annual contract (the 10,000 current contract ends June Insurance advice 30, 2015) 19 QCBS Post 01/12/16 16/04/16 Preparation of CDPs for 80,000 (06 the 31 communes months) May 05, 2017 PROCUREMENT Cameroon : Community Development Program Support Project-Phase III PLAN General Information Country: Cameroon Bank’s Approval Date of the Original Procurement Plan: 2017-05- 30 2021-06- Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P144637 GPN Date: 01 2016-09- Project Name: Community Development Program Support Project-Phase III 06 Loan / Credit No: IDA / 57180, IDA / D2990, IDA / 62240 CELLULE REGIONALE DE COORDONATION - EXTREME NORD Executing Agency(ies): WORKS Activity Reference No. Procurement Estimate Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati High SEA/SH Process Prequalification Bidding Documents Contract / Description Component Review Type Method Document d Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Risk Status Evaluation Report as Issued Completion Type Amount (US$) Documents Justification / Invitation Opening / Minutes Recommendation (US$) Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planne d CM-CRC EXTREME NORD- 8012-CW-RFQ / Petits Component C: travaux d'aménagement des Coordination, management, Request for Single Stage - One Complete 2017-03- 2017-05- 2017-05- 2017-07- 2017- bureaux (cloisonnement des IDA / 57180 Post Limited 5,600.00 4,722.91 monitoring and evaluation Quotations Envelope d 10 26 05 22 06-04 bureaux, équipement and communication étagères pour classement, etc...) à la CRC EN CM-CRC EXTREME NORD- 8013-CW-RFQ / Construct et équipt d'01 bloc de 02 de sc et d'un bloc de Lt à trois comparts à l'EP de Dogba, Component A: Local Request for Single Stage - One 154,638.0 139,405. 2017-03- 2017-06- 2017-05- 2017-10- 2017- au lycée de Gayack et IDA / 57180 Post Limited Signed development support Quotations Envelope 0 62 25 12 20 30 09-17 Construction de 01 bloc de hangar de 52 pces et d'un bloc de Lt à trois comparts au marché de Papata,Commune de Mra II CM-CRC EXTREME NORD- 8016-CW-RFQ / Constructde 6 forages équipés de PMH à Tchékéhi, Component A: Local Request for Single Stage - One 68,485.3 2017-03- 2017-05- 2017-05- 2017-09- 2017- IDA / 57180 Post Limited 96,000.00 Signed Mbokouré, Magaldao development support Quotations Envelope 0 25 30 20 12 08-18 Toupéo, Soukkoungo Galdima, Bourango et Bandalaré, commune de Pétté CM-CRC EXTREME NORD- 8035-CW-RFQ / Construct d'un magasin de stockage à Kéné-Kéné, Construct d'un Component A: Local Request for Single Stage - One 68,573.2 2017-03- 2017-05- 2017-05- 2017-09- 2017- IDA / 57180 Post Limited 82,609.00 Signed bloc de 02 sc équipées à development support Quotations Envelope 6 25 30 20 12 08-18 l'EP de Djafgué, et Construct d'un bloc de Lt à l'EP de Djafgué commune de Pétté CM-CRC EXTREME NORD- 8036-CW-RFQ / Constr d'un forage pastoral à énergie solaire équipé de 02 abreuvoirs à Balaza Lawane Component A: Local Request for Single Stage - One 76,928.1 Complete 2017-03- 2017-05- 2017-05- 2017-09- 2017- IDA / 57180 Post Limited 82,196.00 (Tchalloudi mango) et development support Quotations Envelope 6 d 25 15 20 12 08-18 Constr d'un forage pastoral à énergie solaire équipé de 02 abreuvoirs à Kongola Saïd, Cne Maroua 3 CM-CRC EXTREME NORD- 8037-CW-RFQ / Construct d'un bloc de 02 sc équipées et d'un bloc de Lt à trois Component A: Local Request for Single Stage - One 136,106.0 2017-03- 2017-05- 2017- IDA / 57180 Post Limited 0.00 Canceled comparts à l'EP de Mayel development support Quotations Envelope 0 25 20 08-18 Béi, à l'EP de Bao Hosséré II et à l'EP de Palaoudi, commune Maroua 1 CM-CRC EXTREME NORD- 8040-CW-RFQ / construction d'un bloc Component A: Local Request for Single Stage - One 46,402.6 2017-03- 2017-05- 2017-05- 2017-08- 2017- maternel à l'école Maternelle IDA / 57180 Post Limited 57,421.00 Signed development support Quotations Envelope 2 25 15 20 17 08-18 de Zokok-Laddo et branchement au réseau d'alimentation en eau potable, commune de Maroua 1 CM-CRC EXTREME NORD- 8042-CW-RFQ / Construction de trois Component A: Local Request for Single Stage - One 39,964.5 2017-03- 2017-05- 2017-05- 2017-09- 2017- forages équipés de pompe à IDA / 57180 Post Limited 46,689.00 Signed development support Quotations Envelope 9 25 25 20 12 08-18 motricité humaine à Ouro Dow, Goni Bello et Yoldéo Guiziga, Commune Maroua 1 CM-CRC EXTREME NORD- 8043-CW-RFQ / Construction de d'un bloc de 02 salles de classe Component A: Local Request for Single Stage - One 77,069.0 2017-03- 2017-04- 2017-05- 2017-07- 2017- IDA / 57180 Post Limited 92,247.00 Signed équipées et d'un bloc de development support Quotations Envelope 7 25 25 20 07 08-18 latrines à trois compartiments à l'EP Masfaï et au CES de Boula, commune de Mokolo CM-CRC EXTREME NORD- 8045-CW-RFQ / Construction de 2 forages Component A: Local Request for Single Stage - One 30,426.6 2017-03- 2017-04- 2017-05- 2017-07- 2017- IDA / 57180 Post Limited 33,787.00 Signed équipés de PMH un à Ouro development support Quotations Envelope 4 25 05 20 07 08-18 Kessoum et à Mounam, commune de Mokolo CM-CRC EXTREME NORD- 8047-CW-RFQ / Construction d'un ouvrage Component A: Local Request for Single Stage - One 81,284.7 Complete 2017-03- 2017-03- 2017-05- 2017-10- 2017- de franchissement et IDA / 57180 Post Limited 87,751.00 development support Quotations Envelope 8 d 25 31 20 31 08-18 assainissement(radier-dalot) sur le Mayo Kwayaga, dans la commune de Mogodé CM-CRC EXTREME NORD- 8050-CW-RFQ / Construction d'un bloc de 02 salles de classe équipées Component A: Local Request for Single Stage - One 85,878.4 Complete 2017-03- 2017-04- 2017-05- 2017-06- 2017- IDA / 57180 Post Limited 90,443.00 et d'un bloc de latrines à development support Quotations Envelope 9 d 25 06 20 21 08-18 trois compartiments à l'EP de Saoudjo et au CES de Madaka, commune de Bogo CM-CRC EXTREME NORD- 8053-CW-RFQ / Component A: Local Request for Single Stage - One 28,863.6 2017-03- 2017-04- 2017-05- 2017-07- 2017- Construction d'un forage IDA / 57180 Post Limited 32,294.00 Signed development support Quotations Envelope 3 25 06 20 05 08-18 équipé de PMH à Dambaye et à Bagalaf commune de Bogo CM-CRC EXTREME NORD- 8054-CW-RFQ / construction d'un bloc de deux (02) salles de classe equipees et un (01) bloc Component A: Local Request for Single Stage - One 178,787.0 163,753. Complete 2017-03- 2017-07- 2017-05- 2017-10- 2017- IDA / 57180 Post Limited latrine a trois (03) development support Quotations Envelope 0 46 d 25 07 20 27 09-17 compartiments a l'EP de honkol, a l'EP de darsala, a l'EP de dabanga et l'equipement en meubles a l'ecole maternelle de logone birni CM-CRC EXTREME NORD- 8056-CW-RFQ / construction de trois forages équipés de pompe à Component A: Local Request for Single Stage - One 44,814.2 Complete 2017-03- 2017-04- 2017-05- 2017-06- 2017- IDA / 57180 Post Limited 50,245.00 motricité humaines: un à development support Quotations Envelope 4 d 25 20 20 30 08-18 l'EP de Dabanga, un à l'EP de Honkol et un à l'EP de Darsala dans la Commune de Logone Birni CM-CRC EXTREME NORD- 8057-CW-RFQ / construction d'un forage Component A: Local Request for Single Stage - One 41,388.9 Complete 2017-03- 2017-04- 2017-05- 2017-06- 2017- pastoral équipé de pompe IDA / 57180 Post Limited 45,860.00 development support Quotations Envelope 5 d 25 20 20 30 08-18 immergée à énergie photovoltaique à Sahaba 1 dans la Commune de Logone Birni CM-CRC EXTREME NORD- 8068-CW-RFQ / réhabilitation de la mare artificielle et la construction Component A: Local Request for Single Stage - One 114,601.0 91,831.5 Complete 2017-03- 2017-07- 2017-05- 2017-11- 2017- IDA / 57180 Post Limited d'un forage pastoral à development support Quotations Envelope 0 8 d 25 07 20 27 09-17 energie photovoltaique à Mogong dans la commune de Moutourwa CM-CRC EXTREME NORD- 8072-CW-RFQ / construction de 2 blocs de deux salles de classe Component A: Local Request for Single Stage - One 115,353.0 102,090. 2017-03- 2017-03- 2017-05- 2017-06- 2017- IDA / 57180 Post Limited Signed équipées et de 2 blocs de development support Quotations Envelope 0 02 25 23 20 12 08-18 latrines à trois compartiments EP NGré et EP Afadé dans la commune de Makary CM-CRC EXTREME NORD- 38352-CW-RFB / Travaux de construction d'un forage PMH à Kaliao, Goulmoyo, Mbozo Mofou, Balewa et Component A: Local Single Stage - One 260,774.0 200,809. 2017-11- 2017-11- 2017-12- 2018-01- 2018-01- 2018-02- 2018-01- 2018-03- 2018-04- 2018- Manguirdla (Lot 1), IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 46 27 01 02 13 15 12 19 19 04 06-17 Gadjawai, Guivel, Quartier Méri centre, Nguissar et Kilwo-Valta (Lot 2), Moundour Foulbé, Dogba Maliki, Magawa, Houloum et Tchaki djébé (Lot 3) C-MERI CM-CRC EXTREME NORD- 38353-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 36,949.0 2017-12- 2017-12- 2018-01- 2018-07- 2018- de deux salles de classe IDA / 57180 Post Limited 51,198.00 Signed development support Quotations Envelope 6 02 23 27 12 04-27 équipées et un bloc de latrines au C.E.S de Manguirdla dans la commune de Meri CM-CRC EXTREME NORD- 38354-CW-RFQ / Travaux de construction d'un bloc de Component A: Local Request for Single Stage - One 67,277.8 2017-12- 2017-12- 2018-01- 2018-04- 2018- deux salles de classe IDA / 57180 Post Limited 95,682.00 Signed development support Quotations Envelope 1 02 28 27 04 04-27 équipées avec latrines à l'EP de Domo Doukou et à l'EP de Riganda COMMUNE DE YAGOUA CM-CRC EXTREME NORD- 38355-CW-RFQ / Travaux de construction d'un bloc de deux salles de classe Component A: Local Request for Single Stage - One 82,938.9 2017-12- 2017-12- 2018-01- 2018-03- 2018- IDA / 57180 Post Limited 99,316.00 Signed équipées et un bloc de development support Quotations Envelope 4 02 22 27 27 04-27 latrines à l'EP de Pitoa- Kolara et à l'EP de Badadji COMMUNE DE MOULVOUDAYE CM-CRC EXTREME NORD- 38356-CW-RFQ / Travaux de construction d'un bloc de Component A: Local Request for Single Stage - One 79,132.8 Complete 2017-12- 2017-12- 2018-01- 2018-04- 2018- deux salles équipées et un IDA / 57180 Post Limited 91,386.00 development support Quotations Envelope 6 d 02 22 27 09 04-27 bloc de latrines à l'EP de Djagalaye et au CES de Hardé COMMUNE DE MAROUA Ier CM-CRC EXTREME NORD- 38357-CW-RFQ / Travaux de construction d'un bloc de deux salles équipées et un Component A: Local Request for Single Stage - One 82,420.0 Complete 2017-12- 2017-12- 2018-01- 2018-04- 2018- bloc de latrines CES de IDA / 57180 Post Limited 89,342.00 development support Quotations Envelope 0 d 02 22 27 04 04-27 Balda et Construction d'un bloc de deux salles de classe équipées à l'EP de Sedek Ouro-Gabdo COMMUNE DE BOGO CM-CRC EXTREME NORD- 38358-CW-RFQ / Travaux de Construction de 01 forage PMH A EM de Ldamtsai, Mandaka Component A: Local Request for Single Stage - One 133,467.0 117,088. 2017-12- 2017-12- 2018-01- 2018-04- 2018- Mpoldok, Camp mission de IDA / 57180 Post Limited Signed development support Quotations Envelope 0 54 02 26 27 08 04-27 Tourou, Koudougour II Loctcha, Katamsa Sikia, Gouldoum Moufou, Houdango Dandi et Ouro Bocki(2lots) dans la commune de Mokolo CM-CRC EXTREME NORD- 38359-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 14,057.2 2017-12- 2018-01- 2018-01- 2018-04- 2018- de construction d' un forage IDA / 57180 Post Limited 15,816.00 Signed development support Quotations Envelope 0 02 31 27 05 03-28 équipé de PMH à l'EP de Riganda commune YAGOUA CM-CRC EXTREME NORD- 38360-CW-RFQ / Travaux de construction d'un forage équipé de PMH à l'EP de Component A: Local Request for Single Stage - One 61,321.8 2017-12- 2017-12- 2018-01- 2018-03- 2018- IDA / 57180 Post Limited 72,362.00 Signed Badadji, à l'EP de Pitoa- development support Quotations Envelope 8 02 22 27 26 04-27 Kolara, au lycée de Kolara et à Gadjia Padjonré COMMUNE DE MOULVOUDAYE CM-CRC EXTREME NORD- 38361-CW-RFQ / Travaux de construction d'un forage Component A: Local Request for Single Stage - One 35,012.7 2017-12- 2017-12- 2018-01- 2018-04- 2018- équipé de PMH à l'EP de IDA / 57180 Post Limited 48,640.00 Signed development support Quotations Envelope 5 02 22 27 09 04-27 Yamdjidjing, à l'EP de Djagalaye et à Zébé COMMUNE DE MAROUA Ier CM-CRC EXTREME NORD- 38362-CW-RFQ / Travaux de Construction d'un forage équipé de pompe à motricité humaine à l'EP de Component A: Local Request for Single Stage - One 67,323.3 2017-12- 2017-12- 2018-01- 2018-04- 2018- IDA / 57180 Post Limited 94,648.00 Signed Sedek Ouro Gabdo à Ardo development support Quotations Envelope 9 02 22 27 04 04-27 Foulbé Tankirou à Gagnéri Kourdaya à Guinlaye Guizigaré et Guinlaye Moufouré dans la commune BOGO CM-CRC EXTREME NORD- 38386-CW-RFQ / Travaux de construction d'un bloc de deux salles de classe équipées avec latrines à l'EP Component A: Local Single Stage - One 237,076.0 213,978. 2017-11- 2017-12- 2017-12- 2018-01- 2018-01- 2018-02- 2018-02- 2018-03- 2018-04- 2018- de Mouftoum et à l'Ecole IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 48 27 19 02 13 25 12 01 19 09 06-17 Bilingue de Rhoumzou (Lot 1), au lycée de SIR et à l'EPB de Kwashimalda (Lot 2) , au CES de Goura (Lot 3) dans la commune de Mogode CM-CRC EXTREME NORD- 38387-CW-RFB / Travaux de construction d'un bloc de deux salles équipées et un bloc de latrines à l'EP de Component A: Local Single Stage - One 233,628.0 193,465. 2017-11- 2017-11- 2017-12- 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- 2018-04- 2018- IDA / 57180 Post Request for Bids Open - National Signed Ldamang et à l'EP de Ndrock development support Envelope 0 09 27 01 02 13 13 12 14 19 06 06-17 Tourou (Lot 1), l'EP de Moufou-sud et à l'EP de Zili Yolel (Lot 2),au CES de Mandaka (Lot 3) dans la commune de MokolO CM-CRC EXTREME NORD- 38388-CW-RFB / Travaux de construction d'un radier Component A: Local Single Stage - One 27,858.8 2017-11- 2017-12- 2017-12- 2018-01- 2018-02- 2018-02- 2018-02- 2018-03- 2018-04- 2018- IDA / 57180 Post Request for Bids Open - National 34,548.00 Signed de 12 ml sur le mayo Teki development support Envelope 7 27 11 02 13 19 12 19 19 04 06-17 dans la localité de Teki, dans la commune de Mogode CM-CRC EXTREME NORD- 58606-CW-RFQ / Travaux de Construct d'un bloc de Component A: Local Request for Single Stage - One 73,189.1 2017-10- 2017-12- 2017-12- 2018- 02 sc équipées et d'un bloc IDA / 57180 Post Open - National 86,221.00 Signed development support Quotations Envelope 1 08 03 04 03-03 de Lt à trois comparts à l'EP de Mayel Béi, et à l'EP de Palaoudi l cmne Maroua 1 CM-CRC EXTREME NORD- 58541-CW-RFQ / Travaux de construction d'un forage Component A: Local Request for Single Stage - One 42,885.4 2018-05- 2018-05- 2018-07- 2018-09- 2018- productif équipé de pompe IDA / 57180 Post Limited 63,894.00 Signed development support Quotations Envelope 1 06 17 08 11 10-06 manuelle à EP Louguéré à EP Ouro Nangué à Fakalao à Hodango CM-CRC EXTREME NORD- 58600-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées Component A: Local Request for Single Stage - One 67,400.3 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 93,735.00 Signed et construction d'un bloc de development support Quotations Envelope 4 06 17 01 11 09-29 latrines à trois compartiment à EP de WOUYANG et à l'EP de GONOZO CM-CRC EXTREME NORD- 58693-CW-RFQ / Travaux de Construction d'un atelier de maçonnerie au CETIC de Component A: Local Request for Single Stage - One 43,242.0 Complete 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 68,198.00 Loulou et'un bloc de latrines development support Quotations Envelope 6 d 06 17 08 11 11-05 à trois compartiments au CETIC de Loulou COMMUNE DE NDOUKOULA CM-CRC EXTREME NORD- 58296-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées et d'un bloc de latrines à Component A: Local Request for Single Stage - One 142,608.0 118,724. Complete 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited trois compartiments à l'EP development support Quotations Envelope 0 87 d 06 10 08 10 10-06 de GUIRIOU CENTRE, (lot 01) au Lycée de DOM PYA, à la SAR/SM de Gobo(lot02) dans la cmne de GOBO Page 1 CM-CRC EXTREME NORD- 58490-CW-RFQ / Travaux de construction d'un bloc de Component A: Local Request for Single Stage - One 18,969.0 2018-05- 2018-09- 2018-07- 2018-12- 2018- latrines a quatre (04) IDA / 57180 Post Limited 22,188.00 Signed development support Quotations Envelope 7 06 05 08 26 10-06 compartiments au marché de GOBO et de NOULDAINA dans la cmne de GOBO CM-CRC EXTREME NORD- 58375-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 13,046.6 Complete 2018-05- 2018-05- 2018-07- 2018-09- 2018- de construction d'un forage IDA / 57180 Post Limited 15,668.00 development support Quotations Envelope 9 d 06 10 08 17 08-07 équipé de PMH à l'EP de GUIRIOU CENTRE CM-CRC EXTREME NORD- 58689-CW-RFQ / Travaux de construction d'un bloc de Component A: Local Request for Single Stage - One 35,806.9 Complete 2018-05- 2018-06- 2018-07- 2018-10- 2018- 02 salles de classe équipées IDA / 57180 Post Limited 47,536.00 development support Quotations Envelope 5 d 06 07 08 10 10-06 et d'un bloc de latrines à trois compartiments au CES de Doukroye CM-CRC EXTREME NORD- 58628-CW-RFQ / Travaux de construction d'un forage Component A: Local Request for Single Stage - One 10,491.3 2018-05- 2018-06- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 15,272.00 Signed équipé de PMH à l'EP de development support Quotations Envelope 3 06 13 08 15 10-06 Daloa (Doukroye) dans la cmne de KAIKAI CM-CRC EXTREME NORD- 58637-CW-RFQ / Travaux d'achevement de la Construction des ouvrages Component A: Local Request for Single Stage - One 15,519.7 Complete 2018-05- 2018-07- 2018-10- 2018- annexes d'embarquement IDA / 57180 Post Limited 33,961.00 development support Quotations Envelope 4 d 06 08 10 09-06 (quaie dembarquement et hangar d'abris)des pirogues à LOUGOUANG MASSOUANG dans la cmne de Kaikai CM-CRC EXTREME NORD- 58605-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées Component A: Local Request for Single Stage - One 73,407.1 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 95,312.00 Signed et d'un bloc de latrines à development support Quotations Envelope 8 06 29 08 10 10-06 trois compartiments à EP de Balane au CES de Sirlawé dans la cmne de KAR-HAY CM-CRC EXTREME NORD- 58552-CW-RFQ / Travaux de construction d'un forage équipé de PMH à l'EP de Component A: Local Request for Single Stage - One 65,668.0 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 91,324.00 Signed Damdama à l'EP de development support Quotations Envelope 7 06 29 08 15 10-06 Gouloulou à l'EP Balane à l'EP de REY-FOULAYE à l'EP de Sadielle au CES de Sirlawe CM-CRC EXTREME NORD- 58690-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées Component A: Local Request for Single Stage - One 73,038.9 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 99,800.00 Signed et d'un bloc de latrines à development support Quotations Envelope 7 06 15 08 17 10-06 trois compartiments à l'EP de Bihoré à l'EP de Troké dans la, commue de Tchatibali. CM-CRC EXTREME NORD- 58610-CW-RFQ / Travaux de construction d'un forage Component A: Local Request for Single Stage - One 33,727.6 2018-05- 2018-05- 2018-07- 2018-10- 2018- équipé de PMH à l'EP IDA / 57180 Post Limited 47,159.00 Signed development support Quotations Envelope 8 06 15 08 16 10-06 Saouringwa, à Kada 'a et Glonheme dans la cmne de Tchatibali CM-CRC EXTREME NORD- 58611-CW-RFQ / Travaux de construction d'un forage Component A: Local Request for Single Stage - One 35,580.8 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 48,115.00 Signed équipé de PMH à Bibalé - development support Quotations Envelope 0 06 08 08 11 10-06 Gambour à Goubara à Kassilé dans la commue de Kaele CM-CRC EXTREME NORD- 58489-CW-RFQ / Travaux de réhabilitation de la mare de Garey Kaélé, Component A: Local Request for Single Stage - One 47,962.2 2018-05- 2018-05- 2018-07- 2018-09- 2018- Construction d'un forage IDA / 57180 Post Limited 55,100.00 Signed development support Quotations Envelope 8 06 08 08 11 10-06 pastoral à énergie solaire Garey Kaélé et construction d'un forage équipé de PMH à Kassilé dans la commue de Kaele CM-CRC EXTREME NORD- 58682-CW-RFQ / Travaux de Construction d'un bloc de 02 salles de classe équipées et d'un bloc Component A: Local Request for Single Stage - One 188,121.0 154,981. Complete 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited latrines a trois development support Quotations Envelope 0 86 d 06 08 08 27 10-06 compartiments à l'EP de Badjafe, à l'EP de Zouana, (lot 01 )à l'EP de Tchabeyel et EP de Goudjouing (lot 02) cmne de Kaele. CM-CRC EXTREME NORD- 58614-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées Component A: Local Request for Single Stage - One 72,592.8 2018-05- 2018-10- 2018-07- 2018-11- 2018- d'un bloc de latrines à EP IDA / 57180 Post Limited 87,556.00 Signed development support Quotations Envelope 6 06 01 08 29 10-06 Mayel -Guinadj et un bloc de 02 salles de classe équipées à l'EP de KALAF cmne de Moutourwa. CM-CRC EXTREME NORD- 58527-CW-RFQ / Travaux de construction de 01 Component A: Local Request for Single Stage - One 54,374.2 2018-05- 2018-10- 2018-07- 2018-11- 2018- forage équipé de PMH à IDA / 57180 Post Limited 64,020.00 Signed development support Quotations Envelope 8 06 10 08 16 10-06 Ganaha, à EP de Dourloum à EP de KALAF et EP de Mayel- guinadji dans la cmne de moutourwa CM-CRC EXTREME NORD- 58849-CW-RFQ / Component A: Local Request for Single Stage - One 30,049.0 2018-05- 2018-05- 2018-07- 2018-09- 2018- construction d'un forage IDA / 57180 Post Limited 37,902.00 Signed development support Quotations Envelope 9 06 08 08 24 10-06 équipé de PMH à EM Moskota et à l'EP GOKORO CM-CRC EXTREME NORD- 58676-CW-RFQ / Travaux de Construction d'un bloc de deux salles de classe équipées et d'un bloc Component A: Local Request for Single Stage - One 150,000.0 124,030. 2018-05- 2018-06- 2018-07- 2018-08- 2018- IDA / 57180 Post Limited Signed latrines a trois development support Quotations Envelope 0 36 06 04 08 30 10-06 compartiments au CES de Mazaya à EP ZELE (Soulédé) (lot01) à EP de Doumbéré(lot02) cmne de ROUA CM-CRC EXTREME NORD- 58267-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 23,886.6 2018-05- 2018-08- 2018-07- 2018-10- 2018- de construction d'un forage IDA / 57180 Post Limited 39,124.00 Signed development support Quotations Envelope 6 06 02 08 15 10-06 équipé de PMH à Koulang à Mangavé cmne de MORA CM-CRC EXTREME NORD- 58524-CW-RFQ / Travaux de construction de 01 Component A: Local Request for Single Stage - One 2018-05- 2018-08- 2018-07- 2018-10- 2018- magasin de stockage à IDA / 57180 Post Limited 69,155.00 2,421.57 Signed development support Quotations Envelope 06 02 08 22 11-05 cereale à Sera -Idoumda et un magasin de conservation d'oignon à Kourgui cmne de MORA CM-CRC EXTREME NORD- 58623-CW-RFQ / Travaux de Construction d'un forage équipé de PMH à l'EP GANCE Component A: Local Request for Single Stage - One 63,149.4 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 79,756.00 Signed au CES Toltomari et development support Quotations Envelope 1 06 11 08 03 10-06 Réalisation d’un forage solaire avec borne fontaine à Kolofata cmne de Kolofata CM-CRC EXTREME NORD- 58445-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 131,092.0 110,625. 2018-05- 2018-05- 2018-07- 2018-09- 2018- de 02 salles de classe IDA / 57180 Post Limited Signed development support Quotations Envelope 0 81 06 07 08 24 11-05 équipées s à EP Chéoulew, au CES de Makalingaï (lot01)à EP Tazang (lot02) cmne de Tokombere CM-CRC EXTREME NORD- 58679-CW-RFQ / Travaux de Construction de 01 Component A: Local Request for Single Stage - One 35,355.2 Complete 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 29,122.00 forage équipé de PMH à development support Quotations Envelope 6 d 06 07 08 01 09-06 Baka-Fourwa et à Djaltar dans la cmne de Tokombere CM-CRC EXTREME NORD- 59466-CW-RFQ / TRAVAUX DE REHABILILATION DU Component A: Local Request for Single Stage - One 81,782.2 2018-05- 2018-09- 2018-07- 2018-10- 2019- IDA / 57180 Post Limited 93,480.00 Signed TRONCON HOTEL LE SAHEL- development support Quotations Envelope 2 06 14 08 15 01-04 MAYO-KALIAO (0,7 KM) cmne DE MAROUA Ier CM-CRC EXTREME NORD- 58513-CW-RFQ / TRAVAUX Component A: Local Request for Single Stage - One 74,376.6 2018-05- 2018-05- 2018-07- 2018-08- 2018- DE REHABILILATION DE LA IDA / 57180 Post Limited 90,301.00 Signed development support Quotations Envelope 7 06 14 01 24 12-28 PISTE SOUKOUDJO- BAGRISSE-FARARE (28 KM) CM-CRC EXTREME NORD- 58707-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE Component A: Local Request for Single Stage - One 45,015.4 Complete 2018-05- 2018-10- 2018-07- 2018-12- 2018- CLASSE EQUIPE ET D'UN IDA / 57180 Post Limited 52,286.00 development support Quotations Envelope 5 d 06 01 08 20 10-06 BLOC DE LATRINES A TROIS COMPARTIMENTS A L’EP KOUTOULA DANS LA CMNE DE BLANGOUA CM-CRC EXTREME NORD- 58839-CW-RFQ / TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR LA CONSTRUCTION DE 04 Component A: Local Request for Single Stage - One 68,084.6 2018-05- 2018-10- 2018-07- 2018-12- 2018- IDA / 57180 Post Limited 84,030.00 Signed GUICHETS, 04 MAGASINS, development support Quotations Envelope 6 06 01 08 20 11-05 D’UN HANGAR D’ATTENTE ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE DE 130 m A BLANGOUA CM-CRC EXTREME NORD- 58514-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN Component A: Local Request for Single Stage - One 21,590.5 2018-05- 2018-05- 2018-07- 2018-10- 2018- FORAGE EQUIPE DE PMH A la IDA / 57180 Post Limited 35,201.00 Signed development support Quotations Envelope 5 06 31 08 04 09-06 gare routiere de BLANGOUA ET A L'EP DE KOUTOULA DANS LA CMNE DE BLANGOUA CM-CRC EXTREME NORD- 58434-CW-RFQ / TRAVAUX DE CONSTRUCTION TRAVAUX DE CONSTRUCTION D’UNE MINI Component A: Local Request for Single Stage - One 36,812.8 Complete 2018-05- 2018-10- 2018-07- 2018-12- 2018- IDA / 57180 Post Limited 47,598.00 AEP PASTORAL EQUIPE DE development support Quotations Envelope 0 d 06 02 08 20 10-06 DEUX ABREUVOIRS, D’UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A MAGALAKABIR, DANS LA CMNE DE DARAK CM-CRC EXTREME NORD- 58286-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN Component A: Local Request for Single Stage - One 75,327.5 Complete 2018-05- 2018-06- 2018-07- 2018-10- 2018- FORAGE PASTORAL A IDA / 57180 Post Limited 96,354.00 development support Quotations Envelope 8 d 06 01 08 04 10-06 ENERGIE SOLAIRE A KARENA ET A NAGA DANS LA CMNE DE DARAK CM-CRC EXTREME NORD- 58688-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE CLASSE EQUIPE ET D'UN BLOC DE LATRINES A TROIS Component A: Local Request for Single Stage - One 76,025.4 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 89,200.00 Signed COMPARTIMENTS A L’EP development support Quotations Envelope 7 06 14 08 01 10-06 HILELLE (LOT01) ET CONSTRUCTION D'UN HANGAR AU MARCHE DE GOULFEY GANA (LOT02) cmne DE GOULFEY CM-CRC EXTREME NORD- 58840-CW-RFQ / TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR LA CONSTRUCTION DE 04 Component A: Local Request for Single Stage - One 69,011.4 2018-05- 2018-09- 2018-07- 2018-12- 2018- GUICHETS, 04 MAGASINS, IDA / 57180 Post Limited 86,829.00 Signed development support Quotations Envelope 4 06 24 08 20 11-05 D’UN HANGAR D’ATTENTE, 02 BOUTIQUES ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE DE 90 m A GOULFEY cmne DE GOULFEY CM-CRC EXTREME NORD- 58451-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN FORAGE EQUIPES DE POMPE Component A: Local Request for Single Stage - One 40,595.7 Complete 2018-05- 2018-05- 2018-07- 2018-10- 2018- A MOTRICITE HUMAINE A IDA / 57180 Post Limited 66,094.00 development support Quotations Envelope 8 d 06 14 08 01 10-06 MOUGALAM, A TAWOULWEBE, A GARE ROUTIERE ET A L'EP HILELE COMMUNE DE GOULFEY CM-CRC EXTREME NORD- 58554-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE Component A: Local Request for Single Stage - One 46,481.6 2018-05- 2018-10- 2018-07- 2018-12- 2018- IDA / 57180 Post Limited 52,286.00 Signed CLASSE EQUIPE ET D'UN development support Quotations Envelope 5 06 28 01 20 09-29 BLOC DE LATRINES A TROIS COMPARTIMENTS A L’EP GONONI CM-CRC EXTREME NORD- 58671-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN FORAGE EQUIPE DE POMPE A Component A: Local Request for Single Stage - One 21,590.5 Complete 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 51,376.00 MOTRICITE HUMAINE A development support Quotations Envelope 5 d 06 31 08 04 10-06 MAFOULSO III, A FAMARE ET A L'EP DE GONONI commune DE HILE ALIFA CM-CRC EXTREME NORD- 58631-CW-RFQ / TRAVAUX DE CONSTRUCTION TRAVAUX DE CONSTRUCTION D’UNE MINI Component A: Local Request for Single Stage - One 21,447.8 Complete 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 96,018.00 AEP PASTORAL EQUIPE DE development support Quotations Envelope 3 d 06 31 08 04 10-06 DEUX ABREUVOIRS, D’UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A ABASSOUNI, A DOLE BADA cmne DE HILE ALIFA CM-CRC EXTREME NORD- 58426-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE Component A: Local Request for Single Stage - One 43,152.3 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 52,286.00 Signed CLASSE EQUIPE ET D'UN development support Quotations Envelope 1 06 11 08 24 10-06 BLOC DE LATRINES A TROIS COMPARTIMENTS AU CES D'ADJAÏNE cmne DE KOUSSERI CM-CRC EXTREME NORD- 58417-CW-RFQ / CONSTRUCTION D'UN FORAGE EQUIPE DE POMPE A MOTRICITE HUMAINE AU CES D'ADJAINE ET D'UNE Component A: Local Request for Single Stage - One 104,068.0 82,972.8 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited Signed MINI AEP PASTORAL EQUIPE development support Quotations Envelope 0 2 06 11 08 24 10-06 DE DEUX ABREUVOIRS, D'UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A LACTA 1, ET A MASSAKI COMMUNE DE KOUSSERI CM-CRC EXTREME NORD- 58510-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN FORAGES EQUIPES DE POMPE Component A: Local Request for Single Stage - One 40,954.4 2018-05- 2018-05- 2018-07- 2018-10- 2018- IDA / 57180 Post Limited 49,640.00 Signed A MOTRICITE HUMAINE A development support Quotations Envelope 3 06 15 08 15 10-06 MASSIO-GOURGOURA, A NAGA NDIGUINI, A EP MALTAM. cmne DE MAKARI CM-CRC EXTREME NORD- 58677-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN Component A: Local Request for Single Stage - One 40,757.6 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Open - National 46,901.00 Signed HANGAR AVEC BLOC development support Quotations Envelope 9 06 01 10 09-29 LATRINE AU MARCHE DE BIAMO, cmne DE MAKARI CM-CRC EXTREME NORD- 58398-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE Component A: Local Request for Single Stage - One 43,675.8 2018-05- 2018-05- 2018-07- 2018-09- 2018- IDA / 57180 Post Limited 52,286.00 Signed CLASSE EQUIPE ET D'UN development support Quotations Envelope 4 06 15 08 10 10-06 BLOC DE LATRINES A TROIS COMPARTIMENTS A L'EP DE MALTAM cmne DE MAKARI CM-CRC EXTREME NORD- 58564-CW-RFQ / Travaux des MP D'INSTALLATION D'ECLAIRAGE PUBLIC (10 Component A: Local Request for Single Stage - One 2018-05- 2018-07- 2018- IDA / 57180 Post Limited 47,904.00 0.00 Canceled KITS)AVEC ENERGIE SOLAIRE development support Quotations Envelope 06 08 09-06 DE L'AXE MAIRIE DE HILE ALIFA-BRIGADE DE GENDARMERIE DE HILE Page 2 CM-CRC EXTREME NORD- 58697-CW-RFB / TRAVAUX DE CONSTRUCTION DE DEUX SALLES DE CLASSES EQUIPEES ET DE LATRINES AU CETIC DE OUZAL (LOT Component A: Local Single Stage - Two 230,463.0 2018-05- 2018-05- 2018-05- 2018-06- 2018-08- 2018-10- 2019- IDA / 57180 Post Request for Bids Open - National 0.00 Canceled N°1), CONSTRUCTION DE development support Envelope 0 01 08 06 17 30 04 02-01 DEUX SALLES DE CLASSES EQUIPEES A L'EP DE KORSAMBA ET L'EP DE KARAZAWA (LOT N°2), CONSTRUCTION D'UN BLOC MATERNEL L'EM DE MOZOGO CM-CRC EXTREME NORD- 58498-CW-RFQ / Travaux de Construction d'un bloc de 02 salles de classe Component A: Local Request for Single Stage - One 2018-05- 2018-07- 2018- IDA / 57180 Post Limited 57,225.00 0.00 Canceled équipées à EP de Gance et development support Quotations Envelope 06 08 10-06 d'un bloc de latrines à trois compartiments à L'EP TOLKOMARI cmne de Kolofata CM-CRC EXTREME NORD- 58260-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX (02) SALLES DE CLASSE EQUIPEES A EP Component A: Local Request for Single Stage - One 151,984.0 120,021. 2018-05- 2018-09- 2018-07- 2018-11- 2018- DE GANCE ET D'UN BLOC IDA / 57180 Post Limited Signed development support Quotations Envelope 0 73 06 24 08 29 10-06 DE LATRINES A L'EP TOLKOMARI ( LOT 01) CONSTRUCTION DE DEUX BLOC DE DEUX (02) SALLES DE CLASSE EQUIPEES CES TOLkomari CM-CRC EXTREME NORD- 111329-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 40,309.2 2019-04- 2019-06- 2019-10- 2019- de 02 salles de classe IDA / 57180 Post Open - National 49,652.00 Signed development support Quotations Envelope 3 06 01 08 08-30 équipé et d'un bloc de latrines au CETIC de Tchévi dans la commune de Bourha CM-CRC EXTREME NORD- 111255-CW-RFQ / Travaux de Travaux de Construction Component A: Local Request for Single Stage - One 54,869.3 2019-04- 2019-06- 2019-11- 2019- d'un forage PMH au CETIC IDA / 57180 Post Open - National 65,429.00 Signed development support Quotations Envelope 8 06 01 04 08-30 de Tchévi, à Zouvou- yolde à DOUVA et à ZEU dans la commune de Bourha CM-CRC EXTREME NORD- 111381-CW-RFQ / Travaux de Construction des caniveaux en BA à Bourha Component A: Local Request for Single Stage - One 52,560.1 2019-04- 2019-06- 2019-10- 2019- IDA / 57180 Post Open - National 69,336.00 Signed (axe Hamadou -ZRA-Bello development support Quotations Envelope 0 06 01 03 08-30 Hayatou) (lot 01) et à Boukoula face commissariat (lot 02) dans la Commune de Bourha CM-CRC EXTREME NORD- 111363-CW-RFB / Travaux de Construction de deux (02) blocs de dix (10) boutiques au marché de Component A: Local Single Stage - One 258,957.0 17,073,0 2019-04- 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-12- 2019- HINA cote A lot (01) et IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 76.62 01 24 06 18 21 17 24 22 19 11-19 Travaux de Construction de deux (02) blocs de dix (10) boutique et un bloc latrines vip au marché de HINA cote B lot (02), commune de HINA. CM-CRC EXTREME NORD- 111379-CW-RFQ / Travaux d'extension du reseau Component A: Local Single Stage - One 205,088.0 171,312. 2019-04- 2019-05- 2019-04- 2019-05- 2019-07- 2019-06- 2019-07- 2019-07- 2019-10- 2019- electrique de Dargala centre- IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 93 01 14 06 18 01 17 02 22 17 11-19 Roufirde, Roufirde- Gassayel, Gassayel- Guertogalwo dans la commune de Dargala CM-CRC EXTREME NORD- 111324-CW-RFQ / Travaux de Construction de 01 Under forage à PMH à Yoldé- Component A: Local Request for Single Stage - One 100,326.0 2019-04- 2019-06- 2019- IDA / 57180 Post Open - National 0.00 Implemen Naggué, à Tchakamadjé, development support Quotations Envelope 0 06 01 09-29 tation Yaga djibiwo, à Bakourebi (Abba wollo) Toukou mayel(Ouro-Bedem) et à MAYA ,commune de Pétté CM-CRC EXTREME NORD- 111354-CW-RFQ / Travaux de Construction d'un mini Under Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- adduction d'eau à energie IDA / 57180 Post Open - National 52,340.00 0.00 Implemen development support Quotations Envelope 06 01 08-30 photovoltaique pour usage tation agricole a fadare dans la commune de pette CM-CRC EXTREME NORD- 111372-CW-RFQ / Travaux de Construction de 01 Component A: Local Request for Single Stage - One 22,465.4 Complete 2019-04- 2019-06- 2019-11- 2019- IDA / 57180 Post Open - National 32,707.00 forage à PMH à EP lobokri et development support Quotations Envelope 8 d 06 01 04 08-30 à dahounga gholonguini, dans la Commune de Dziguilao CM-CRC EXTREME NORD- 111360-CW-RFB / Travaux de Construction d'un bloc de deux salles de classe Component A: Local Single Stage - One 207,364.0 160,942. 2019-04- 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-09- 2019- équipées et d'un bloc de IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 65 01 09 06 18 10 17 11 22 30 11-19 latrines à trois compartiments à EP REBEDE EP LOBOKRI, (lot1) EP MBITOU et CES SOUEYE (lot2) dans la Commune de Dziguilao CM-CRC EXTREME NORD- 111319-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 41,717.1 Complete 2019-04- 2019-06- 2019-08- 2019- de deux salles de classe IDA / 57180 Post Open - National 47,483.00 development support Quotations Envelope 8 d 06 01 27 08-30 équipées et d'un bloc latrine à trois compartiments à l'EP de Ligazang, commune de Mindif CM-CRC EXTREME NORD- 111254-CW-RFQ / Travaux de Construction et équipement d'un centre de Component A: Local Request for Single Stage - One 132,500.0 102,729. 2019-04- 2019-06- 2019-08- 2019- IDA / 57180 Post Open - National Signed santé intégré avec development support Quotations Envelope 0 06 06 01 27 09-29 incinerateur et un bloc de latrines à trois compartiments à MATFAI, dans la commune de Mindif CM-CRC EXTREME NORD- 111382-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 32,342.7 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National 38,095.00 Signed pastoral a energie development support Quotations Envelope 0 06 01 07 08-30 photovoltaique au marché à bétail à Moulvoudaye CM-CRC EXTREME NORD- 111373-CW-RFB / Travaux d'aménagement du marché à bétail en contruisant un Component A: Local Request for Single Stage - One 42,683.0 2019-04- 2019-06- 2019-12- 2019- parc à betail une cloture un IDA / 57180 Post Open - National 56,123.00 Signed development support Quotations Envelope 7 06 01 08 09-29 quai d'embarquement et un bloc latrine a trois compartiments dans la Commune de Moulvoudaye. CM-CRC EXTREME NORD- 111380-CW-RFB / Travaux de Construction de 02 sdc et 3 latriness à EP Component A: Local Single Stage - One 234,082.0 186,401. 2019-04- 2019-05- 2019-04- 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-10- 2019- KAOSSERE, à l'EP Ticheeo IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 14 01 02 06 18 31 17 01 22 11 10-20 Kolandi, à l'EP Tchoura-Bizili L1 et de 02 SDC EPB Touloum L2 et DE 2 SDC avec BUREAUX A L’EPP SAOTSAI L3 Cune de Touloum CM-CRC EXTREME NORD- 111358-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 13,255.7 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National 15,380.00 Signed équipé de PMH à lycee development support Quotations Envelope 0 06 01 26 07-31 bilingue dans la commue de Kaele CM-CRC EXTREME NORD- 111384-CW-RFQ / Travaux de Construction de 01 Component A: Local Request for Single Stage - One 31,562.3 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National 50,833.00 Signed forage à PMH à Gai gai, à EP development support Quotations Envelope 7 06 01 10 08-30 Golonpoui et à EP Kankwa, dans la commune de Datcheka CM-CRC EXTREME NORD- 111395-CW-RFQ / Travaux de Construction d'un bloc de 02 salles de classe Component A: Local Request for Single Stage - One 149,671.0 121,571. 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National Signed équipées et avec un bloc de development support Quotations Envelope 0 86 06 01 09 08-30 latrines à trois compartiments à EP Golonpoui , EP Kankrwa et EP Guidima , dans la commune de Datcheka CM-CRC EXTREME NORD- 111378-CW-RFQ / Travaux de Construction d'un bloc de deux salles de classe Component A: Local Request for Single Stage - One 175,994.0 67,097.9 2019-04- 2019-06- 2019-10- 2019- IDA / 57180 Post Open - National Signed équipées au CETIC de Vélé, development support Quotations Envelope 0 6 06 01 28 08-30 au CES de Widigue , au CES de Dabaye et au CES d'Agolla, dans la commune de Guémé CM-CRC EXTREME NORD- 111369-CW-RFQ / Travaux de Construction d'un hangar 52 places au marché de Component A: Local Request for Single Stage - One 57,109.6 2019-04- 2019-06- 2019-08- 2019- IDA / 57180 Post Open - National 67,637.00 Signed Gabaraye et Travaux de development support Quotations Envelope 1 06 01 27 08-30 Construction d'un bloc de latrines au marché de Gabaraye, commune de Guémé CM-CRC EXTREME NORD- 111362-CW-RFQ / Travaux de Construction d'un centre Component A: Local Request for Single Stage - One 127,436.0 106,966. 2019-04- 2019-06- 2019-10- 2019- IDA / 57180 Post Open - National Signed de santé intégré équipé et development support Quotations Envelope 0 95 06 01 08 09-29 un bloc de latrines au CSI à Nguéring, commune de Gueré CM-CRC EXTREME NORD- 111396-CW-RFQ / Component A: Local Request for Single Stage - One 27,215.6 2019-04- 2019-06- 2019-10- 2019- Construction d'un bloc de IDA / 57180 Post Open - National 32,708.00 Signed development support Quotations Envelope 4 06 01 09 08-30 05 boutiques au marché d'Ardaf Commune de Guere CM-CRC EXTREME NORD- 111388-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 12,359.6 2019-04- 2019-06- 2020-01- 2019- IDA / 57180 Post Open - National 15,311.00 Signed équipé de PMH à l'EP de development support Quotations Envelope 6 06 01 23 07-31 DAMA Djougong, commune de Kai kai CM-CRC EXTREME NORD- 111390-CW-RFQ / CONSTRUCTION DEUX Component A: Local Request for Single Stage - One 40,484.4 Complete 2019-04- 2019-06- 2019-08- 2019- IDA / 57180 Post Open - National 69,678.00 BLOCS DE CINQ (05) development support Quotations Envelope 0 d 06 01 22 08-30 BOUTIQUES AU MARCHÉ DE KALFOU, DANS LA COMMUNE DE KALFOU CM-CRC EXTREME NORD- 111371-CW-RFQ / Travaux de Construction d'un forage équipé de pompe à Component A: Local Request for Single Stage - One 57,350.2 2019-04- 2019-06- 2019-11- 2019- motricité humaine à Gandou IDA / 57180 Post Open - National 67,386.00 Signed development support Quotations Envelope 9 06 01 22 08-30 Golopo, au CES de Zaria, à Djada, réhabilitation d'un forage PMH à Delta Guibéré et Mandara, dans la commune de Kalfou CM-CRC EXTREME NORD- 111398-CW-RFQ / Under Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- Équipement en matériel IDA / 57180 Post Open - National 16,804.00 0.00 Implemen development support Quotations Envelope 06 01 07-31 médicaux au CSI de Takreo tation yoldeo Commune Kar Hay CM-CRC EXTREME NORD- 111260-CW-RFQ / Electrification du nouveau Component A: Local Request for Single Stage - One 152,907.0 134,395. 2019-04- 2019-06- 2019-12- 2019- marché de Guirvidig (lot 01) IDA / 57180 Post Open - National Signed development support Quotations Envelope 0 99 06 01 06 09-29 et de la localité de Yangah (lot 02) , dans la commune de Maga CM-CRC EXTREME NORD- 111368-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 13,773.4 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National 15,759.00 Signed équipé de pompe à development support Quotations Envelope 0 06 01 06 07-31 motricité humaine à Bindiriel Danghou, commue de Tchatibali CM-CRC EXTREME NORD- 111259-CW-RFB / Travaux de Construction d'un bloc de 02 salles de classe équipées et d'un bloc de Component A: Local Single Stage - One 244,743.0 78,116.8 2019-04- 2019-05- 2019-04- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- 2019-10- 2019- latrines à IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 5 01 02 06 18 13 17 14 22 23 11-19 troiscompartiments au CES Kamargui, à EP Goulourgou (lot 02), EP Bigi, EP de Djenreng (lot 02)et EP Waimou (lot 03) COMMUNE DE WINA CM-CRC EXTREME NORD- 111383-CW-RFQ / Travaux de Construction D’UN BLOC DE DEUX SALLES DE CLASSE Component A: Local Request for Single Stage - One 32,203.2 2019-04- 2019-06- 2019-12- 2019- IDA / 57180 Post Open - National 96,762.00 Signed AVEC BUREAUX EQUIPES au development support Quotations Envelope 2 06 01 03 09-29 CES de DJOGOIDI et au lycee de Vounaloum Commune de yagoua CM-CRC EXTREME NORD- 111365-CW-RFQ / Travaux de Construction d'un hangar Component A: Local Request for Single Stage - One 56,945.7 2019-04- 2019-06- 2019-10- 2019- IDA / 57180 Post Open - National 76,074.00 Signed de 28 places et d'une development support Quotations Envelope 2 06 01 08 09-29 boucherie au marché de Velé, dans la commune de Guémé CM-CRC EXTREME NORD- 111374-CW-RFQ / Travaux Under de Construction de 01 Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- IDA / 57180 Post Open - National 38,095.00 0.00 Implemen forage à énergie solaire à development support Quotations Envelope 06 01 08-30 tation CSI de Bosgoye, dans la commune de Wina CM-CRC EXTREME NORD- 111389-CW-RFQ / Travaux de Construction de 2 salles de classe et de latrines à l'EP de BIJE ( lot 01) , Component A: Local Request for Single Stage - One 80,535.3 2019-04- 2019-06- 2019-05- 2019- Construction de 2 salles de IDA / 57180 Post Open - National 96,542.00 Signed development support Quotations Envelope 6 06 01 27 08-30 classes à EPPB de TOKOMBERE et equipement en table bancs et bureaux au CES de makilingai (lot 02) dans la commune de Tokombere CM-CRC EXTREME NORD- 111392-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 55,757.8 Complete 2019-04- 2019-06- 2019-05- 2019- de deux salle de classe IDA / 57180 Post Open - National 67,299.00 development support Quotations Envelope 5 d 06 01 25 08-30 équipés et d'un bloc latrines à Magala Djamene dans la commune de Darak CM-CRC EXTREME NORD- 111385-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 10,462.3 Complete 2019-04- 2019-06- 2019-05- 2019- de Construction de 01 IDA / 57180 Post Open - National 19,048.00 development support Quotations Envelope 9 d 06 01 25 08-30 forage PMH à Magala Djamene, dans la commune de Darak CM-CRC EXTREME NORD- 111325-CW-RFB / Travaux de Construction d'un bloc de deux salles de classe Component A: Local Single Stage - One 226,885.0 94,907.5 2019-04- 2019-03- 2019-04- 2019-05- 2019-04- 2019-06- 2019-04- 2019-07- 2019-07- 2019- équipées et d'un bloc de IDA / 57180 Post Request for Bids Open - National Signed development support Envelope 0 3 01 28 06 18 24 17 25 22 10 11-19 latrines à trois compartiments à EP GADAFAI, au Lycée de Fotokol à EP Magadji et à EP de GUEGUERI, commune de Fotokol CM-CRC EXTREME NORD- 111261-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 31,367.2 Complete 2019-04- 2019-06- 2019-07- 2019- IDA / 57180 Post Open - National 34,286.00 de Construction d'un development support Quotations Envelope 5 d 06 01 02 08-30 magasin de stockage à Goulfey CM-CRC EXTREME NORD- 111367-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 30,637.2 2019-04- 2019-06- 2019-05- 2019- de Construction d'une mini IDA / 57180 Post Open - National 48,024.00 Signed development support Quotations Envelope 0 06 01 25 08-30 AEP pastorale à énergie solaire à fadja commune de Hilé Alifa CM-CRC EXTREME NORD- 111320-CW-RFQ / Travaux de Construction de 01 Component A: Local Request for Single Stage - One 36,050.5 Complete 2019-04- 2019-06- 2019-05- 2019- forage PMH à Michiska IDA / 57180 Post Open - National 49,510.00 development support Quotations Envelope 8 d 06 01 25 08-30 Mousgoum, OUNANGARE et NGADA 1, dans la commune de Logone Birni CM-CRC EXTREME NORD- 111327-CW-RFB / Travaux Component A: Local Request for Single Stage - One 40,199.6 2019-04- 2019-06- 2019-09- 2019- de Construction d'un IDA / 57180 Post Open - National 48,020.00 Signed development support Quotations Envelope 3 06 01 11 08-30 magasin de stockage à zigague, dans la commune de Waza CM-CRC EXTREME NORD- 111322-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 38,848.3 Complete 2019-04- 2019-06- 2019-07- 2019- de Construction d'un forage IDA / 57180 Post Open - National 50,855.00 development support Quotations Envelope 8 d 06 01 15 08-30 PMH à malia, NDIGUINA et MADA dans la commune de Waza Page 3 CM-CRC EXTREME NORD- 111377-CW-RFQ / Travaux d’extension du réseau électrique en moyenne Component A: Local Request for Single Stage - One 120,000.0 108,328. 2020-10- 2020-12- 2021-01- 2021- tension (MT) et basse IDA / 57180 Post Open - National Signed development support Quotations Envelope 0 90 05 16 08 12-31 tension (BT) triphasé et un transformateur H61 160 KVA dans les quartiers de Wourndé II et III, commune de Maroua 2 CM-CRC EXTREME NORD- 111376-CW-RFQ / Travaux d’electrification en moyenne Component A: Local Request for Single Stage - One 130,938.0 116,385. 2019-04- 2019-06- 2019-09- 2019- tension (MT) et basse IDA / 57180 Post Open - National Signed development support Quotations Envelope 0 17 06 01 02 09-29 tension (BT) monophasé de l'axe Barzao- barza foulbe- Barza-Guiziga, commune de Gazawa CM-CRC EXTREME NORD- 111355-CW-RFQ / Fourniture et installation de 07 lampadaires solaires Component A: Local Request for Single Stage - One 15,778.3 2019-04- 2019-06- 2019-08- 2019- composés de panneaux IDA / 57180 Post Open - National 19,048.00 Signed development support Quotations Envelope 5 06 01 27 07-31 solaires monocristallins et de batteries de type gel dans le centre urbain de vele commune DE GUEME CM-CRC EXTREME NORD- 111331-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- IDA / 57180 Post Open - National 15,238.00 0.00 Canceled équipé de pompe à development support Quotations Envelope 06 01 07-31 motricité humaine a Djafgadjie, commue de yagoua CM-CRC EXTREME NORD- 111386-CW-RFQ / Travaux de Construction d'un CSI Component A: Local Request for Single Stage - One 152,381.0 2019-04- 2019-06- 2019- équipé avec case d'astreinte, IDA / 57180 Post Open - National 0.00 Canceled development support Quotations Envelope 0 06 01 09-29 un incinérateur et un bloc de latrines au CSI Djiddeo Garre, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 111433-CW-RFQ / Component A: Local Request for Single Stage - One 2019-09- 2019-11- 2020- IDA / 57180 Post Open - National 10,000.00 0.00 Canceled réalisation d'un parc à bétail development support Quotations Envelope 07 02 04-30 dans la commune de Wina (GP) CM-CRC EXTREME NORD- 111394-CW-RFQ / Travaux de Construction d’un forage Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- IDA / 57180 Post Open - National 29,376.00 0.00 Canceled à énergie solaire avec development support Quotations Envelope 06 01 08-30 château au centre de santé de Djiddéo, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 111387-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019- de construction d'un forage IDA / 57180 Post Open - National 15,238.00 0.00 Canceled development support Quotations Envelope 06 01 07-31 pmh à l'EP Dolgaye Commune Kar Hay CM-CRC EXTREME NORD- 196682-CW-RFQ / Travaux de Construction d'un CSI Component A: Local Request for Single Stage - One 120,952.0 97,049.8 2020-11- 2021-01- 2021-01- 2021- équipé avec un incinérateur IDA / 57180 Post Open - National Signed development support Quotations Envelope 0 5 04 15 26 05-15 et un bloc de latrines au CSI Djiddeo Garre, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 196726-CW-RFQ / Travaux de Construction et Component A: Local Request for Single Stage - One 36,267.8 2020-11- 2021-01- 2021-01- 2021- équipement des blocs des IDA / 57180 Post Open - National 45,714.00 Signed development support Quotations Envelope 2 04 15 26 04-15 salles de classes et d'un bloc de latrines au CES de GUINADJI Commune de Maroua III CM-CRC EXTREME NORD- 196667-CW-RFQ / Travaux Under Component A: Local Request for Single Stage - One 10,958.0 2020-11- 2021-01- 2021-01- 2021- de Construction d’un forage IDA / 57180 Post Open - National 15,238.00 Implemen development support Quotations Envelope 5 04 15 26 03-16 PMH au centre de santé de tation Djiddéo Commune de Maroua III CM-CRC EXTREME NORD- 196678-CW-RFQ / REALISATION D’UN FORAGE EQUIPE DE POMPE A MOTRICITE HUMAINE A Under Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- GUIVEL, QUARTIER MERI IDA / 57180 Post Open - National 57,244.00 0.00 Implemen development support Quotations Envelope 04 15 04-15 CENTRE ET KILWO-VALTA tation ET L’ACHEVEMENT DE LA CONSTRUCTION DES FORAGES DE GADJAWAI ET NGUISSAR DANS LA COMMUNE DE MERI CM-CRC EXTREME NORD- 196722-CW-RFQ / Travaux de CONSTRUCTION D’UN Pending FORAGE PASTORAL A Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 41,546.00 0.00 Implemen ENERGIE SOLAIRE EQUIPE development support Quotations Envelope 04 15 04-15 tation D’UN château ET DE (02) ABREUVOIRS DANS LA LOCALITE DE DJONGDONG, COMMUNE DE WINA CM-CRC EXTREME NORD- 196718-CW-RFQ / Travaux Pending de Construction de 01 Component A: Local Request for Single Stage - One 2020-10- 2020-12- 2021- IDA / 57180 Post Open - National 38,095.00 0.00 Implemen forage à énergie solaire à development support Quotations Envelope 05 16 03-16 tation CSI de Bosgoye, dans la commune de Wina CM-CRC EXTREME NORD- 196724-CW-RFQ / Travaux de CONSTRUCTION D’UN FORAGE PASTORAL A Component A: Local Request for Single Stage - One 36,344.1 2020-11- 2021-01- 2021-01- 2021- IDA / 57180 Post Open - National 40,000.00 Signed ENERGIE SOLAIRE EQUIPE development support Quotations Envelope 7 04 15 26 04-15 D’UN château ET DE (02) ABREUVOIRS DANS LA LOCALITE DE MIZILING WAILA MAYO, COMMUNE DE GAZAWA CM-CRC EXTREME NORD- 196687-CW-RFQ / Travaux Component A: Local Request for Single Stage - One 14,150.1 2020-11- 2021-01- 2021-01- 2021- de Construction d'un forage IDA / 57180 Post Open - National 15,631.00 Signed development support Quotations Envelope 2 04 15 08 03-16 équipé de PMH de Yonkolel Commune de Dargala. CM-CRC EXTREME NORD- 196720-CW-RFQ / Travaux de Construction d'un forage Under équipé de PMH à lalepaki et Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 17,143.00 0.00 Implemen Acquisition d’une caisse à development support Quotations Envelope 04 15 03-16 tation outils pour l’entretien des forages dans la commune de Commune de Touloum CM-CRC EXTREME NORD- 196723-CW-RFQ / TRAVAUX DE CONSTRUCT D’UN BLOC DE 2 SALLES DE CLASSE EQUIPEES ET D’UN Under Component A: Local Request for Single Stage - One 2020-11- 2021-03- 2021- BLOC DE LATRINES À L'EP IDA / 57180 Post Open - National 87,964.00 0.00 Implemen development support Quotations Envelope 04 16 06-14 TCHOURA-BIZILI ET tation CONSTRUCTION D'UN BLOC DE 02 SALLES DE CLASSE ÉQUIPÉES À EP BILINGUE DE TOULOUM COMMUNE DE TOULOUM CM-CRC EXTREME NORD- 196721-CW-RFQ / TRAVAUX DE CONSTRUCTION D’UN BLOC Pending Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- DE DEUX SALLES DE CLASSE IDA / 57180 Post Open - National 45,113.00 0.00 Implemen development support Quotations Envelope 04 15 04-15 EQUIPEES ET D’UN BLOC DE tation LATRINES À TROIS COMPARTIMENTS à l'EP de ZANYAO Commune de YAGOUA CM-CRC EXTREME NORD- 196681-CW-RFQ / Travaux de Construction d’un forage équipé de pompe à Component A: Local Request for Single Stage - One 71,202.8 2020-11- 2021-01- 2021-01- 2021- IDA / 57180 Post Open - National 80,952.00 Signed motricité humaine à Dinao, development support Quotations Envelope 6 04 15 08 04-15 Louggol palé, Kodadjiho, Hamadalao et Golombeswé Commune KALFOU CM-CRC EXTREME NORD- 196688-CW-RFQ / Travaux Pending de Construction d'un forage Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 32,381.00 0.00 Implemen équipé de PMH à douang et development support Quotations Envelope 04 15 03-16 tation dingue-Gabaraye Commune de Gueme CM-CRC EXTREME NORD- 196677-CW-RFQ / Réalisation d’un (01) forage Component A: Local Request for Single Stage - One 41,275.2 2020-11- 2021-01- 2021-01- 2021- pastoral photovoltaïque et IDA / 57180 Post Open - National 47,200.00 Signed development support Quotations Envelope 8 04 15 08 04-15 de deux abreuvoirs au lieu- dit KOLOFATA GUIDI dans la commune de KOLOFATA CM-CRC EXTREME NORD- 196719-CW-RFQ / Travaux Under Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- de construction d'un forage IDA / 57180 Post Open - National 13,742.00 0.00 Implemen development support Quotations Envelope 04 15 04-15 équipé de PMH à Koulang tation Commune de MORA CM-CRC EXTREME NORD- 196685-CW-RFQ / Travaux de Construction d'un forage Component A: Local Request for Single Stage - One 14,195.0 2020-10- 2020-12- 2021-01- 2021- IDA / 57180 Post Open - National 16,190.00 Signed équipé de pompe à development support Quotations Envelope 1 05 16 08 02-14 motricité humaine à Guermé Kalfou Commune de Kalfou CM-CRC EXTREME NORD- 196671-CW-RFQ / Travaux de Construction d'un bloc de deux salle de classe Under équipées à l'EPB DE MADA Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 95,238.00 0.00 Implemen KOLKOCH ET A LEP development support Quotations Envelope 04 15 05-15 tation MAMBEZA et Construction d'un bloc de latrines à l'EPB DE MADA KOLKOCH ET Commune de Tokombere CM-CRC EXTREME NORD- 196727-CW-RFQ / TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR Pending LA CONSTRUCTION DE 04 Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 95,238.00 0.00 Implemen GUICHETS, 04 MAGASINS, development support Quotations Envelope 04 15 05-15 tation D’UN HANGAR D’ATTENTE ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE COMMUNE DE YAGOUA CM-CRC EXTREME NORD- 204463-CW-RFQ / travaux de construction d’un bloc Component A: Local Request for Single Stage - One 48,124.0 2020-12- 2021-02- 2021-01- 2021- de deux salles de classe IDA / 62240 Post Open - National 57,142.86 Signed development support Quotations Envelope 6 01 02 15 06-02 équipées avec bloc latrines à à l’EP d’Afadé Groupe 2 Commune Makary CM-CRC EXTREME NORD- Component C: 196964-CW-RFQ / Coordination, management, Request for Single Stage - One 2020-11- 2020-12- 2021- Aménagement d'un parking IDA / 62240 Post Limited 5,000.00 0.00 Canceled monitoring and evaluation Quotations Envelope 04 30 01-29 additionnel et des bureaux and communication de la crc-EN à maroua CM-CRC EXTREME NORD- 196679-CW-RFQ / Travaux de Construction d'un dalot mixte (BA et Beton Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 62,857.00 0.00 Canceled cyclopeen) de 2x2,5x6 m de development support Quotations Envelope 04 15 05-15 franchissement de 5 ml et 22 m de portée sur le mayo- Guili Commune de Bourha. CM-CRC EXTREME NORD- 196672-CW-RFQ / REALISATION D’UN FORAGE Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 15,238.00 0.00 Canceled EQUIPE DE POMPE A development support Quotations Envelope 04 15 03-16 MOTRICITE HUMAINE A Dolgaye Commune Kar Hay CM-CRC EXTREME NORD- 196725-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- IDA / 57180 Post Open - National 43,810.00 0.00 Canceled de deux salles de classe development support Quotations Envelope 04 15 04-15 équipées au lycee de Goundaye Commune de Dziguilao. CM-CRC EXTREME NORD- 196686-CW-RFQ / Travaux de Construction d'un bloc Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021- de 02 salles de classe IDA / 57180 Post Open - National 48,949.00 0.00 Canceled development support Quotations Envelope 04 15 04-15 équipées et d'un bloc de latrines à trois compartiments a EP Waimou COMMUNE DE WINA CM-CRC EXTREME NORD- 222521-CW-RFQ / travaux de construct et équipement Pending Component A: Local Request for Single Stage - One 152,380.0 2021-04- 2021-06- 2021- d’une salle d’hospitalisation IDA / 62240 Post Open - National 0.00 Implemen development support Quotations Envelope 0 13 08 10-06 et d'un bloc opératoire au tation CMA de Logone birni Commune de Logone birni CM-CRC EXTREME NORD- 222525-CW-RFQ / travaux de construct d’1 bloc maternel et latrines à EM Pending Component A: Local Request for Single Stage - One 148,470.0 2021-04- 2021-06- 2021- Logone birni (lot 01) et IDA / 62240 Post Open - National 0.00 Implemen development support Quotations Envelope 0 13 08 10-06 Réhabilitation de 6 salles de tation classe avec bureau attenant et équipement a EP Logone birni GPE 1 A (lot 02) Commune de Logone birni CM-CRC EXTREME NORD- 222842-CW-RFQ / Travaux de construct et équipement Pending Component A: Local Request for Single Stage - One 152,380.0 2021-04- 2021-06- 2021- d’une salle d’hospitalisation IDA / 62240 Post Open - National 0.00 Implemen development support Quotations Envelope 0 13 08 10-06 et d'un bloc opératoire au tation CMA de Fotokol Commune de Fotokol (A2011B1) CM-CRC EXTREME NORD- 222748-CW-RFQ / Travaux de construct d’un forage équipé de pompe à Pending Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- motricité humaine à Mada IDA / 62240 Post Open - National 73,180.00 0.00 Implemen development support Quotations Envelope 13 08 10-06 (Ngroh), à Goura 2 tation (Mosquée), à Labado, à Chou et réhabilitation d’un forage à Mada 1 (quartier Sara) Commune de Makary CM-CRC EXTREME NORD- 222522-CW-RFQ / Travaux Pending Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- de construct d’une mini AEP IDA / 62240 Post Open - National 38,020.00 0.00 Implemen development support Quotations Envelope 13 08 10-06 au camp des réfugiés tation d’Afadé Commune de Makary CM-CRC EXTREME NORD- 222828-CW-RFQ / Travaux Pending Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- de construct d’un forage IDA / 62240 Post Open - National 21,915.00 0.00 Implemen development support Quotations Envelope 13 08 09-06 équipé de PMH à Tagawa tation Commune de Waza CM-CRC EXTREME NORD- 222782-CW-RFQ / Travaux de réalisation d’un forage productif équipé de pompe à motricité humaine dans Pending Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- les localités de : YEME, IDA / 62240 Post Open - National 96,820.00 0.00 Implemen development support Quotations Envelope 13 08 10-06 DANDAYA, KOLDIMA, tation MADJINA et MEHE EMMA (Camp refugié) dans la Commune de Mora, Département du Mayo Sava. CM-CRC EXTREME NORD- 222778-CW-RFQ / Travaux de construct d’1 logement d'astreint et d'un mur de Pending cloture à l’EP IGAWA MEME Component A: Local Request for Single Stage - One 198,220.0 2021-04- 2021-06- 2021- IDA / 62240 Post Open - National 0.00 Implemen (lot1) et de construct de 4 development support Quotations Envelope 0 13 08 10-06 tation salles de classe équipées avec 1 bureau attenant et de latrines à l’EP de KOTCHEREHE (lot 02) Commune de Mora CM-CRC EXTREME NORD- 222959-CW-RFQ / TRAVAUX DE construct D’UN BLOC DE DEUX SALLES DE CLASSE EQUIPEES AVEC Pending BUREAU ET D’UN BLOC Component A: Local Request for Single Stage - One 189,335.0 2021-04- 2021-06- 2021- IDA / 62240 Post Open - National 0.00 Implemen LATRINE A TROIS development support Quotations Envelope 0 13 08 06-20 tation COMPARTIMENTS A L’EPB DE KOSSEHONE, L'EP WANDAI (lot 01) ET L'EP NDROCK (lot 02) DANS LA COMMUNE DE MOKOLO, DEPARTEMENT DU MAYO-TSANAGA. CM-CRC EXTREME NORD- 222785-CW-RFQ / Travaux de construct de 01 forage à Pending Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- Zamai, à Ldagodja-Tourou, IDA / 62240 Post Open - National 67,115.00 0.00 Implemen development support Quotations Envelope 13 08 10-06 à Ngolkodjala-Kosséhone et tation à Wandaï-djamboutou Commune de Mokolo Page 4 CM-CRC EXTREME NORD- 222977-CW-RFQ / TRAVAUX DE construct ET Pending EQUIPEMENT DU CENTRE DE Component A: Local Request for Single Stage - One 152,380.0 2021-04- 2021-06- 2021- IDA / 62240 Post Open - National 0.00 Implemen SANTE INTEGRE A development support Quotations Envelope 0 13 08 06-20 tation KOSSEHONE DANS LA COMMUNE DE MOKOLO, DEPARTEMENT DU MAYO- TSANAGA.(A2011B1) CM-CRC EXTREME NORD- 222983-CW-RFQ / Travaux Pending de Construction de 01 Component A: Local Request for Single Stage - One 2021-04- 2021-06- 2021- IDA / 57180 Post Open - National 34,286.00 0.00 Implemen forage à énergie solaire au development support Quotations Envelope 13 08 09-06 tation CSI de hile haoussa, dans la commune de kousseri (A2031C1) CM-CRC EXTREME NORD- 228212-CW-RFQ / travaux de construction d'un bloc Pending Component A: Local Request for Single Stage - One 2021-05- 2021-07- 2021- latrines a troix IDA / 57180 Post Open - National 9,000.00 0.00 Implemen development support Quotations Envelope 10 05 09-03 compartiement et tation construction d'un incinerateur au CSI de hile haoussa dans la Commune de kousseri CM-CRC EXTREME NORD- 237615-CW-RFQ / construct de 6 SDC équipées avec bureau et Request for Pending latrines à EP de BIAMO (lot Component A: Local Request for Single Stage - One 285,350.0 2021-06- 2021-08- 2022- IDA / 62240 Post Open - National Quotations (Non 0.00 Implemen 01) construct de 2 SDC avec development support Quotations Envelope 0 06 01 01-28 Bank-SPD) tation bureau a EP GRP 2 de BODO (lot 02) construct de 2 SDC avec bureau et latrines a EP de DJAMOUS (lot 03) Commune de Makary CM-CRC EXTREME NORD- 237617-CW-RFQ / travaux de construct de 4 salles de classe équipées avec 2 Request for Pending Component A: Local Request for Single Stage - One 253,980.0 2021-06- 2021-08- 2022- bureau à EP Fotokol (lot 01) IDA / 62240 Post Open - National Quotations (Non 0.00 Implemen development support Quotations Envelope 0 06 01 01-28 et construct de 4 salles de Bank-SPD) tation classe équipées avec 2 bureau et de 3 blocs de latrines à EP Fotokol (lot 02) Commune de Fotokol GOODS Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Status Evaluation Report as Issued Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual CM-CRC EXTREME NORD- 7991-GO-RFQ / Acquisition Component C: des fournitures de bureaux Coordination, management, Request for Single Stage - One 2017-03- 2017-05- 2017-05- 2017-06- 2017-05- IDA / 57180 Post Limited 10,000.00 8,556.39 Signed du matériels d'entretien et monitoring and evaluation Quotations Envelope 10 26 05 22 19 des fournitures diverses à la and communication CRC, Région de l'Extrême- Nord CM-CRC EXTREME NORD- 8000-GO-RFQ / Acquisition des consomables Component C: Informatiques (Encres, clés Coordination, management, Request for Single Stage - One 2017-03- 2017-05- 2017-05- 2017-07- 2017-05- IDA / 57180 Post Limited 10,000.00 5,074.65 Signed internet, CD, 2 disques durs monitoring and evaluation Quotations Envelope 10 26 05 22 19 externes Tera, 9 clés USB, and communication antivirus) à la CRC, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8001-GO-RFQ / Acquisition des fournitures pour Component C: véhicules ((5pneusX3véh), 3 Coordination, management, Request for Single Stage - One 2017-03- 2017-05- 2017-05- boîtes à pharmacie, 3 IDA / 57180 Post Limited 10,000.00 0.00 Canceled monitoring and evaluation Quotations Envelope 10 05 19 extincteurs,3 pelles, 6 and communication paires de gants, 3machettes, 3manteaux...) à la CRC, Région de l'Extrême- Nord CM-CRC EXTREME NORD- Component C: 8003-GO-RFQ / acquisition, Coordination, management, Request for Single Stage - One 2017-03- 2017-12- 2017-05- 2017-12- 2017-07- 2018-01- IDA / 57180 Post Limited 9,000.00 4,880.26 Completed aménagement et monitoring and evaluation Quotations Envelope 10 04 05 29 04 19 équipement de 2 conteneurs and communication de 40 pieds Component C: CM-CRC EXTREME NORD- Coordination, management, Request for Single Stage - One 2017-03- 2017-10- 2017-05- 2017-12- 2017-06- 2018-01- 8006-GO-RFQ / aquisition IDA / 57180 Post Limited 6,000.00 5,492.69 Completed monitoring and evaluation Quotations Envelope 10 03 05 22 04 15 et installation de 10 splits and communication CM-CRC EXTREME NORD- 8008-GO-RFQ / acquisition Component C: du kit à outils du Coordination, management, Request for Single Stage - One 2017-03- 2017-05- 2017-06- CCI(scléromètre, lazermètre, IDA / 57180 Post Limited 1,500.00 0.00 Canceled monitoring and evaluation Quotations Envelope 10 05 04 odomètre, pi à coulisse and communication électronique, EPI, Gilets de sauvetage CM-CRC EXTREME NORD- 8009-GO-RFQ / fourniture des services de maintenance Component C: électrique, climatiseurs, Coordination, management, Request for Single Stage - One 2017-03- 2017-05- 2017-05- 2017-07- 2018-05- IDA / 57180 Post Limited 4,800.00 2,176.75 Signed groupe électrogène, monitoring and evaluation Quotations Envelope 10 26 05 24 05 plolmberie et menuiserie à and communication la CRC, Région de l'Extrême- Nord CM-CRC EXTREME NORD- 38389-GO-RFQ / Equipement en table bancs, tables et chaise pour Component A: Local Request for Single Stage - One 2017-12- 2017-12- 2018-01- 2018-04- 2018-04- Enseignants et armoires au IDA / 57180 Post Limited 16,265.00 12,882.93 Signed development support Quotations Envelope 02 19 27 09 27 CETIC de Mogodé, à l'EP de SIR, à l'EPB de Rhoumsiki et à l'EP de Tchanawa dans la commune de Mogode CM-CRC EXTREME NORD- 58709-GO-RFQ / Acquisition des consomables Informatiques Component A: Local Request for Single Stage - One 2017-10- 2017-10- 2017-12- 2017-12- 2017-12- IDA / 57180 Post Limited 2,600.00 1,816.76 Signed (Encres, clés internet, CD, 2 development support Quotations Envelope 08 03 03 07 17 disques durs externes Tera, 9 clés USB, antivirus) à la CRC, Région de l'Extrême- Nord VAGUE 2 CM-CRC EXTREME NORD- 58529-GO-RFP / Fourniture d' une pirogue à moteur 30CV type E40GMHL (avec coque en fibre de verre) et Component A: Local Request for Single Stage - One 2018-05- 2018-06- 2018-07- 2018-10- 2018-08- 2018-12- IDA / 57180 Post Limited 26,974.00 25,881.80 Completed des équipements annexes: development support Quotations Envelope 06 13 01 23 30 21 portes tout tricycle tractable, pagaies, gilets de sauvetage, panneaux de labelisation) dans la cmne de KAIKAI CM-CRC EXTREME NORD- 111400-GO-RFQ / Fourniture en mobilier et Component A: Local Request for Single Stage - One 2019-04- 2019-06- 2019-08- 2019-07- petit materiel sanitaire de IDA / 57180 Post Open - National 49,494.00 38,928.38 Signed development support Quotations Envelope 06 01 27 31 CSI de Mindif, de Modjombodi, de Maoudine et de Mogom dans la commune de Mindif. CM-CRC EXTREME NORD- 196822-GO-RFQ / Fourniture et installation de Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021-01- 2021-04- 39 lampadaires a énergie IDA / 57180 Post Open - National 89,143.00 68,717.03 Signed development support Quotations Envelope 04 15 08 15 solaire dont 10 à Ndoukoula,14 à Dagaï Kola et de 15 à Loulou Commune de Ndoukoula CM-CRC EXTREME NORD- 196840-GO-RFQ / Fourniture et l'installation Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021-01- 2021-07- IDA / 57180 Post Open - National 16,571.00 12,009.59 Signed de 3 poteaux solaires à development support Quotations Envelope 04 15 08 14 Ouro Bone et 03 à Modjombodi Commune de Mindif. CM-CRC EXTREME NORD- 196835-GO-RFQ / Fourniture et installation de Component A: Local Request for Single Stage - One 2020-11- 2020-12- 2021-01- 2021-03- IDA / 57180 Post Open - National 31,429.00 27,298.43 Signed 12 poteaux solaires de l’axe development support Quotations Envelope 04 30 08 30 Sous-préfecture- Ngaoundéréo Commune de Kalfou CM-CRC EXTREME NORD- 196829-GO-RFQ / Pending Fourniture et installation Component A: Local Request for Single Stage - One 2020-11- 2020-12- 2021-02- IDA / 57180 Post Limited 9,905.00 0.00 Implement d’un kit solaire pour development support Quotations Envelope 04 30 28 ation l’alimentation en energie électrique du lycée de gabaraye. Commune Gueme. CM-CRC EXTREME NORD- Component C: Under 196917-GO-RFQ / Coordination, management, Request for Single Stage - One 2020-11- 2020-12- 2021-01- IDA / 62240 Post Limited 9,000.00 0.00 Implement Fourniture et installation monitoring and evaluation Quotations Envelope 04 30 29 ation des stores et moquettes à la and communication CRC EN CM-CRC EXTREME NORD- 196937-GO-RFQ / Fourniture et installation du Component C: matériel informatique (5 Under Coordination, management, Request for Single Stage - One 2020-11- 2020-11- 2020-12- 2021-01- ordinateurs portables pour IDA / 62240 Post Limited 18,000.00 0.00 Implement monitoring and evaluation Quotations Envelope 04 09 30 29 CR, RRSE, CPTR, CCI2 et ation and communication ARPM) et de reprographie (deux photocopieurs professionnels) à la CRC de l’Extrême-nord CM-CRC EXTREME NORD- 196954-GO-RFQ / Achat de Component C: matériels, équipements et Pending Coordination, management, Request for Single Stage - One 2020-11- 2020-12- 2021-01- mobilier de bureaux(chaises IDA / 62240 Post Limited 8,400.00 0.00 Implement monitoring and evaluation Quotations Envelope 04 30 29 réception(20), fauteuil ation and communication directeur(10), 2bureaux) à la CRC Région de l'Extrême- Nord CM-CRC EXTREME NORD- 196957-GO-RFQ / Component C: Acquisition des fournitures Coordination, management, Request for Single Stage - One 2020-11- 2020-11- 2020-12- 2020-12- 2021-01- IDA / 62240 Post Limited 8,000.00 7,316.27 Signed de bureaux et divers pour le monitoring and evaluation Quotations Envelope 04 26 30 14 29 compte de la CRC, Région and communication de l'Extrême-Nord CM-CRC EXTREME NORD- Component C: 196959-GO-RFQ / Coordination, management, Request for Single Stage - One 2020-11- 2020-10- 2020-12- 2020-12- 2021-06- Fourniture des services de IDA / 62240 Post Limited 4,937.00 8,659.75 Signed monitoring and evaluation Quotations Envelope 04 26 30 31 28 gardiennage à la CRC, and communication Région de l'Extrême-Nord CM-CRC EXTREME NORD- 196961-GO-RFQ / Fournture de service de Maintenance informatique Component C: (photocopieur, scanner, Coordination, management, Request for Single Stage - One 2020-11- 2020-10- 2020-12- 2020-12- 2021-12- IDA / 62240 Post Limited 4,800.00 4,428.86 Signed ordinateur portable , monitoring and evaluation Quotations Envelope 04 26 30 31 25 desktop et copieur à la CRC- and communication EN lot 01 et maintenance électricité, climatisseur, groupe électrogène et plomberie lot 02 à la CRC- EN CM-CRC EXTREME NORD- 196962-GO-RFQ / Acquisition de 6 Kits solaires pour les communes Component B: Support to Pending Request for Single Stage - One 2020-11- 2021-02- 2021-07- de Mora, Fotokol, Makary, IDA / 62240 the decentralization Post Open - National 69,600.00 0.00 Implement Quotations Envelope 21 01 31 Logone Birni, mokolo et process ation Waza pour le fonctionnement de SIMBA dans la Region de l'Extreme- nord CM-CRC EXTREME NORD- 204462-GO-RFQ / Pending Component A: Local Request for Single Stage - One 2020-12- 2021-02- 2021-04- fourniture en equipements IDA / 62240 Post Open - National 60,000.00 0.00 Implement development support Quotations Envelope 01 02 03 et medicaments aux CSI de ation Zizagué et CSI de Waza CM-CRC EXTREME NORD- 204459-GO-RFQ / fourniture en equipements Under Component A: Local Request for Single Stage - One 2020-12- 2021-02- 2021-04- et medicaments aux CSI de IDA / 62240 Post Open - National 60,000.00 0.00 Implement development support Quotations Envelope 01 02 03 Kossa et au CSI de Méhé ation Emma dans la commune de Commune de Mora CM-CRC EXTREME NORD- 196810-GO-RFQ / Fourniture en Equipement en 60 tables bancs et un Component A: Local Request for Single Stage - One 2020-11- 2020-12- 2021-02- IDA / 57180 Post Limited 9,905.00 0.00 Canceled bureau à l'EP Guinlaye et development support Quotations Envelope 04 30 28 111 tables bancs et un bureau à l'EP BOGO SIRATARE I Commune de BOGO CM-CRC EXTREME NORD- 196816-GO-RFQ / Fourniture en équipement Component A: Local Request for Single Stage - One 2020-10- 2020-12- 2021-02- en 200 tables bancs, 4 IDA / 57180 Post Open - National 12,952.00 0.00 Canceled development support Quotations Envelope 05 16 14 bureaux, 4 chaises rembourrées et 4 armoires à l'EP MAGA IIB Commune de Maga. CM-CRC EXTREME NORD- 196797-GO-RFQ / Component A: Local Request for Single Stage - One 2020-11- 2021-01- 2021-03- Fourniture en Équipement IDA / 57180 Post Open - National 12,801.00 0.00 Canceled development support Quotations Envelope 04 15 16 en matériel médicaux au CSI de Takreo yoldeo Commune Kar Hay CM-CRC EXTREME NORD- Component C: 222789-GO-RFQ / Pending Coordination, management, Request for Single Stage - One 2021-04- 2021-06- 2021-12- Fourniture de Achat de 3 IDA / 62240 Post Limited 6,000.00 0.00 Implement monitoring and evaluation Quotations Envelope 13 08 05 scanners professionnels à la ation and communication CRC de l’Extrême-nord ( C101203) CM-CRC EXTREME NORD- 222792-GO-RFQ / Component C: Pending Acquisition de Coordination, management, Request for Single Stage - One 2021-04- 2021-06- 2021-07- IDA / 62240 Post Limited 15,000.00 0.00 Implement consommables monitoring and evaluation Quotations Envelope 13 08 08 ation informatiques et autres and communication fournitures dela CRC, Région de l'EN ( C101303) CM-CRC EXTREME NORD- 222730-GO-RFQ / Component C: Pending Acquisition des fournitures Coordination, management, Request for Single Stage - One 2021-04- 2021-06- 2021-07- IDA / 62240 Post Limited 9,000.00 0.00 Implement de bureaux et divers pour le monitoring and evaluation Quotations Envelope 13 08 08 ation compte de la CRC, Région and communication de l'Extrême-Nord (C101301) CM-CRC EXTREME NORD- 222841-GO-RFQ / Component C: Pending Acquisition des fournitures Coordination, management, Request for Single Stage - One 2021-04- 2021-06- 2021-12- IDA / 62240 Post Limited 4,935.00 0.00 Implement pour véhicules à la CRC, monitoring and evaluation Quotations Envelope 13 08 05 ation Région de l'Extrême-Nord and communication (C101304) CM-CRC EXTREME NORD- 222795-GO-RFQ / Component C: Pending Acquisition d'un vehicule Coordination, management, Request for Single Stage - One 2021-04- 2021-06- 2021-08- IDA / 62240 Post Open - National 50,000.00 0.00 Implement pick up pour le compte de monitoring and evaluation Quotations Envelope 13 08 07 ation la CRC, Région de l'Extrême- and communication Nord (C101205) CM-CRC EXTREME NORD- 222798-GO-RFQ / FOURNITURE ET INSTALLATION D’UNE MINI Pending CENTRALE SOLAIRE AU CSI Component A: Local Request for 2021-04- 2021-06- 2021-09- IDA / 62240 Post 56,935.00 0.00 Implement DE KOSSA, DANS LA development support Quotations 13 08 06 ation COMMUNE DE MORA, DEPARTEMENT DU MAYO- SAVA, REGION DE L’EXTREME – NORD. (A2011B1) NON CONSULTING SERVICES Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Bid Evaluation Loan / Credit Market Procurement Prequalificati Process Prequalification Bidding Documents Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Report and Signed Contract No. Approach Process on (Y/N) Status Evaluation Report as Issued Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes Recommendation Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned for Award Actual Planned Actual Planned Actual CM-CRC EXTREME NORD- 111430-NC-RFQ / Selection d'une agence d'edition pour la production d'un bulletin Component A: Local Request for Single Stage - One 2019-06- 2019-08- 2019-11- 2020-08- IDA / 57180 Post Open - National 47,000.00 31,781.53 Signed trimestriel d'informations development support Quotations Envelope 09 04 15 03 communales(47 communes) dans la region de l'Extreme- nord CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Opening of Combined Loan / Credit Market Contract Type Estimated Process Expression of Request for Evaluation of Contract / Description Component Review Type Method Amount Terms of Reference Request for Technical Proposals Evaluation Report Signed Contract No. Approach Amount (US$) Status Interest Notice Proposals as Issued Technical Proposal Completion (US$) Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual CM-CRC EXTREME NORD- 8076-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-07- 2018-05- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 20,007.04 Completed l'actualisation du PCD de la 10 04 31 14 10 13 22 18 06 14 05 process Selection commune de Guéré, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8082-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-07- 2018-05- IDA / 57180 the decentralization Post Qualification Open - National 26,970.00 22,183.49 Signed l'actualisation du PCD de la 10 04 31 14 10 13 22 18 11 14 process Selection commune de Kalfou, Région de l'Extrême-Nord Page 5 CM-CRC EXTREME NORD- 8088-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-07- 2018-05- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 18,355.82 Signed l'actualisation du PCD de la 10 04 31 14 09 13 22 18 06 14 process Selection commune de Mindif, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8094-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-07- 2018-05- IDA / 57180 the decentralization Post Qualification Open - National 53,760.00 30,571.90 Signed l'actualisation du PCD de la 10 04 31 14 10 13 27 18 06 14 process Selection commune de Gazawa., Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8093-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-06- 2018-05- IDA / 57180 the decentralization Post Qualification Open - National 15,570.00 29,601.16 Signed l'actualisation du PCD de la 10 04 31 14 09 13 22 18 27 14 process Selection commune de Guidiguis, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8097-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-03- 2017-05- 2017-03- 2017-05- 2017-06- 2017-06- 2018-03- 2017-07- 2018-07- 2018-05- IDA / 57180 the decentralization Post Qualification Open - National 57,600.00 18,445.45 Signed l'actualisation du PCD de la 10 04 31 14 10 13 27 18 06 14 process Selection commune de Dargala, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29268-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 8,628.26 Completed l'actualisation du PCD de la 20 04 11 24 10 24 22 28 06 24 05 process Selection commune de WINA, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29270-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 26,460.00 29,798.62 Signed l'actualisation du PCD de la 20 23 11 24 09 24 27 28 16 24 process Selection commune de BOURHA, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29272-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 23,663.61 Signed l'actualisation du PCD de la 20 04 11 24 10 24 27 28 06 24 process Selection commune de Hina, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29273-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-06- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 15,570.00 9,919.43 Signed l'actualisation du PCD de la 20 04 11 24 10 24 27 28 25 24 process Selection commune de Koza, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29274-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 53,760.00 37,441.16 Signed l'actualisation du PCD de la 20 04 11 24 10 24 27 28 06 24 process Selection commune de Mozogo., Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29276-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-10- 2017-11- 2017-12- 2018-01- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 57,600.00 0.00 Canceled l'actualisation du PCD de la 20 11 24 24 28 24 process Selection commune de Kolofata, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29277-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-01- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 57,600.00 0.00 Canceled l'actualisation du PCD de la 20 04 11 24 10 24 28 24 process Selection commune de Kolofata, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29280-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-10- 2017-11- 2017-12- 2018-01- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 26,970.00 0.00 Canceled l'actualisation du PCD de la 20 11 24 24 28 24 process Selection commune de Goulfey, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29281-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-10- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 26,460.00 17,141.65 Signed l'actualisation du PCD de la 20 04 11 24 14 24 22 28 06 24 process Selection commune de FOTOKOL, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29282-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 -2,518.29 Completed l'actualisation du PCD de la 20 04 11 24 15 24 20 28 06 24 05 process Selection commune de Blangoua, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29284-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2017-09- 2017-05- 2017-10- 2017-11- 2017-06- 2017-12- 2018-03- 2018-01- 2018-07- 2018-11- IDA / 57180 the decentralization Post Qualification Open - National 15,570.00 31,593.26 Signed l'actualisation du PCD de la 20 04 11 24 15 24 22 28 11 24 process Selection commune de Darak, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 8089-CS-CQS / sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-09- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- IDA / 57180 the decentralization Post Qualification Open - National 26,460.00 19,922.77 Signed l'actualisation du PCD de la 15 28 06 19 07 18 21 23 01 19 process Selection commune de Datcheka, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29269-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-09- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- IDA / 57180 the decentralization Post Qualification Open - National 26,970.00 18,485.99 Signed l'actualisation du PCD de la 15 28 06 19 07 18 21 23 01 19 process Selection commune de TCHATIBALI, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29278-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-09- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 63,060.00 -1,222.01 Completed l'actualisation du PCD de la 15 28 06 19 10 18 21 23 01 19 05 process Selection commune de Waza, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29285-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-09- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- IDA / 57180 the decentralization Post Qualification Open - National 53,760.00 1,279.72 Signed l'actualisation du PCD de la 15 28 06 19 10 18 21 23 01 19 process Selection commune deHILE-ALIFA., Région de l'Extrême-Nord CM-CRC EXTREME NORD- 58613-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-09- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 26,070.00 24,573.33 Completed l'actualisation du PCD de la 15 28 06 19 10 18 21 23 01 19 05 process Selection cmne de Goulfey, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 58629-CS-CQS / Sélection Component B: Support to Consultant d'un consultant pour 2018-06- 2018-10- 2018-07- 2018-08- 2018-11- 2018-09- 2018-12- 2018-10- 2019-03- 2019-08- 2020-08- IDA / 57180 the decentralization Post Qualification Open - National 57,600.00 -2,073.39 Completed l'actualisation du PCD de la 15 02 06 19 06 18 21 23 01 19 05 process Selection cmne de Kolofata, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 58563-CS-CQS / Sélection de deux consultants (OAL) Consultant Component A: Local 2017-04- 2017-03- 2017-04- 2017-06- 2017-04- 2017-07- 2017-05- 2017-08- 2017-09- 2017-11- pour la collecte et la saisie IDA / 57180 Post Qualification Open - National 85,727.00 546,754.14 Signed development support 05 30 26 09 19 09 27 13 27 11 des données du score cadre Selection deans 21 cmnes , Région de l'Extrême-Nord CM-CRC EXTREME NORD- 111119-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2020-09- 2019-06- 2019-08- 2019-09- 2019-10- 2020-08- d'un OAL pour IDA / D2990 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 14 22 05 04 09 04 l'actualisation légère du PCD process Selection de la commune de KAI KAI CM-CRC EXTREME NORD- 111118-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2021-05- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 31 l'actualisation légère du PCD process Selection de la commune de YAGOUA CM-CRC EXTREME NORD- 111218-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-12- 2019-09- 2020-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 04 l'actualisation légère du PCD process Selection de la commune de TOKOMBERE CM-CRC EXTREME NORD- 111121-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 04 l'actualisation légère du PCD process Selection de la commune de NDOUKOULA CM-CRC EXTREME NORD- 111120-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 04 l'actualisation légère du PCD process Selection de la commune de MOUTOURWA CM-CRC EXTREME NORD- 111122-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 04 l'actualisation légère du PCD process Selection de la commune de MOGODE CM-CRC EXTREME NORD- 111231-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 04 l'actualisation légère du PCD process Selection de la commune de MAKARY CM-CRC EXTREME NORD- 111232-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- 2020-09- 2019-10- 2019-11- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 29 04 14 09 08 l'actualisation légère du PCD process Selection de la commune de LOGONE BIRNI CM-CRC EXTREME NORD- 111123-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2020-07- 2019-09- 2020-05- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 14 04 26 09 04 l'actualisation légère du PCD process Selection de la commune de KAELE CM-CRC EXTREME NORD- 111124-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2019-07- 2019-06- 2019-08- 2020-07- 2019-09- 2020-05- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 25 22 05 15 04 26 09 04 l'actualisation légère du PCD process Selection de la commune de BOGO CM-CRC EXTREME NORD- 111230-CS-CQS / Sélection Component B: Support to Consultant 2019-06- 2020-09- 2019-06- 2019-08- 2019-09- 2019-10- 2020-08- d'un OAL pour IDA / 57180 the decentralization Post Qualification Open - National 13,000.00 0.00 Canceled 01 14 22 05 04 09 04 l'actualisation légère du PCD process Selection de la commune de MOKOLO CM-CRC EXTREME NORD- 222975-CS-CQS / Sélection d'un consultant (OSC) pour la collecte et la saisie des Component B: Support to Consultant Pending 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022-02- données du score cadre IDA / 62240 the decentralization Post Qualification Open - National 36,400.00 0.00 Implementation 08 29 12 12 16 12 dans 7 communes (darak process Selection hile alifa, blangoua, Fotokol, kousseri zina et waza) , Région de l'Extrême-Nord ( B201103) CM-CRC EXTREME NORD- 222973-CS-CQS / Sélection d'un consultant (OSC) pour la collecte et la saisie des Component B: Support to Consultant Pending 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022-02- données du score cadre IDA / 62240 the decentralization Post Qualification Open - National 36,400.00 0.00 Implementation 08 29 12 12 16 12 deans 7 communes (mora, process Selection kolofata, meri, maroua 1, Bourha, Koza et mokolo) , Région de l'Extrême-Nord ( B201103) CM-CRC EXTREME NORD- 222960-CS-CQS / Sélection d'un consultant (OSC) pour la collecte et la saisie des Component B: Support to Consultant Pending 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022-02- données du score cadre IDA / 62240 the decentralization Post Qualification Open - National 31,200.00 0.00 Implementation 08 29 12 12 16 12 deans 6 communes (bogo, process Selection pette, maroua 3, TOULOUM,Mindif , GUIDIGUIS°, Région de l'Extrême-Nord ( B201103) CM-CRC EXTREME NORD- 222968-CS-CQS / Sélection d'un consultant (OSC) pour la collecte et la saisie des Component B: Support to Consultant Pending 2021-04- 2021-04- 2021-06- 2021-07- 2021-08- 2022-02- données du score cadre IDA / 62240 the decentralization Post Qualification Open - National 31,200.00 0.00 Implementation 08 29 12 12 16 12 deans 6 communes (Krhay, process Selection Kalfou, guere, wina datcheka et kaikai), Région de l'Extrême-Nord ( B201103) INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated Contract / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract No. Approach Amount (US$) Status Contract Completion (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-CRC EXTREME NORD- 8103-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2017-03- 2017-05- 2017-03- 2017-06- 2017-04- 2017-06- 2017-05- 2017-12- 2017-06- IDA / 57180 Post Consultant Limited 3,000.00 3,805.88 Signed environnementales de development support 06 08 11 12 01 16 06 28 20 Selection Construction d'un bloc saitaire et d'un bloc de latrines au CSI de Djiddeo garre, commune de Maroua III CM-CRC EXTREME NORD- 8107-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-03- 2017-05- 2017-03- 2017-06- 2017-04- 2017-06- 2017-05- 2017-06- 2017-06- 2018-01- environnementales de IDA / 57180 Post Consultant Limited 2,600.00 1,522.35 Completed development support 06 08 11 13 01 16 06 19 20 25 Construction de 2 forages Selection équipés de PMH, un à Dolddosewo et un Ngouroré et la construction d'un bief à Kossewa, commune Maroua II CM-CRC EXTREME NORD- 8110-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-03- 2017-03- 2017-04- 2017-05- 2017-06- environnementales de IDA / 57180 Post Consultant Limited 3,000.00 0.00 Canceled development support 06 11 01 06 20 Construction d'un bloc Selection sanitaire et d'un bloc de latrines au centre de santé de Rhumzou, dans la commune de Mogodé CM-CRC EXTREME NORD- 8112-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local 2017-03- 2017-05- 2017-03- 2017-09- 2017-04- 2017-09- 2017-05- 2017-10- 2017-06- 2017-10- IDA / 57180 Post Consultant Limited 2,400.00 2,093.23 Completed de Construction d'un bloc development support 06 08 11 05 01 12 06 20 20 23 Selection de deux salles de classe équipées d'un bloc latrines a trois compartiements à l'EP de Sedek Ourogabdo et au CES de BOGO CM-CRC EXTREME NORD- 8114-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité MP de Individual Component A: Local 2017-03- 2017-05- 2017-03- 2017-09- 2017-04- 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- Construction d 6 forage IDA / 57180 Post Consultant Limited 5,600.00 3,615.59 Completed development support 06 08 11 05 01 12 06 20 20 23 équipé de pompe à Selection motricité humaine et e deux (02) forages équipé de pompe à motricité humaine et rehabilitation de deux forages exista commune de BOGO CM-CRC EXTREME NORD- 8118-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction et Individual équipement d'01 bloc de 02 Component A: Local 2017-03- 2017-04- 2017-03- 2017-04- 2017-04- 2017-10- 2017-05- 2017-11- 2017-08- IDA / 57180 Post Consultant Limited 6,186.00 3,107.61 Signed salles de classe et d'un bloc development support 06 03 11 07 01 11 06 01 04 Selection de latrines à trois compartiments à l'EP Dogba, Gayack dans Construction d1 hangar et d'un bloc de latrines A PAPATA CM-CRC EXTREME NORD- 8122-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-10- 2017-05- 2017-10- 2017-08- magasin de stockage à Kéné- IDA / 57180 Post Consultant Limited 3,304.00 2,572.86 Signed development support 06 10 11 08 01 26 06 30 04 Kéné, Construction d'un Selection bloc de 02 salles de classe équipées à l'EP de Djafgué, et Construction d'un bloc de latrines à l'EP de Djafgué cne Page 6 CM-CRC EXTREME NORD- 8126-CS-INDV / sélection d'un consultant pour le sui/contrôle des travaux de Individual réalisation de 6 forages Component A: Local 2017-03- 2017-03- 2017-04- 2017-05- 2017-08- IDA / 57180 Post Consultant Limited 3,840.00 0.00 Canceled équipés de PMH à Tchékéhi, development support 06 11 01 06 04 Selection Mbokouré, Magaldao Toupéo, Soukkoungo Galdima, Bourango et Bandalaré dans la commune de Pétté CM-CRC EXTREME NORD- 8130-CS-INDV / sélection d'un consultant pour le suivi/controle des travaux Individual de Construction d'un forage Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-11- 2017-05- 2017-11- 2017-08- IDA / 57180 Post Consultant Limited 3,200.00 3,047.82 Signed pastoral à énergie solaire development support 06 10 11 08 01 08 06 20 04 Selection Balaza Lawane (Tchalloudi mango) 1 forage pastoral à énergie solaire à Kongola Saïd, commune de Maroua 3 CM-CRC EXTREME NORD- 8154-CS-INDV / sélection d'un consultant pour le suivi/controle des travaux de Construction d'un bloc Individual Component A: Local 2017-03- 2017-03- 2017-04- 2017-05- 2017-08- de 02 salles de classe IDA / 57180 Post Consultant Limited 5,544.00 0.00 Canceled development support 06 11 01 06 04 équipées et d'un bloc de Selection latrines à trois compartiments à l'EP de Mayel Béi, à l'EP de Bao Hosséré II et à l'EP de Palaoudi, commune Maroua 1 CM-CRC EXTREME NORD- 8157-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual de construction d'un bloc Component A: Local 2017-03- 2017-03- 2017-04- 2017-05- 2017-08- IDA / 57180 Post Consultant Limited 2,292.00 0.00 Canceled maternel à l'école Maternelle development support 06 11 01 06 04 Selection de Zokok-Laddo et branchement au réseau d'alimentation en eau potable, commune de Maroua 1 CM-CRC EXTREME NORD- 8159-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-06- 2017-04- 2017-06- 2017-05- 2017-06- 2017-08- 2018-02- de Construction de trois IDA / 57180 Post Consultant Limited 1,840.00 1,591.10 Completed development support 06 10 11 13 01 30 06 30 04 20 forages équipés de pompe à Selection motricité humaine à Ouro Dow, Goni Bello et Yoldéo Guiziga, Commune Maroua 1 CM-CRC EXTREME NORD- 8161-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual de Construction d'un bloc Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-06- 2017-05- 2017-06- 2017-08- IDA / 57180 Post Consultant Limited 3,690.00 3,041.89 Signed de 02 salles de classe development support 06 10 11 08 01 30 06 30 04 Selection équipées et d'un bloc de latrines à trois compartiments à l'EP Masfaï et au CES de Boula, commune de Mokolo CM-CRC EXTREME NORD- 8163-CS-INDV / sélection d'un consultant pour le Individual suivi/contrôle des travaux Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-06- 2017-05- 2017-09- 2017-08- IDA / 57180 Post Consultant Limited 1,350.00 1,113.47 Signed de Construction de 2 development support 06 10 11 08 01 06 06 14 04 Selection forages équipés de PMH un à Ouro Kessoum et à Mounam, commune de Mokolo CM-CRC EXTREME NORD- 8165-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-12- 2017-05- 2018-01- 2017-08- 2018-04- de construction d'un IDA / 57180 Post Consultant Limited 3,510.00 3,246.38 Completed development support 06 10 11 08 01 28 06 31 04 24 ouvrage de franchissement Selection et d'assainissement sur le mayo-kwayaga, dans la commune de Mogodé CM-CRC EXTREME NORD- 8166-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual de Construction d'un bloc Component A: Local 2017-03- 2017-03- 2017-03- 2017-04- 2017-04- 2017-06- 2017-05- 2017-06- 2017-08- 2017-09- IDA / 57180 Post Consultant Limited 3,618.00 2,776.20 Completed de 02 salles de classe development support 06 31 11 07 01 14 06 21 04 27 Selection équipées et d'un bloc de latrines à trois compartiments à l'EP de Saoudjo et au CES de Madaka, commune de Bogo CM-CRC EXTREME NORD- 8246-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux de Construction d'un forage Individual Component A: Local 2017-03- 2017-03- 2017-03- 2017-04- 2017-04- 2017-06- 2017-05- 2017-06- 2017-08- 2017-08- équipé de PMH à Dambaye IDA / 57180 Post Consultant Limited 4,913.00 1,125.49 Completed development support 06 31 11 07 01 14 06 21 04 16 et à Bagalaf etAménagement Selection d'un bas-fond avec un forage à énergie solaire à Ouro Mésséré pour les cultures maraichères, commune de Bogo CM-CRC EXTREME NORD- 8247-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux deconstruction d'un bloc de Individual deux (02) salles de classe Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-11- 2017-05- 2017-11- 2017-09- IDA / 57180 Post Consultant Limited 7,152.00 6,461.92 Signed equipees et un (01) bloc development support 06 10 11 08 01 10 06 15 03 Selection latrine a trois (03) compartiments a l'EP de honkol, a l'EP de darsala, a l'EP de dabanga et l'equipement en me CM-CRC EXTREME NORD- 8248-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux deconstruction d'un forage Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-06- 2017-05- 2017-06- 2017-09- 2017-09- équipé d'une pompe à IDA / 57180 Post Consultant Limited 3,280.00 3,398.97 Completed development support 06 10 11 08 01 02 06 10 03 29 motricité humaine à l' EP de Selection Darsala, l' EP de Dabanga, et un forage pastoral solaire au village Sahaba 1, l'EP groupe de Logone birni et à EP Ho CM-CRC EXTREME NORD- 8249-CS-INDV / sélection d'un consultant pour le Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-05- 2017-04- 2017-11- 2017-05- 2018-01- 2017-09- 2018-06- suivi/contrôle des travaux IDA / 57180 Post Consultant Limited 4,584.00 3,598.46 Completed development support 06 10 11 08 01 24 06 20 03 13 de réalisation d'une mare Selection artificielle à Mogon dans la commune de Moutourwa CM-CRC EXTREME NORD- 8250-CS-INDV / sélection d'un consultant pour le suivi/contrôle des travaux Individual Component A: Local 2017-03- 2017-04- 2017-03- 2017-07- 2017-04- 2017-07- 2017-05- 2017-07- 2017-08- de construction d'un bloc de IDA / 57180 Post Consultant Limited 4,614.00 4,102.81 Signed development support 06 10 11 17 01 24 06 24 04 deux salles de classe et de Selection deux blocs de latrines à l'EP de Afadé et à l'EP de NGré dans la commune de Makary CM-CRC EXTREME NORD- 8251-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de Construction de 6 Component A: Local 2017-03- 2017-04- 2017-03- 2017-09- 2017-04- 2017-09- 2017-05- 2018-01- 2017-08- IDA / 57180 Post Consultant Limited 3,840.00 3,192.11 Signed forages équipés de PMH à development support 06 10 11 18 01 25 06 11 04 Selection Tchékéhi, Mbokouré, Magaldao Toupéo, Soukkoungo Galdima, Bourango et Bandalaré dans la commune de Pétté CM-CRC EXTREME NORD- 8252-CS-INDV / Sélection de 3 consultants pour Individual l'appui du CCI dans la Component A: Local 2017-03- 2017-03- 2017-04- 2017-05- 2018-05- IDA / 57180 Post Consultant Limited 27,632.00 0.00 Canceled passation des marchés, le development support 06 11 01 06 06 Selection suivi et l'exécution des projets à la CRC, Région de l'Extrême-Nord CM-CRC EXTREME NORD- 29287-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-07- 2018-01- 2017-09- IDA / 57180 Post Consultant Limited 8,500.00 5,328.23 Completed de Construction d'un forage development support 20 08 25 09 16 16 20 10 04 22 Selection PMH à Guivel Méri centre, à Houloum, à Tchaki Djébé, à Kilwo, à Mbozo Mofou, à Balewa, à Nguissar, au quartier Hot CM-CRC EXTREME NORD- 29288-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-07- 2018-01- 2017-09- environnementales des MP IDA / 57180 Post Consultant Limited 2,400.00 3,425.29 Completed development support 20 08 25 12 16 16 20 10 04 22 de Construction d'un bloc Selection de deux salles de classe équipées avec un bloc latrines au CES de Manguirdla et Construction d'un magasin de stockage à CM-CRC EXTREME NORD- 29289-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-11- 2017-08- 2018-01- 2017-10- environnementales des MP IDA / 57180 Post Consultant Limited 2,000.00 2,367.54 Completed development support 20 08 25 19 16 20 01 04 04 de Construction 01 bloc de Selection deux salles de classe équipées avec un bloc latrines à l'EP de Djagalaï et au CES de Hardé dans la commune de MRA IER CM-CRC EXTREME NORD- 29291-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-06- 2018-01- 2017-10- environnementales des MP IDA / 57180 Post Consultant Limited 1,600.00 1,694.12 Completed development support 20 08 25 13 16 16 20 19 04 04 de Construction d'un forage Selection équipé de pompe à motricité humaine à Nyamdjidim et à Zébé dans la commune de Maroua I (2 FORAGES PMH) CM-CRC EXTREME NORD- 29292-CS-INDV / Sélection d'un consultant pour les Etudes des des MP de Construction d'un bloc de Individual Component A: Local 2017-09- 2017-05- 2017-11- 2017-06- 2017-11- 2017-06- 2018-01- 2017-07- 2018-02- 2017-09- 02 salles de classe équipées IDA / 57180 Post Consultant Open 3,750.00 4,231.37 Completed development support 21 08 09 12 30 16 04 04 18 21 avec 01 bloc de latrines à Selection l'EP de Ndrock Tourou, à EP Zili Yolel, à EP Moufou Sud, EP de Ldamang et au CES Mandaka commune mokolo CM-CRC EXTREME NORD- 29293-CS-INDV / Sélection d'1 consultant pour Individual Component A: Local 2017-09- 2017-05- 2017-11- 2017-06- 2017-11- 2017-09- 2018-01- 2017-09- 2018-02- 2017-09- l'élaboration des Etudes des IDA / 57180 Post Consultant Open 5,000.00 3,001.30 Completed development support 21 08 09 12 30 08 04 14 18 21 MP de Construction de 08 Selection forage PMH dans la commune de mokolo CM-CRC EXTREME NORD- 29295-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-12- 2018-01- 2018-01- environnementales MP IDA / 57180 Post Consultant Limited 1,600.00 2,664.12 Completed development support 20 08 25 12 16 16 20 20 04 10 Construction d'1 bloc de Selection deux salles de classe équipées et 1 bloc de latrine à l'EP de Pitoa Kolara et à l'EP de Badadji dans la cne de moulvoudaye CM-CRC EXTREME NORD- 29297-CS-INDV / Sélection d'un consultant pour Etudes de faisabilité des MP de Construction d'un forage Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-05- 2017-10- 2017-06- 2017-11- 2017-08- 2018-01- 2017-09- PMH à Hourgoum, IDA / 57180 Post Consultant Limited 3,000.00 2,568.97 Completed development support 20 08 25 13 16 18 20 28 04 28 Goumlaye, Kadaye Selection Djamboutou, à Gadja Padjonré et au Lycée de Kolara , EP piotao kaloara et Ep bardadji dans la commune de Moulvoudaye CM-CRC EXTREME NORD- 29299-CS-INDV / Sélection d'un consultant pour Etudes d des MP de Construction d'1 bloc de Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-07- 2018-01- 2017-09- deux salles de classe et d'1 IDA / 57180 Post Consultant Limited 4,000.00 5,113.88 Completed development support 20 08 25 12 16 16 20 10 04 22 bloc de latrine à l'EP Selection MOUFTOUM , au CES GOURIA, Lycée de SIR, à l'EPB de RHUMZOU , à l'EPB de KWASHIMANDA et équipement tables banc cne de MOZOGO CM-CRC EXTREME NORD- 29300-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-09- 2018-01- 2017-09- environnementales des MP IDA / 57180 Post Consultant Limited 2,000.00 2,534.91 Completed development support 20 08 25 12 16 16 20 07 04 22 de Construction d'un Selection ouvrage d'assainissement et de franchissement sur le Mayo Teki à TEKI commune de MOGODE CM-CRC EXTREME NORD- 29301-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Sélection d'un consultant Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-07- 2018-01- 2017-09- pour l'élaboration des IDA / 57180 Post Consultant Limited 4,950.00 3,805.88 Completed development support 20 08 25 06 16 16 20 10 04 22 Etudes de faisabilité Selection techniques et environnementales des MP de Construction d'un forage équipé à PMH (8 Forages) da commune de MOGODE CM-CRC EXTREME NORD- 29302-CS-INDV / Sélection d'un consultant pour Elaboration étude des MP de Construction d'1 bloc de Individual Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-06- 2018-01- 2017-09- deux salles de classe IDA / 57180 Post Consultant Limited 4,000.00 4,894.14 Completed development support 20 08 25 12 16 16 20 16 04 22 équipées et d'1 bloc de Selection latrines à l'EP Souaye Dana, à l'EP Domo Doukou, à l'EP de Riganda, à l'EP Kao-Galak et à l'EP Bilingue Vounsia CNE YAGOUA CM-CRC EXTREME NORD- 29303-CS-INDV / Sélection d'un consultant pourétude des MP de Construction d'un Individual forage equipe de PMH à l'EP Component A: Local 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2017-06- 2017-11- 2017-06- 2018-01- 2017-09- IDA / 57180 Post Consultant Limited 3,000.00 4,869.96 Completed Souaye Dana, à l'EP Domo development support 20 08 25 12 16 16 20 18 04 22 Selection Doukou, à l'EP de Riganda, à l'EP Kao-Galak et à l'EP Bi Vounsia dans la commune de Yagoua CM-CRC EXTREME NORD- 38284-CS-INDV / ÉTUDES DE FAISABILITÉ DES MP DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE CLASSE Individual ÉQUIPÉES À L'EP KOZA I, À Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 6,600.00 2,458.96 Completed L'EP KOZA II, À L'EP development support 26 11 01 02 22 06 26 16 12 04 Selection DAKOTCHERE, À L'EP DE KILDA ET À L'EP DE GABOUA, CONSTRUCTION D'UN BLOC LATRINES A L'EP DE GABOUA, DANS LA COMMUNE DE KOZA CM-CRC EXTREME NORD- 38285-CS-INDV / ETUDES de faisabilité des MP de Individual Construction d'un forage Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 1,000.00 1,134.91 Completed équipé de pompe à development support 27 11 02 02 23 06 27 16 13 04 Selection motricité humaine a l'EP de KILDA dans la commune de KOZA dans la commune de KOZA CM-CRC EXTREME NORD- 38286-CS-INDV / ETUDES de faisabilité des MP d'équipement en tables Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- banc et bureaux ( 60 tables IDA / 57180 Post Consultant Limited 1,800.00 756.60 Completed development support 27 11 02 02 23 06 27 16 13 04 banc + 02 bureaux et 02 Selection Chaises) a l'EP de KOZA I , l'EP de KOZA II, a l'EP de GABOUA, dans la commune de KOZA CM-CRC EXTREME NORD- 38287-CS-INDV / ETUDES de faisabilité des MP de Construction d'un bloc de deux salles de classe Individual équipées et d'un bloc de Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 6,000.00 2,601.01 Completed latrines à trois development support 27 11 02 02 23 06 27 16 13 06 Selection compartiments au CES MAZAYA, à l'EPB de MIDRE, l'EP ZELE SOULEDE, l'EP BAO DALBAI et l'EP DOUMDERE dans la commune de ROUA dans la Page 7 CM-CRC EXTREME NORD- 38288-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-12- 2018-03- 2018-03- équipé de pompe à IDA / 57180 Post Consultant Limited 4,000.00 2,811.29 Completed development support 26 11 01 02 22 06 26 20 12 06 motricité humaine à l'EP Selection ZELE SOULEDE, à l'EP BAO DALBAI, au CES MAZAYA et à l'EP DOUMDERE dans la commune de ROUA CM-CRC EXTREME NORD- 38289-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- équipé de pompe à IDA / 57180 Post Consultant Limited 3,000.00 2,054.80 Signed development support 27 14 02 14 23 06 27 06 13 motricité humaine au CETIC Selection D'OUZAL, l'EP GOKORO et l'EM de MOSKOTA dans la commune MOZOGO CM-CRC EXTREME NORD- 38290-CS-INDV / ETUDES des MP de Construction de deux salles de classe équipées et d'1 bloc latrines Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2018-10- 2018-03- au CETIC D'OUZAL, l'EP IDA / 57180 Post Consultant Limited 9,600.00 10,413.78 Signed development support 27 14 02 14 23 06 27 09 13 NGUETCHEWE ,de deux Selection salles de classe équipées à l'EPB MOZOGO, L'EP KORASAMBA, l'EP KARAZAWA l'EP GOKORO et d1 atelier à la SAR/SM et CETIC MOZOGO CM-CRC EXTREME NORD- 38291-CS-INDV / ETUDES de faisabilité des MP de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- Construction d'un hangar de IDA / 57180 Post Consultant Limited 2,400.00 2,680.17 Signed development support 27 14 02 14 23 06 27 09 13 marché au marché de Selection MAWA MOZOGO et au marche de MOSKOTA CM-CRC EXTREME NORD- 38292-CS-INDV / ETUDES de faisabilité des MP de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- Construction d'un bloc IDA / 57180 Post Consultant Limited 2,400.00 2,405.98 Signed development support 27 14 02 14 23 06 27 09 13 maternelle équipée à L'EM Selection DE MOSKOTA et d'une cloture a l'EM de MOZOGO CM-CRC EXTREME NORD- 38293-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2018-12- équipé de pompe à IDA / 57180 Post Consultant Limited 4,000.00 1,903.46 Completed development support 27 11 02 02 23 06 27 16 13 20 motricité humaine à Ildin- Selection toungouloun, Wouro Wandou Moufou, Narewa Et Makoumba dans la commune de GAZAWA CM-CRC EXTREME NORD- 38294-CS-INDV / ETUDES de faisabilité des MP de Construction de deux salles de classe équipées et d'un Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- bloc de latrines à l'EP de IDA / 57180 Post Consultant Limited 3,600.00 2,577.87 Completed development support 27 11 02 02 23 06 27 16 13 23 wouyang, à l'EP de GONOZO Selection et construction d'un atelier de maçonnerie et d'un bloc latrine au CETIC de Loulou A NDOUKOULA CM-CRC EXTREME NORD- 38295-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual équipé de pompe PMH à Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 5,600.00 2,575.26 Completed l'EP de Ouro-Nangué, à l'EP development support 27 11 02 02 23 06 27 16 13 23 Selection MOUDVAR, à l'EP de Gonozo, à Fakalao, à EP Louguéré, à Talandé et à Hodango CMNE NDOUKOULA CM-CRC EXTREME NORD- 38296-CS-INDV / ETUDES de faisabilité des MP d' Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2018-11- Extension du réseau IDA / 57180 Post Consultant Limited 6,000.00 4,722.68 Completed development support 27 11 02 02 23 06 27 16 13 17 électrique Loulou- Selection Ndoukoula-Dagaï (22km) COMMUNE NDOUKOULA CM-CRC EXTREME NORD- 38297-CS-INDV / ETUDES de faisabilité des MP de Construction de deux salles de classe équipées et Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- d'un bloc de latrines à l'EP IDA / 57180 Post Consultant Limited 5,400.00 2,161.74 Completed development support 27 11 02 02 23 06 27 16 13 13 de Bihoré, à l'EP de Troké, à Selection l'EP de Goua et à l'EP de Youaye Mbogue et équipement des salles de classe au lycée de TCHATIBALI CM-CRC EXTREME NORD- 38298-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual équipé de pompe à Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 4,500.00 2,368.41 Completed motricité Humaine à Gané development support 27 11 02 02 23 06 27 16 13 13 Selection (quartier bili), à L'EP de Saouringwa, à Danglao(quartier Bidomo), Kada'a Glonhene, Bindiriel Danghou commune Tchatibali CM-CRC EXTREME NORD- 38299-CS-INDV / ETUDES de faisabilité des MP de Construction d'un bloc de deux salles de classe Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- équipées et d'un bloc de IDA / 57180 Post Consultant Limited 6,000.00 2,593.97 Completed development support 27 11 02 02 23 06 27 11 13 06 latrines à trois Selection compartiments l'EP de Balané, au CES de Sirlawé, l'EP de Rey-foulaye, l'EP de Datchéka-takréo,l'EP de Sadielle COMMUNE DE KARHAY. CM-CRC EXTREME NORD- 38300-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage équipé de pompe à Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- motricité Humaine à l'EP de IDA / 57180 Post Consultant Limited 5,600.00 2,577.87 Completed development support 27 11 02 02 23 06 27 16 13 06 Balané, à l'école des parents Selection de Gouloulou, à l'EP de Rey- foulaye, à l'EP de Sadielle, à l'EP de Damdama, au CES de Sirlawé, au CSI de Doukoula 1 CM-CRC EXTREME NORD- 38301-CS-INDV / ETUDES de faisabilité des MP de Construction d'un Centre de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- Santé intégré équipé, un IDA / 57180 Post Consultant Limited 2,800.00 2,828.45 Completed development support 27 11 02 28 23 06 27 16 13 06 incinérateur, et un bloc de Selection latrines au Centre de Santé Intégré de Doukoula 1 commune KARHAY CM-CRC EXTREME NORD- 38302-CS-INDV / ETUDES de faisabilité des MP de Construction de deux salles de classe équipées et d'un  Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- bloc latrines au Lycée tech IDA / 57180 Post Consultant Limited 6,000.00 3,045.09 Signed development support 27 11 02 02 23 06 27 09 13 de Gobo, l' EP GUIRIOU Selection CENTRE, Lycée de DOM PYA, la SAR/ SM Gobo, et la construction d'un bloc latrines au marché de GOBO et de NOULD CM-CRC EXTREME NORD- 38303-CS-INDV / ETUDES de faisabilité des MP de construction d'un forage pastoral équipé de pompe à Individual énergie photovoltaïque à Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- IDA / 57180 Post Consultant Limited 4,000.00 3,026.19 Signed GALAM BASSA et la development support 27 11 02 02 23 06 27 09 13 Selection construction d'un forage équipé de PMH au CES de POLGUE, à l'EP GUIRIOU CENTRE et à la SAR/ SM de Gobo CM-CRC EXTREME NORD- 38304-CS-INDV / ETUDES de faisabilité des MP de Construction d'un  bloc de deux salles de classe Individual équipées et construction Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 4,800.00 2,819.53 Completed d'un  bloc latrine à trois development support 27 11 02 02 23 06 27 09 13 14 Selection compartiment au CES de Doukroye, au CETIC de Doreissou, à l'EP de Dama - Djougong et à l'EP de DJOWELNANDJI communeKAIKAI CM-CRC EXTREME NORD- 38305-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage équipé de PMH au CETIC de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- Doressou, a l'EP de Daram - IDA / 57180 Post Consultant Limited 5,400.00 2,819.53 Completed development support 27 11 02 02 23 06 27 09 13 14 Djougong, à l' EP de Daloa Selection (Doukroye), au Lycée de Bégué Palam, au Lycée de Daram-Doreissou centre, à l'EP de Memié COMMUNE DE KAI-KAI CM-CRC EXTREME NORD- 38306-CS-INDV / ETUDES de faisabilité des MP de Construction d'un  bloc de deux salles de classe Individual équipées et de construction Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-11- IDA / 57180 Post Consultant Limited 8,000.00 4,728.78 Completed d'un  bloc de latrines à trois development support 27 11 02 02 23 06 27 16 13 30 Selection compartiments à l'EP de Doumrou, à l'EP Mizao, à l'EP de Bipaing, a l' EP de Goudjouing, au lycée de Mindjil, à E CM-CRC EXTREME NORD- 38307-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage équipé de PMH à Bibalé - Individual Gambour, à Goubara, à Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-11- IDA / 57180 Post Consultant Limited 5,400.00 4,699.43 Completed Kourong, à Kassilé. Et development support 27 11 02 02 23 06 27 16 13 30 Selection l'actualisationdes microprojets de réhabilitation de la mare de Garey Kaélé et la construction d'un forage pastoral à énergie so CM-CRC EXTREME NORD- 38308-CS-INDV / ETUDES de faisabilité des MP de Construction d'un  bloc de deux salles de classe Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- équipées à EP Dourdoum, IDA / 57180 Post Consultant Limited 3,000.00 2,689.95 Completed development support 27 11 02 02 23 06 27 18 13 15 à EP Kalaf, à EP Mayel - Selection Guinadji et Construction d'un  bloc latrine à trois compartiment à EP Mayel - Guinadji COMMUNE DE Moutourwa CM-CRC EXTREME NORD- 38309-CS-INDV / ETUDES de faisabilité du MP de Individual Construction d'un forage Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 1,000.00 2,086.45 Completed équipé de PMH À development support 27 11 02 02 23 06 27 17 13 15 Selection GANAHA,EP DOURDOUM, À EP KALAF, À EP MAYEL - GUINADJI COMMUNE DE Moutourwa CM-CRC EXTREME NORD- 38310-CS-INDV / ETUDES de faisabilité du MP Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- d'électrification en énergie IDA / 57180 Post Consultant Limited 3,600.00 1,879.77 Signed development support 27 11 02 02 23 06 27 16 13 solaire de la localité de Selection Magada carrefour COMMUNE DE Moutourwa CM-CRC EXTREME NORD- 38311-CS-INDV / ETUDES de faisabilité des MP de Construction d'un bloc de deux salles de classe Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-12- 2018-03- 2017-12- équipées à l'EP de IDA / 57180 Post Consultant Limited 6,000.00 4,905.06 Completed development support 27 14 02 14 23 25 27 05 13 09 Gouvaka, à l'EP de Majé, à Selection l'EP de Malika et construction de 01 magasin de stockage à Oignon à Sera -Idoumda et à Kourgui COMMUNE DE MORA CM-CRC EXTREME NORD- 38312-CS-INDV / ETUDES de faisabilité des MP de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-12- 2018-01- 2017-12- 2018-03- 2017-12- Construction d'un forage IDA / 57180 Post Consultant Limited 2,000.00 2,633.18 Completed development support 27 14 02 14 23 05 27 05 13 09 équipé de pompe à Selection motricité Humaine à Koulang, à Mangavé COMMUNE DE MORA CM-CRC EXTREME NORD- 38313-CS-INDV / ETUDES de faisabilité des MP de Construction d'un forage Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- équipé de pompe à IDA / 57180 Post Consultant Limited 3,000.00 1,962.54 Completed development support 27 14 02 28 23 06 27 16 13 19 motricité humaine dans les Selection localités de WOLORDE- TCABAWOL, BAKA FOURWA ET DJALTAR dans la commune de TOKOMBERE CM-CRC EXTREME NORD- 38314-CS-INDV / ETUDES de faisabilité des MP de Construction d'un bloc de Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-10- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- deux salles de classe IDA / 57180 Post Consultant Limited 3,200.00 2,689.95 Completed development support 27 11 02 02 23 06 27 06 13 19 équipées à l'EP DE Selection TSABATSABA,L'EP CHEOULEW, l'EP TAZANG ET AU CES DE MAKALINGAI dans la commune de TOKOMBERE CM-CRC EXTREME NORD- 38315-CS-INDV / ETUDES de faisabilité des MP de Construction d'un bloc de deux salles de classe Individual Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- équipées à l'EP DE GANCE, IDA / 57180 Post Consultant Limited 3,000.00 3,961.78 Completed development support 27 14 02 14 23 25 27 25 13 14 AU CES DE TOLKOMARI et Selection Construction d'un bloc de latrines a trois compartiments au CES de TOLKOMARI, commune de KOLOFATA CM-CRC EXTREME NORD- 38316-CS-INDV / ETUDES de faisabilité du MP de Construction d'un forage pastoral équipé de pompe à Individual énergie solaire avec Component A: Local 2017-11- 2017-09- 2017-12- 2017-09- 2017-12- 2017-10- 2018-01- 2017-10- 2018-03- 2017-12- IDA / 57180 Post Consultant Limited 2,800.00 3,961.78 Completed réservoir et abreuvoirs à development support 27 14 02 14 23 25 27 25 13 14 Selection Kolofata-Guidi et Construction d'un forage équipé de pompe à motricité humaine au CES de TOLKOMARI dans la commune de KOLO CM-CRC EXTREME NORD- 38317-CS-INDV / ETUDES DE FAISABILITE DU MP CONSTRUCTION D'UN BLOC Individual DE DEUX SALLES DE CLASSE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,650.00 1,505.22 Completed EQUIPE ET D'UN BLOC DE development support 27 06 02 06 23 17 27 20 13 22 Selection LATRINES A TROIS COMPARTIMENTS A L'EP KOUTOULA COMMUNE DE BLANGOUA CM-CRC EXTREME NORD- 38318-CS-INDV / ETUDES Individual DE FAISABILITE DU MP Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 2,700.00 2,409.68 Completed CONSTRUCTION D'UNE development support 27 06 02 06 23 17 27 20 13 22 Selection GARE ROUTIERE AVEC BLOC LATRINES A BLANGOUA CM-CRC EXTREME NORD- 38319-CS-INDV / ELABORATION DES ETUDES Individual DE FAISABILITE DU MP DE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 2,000.00 1,880.84 Completed CONSTRUCTION D'UN development support 27 06 02 06 23 17 27 17 13 25 Selection FORAGE EQUIPE DE PMH A ABINKRO ET A KOUTALA DANS LA COMMUNE DE BLANGOUA CM-CRC EXTREME NORD- 38320-CS-INDV / ETUDES DE FAISABILITE DU MP D Individual CONSTRUCTION D'UN Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 2,700.00 2,539.13 Completed FORAGE PASTORAL A development support 27 06 02 06 23 17 27 17 13 21 Selection ENERGIE SOLAIRE A MAGALAKABIR, A KARENA ET A NAGA COMMUNE DE DARAK CM-CRC EXTREME NORD- 38321-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN BLOC Individual DE DEUX SALLES DE CLASSE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,650.00 1,472.58 Completed EQUIPE ET D'UN BLOC DE development support 27 06 02 06 23 17 27 20 13 23 Selection LATRINES A TROIS COMPARTIMENTS A L'EP HILELLE COMMUNE DE GOULFEY Page 8 CM-CRC EXTREME NORD- 38322-CS-INDV / ETUDES DE FAISABILITE DU MP DE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- CONSTRUCTION D'UN IDA / 57180 Post Consultant Limited 1,170.00 1,099.00 Completed development support 27 06 02 06 23 17 27 20 13 23 HANGAR AU MARCHE DE Selection GOULFEY GANA COMMUNE DE GOULFEY CM-CRC EXTREME NORD- 38323-CS-INDV / ETUDES DE FAISABILITE DU MP DE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- CONSTRUCTION D'UN IDA / 57180 Post Consultant Limited 1,140.00 1,017.42 Completed development support 27 06 02 06 23 17 27 20 13 23 MAGASIN DE STOCKAGE A Selection GOULFEY COMMUNE DE GOULFEY CM-CRC EXTREME NORD- 38324-CS-INDV / ETUDES DE FAISABILITE DU MP DE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- CONSTRUCTION D'UNE IDA / 57180 Post Consultant Limited 2,700.00 2,409.68 Completed development support 27 06 02 14 23 17 27 20 13 23 GARE ROUTIERE AVEC BLOC Selection LATRINES A GOULFEY COMMUNE DE GOULFEY CM-CRC EXTREME NORD- 38325-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN FORAGE PASTORAL A Individual ENERGIE SOLAIRE A Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 4,000.00 3,761.68 Completed DJAGALAT, A AKMASSIRAK development support 27 06 02 06 23 17 27 17 13 23 Selection ET DE LA CONSTRUCTION D'UN FORAGE EQUIPES DEPMH A MOUGALAM, A LA GARE ROUTIERE DE GOULFEY, A TAWOULWEBE ET A L'EP HILELE COMMUNE DE GOULFEY CM-CRC EXTREME NORD- 38326-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN CENTRE DE SANTE INTEGRE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- EQUIPE, AVEC BLOC DE IDA / 57180 Post Consultant Limited 4,500.00 4,016.14 Completed development support 27 06 02 14 23 17 27 20 13 23 LATRINES ET UN Selection INCINERATEUR A HILE HAOUSSA COMMUNE DE HILE ALIFA " CM-CRC EXTREME NORD- 38327-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN BLOC Individual DE DEUX SALLES DE CLASSE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,650.00 1,472.58 Completed EQUIPE ET D'UN BLOC DE development support 27 06 02 14 23 17 27 20 13 23 Selection LATRINES A TROIS COMPARTIMENTS AU CES D'ADJAÏNE COMMUNE DE HILE ALIFA CM-CRC EXTREME NORD- 38328-CS-INDV / TUDE DES MICROPROJETS DE CONSTRUCTION D'UN FORAGE PASTORAL A Individual ENERGIE SOLAIRE A LACTA Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 2,800.00 2,633.18 Completed 1, MASSAKI ET development support 27 06 02 06 23 17 27 17 13 23 Selection CONSTRUCTION D'UN FORGAE EQUIPE DE POMPE A MOTRICITE HUMAINE AU CES D'ADJAINE ET AU CSI DE HILE HAOUSSA COMMUNE DE HILE ALIFA CM-CRC EXTREME NORD- 38329-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION DE QUATRE FORAGES EQUIPES DE POMPE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- A MOTRICITE HUMAINE AU IDA / 57180 Post Consultant Limited 2,800.00 2,554.31 Completed development support 27 06 02 06 23 17 27 17 13 22 MARCHE A BETAIL DE Selection MADA, A MASSIO- GOURGOURA, A NAGA NDIGUINI, A EP MALTAM COMMMUNE DE MAKARY CM-CRC EXTREME NORD- 38330-CS-INDV / ETUDES DE FAISABILITE DU MP DE Individual CONSTRUCTION D'UNE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,500.00 1,338.71 Completed CLOTURE ET D'UN BLOC DE development support 27 06 02 14 23 17 27 20 13 22 Selection LATRINES AU MARCHE A BETAIL DE MADA COMMMUNE DE MAKARY CM-CRC EXTREME NORD- 38331-CS-INDV / ETUDES DE FAISABILITE DU MP DE Individual Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- CONSTRUCTION D'UN IDA / 57180 Post Consultant Limited 1,170.00 1,044.20 Completed development support 27 06 02 06 23 17 27 20 13 22 HANGAR AVEC BLOC Selection LATRINE AU MARCHE DE BIAMO, COMMMUNE DE MAKARY CM-CRC EXTREME NORD- 38332-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN BLOC Individual DE DEUX SALLES DE CLASSE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,650.00 1,505.22 Completed EQUIPE ET D'UN BLOC DE development support 27 06 02 06 23 17 27 20 13 23 Selection LATRINES A TROIS COMPARTIMENTS A L'EP DE MALTAM COMMMUNE DE MAKARY CM-CRC EXTREME NORD- 38333-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN BLOC Individual DE DEUX SALLES DE CLASSE Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,650.00 1,472.58 Completed EQUIPE ET D'UN BLOC DE development support 27 06 02 14 23 17 27 20 13 25 Selection LATRINES A TROIS COMPARTIMENTS A L'EP GONONI COMMUNE DE HILE ALIFA CM-CRC EXTREME NORD- 38334-CS-INDV / ETUDES DE FAISABILITE DU MP DE CONSTRUCTION D'UN FORAGE PASTORAL A Individual ENERGIE SOLAIRE A Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 5,700.00 5,360.39 Completed ABASSOUNI, A HILE ALIFA 1, development support 27 06 02 06 23 17 27 17 13 25 Selection A FADJA, A DOLE BADA ET CONSTRUCTION D'UN FORAGE EQUIPE DE PMH A MAFOULSO III, A FAMARE ET A L'EP DE GONONI COMMUNE DE HILE ALIFA CM-CRC EXTREME NORD- 38335-CS-INDV / ETUDES DE FAISABILITE DES MP D'INSTALLATION Individual D'ECLAIRAGE PUBLIC (10 Component A: Local 2017-11- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-01- 2017-11- 2018-03- 2018-03- IDA / 57180 Post Consultant Limited 1,600.00 1,504.67 Completed KITS)AVEC ENERGIE SOLAIRE development support 27 06 02 06 23 17 27 17 13 25 Selection DE L'AXE MAIRIE DE HILE ALIFA-BRIGADE DE GENDARMERIE DE HILE COMMUNE DE HILE ALIFA CM-CRC EXTREME NORD- 38336-CS-INDV / Suivi/contrôle de la Construction de deux salles de classe équipées avec Individual latrines à l'EP Mouftoum et Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-03- 2018-01- 2018-04- 2018-05- IDA / 57180 Post Consultant Limited 9,483.00 7,714.59 Signed à l'EPB Rhoumzou, au lycée development support 27 05 02 28 23 06 27 10 27 Selection SIR et à l'EPB Kwashimalda, Et CES Goura et Equipment au CETIC Mogodé, à l'EP SIR, à l'EPB Rhoumsiki et à l'EP Tchanawa CM-CRC EXTREME NORD- 38337-CS-INDV / Suivi/contrôle des Travaux Individual Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- construction d'un radier de IDA / 57180 Post Consultant Limited 13,819.00 1,115.61 Signed development support 27 05 02 28 23 06 27 10 27 12 ml sur le mayo Teki Selection dans la localité de Teki, Commune de Mogode CM-CRC EXTREME NORD- 38338-CS-INDV / Suivi/contrôle des Travaux de construction d'un bloc de deux salles équipées et un Individual Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- bloc de latrines à l'EP de IDA / 57180 Post Consultant Limited 9,345.00 6,782.81 Signed development support 27 05 02 07 23 06 27 10 27 Ldamang et à l'EP de Ndrock Selection Tourou, à l'EP de Moufou- sud et à l'EP de Zili Yolel et au CES de Mandaka COMMUNE DE MOKOLO CM-CRC EXTREME NORD- 38339-CS-INDV / Suivi/contrôle des Travaux Construction de 01 forage équipé dePMH à EM de Individual Ldamtsai, Mandaka Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-05- IDA / 57180 Post Consultant Limited 5,339.00 2,320.44 Signed Mpoldok, Camp mission de development support 27 05 02 28 23 06 27 10 27 Selection Tourou, Koudougour II Loctcha, Katamsa Sikia, Gouldoum Moufou, Houdango Dandi et Ouro Bocki(2lots) COMMUNE DE MOKOLO CM-CRC EXTREME NORD- 38341-CS-INDV / Suivi/contrôle des Travaux de construction d'un forage Individual Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- équipé de PMH dans les IDA / 57180 Post Consultant Limited 3,477.00 2,737.83 Signed development support 27 05 02 02 23 04 27 06 27 localités de Gadjawai, Selection Guivel, Quartier Méri centre, Nguissar et Kilwo-Valta (Lot 2) COMMUNE DE MERI CM-CRC EXTREME NORD- 38343-CS-INDV / Suivi/contrôle des Travaux Individual Construction d'un bloc de Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 2,047.00 1,429.35 Signed deux salles de classe development support 27 05 02 07 23 04 27 06 27 Selection équipées et un bloc de latrines au C.E.S de Manguirdla commune de MERI CM-CRC EXTREME NORD- 38344-CS-INDV / Suivi/contrôle des Travaux Individual de construction d'un bloc de Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 3,827.00 2,945.17 Signed deux salles de classe development support 27 05 02 07 23 05 27 10 27 Selection équipées avec latrines à l'EP de Domo Doukou et à l'EP de Riganda commune de yagoua CM-CRC EXTREME NORD- 38345-CS-INDV / Individual Suivi/contrôle des Travaux Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-03- IDA / 57180 Post Consultant Limited 623.00 526.56 Signed de construction d' un forage development support 27 05 02 07 23 05 27 10 28 Selection équipé de PMH à l'EP de Riganda de yagoua CM-CRC EXTREME NORD- 38346-CS-INDV / Suivi/contrôle des Travaux construction d'un forage Individual Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- équipé de PMH à l'EP de IDA / 57180 Post Consultant Limited 2,895.00 2,945.17 Signed development support 27 05 02 08 23 05 27 10 27 Badadji, à l'EP de Pitoa- Selection Kolara, au lycée de Kolara et à Gadjia Padjonré commune de moulvoudaye CM-CRC EXTREME NORD- 38347-CS-INDV / Suivi/contrôle des Travaux Individual construction d'un bloc de Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 3,973.00 2,945.17 Signed deux salles de classe development support 27 05 02 28 23 05 27 10 27 Selection équipées et un bloc de latrines à l'EP de Pitoa- Kolara et à l'EP de Badadji CM-CRC EXTREME NORD- 38348-CS-INDV / Suivi/contrôle des Travaux Individual de construction d'un bloc de Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 3,655.00 3,010.44 Signed deux salles équipées et un development support 27 05 02 28 23 04 27 06 27 Selection bloc de latrines à l'EP de Djagalaye et au CES de Hardé commune de Maroua I CM-CRC EXTREME NORD- 38349-CS-INDV / Suivi/contrôle des Travaux Individual construction d'un forage Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 1,946.00 1,350.14 Signed équipé de PMH à l'EP de development support 27 05 02 28 23 04 27 06 27 Selection Yamdjidjing, à l'EP de Djagalaye et à Zébé commune de MAROUA I CM-CRC EXTREME NORD- 38350-CS-INDV / Suivi/contrôle de Travaux de construction d'un bloc de Individual deux salles équipées et un Component A: Local 2017-11- 2018-03- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- 2019-08- IDA / 57180 Post Consultant Limited 3,574.00 2,976.37 Completed bloc de latrines CES de development support 27 14 02 21 23 04 27 06 27 08 Selection Balda et Construction d'un bloc de deux salles de classe équipées à l'EP de Sedek Ouro-Gabdo commune de BOGO CM-CRC EXTREME NORD- 38351-CS-INDV / Suivi/contrôle de Travaux de Construction d'un forage équipé de pompe à Individual Component A: Local 2017-11- 2018-02- 2017-12- 2018-02- 2017-12- 2018-04- 2018-01- 2018-04- 2018-05- motricité humaine à l'EP de IDA / 57180 Post Consultant Limited 3,786.00 2,477.61 Signed development support 27 05 02 28 23 04 27 12 27 Sedek Ouro Gabdo à Ardo Selection Foulbé Tankirou à Gagnéri Kourdaya à Guinlaye Guizigaré et Guinlaye Moufouré dans la commune BOGO CM-CRC EXTREME NORD- 58686-CS-INDV / Sélection d'un consultant pour etudes de faisabilité DU Individual Component A: Local 2017-11- 2017-11- 2018-01- 2017-12- 2018-02- 2018-12- 2018-03- 2018-02- 2018-04- MICROPROJET DES TRAVAUX IDA / 57180 Post Consultant Open 3,000.00 2,587.10 Signed development support 27 27 15 14 05 21 12 21 26 DE REHABILILATION DU Selection TRONCON HOTEL LE SAHEL- MAYO-KALIAO (0,7 KM) cmne DE MAROUA Ier CM-CRC EXTREME NORD- 58621-CS-INDV / Sélection d'un consultant pour etudes Individual de faisabilité des MP de Component A: Local 2017-11- 2017-11- 2018-01- 2018-01- 2018-02- 2018-02- 2018-03- 2018-11- 2018-04- IDA / 57180 Post Consultant Open 3,000.00 2,648.73 Signed REHABILILATION DE LA development support 27 28 15 25 05 01 12 19 26 Selection PISTE SOUKOUDJO- BAGRISSE-FARARE (28 KM) dans la cmne de Pette. CM-CRC EXTREME NORD- 58856-CS-INDV / Sélection d'un consultant pour lEtudes de faisabilité des MP de Individual Construction de 01 Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-12- IDA / 57180 Post Consultant Open 2,200.00 1,902.66 Completed batiment abritant le bloc development support 27 08 15 22 05 02 09 16 24 20 Selection opératoire, la salle d'échographie au CMA avec clôture et un bloc de latrine au CMA de Gazawa dans la cmne de Gazawa. CM-CRC EXTREME NORD- 58511-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- construction de 01 forage à IDA / 57180 Post Consultant Open 3,000.00 2,596.59 Completed development support 27 08 15 22 05 02 09 06 24 20 PMH à Yoldé-Naggué à Selection Hodema à Tchakamadjé à Yaga -Djibiwo à Bakourehi cmne de Pette. CM-CRC EXTREME NORD- 58487-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- construction de 01 forage à IDA / 57180 Post Consultant Open 2,400.00 2,089.44 Signed development support 27 08 15 22 05 02 09 09 24 PMH au CES de Guinadji à Selection DJARELOL ALIOUM et un forage solaire au CSI de Djiddéo cmne de MAROUA III. CM-CRC EXTREME NORD- 58620-CS-INDV / Sélection d'un consultant pour etudes Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- de faisabilité des MP de IDA / 57180 Post Consultant Open 1,000.00 3,935.36 Signed development support 27 08 15 15 05 02 09 06 24 Contruction d'un bloc de 2 Selection salles de classe au CES GOBIO dans la cmne de Kalfou. CM-CRC EXTREME NORD- 58492-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de construct d'un forage à PMH Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-12- à Meskina Tifouli à Djabéwal IDA / 57180 Post Consultant Open 4,600.00 3,940.34 Completed development support 27 08 15 05 02 09 06 24 27 à Gandou Guinane au CES Selection de Zaria à Delta Guibéré et Rehabilitation d'un forage à Djada à Mandara dans la cmne de Kalfou. Page 9 CM-CRC EXTREME NORD- 58568-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- Construction de 01 forage IDA / 57180 Post Consultant Open 2,400.00 2,439.92 Completed development support 27 02 15 22 05 02 09 06 24 30 equipé de PMH au CETIC de Selection Tchévi à ZEU à ZOUVOU - YOLDE à DOUVA cmne DE BOURHA(04 MP) CM-CRC EXTREME NORD- 58678-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Rehabilitation de la route Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- Guili-ZEU, construction des IDA / 57180 Post Consultant Open 4,000.00 3,148.29 Completed development support 27 08 15 15 05 02 09 06 24 30 caniveaux à Bourha (axe Selection Hamadou -ZRA-Bello Hayatou) et Construction des caniveaux à Boukoula face commissariat cmne de Bourha. CM-CRC EXTREME NORD- 58538-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-05- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- construction d'un bloc de 02 IDA / 57180 Post Consultant Open 1,300.00 1,136.88 Completed development support 27 02 15 24 05 02 09 06 24 30 salles de classe équipées et Selection d'un bloc de latrines à trois compartiments au CETIC de Tchevi cmne de Bourha. CM-CRC EXTREME NORD- 58385-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual construct bloc de 02 SC Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 4,750.00 3,128.80 Completed equipés et d'un bloc de development support 27 08 15 15 05 02 09 04 24 09 Selection latrines à EP KAOSSERE à EP LIOUDE à L'EP B de TOULOUM à L'EP TCHOURA BIZILI à EP SAOTSAI cmne de TOULOUM CM-CRC EXTREME NORD- 58328-CS-INDV / Sélection d'un consultant pour etudes Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- de faisabilité des MP de IDA / 57180 Post Consultant Open 1,000.00 1,394.24 Completed development support 27 08 15 15 05 02 09 04 24 09 Construction de 01 forage à Selection PMH à L'EP TCHOURA BIZILI cmne de Touloum CM-CRC EXTREME NORD- 58649-CS-INDV / Sélection d'un consultant pour etudes Individual de faisabilité des MP de Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 1,600.00 1,401.01 Completed construction d'un bloc de 03 development support 27 08 15 22 05 02 09 04 24 09 Selection boutiques au marché centrale de Touloum et 02 boutiques au marché de SAOTSAI 1 CM-CRC EXTREME NORD- 58694-CS-INDV / Sélection d'un consultant pour etudes de faisabilité des MP de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-05- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- 2018-12- Construction d'un CSI d'un IDA / 57180 Post Consultant Open 5,600.00 4,897.34 Completed development support 27 08 15 24 05 02 09 06 24 08 logement d'astreinte et d'un Selection incinerateur et d'un bloc latrine à Danigué et à Nguéring (06 MP) CM-CRC EXTREME NORD- 58325-CS-INDV / sélection d1 consultant pour le suivi/controle des travaux de Construction d'un bloc Individual Component A: Local 2017-09- 2017-09- 2017-09- 2017-09- 2017-10- 2017-11- 2017-11- 2017-11- 2018-02- de 02 salles de classe et de IDA / 57180 Post Consultant Limited 6,200.00 5,558.23 Signed development support 12 12 17 12 08 04 12 06 10 latrines à l'EP de Mayel Béi Selection et l'EP de Palaoudi et travaux de construction d'un bloc maternel à EM de Zokok-Laddeo cmne de Maroua 1 CM-CRC EXTREME NORD- 58591-CS-INDV / Sélection d'un Consultant pour le Individual Suivi/contrôle des Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-08- 2019-02- IDA / 57180 Post Consultant Open 3,936.00 3,082.22 Signed TRAVAUX DE development support 02 01 20 16 11 27 15 18 11 Selection REHABILILATION DU TRONCON HOTEL LE SAHEL- MAYO-KALIAO (0,7 KM) cmne DE MAROUA Ier CM-CRC EXTREME NORD- 58842-CS-INDV / Sélection d'un Consultant pour le Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-10- 2018-08- 2018-11- 2019-02- Suivi/contrôle des TRAVAUX IDA / 57180 Post Consultant Open 3,802.00 3,274.86 Signed development support 02 03 20 08 11 16 15 29 11 DE REHABILILATION DE LA Selection PISTE SOUKOUDJO- BAGRISSE-FARARE (28 KM) CM-CRC EXTREME NORD- 58553-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-09- 2018-11- de construction d'un forage IDA / 57180 Post Consultant Open 2,690.00 2,075.63 Signed development support 02 01 20 16 11 27 15 27 13 productif équipé de pompe Selection manuelle à EP Louguéré à EP Ouro Nangué à Fakalao à Hodango CM-CRC EXTREME NORD- 58315-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de construction d'un bloc de Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 3,947.00 2,940.47 Signed 02 salles de classe équipées development support 02 01 20 16 11 27 15 25 13 Selection et construction d'un bloc de latrines à trois compartiment à EP de WOUYANG et à l'EP de GONOZO CM-CRC EXTREME NORD- 58549-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- de Construction d'un atelier IDA / 57180 Post Consultant Open 2,871.00 1,729.69 Signed development support 02 01 20 16 11 27 15 25 13 de maçonnerie au CETIC de Selection Loulou et'un bloc de latrines à trois compartiments au CETIC de Loulou CM-CRC EXTREME NORD- 58669-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de construction de 02 salles Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-11- 2019-06- IDA / 57180 Post Consultant Open 8,006.00 4,880.90 Completed de classe et d'un bloc de development support 02 01 20 16 11 27 15 01 13 18 Selection latrines au Lycée Tech de Gobo, à l'EP de GUIRIOU CENTR, au Lycée de DOM PYA, à la SAR/SM de Gobo dans la cmne de GOBO CM-CRC EXTREME NORD- 58684-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-10- 2019-05- de construction d'un bloc de IDA / 57180 Post Consultant Open 934.00 748.35 Completed development support 02 01 20 16 11 27 15 01 14 22 latrines a quatre (04) Selection compartiments au marché de GOBO et de NOULDAINA dans la cmne de GOBO CM-CRC EXTREME NORD- 58850-CS-INDV / Sélection d'un Consultant pour le Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-09- 2019-03- Suivi/contrôle des Travaux IDA / 57180 Post Consultant Open 660.00 574.90 Completed development support 02 01 20 16 11 27 15 15 29 01 de construction d'un forage Selection équipé de PMH à l'EP de GUIRIOU CENTRE CM-CRC EXTREME NORD- 58558-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-11- 2018-08- 2018-12- 2018-11- de construction d'un bloc de IDA / 57180 Post Consultant Open 2,002.00 1,433.49 Signed development support 02 03 20 23 11 03 15 27 13 02 salles de classe équipées Selection et d'un bloc de latrines à trois compartiments au CES de Doukroye CM-CRC EXTREME NORD- 58560-CS-INDV / Sélection d'un Consultant pour le Individual Suivi/contrôle des Travaux Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-11- 2018-08- 2018-12- 2018-09- IDA / 57180 Post Consultant Open 643.00 517.42 Signed de construction d'un forage development support 02 03 20 27 11 03 15 18 14 Selection équipé de PMH à l'EP de Daloa (Doukroye) dans la cmne de KAIKAI CM-CRC EXTREME NORD- 58636-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de construction d'un bloc de Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-11- 2019-05- IDA / 57180 Post Consultant Open 4,013.00 2,853.99 Completed 02 salles de classe équipées development support 02 01 20 16 11 27 15 01 13 30 Selection et d'un bloc de latrines à trois compartiments à EP de Balane au CES de Sirlawé dans la cmne de KAR-HAY CM-CRC EXTREME NORD- 58634-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de construction d'un forage Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-11- équipé de PMH à l'EP de IDA / 57180 Post Consultant Open 3,845.00 2,594.54 Signed development support 02 01 20 16 11 27 15 01 13 Damdama à l'école des Selection parents de Gouloulou à l'EP Balane à l'EP de REY- FOULAYE à l'EP de Sadielle au CES de Sirlawe CM-CRC EXTREME NORD- 58701-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de construction d'un bloc de Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-09- 2018-11- IDA / 57180 Post Consultant Open 4,332.00 2,789.46 Signed 02 salles de classe équipées development support 02 01 20 16 11 27 15 17 13 Selection et d'un bloc de latrines à trois compartiments à l'EP de Bihoré à l'EP de Troké dans la, commue de Tchatibali. CM-CRC EXTREME NORD- 58848-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-11- 2018-11- de construction d'un forage IDA / 57180 Post Consultant Open 1,986.00 1,394.73 Signed development support 02 01 20 16 11 27 15 05 13 équipé de PMH à l'EP Selection Saouringwa, à Kada et 'a Glonheme dans la cmne de Tchatibali CM-CRC EXTREME NORD- 58615-CS-INDV / Sélection d'un Consultant pour le Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-09- 2018-10- Suivi/contrôle des Travaux IDA / 57180 Post Consultant Open 2,026.00 1,917.50 Signed development support 02 01 20 16 11 27 15 03 14 de construction d'un forage Selection équipé de PMH à Bibalé - Gambour à Goubara à Kassilé CM-CRC EXTREME NORD- 58667-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de réhabilitation de la mare Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-09- 2018-11- de Garey Kaélé, IDA / 57180 Post Consultant Open 2,320.00 1,917.50 Signed development support 02 01 20 23 11 30 15 18 13 Construction d'un forage Selection pastoral à énergie solaire Garey Kaélé et construction d'un forage équipé de PMH à Kassilé dans la commue de Kaele CM-CRC EXTREME NORD- 58555-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de construct de 02 salles Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 7,921.00 5,839.65 Signed de classe équipées et bloc development support 02 01 20 16 11 27 15 15 13 Selection latrines à l'EP de Badjafe, à l'EP de Zouana à l'EP de Tchabeyel et EP de Goudjouing cmne de Kaele. CM-CRC EXTREME NORD- 58641-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des travaux Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-11- 2018-08- 2018-11- 2018-11- de construction de 02 salles IDA / 57180 Post Consultant Open 3,687.00 2,782.38 Signed development support 02 03 20 26 11 03 15 07 13 de classe et d'un bloc de Selection latrines à EP Mayel -Guinadj et 02 salles de classe à l'EP de KALAF cmne de Moutourwa. CM-CRC EXTREME NORD- 58703-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des travaux Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-11- 2018-08- 2018-11- 2018-11- de construction de 01 IDA / 57180 Post Consultant Open 2,696.00 2,086.79 Signed development support 02 03 20 26 11 03 15 19 13 forage équipé de PMH à Selection Ganaha, à EP de Dourloum à EP de KALAF et EP de Mayel- guinadji dans la cmne de moutourwa CM-CRC EXTREME NORD- 58306-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôletravaux de construction de 02 salles de Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- 2019-01- classe et d'un bloc de IDA / 57180 Post Consultant Open 2,339.00 1,656.24 Completed development support 02 01 20 23 11 30 15 25 13 03 latrines à l'EP de GABOUA et Selection Equipements en tables- bancs et bureauxà l'EP de KOZA 1, Koza 2 et Gaboua dans la cmne de KOZA CM-CRC EXTREME NORD- 58522-CS-INDV / Sélection d'un Consultant pour le Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-10- Suivi/contrôle des Travaux IDA / 57180 Post Consultant Open 1,596.00 1,391.14 Signed development support 02 01 20 16 11 30 15 15 14 de construction d'un forage Selection équipé de PMH à EM Moskota et à l'EP GOKORO CM-CRC EXTREME NORD- 58708-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual de travaux de construction Component A: Local 2018-05- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2018-11- 2018-11- IDA / 57180 Post Consultant Open 3,809.00 3,138.14 Signed de 02 salles de classe et development support 02 01 20 23 11 30 15 07 13 Selection d'un bloc de latrines au CETIC D'OUZAL et Construction d'un bloc de deux salles de classe équipées à l'EP KARAZAWA CM-CRC EXTREME NORD- 58298-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2018-11- 2018-09- de construction d'un bloc IDA / 57180 Post Consultant Open 4,136.00 3,312.48 Signed development support 02 01 20 23 11 30 15 07 29 maternelle à EM de Selection MOSKOTA et Construction d'un bloc de salle de classe équipé à l'EP KORSAMBA CM-CRC EXTREME NORD- 58692-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux de Construction d'un bloc Individual de deux salles de classe Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 6,000.00 3,504.25 Signed équipées et d'un bloc development support 02 01 20 23 11 30 15 25 13 Selection latrines a trois compartiments au CES de Mazaya à EP ZELE (Soulédé) (lot01) à EP de Doumbéré(lot02) cmne de ROUA CM-CRC EXTREME NORD- 58291-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des construct de 02 SC equipées Gouvaka Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-09- 2018-07- 2018-10- 2018-08- 2018-10- 2018-09- Chefferie et équipement IDA / 57180 Post Consultant Open 5,825.00 4,178.33 Signed development support 02 03 20 03 11 16 15 22 29 bureau et construct de 02 Selection SC equipées à L'EP de Majéconstruct de 02 SC equipées et équipement SC existantes à L'EP de Malika CM-CRC EXTREME NORD- 58612-CS-INDV / Sélection d'un Consultant pour le Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-10- 2018-08- 2018-11- 2018-10- Suivi/contrôle des Travaux IDA / 57180 Post Consultant Open 1,647.00 1,220.39 Signed development support 02 03 20 06 11 16 15 06 14 de construction d'un forage Selection équipé de PMH à Koulang à Mangavé cmne de MORA CM-CRC EXTREME NORD- 58556-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-10- 2018-08- 2018-10- 2018-11- de construction de 01 IDA / 57180 Post Consultant Open 2,912.00 2,440.77 Signed development support 02 03 20 08 11 16 15 22 13 magasin de stockage de Selection cereale à Sera -Idoumda et de conservation d'oignon àà Kourgui cmne de MORA Page 10 CM-CRC EXTREME NORD- 58593-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle de Travaux Individual de Construction d'un bloc Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- IDA / 57180 Post Consultant Open 2,409.00 2,085.86 Signed de 02 salles de classe development support 02 01 20 01 11 27 15 14 13 Selection équipées à EP de Gance et d'un bloc de latrines à trois compartiments à L'EP TOLKOMARI cmne de Kolofata CM-CRC EXTREME NORD- 58609-CS-INDV / Selction d un consultant pour le Individual suivi/controle Travaux de Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-11- 2019-08- IDA / 57180 Post Consultant Open 3,990.00 2,789.46 Completed Construction de deux bloc development support 02 01 20 16 11 27 15 24 13 02 Selection de 02 salles de classe équipées aux CES TOLKOMARI I cmne de Kolofata. CM-CRC EXTREME NORD- 58666-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle de Travaux Individual de Construction d'un forage Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-08- 2018-11- IDA / 57180 Post Consultant Open 3,358.00 2,615.12 Signed équipé de PMH à l'EP GANCE development support 02 01 20 16 11 27 15 16 13 Selection au CES Toltomari et Réalisation d’un forage solaire avec borne fontaine à Kolofata cmne de Kolofata CM-CRC EXTREME NORD- 58646-CS-INDV / Sélection d'un Consultant pour le Suivi/contrôle des Travaux Individual Component A: Local 2018-05- 2018-08- 2018-06- 2018-10- 2018-07- 2018-10- 2018-08- 2018-10- 2018-11- 2019-03- de Construction d'un bloc IDA / 57180 Post Consultant Open 5,520.00 3,897.16 Completed development support 02 03 20 05 11 08 15 12 13 12 de 02 salles de classe Selection équipées s à EP Chéoulew au CES de Makalingaï (lot01)à EP Tazang (lot02) cmne de Tokombere CM-CRC EXTREME NORD- 58545-CS-INDV / Sélection d'un Consultant pour le Individual Suivi/contrôle des Travaux Component A: Local 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-10- 2018-10- 2018-12- IDA / 57180 Post Consultant Open 1,226.00 1,420.87 Completed de Construction de 01 development support 02 01 20 01 11 27 15 22 14 18 Selection forage équipé de PMH à Baka-Fourwa et à Djaltar dans la cmne de Tokombere CM-CRC EXTREME NORD- 58642-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX DE CONSTRUCTION D'UN Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-12- 2018-11- BLOC DE DEUX SALLES DE IDA / 57180 Post Consultant Open 2,201.00 1,817.81 Signed development support 02 23 20 13 11 20 15 13 13 CLASSE EQUIPE ET D'UN Selection BLOC DE LATRINES A TROIS COMPARTIMENTS A L’EP KOUTOULA DANS LA CMNE DE BLANGOUA CM-CRC EXTREME NORD- 58705-CS-INDV / SUIVI CONTROLE DES TRAVAUX D'AMENAGEMENT D'UNE GARE ROUTIERE PAR LA Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-12- 2019-09- CONSTRUCTION DE 04 IDA / 57180 Post Consultant Open 3,600.00 2,707.83 Completed development support 02 23 20 13 11 20 15 23 13 08 GUICHETS, 04 MAGASINS, Selection D'UN HANGAR D'ATTENTE ET D'UN BLOC LATRINE AVEC UN MUR D'ENCEINTE DE 130 m A BLANGOUA CM-CRC EXTREME NORD- 58559-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- DE CONSTRUCTION D'UN IDA / 57180 Post Consultant Open 1,482.00 856.87 Signed development support 02 23 20 19 11 20 15 27 13 FORAGE EQUIPE DE PMH A la Selection gare routiere de BLANGOUA ET A L'EP DE KOUTOULA DANS LA CMNE DE BLANGOUA CM-CRC EXTREME NORD- 58681-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- 2019-02- DE CONSTRUCTION D'UN IDA / 57180 Post Consultant Open 4,057.00 4,474.93 Completed development support 02 23 20 13 11 20 15 24 13 02 FORAGE PASTORAL A Selection ENERGIE SOLAIRE A KARENA ET A NAGA DANS LA CMNE DE DARAK CM-CRC EXTREME NORD- 58838-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-12- 2018-11- 2019-07- CLASSE EQUIPE ET D'UN IDA / 57180 Post Consultant Open 3,756.00 3,047.10 Completed development support 02 23 20 16 11 20 15 03 13 05 BLOC DE LATRINES A TROIS Selection COMPARTIMENTS A L’EP HILELLE ) ET CONSTRUCTION D'UN HANGAR AU MARCHE DE GOULFEY GANA cmne DE GOULFEY CM-CRC EXTREME NORD- 58567-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR LA Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-12- 2018-11- 2019-10- CONSTRUCTION DE 04 IDA / 57180 Post Consultant Open 3,656.00 2,698.86 Completed development support 02 23 20 16 11 20 15 17 13 11 GUICHETS, 04 MAGASINS, Selection D’UN HANGAR D’ATTENTE, 02 BOUTIQUES ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE DE 90 m A GOULFEY cmne DE GOULFEY CM-CRC EXTREME NORD- 58594-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DE CONSTRUCTION D'UN Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- IDA / 57180 Post Consultant Open 2,087.00 853.74 Signed FORAGE EQUIPES DE POMPE development support 02 23 20 13 11 20 15 27 13 Selection A MOTRICITE HUMAINE A MOUGALAM,A TAWOULWEBE ET A L'EP HILELE cmne DE HILE ALIFA CM-CRC EXTREME NORD- 58565-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DE CONSTRUCTION D'UN Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- IDA / 57180 Post Consultant Open 2,477.00 1,859.26 Signed BLOC DE DEUX SALLES DE development support 02 23 20 11 20 15 22 13 Selection CLASSE EQUIPE ET D'UN BLOC DE LATRINES A TROIS COMPARTIMENTS A L’EP GONONI CM-CRC EXTREME NORD- 58519-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DE CONSTRUCTION D'UN Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- IDA / 57180 Post Consultant Open 2,163.00 853.74 Signed FORAGE EQUIPE DE POMPE A development support 02 23 20 13 11 20 15 27 13 Selection MOTRICITE HUMAINE A MAFOULSO III, A FAMARE ET A L'EP DE GONONI cmne DE HILE ALIFA CM-CRC EXTREME NORD- 58608-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX DE CONSTRUCTIOND’UNE Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- MINI AEP PASTORAL EQUIPE IDA / 57180 Post Consultant Open 4,043.00 3,065.26 Signed development support 02 23 20 13 11 20 15 27 13 DE DEUX ABREUVOIRS, Selection D’UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A ABASSOUNI, A DOLE BADA cmne DE HILE ALIFA CM-CRC EXTREME NORD- 58557-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX DE CONSTRUCTION D'UN Individual Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- BLOC DE DEUX SALLES DE IDA / 57180 Post Consultant Open 2,350.00 1,735.98 Signed development support 02 23 20 16 11 20 15 24 13 CLASSE EQUIPE ET D'UN Selection BLOC DE LATRINES A TROIS COMPARTIMENTS AU CES D'ADJAÏNE A HILE HAOUSSA cmne DE KOUSSERI CM-CRC EXTREME NORD- 58569-CS-INDV / SELECTION CONSULTANT Individual SUIVI/CONTROLE TRAVAUX Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-12- 2018-11- IDA / 57180 Post Consultant Open 1,975.00 1,629.76 Signed DE CONSTRUCTION D'UN development support 02 23 20 16 11 20 15 03 13 Selection HANGAR AVEC BLOC LATRINE AU MARCHE DE BIAMO, cmne DE MAKARI CM-CRC EXTREME NORD- 58691-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DE CONSTRUCTION D'UN Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- 2018-07- 2018-11- 2019-07- IDA / 57180 Post Consultant Open 2,201.00 1,629.76 Completed BLOC DE DEUX SALLES DE development support 02 23 20 16 11 20 15 24 13 20 Selection CLASSE EQUIPE ET D'UN BLOC DE LATRINES A TROIS COMPARTIMENTS A L'EP DE MALTAM cmne DE MAKARI CM-CRC EXTREME NORD- 58495-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DEs MP D'INSTALLATION Component A: Local 2018-05- 2018-06- 2018-07- 2018-08- 2018-10- IDA / 57180 Post Consultant Open 2,017.00 0.00 Canceled D'ECLAIRAGE PUBLIC (10 development support 02 20 11 15 14 Selection KITS)AVEC ENERGIE SOLAIRE DE L'AXE MAIRIE DE HILE ALIFA-BRIGADE DE GENDARMERIE DE HILE CM-CRC EXTREME NORD- 38340-CS-INDV / Suivi/contrôle des Travaux construction d'un forage Individual Component A: Local 2017-11- 2018-02- 2017-12- 2017-12- 2018-01- 2018-04- équipé de PMH dans les IDA / 57180 Post Consultant Limited 3,477.00 0.00 Canceled development support 27 05 02 23 27 27 localités de Kaliao, Selection Goulmoyo, Mbozo Mofou, Balewa et Manguirdla (Lot1) COMMUNE DE MERI CM-CRC EXTREME NORD- 38342-CS-INDV / Suivi/contrôle technique et environnemental des travaux de construction Individual d'un forage équipé de PMH Component A: Local 2017-11- 2018-02- 2017-12- 2018-03- 2017-12- 2018-04- 2018-01- 2018-04- 2018-04- IDA / 57180 Post Consultant Limited 6,954.00 5,699.52 Signed dans les localités de Kaliao, development support 27 05 02 28 23 04 27 06 27 Selection Goulmoyo, Mbozo Mofou, Balewa et Manguirdla, Moundour Foulbé, Dogba Maliki, Magawa, Houloum et Tchaki djébé Commune de MERI CM-CRC EXTREME NORD- 83169-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-06- 2018-10- 2018-08- 2018-10- 2018-08- 2018-10- 2018-09- 2018-10- 2018-11- 2019-12- IDA / 57180 Post Consultant Open 4,500.00 3,858.02 Completed environnementales des MP development support 15 08 03 26 24 27 28 27 12 19 Selection d'électrification de la localité de Dargala centre- Lycée de Dargala et Dargala- Hodande Commune de Dargala. CM-CRC EXTREME NORD- 83165-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-06- 2018-10- 2018-08- 2018-10- 2018-08- 2018-10- 2018-09- 2018-10- 2018-11- 2018-12- construction d'un (01) IDA / 57180 Post Consultant Open 3,500.00 3,542.39 Completed development support 15 08 03 25 24 27 28 27 12 19 forage à PMH à Dargala- Selection Centre à Hardéo-Golo à Yonkolel à Toupouré- Sirataré à Wirdiwo à Ouro- Domayo à Ouro-Hitgo Commune de Dargala. CM-CRC EXTREME NORD- 83171-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2019-01- IDA / 57180 Post Consultant Open 4,000.00 4,048.44 Completed environnementales des MP development support 15 08 03 25 24 27 28 29 14 03 Selection de Rehabilitation des routes dans les quartiers de Wourndé II, III, VI long d'environ 3 km Commune de Maroua II. CM-CRC EXTREME NORD- 83155-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-12- 2019-03- 2019-01- IDA / 57180 Post Consultant Open 4,000.00 4,223.60 Completed environnementales des MP development support 15 08 03 25 24 27 28 06 14 03 Selection d'extension du réseau électrique dans les quartiers de Wourndé II, III, VI Commune de Maroua II. CM-CRC EXTREME NORD- 83158-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- IDA / 57180 Post Consultant Open 1,600.00 1,709.83 Completed environnementales des MP development support 15 10 03 26 24 27 28 29 14 22 Selection de Construction d’une aire d’abattage d’un bloc latrines et d’un forage à Doursoungo Commune de Maroua III. CM-CRC EXTREME NORD- 83143-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-02- 2018-11- IDA / 57180 Post Consultant Open 3,000.00 3,570.54 Completed d'éclairage public à energie development support 15 08 03 24 24 27 28 29 27 08 Selection solaire dans les localités de Mindif, Ouro Bouné, Modjombodi, Djodjong et Djouta Wade Commune de Mindif CM-CRC EXTREME NORD- 83159-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilitédes MP de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-11- construction et équipement IDA / 57180 Post Consultant Open 5,000.00 5,149.62 Completed development support 15 08 03 26 24 27 28 29 14 08 d'un CSI à Hoppo et Selection fourniture en équipement dans les CSI de Mindif de Modjombodi de Maoundine et de Mogom Commune de Mindif. CM-CRC EXTREME NORD- 83145-CS-INDV / Sélection d'1 consultant pour EF des MP de Construction d'1 bloc de 02 salles classe et Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-11- d'1 bloc de latrines à EP IDA / 57180 Post Consultant Open 5,400.00 5,984.42 Completed development support 15 10 03 25 24 27 28 27 14 23 Rebede au CES de Selection Dongrosse au CES de Soueye,à EP Mbiteu à EP Lobokri à EP SAIGA et équipements à l'EP Danhou Commune de Dziguilao. CM-CRC EXTREME NORD- 83147-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-11- IDA / 57180 Post Consultant Open 1,200.00 2,665.22 Completed environnementales des MP development support 15 08 03 23 24 27 28 23 14 23 Selection de construction d'un (01) forage à PMH à l’EP de SAIGA et de Lobokri dans la Commune de Dziguilao. . CM-CRC EXTREME NORD- 83160-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité de Construction Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- IDA / 57180 Post Consultant Open 3,369.00 3,040.99 Signed d'un bloc de 02 salles de development support 15 08 03 26 24 27 28 28 14 Selection classe équipées et d'un bloc de latrines à EP Guidima, à EP Kankrwa, à EP Golonpoui dans la Commune de Datcheka. CM-CRC EXTREME NORD- 83188-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- construction d'1 forage à IDA / 57180 Post Consultant Open 3,500.00 3,625.14 Completed development support 15 08 03 27 24 27 28 27 14 27 PMH à EP Kankrwa, à EP Selection Golonpoui, à l'abattoir du marché de Zouaye, à Gaï Gaï, à Tining, à Tibali et à Lara dans la Commune de Datcheka. CM-CRC EXTREME NORD- 83167-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- faisabilité techniques et IDA / 57180 Post Consultant Open 1,130.00 1,519.93 Completed development support 15 08 03 26 24 27 28 29 14 27 environnementales des MP Selection de construction d'un abattoir au marché de Zouaye Commune de Datcheka. Page 11 CM-CRC EXTREME NORD- 83151-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2019-12- Construction d'un bloc de IDA / 57180 Post Consultant Open 4,500.00 4,385.81 Completed development support 15 10 03 26 24 27 28 27 14 12 deux salles de classe Selection équipées au CES d'Agolla, au CES de Dabaye, au CES de Widigue, au CETIC de Vele et au Lycée de Kartoua Commune de Gueme. CM-CRC EXTREME NORD- 83168-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- IDA / 57180 Post Consultant Open 1,900.00 1,910.99 Completed environnementales des MP development support 15 10 03 26 24 27 28 29 14 12 Selection de Construction d'un hangar au marché de Dabaye et d'un bloc de latrines VIP au marché de Gabaraye commune de Gueme. CM-CRC EXTREME NORD- 83191-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- faisabilité techniques et IDA / 57180 Post Consultant Open 1,900.00 1,909.51 Completed development support 15 08 03 26 24 27 28 29 14 12 environnementales des MP Selection de Construction d'une boucherie et d'un hangar au marché de Vele commune de Gueme. CM-CRC EXTREME NORD- 83148-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-12- 2019-03- 2018-12- d'extention de l'électricité IDA / 57180 Post Consultant Open 6,000.00 5,903.98 Completed development support 15 08 03 26 24 27 28 06 14 14 dans la localité de Maga et Selection electrification du marché de Guirvidig des quartiers environnant et de la localité de Yanga Commune de Maga. CM-CRC EXTREME NORD- 83187-CS-INDV / Sélection d'1 consultant élaboration des EF des MP Construction d'1 bloc de 02 salles de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-11- classe équipées et 01 bloc IDA / 57180 Post Consultant Open 5,600.00 4,723.18 Completed development support 15 08 03 25 24 27 28 29 14 15 latrines à EP Djenreng à EP Selection Djarwar à EP Vaidou à EP Waimou à EP Bigdi à EP Guidoua à EP Goulourgou au CES de Kamargui Commune Wina. CM-CRC EXTREME NORD- 83153-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-11- construction de 01 forage à IDA / 57180 Post Consultant Open 2,400.00 3,469.96 Completed development support 15 08 03 25 24 27 28 29 14 15 énergie solaire au CSI de Selection Bosgoye d’01 forage pastoral à énergie solaire à Djongdong et d’un forage à PMH à EP Vaidou Comune de Wina CM-CRC EXTREME NORD- 83156-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-05- 2018-05- 2018-07- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-10- faisabilité techniques et IDA / 57180 Post Consultant Open 2,400.00 4,853.80 Signed development support 27 08 15 26 05 02 09 06 24 environnementales des MP Selection de contruction d’un mini AEP aux CSI de Danigué et Nguéring Commune de Guere. CM-CRC EXTREME NORD- 83184-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-12- 2018-10- 2018-12- 2018-10- 2019-01- 2018-10- 2019-03- 2018-12- IDA / 57180 Post Consultant Open 3,000.00 3,037.47 Completed environnementales des MP development support 15 08 03 26 24 27 28 29 14 07 Selection de construction de 04 blocs de 10 boutique et Construction de latrines VIP au marché de HINA CM-CRC EXTREME NORD- 83185-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- environnementales des MP IDA / 57180 Post Consultant Direct 1,600.00 1,633.42 Signed development support 15 11 25 13 15 18 20 06 03 de Construction d'un bloc Selection de deux salles de classe équipées et un bloc latrines a trois compartiments à Magala-Djamene Commune Darak. CM-CRC EXTREME NORD- 83146-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-10- 2019-02- faisabilité techniques et IDA / 57180 Post Consultant Direct 3,700.00 3,357.24 Signed development support 15 11 25 18 15 25 20 25 03 environnementales des MP Selection d'electrification en énergie solaire de l'auberge municipal et hôtel de ville de Darak CM-CRC EXTREME NORD- 83164-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- 2018-12- Construction d'1 bloc de IDA / 57180 Post Consultant Direct 5,000.00 6,462.69 Completed development support 15 11 25 17 15 18 20 05 03 14 deux salles de classe Selection équipées et un bloc latrines à EP DEGA, à EP GADAFAI, à EP NIGUE et à EP WAROU I Commune Fotokol. CM-CRC EXTREME NORD- 83190-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité des MP de Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-10- 2019-02- IDA / 57180 Post Consultant Direct 3,000.00 2,685.79 Signed Construction d’un (01) development support 15 11 25 25 15 25 20 25 03 Selection forage PMH dans les lotalités de Amssadeck, de Barkari II, de Djabrari, de Haigayo II Commune Fotokol. CM-CRC EXTREME NORD- 83142-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité des MP de Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- 2018-12- Construction d'un bloc de IDA / 57180 Post Consultant Direct 2,500.00 3,277.70 Completed development support 15 01 25 11 15 18 20 05 03 14 deux salles de classe Selection équipées et un bloc latrines a trois compartiments à EP WAROU II et à EP OH HAMADIE Commune Fotokol. CM-CRC EXTREME NORD- 83149-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité des MP de Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-10- 2019-02- IDA / 57180 Post Consultant Direct 3,000.00 2,685.79 Signed Construction d’un (01) development support 15 11 25 11 15 18 20 23 03 Selection forage PMH dans les lotalités de Kabetoua, de OH Isseini, de Warou II et de Worokaime Commune Fotokol. CM-CRC EXTREME NORD- 83152-CS-INDV / Sélection d'1 consultant pour l'élaboration des EF des MP de Construction d'1 bloc de Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- deux salles de classe IDA / 57180 Post Consultant Direct 3,800.00 5,427.12 Signed development support 15 11 25 11 15 18 20 05 03 équipées et 01 bloc latrines Selection à EP DAVA à EP Kabéla et à EP Beré et fourniture en equipement pour les EP Commune Logone-Birni. CM-CRC EXTREME NORD- 83141-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques des Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2019-10- 2018-12- 2018-11- 2019-02- MP de Construction d’un IDA / 57180 Post Consultant Direct 4,200.00 5,091.18 Signed development support 15 11 25 11 15 18 20 06 03 (01) forage PMH dans les Selection lotalités de Ounangaré de Ngada I de Ngada II de Michiska Mousgoum de Marafine I de SHI commune de Logone-Birni CM-CRC EXTREME NORD- 83162-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- faisabilité techniques et IDA / 57180 Post Consultant Direct 1,600.00 1,678.62 Signed development support 15 11 25 17 15 18 20 06 03 environnementales des MP Selection de Construction d'un magasin de stockage de cereale à Zigagué Commune de Waza CM-CRC EXTREME NORD- 83150-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-10- 2019-02- IDA / 57180 Post Consultant Direct 2,400.00 2,280.74 Signed environnementales des MP development support 15 11 25 11 15 18 20 31 03 Selection de Construction d’un (01) forage PMH dans les lotalités de Ndiguina, de Malia et de Mada 1 Commune de Waza CM-CRC EXTREME NORD- 83140-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-11- 2018-12- 2018-11- 2019-02- IDA / 57180 Post Consultant Direct 4,000.00 5,913.04 Signed environnementales des MP development support 15 11 25 11 15 13 20 16 03 Selection de construction d’une mini approvisionement en eau potable à Zigagué Commune de Waza CM-CRC EXTREME NORD- 83154-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité techniques et Individual Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-11- 2019-02- environnementales des MP IDA / 57180 Post Consultant Direct 2,000.00 2,044.34 Signed development support 15 11 25 11 15 18 20 06 03 de Construction d'un bloc Selection de deux salles de classe équipées et un bloc latrines a trois compartiments à EP de Davagang Commune Zina. CM-CRC EXTREME NORD- 83161-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual faisabilité techniques et Component A: Local 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-10- 2018-12- 2018-10- 2019-02- IDA / 57180 Post Consultant Direct 2,400.00 2,182.21 Signed environnementales des MP development support 15 11 25 25 15 25 20 25 03 Selection de Construction d’un (01) forage PMH dans les lotalités de ZAMA et de Gadabou Commune de ZINA CM-CRC EXTREME NORD- 58303-CS-INDV / Sélection Individual d'un Consultant pour le Component A: Local 2018-05- 2018-06- 2018-07- 2018-08- 2018-09- IDA / 57180 Post Consultant Open 1,735.00 0.00 Canceled Suivi/contrôle des Travaux development support 02 20 11 15 29 Selection Construction d'une clôture à EM de MOZOGO CM-CRC EXTREME NORD- 58550-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE CONSTRUCTION D’UNE MINI Individual Component A: Local 2018-05- 2018-06- 2018-07- 2018-08- 2018-10- AEP PASTORAL EQUIPE DE IDA / 57180 Post Consultant Open 2,004.00 0.00 Canceled development support 02 20 11 15 14 DEUX ABREUVOIRS, D’UNE Selection POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A MAGALAKABIR, DANS LA CMNE DE DARAK CM-CRC EXTREME NORD- 58544-CS-INDV / SUIVI/CONTROLE CONSTRUCTION D'UN FORAGE EQUIPE DE POMPE A Individual MOTRICITE HUMAINE AU Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2018-11- IDA / 57180 Post Consultant Open 4,382.00 0.00 Canceled CES D'ADJAINE ET D'UNE development support 02 23 20 11 15 13 Selection MINI AEP PASTORAL EQUIPE DE DEUX ABREUVOIRS, D'UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A LACTA 1, MASSAKI CM-CRC EXTREME NORD- 58518-CS-INDV / SELECTION CONSULTANT SUIVI/CONTROLE TRAVAUX Individual DE CONSTRUCTION D'UN Component A: Local 2018-05- 2018-05- 2018-06- 2018-07- 2018-08- 2018-11- IDA / 57180 Post Consultant Open 2,090.00 0.00 Canceled FORAGES EQUIPES DE POMPE development support 02 23 20 11 15 13 Selection A MOTRICITE HUMAINE A MASSIO-GOURGOURA, A NAGA NDIGUINI, A EP MALTAM. cmne DE MAKARI CM-CRC EXTREME NORD- 111116-CS-INDV / suivi controle des travaux de Individual construction d'un bloc de 02 Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-08- 2019-09- 2019-10- 2019-12- IDA / 57180 Post Consultant Open 1,986.00 2,044.34 Signed salles de classe équipé et development support 03 17 22 11 12 05 16 09 15 Selection d'un bloc de latrines au CETIC de Tchévi dans la commune de Bourha CM-CRC EXTREME NORD- 111253-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2020-03- 2019-12- construction d'un forage IDA / 57180 Post Consultant Open 2,617.00 2,253.55 Signed development support 03 17 22 24 12 05 16 02 15 PMH au CETIC de Tchévi, à Selection Zouvou- yolde à DOUVA et à ZEU dans la commune de Bourha CM-CRC EXTREME NORD- 111266-CS-INDV / suivi controle des travaux de Individual construction des caniveaux Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-08- 2019-09- 2019-10- 2019-12- IDA / 57180 Post Consultant Open 2,774.00 2,545.59 Signed en BA à Bourha (axe development support 03 17 22 24 12 05 16 09 15 Selection Hamadou -ZRA-Bello Hayatou) et à Boukoula face commissariat ( dans la Commune de Bourha CM-CRC EXTREME NORD- 111262-CS-INDV / suivi controle des travaux de construction de 2 blocs de Individual 10 boutiques au marché de Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-11- 2020-01- IDA / 57180 Post Consultant Open 10,360.00 13,312.67 Signed HINA cote A l1 et development support 03 17 22 24 12 01 16 15 14 Selection construction de 2 blocs de 10 boutiques au marché de HINA et latrines vip au marché de HINA cote B lot (02), commune de HINA. CM-CRC EXTREME NORD- 111341-CS-INDV / suivi controle des travaux de construction de 01 forage à Individual Component A: Local Under 2019-06- 2021-01- 2019-07- 2019-08- 2019-09- 2019-12- PMH à Yoldé-Naggué, à IDA / 57180 Post Consultant Open 4,014.00 0.00 development support Implementation 03 06 22 12 16 15 Tchakamadjé, Yaga djibiwo, Selection à Bakourebi (Abba wollo) Toukou mayel(Ouro-Bedem) et à MAYA ,commune de Pétté CM-CRC EXTREME NORD- 111359-CS-INDV / suivi controle des travaux de Individual construction d'un mini Component A: Local Under 2019-06- 2021-01- 2019-07- 2019-08- 2019-09- 2019-12- IDA / 57180 Post Consultant Open 2,094.00 0.00 adduction d'eau à energie development support Implementation 03 06 22 12 16 15 Selection photovoltaique pour usage agricole a fadare dans la commune de pette CM-CRC EXTREME NORD- 111337-CS-INDV / suivi controle des travaux de construction d'un bloc de Individual deux salles de classe Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2020-01- IDA / 57180 Post Consultant Open 8,296.00 8,954.03 Signed équipées et d'un bloc de development support 03 17 22 24 12 25 16 15 14 Selection latrines à trois compartiments à EP SAIGA, EP LOBOKRI, EP MBITEU et CES SOUEYE dans la Commune de Dziguilao CM-CRC EXTREME NORD- 111334-CS-INDV / suivi controle des travaux de Individual construction d'un bloc de Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-12- 2019-12- IDA / 57180 Post Consultant Open 1,900.00 1,678.62 Signed deux salles de classe development support 03 17 22 24 12 28 16 06 15 Selection équipées et d'un bloc latrine à trois compartiments à l'EP de Ligazang, commune de Mindif CM-CRC EXTREME NORD- 111352-CS-INDV / suivi controle des travaux de construction et équipement d'un csi avec incinerateur et Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-12- 2020-01- latrines à MATFAI, et IDA / 57180 Post Consultant Open 7,281.00 5,108.10 Signed development support 03 17 22 24 12 05 16 06 14 Fourniture en mobilier et Selection petit materiel sanitaire de CSI de Mindif, de Modjombodi, de Maoudine et de Mogom dans la commune de Mindif Page 12 CM-CRC EXTREME NORD- 111263-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-11- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-12- 2019-12- construction d'un forage IDA / 57180 Post Consultant Open 1,524.00 1,702.70 Signed development support 03 25 22 24 12 22 16 06 15 pastoral a energie Selection photovoltaique au marché à bétail à Moulvoudaye CM-CRC EXTREME NORD- 111348-CS-INDV / suivi controle des travaux d'aménagement du marché Individual à bétail en contruisant un Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-12- 2020-01- IDA / 57180 Post Consultant Open 2,245.00 2,000.67 Signed parc à betail une cloture un development support 03 17 22 24 12 22 16 06 14 Selection quai d'embarquement et un bloc latrine a trois compartiments dans la Commune de Moulvoudaye. CM-CRC EXTREME NORD- 111264-CS-INDV / suivi controle des travaux de construction de 02 SDC et de latrines à EP KAOSSERE, à Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2020-01- l'EP Ticheeo Kolandi à l'EP IDA / 57180 Post Consultant Open 9,364.00 4,784.86 Signed development support 03 17 22 24 12 28 16 25 14 Tchoura-Bizili et de SDC à Selection EPB Touloum et de 2 SDC AVEC BUREAUX A L’EPP SAOTSAI.Commune de Touloum CM-CRC EXTREME NORD- 111272-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-12- 2019-12- construction de 01 forage à IDA / 57180 Post Consultant Open 2,034.00 1,699.43 Signed development support 03 17 22 24 12 05 16 06 15 PMH à Gai gai, à EP Selection Golonpoui et à EP Kankwa, dans la commune de Datcheka CM-CRC EXTREME NORD- 111265-CS-INDV / suivi controle des travaux de construction d'un bloc de 02 Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-12- 2019-12- salles de classe équipées et IDA / 57180 Post Consultant Open 5,988.00 4,866.93 Signed development support 03 17 22 24 12 06 16 06 15 avec un bloc de latrines à Selection trois compartiments à EP Golonpoui , EP Kankrwa et EP Guidima , dans la commune de Datcheka CM-CRC EXTREME NORD- 111236-CS-INDV / suivi controle des travaux de construction d'un bloc de Individual deux salles de classe Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2019-12- IDA / 57180 Post Consultant Open 7,041.00 10,911.03 Signed équipées au CETIC de Vélé, development support 03 17 22 24 12 24 16 18 15 Selection au CES de Widigue (lot01), au CES de Dabaye et au CES d'Agolla, (lot02) dans la commune de Guémé CM-CRC EXTREME NORD- 111273-CS-INDV / suivi controle des travaux de construction d'un hangar 52 Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2019-12- places au marché de IDA / 57180 Post Consultant Open 2,706.00 3,058.97 Signed development support 03 17 22 24 12 23 16 05 15 Gabaraye et suivi controle Selection des travaux de construction d'un bloc de latrines au marché de Gabaraye, commune de Guémé CM-CRC EXTREME NORD- 111252-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-07- 2019-07- 2019-10- 2019-08- 2019-11- 2019-09- 2020-01- 2020-01- construction d'un centre de IDA / 57180 Post Consultant Open 5,098.00 3,615.78 Signed development support 03 24 22 29 12 05 16 06 14 santé intégré équipé et un Selection bloc de latrines au CSI à Nguéring, commune de Gueré CM-CRC EXTREME NORD- 111335-CS-INDV / suivi Individual controle des travaux de Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2019-12- IDA / 57180 Post Consultant Open 1,308.00 1,678.62 Signed construction d'un bloc de 05 development support 03 17 22 24 12 23 16 05 15 Selection boutiques au marché d'Ardaf Commune de Guere CM-CRC EXTREME NORD- 111277-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- 2019-09- 2019-11- 2019-12- 2020-01- CONSTRUCTION DEUX IDA / 57180 Post Consultant Open 2,787.00 2,182.21 Completed development support 03 17 22 24 12 28 16 09 15 22 BLOCS DE CINQ (05) Selection BOUTIQUES AU MARCHÉ DE KALFOU, DANS LA COMMUNE DE KALFOU CM-CRC EXTREME NORD- 111340-CS-INDV / suivi controle des travaux de construction d'un forage Individual équipé de pompe à Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-12- 2019-12- IDA / 57180 Post Consultant Open 2,696.00 2,375.46 Signed motricité humaine à Gandou development support 03 17 22 24 12 05 16 06 15 Selection Golopo, au CES de Zaria, à Djada, réhabilitation d'un forage PMH à Delta Guibéré et Mandara, dans la commune de Kalfou CM-CRC EXTREME NORD- 111338-CS-INDV / suivi controle des travaux de construction d'un bloc de 02 Individual salles de classe équipées et Component A: Local 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2019-11- 2019-09- 2019-11- 2020-01- IDA / 57180 Post Consultant Open 9,791.00 82,526.23 Signed d'un bloc de latrines à development support 03 17 22 24 12 08 16 06 14 Selection troiscompartiments au CES Kamargui, à EP Goulourgou , EP Bigi, EP de Djenreng et EP Waimou commune de wina CM-CRC EXTREME NORD- 111256-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-04- 2019-06- 2019-05- 2019-07- 2019-06- 2019-10- 2019-07- 2019-11- 2019-11- construction d'un hangar de IDA / 57180 Post Consultant Open 3,051.00 3,357.24 Signed development support 01 17 20 24 10 23 15 05 12 28 places et d'une Selection boucherie au marché de Veleé, dans la commune de Guémé CM-CRC EXTREME NORD- 111346-CS-INDV / suivi controle des travaux Individual Component A: Local 2019-04- 2019-06- 2019-05- 2019-07- 2019-06- 2019-12- 2019-07- 2019-12- 2019-10- d'éclairage public à energie IDA / 57180 Post Consultant Open 762.00 923.86 Signed development support 01 17 20 24 10 05 15 06 13 solaire de 07 poteaux Selection solaires dans le centre urbain de vele Commune GUEME CM-CRC EXTREME NORD- 111351-CS-INDV / suivi controle des travaux de Individual Component A: Local Under 2019-04- 2021-01- 2019-05- 2019-06- 2019-07- 2019-10- construction de 01 forage à IDA / 57180 Post Consultant Open 1,524.00 0.00 development support Implementation 01 07 20 10 15 13 énergie solaire à CSI de Selection Bosgoye, dans la commune de Wina CM-CRC EXTREME NORD- 111361-CS-INDV / suivi controle des travaux de construction 02 salles de Individual classe et de latrines à l'EP Component A: Local 2019-04- 2019-06- 2019-05- 2019-07- 2019-06- 2019-07- 2019-07- 2019-08- 2019-10- IDA / 57180 Post Consultant Open 3,862.00 3,886.40 Signed BIJE construction de 2 development support 01 17 20 24 10 30 15 02 13 Selection salles de classeà EPPB de TOKOMBERE et equipement CES de makilingaidans la commune de Tokombere CM-CRC EXTREME NORD- 111326-CS-INDV / suivi controle des travaux de Individual construction d'un bloc de Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-05- 2019-10- 2019-07- IDA / 57180 Post Consultant Open 2,692.00 2,517.93 Completed deux salle de classe équipés development support 01 08 20 06 10 16 15 25 13 25 Selection et d'un bloc latrines à Magala Djamene dans la commune de Darak CM-CRC EXTREME NORD- 111332-CS-INDV / suivi Individual controle des travaux de Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-05- 2019-10- 2019-07- IDA / 57180 Post Consultant Open 762.00 839.08 Completed construction de 01 forage development support 01 08 20 07 10 16 15 21 13 17 Selection PMH à Magala Djamene, dans la commune de Darak CM-CRC EXTREME NORD- 111257-CS-INDV / suivi controle des travaux de construction d'un bloc de Individual deux salles de classe Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-09- 2019-11- IDA / 57180 Post Consultant Open 9,077.00 10,679.58 Signed équipées et d'un bloc de development support 01 08 20 07 10 16 15 10 12 Selection latrines à trois compartiments à EP GADAFAI, au Lycée de Fotokol à EP Magadji et à EP de GUEGUERI, commune de Fotokol CM-CRC EXTREME NORD- 111345-CS-INDV / suivi Individual Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-07- 2019-10- 2019-07- controle des travaux de IDA / 57180 Post Consultant Open 1,372.00 1,184.55 Completed development support 01 08 20 08 10 16 15 02 13 02 construction d'un magasin Selection de stockage à Goulfey CM-CRC EXTREME NORD- 111330-CS-INDV / suivi Individual controle des travaux de Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-05- 2019-10- IDA / 57180 Post Consultant Open 1,921.00 1,687.46 Signed construction d'une mini AEP development support 01 08 20 07 10 16 15 25 13 Selection pastorale à énergie solaire à fadja commune de Hilé Alifa CM-CRC EXTREME NORD- 111342-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-05- 2019-10- 2019-07- construction de 01 forage IDA / 57180 Post Consultant Open 1,981.00 2,531.19 Completed development support 01 08 20 08 10 16 15 27 13 05 PMH à Michiska Mousgoum, Selection OUNANGARE et NGADA, dans la commune de Logone Birni CM-CRC EXTREME NORD- 111258-CS-INDV / suivi Individual controle des travaux de Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-09- 2019-10- IDA / 57180 Post Consultant Open 1,921.00 2,531.19 Signed construction d'un magasin development support 01 08 20 07 10 16 15 21 13 Selection de stockage à zigague, dans la commune de Waza CM-CRC EXTREME NORD- 111356-CS-INDV / suivi Individual controle des travaux de Component A: Local 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-05- 2019-07- 2019-07- 2019-10- IDA / 57180 Post Consultant Open 2,034.00 2,328.61 Signed construction d'un forage development support 01 08 20 07 10 16 15 19 13 Selection PMH à malia, NDIGUINA et MADA dans la commune de Waza CM-CRC EXTREME NORD- 83186-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de Individual Component A: Local 2018-10- 2018-12- 2018-12- 2019-01- 2019-03- faisabilité techniques et IDA / 57180 Post Consultant Open 1,400.00 0.00 Canceled development support 15 03 24 28 14 environnementales des MP Selection de Construction d'un centre multimédia à Dziguilao dans la Commune de Dziguilao CM-CRC EXTREME NORD- 111318-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2019-11- 2019-07- 2019-08- 2019-09- 2019-11- construction d'un forage IDA / 57180 Post Consultant Open 610.00 0.00 Canceled development support 03 25 22 12 16 15 équipé de pompe à Selection motricité humaine a Djafgadjie, commue de yagoua CM-CRC EXTREME NORD- 111349-CS-INDV / suivi controle des travaux de construction D’UN BLOC DE Individual Component A: Local 2019-06- 2019-11- 2019-07- 2019-08- 2019-09- 2020-01- DEUX SALLES DE CLASSE IDA / 57180 Post Consultant Open 3,871.00 0.00 Canceled development support 03 25 22 12 16 14 AVEC BUREAUX EQUIPES au Selection CES de DJOGOIDI et au lycee de Vounaloum Commune de yagoua CM-CRC EXTREME NORD- 111370-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Component A: Local 2018-10- 2019-11- 2018-12- 2018-12- 2019-01- 2019-02- Etudes de faisabilité IDA / 57180 Post Consultant Open 2,200.00 0.00 Canceled development support 15 25 03 24 28 27 techniques et Selection environnementales de CONSTRUCTION D'UN BLOC DE MATERNITÉ ÉQUIPÉ AU CMA DE GAZAWA CM-CRC EXTREME NORD- 111234-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Component A: Local 2019-01- 2020-01- 2019-02- 2019-03- 2019-04- 2019-05- Etudes de faisabilité IDA / 57180 Post Consultant Open 1,000.00 0.00 Canceled development support 02 06 20 13 17 17 techniques et Selection environnementales d'un microprojet de construction d'un parc à bétail dans la commune de WINA CM-CRC EXTREME NORD- 111353-CS-INDV / suivi controle des travaux de Individual construction d'un CSI équipé Component A: Local 2019-06- 2020-03- 2019-07- 2019-08- 2019-09- 2020-01- IDA / 57180 Post Consultant Open 6,096.00 0.00 Canceled avec case d'astreinte, un development support 03 04 22 12 16 14 Selection incinérateur et un bloc de latrines au CSI Djiddeo Garre, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 111235-CS-INDV / Sélection d'un consultant pour l'élaboration des Etudes de faisabilité Individual Component A: Local 2019-04- 2020-03- 2019-05- 2019-06- 2019-07- 2019-08- techniques et IDA / 57180 Post Consultant Open 2,400.00 0.00 Canceled development support 01 04 20 10 15 29 environnementales de Selection construction d'un forage agricole à énergie solaire à Doumer et d'un construction d'un forage à énergie solaire à Djaodé CM-CRC EXTREME NORD- 111344-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2020-03- 2019-07- 2019-08- 2019-09- 2019-11- construction d'un forage IDA / 57180 Post Consultant Open 615.00 0.00 Canceled development support 03 04 22 12 16 15 équipé de PMH à lycee Selection bilingue dans la commue de Kaele CM-CRC EXTREME NORD- 111350-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2021-01- 2019-07- 2019-08- 2019-09- 2019-12- construction d’un forage à IDA / 57180 Post Consultant Open 1,178.00 0.00 Canceled development support 03 06 22 12 16 15 énergie solaire avec château Selection au centre de santé de Djiddéo, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 111357-CS-INDV / suivi Individual Component A: Local 2019-04- 2020-03- 2019-05- 2019-06- 2019-07- 2019-10- controle des travaux de IDA / 57180 Post Consultant Open 1,000.00 0.00 Canceled development support 01 04 20 10 15 13 réalisation d'un parc à bétail Selection dans la commune de Wina (GP) CM-CRC EXTREME NORD- 111347-CS-INDV / suivi controle des travaux de Individual Component A: Local 2019-06- 2020-03- 2019-07- 2019-08- 2019-09- 2019-11- construction d'un forage IDA / 57180 Post Consultant Open 630.00 0.00 Canceled development support 03 04 22 12 16 15 équipé de pompe à Selection motricité humaine à Bindiriel Danghou, commue de Tchatibali CM-CRC EXTREME NORD- 196621-CS-INDV / Suivi controle des travaux de Individual Construction d'un CSI Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-06- IDA / 57180 Post Consultant Open 4,838.00 0.00 équipé avec un incinérateur development support Implementation 30 06 27 17 21 21 Selection et un bloc de latrines au CSI Djiddeo Garre, dans la commune de Maroua 3 CM-CRC EXTREME NORD- 196857-CS-INDV / Suivi controle des travaux de Individual Construction et équipement Component A: Local Under 2020-10- 2020-11- 2020-11- 2020-12- 2021-01- 2021-04- IDA / 57180 Post Consultant Direct 1,829.00 0.00 des blocs des salles de development support Implementation 30 26 18 09 13 13 Selection classes et d'un bloc de latrines au CES de GUINADJI Commune de Maroua III CM-CRC EXTREME NORD- 196547-CS-INDV / Suivi controle des travaux de Construction D’UN FORAGE Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- PASTORAL A ENERGIE IDA / 57180 Post Consultant Open 1,662.00 0.00 development support Implementation 30 06 27 17 21 22 SOLAIRE EQUIPE D’UN Selection FORAGE ET DE (02) ABREUVOIRS DANS LA LOCALITE DE DJONGDONG, COMMUNE DE WINA, CM-CRC EXTREME NORD- 196622-CS-INDV / Suivi controle des travaux de CONSTRUCTION D’UN Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- FORAGE PASTORAL A IDA / 57180 Post Consultant Open 1,600.00 0.00 development support Implementation 30 06 27 17 21 22 ENERGIE SOLAIRE EQUIPE Selection D’UN château ET DE (02) ABREUVOIRS DANS LA LOCALITE DEMIZILING WAILA MAYO, COMMUNE DE GAZAWA CM-CRC EXTREME NORD- 196544-CS-INDV / Suivi controle des travaux deTravaux d'Eclairage public Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- en énergie solaire de 10 IDA / 57180 Post Consultant Open 3,566.00 0.00 development support Implementation 30 06 27 17 21 22 poteaux à Ndoukoula de 14 Selection poteaux à Dagaï Kola et de 15 poteaux à Loulou Commune de Ndoukoula Page 13 CM-CRC EXTREME NORD- 196628-CS-INDV / Suivi controle des travaux de Individual Component A: Local 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- 2021-05- Construction d'un bloc de IDA / 57180 Post Consultant Open 1,752.00 0.00 Canceled development support 30 26 18 08 12 13 deux salles de classe Selection équipées au lycee de Goundaye Commune de Dziguilao. CM-CRC EXTREME NORD- 196564-CS-INDV / Suivi controle des travaux de Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- Construction d'un bloc de IDA / 57180 Post Consultant Open 1,805.00 0.00 development support Implementation 30 06 27 17 21 22 deux salles de classe Selection équipées à l'EP de ZANYAO Commune de YAGOUA CM-CRC EXTREME NORD- 196526-CS-INDV / Suivi controle des travaux de construction d’un forage Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- équipé de pompe à IDA / 57180 Post Consultant Open 3,238.00 0.00 development support Implementation 30 06 27 17 21 22 motricité humaine à Dinao, Selection Louggol palé, Kodadjiho, Hamadalao et Golombeswé Commune KALFOU CM-CRC EXTREME NORD- 196638-CS-INDV / Suivi controle des travaux de Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- Construction d'un forage IDA / 57180 Post Consultant Open 1,295.00 0.00 development support Implementation 30 06 27 17 21 22 équipé de PMH à douang et Selection dingue-Gabaraye Commune de Gueme CM-CRC EXTREME NORD- 196889-CS-INDV / Suivi controle des travaux d'eclairage public par la Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-02- fourniture et l'installation de IDA / 57180 Post Consultant Open 1,295.00 0.00 development support Implementation 30 06 18 08 12 21 12 poteaux solaires de l’axe Selection Sous-préfecture- Ngaoundéréo Commune de Kalfou CM-CRC EXTREME NORD- 196540-CS-INDV / Suivi controle des travaux de Construction d'un bloc de deux salle de classe Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- équipées à l'EPB DE MADA IDA / 57180 Post Consultant Open 3,810.00 0.00 development support Implementation 30 06 27 17 21 22 KOLKOCH ET A LEP Selection MAMBEZA et Construction d'un bloc de latrines à l'EPB DE MADA KOLKOCH ET Commune de Tokombere CM-CRC EXTREME NORD- 196623-CS-INDV / Suivi controle des TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR LA Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- CONSTRUCTION DE 04 IDA / 57180 Post Consultant Open 3,810.00 0.00 development support Implementation 30 06 27 17 21 22 GUICHETS, 04 MAGASINS, Selection D’UN HANGAR D’ATTENTE ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE COMMUNE DE YAGOUA CM-CRC EXTREME NORD- 196853-CS-INDV / Suivi contrôle de la fourniture en Individual en equipement en 200 Component A: Local 2020-10- 2020-11- 2020-11- 2020-12- 2021-01- 2021-04- IDA / 57180 Post Consultant Direct 445.00 0.00 Canceled tables bancs, 4 bureaux, 4 development support 30 30 18 09 13 13 Selection chaises rembourées et 4 armoires à l'EP MAGA IIB Commune de Maga. CM-CRC EXTREME NORD- 196553-CS-INDV / Suivi controle des travaux Individual d'Eclairage public par la Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-05- IDA / 57180 Post Consultant Open 1,000.00 0.00 fourniture et l'installation de development support Implementation 30 06 27 17 21 22 Selection 3 poteaux solaires à Ouro Bone et 03 à Modjombodi Commune de Mindif CM-CRC EXTREME NORD- 196619-CS-INDV / Suivi Individual controle des travaux de Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-04- IDA / 57180 Post Consultant Open 1,000.00 0.00 Construction d’un forage development support Implementation 30 06 27 17 21 22 Selection PMH au centre de santé de Djiddéo Commune de Maroua III CM-CRC EXTREME NORD- 196626-CS-INDV / Suivi Individual controle des travaux de Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-04- IDA / 57180 Post Consultant Open 1,000.00 0.00 Construction d'un forage development support Implementation 30 06 27 17 21 22 Selection équipé de PMH de Yonkolel Commune de Dargala. CM-CRC EXTREME NORD- 196535-CS-INDV / Suivi controle des travaux de Construction d'un forage Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-04- équipé de PMH à lalepaki et IDA / 57180 Post Consultant Open 1,000.00 0.00 development support Implementation 30 06 27 17 21 22 Acquisition d’une caisse à Selection outils pour l’entretien des forages dans la commune de Commune de Touloum CM-CRC EXTREME NORD- 196576-CS-INDV / Suivi controle des travaux de Individual fourniture et installation Component A: Local Under 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- 2021-02- IDA / 57180 Post Consultant Open 1,000.00 0.00 d’un kit solaire pour development support Implementation 30 25 27 17 21 27 Selection l’alimentation en energie électrique du lycée de gabaraye. Commune Gueme. CM-CRC EXTREME NORD- 196627-CS-INDV / Suivi controle des travaux de Individual Component A: Local Under 2020-10- 2021-01- 2020-12- 2021-01- 2021-02- 2021-04- Construction d'un forage IDA / 57180 Post Consultant Open 1,000.00 0.00 development support Implementation 30 06 27 17 21 22 équipé de pompe à Selection motricité humaine à Guermé Kalfou Commune de Kalfou CM-CRC EXTREME NORD- 196845-CS-INDV / Suivi contrôle de la fourniture en Equipement en 60 tables Individual Component A: Local 2020-10- 2020-11- 2020-11- 2020-12- 2021-01- 2021-04- bancs et un bureau à l'EP IDA / 57180 Post Consultant Direct 1,000.00 0.00 Canceled development support 30 26 18 09 13 13 Guinlaye et 111 tables Selection bancs et un bureau à l'EP BOGO SIRATARE I Commune de BOGO CM-CRC EXTREME NORD- 204438-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 3,800.00 0.00 de Construction de salles de development support Implementation 16 21 12 16 02 Selection classe équipées dans le complexe d'écoles publiques Grpe 1, 2, 3 et 4 de Fotokol, commune fotokol. CM-CRC EXTREME NORD- 204457-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local 2020-11- 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Limited 4,200.00 0.00 Under Review development support 16 13 21 12 16 02 de travaux Rénovation et Selection équipement du CMA de Fotokol Commune de FOTOKOL CM-CRC EXTREME NORD- 204439-CS-INDV / Elaboration des Etudes de faisabilité des MP de Individual Construction d’un forage Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 3,400.00 0.00 équipé de pompe à development support Implementation 16 21 12 16 02 Selection motricité humaine à Mada (Ngroh), à Goura 2, à Labado, à Chou et réhabilitation d’un forage à Mada 1 Commune de Makary CM-CRC EXTREME NORD- 204435-CS-INDV / Elaboration des Etudes de Individual faisabilité techniques et Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-01- IDA / 62240 Post Consultant Limited 2,200.00 0.00 environnementales des MP development support Implementation 16 21 12 16 19 Selection de Construction d’une mini AEP au camp des réfugiés d’Afadé Commune de Makary CM-CRC EXTREME NORD- 204447-CS-INDV / Elaboration des Etudes de faisabilité techniques et environnementales des MP Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- de Construction d’un bloc IDA / 62240 Post Consultant Limited 2,400.00 0.00 development support Implementation 16 21 12 16 02 de deux salles de classe Selection équipées avec bloc latrines à l’EP de Djamous à l’EP BODO (1 ET 2) et à l'EP BIAMO Commune de Makary CM-CRC EXTREME NORD- 204456-CS-INDV / Elaboration des Etudes de faisabilité des MP de Construction d’un bloc de Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- deux salles de classe IDA / 62240 Post Consultant Limited 3,000.00 0.00 development support Implementation 16 21 12 16 02 équipées dans les EP gpe Selection 1A, 1B et Construction d’un bloc maternel à l’école maternelle de Logone Birni Commune de Logone Birni CM-CRC EXTREME NORD- 204441-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 3,000.00 0.00 de Construction et development support Implementation 16 21 12 16 02 Selection équipement d’une salle d’hospitalisation et bloc opératoire au CMA de Logone birni Commune de Logone Birni CM-CRC EXTREME NORD- 204443-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Direct 1,600.00 0.00 development support Implementation 16 26 17 21 07 d'Equipement et fourniture Selection de médicaments aux CSI de Zizagué et CSI de Waza Commune de waza CM-CRC EXTREME NORD- 204436-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Limited 1,600.00 0.00 development support Implementation 16 21 12 16 02 de Construction d’un forage Selection équipé de PMH à Tagawa Y/C etude complementaire Commune de Waza CM-CRC EXTREME NORD- 204381-CS-INDV / Elaboration des Etudes de Individual faisabilité techniques et Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 1,600.00 0.00 environnementales des MP development support Implementation 16 21 12 25 11 Selection d'Alimentation en énergie solaire du CSI de Kossa Commune de Mora CM-CRC EXTREME NORD- 204454-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Direct 1,300.00 0.00 development support Implementation 16 26 17 21 07 de Equipement et fourniture Selection de médicaments au CSI de Kossa et au CSI de Méhé Emma Commune de Mora CM-CRC EXTREME NORD- 204455-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 2,900.00 0.00 de Construction d’un forage development support Implementation 16 21 12 16 02 Selection équipé de PMH à Yémé, Dandaya, à Koldima, Madina et au Camp des réfugiés de Méhé Emma Commune de Mora CM-CRC EXTREME NORD- 204445-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Limited 2,200.00 0.00 development support Implementation 16 21 12 16 02 de Construction d’un bloc Selection de deux salles équipées à l’EP d’Igawa et kotcherehe Commune de Mora CM-CRC EXTREME NORD- 204444-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual environnementales des MP Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- IDA / 62240 Post Consultant Limited 3,600.00 0.00 Construction d’un bloc de development support Implementation 16 21 12 16 02 Selection 02 salles de classe à EPB Kosséhone, à EP NDROCK Tourou, EP de Wandaï Commune de Mokolo CM-CRC EXTREME NORD- 204458-CS-INDV / suivi- contrôle des travaux de Individual construction d’un bloc de Component A: Local Under 2020-11- 2021-01- 2020-12- 2020-12- 2021-01- 2021-05- IDA / 62240 Post Consultant Limited 2,285.71 0.00 deux salles de classe development support Implementation 26 06 01 22 26 26 Selection équipées avec bloc latrines à à l’EP d’Afadé Groupe 2 Commune Makary CM-CRC EXTREME NORD- 204386-CS-INDV / Elaboration des Etudes de Individual faisabilité techniques et Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-02- IDA / 62240 Post Consultant Limited 1,800.00 0.00 environnementales des MP development support Implementation 16 21 05 09 23 Selection de Construction d'un bloc de CSI au CSI de kossehone Commune de Mokolo CM-CRC EXTREME NORD- 204453-CS-INDV / Elaboration des Etudes de faisabilité techniques et Individual Component A: Local Pending 2020-11- 2020-11- 2020-12- 2021-01- 2021-03- environnementales des MP IDA / 62240 Post Consultant Limited 2,600.00 0.00 development support Implementation 16 21 12 16 02 deConstruction de 01 Selection forage à Zamai, à EP FERDE, à Kosséhone et à Ldendeng Commune de Mokolo CM-CRC EXTREME NORD- 196625-CS-INDV / Suivi Individual contrôle de la fourniture en Component A: Local 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- 2021-04- IDA / 57180 Post Consultant Open 1,000.00 0.00 Canceled en Équipement en matériel development support 30 25 27 17 21 22 Selection médicaux au CSI de Takreo yoldeo Commune Kar Hay CM-CRC EXTREME NORD- 196620-CS-INDV / Suivi controle des travaux de Individual Component A: Local 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- 2021-04- REALISATION D’UN FORAGE IDA / 57180 Post Consultant Open 1,000.00 0.00 Canceled development support 30 25 27 17 21 22 EQUIPE DE POMPE A Selection MOTRICITE HUMAINE A Dolgaye Commune Kar Hay CM-CRC EXTREME NORD- 222830-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Etudes de faisabilité Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-09- IDA / 62240 Post Consultant Open 3,600.00 0.00 techniques et development support Implementation 08 27 17 22 05 Selection environnementales des MP d'Alimentation en énergie solaire au CMA de de Fotokol Commune de Fotokol (A101201) CM-CRC EXTREME NORD- 222746-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Etudes de faisabilité Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-09- IDA / 62240 Post Consultant Open 3,600.00 0.00 techniques et development support Implementation 08 27 17 22 05 Selection environnementales des MP de construct d’une mini AEP au cma de Logone birni Commune de Logone birni (A101201) CM-CRC EXTREME NORD- 222774-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Etudes de faisabilité Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-09- IDA / 62240 Post Consultant Open 3,000.00 0.00 techniques et development support Implementation 08 27 17 22 05 Selection environnementales des MP d'Alimentation en énergie solaire au cma de Logone birni Commune de Logone birni (A101201) Page 14 CM-CRC EXTREME NORD- 222796-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Etudes de faisabilité Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-09- IDA / 62240 Post Consultant Open 1,300.00 0.00 techniques et development support Implementation 08 27 17 22 05 Selection environnementales des MP construct d’un bloc de 02 salles de classe à EP mokola djavdjaya Commune de Mokolo (A101201) CM-CRC EXTREME NORD- 222805-CS-INDV / Sélection d'un consultant pour l'élaboration des Individual Etudes de faisabilité Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-09- IDA / 62240 Post Consultant Open 1,800.00 0.00 techniques et development support Implementation 08 27 17 22 05 Selection environnementales des MP deconstruct de 01 forage À Zamai, à ferdé et Ldendeng Commune de Mokolo (A101201) CM-CRC EXTREME NORD- 222751-CS-INDV / suivi controle des travaux de Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- construct et équipement IDA / 62240 Post Consultant Open 6,095.00 0.00 development support Implementation 08 27 17 22 19 d’une salle d’hospitalisation Selection et d'un bloc opératoire au CMA de Logone birni CM-CRC EXTREME NORD- 222781-CS-INDV / suivi controle des travaux de construct d’1 bloc maternel Individual et latrines à EM Logone Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 5,940.00 0.00 birni et Réhabilitation de 6 development support Implementation 08 27 17 22 19 Selection salles de classe avec bureau attenant et équipement a EP Logone birni GPE 1 A Commune de Logone birni CM-CRC EXTREME NORD- 222801-CS-INDV / suivi controle des travaux de Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2022-01- construct et équipement IDA / 62240 Post Consultant Open 6,095.00 0.00 development support Implementation 08 27 17 22 18 d’une salle d’hospitalisation Selection et d'un bloc opératoire au CMA de Fotokol CM-CRC EXTREME NORD- 222786-CS-INDV / suivi controle des travaux de construct de 4 salles de Individual classe équipées avec 2 Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 9,145.00 0.00 bureau à EP Fotokol et development support Implementation 08 27 17 22 19 Selection construct de 4 salles de classe équipées avec 2 bureau et de 3 blocs de latrines à EP Fotokol Commune de Fotokol CM-CRC EXTREME NORD- 222787-CS-INDV / suivi controle des travaux de construct de deux blocs de deux salles de classe Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- équipées, d'un bloc de deux IDA / 62240 Post Consultant Open 6,505.00 0.00 development support Implementation 08 27 17 22 19 salles de classe équipées Selection avec bureau pour enseignants et d'un bloc latrines a trois compartiments à EP de BIAMO Commune de Makary CM-CRC EXTREME NORD- 222777-CS-INDV / suivi controle des construct de 6 SDC équipées avec bureau et latrines à EP de BIAMO Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- construct de 2 SDC avec IDA / 62240 Post Consultant Open 4,910.00 0.00 development support Implementation 08 27 17 22 19 bureau a EP GRP 2 de BODO, Selection construct de 2 SDC avec bureau et latrines a EP de DJAMOUS Commune de Makary CM-CRC EXTREME NORD- 222823-CS-INDV / suivi controle des travaux de construct d’un forage Individual équipé de pompe à Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-08- IDA / 62240 Post Consultant Open 2,925.00 0.00 motricité humaine à Mada development support Implementation 08 27 17 22 03 Selection (Ngroh), à Goura 2 (Mosquée), à Labado, à Chou et réhabilitation d’un forage à Mada 1 (quartier Sara) Commune de Makary CM-CRC EXTREME NORD- 222826-CS-INDV / suivi Individual controle des travaux de Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 1,520.00 0.00 construct d’une mini AEP au development support Implementation 08 27 17 22 19 Selection camp des réfugiés d’Afadé Commune de Makary CM-CRC EXTREME NORD- 222762-CS-INDV / suivi Individual controle des travaux de Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-10- IDA / 62240 Post Consultant Open 1,000.00 0.00 construct d’un forage development support Implementation 08 27 17 22 20 Selection équipé de PMH à Tagawa Commune de Waza CM-CRC EXTREME NORD- 222808-CS-INDV / suivi controle des travaux de réalisation d’un forage productif équipé de pompe Individual à motricité humaine dans Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 3,875.00 0.00 les localités de : YEME, development support Implementation 08 27 17 22 19 Selection DANDAYA, KOLDIMA, MADJINA et MEHE EMMA (Camp refugié) dans la Commune de Mora, Département du Mayo Sava. CM-CRC EXTREME NORD- 222824-CS-INDV / suivi controle des de construct d’1 logement d'astreint et Individual d'un mur de cloture à l’EP Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 7,930.00 0.00 IGAWA MEME,et de development support Implementation 08 27 17 22 19 Selection construct de 4 salles de classe équipées avec 1 bureau attenant et de latrines à l’EP de KOTCHEREHE Commune de Mora CM-CRC EXTREME NORD- 222799-CS-INDV / SUIVI CONTROLE DES TRAVAUX DE construct D’UN BLOC DE DEUX SALLES DE CLASSE EQUIPEES AVEC BUREAU ET Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- D’UN BLOC LATRINE A IDA / 62240 Post Consultant Open 7,575.00 0.00 development support Implementation 08 27 17 22 19 TROIS COMPARTIMENTS A Selection L’EPB DE KOSSEHONE, L'EP WANDAI ET L'EP NDROCK DANS LA COMMUNE DE MOKOLO, DEPARTEMENT DU MAYO-TSANAGA. CM-CRC EXTREME NORD- 222768-CS-INDV / Suivi contrôle des travaux de Individual construct de 01 forage à Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- IDA / 62240 Post Consultant Open 2,685.00 0.00 Zamai, à Ldagodja-Tourou, development support Implementation 08 27 17 22 19 Selection à Ngolkodjala-Kosséhone et à Wandaï-djamboutou Commune de Mokolo CM-CRC EXTREME NORD- 222737-CS-INDV / SUIVI CONTROLE DES TRAVAUX DE construct ET Individual Component A: Local Pending 2021-04- 2021-05- 2021-06- 2021-07- 2021-11- EQUIPEMENT DU CENTRE DE IDA / 62240 Post Consultant Open 6,095.00 0.00 development support Implementation 08 27 17 22 19 SANTE INTEGRE A Selection KOSSEHONE DANS LA COMMUNE DE MOKOLO, DEPARTEMENT DU MAYO- TSANAGA. CM-CRC EXTREME NORD- 222987-CS-INDV / Suivi contrôle des Travaux de Individual Component A: Local Pending 2021-05- 2021-06- 2021-07- 2021-08- 2021-10- Construction de 01 forage IDA / 57180 Post Consultant Open 1,371.00 0.00 development support Implementation 05 23 14 18 17 à énergie solaire au CSI de Selection hile haoussa, dans la commune de kousseri (A2031C1) CM-CRC EXTREME NORD- 228207-CS-INDV / Suivi contrôle des travaux de Individual construction d'un bloc Component A: Local Pending 2021-05- 2021-06- 2021-07- 2021-08- 2021-10- IDA / 62240 Post Consultant Open 1,000.00 0.00 latrines a troix development support Implementation 05 23 14 18 17 Selection compartiement et construction d'un incinerateur au CSI de hile haoussa dans la Commune de kousseri CM-CRC EXTREME NORD- 222755-CS-INDV / suivi controle des travaux de FOURNITURE ET Individual INSTALLATION D’UNE MINI Component A: Local Pending 2021-06- 2021-07- 2021-08- 2021-09- 2022-01- IDA / 62240 Post Consultant Open 2,275.00 0.00 CENTRALE SOLAIRE AU CSI development support Implementation 01 20 10 14 12 Selection DE KOSSA, DANS LA COMMUNE DE MORA, DEPARTEMENT DU MAYO- SAVA, REGION DE L’EXTREME – NORD. Page 15 PROCUREMENT PLAN (Textual Part) Project information: [Sudan] [Sudan Family Support Program] (SFSP) (P173521) Project Implementation agency: [Ministry of Finance & Economic Planning/ PIU] Date of the Procurement Plan: [31/08/2020] Period covered by this Procurement Plan: [18 Month] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [Sudan procurement contracting and disposal of assets law 2010], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. [Applicable as provide in section 5 paragraph 5.3 to 5.6 of procurement REGULATION for IPF Borrowers] When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable is for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. [N/A] PROCUREMENT Sudan : Sudan Family Support Project PLAN General Information Country: Sudan Bank’s Approval Date of the Original Procurement Plan: 2020-11-22 2021-05-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173521 GPN Date: Project Name: Sudan Family Support Project Loan / Credit No: IDA / D7350 Ministry of Finance and Economic Planning Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-MOWSS-202443-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / ICT Hardware / USSD IDA / D7350 Delivery Systems and Build Post Limited 190,000.00 0.00 Implementati 2020-11-06 2021-01-01 2021-06-30 Quotations Envelope Gateway Institutional Capacity on SD-MOWSS-202446-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / Laptops for physical IDA / D7350 Delivery Systems and Build Post Limited 125,000.00 0.00 Implementati 2020-11-06 2021-01-01 2021-06-30 Quotations Envelope Registration Institutional Capacity on SD-MOWSS-202448-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / Tablets for physical IDA / D7350 Delivery Systems and Build Post Limited 60,000.00 0.00 Implementati 2020-11-06 2021-01-01 2021-06-30 Quotations Envelope registration Institutional Capacity on SD-MOWSS-202449-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / Rent bandwidth for USSD IDA / D7350 Delivery Systems and Build Post Limited 3,000.00 0.00 Implementati 2020-11-06 2021-01-01 2021-06-30 Quotations Envelope (three Telcos) Institutional Capacity on Component 2: Establish Pending SD-MOWSS-202639-GO-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 10,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / CRM Software Quotations Envelope Institutional Capacity on SD-MOWSS-202640-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / Vehicle for Mobile IDA / D7350 Delivery Systems and Build Post Limited 1,375,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 Quotations Envelope registration Institutional Capacity on SD-MOWSS-202642-GO-RFQ Component 2: Establish Pending Request for Single Stage - One / Satellite Communication for IDA / D7350 Delivery Systems and Build Post Open - International 125,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 Quotations Envelope registration vehicles Institutional Capacity on Component 2: Establish Under SD-MOFEP-235901-GO-RFB Single Stage - One IDA / D7350 Delivery Systems and Build Post Request for Bids Open - National 750,000.00 0.00 Implementati 2021-05-24 2021-05-30 2021-05-30 2021-07-15 2021-07-21 2021-07-29 2021-08-15 / Supply of Tablets Envelope Institutional Capacity on Component 2: Establish Pending SD-MOFEP-236095-GO-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 100,000.00 0.00 Implementati 2021-07-05 2021-08-30 2022-02-26 / Supply of tablets Quotations Envelope Institutional Capacity on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Project Pending SD-MOWSS-202694-NC-RFQ Request for Single Stage - One IDA / D7350 Management, Monitoring and Post Limited 11,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / Office furniture Quotations Envelope Evaluation, and Learning on Component 3: Project Pending SD-MOWSS-202703-NC-RFQ Request for Single Stage - One IDA / D7350 Management, Monitoring and Post Limited 5,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / Software Packages Quotations Envelope Evaluation, and Learning on Component 2: Establish Pending SD-MOWSS-202704-NC-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 10,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / Cell Phone Quotations Envelope Institutional Capacity on Component 2: Establish Pending SD-MOWSS-202705-NC-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 3,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / Stationery Quotations Envelope Institutional Capacity on Component 2: Establish Pending SD-MOWSS-202707-NC-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 14,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / monitors/docking stations Quotations Envelope Institutional Capacity on Component 2: Establish Pending SD-MOWSS-202708-NC-RFQ Request for Single Stage - One IDA / D7350 Delivery Systems and Build Post Limited 20,000.00 0.00 Implementati 2020-11-09 2021-01-04 2021-07-03 / Vehicle rent for Sr staff Quotations Envelope Institutional Capacity on SD-MOFEP-207302-NC-RFQ Component 2: Establish Pending Request for Single Stage - One / Data Protection Authority / IDA / D7350 Delivery Systems and Build Post Limited 300,000.00 0.00 Implementati 2020-12-06 2021-01-31 2021-07-30 Quotations Envelope Institutional arrangments Institutional Capacity on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Component 2: Establish SD-MOWSS-202671-CS- Quality And Cost- Pending IDA / D7350 Delivery Systems and Build Post Open - International 250,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 QCBS / Reconciliation Audit Based Selection Implementation Institutional Capacity SD-MOWSS-202673-CS- Component 2: Establish QCBS / Payment Services Quality And Cost- Pending IDA / D7350 Delivery Systems and Build Post Open - International 150,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 Providers (MNOs, Banks, Based Selection Implementation Institutional Capacity Other) SD-MOWSS-202679-CS- Component 2: Establish Quality And Cost- Pending QCBS / MIS Development IDA / D7350 Delivery Systems and Build Post Open - International 200,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 Based Selection Implementation (Firm) Institutional Capacity Component 2: Establish SD-MOWSS-202680-CS- Quality And Cost- Pending IDA / D7350 Delivery Systems and Build Post Open - International 15,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 QCBS / MEL Framework (Firm) Based Selection Implementation Institutional Capacity SD-MOWSS-202681-CS- Component 2: Establish Quality And Cost- Pending QCBS / Media Content IDA / D7350 Delivery Systems and Build Post Open - National 15,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 Based Selection Implementation Creation Institutional Capacity Component 2: Establish SD-MOWSS-202682-CS- Quality And Cost- Pending IDA / D7350 Delivery Systems and Build Post Open - National 15,000.00 0.00 2020-11-04 2020-11-25 2021-01-08 2021-02-05 2021-03-07 2021-04-11 2021-05-16 2022-05-16 QCBS / Media Punchers Based Selection Implementation Institutional Capacity INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-MOWSS-201613-CS-CQS Component 3: Project Individual Under / ENROLLMENT MA / IDA / D7350 Management, Monitoring and Post Consultant Open 12,000.00 0.00 2020-11-02 2021-02-22 2020-12-21 2021-01-11 2021-02-15 2021-08-14 Implementation Enrolment Manager Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202658-CS- Under IDA / D7350 Management, Monitoring and Post Consultant Open 12,000.00 0.00 2020-11-02 2021-02-22 2020-12-21 2021-01-11 2021-02-15 2021-08-14 INDV / Payment Manager Implementation Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202659-CS- Under IDA / D7350 Management, Monitoring and Post Consultant Open 12,000.00 0.00 2020-11-02 2021-02-22 2020-12-21 2021-01-11 2021-02-15 2021-08-14 INDV / Information Security Implementation Evaluation, and Learning Selection SD-MOWSS-202657-CS- Component 3: Project Individual INDV / Communication IDA / D7350 Management, Monitoring and Prior Consultant Open 12,000.00 0.00 Under Review 2020-11-02 2020-12-21 2021-01-11 2021-02-15 2021-08-14 Manager Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202663-CS- Under IDA / D7350 Management, Monitoring and Post Consultant Limited 40,000.00 0.00 2020-11-04 2021-02-22 2020-11-09 2020-11-30 2021-01-04 2021-07-03 INDV / Program Manager Implementation Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202660-CS- Pending IDA / D7350 Management, Monitoring and Post Consultant Open 12,000.00 0.00 2020-11-02 2020-12-21 2021-01-11 2021-02-15 2021-08-14 INDV / MIS Manager Implementation Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202661-CS- Under IDA / D7350 Management, Monitoring and Post Consultant Open 12,000.00 0.00 2020-11-02 2021-02-22 2020-12-21 2021-01-11 2021-02-15 2021-08-14 INDV / MEL Manager Implementation Evaluation, and Learning Selection SD-MOWSS-202664-CS- Component 3: Project Individual Pending INDV / Database IDA / D7350 Management, Monitoring and Post Consultant Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Administrator Evaluation, and Learning Selection SD-MOWSS-202666-CS- Component 3: Project Individual Pending INDV / Network IDA / D7350 Management, Monitoring and Post Consultant Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Administration Evaluation, and Learning Selection SD-MOWSS-202667-CS- Component 3: Project Individual Pending INDV / Family Enrolment Lead IDA / D7350 Management, Monitoring and Post Consultant Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Officer Evaluation, and Learning Selection SD-MOWSS-202668-CS- Component 3: Project Individual Pending INDV / Registration Focal IDA / D7350 Management, Monitoring and Post Consultant Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Points per State Evaluation, and Learning Selection Component 3: Project Individual SD-MOWSS-202649-CS- Pending IDA / D7350 Management, Monitoring and Post Consultant Limited 18,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 INDV / Payments Officer Implementation Evaluation, and Learning Selection SD-MOWSS-202651-CS- Component 3: Project Individual Pending INDV / Grievance Redress IDA / D7350 Management, Monitoring and Post Consultant Limited 12,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Officer Evaluation, and Learning Selection SD-MOWSS-202652-CS- Component 3: Project Individual Pending INDV / Privacy and Digital IDA / D7350 Management, Monitoring and Post Consultant Limited 21,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Ethics Officer Evaluation, and Learning Selection SD-MOWSS-202653-CS- Component 3: Project Individual Pending INDV / Civil Society and IDA / D7350 Management, Monitoring and Post Consultant Limited 21,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Community Outreach Officer Evaluation, and Learning Selection SD-MOWSS-202655-CS- Component 3: Project Individual Pending INDV / State-level IDA / D7350 Management, Monitoring and Post Consultant Limited 12,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Communication Coordinator Evaluation, and Learning Selection SD-MOWSS-202656-CS- Component 3: Project Individual Pending INDV / Gender / Social Impact IDA / D7350 Management, Monitoring and Post Consultant Limited 12,000.00 0.00 2020-11-04 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Specialist Evaluation, and Learning Selection SD-MOWSS-202670-CS- Component 3: Project Individual Under INDV / Project Procurement IDA / D7350 Management, Monitoring and Prior Consultant Limited 21,000.00 0.00 2020-11-04 2021-02-22 2020-11-09 2020-11-30 2021-01-04 2021-07-03 Implementation Specialist Evaluation, and Learning Selection Page 2 Component 3: Project SD-MOFEP-236088-CS-CDS Pending IDA / D7350 Management, Monitoring and Post Direct Selection Direct 42,000.00 0.00 2021-06-15 2021-06-25 2021-08-29 2022-02-25 / Hiring of Legal advisor Implementation Evaluation, and Learning SD-MOFEP-236097-CS-INDV Component 3: Project Individual Pending / Digital Channel Enrollment IDA / D7350 Management, Monitoring and Post Consultant Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Implementation Officer Evaluation, and Learning Selection SD-MOFEP-236104-CS-INDV Component 3: Project Individual Pending / Family Enrollment Team IDA / D7350 Management, Monitoring and Post Consultant Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Implementation leader Evaluation, and Learning Selection Component 3: Project Individual SD-MOFEP-236106-CS-INDV Pending IDA / D7350 Management, Monitoring and Post Consultant Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 / Business Analyst Implementation Evaluation, and Learning Selection Component 3: Project Individual SD-MOFEP-236111-CS-INDV Pending IDA / D7350 Management, Monitoring and Post Consultant Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 / hiring of Payment Officer Implementation Evaluation, and Learning Selection SD-MOFEP-236113-CS-INDV Component 3: Project Individual Pending / hiring of Social Media IDA / D7350 Management, Monitoring and Post Consultant Limited 30,000.00 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Implementation Associate Evaluation, and Learning Selection Page 3 PROCUREMENT PLAN (Textual Part) Project information: SUDAN EDUCATION COVID-19 RESPONSE Sudan, (SECEP) P174220 Project Implementation agency: Federal Ministry of Education Date of the Procurement Plan: May 2020 Period covered by this Procurement Plan: [May 2020 –Feb 2021] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [ Not applicable], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. The project will implement procurement of goods that will contribute to project’s objective, through the Alternative Procurement Arrangements (APA) where the recipient is a 3rd party e.g. a UN Agency. To expedite, prioritize 3rd parties with whom the Bank already has APA arrangements to minimize time required for the APA assessments. Agencies with existing APA arrangements include WHO, UNICEF, FAO, UNOPS, WFP, UNDP and ICRC. PROCUREMENT Sudan : Sudan Education COVID-19 Response PLAN General Information Country: Sudan Bank’s Approval Date of the Original Procurement Plan: 2021-05-30 2021-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174220 GPN Date: Project Name: Sudan Education COVID-19 Response Loan / Credit No: TF / B3339 Ministry of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-MOE-210604-GO-RFQ / Supporting safe transition Pending Printing and distribution of Request for Single Stage - One TF / B3339 back to school during Post Open - National 1,300,000.00 0.00 Implementati 2021-01-20 2021-02-03 2021-02-28 assignments for Basic School Quotations Envelope recovery on Students SD-MOE-210623-GO-DIR / Pending Program coordination and Procurement Ready Made TF / B3339 Post Direct Selection Direct 50,000.00 0.00 Implementati 2020-12-25 2020-12-30 2021-02-03 2021-08-02 management Accounting Software for PCU on SD-MOE-210624-GO-RFQ / Pending Program coordination and Request for Single Stage - One Procurement of laptops for TF / B3339 Post Open - National 30,000.00 0.00 Implementati 2020-12-30 2021-02-24 2021-08-23 management Quotations Envelope PCU on SD-MOE-210625-GO-RFQ / Pending Procurement of photocopier Program coordination and Request for Single Stage - One TF / B3339 Post Open - National 32,000.00 0.00 Implementati 2021-01-04 2021-03-01 2021-08-28 for PCU management Quotations Envelope on Office Equipment SD-MOE-210626-GO-UN / Pending Procurement of Vehicles for Program coordination and UN Agencies TF / B3339 Post Direct 120,000.00 0.00 Implementati 2020-12-30 2021-01-04 2021-02-08 2021-08-07 states (four Pick-Up double management (Direct) on cabin) SD-MOE-210627-GO-RFQ / Pending Program coordination and Request for Single Stage - One Procurement of Audiovisuals TF / B3339 Post Open - National 50,000.00 0.00 Implementati 2021-01-20 2021-03-17 2021-09-13 management Quotations Envelope tools for distant learning on Supporting learning SD-MOE-210609-GO-UN / continuity at the basic Pending Procurement of (100,000) Single Stage - Two TF / B3339 education level during the Prior Request for Bids Open - National 2,000,000.00 0.00 Implementati 2021-06-15 2021-06-20 2021-07-04 2021-07-20 2021-09-30 Solar FM/AM/SW portable Envelope COVID-19 pandemic and on radios school system shutdown SD-MOE-210605-GO-RFQ / Supporting safe transition Pending Request for Single Stage - One Provision of 1,760 storage TF / B3339 back to school during Post Open - National 880,000.00 0.00 Implementati 2021-06-06 2021-07-13 2021-08-09 Quotations Envelope Water tanks to schools recovery on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Supporting learning SD-MOE-210599-NC-RFP / continuity at the basic Pending Request for Single Stage - Two General broadcasting (COVID- TF / B3339 education level during the Post Limited 400,000.00 0.00 Implementati 2020-12-20 2021-01-12 2021-01-19 2021-01-26 2021-03-17 2022-09-08 Proposals Envelope 19 awareness, WASH) COVID-19 pandemic and on school system shutdown Supporting learning SD-MOE-210603-NC-RFP / continuity at the basic Pending Request for Improving of education TF / B3339 education level during the Post Limited 700,000.00 0.00 Implementati 2021-01-05 2021-02-21 2021-02-21 2021-02-28 2021-04-06 2022-05-05 Proposals quality in Math and reading COVID-19 pandemic and on school system shutdown CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-MOE-210611-CS-CQS / Consultant Program coordination and Pending Hiring of PCU Financial TF / B3339 Post Qualification Open - National 24,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 management Implementation Management Officer Selection Consultant SD-MOE-210618-CS-CQS / Program coordination and Pending TF / B3339 Post Qualification Open - National 36,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 Hiring of PCU M&E Specialist management Implementation Selection Consultant SD-MOE-210619-CS-CQS / Program coordination and Pending TF / B3339 Post Qualification Open - National 36,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 Hiring of PCU Data Specialist management Implementation Selection SD-MOE-210620-CS-CQS / Consultant Program coordination and Pending Hiring of PCU Assistant Data TF / B3339 Post Qualification Open - National 24,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 management Implementation Specialist Selection Consultant SD-MOE-210621-CS-CQS / Program coordination and Pending TF / B3339 Post Qualification Open - National 24,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 Hiring of PCU ICT Officer management Implementation Selection Page 1 SD-MOE-210622-CS-CQS / Consultant Program coordination and Pending Hiring of PCU communication TF / B3339 Post Qualification Open - National 24,000.00 0.00 2020-12-25 2021-01-15 2021-02-28 2021-03-30 2021-05-04 2021-10-31 management Implementation officer Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: DRC - Regional Great Lakes Integrated Development Project (P-143307) Project Implementation agency: Ministry of Agriculture Date of the Procurement Plan: April 18, 2017 Period covered by this Procurement Plan: July2014 – July 31, 2017 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: Request for quotations; Works: Not Applicable Other Relevant Procurement Information. PROCUREMENT Eastern Africa : AFR RI-Regional Great Lakes Integrated Agriculture Development Project PLAN General Information Country: Eastern Africa Bank’s Approval Date of the Original Procurement Plan: 2017-04-18 2021-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P143307 GPN Date: 2018-11-02 Project Name: AFR RI-Regional Great Lakes Integrated Agriculture Development Project Loan / Credit No: IDA / Q9260, IDA / 58520, IDA / Q9610 Ministry of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-MINAGRI-79144-CW- RFB / Travaux de Support Services and Project Single Stage - One 2018-10- 2019-01- 2018-10- 2019-07- 2018-11- 2019-02- 2018-12- 2019-03- 2019-01- 2019-08- 2019-07- IDA / 58520 Prior Request for Bids Open - National 500,000.00 656,215.93 Signed réhabilitation des bâtiments Management Envelope 03 11 08 13 19 22 19 29 23 09 22 des inspestions provinciales de Sud Kivu ZR-MINAGRI-78946-CW- RFB / Travaux de Support Services and Project Single Stage - One 2018-10- 2019-01- 2018-10- 2018-11- 2019-02- 2018-12- 2019-03- 2019-01- 2019-06- 2019-07- IDA / 58520 Post Request for Bids Open - National 500,000.00 486,607.72 Signed réhabilitation des bâtiments Management Envelope 03 11 08 19 22 19 21 23 24 22 des inspestions provinciales de Tanganyika ZR-MINAGRI-79093-CW- RFQ / Travaux de réhabilitation des bâtiments devant servir des bureaux du Support Services and Project Request for Single Stage - One 2018-10- 2019-02- 2018-12- 2019-05- 2019-06- IDA / 58520 Post Limited 80,000.00 79,437.21 Signed Ministre Provincial de Management Quotations Envelope 08 02 03 16 01 l'Agriculture,Pêche et Elevage et du Développement Rural du Tanganyika ZR-MINAGRI-105397-CW- RFQ / Travaux de Réhabilitation des bâtiments Support Services and Project Request for Single Stage - One 2019-05- 2019-10- 2019-07- 2019-12- 2020-01- abritant le Bureau_ du IDA / 58520 Post Limited 30,000.00 24,227.50 Signed Management Quotations Envelope 15 09 10 09 06 Ministère provincial de l’Agriculture, pèche et élevage du Sud-Kivu ZR-MINAGRI-133733-CW- RFQ / Travaux de Pending réhabilitation du bâtiment Support Services and Project Request for Single Stage - One 2019-10- 2019-12- 2020-06- IDA / 58520 Post Limited 40,000.00 0.00 Implementa devant servir des bureaux Management Quotations Envelope 20 15 12 tion provisoires de l'IPAPEL Sud Kivu ZR-MINAGRI-169983-CW- RFQ / Travaux d'aménagement du bâtiment Pending Support Services and Project Request for Single Stage - One 2020-08- 2020-09- 2021-03- abritant les bureaux des IDA / 58520 Post Limited 80,000.00 0.00 Implementa Management Quotations Envelope 04 29 28 services du Secrétariat tion Général à la Pêche et Elevage sur l'avenue de la libération (SQUAV) ZR-MINAGRI-169808-CW- DIR / Contractualisation avec SAGEC KAT pour les travaux de construction des bureaux Support for the development Pending 2020-07- 2020-08- 2020-09- 2021-03- complémentaires des des IDA / 58520 of the private agro- Post Direct Selection Direct 145,000.00 0.00 Implementa 30 04 08 07 inspections de l'Agriculture industrial sector tion et du Développement Rural de la province de Tanganyika et aménagement extérieur ZR-MINAGRI-169820-CW- RFQ / Travaux de Pending Support Services and Project Request for Single Stage - One 2020-05- 2020-07- 2021-01- construction de deux (2) IDA / 58520 Post Limited 200,000.00 0.00 Implementa Management Quotations Envelope 20 15 11 laboratoires du SENASEM et tion de l'INERA Tanganyika ZR-MINAGRI-169811-CW- DIR / Contractualisation avec KIMA CONSTRUCTION pour Under la réalisation des travaux de Support Services and Project 2020-06- 2020-10- 2020-06- 2020-10- 2020-08- 2021-01- IDA / 58520 Post Direct Selection Direct 25,000.00 25,377.38 Implementa la clôture et d'aménagement Management 22 07 27 12 01 28 tion extérieur des bureaux du Ministre Provincial de l'Agriculture Sud Kivu ZR-MINAGRI-188529-CW- RFQ / Travaux de construction de six (06) Pending Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-05- Centres Communautaires de IDA / 58520 Post Limited 200,000.00 0.00 Implementa Development Quotations Envelope 07 02 31 Transformation de Riz tion (CCTRIZ) dans la Province de Tanganyika ZR-MINAGRI-188543-CW- RFQ / Travaux de construction de Entrepôts Pending Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- dépôts de stockage à IDA / 58520 Post Limited 200,000.00 0.00 Implementa Development Quotations Envelope 05 31 29 Rugumba, Rugo, Lwaminwa, tion Katibili, Muhala et Kabimba dans la Province du Tanganyika ZR-MINAGRI-188540-CW- RFQ / Travaux de construction de 6 dépôts de Pending Agriculture Value Chain Request for Single Stage - One 2020-09- 2020-11- 2021-04- stockage à Rugumba, Rugo, IDA / 58520 Post Limited 150,000.00 0.00 Implementa Development Quotations Envelope 06 01 30 Lwaminwa, Katibili, Muhala tion et Kabimba dans la Province du Tanganyika ZR-MINAGRI-188521-CW- RFQ / Travaux de construction de deux (02) dépôts vétérinaires dans la Pending Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-06- ville de Kalemie et deux (02) IDA / Q9610 Post Limited 150,000.00 0.00 Implementa Development Quotations Envelope 27 22 20 cliniques vétérinaires dans tion les bassins de production de la Rugumba et Lwamina, territoire de Kalemie/Tanganyika ZR-MINAGRI-188479-CW- DIR / Contractualisation avec l'Entreprise SAGEC KAT SARL pour les travaux complémentaires de Support Services and Project 2020-09- 2020-10- 2020-09- 2020-10- 2020-10- 2020-11- 2021-04- Réhabilitation du bâtiment IDA / 58520 Post Direct Selection Direct 150,000.00 149,428.76 Signed Management 16 07 21 12 26 23 24 devant servir des bureaux des Inspections Provinciales de l’Agriculture et du Développement Rural du Sud Kivu ZR-MINAGRI-188497-CW- RFQ / Travaux de construction du laboratoire Pending Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-06- de la Coordination IDA / 58520 Post Limited 170,000.00 0.00 Implementa Development Quotations Envelope 23 18 16 Provinciale de Service tion National de Semences (SENASEM)/Tanganyika ZR-MINAGRI-188489-CW- RFQ / Travaux de Pending Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-06- construction des Unités de IDA / 58520 Post Limited 200,000.00 0.00 Implementa Development Quotations Envelope 26 21 19 transformation du lait dans tion territoire de Kalemie/Tanganyika ZR-MINAGRI-188545-CW- RFQ / Travaux de constuction de dix Centres (Bâtiments) Communautaires Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-05- de Transformation de Maïs IDA / 58520 Post Limited 230,000.00 0.00 Canceled Development Quotations Envelope 06 01 30 dont 2 à Kabimba, 2 à Rugo, 2 à Rugumba, 2 à Katibili et 2 à Lwamminwa dans la Province de Tanganyika ZR-MINAGRI-210011-GO- RFQ / Travaux de Pending construction de deux (2) mini Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 20,000.00 0.00 Implementa chambres froides dont 1 à Development Quotations Envelope 13 10 07 tion Luberezi et 1 Mutarule, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210021-CW- RFQ / Construction de deux (2) mini laboratoires de Service National de Semences (SENASEM) dont 1 à Bwegera Pending Support Services and Project Request for Single Stage - One 2021-01- 2021-03- 2021-09- et 1 Fizi centre, d’un (1) mur IDA / 58520 Post Limited 123,000.00 0.00 Implementa Management Quotations Envelope 30 27 23 de clôture et aménagement tion des paillasses dans la salle de labo physique et phytopathologie aux bureaux de SENASEM Bukavu ZR-MINAGRI-210108-CW- RFQ / Travaux de construction de deux (02) Pending Agriculture Value Chain Request for Single Stage - One 2021-01- 2021-03- 2021-09- provenderies dans les IDA / 58520 Post Limited 65,000.00 0.00 Implementa Development Quotations Envelope 20 17 13 Bassins de production de tion Rugumba et Lwaminwa dans la Province de Tanganyika ZR-MINAGRI-210111-CW- RFQ / Travaux de construction de quatre (04) Pending boutiques d'intrants Agriculture Value Chain Request for Single Stage - One 2021-01- 2021-03- 2021-09- IDA / 58520 Post Limited 128,000.00 0.00 Implementa agricoles dans les Bassins de Development Quotations Envelope 25 22 18 tion production de Rugumba, Kabimba, Kalemie et Kamango dans la Province de Tanganyika Page 1 ZR-MINAGRI-210125-CW- RFQ / Travaux de construction de quatre (4) Centres de Collecte et Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- Transformation de Manioc IDA / 58520 Post Limited 153,000.00 0.00 Implementa Development Quotations Envelope 01 29 25 dont 2 à Bitale, 1 à Bulmbika tion et 1 à Mulonge, dans le territoire de Kalehe, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210132-CW- RFQ / Travaux de construction de quatre (4) Centres de Collecte et Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- Transformation de Manioc IDA / 58520 Post Limited 153,000.00 0.00 Implementa Development Quotations Envelope 01 29 25 dont 1 à Mubuku, 1 à Karasi, tion 1 à Kitchanga et 1 à Maibano, dans le territoire de Kalehe, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210126-CW- RFQ / Travaux de construction de deux (2) Pending Centres de Collecte et Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- IDA / 58520 Post Limited 77,000.00 0.00 Implementa Transformation de Manioc Development Quotations Envelope 01 29 25 tion dont 1 à Katanga et 1 à Malinde, dans le territoire de Fizi, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210127-CW- RFQ / Travaux de construction de cinq (5) Pending Centres de Collecte et Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- IDA / 58520 Post Limited 192,000.00 0.00 Implementa Transformation de Manioc Development Quotations Envelope 01 29 25 tion dont 3 à Katana, 1 à Kavumu et 1 à Luhihi, dans le territoire de Kabare, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210129-CW- RFQ / Travaux de construction de trois (3) Centres de Collecte et Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- Transformation de Manioc IDA / 58520 Post Limited 115,000.00 0.00 Implementa Development Quotations Envelope 01 29 25 dont 1 à Sange, 1 à Kiliba et tion 1 à Runingu, dans le territoire d’Uvira, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210130-CW- RFQ / Travaux de construction de quatre (4) Centres de Collecte et Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- Transformation de Manioc IDA / 58520 Post Limited 153,000.00 0.00 Implementa Development Quotations Envelope 01 29 25 dont 2 à Kamanyola, 1 à tion Luvungi et 1 à Lubarika, dans la plaine de Ruzizi, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-195187-CW- Pending RFQ / Travaux de Agriculture Value Chain Request for Single Stage - One 2021-01- 2021-03- 2021-08- IDA / 58520 Post Limited 160,000.00 0.00 Implementa construction du laboratoire Development Quotations Envelope 04 01 28 tion de l'INERA dans le territoire de Kalemie ZR-MINAGRI-210336-CW- RFQ / Construction des aires de sechage semi ouverts Pending dans le groupement de Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 41,000.00 0.00 Implementa Bushumba dans le territoire Development Quotations Envelope 08 05 02 tion de Kabare et le groupement d'Itara dans le territoire d'Uvira, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210338-CW- RFQ / Construction des aires Pending de sechage non couverts à Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 18,000.00 0.00 Implementa Sebele dans le territoire de Development Quotations Envelope 08 05 02 tion Fizi et à Uvira, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210648-CW- RFQ / Travaux de construction de sept (7) abris dont six (6) pour mini- Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- minoterie et un (1) pour mini- IDA / 58520 Post Limited 84,000.00 0.00 Implementa Development Quotations Envelope 03 31 27 laiterie de type 2, et d’une tion (1) provenderie, dans le territoire de Kabare, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210650-CW- RFQ / Travaux de construction de quatre (4) Pending abris dont un (1) pour mini- Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- IDA / Q9260 Post Limited 42,000.00 0.00 Implementa minoterie et trois (3) pour Development Quotations Envelope 03 31 27 tion mini-laiterie de type 2, dans le territoire de Kalehe, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210651-CW- RFQ / Travaux de construction de dix (10) abris dont huit (8) pour mini- Pending minoterie, un (1) pour rizerie Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- IDA / 58520 Post Limited 110,000.00 0.00 Implementa de type 2 (SB-50 ou Development Quotations Envelope 03 31 27 tion équivalent) et un (1) pour mini-laiterie de type 2, dans le territoire de Fizi, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210653-CW- RFQ / Travaux de construction de deux (2) Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- abris pour mini-laiterie de IDA / 58520 Post Limited 34,000.00 0.00 Implementa Development Quotations Envelope 03 31 27 type 2 et une (1) tion provenderie, à Bukavu, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210654-CW- RFQ / Travaux de construction de seize (16) abris dont douze (12) pour Pending mini minoterie, trois (3) pour Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- IDA / 58520 Post Limited 174,000.00 0.00 Implementa rizerie type 2 (SB-50 ou Development Quotations Envelope 03 31 27 tion équivalent), un (1) pour mini- laiterie de type 2 et d’une (1) provenderie dans la plaine de Ruzizi (Territoires d’Uvira et Walungu) ZR-MINAGRI-210656-CW- RFQ / Travaux de construction de quatorze (14) abris dont cinq (5) pour Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-03- 2021-09- mini-minoterie, deux (2) IDA / 58520 Post Limited 141,000.00 0.00 Implementa Development Quotations Envelope 03 31 27 pour rizerie de type 2, un (1) tion pour entrepot des intrants agricoles et six (6) pour mini- laiterie de type 2, dans le territoire d’Uvira ZR-MINAGRI-210894-CW- RFQ / Travaux de construction de trois (3) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 171,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines et d’un tion (1) entrepôt semencier à Katanga, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210893-CW- RFQ / Travaux de construction de trois (3) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 171,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines à Baraka tion et d’un (1) entrepôt semencier à Nemba, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210891-CW- RFQ / Travaux de construction de trois (3) entrepôts des produits Pending agricoles avec bureaux des Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 171,000.00 0.00 Implementa préposés et latrines dont 1 à Development Quotations Envelope 10 07 04 tion Sebele, 1 à Kabondonzi et 1 à Malinde et d’un (1) entrepôt semencier à Sebele, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210886-CW- RFQ / Travaux de construction de quatre (4) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 187,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines dont tion deux (2) à Fizi centre et deux (2) à Mulongwe, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210885-CW- RFQ / Travaux de construction de trois (3) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 200,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines et de tion deux (2) entrepôts semenciers à Sange, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210892-CW- RFQ / Travaux de construction de trois (3) entrepôts des produits Pending agricoles avec bureaux des Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 171,000.00 0.00 Implementa préposés et latrines dont un Development Quotations Envelope 10 07 04 tion (1) à Kiliba et deux (2) à Runingu, et d’un (1) entrepôt semencier à Kiliba, dans le cadre du PICAGL, UPEP Sud- Kivu Page 2 ZR-MINAGRI-210890-CW- RFQ / Travaux de construction de quatre (4) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 187,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines dont tion trois (3) à Luvungi et un (1) à Lubarika, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210887-CW- RFQ / Travaux de construction de quatre (4) entrepôts des produits Pending agricoles avec bureaux des Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 187,000.00 0.00 Implementa préposés et latrines dont un Development Quotations Envelope 10 07 04 tion (1) à Kagando, un (1) à Kahwizi, un (1) à Kigongo et un (1) à Murunga, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210884-CW- RFQ / Travaux de construction de deux (2) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 124,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines et d’un tion (1) entrepôt semencier à Nyangezi, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210888-CW- RFQ / Travaux de construction de trois (3) Pending entrepôts des produits Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 140,000.00 0.00 Implementa agricoles avec bureaux des Development Quotations Envelope 10 07 04 tion préposés et latrines à Kamanyola, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210889-CW- RFQ / Travaux de construction de deux (2) entrepôts des produits Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- agricoles avec bureaux des IDA / 58520 Post Limited 95,000.00 0.00 Implementa Development Quotations Envelope 10 07 04 préposés et latrines dont un tion (1) à Mudaka et un (1) à Bunyakiri/Bitale, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210974-CW- RFQ / Travaux de Pending construction d’une (1) laiterie Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 58520 Post Limited 32,000.00 0.00 Implementa de type 3 à Cirunga, dans le Development Quotations Envelope 06 03 30 tion territoire de Kabare, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210975-CW- RFQ / Travaux de construction de trois (3) Pending laiteries de type 3 dont deux Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 58520 Post Limited 96,000.00 0.00 Implementa (2) à Luvungi et une (1) à Development Quotations Envelope 06 03 30 tion Bwegera, dans le territoire d’Uvira, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210973-CW- RFQ / Travaux de construction de quatre (4) Pending laiteries de type 3 dont 1 à Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-09- IDA / 58520 Post Limited 130,000.00 0.00 Implementa Sange, 1 à Kavimvira et 2 à Development Quotations Envelope 06 03 30 tion Uvira, dans le territoire d’Uvira, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-188474-CW- RFQ / Travaux de constuction de sept Centres (Bâtiments) Communautaires Pending de Transformation de Manioc Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- IDA / 58520 Post Limited 200,000.00 0.00 Implementa ( CCTMA) dont 1 à Kabimba, Development Quotations Envelope 05 31 29 tion 1 à Rugo, 1 à Rugumba, 2 à Katibili, 1 à Tabacongo et 1 à Lwamminwa dans la Province de Tanganyika GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PARSSA-6375-GO-RFQ / Pending Acquisition matériels Support Services and Project Request for Single Stage - One 2016-06- 2016-08- 2017-02- IDA / Q9260 Post Limited 16,000.00 0.00 Implementat informatiques en faveur du Management Quotations Envelope 17 12 08 ion personnel PICAGL ZR-PARSSA-5170-GO-RFQ / Under Acquisition de 3 véhicules en Support Services and Project Request for Single Stage - One 2015-10- 2015-12- 2016-06- IDA / Q9260 Post Limited 120,000.00 0.00 Implementat faveur des coordinations Management Quotations Envelope 15 10 07 ion provinciales ZR-PARSSA-5154-GO-DIR / Acquisition du logiciel de Support Services and Project 2015-09- 2015-09- 2015-11- 2015-10- 2016-05- IDA / Q9260 Post Direct Selection Direct 37,000.00 50,591.91 Signed gestion financière et Management 24 29 03 22 01 comptable Tom² pro MOF-REF-5 / Acquisition Agriculture Value Chain Request for Single Stage - One 2018-11- 2019-01- 2019-07- IDA / 58520 Post Limited 160,000.00 0.00 Canceled des camions Development Quotations Envelope 27 22 21 MOF-REF-6 / Acquisition des matériels pour la Support Services and Project Request for Single Stage - One 2018-11- 2019-01- 2019-07- vaccination contre la peste IDA / 58520 Post Limited 80,000.00 0.00 Canceled Management Quotations Envelope 28 23 22 bovine et la PPR dans les provinces de Sud Kivu et de Tanganyika MOF-REF-7 / Fourniture et mise en service des matériels informatiques et de Support Services and Project Single Stage - One 2018-10- 2018-10- 2018-12- 2019-01- 2019-02- 2019-08- IDA / 58520 Post Request for Bids Open - National 250,000.00 0.00 Canceled reprographie en faveur du Management Envelope 18 23 04 03 07 06 Projet et des services impliqués ZR-MINAGRI-78950-GO- RFQ / Acquisition de fournitures de bureau et Support Services and Project Request for Single Stage - One 2018-10- 2018-12- 2019-06- consommables informatiques IDA / 58520 Post Limited 60,000.00 0.00 Canceled Management Quotations Envelope 24 19 17 en faveur de l'Unité Nationale de Projet et les services impliqués du MINAGRI, PEL et DR ZR-MINAGRI-78990-GO- RFB / Acquisition des Support Services and Project Single Stage - One 2018-11- 2018-11- 2018-12- 2019-01- 2019-02- 2019-08- IDA / 58520 Post Request for Bids Open - National 150,000.00 0.00 Canceled matériels de sensibilisation Management Envelope 01 06 18 17 21 20 et visibilité en faveur de l'UNCP ZR-MINAGRI-78881-GO- RFQ / Fourniture et installation des équipements Support Services and Project Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-12- 2019-05- IDA / 58520 Post Limited 24,000.00 18,547.00 Signed pour la connexion internet et Management Quotations Envelope 06 16 01 03 30 abonnement annuel du bureau de l'UPEP PICAGL Sud- Kivu ZR-MINAGRI-79034-GO- RFQ / Fourniture et Support Services and Project Request for Single Stage - One 2018-10- 2018-08- 2018-12- 2018-10- 2019-06- 2019-04- installation des mobiliers de IDA / 58520 Post Limited 30,000.00 31,481.80 Completed Management Quotations Envelope 20 20 15 03 13 30 bureau pour l'Unité Provinciale d’Exécution du PICAGL Sud-Kivu ZR-MINAGRI-79167-GO- Pending RFQ / Fournitures et mise Support Services and Project Request for Single Stage - One 2018-11- 2019-01- 2019-07- IDA / 58520 Post Limited 15,000.00 0.00 Implementat service des kits solaires Management Quotations Envelope 11 06 05 ion pour l'UPEP PICAGL Sud-Kivu ZR-MINAGRI-78817-GO- Pending RFQ / Acquisition de Support Services and Project Request for Single Stage - One 2018-10- 2018-12- 2019-06- IDA / 58520 Post Limited 15,000.00 0.00 Implementat carburant et lufrifiant pour Management Quotations Envelope 20 15 13 ion les véhicules de l'UPEP PICAGL Sud-Kivu ZR-MINAGRI-79039-GO- RFQ / Fourniture et mise en service des matériels Support Services and Project Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-12- 2019-06- 2019-01- IDA / 58520 Post Limited 40,000.00 40,515.00 Completed informatiques et de Management Quotations Envelope 20 16 15 03 13 15 reprographie pour l’Unité Provinciale d’Exécution du PICAGL Sud-Kivu. ZR-MINAGRI-78971-GO- RFQ / Acquisition des Support Services and Project Request for Single Stage - One 2019-01- 2018-11- 2019-02- 2019-02- 2019-08- 2019-04- IDA / 58520 Post Limited 15,000.00 7,475.00 Completed matériels de sensibilisation Management Quotations Envelope 02 30 27 18 26 22 et visibilité en faveur de l'UPEP Sud Kivu ZR-MINAGRI-79095-GO- RFQ / Fourniture et installation des équipements Support Services and Project Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-11- 2019-05- IDA / 58520 Post Limited 24,000.00 27,280.00 Signed pour la connexion internet et Management Quotations Envelope 06 26 01 22 30 abonnement annuel du bureau de l'UPEP PICAGL Tanganyika ZR-MINAGRI-79160-GO- RFQ / Fourniture et Support Services and Project Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-12- 2019-06- 2019-04- installation des mobiliers de IDA / 58520 Post Limited 30,000.00 27,400.00 Completed Management Quotations Envelope 20 23 15 03 13 08 bureau pour l'Unité Provinciale d’Exécution du PICAGL Tanganyika ZR-MINAGRI-79165-GO- Pending RFQ / Fournitures et Support Services and Project Request for Single Stage - One 2018-11- 2019-01- 2019-07- IDA / 58520 Post Limited 15,000.00 0.00 Implementat installation des équipements Management Quotations Envelope 11 06 05 ion solaires pour l'UPEP PICAGL Tanganyika Page 3 ZR-MINAGRI-78973-GO- RFQ / Acquisition de Support Services and Project Request for Single Stage - One 2018-10- 2019-01- 2018-12- 2019-05- 2019-06- IDA / 58520 Post Limited 15,000.00 15,000.00 Signed carburant et lufrifiant pour Management Quotations Envelope 20 18 15 13 13 les véhicules de l'UPEP PICAGL Tanganyika ZR-MINAGRI-79163-GO- RFQ / Fourniture et mise en service des matériels Support Services and Project Request for Single Stage - One 2018-10- 2018-10- 2018-12- 2018-11- 2019-06- IDA / 58520 Post Limited 40,000.00 36,358.51 Signed informatiques et de Management Quotations Envelope 20 26 15 23 13 reprographie pour l’Unité Provinciale d’Exécution du PICAGL Tanganyika ZR-MINAGRI-79102-GO- RFQ / Acquisition des Support Services and Project Request for Single Stage - One 2019-01- 2018-10- 2019-02- 2018-12- 2019-08- IDA / 58520 Post Limited 15,000.00 11,565.00 Signed matériels de sensibilisation Management Quotations Envelope 02 26 27 03 26 et visibilité en faveur de l'UPEP Tanganyika ZR-MINAGRI-78926-GO- Support Services and Project 2018-09- 2018-10- 2018-09- 2018-10- 2018-11- 2019-04- DIR / Acquisition des IDA / 58520 Post Direct Selection Direct 700,000.00 461,362.00 Signed Management 15 22 20 25 30 23 véhicules 4X4 TT auprès de l'UNOPS ZR-MINAGRI-78949-GO- Pending Support Services and Project 2018-09- 2018-09- 2018-10- 2019-04- DIR / Acquisition des motos IDA / 58520 Post Direct Selection Direct 110,000.00 0.00 Implementat Management 15 20 25 23 DT 125 auprès de l'UNOPS ion ZR-MINAGRI-105380-GO- RFQ / Fourniture et montage des mobiliers pour le Pending personnel complémentaire Support Services and Project Request for Single Stage - One 2019-04- 2019-06- 2019-12- IDA / 58520 Post Limited 65,200.00 0.00 Implementat du PICAGL, la salle de Management Quotations Envelope 23 18 15 ion réunions du SG Agriculture et pour les services de l'Agriculture(SNSA, DPPV et DMPCC) ZR-MINAGRI-105371-GO- RFQ / Fourniture et Pending installation de matériels de Support Services and Project Request for Single Stage - One 2019-04- 2019-06- 2020-06- IDA / 58520 Post Limited 80,000.00 0.00 Implementat connexion internet pour le Management Quotations Envelope 23 18 17 ion bureau complémentaire de l'UNCP PICAGL ZR-MINAGRI-105378-GO- RFQ / Acquisition de fournitures de bureau et Pending consommables informatiques Support Services and Project Request for Single Stage - One 2019-05- 2019-06- 2019-12- IDA / 58520 Post Limited 60,000.00 0.00 Implementat en faveur de l'Unité Nationale Management Quotations Envelope 01 26 23 ion de Projet et les services impliqués du MINAGRI, PEL et DR ZR-MINAGRI-105314-GO- RFQ / Fourniture et mise en Pending service des matériels de Support Services and Project Request for Single Stage - One 2018-10- 2018-12- 2019-03- IDA / 58520 Post Limited 5,000.00 0.00 Implementat laboratoire du Service Management Quotations Envelope 24 19 19 ion National des Fertilisants et Intrants Connexes(SENAFIC) ZR-MINAGRI-105370-GO- RFQ / Acquisition des matériels de sensibilisation Support Services and Project Request for Single Stage - One 2019-06- 2019-05- 2019-07- 2019-06- 2020-01- IDA / 58520 Post Limited 15,000.00 14,523.75 Signed et visibilité en faveur de Management Quotations Envelope 02 30 28 25 24 l'UPEP Tanganyika pour l'exercice 2019 ZR-MINAGRI-105372-GO- RFQ / Fourniture et montage des mobiliers pour les Support Services and Project Request for Single Stage - One 2019-10- 2018-10- 2019-11- 2018-12- 2020-05- 2019-04- IDA / 58520 Post Limited 15,000.00 27,400.00 Completed inspections provinciales de Management Quotations Envelope 03 28 28 03 26 08 l'Agriculture et Dévelopement Rural de Tanganyka ZR-MINAGRI-105353-GO- RFQ / Fourniture et installation des matériels informatiques et de Support Services and Project Request for Single Stage - One 2019-10- 2019-05- 2019-11- 2019-06- 2020-05- reprographie pour les IDA / 58520 Post Limited 13,000.00 12,895.00 Signed Management Quotations Envelope 03 28 28 21 26 services du Ministère provincial de l'Agriculture, Pêche et Elevage et du Développement Rural du Tanganyka ZR-MINAGRI-105392-GO- RFQ / Acquisition de fournitures de bureau et consommables informatiques Support Services and Project Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-12- IDA / 58520 Post Limited 18,000.00 17,971.65 Signed pour l'UPEP, les Inspections Management Quotations Envelope 03 30 28 21 25 Provinciales de l'Agriculture et du Développement Rural de Tanganyika ZR-MINAGRI-105400-GO- RFQ / Fourniture et installation du groupe electrogène de 60 kva pour Support Services and Project Request for Single Stage - One 2019-10- 2019-05- 2019-11- 2019-06- 2020-05- 2019-08- IDA / 58520 Post Limited 30,000.00 29,958.50 Completed le bâtiment l'inspection Management Quotations Envelope 03 24 28 12 26 23 provinciale de l'Agriculture et du Développement Rural Tanganyika ZR-MINAGRI-105329-GO- RFQ / Fourniture et installation de 20 splits de 12.000 BTU (dont 2 pour les Pending Support Services and Project Request for Single Stage - One 2019-10- 2019-11- 2020-05- locaux serveurs et 18 pour IDA / 58520 Post Limited 16,000.00 0.00 Implementat Management Quotations Envelope 03 28 26 les bureaux des inspections ion de l'Agriculrure et du Développement Rural) en faveur de l'UPEP Tanganyika ZR-MINAGRI-105323-GO- RFQ / Acquisition des Support Services and Project Request for Single Stage - One 2019-04- 2019-10- 2019-06- 2019-11- 2019-12- 2020-01- mobiliers des bureaux pour IDA / 58520 Post Limited 15,000.00 12,331.00 Completed Management Quotations Envelope 15 09 10 12 07 22 l'inspection provinciale de l'agriculture au Sud KIVU ZR-MINAGRI-105359-GO- RFQ / Acquisition des matériels informatiques pour Support Services and Project Request for Single Stage - One 2019-09- 2019-08- 2019-11- 2019-09- 2020-05- 2019-10- IDA / 58520 Post Limited 13,000.00 12,200.00 Completed les services du Ministère Management Quotations Envelope 21 16 16 17 14 02 Provincial de l’agriculture et UPEP Sud Kivu ZR-MINAGRI-105402-GO- RFQ / Acquisition de Support Services and Project Request for Single Stage - One 2019-04- 2019-06- 2019-06- 2019-08- 2019-12- carburant et lubrifiant pour IDA / 58520 Post Limited 15,000.00 9,996.80 Signed Management Quotations Envelope 12 26 07 28 04 les véhicules de l'UPEP PICAGL Sud Kivu Pending ZR-MINAGRI-105278-GO- Support Services and Project Request for Single Stage - One 2019-04- 2019-05- 2020-05- IDA / 58520 Post Limited 10,000.00 0.00 Implementat RFQ / travaux Management Quotations Envelope 01 27 26 ion ZR-MINAGRI-117750-GO- RFQ / Fourniture et Support Services and Project Request for Single Stage - One 2019-07- 2019-06- 2019-09- 2019-08- 2019-11- 2019-10- installation de groupe IDA / 58520 Post Limited 25,000.00 20,760.50 Completed Management Quotations Envelope 30 26 24 28 08 02 électrogène de 60 Kva pour le bureau de l'UPEP/Sud-Kivu ZR-MINAGRI-117751-GO- RFQ / Acquisition de fournitures de bureau et Support Services and Project Request for Single Stage - One 2019-07- 2019-10- 2019-09- 2019-11- 2019-11- consommables informatiques IDA / 58520 Post Limited 25,000.00 17,802.50 Signed Management Quotations Envelope 30 09 24 12 08 pour l'UPEP/Sud-Kivu, les Inspections de l'Agriculture et du Développement Rural ZR-MINAGRI-133012-GO- DIR / Acquisition et livraison de 2 véhicules Pending complémentaires pour le Support Services and Project 2019-10- 2019-10- 2019-12- 2019-12- IDA / 58520 Post Direct Selection Direct 110,000.00 0.00 Implementat Laboratoire Vétérinaire de Management 25 30 04 13 ion Kinshasa(LABOVET) et le Secrétariat Général au Développement Rural ZR-MINAGRI-170574-GO- RFQ / Acquisition mobiliers Pending Support Services and Project Request for Single Stage - One 2020-06- 2020-08- 2021-02- de bureaux complémentaires IDA / 58520 Post Limited 10,500.00 0.00 Implementat Management Quotations Envelope 20 15 11 pour le personnel l'UPEP ion Tanganyika ZR-MINAGRI-169843-GO- RFQ / Acquisition matériels de visibilité et sensibilisation Pending Support Services and Project Request for Single Stage - One 2020-05- 2020-07- 2021-01- du mécanisme de Gestion IDA / 58520 Post Limited 15,000.00 0.00 Implementat Management Quotations Envelope 20 15 11 des Plaintes (MGP) en faveur ion de l'UPEP Tanganyika exercice 2020 Tanganyika ZR-MINAGRI-169881-GO- RFQ / Fourniture et installation de splits de Pending 12000 BTU pour les bureaux Support Services and Project Request for Single Stage - One 2020-06- 2020-08- 2021-02- IDA / 58520 Post Limited 28,000.00 0.00 Implementat des inspections de Management Quotations Envelope 20 15 11 ion l'Agriculture et du Développement Rural de la province de Tanganyika ZR-MINAGRI-169913-GO- RFQ / Recrutement d'un prestataire pour l'entretien et Pending la réparation des splits des Support Services and Project Request for Single Stage - One 2020-06- 2020-08- 2021-02- IDA / 58520 Post Limited 15,000.00 0.00 Implementat bureaux des Inspections de Management Quotations Envelope 25 20 16 ion l'Agriculture et du Développement Rural de la Province de Tanganyika ZR-MINAGRI-169918-GO- CDD / Acquisitions de 52 Community Pending taureaux (géniteurs) en Agriculture Value Chain 2020-05- 2020-06- 2020-07- 2021-01- IDA / 58520 Post Driven Direct 120,000.00 0.00 Implementat faveur de l'Inspection Development 30 04 09 05 Development ion Provinciale de l'Agriculture, Pêche et Elevage du Sud Kivu Page 4 ZR-MINAGRI-169991-GO- RFQ / Acquisition des fournitures de bureau et consommables informatiques Pending pour les services des Support Services and Project Request for Single Stage - One 2020-01- 2020-03- 2020-09- IDA / 58520 Post Limited 25,000.00 0.00 Implementat Ministères provinciaux de Management Quotations Envelope 20 16 12 ion l'Agriculture, Pêche et Elevage et du Développement Rural et l'UPEP Tanganyika (Exercice 2020) ZR-MINAGRI-169902-GO- RFQ / Fourniture et Pending installation des kits solaires Support Services and Project Request for Single Stage - One 2020-06- 2020-08- 2021-02- IDA / 58520 Post Limited 20,000.00 0.00 Implementat pour le bâtiment de Management Quotations Envelope 20 15 11 ion l'inspection provinciale de l'Agriculture de Tanganyika ZR-MINAGRI-169993-GO- RFQ / Installation des équipements de la connexion internet ainsi que Pending l’abonnement annuel pour Support Services and Project Request for Single Stage - One 2020-06- 2020-08- 2021-02- IDA / 58520 Post Limited 30,000.00 0.00 Implementat les Bureaux de UPEP et des Management Quotations Envelope 20 15 11 ion Inspections Provinciales de l’Agriculture, Pêche, Elevage et du Développement Rural de Tanganyika ZR-MINAGRI-170560-GO- RFQ / Acquisition et installation de mobiliers de Support Services and Project Request for Single Stage - One 2020-08- 2020-03- 2020-10- 2020-05- 2021-04- bureau du Ministère IDA / 58520 Post Limited 15,000.00 11,020.00 Signed Management Quotations Envelope 20 19 15 05 13 Provincial de l"Agriculture, Pêche et Elevage, et Développement Rural du Sud- Kivu ZR-MINAGRI-170565-GO- RFQ / Fourniture et installation des kits solaires Support Services and Project Request for Single Stage - One 2020-08- 2020-11- 2020-10- 2021-01- 2021-04- IDA / 58520 Post Limited 20,000.00 31,318.90 Signed pour le bâtiment de Management Quotations Envelope 20 18 15 15 13 l'inspection provinciale de l'Agriculture de Sud Kivu ZR-MINAGRI-170575-GO- RFQ / Acquisition, installation et fourniture internet pour le nouveau Support Services and Project Request for Single Stage - One 2020-07- 2020-09- 2020-09- 2020-11- 2021-03- bâtiment des Inspections IDA / 58520 Post Limited 26,000.00 7,051.50 Signed Management Quotations Envelope 15 15 09 09 08 Provinciales de l'Agriculture, Pêche et Elevage, et du Développement Rural du Sud- Kivu et du Ministère Provincial ZR-MINAGRI-169976-GO- RFQ / Acquisition et montage des équipements informatiques et bureaux pour la coordination Support Services and Project Request for Single Stage - One 2020-05- 2020-02- 2020-07- 2020-03- 2021-01- 2020-09- provinciale du Sud-Kivu (4 IDA / 58520 Post Limited 32,000.00 21,715.00 Completed Management Quotations Envelope 20 17 15 24 11 04 onduleurs, 4 imprimentes, 4 stabilisateurs pour les 4 spécialistes, photocopiie en couleur) et pour le Ministre Provincial Agric du Sud Kivu ZR-MINAGRI-169898-GO- RFQ / Acquisition matériels de visibilité pour l'UPEP Sud Support Services and Project Request for Single Stage - One 2020-05- 2020-02- 2020-07- 2020-03- 2021-01- 2020-08- Kivu ( Roll up, T-shirt, IDA / 58520 Post Limited 30,000.00 28,270.00 Completed Management Quotations Envelope 21 17 16 24 12 21 Calendrier, Gilets, Képis, Agendas, Dépliants) pour l'exercice 2020 ZR-MINAGRI-169728-GO- RFQ / Acquisition des matériels et d'équipements Support Services and Project Request for Single Stage - One 2020-05- 2020-04- 2020-07- 2020-06- 2021-01- 2020-07- IDA / 58520 Post Limited 5,000.00 2,485.00 Completed de terrain (imperméables, Management Quotations Envelope 22 27 17 10 13 15 bottes, parapluies) en faveur de l'UPEP Sud Kivu ZR-MINAGRI-169813-GO- RFQ / Reproduction de guide Pending Support Services and Project Request for Single Stage - One 2020-05- 2020-07- 2021-01- des bonnes pratiques pour la IDA / 58520 Post Limited 7,500.00 0.00 Implementat Management Quotations Envelope 23 18 14 production végétales et ion animales au Sud Kivu ZR-MINAGRI-187940-GO- Pending RFQ / Acquisition des Support Services and Project Request for Single Stage - One 2020-10- 2020-11- 2021-05- IDA / 58520 Post Limited 150,000.00 0.00 Implementat matériels de visibilité et de Management Quotations Envelope 05 30 29 ion sensibilisation pour l'UNCP ZR-MINAGRI-188537-GO- RFQ / Acquisition mobiliers Pending Support Services and Project Request for Single Stage - One 2020-04- 2020-06- 2020-12- de bureaux complémentaires IDA / 58520 Post Limited 20,000.00 0.00 Implementat Management Quotations Envelope 20 15 12 pour le personnel de l 'UPEP ion Tanganyika ZR-MINAGRI-188508-GO- RFQ / Acquisition des équipements de transformation du manioc en Pending Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- faveur de dix (10) Centres IDA / 58520 Post Limited 150,000.00 0.00 Implementat Development Quotations Envelope 04 30 28 Communautaires de ion Transformation de manioc dans la Province du Tanganyika ZR-MINAGRI-188515-GO- RFQ / Acquisition des équipements de Pending transformation du manioc en Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- IDA / 58520 Post Limited 100,000.00 0.00 Implementat faveur de dix (10) Centres Development Quotations Envelope 05 31 29 ion Communautaires de Transformation de Maïs dans la Province du Tanganyika ZR-MINAGRI-188533-GO- RFQ / Acquisition d'1 drone et d' 1 appareil photo Pending professionnel et camera Support Services and Project Request for Single Stage - One 2020-11- 2021-01- 2021-06- IDA / 58520 Post Limited 6,000.00 0.00 Implementat hybride pour la couverture Management Quotations Envelope 06 01 30 ion communicationnelle des activités du Projet dans la Province du Tanganyika ZR-MINAGRI-188499-GO- RFQ / Acquisition de 5 motos en faveur de Délégués à Pied Pending d'Ouevre en charge de la Agriculture Value Chain Request for Single Stage - One 2020-11- 2021-01- 2021-07- IDA / 58520 Post Limited 24,000.00 0.00 Implementat surveillance des travaux de Development Quotations Envelope 07 02 01 ion construction des Centres Communautaires dans la Province du Tanganyika ZR-MINAGRI-188507-GO- RFQ / Acquisition de Pending matériels et équipements de Agriculture Value Chain Request for Single Stage - One 2020-10- 2020-12- 2021-06- IDA / 58520 Post Limited 60,000.00 0.00 Implementat provenderie pour les Development Quotations Envelope 25 20 18 ion éleveurs et les OP dans la ville de Kalemie/Tanganyika ZR-MINAGRI-188504-GO- RFQ / Acquisition et installation de 6 Pending Décortiqueuse à riz des Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- IDA / 58520 Post Limited 120,000.00 0.00 Implementat coopératives rizicoles dans Development Quotations Envelope 03 29 27 ion les six bassins de production, territoire de Kalemie dans la province de Tanganyika MOF-REF-26 / Acquisition de 10 Tricycles pour la collecte de paddy des Pending Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- coopératives rizicoles dans IDA / Q9610 Post Limited 50,000.00 0.00 Implementat Development Quotations Envelope 04 30 28 les six bassins de ion production, territoire de Kalemie dans la province de Tanganyika ZR-MINAGRI-188542-GO- RFQ / Acquisition de dix (10) Cages flottantes complètes Pending Agriculture Value Chain Request for Single Stage - One 2020-11- 2020-12- 2021-06- avec accessoires et IDA / 58520 Post Limited 40,000.00 0.00 Implementat Development Quotations Envelope 05 31 29 installation dans le territoire ion de Kalemie dans la province de Tanganyika ZR-MINAGRI-188505-GO- RFQ / Aiquisition et installation de 4 unités de pêche complete pour l'approvisionnement regulier Pending Agriculture Value Chain Request for Single Stage - One 2020-11- 2021-01- 2021-06- en poisson des unités de IDA / 58520 Post Limited 120,000.00 0.00 Implementat Development Quotations Envelope 06 01 30 transformation de plateforme ion et conservation du poisson à Kasambondo, Kabuga, Kalemie et Kabimba dans la Province du Tanganyika ZR-MINAGRI-188526-GO- RFQ / Fourniture, installation des matériels pour Pending Support Services and Project Request for Single Stage - One 2020-08- 2020-10- 2021-04- connexion internet ainsi que IDA / 58520 Post Limited 13,000.00 0.00 Implementat Management Quotations Envelope 20 15 13 l'abonnement annuel en ion faveur du bureau du Ministre de l'agriculture de Tanganyika ZR-MINAGRI-188544-GO- RFQ / Acquisition et installation de 10 splits muraux en faveur du Support Services and Project Request for Single Stage - One 2020-09- 2020-08- 2020-11- 2020-11- 2021-05- bâtiment devant servir des IDA / 58520 Post Limited 8,500.00 8,100.00 Signed Management Quotations Envelope 20 24 15 09 14 bureaux pour l'UPEP et Inspections Provinciales de de l'Agriculture et Pêche de la Prvonce du Sud Kivu Page 5 ZR-MINAGRI-188511-GO- RFB / Acquisition d'un lot de 120 génisses pour les Pending Agriculture Value Chain Single Stage - One 2020-10- 2020-10- 2020-12- 2021-01- 2021-02- 2021-08- coopératives, les éleveurs IDA / 58520 Post Request for Bids Open - National 100,000.00 0.00 Implementat Development Envelope 16 21 02 01 05 04 particuliers et les OP dans le ion territoire de Kalemie/Tanganyika ZR-MINAGRI-188502-GO- RFQ / Acquisition des équipements de Pending transformation du manioc en Agriculture Value Chain Request for Single Stage - One 2020-11- 2021-01- 2021-06- IDA / 58520 Post Limited 90,000.00 0.00 Implementat faveur de Centres Development Quotations Envelope 06 01 30 ion Communautaires de Transformation du Riz dans la Province du Tanganyika ZR-MINAGRI-187936-GO- RFQ / Fourniture et mise en service des matériels Pending informatiques, de Support Services and Project Request for Single Stage - One 2020-11- 2020-12- 2021-02- IDA / 58520 Post Limited 250,000.00 0.00 Implementat reproduction et de Management Quotations Envelope 03 29 27 ion vidéoconférence pour le personnel du projet ainsi que les services impliqués ZR-MINAGRI-209975-GO- RFQ / Acquisition de fournitures de bureau et consommables informatiques Pending Support Services and Project Request for Single Stage - One 2020-12- 2021-02- 2021-08- pour l’UPEP PICAGL Sud-Kivu IDA / 58520 Post Limited 30,000.00 0.00 Implementat Management Quotations Envelope 25 19 18 et les Inspections ion provinciales de l'Agriculture, Pêche et Elevage, et du Développement Rural du Sud- Kivu ZR-MINAGRI-210054-GO- RFQ / Acquisition des moulins à manioc en faveur Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- de vingt-deux (22) Centres IDA / 58520 Post Limited 66,000.00 0.00 Implementat Development Quotations Envelope 15 12 09 de Collecte et de ion Transformation de Manioc, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210048-GO- RFQ / Acquisition des presses à vérins hydrauliques Pending motorisées en faveur de Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 98,000.00 0.00 Implementat vingt-deux (22) Centres de Development Quotations Envelope 15 12 09 ion Collecte et de Transformation de Manioc, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210053-GO- RFQ / Acquisition des râpeuses avec châssis en Pending faveur de vingt-deux (22) Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 60,000.00 0.00 Implementat Centres de Collecte et de Development Quotations Envelope 15 12 09 ion Transformation de Manioc, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210046-GO- RFQ / Acquisition des séchoirs solaires en faveur Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- de vingt-deux (22) Centres IDA / 58520 Post Limited 66,000.00 0.00 Implementat Development Quotations Envelope 15 12 09 de Collecte et de ion Transformation de Manioc, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210051-GO- RFQ / Acquisition des kits d'insémination artificielle en Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- faveur de trois (3) IDA / 58520 Post Limited 25,000.00 0.00 Implementat Development Quotations Envelope 22 19 16 institutions et cabinets ion spécialisés, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210058-GO- RFQ / Acquisition des Pending équipements en faveur de Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 45,000.00 0.00 Implementat deux (2) micro-minoteries Development Quotations Envelope 22 19 16 ion du riz, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210056-GO- RFQ / Acquisition des Pending équipements en faveur d'un Agriculture Value Chain Request for Single Stage - One 2021-03- 2021-04- 2021-10- IDA / 58520 Post Limited 35,000.00 0.00 Implementat (1) Centre de Collecte du Development Quotations Envelope 01 26 23 ion Lait, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210059-GO- RFQ / Fourniture et Pending installation des kits solaires Agriculture Value Chain Request for Single Stage - One 2021-03- 2021-04- 2021-10- IDA / 58520 Post Limited 35,000.00 0.00 Implementat en faveur d'un (1) Centre de Development Quotations Envelope 01 26 23 ion Collecte du Lait, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210055-GO- RFQ / Acquisition des équipements en faveur de Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- trois (3) Provenderies à IDA / 58520 Post Limited 28,000.00 0.00 Implementat Development Quotations Envelope 22 19 16 Luvungi, Kabare et Bukavu, ion dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210082-GO- RFQ / Acquisition de vingt (20) tricycles motorisés en faveur de coopératives, associations et autres, pour Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- la collecte et le transport de IDA / 58520 Post Limited 80,000.00 0.00 Implementat Development Quotations Envelope 24 21 18 paddy, manioc, boutures, ion lait,..., dans le bassin d'Uvira, Province du Sud-Kivu,dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210084-GO- RFQ / Acquisition de dix (10) tricycles motorisés en faveur de coopératives, associations Pending et autres, pour la collecte et Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 40,000.00 0.00 Implementat le transport de paddy, Development Quotations Envelope 24 21 18 ion manioc, boutures, lait, ... dans le bassin de Fizi, Province du Sud-Kivu, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210081-GO- RFQ / Acquisition de dix- sept (17) tricycles motorisés en faveur de coopératives, Pending associations et autres, pour Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 68,000.00 0.00 Implementat la collecte et le transport de Development Quotations Envelope 24 21 18 ion paddy, manioc, boutures, lait,..., dans les bassins de Kalehe, Kabare et Walungu, Province du Sud-Kivu ZR-MINAGRI-210090-GO- RFQ / Acquisition des Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- produits vétérinaires, dans le IDA / 58520 Post Limited 95,000.00 0.00 Implementat Development Quotations Envelope 22 19 16 cadre du PICAGL, UPEP Sud- ion Kivu ZR-MINAGRI-210086-GO- RFQ / Acquisition des découpeuses avec châssis en Pending faveur de vingt-deux (22) Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 55,000.00 0.00 Implementat Centres de Collecte et de Development Quotations Envelope 15 12 09 ion Transformation de Manioc,dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210089-GO- RFQ / Acquisition des machines pour coudre les sacs en faveur de vingt-deux Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- (22) Centres de Collecte et IDA / 58520 Post Limited 25,000.00 0.00 Implementat Development Quotations Envelope 15 12 09 de Transformation de Manioc ion et trois (3) provenderies, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210446-GO- RFQ / Acquisition des matériels et équipements pour le conditionnement et la conservation du lait en Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- faveur de huit (8) mini- IDA / 58520 Post Limited 50,000.00 0.00 Implementat Development Quotations Envelope 17 14 11 laiteries de type 3, quatorze ion (14) mini-laiteries de type 2 et deux (2) mini-laiteries de type 1, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210445-GO- RFQ / Acquisition des matériels pour la pasteurisation du lait en Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- faveur de huit (8) mini- IDA / 58520 Post Limited 45,000.00 0.00 Implementat Development Quotations Envelope 17 14 11 laiteries de type 3 et ion quatorze (14) mini-laiteries de type 2, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210448-GO- RFQ / Acquisition des réchauds à gaz en faveur de Pending huit (8) mini-laiteries de type Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 12,000.00 0.00 Implementat 3 et quatorze (14) mini- Development Quotations Envelope 17 14 11 ion laiteries de type 2, dans le cadre du PICAGL, UPEP Sud- Kivu Page 6 ZR-MINAGRI-210449-GO- RFQ / Acquisition des kits solaires en faveur de huit (8) mini-laiteries de type 3, Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- quatorze (14) mini-laiteries IDA / 58520 Post Limited 36,000.00 0.00 Implementat Development Quotations Envelope 17 14 11 de type 2 et deux (2) mini- ion laiteries de type 1, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210642-GO- RFQ / Acquisition des matériels d’entreposage en faveur de 33 mini-minoteries Pending de manioc, 19 rizeries de Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 50,000.00 0.00 Implementat type 1 (Zaccaria ou Development Quotations Envelope 20 17 14 ion équivalent), 6 rizeries de type 2 (SB-50 ou équivalent) et 3 provenderies, dans le cadre du Projet PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210644-GO- RFQ / Acquisition des sacs d’emballage en faveur de 33 mini-minoteries de manioc, Pending 19 rizeries de type 1 Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 40,000.00 0.00 Implementat (Zaccaria ou équivalent), 6 Development Quotations Envelope 16 13 10 ion rizeries de type 2 (SB-50 ou équivalent) et 3 provenderies, dans le cadre du Projet PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210645-GO- RFQ / Acquisition des équipements en faveur de Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- trente-trois (33) mini IDA / 58520 Post Limited 99,000.00 0.00 Implementat Development Quotations Envelope 20 17 14 minoteries de manioc, dans ion le cadre du Projet PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210646-GO- RFQ / Acquisition des décortiqueuses en faveur de Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- six (6) rizeries de type 2 (SB- IDA / 58520 Post Limited 90,000.00 0.00 Implementat Development Quotations Envelope 20 17 14 50 ou équivalent), dans le ion cadre du Projet PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210647-GO- RFQ / Acquisition des générateurs d'énergie en faveur de 33 mini-minoteries Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- de manioc, 19 rizeries de IDA / 58520 Post Limited 72,000.00 0.00 Implementat Development Quotations Envelope 20 17 14 type 1 (Zaccaria ou ion équivalent) et 6 rizeries de type 2 (SB-50 ou équivalent), dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-211078-GO- RFQ / Acquisition, installation et fourniture de la connexion internet aux Pending Support Services and Project Request for Single Stage - One 2021-01- 2021-03- 2021-09- bureaux de l'UPEP Sud-Kivu IDA / 58520 Post Limited 20,000.00 0.00 Implementat Management Quotations Envelope 30 27 23 et du Ministre Provincial de ion l'Agriculture, Pêche et Elevage, et Développement Rural du Sud-Kivu ZR-MINAGRI-211393-GO- RFQ / Acquisition des taureaux géniteurs de race Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- améliorée à livrer dans le IDA / 58520 Post Limited 25,000.00 0.00 Implementat Development Quotations Envelope 27 24 21 bassin de Fizi-Mutambala, ion dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-211394-GO- RFQ / Acquisition des taureaux géniteurs de race Pending Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- améliorée à livrer dans la IDA / 58520 Post Limited 70,000.00 0.00 Implementat Development Quotations Envelope 27 24 21 plaine de Ruzizi et moyens ion plateaux, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-211397-GO- RFQ / Acquisition des Pending taureaux géniteurs de race Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 50,000.00 0.00 Implementat améliorée à livrer à Kalehe, Development Quotations Envelope 27 24 21 ion dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-211395-GO- RFQ / Acquisition des Pending taureaux géniteurs de race Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 25,000.00 0.00 Implementat améliorée à livrer à Walungu, Development Quotations Envelope 27 24 21 ion dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-211396-GO- RFQ / Acquisition des Pending taureaux géniteurs de race Agriculture Value Chain Request for Single Stage - One 2021-02- 2021-04- 2021-10- IDA / 58520 Post Limited 55,000.00 0.00 Implementat améliorée à livrer à Kabare, Development Quotations Envelope 27 24 21 ion dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-214234-GO- RFB / Acquisition des décortiqueuses en faveur de Pending Agriculture Value Chain Single Stage - One 2021-02- 2021-03- 2021-04- 2021-05- 2021-06- 2021-12- dix-neuf (19) rizeries de type IDA / 58520 Post Request for Bids Open - National 500,000.00 0.00 Implementat Development Envelope 26 03 14 14 18 15 1 (Zaccaria Modèle ZX-6 ou ion équivalent), dans le cadre du Projet PICAGL, UPEP Sud-Kivu NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-MINAGRI-79168-NC- RFQ / Location des bureaux Pending Support Services and Project Request for Single Stage - One 2018-10- 2018-12- 2019-06- devant abriter le personnel IDA / 58520 Post Limited 60,000.00 0.00 Implementat Management Quotations Envelope 18 13 11 complémentaire de l'UNCP ion PICAGL ZR-MINAGRI-78968-NC- RFQ / Location des bureaux Support Services and Project Request for Single Stage - One 2018-08- 2018-06- 2018-10- 2018-10- 2019-04- devant abriter l’Unité IDA / 58520 Post Limited 30,000.00 30,000.00 Signed Management Quotations Envelope 18 25 13 02 11 Provinciale d’Exécution du PICAGL Sud-Kivu ZR-MINAGRI-79170-NC- RFQ / Fourniture des services Support Services and Project Request for Single Stage - One 2018-09- 2018-07- 2018-11- 2018-10- 2019-05- de gardiennage à l’Unité IDA / 58520 Post Limited 14,000.00 8,940.00 Signed Management Quotations Envelope 08 09 03 04 02 Provinciale d’Exécution du PICAGL Sud-Kivu ZR-MINAGRI-79128-NC- RFQ / Services d’entretien Support Services and Project Request for Single Stage - One 2018-09- 2018-08- 2018-11- 2018-10- 2019-05- des bureaux de l’Unité IDA / 58520 Post Limited 9,600.00 7,200.00 Signed Management Quotations Envelope 08 20 03 04 02 Provinciale d’Exécution du PICAGL Sud-Kivu ZR-MINAGRI-79094-NC-DIR / Location des bureaux Support Services and Project 2018-08- 2018-09- 2018-08- 2018-09- 2018-09- 2018-09- 2019-03- 2019-09- devant abriter l’Unité IDA / 58520 Post Direct Selection Direct 36,000.00 36,000.00 Completed Management 13 13 18 15 22 15 21 15 Provinciale d’Exécution du PICAGL Tanganyika ZR-MINAGRI-79148-NC- RFQ / Fourniture des services Support Services and Project Request for Single Stage - One 2018-09- 2018-10- 2018-11- 2018-12- 2019-05- de gardiennage à l’Unité IDA / 58520 Post Limited 14,000.00 11,720.00 Signed Management Quotations Envelope 08 23 03 04 02 Provinciale d’Exécution du PICAGL Tanganyika ZR-MINAGRI-78928-NC- RFQ / Services d’entretien Support Services and Project Request for Single Stage - One 2018-09- 2018-10- 2018-11- 2018-12- 2019-05- des bureaux de l’Unité IDA / 58520 Post Limited 9,600.00 7,200.00 Signed Management Quotations Envelope 08 24 03 06 02 Provinciale d’Exécution du PICAGL Tanganyika ZR-MINAGRI-105102-NC- RFQ / Prestataire de service Pending pour le gardiennage des Support Services and Project Request for Single Stage - One 2019-04- 2019-06- 2020-06- IDA / 58520 Post Limited 17,000.00 0.00 Implementat bureaux du personnel Management Quotations Envelope 06 01 01 ion complémentaire de l'UNCP PICAGL ZR-MINAGRI-105298-NC- RFQ / Prestataire de service Pending Support Services and Project Request for Single Stage - One 2018-10- 2018-12- 2019-12- pour le nettoyage des IDA / 58520 Post Limited 15,000.00 0.00 Implementat Management Quotations Envelope 18 13 12 bureaux du personnel ion complémentaire de l'UNCP PICAGL ZR-MINAGRI-105101-NC- RFQ / Affretement d'un avion Pending Support Services and Project Request for Single Stage - One 2019-03- 2019-05- 2019-11- pour les missions conjointes IDA / 58520 Post Limited 100,000.00 0.00 Implementat Management Quotations Envelope 18 13 09 de supervision ion (Gouvernement Banque mondiale) ZR-MINAGRI-105389-NC- RFQ / Sélection d'un prestataire pour l'entretien et Pending Support Services and Project Request for Single Stage - One 2019-04- 2019-05- 2020-05- réparation des véhicules, IDA / 58520 Post Limited 14,000.00 0.00 Implementat Management Quotations Envelope 02 28 05 motos motos et groupe ion électrogène(IRD) pour l'UPEP Tanganyika ZR-MINAGRI-105388-NC- RFQ / Sélection d'un Pending Support Services and Project Request for Single Stage - One 2019-11- 2019-12- 2020-06- prestataire pour l'entretien et IDA / 58520 Post Limited 14,000.00 0.00 Implementat Management Quotations Envelope 02 28 25 réparation des splits muraux ion pour l'UPEP Tanganyika Page 7 ZR-MINAGRI-105296-NC- RFQ / Recrutement d'un prestataire pour l'entretien et Support Services and Project Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2020-06- réparation des matériels IDA / 58520 Post Limited 8,000.00 7,800.00 Signed Management Quotations Envelope 03 28 28 24 26 informatiques et de reprographie pour l'UPEP Tanganyika MOF-REF-125 / Sélection d'un prestataire pour Pending l'entretien et réparation des Support Services and Project Request for Single Stage - One 2019-04- 2019-06- 2020-06- IDA / 58520 Post Limited 20,000.00 0.00 Implementat véhicules, motos et groupe Management Quotations Envelope 14 09 08 ion électrogène(IRD) pour l'UPEP Sud Kivu ZR-MINAGRI-170554-NC- Pending DIR / Mise à jour et Support Services and Project 2020-07- 2020-07- 2020-09- 2021-03- IDA / 58520 Post Direct Selection Direct 37,500.00 0.00 Implementat utilisation de la version Management 25 30 03 02 ion TOMPRO WEB du logiciel PICAGL ZR-MINAGRI-169816-NC- DIR / Renouvellement du Contrat avec Union pour l'Emancipation de la Femme Support Services and Project 2020-01- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2020-08- IDA / 58520 Post Direct Selection Direct 7,200.00 7,200.00 Signed Autochtone (UEFA ) pour Management 02 01 07 02 11 10 09 l'entretien des bureaux de l’Unité Provinciale d’Exécution de Projet (UPEP) Tanganyika ZR-MINAGRI-169814-NC- DIR / Renouvellement du Contrat avec le prestataire HUMAN DIGNITY IN THE Support Services and Project 2020-01- 2019-12- 2020-01- 2020-02- 2020-02- 2020-02- 2020-08- IDA / 58520 Post Direct Selection Direct 10,920.00 10,920.00 Signed WORLD (HDW) pour le Management 03 02 08 05 12 06 10 gardiennage des bureaux de l’Unité Provinciale d’Exécution de Projet Tanganyika ZR-MINAGRI-169988-NC- RFQ / Selection d'un Under prestataire pour l'entretien et Support Services and Project Request for Single Stage - One 2020-05- 2020-02- 2020-07- 2021-01- IDA / 58520 Post Limited 20,000.00 19,754.20 Implementat réparation des véhicules, Management Quotations Envelope 26 17 21 17 ion motos et groupe electrogène pour l'UPEP Sud-Kivu ZR-MINAGRI-188482-NC- DIR / Contractualisation avec les radios, télévisions communautaires et Associations locales pour la Pending communication sociale de Support Services and Project 2020-08- 2020-08- 2020-09- 2021-03- IDA / 58520 Post Direct Selection Direct 35,000.00 0.00 Implementat proximité dans la Province Management 16 21 25 24 ion du Tanganyika ( RTNC, RTGT, TELE 6, AFYA FM, RADIO KAOZE, COJELTA, CJDT et BAKOYOKA SON naTanganyika) ZR-MINAGRI-170570-NC- RFQ / Contractualisation avec huit radios communautaires au Sud Kivu pour la sensibilisation des Pending Support Services and Project 2020-08- 2020-08- 2020-09- 2021-03- activités du Projet ( Radio IDA / 58520 Post Direct Selection Direct 35,000.00 0.00 Implementat Management 15 20 24 23 Maéndeleo, Radio Umoja, ion Radio Baraka, Radio Messager du Peuple, Radio notre Dame de Tanganyika, Radio Flash FM, Radio AMKA, Radio RTBO) ZR-MINAGRI-196114-NC- RFQ / Recrutement d'un prestataire des services de Support Services and Project Request for Single Stage - One 2020-10- 2020-10- 2020-12- 2020-11- 2021-06- gardiennage des bureaux de IDA / 58520 Post Limited 14,000.00 9,600.00 Signed Management Quotations Envelope 20 02 15 09 13 l’Unité Provinciale d’Exécution du Projet PICAGL (UPEP) / Sud-Kivu ZR-MINAGRI-196116-NC- RFQ / Recrutement d'un prestataire des services d’entretien des bureaux et Support Services and Project Request for Single Stage - One 2020-10- 2020-10- 2020-12- 2020-11- 2021-06- IDA / 58520 Post Limited 14,000.00 10,800.00 Signed d'aménagement de la Cour Management Quotations Envelope 20 02 15 09 13 de l’Unité Provinciale d’Exécution du Projet PICAGL (UPEP) / Sud-Kivu ZR-MINAGRI-210104-NC- RFQ / Recrutement d'un prestataire des services de Pending Support Services and Project Request for Single Stage - One 2021-01- 2021-03- 2021-09- gardiennage des bureaux de IDA / 58520 Post Limited 14,000.00 0.00 Implementat Management Quotations Envelope 10 07 03 l’Unité Provinciale ion d’Exécution du Projet PICAGL (UPEP) / Tanganyika ZR-MINAGRI-210105-NC- RFQ / Recrutement d'un prestataire des services Pending d’entretien des bureaux et Support Services and Project Request for Single Stage - One 2021-01- 2021-03- 2021-09- IDA / 58520 Post Limited 15,000.00 0.00 Implementat d'aménagement de la Cour Management Quotations Envelope 10 07 03 ion de l’Unité Provinciale d’Exécution du Projet PICAGL (UPEP) / Tanganyika CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PARSSA-4343-CS-CQS / Consultant Recrutement d'un Cabinet Support Services and Project 2016-12- 2017-02- 2017-03- 2016-09- 2017-04- 2016-09- 2017-10- IDA / Q9260 Post Qualification Open - National 90,000.00 81,902.00 Signed 2016-12-08 pour la Sélection du Management 29 11 13 13 17 21 14 Selection Personnel Essentiel du PICAGL ZR-PARSSA-5160-CS-QBS / Elaboration schéma directeur Agriculture Value Chain Quality Based Open - Pending 2015-11- 2016-01- 2016-01- 2016-02- 2016-03- 2016-05- 2017-05- IDA / Q9260 Post 500,000.00 0.00 2015-10-29 sur le corridor Bukavu-Uvira- Development Selection International Implementation 19 02 30 29 30 04 04 Kalemie ZR-MINAGRI-78952-CS- QCBS / Recrutement d'un Support for the development consultant firme pour la Quality And Cost- Pending 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2020-04- IDA / 58520 of the private agro- Post Open - National 500,000.00 0.00 2018-10-02 réalisation des études Based Selection Implementation 23 06 03 02 09 13 12 industrial sector sectorielles pour la mise en place de parc agroindustriel ZR-MINAGRI-78955-CS- QCBS / Recrutement d'un Support for the development consultant firme pour la Quality And Cost- Open - Pending 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2020-04- IDA / 58520 of the private agro- Post 500,000.00 0.00 2018-10-02 réalisation de l'étude du Based Selection International Implementation 23 06 03 02 09 13 12 industrial sector marché pour le parc agroindustriel ZR-MINAGRI-78984-CS- QCBS / Recrutement d'un Support for the development Quality And Cost- Open - Pending 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2020-04- consultant firme pour le IDA / 58520 of the private agro- Post 500,000.00 0.00 2018-10-02 Based Selection International Implementation 23 06 03 02 09 13 12 renforcement des capacités industrial sector des institutions financières ZR-MINAGRI-79138-CS-QBS / Recrutement d'une ONG Agriculture Value Chain Quality Based Under 2020-09- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2020-06- spécialisée dans les IDA / 58520 Post Open - National 150,000.00 0.00 2018-12-01 Development Selection Implementation 11 22 04 04 03 03 07 06 questions des violences basées sur le genre VSBG ZR-MINAGRI-78906-CS- QCBS / Recrutement d'un consultant firme pour la Support Services and Project Quality And Cost- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2020-05- réalisation des études IDA / 58520 Prior Open - National 500,000.00 0.00 Canceled 2018-11-10 Management Based Selection 01 14 11 13 17 22 21 d'orientation pour l'appui aux services fonciers dans l'aire d'intervention du PICAGL ZR-MINAGRI-78816-CS- QCBS / Consultant chargé Agriculture Value Chain Quality And Cost- Pending 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2020-06- d'évaluation de la sécurité IDA / 58520 Post Open - National 100,000.00 0.00 2018-12-17 Development Based Selection Implementation 07 20 20 19 24 28 27 alimentaire dans les zones du projet ZR-MINAGRI-79114-CS- QCBS / Recrutement d''un auditeur externe pour la Support Services and Project Quality And Cost- Open - Under 2019-01- 2018-10- 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2020-04- certification des états IDA / 58520 Post 170,000.00 0.00 2018-10-02 Management Based Selection International Implementation 19 23 06 03 02 09 13 12 financiers des exercices comptables 2018, 2019 et 2020 ZR-MINAGRI-105374-CS- QCBS / Recrutement d'un consultant firme pour la Support Services and Project Quality And Cost- Open - 2019-07- 2019-08- 2019-09- 2019-10- 2019-11- 2019-12- 2020-12- réalisation des études IDA / 58520 Prior 500,000.00 0.00 Canceled 2019-06-17 Management Based Selection International 08 21 18 18 22 27 26 d'orientation pour l'appui aux services fonciers dans l'aire d'intervention du PICAGL ZR-MINAGRI-78821-CS-QBS / Recrutement d'un Support Services and Project Quality Based Open - 2019-05- 2018-12- 2019-02- 2019-03- 2019-04- 2019-05- 2019-06- 2020-06- consultant firme pour la IDA / 58520 Prior 500,000.00 0.00 Canceled 2018-12-10 Management Selection International 28 31 13 13 12 12 16 15 réalisation de l' étude de référence du projet ZR-MINAGRI-140241-CS- CQS / Bureau d’Etude pour l'élaboration de la Notice d’Impact Environnemental et Consultant Support Services and Project 2019-11- 2020-01- 2020-01- 2020-03- 2021-03- Social de la construction de IDA / 58520 Post Qualification Open - National 70,000.00 0.00 Canceled 2019-10-28 Management 18 01 31 06 06 la microcentrale Selection hydroélectrique de MUTSUVA dans le territoire de KABARE, Province du SUD- KIVU. Page 8 ZR-MINAGRI-140242-CS- CQS / Bureau d’Etude pour la réalisation des études techniques des travaux de Consultant 2019-11- 2020-01- 2020-02- 2020-03- 2020-05- construction de la IDA / 58520 Regional integration Post Qualification Open - National 120,000.00 0.00 Canceled 2019-11-08 29 12 11 17 16 microcentrale Selection hydroélectrique de MUTSUVA dans le territoire de KABARE, Province du SUD- KIVU. ZR-MINAGRI-169986-CS- CQS / Recrutement d'un bureau d'études pour la réalisation des études Consultant techniques et Support Services and Project Under 2020-09- 2020-08- 2020-09- 2020-10- 2020-12- 2021-06- IDA / 58520 Post Qualification Open - National 50,000.00 0.00 2020-07-26 environnementales des Management Implementation 11 16 29 29 03 01 Selection travaux d'aménagement des bureaux DMPCC, ancien bureaux du Secrétaire Général et PARRSA ZR-MINAGRI-169823-CS- CQS / Recrutement d'un consultant (bureau d'étude) Consultant pour la rélisation des études Support Services and Project Pending 2020-08- 2020-10- 2020-11- 2020-12- 2021-06- IDA / 58520 Post Qualification Open - National 250,000.00 0.00 2020-07-29 faisabilités techniques et Management Implementation 19 02 01 06 04 Selection soci-environnementales de trois plates formes multiservices dans la Province du Sud-Kivu MOF-REF-45 / Recrutement d'une ONG spécialisée en Support Services and Project Quality And Cost- Open - 2018-12- 2019-01- 2019-02- 2019-03- 2019-04- 2019-05- 2020-05- IDA / 58520 Prior 500,000.00 0.00 Canceled 2018-11-15 gestion de conflits dans l'aire Management Based Selection International 06 19 16 18 22 27 26 d'intervention de PICAGL ZR-MINAGRI-105368-CS- CQS / Recrutement d'une Consultant ONG pour la mise en œuvre Support Services and Project Pending 2020-11- 2020-12- 2021-01- 2021-02- 2021-08- IDA / 58520 Post Qualification Open - National 350,000.00 0.00 2020-10-14 du Plan d'Actions en Faveur Management Implementation 04 18 17 21 20 Selection des Populations Autoctones de l'aire d'intervention du PICAGL ZR-MINAGRI-140242-CS- CQS-2 / Bureau d’Etude pour la réalisation des études d'impacts environnemental et Consultant social des travaux de Pending 2020-11- 2021-01- 2021-02- 2021-03- 2021-05- IDA / 58520 Regional integration Post Qualification Open - National 70,000.00 0.00 2020-10-31 construction de la Implementation 21 04 03 10 09 Selection microcentrale hydroélectrique de MUTSUVA dans le territoire de KABARE, Province du SUD-KIVU. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PARSSA-4340-CS-CDS / Consultant individuel devant actualiser le manuel des procédures administratives, Support Services and Project 2016-12- 2017-02- 2016-09- 2017-08- IDA / Q9260 Prior Direct Selection Direct 25,000.00 41,591.00 Signed 2016-12-08 financières, comptables et Management 18 21 05 20 passation des marchés de l'UNCP PARRSA en prenant compte l'exécution de PICAGL ZR-PARSSA-6313-CS-CDS / Recrutement consultant Support Services and Project 2015-12- 2016-02- 2015-12- 2016-08- élaboration des documents IDA / Q9260 Prior Direct Selection Direct 200,000.00 190,630.00 Signed 2015-12-10 Management 20 23 03 21 cadres de gestion environnementale ZR-PARSSA-6325-CS-CDS / Consultant individuel en Support Services and Project 2015-08- 2015-10- 2015-07- 2016-04- IDA / Q9260 Prior Direct Selection Direct 25,000.00 24,104.00 Signed 2015-07-25 charge de l' élaboration Management 04 08 03 05 termes de référence ZR-PARSSA-6314-CS-INDV / Recrutement de deux Individual Support Services and Project 2016-06- 2016-06- 2015-11- 2016-08- 2016-01- 2017-01- Consultants individuels en IDA / Q9260 Post Consultant Limited 32,000.00 36,000.00 Signed 2016-06-02 Management 07 28 27 02 18 29 appui aux comités Selection préparatoires ZR-PARSSA-6321-CS-CDS / Recrutement d'un Consultant Support Services and Project 2016-09- 2016-11- 2016-09- 2017-05- individuel pour la mise à jour IDA / Q9260 Prior Direct Selection Direct 25,000.00 41,591.00 Signed 2016-09-16 Management 26 30 15 29 du PARRSA pour tenir compte de PICAGL ZR-PARSSA-5149-CS-CDS / Recrutement du Consortium Agriculture Value Chain 2016-06- 2016-08- 2016-11- 2017-02- UCB-UEA- SENASEM pour la IDA / Q9260 Prior Direct Selection Direct 120,000.00 1,044,956.00 Signed 2016-06-13 Development 23 27 21 23 sélection participative des variétés de riz ZR-PARSSA-5150-CS-INDV / Recrutement de trois Individual Support Services and Project Pending 2016-11- 2016-12- 2017-01- 2017-07- chauffeurs en faveur des IDA / Q9260 Post Consultant Open 12,000.00 0.00 2016-09-30 Management Implementation 18 09 13 12 coordinations provinciales Selection PICAGL ZR-MINAGRI-78820-CS- CDS / Contractualusation Agriculture Value Chain 2018-11- 2019-02- 2019-01- 2019-08- avec RIKOLTO pour l'appui à IDA / 58520 Prior Direct Selection Direct 3,000,000.00 5,500,000.00 Under Review 2018-11-20 Development 30 03 14 02 la mise en œuvre de la chaine de valeur riz ZR-MINAGRI-78874-CS- CDS / Contractualusation avec IITA pour l'appui à la Agriculture Value Chain 2019-01- 2019-03- 2019-01- 2019-09- IDA / 58520 Prior Direct Selection Direct 10,950,000.00 10,209,591.00 Signed 2018-12-27 mise en œuvre de la chaine Development 06 12 10 08 de valeur manioc et création de l'emploi des jeunes ZR-MINAGRI-78980-CS- CDS / Contractualusation avec les instituts de CGIAR pour l'appui à la mise en 2019-01- 2019-03- 2019-03- 2019-09- IDA / 58520 Regional integration Prior Direct Selection Direct 7,780,000.00 8,834,538.00 Signed 2018-12-27 oeuvre de l’intégration 06 12 25 08 régionale des centres de recherche et aux services d’appui et gestion du projet ZR-MINAGRI-78983-CS- CDS / Contractualusation Agriculture Value Chain 2019-01- 2019-03- 2019-01- 2019-09- avec VSF pour l'appui à la IDA / 58520 Prior Direct Selection Direct 3,000,000.00 3,437,132.00 Under Review 2018-12-28 Development 07 13 29 09 mise en œuvre de la chaine de valeur élevage laitier ZR-MINAGRI-78877-CS- CDS / Assistance technique Agriculture Value Chain 2019-01- 2019-03- 2019-07- 2019-09- IDA / 58520 Prior Direct Selection Direct 2,000,000.00 2,000,000.00 Signed 2018-12-29 de la FAO pour la chaîne de Development 08 14 01 10 valeur peche et aquaculture ZR-MINAGRI-78658-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-07- 2019-02- 2019-03- 2019-04- 2019-10- IDA / 58520 Post Consultant Open 120,000.00 0.00 2018-12-30 spécialiste national en Management Implementation 25 17 10 14 11 Selection nutrition ZR-MINAGRI-78876-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-07- 2019-02- 2019-03- 2019-04- 2019-10- IDA / 58520 Post Consultant Open 120,000.00 0.00 2018-12-31 spécialiste en gestion des Management Implementation 25 18 11 15 12 Selection savoirs ZR-MINAGRI-79098-CS- CDS / Maitrise d'Ouvrage Délégué avec UNOPS pour le Agriculture Value Chain 2018-10- 2018-12- 2018-10- 2019-06- Développement IDA / 58520 Prior Direct Selection Direct 38,000,000.00 38,000,000.00 Signed 2018-10-02 Development 12 16 18 14 d'infrastructures proritaires en appui aux chaines de valeur sélectionnées  MOF-REF-21 / Recrutement Individual Support Services and Project 2018-09- 2018-10- 2018-11- 2019-05- d'un spécialiste en suivi et IDA / 58520 Prior Consultant Limited 240,000.00 0.00 Canceled 2018-09-23 Management 28 19 23 22 évaluation en faveur de Selection l'UNCP Individual MOF-REF-22 / Recrutement Support Services and Project 2018-11- 2018-12- 2019-01- 2019-07- IDA / 58520 Prior Consultant Open - National 240,000.00 0.00 Canceled 2018-09-23 d'un auditeur interne Management 11 02 06 05 Selection ZR-MINAGRI-78879-CS- Individual INDV / Recrutement d'un Support Services and Project Pending 2018-08- 2018-08- 2018-09- 2019-03- IDA / 58520 Prior Consultant Open 210,000.00 0.00 2018-06-14 Chargé de Passation des Management Implementation 02 23 27 26 Selection Marchés en faveur de l'UNCP ZR-MINAGRI-79003-CS- INDV / Recrutement de deux Individual Support Services and Project Pending 2016-09- 2016-10- 2016-11- 2017-05- coordonnateurs provinciaux IDA / 58520 Prior Consultant Open 500,000.00 0.00 2016-08-09 Management Implementation 27 18 22 21 pour les UPEP Sud Kivu et Selection Tanganyika ZR-MINAGRI-79009-CS- INDV / Recrutement Individual Support Services and Project Pending 2016-09- 2016-10- 2016-11- 2017-05- spécialistes provinciaux en IDA / 58520 Post Consultant Open 400,000.00 0.00 2016-08-09 Management Implementation 27 18 22 21 suivi et évaluation pour les Selection UPEP Sud Kivu et Tanganyika ZR-MINAGRI-79142-CS- INDV / Recrutement de deux Individual Support Services and Project Under 2019-07- 2018-11- 2018-11- 2019-01- 2019-07- experts en charge de IDA / 58520 Prior Consultant Open 400,000.00 0.00 2018-09-20 Management Implementation 25 08 29 03 02 l'agronomie et de la Selection recherche appliquée ZR-MINAGRI-78660-CS- Individual INDV / Recrutement de deux Support Services and Project Under 2019-07- 2018-11- 2018-11- 2019-01- 2019-07- IDA / 58520 Prior Consultant Open 400,000.00 0.00 2018-09-21 experts en travaux de génie Management Implementation 25 09 30 04 03 Selection civil Page 9 ZR-MINAGRI-78666-CS- Individual INDV / Recrutement de deux Support Services and Project 2018-12- 2018-12- 2019-02- 2019-08- IDA / 58520 Prior Consultant Open 400,000.00 0.00 Canceled 2018-10-22 spécialistes en Management 10 31 04 03 Selection développement du secteur privé ZR-MINAGRI-78965-CS- Individual INDV / Recrutement de deux Support Services and Project Pending 2016-09- 2016-10- 2016-11- 2017-05- IDA / 58520 Post Consultant Open 400,000.00 0.00 2016-08-09 spécialistes provinciaux en Management Implementation 27 18 22 21 Selection passation des marchés ZR-MINAGRI-78889-CS- Individual Support Services and Project Pending 2016-08- 2016-09- 2016-10- 2017-04- INDV / Recrutement de deux IDA / 58520 Post Consultant Limited 360,000.00 0.00 2016-08-09 Management Implementation 14 04 09 07 comptables provinciaux Selection ZR-MINAGRI-78812-CS- INDV / Recrutement de deux Individual Support Services and Project Pending 2016-09- 2016-10- 2016-11- 2017-05- spécialistes provinciaux en IDA / 58520 Post Consultant Open 360,000.00 0.00 2016-08-09 Management Implementation 27 18 22 21 sauvegarde Selection environnementale et sociale ZR-MINAGRI-78813-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-07- 2018-11- 2018-12- 2019-01- 2019-07- IDA / 58520 Prior Consultant Open 210,000.00 0.00 2018-09-26 spécialiste national en Management Implementation 25 14 05 09 08 Selection sauvegarde environnementale ZR-MINAGRI-79116-CS- Individual INDV / Recrutement d'un Support Services and Project Pending 2018-11- 2018-12- 2019-01- 2019-07- IDA / 58520 Post Consultant Open 210,000.00 0.00 2018-09-27 spécialiste national en Management Implementation 15 06 10 09 Selection sauvegarde sociale ZR-MINAGRI-78891-CS- Individual INDV / Recrutement de deux Support Services and Project Pending 2018-11- 2018-12- 2019-01- 2019-07- IDA / 58520 Post Consultant Open 210,000.00 0.00 2018-09-28 assistants provinciaux en Management Implementation 16 07 11 10 Selection communication ZR-MINAGRI-79172-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-07- 2018-11- 2018-11- 2019-01- 2019-07- IDA / 58520 Prior Consultant Open 210,000.00 0.00 2018-09-19 expert en gestion de Projet Management Implementation 25 07 28 02 01 Selection en faveur de l'UNCP ZR-MINAGRI-79012-CS- CDS / Recrutement d'un Support Services and Project Pending 2018-10- 2018-12- 2019-06- IDA / 58520 Post Direct Selection Direct 60,000.00 0.00 2018-10-02 consultant individuel pour la Management Implementation 12 16 14 mise en place du tableau de bord ZR-MINAGRI-79018-CS- INDV / Recrutement d'un consultant individuel pour Individual Agriculture Value Chain Under 2019-07- 2018-12- 2018-12- 2019-02- 2019-08- l'élaboration du plan d'action IDA / 58520 Post Consultant Limited 40,000.00 0.00 2018-12-05 Development Implementation 13 10 31 04 03 en faveur des populations Selection autochtones dans l'aire d'intervention du PICAGL ZR-MINAGRI-79166-CS- CDS / Protocole d'accord Support for the development avec ANAPI pour Pending 2019-01- 2019-03- 2019-09- IDA / 58520 of the private agro- Post Direct Selection Direct 100,000.00 0.00 2018-12-26 l'amélioration du climat d' Implementation 05 11 07 industrial sector affaires dans l'aire d'intervention du PICAGL au Sud Kivu et Tanganyika ZR-MINAGRI-78814-CS- CDS / Protocole d'accord Agriculture Value Chain Pending 2018-10- 2018-12- 2019-06- avec SENASEM pour IDA / 58520 Post Direct Selection Direct 350,000.00 0.00 2018-09-28 Development Implementation 08 12 10 l'inspection, contrôle et certification des semences dans l'aire du Projet ZR-MINAGRI-79117-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-10- 2018-12- 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 12,000.00 Signed 2018-10-31 Caissier pour l'UPEP PICAGL Management 11 19 20 09 28 13 07 12 Selection Sud-Kivu ZR-MINAGRI-78908-CS- Individual INDV / Recrutement d'un Support Services and Project Pending 2018-12- 2019-01- 2019-02- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 0.00 2018-10-31 Assistant en communition Management Implementation 19 09 13 12 Selection pour l'UPEP PICAGL Sud-Kivu ZR-MINAGRI-79120-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 12,000.00 Signed 2018-10-31 Secrétaire l'UPEP PICAGL Sud- Management 19 09 30 13 07 12 Selection Kivu ZR-MINAGRI-78991-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-10- 2018-12- 2019-01- 2018-11- 2019-02- 2018-12- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 12,000.00 Signed 2018-10-31 Assistant de logistique pour Management 11 19 09 28 13 07 12 Selection l'UPEP PICAGL Sud-Kivu ZR-MINAGRI-78910-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-02- 2018-12- 2019-01- 2019-02- 2019-08- IDA / 58520 Post Consultant Open 9,000.00 0.00 2018-10-31 Chauffeur complémentaire Management Implementation 07 19 09 13 12 Selection pour l'UPEP PICAGL Sud-Kivu ZR-MINAGRI-79132-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-12- 2019-01- 2019-01- 2019-02- 2019-01- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 12,000.00 Signed 2018-10-31 caissier pour l'UPEP PICAGL Management 19 09 07 13 07 12 Selection Tanganyika ZR-MINAGRI-78976-CS- INDV / Recrutement d'un Individual Support Services and Project Pending 2018-11- 2018-11- 2018-12- 2019-06- assistant en communition IDA / 58520 Post Consultant Limited 12,000.00 0.00 2018-10-31 Management Implementation 05 26 31 29 pour l'UPEP PICAGL Selection Tanganyika ZR-MINAGRI-78995-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-10- 2018-11- 2018-12- 2018-11- 2019-01- 2018-12- 2019-01- 2019-06- IDA / 58520 Post Consultant Limited 12,000.00 12,000.00 Signed 2018-10-31 secrétaire l'UPEP PICAGL Management 11 05 26 26 07 31 07 29 Selection Tanganyika ZR-MINAGRI-79136-CS- Individual INDV / Recrutement d'un Support Services and Project 2018-12- 2019-01- 2018-12- 2019-02- 2019-01- 2019-08- IDA / 58520 Post Consultant Open 12,000.00 12,000.00 Signed 2018-10-31 assistant de logistique pour Management 19 09 28 13 07 12 Selection l'UPEP PICAGL Tanganika ZR-MINAGRI-78882-CS- INDV / Recrutement d'un Individual Support Services and Project Under 2019-02- 2018-12- 2019-01- 2019-02- 2019-08- chauffeur complémentaire IDA / 58520 Post Consultant Open 9,000.00 0.00 2018-10-31 Management Implementation 07 19 09 13 12 pour l'UPEP PICAGL Selection Tanganyika ZR-MINAGRI-79000-CS- INDV / Recrutement d'un Délégué à pied d'œuvre pour Individual Support Services and Project 2019-03- 2019-01- 2019-05- 2019-01- 2019-06- 2019-02- 2019-06- 2019-08- le contrôle et surveillance IDA / 58520 Post Consultant Open 10,000.00 6,000.00 Signed 2018-11-15 Management 15 03 16 24 06 28 06 27 des travaux de réhabilitation Selection du bureau du Ministre Provincial de l'Agriculture du Tanganyika ZR-MINAGRI-79096-CS- Individual Support Services and Project Pending 2018-08- 2018-08- 2018-09- 2019-03- INDV / Recrutement d'un IDA / 58520 Post Consultant Open 180,000.00 0.00 2018-06-14 Management Implementation 02 23 27 26 comptable national Selection ZR-MINAGRI-78986-CS- CDS / Contractualisation avec STUDI INTERNATIONAL Agriculture Value Chain Under 2019-10- 2018-10- 2018-12- 2019-06- pour la mise à jour des IDA / 58520 Post Direct Selection Direct 120,000.00 0.00 2018-09-30 Development Implementation 18 10 14 12 documents de sauvegarde environnementale et social du PICAGL ZR-MINAGRI-79173-CS- CDS / Contractualisation avec le consortium UCB, Agriculture Value Chain Pending 2018-10- 2018-12- 2019-06- UEA, INERA et SENASEM pour IDA / 58520 Post Direct Selection Direct 170,000.00 0.00 2018-09-23 Development Implementation 03 07 05 la sélection participative des variétés de riz dans la province de Tanganyika ZR-MINAGRI-79014-CS- CDS / Contractualisation Support Services and Project 2018-10- 2018-12- 2019-01- 2019-06- avec SAPHIR IDA / 58520 Post Direct Selection Direct 120,000.00 96,786.00 Signed 2018-10-04 Management 14 18 15 16 DEVELOPPEMENT pour le recrutement du personnel complémentaire de PICAGL ZR-MINAGRI-78988-CS- CDS / Protocole d'accord avec l'INERA pour la Agriculture Value Chain Pending 2018-10- 2018-12- 2019-06- IDA / 58520 Post Direct Selection Direct 350,000.00 0.00 2018-09-27 production des semences Development Implementation 07 11 09 des variétés améliorées dans l'aire du Projet ZR-MINAGRI-105382-CS- CDS / Recrutement de deux délégués à pied d'œuvre pour la surveillance des Support Services and Project 2019-07- 2019-05- 2019-09- 2019-07- 2019-11- 2020-01- IDA / 58520 Post Direct Selection Direct 50,000.00 49,695.00 Signed 2019-05-03 travaux de réhabilitation des Management 08 13 10 17 15 13 bâtiments des inspections provinciales de l'Agriculture du Sud Kivu et Tanganyika ZR-MINAGRI-105304-CS- CDS / Contractualisation avec SAPHIR Support Services and Project 2019-07- 2018-10- 2019-09- 2018-12- 2020-01- 2019-02- IDA / 58520 Post Direct Selection Direct 80,000.00 9,456,960.00 Signed 2018-10-04 DEVELOPPEMENT pour le Management 21 14 13 18 31 01 développement des compétences des ressources humaines du Projet PICAGL ZR-MINAGRI-105356-CS- Individual INDV / Recrutement d'un Support Services and Project Under 2019-07- 2019-03- 2019-04- 2019-05- 2020-05- IDA / 58520 Post Consultant Open 40,000.00 0.00 2019-01-21 logisticien pour l'UNCP Management Implementation 25 11 01 06 05 Selection PICAGL ZR-MINAGRI-105386-CS- INDV / Recrutement d'un Individual Consultant individuel pour Support Services and Project Pending 2019-06- 2019-07- 2019-08- 2020-02- IDA / 58520 Post Consultant Open 35,000.00 0.00 2019-05-06 l'élaboration du guide Management Implementation 24 15 19 15 Selection environnemental du volet végétal de PICAGL Page 10 ZR-MINAGRI-105396-CS- INDV / Recrutement d'un Individual Support Services and Project Pending 2019-04- 2019-05- 2019-06- 2019-12- Consultant individuel pour la IDA / 58520 Post Consultant Limited 35,000.00 0.00 2019-04-06 Management Implementation 11 02 06 03 sensibilisation aux enjeux Selection environnementaux MOF-REF-120 / Individual Recrutement d'un chauffeur Support Services and Project Pending 2019-03- 2019-03- 2019-04- 2020-04- IDA / 58520 Post Consultant Limited 9,000.00 0.00 2019-02-25 complémentaire pour l'UPEP Management Implementation 02 23 27 26 Selection PICAGL Sud-Kivu ZR-MINAGRI-105399-CS- INDV / Recrutement d"un consultant chargé des Individual études techniques et Support Services and Project Under 2019-10- 2019-07- 2019-07- 2019-09- 2020-02- IDA / 58520 Post Consultant Open 25,000.00 0.00 2019-05-20 surveillance des travaux de Management Implementation 08 08 29 02 29 Selection réhabilitation du Ministère et le bâtiments devant abriter provisoirement l’IPAPEL Sud Kivu ZR-MINAGRI-117752-CS- INDV / Recrutement d'un Individual Agriculture Value Chain Under 2019-07- 2019-09- 2019-09- 2019-10- 2021-12- Spécialiste en Agribusiness IDA / 58520 Post Consultant Open 96,000.00 0.00 2019-07-15 Development Implementation 08 02 23 28 31 et développement de chaînes Selection de valeur ZR-MINAGRI-117753-CS- Individual INDV / Recrutement d'un Agriculture Value Chain Under 2019-07- 2019-09- 2019-10- 2019-11- 2021-12- IDA / 58520 Post Consultant Open 96,000.00 0.00 2019-07-24 Spécialiste en Finance Rurale Development Implementation 08 11 02 06 31 Selection pour le secteur agricole ZR-MINAGRI-105103-CS- INDV / Recrutement d'un consultant individuel pour Individual Support Services and Project 2019-06- 2019-06- 2019-07- 2020-01- l'élaboration du plan d'action IDA / 58520 Post Consultant Open 40,000.00 0.00 Canceled 2019-04-17 Management 05 26 31 27 en faveur des populations Selection autochtones dans l'aire d'intervention du PICAGL ZR-MINAGRI-78904-CS- INDV / Recrutement d'un Individual Support Services and Project 2018-11- 2018-12- 2019-01- 2019-07- consultant individuel pour IDA / 58520 Post Consultant Open 40,000.00 0.00 Canceled 2018-10-06 Management 24 15 19 18 l'élaboration du manuel Selection d'accès au crédit ZR-MINAGRI-122621-CS- CDS / Recrutement de Support for the development Under 2019-07- 2019-08- 2019-10- 2020-04- Monsieur Ibrahim Dione IDA / 58520 of the private agro- Post Direct Selection Direct 40,000.00 0.00 2019-07-31 Implementation 25 10 14 11 pour l'élaboration du manuel industrial sector d'accès au crédit ZR-MINAGRI-122617-CS- CDS / Recrutement de l'IFPRI Agriculture Value Chain 2019-08- 2019-08- 2019-11- 2019-10- 2020-12- 2020-04- IDA / 58520 Prior Direct Selection Direct 500,000.00 452,114.90 Signed 2019-07-31 pour la réalisation de l' étude Development 28 10 05 14 15 11 de référence du PICAGL ZR-MINAGRI-140233-CS- CDS / Etude de faisabilité d'un plan d'opération de d'un Support for the development plan d'aménagement d'un Under 2019-11- 2019-11- 2020-03- 2020-01- 2020-07- IDA / 58520 of the private agro- Prior Direct Selection Direct 1,200,000.00 0.00 2019-10-30 parc agroindustriel dans la Implementation 30 09 20 13 11 industrial sector plaine de Rugumba dans le territoire de Kaliémie dans la Province de Tanganyika avec ONUDI ZR-MINAGRI-140238-CS- CDS / Réalisation de la Agriculture Value Chain Under 2019-12- 2019-11- 2020-01- 2020-07- cartographie des sols sur le IDA / 58520 Post Direct Selection Direct 120,000.00 0.00 2019-10-30 Development Implementation 15 09 13 11 corridor Bukavu -Kalemie avec IITA ZR-MINAGRI-148116-CS- CDS / Réalisation des études techniques, d'impacts environnemental et social Agriculture Value Chain Under 2019-12- 2019-12- 2020-03- 2020-08- des travaux de construction IDA / 58520 Post Direct Selection Direct 150,000.00 0.00 2019-12-20 Development Implementation 14 30 04 31 de la microcentrale hydroélectrique de MUTSUVA dans le territoire de KABARE, Province du SUD-KIVU avec STUCKY SA ZR-MINAGRI-148122-CS- INDV / Recrutement d'un Individual Responsable Provincial de Support Services and Project 2019-12- 2020-01- 2020-08- 2020-02- 2020-08- 2020-03- 2020-10- 2020-09- IDA / 58520 Post Consultant Limited 90,000.00 42,000.00 Signed 2020-01-15 Suivi et Évaluation pour Management 14 20 26 10 28 16 28 12 Selection l'Unité Provinciale d'Exécution de Tanganyika ZR-MINAGRI-148125-CS- INDV / Recrutement d'un Individual chargé de Passation des Support Services and Project Under 2019-12- 2020-01- 2020-02- 2020-03- 2020-09- IDA / 58520 Post Consultant Limited 90,000.00 0.00 2020-01-15 Marchés pour l'Unité Management Implementation 14 20 10 16 12 Selection Provinciale d'Exécution du Projet Sud Kivu ZR-MINAGRI-157206-CS- CDS / Recrutement de M. ISSA DRAME pour le renforcement des capacités des acteurs impliqués dans Support Services and Project Under 2020-02- 2020-03- 2020-05- 2020-11- la mise en œuvre du projet IDA / 58520 Post Direct Selection Direct 35,000.00 0.00 2020-02-20 Management Implementation 07 01 05 01 en suivi-évaluation et rapportage et l’appui à l’élaboration du rapport de la mission conjointe de supervision du PICAGL ZR-MINAGRI-170568-CS- INDV / Recrutement d'un consultant individuel pour la Individual réalisation des études Support Services and Project Pending 2020-08- 2020-09- 2020-10- 2021-04- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2020-08-15 techniques des travaux de Management Implementation 20 10 15 13 Selection construction du laboratoire du SENASEM et INERA Tanganyika ZR-MINAGRI-169817-CS- INDV / Recrutement d'un Délégué à Pied d'Oeuvre pour Individual le contrôle et la surveillance Support Services and Project Pending 2020-08- 2020-09- 2020-10- 2021-04- IDA / 58520 Post Consultant Limited 12,000.00 0.00 2020-08-15 des travaux de construction Management Implementation 20 10 15 13 Selection de deux (2) laboratoires du SENASEM et de l'INERA Tanganyika ZR-MINAGRI-169895-CS- INDV / Recrutement consultant pour la traduction Individual Support Services and Project Pending 2020-08- 2020-09- 2020-10- 2021-04- du guide de bonnes IDA / 58520 Post Consultant Limited 3,000.00 0.00 2020-08-10 Management Implementation 15 05 10 08 pratiques environnementales Selection et sociales du PICAGL en swahili en faveur de l'UPEP Tanganyika ZR-MINAGRI-169847-CS- INDV / Recrutement Individual Support Services and Project Pending 2020-07- 2020-07- 2020-07- 2020-07- consultant pour infographie IDA / 58520 Post Consultant 8,000.00 0.00 2020-07-10 Management Implementation 10 10 10 10 du Guide Selection environnemental/Tanganyika ZR-MINAGRI-169821-CS- INDV / Recrutement d'un délégué à pied d'œuvre (DPO) pour le contrôle et Individual surveillance des travaux de Support Services and Project Pending 2020-05- 2020-06- 2020-07- 2021-01- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2020-05-20 réhabiitation du bâtiment Management Implementation 25 15 20 16 Selection complémentaire de l'Inspection Provinciale de l'Agriculture, Pêche et Elevage de la province du Sud Kivu ZR-MINAGRI-185889-CS- CDS / Recrutement du bureau d'études INTAIRPLAN Support Services and Project Under 2020-10- 2020-08- 2020-11- 2020-12- Gmb H pour la revue des IDA / 58520 Post Direct Selection Direct 60,000.00 0.00 2020-08-20 Management Implementation 13 30 03 18 études techniques de travaux de réhabilitation de routes de desserte agricole ZR-MINAGRI-188541-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre (DPO) pour la surveillance et le contrôle des travaux de Individual Agriculture Value Chain Under 2020-09- 2020-11- 2020-12- 2021-01- 2021-07- construction de 6 dépôts de IDA / 58520 Post Consultant Open 12,000.00 0.00 2020-10-01 Development Implementation 30 19 10 14 13 stockage dont deux (02) à Selection Rugumba, deux (02) à Lwaminwa et deux (02) à Katibili dans la Province de Tanganyika ZR-MINAGRI-188506-CS- INDV / Recrutement d'un Délégué à Pied d'Oeuvre pour la surveillance et le contrôle Individual Agriculture Value Chain Under 2020-09- 2020-11- 2020-12- 2021-01- 2021-07- des travaux de construction IDA / 58520 Post Consultant Open 12,000.00 0.00 2020-10-02 Development Implementation 29 20 11 15 14 de 10 Bâtiments devant Selection abriter les unités de transformation de manioc dans la Province de Tanganyika ZR-MINAGRI-188518-CS- INDV / Recrutement d'un Délégué à Pied d'Oeuvre pour la surveillance et le contrôle des travaux de construction Individual Agriculture Value Chain 2021-01- 2020-11- 2020-12- 2021-01- 2021-07- de 6 Bâtiments devant abriter IDA / 58520 Post Consultant Open 12,000.00 0.00 Under Review 2020-10-03 Development 28 21 12 16 15 les équipements de Selection transformation de Riz dans les six Bassins de production dans la Province de Tanganyika Page 11 ZR-MINAGRI-188546-CS- INDV / Recrutement d'un Délégué à Pied d'Oeuvre pour la surveillance et le contrôle Individual Agriculture Value Chain Pending 2020-11- 2020-12- 2021-01- 2021-07- des travaux de construction IDA / 58520 Post Consultant Open 12,000.00 0.00 2020-10-04 Development Implementation 22 13 17 16 de 10 bâtiments devant Selection abriter les unités de transformation de maïs dans la Province de Tanganyika ZR-MINAGRI-188527-CS- INDV / Recrutement d'un Délégué à Pied d'Ouevre pour le contrôle et la surveillance Individual Agriculture Value Chain Pending 2020-12- 2021-01- 2021-02- 2021-08- travaux de construction de 2 IDA / 58520 Post Consultant Open 12,000.00 0.00 2020-10-25 Development Implementation 13 03 07 06 dépôts vétérinaires et 2 Selection cliniques vétérinaires dans les bassins de la Rugumba et Lwamina, territoire de Kalemie ZR-MINAGRI-188525-CS- INDV / Recrutement d'un Délégué à Pied d'Ouevre (DPO) pour le contrôle et la Individual Agriculture Value Chain Under 2020-09- 2020-12- 2021-01- 2021-02- 2021-08- surveillance des travaux de IDA / 58520 Post Consultant Open 12,000.00 0.00 2020-10-26 Development Implementation 30 14 04 08 07 construction de huit (08) Selection mini laiteries dans les six bassins de production, territoire de Kalemie ZR-MINAGRI-188484-CS- INDV / Recrutement d'un Délégué à Pied d'Oeuvre (DPO) pour le contrôle et la surveillance des travaux de Individual Agriculture Value Chain Under 2020-09- 2020-12- 2021-01- 2021-02- 2021-08- construction de deux (02) IDA / 58520 Post Consultant Open 6,000.00 0.00 2020-10-27 Development Implementation 30 15 05 09 08 cliniques vétérinaires dans Selection les bassins de production de la Rugumba et Lwamina, territoire de Kalemie/Tanganyika ZR-MINAGRI-188538-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre Individual (DPO) pour le contrôle et la Agriculture Value Chain Pending 2020-12- 2021-01- 2021-02- 2021-08- IDA / 58520 Post Consultant Open 6,000.00 0.00 2020-10-28 surveillance des travaux de Development Implementation 16 06 10 09 Selection construction de deux (02) dépôts vétérinaires dans la ville de Kalemie/Tanganyika ZR-MINAGRI-188524-CS- INDV / Recrutement Individual consultant pour la traduction Support Services and Project Pending 2020-08- 2020-09- 2020-10- 2021-04- IDA / 58520 Post Consultant Limited 3,000.00 0.00 2020-08-21 du guide de bonnes Management Implementation 26 16 21 19 Selection pratiques environnementales et sociales du PICAGL en swahili/Sud Kivu ZR-MINAGRI-188869-CS- CDS / Contractualisation avec Monsieur Freddy KAPIAMBA WA KAPIAMBA pour le contrôle des travaux Support Services and Project Under 2020-12- 2020-09- 2020-11- 2021-05- complémentaires de IDA / 58520 Post Direct Selection Direct 14,000.00 0.00 2020-09-15 Management Implementation 11 25 29 28 Réhabilitation du bâtiment devant servir des bureaux des Inspections Provinciales de l’Agriculture et du Développement Rural de Tanganyika ZR-MINAGRI-188911-CS- CDS / Contractualisation avec Monsieur Mabel LUBEMBE NZUNGA pour le contrôle et la surveillance Support Services and Project Pending 2020-09- 2020-12- 2021-05- des Travaux IDA / 58520 Post Direct Selection Direct 14,000.00 0.00 2020-09-17 Management Implementation 27 01 30 complémentaires de réhabilitation du bâtiment des bureaux des Inspections Provinciales de l’Agriculture, Pêche, Elevage et Développent Rural du Sud Kivu ZR-MINAGRI-188912-CS- CDS / Contractualisation avec Monsieur MASEMBE WASIKATENDA Samy pour le contrôle et la surveillance Support Services and Project Pending 2020-09- 2020-12- 2021-05- des travaux de réhabilitation IDA / 58520 Post Direct Selection Direct 14,000.00 0.00 2020-09-17 Management Implementation 27 01 30 des bureaux du Ministère Provincial de l’Agriculture, Pêche, Elevage et Développement Rural du Sud- Kivu ZR-MINAGRI-189089-CS- CDS / Contractualisation Support Services and Project Under 2020-11- 2020-09- 2020-11- 2021-05- avec Monsieur IBRAHIMA IDA / 58520 Post Direct Selection Direct 16,000.00 0.00 2020-09-15 Management Implementation 08 25 29 28 DIONE pour la mise à jour du tableau de bord du Projet PICAGL ZR-MINAGRI-188459-CS- CDS / Contractualisation avec la firme Zuid Oost Azië Support Services and Project 2020-11- 2021-01- 2021-07- IDA / 58520 Prior Direct Selection Direct 500,000.00 0.00 Under Review 2020-10-29 (ZOA) pour la gestion des Management 08 12 11 conflits et questions foncières dans la zone d'intervention du PICAGL ZR-MINAGRI-196112-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre pour Individual Agriculture Value Chain 2020-10- 2020-12- 2020-12- 2021-01- 2021-07- la surveillance et le contrôle IDA / 58520 Post Consultant Open 12,000.00 0.00 Under Review 2020-10-15 Development 28 03 24 28 27 des travaux de construction Selection du Laboratoire du SENASEM du Tanganyika ZR-MINAGRI-196113-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre pour Individual Agriculture Value Chain 2020-10- 2020-12- 2020-12- 2021-01- 2021-07- la surveillance et le contrôle IDA / 58520 Post Consultant Open 12,000.00 0.00 Under Review 2020-10-15 Development 28 03 24 28 27 des travaux de construction Selection du Laboratoire de l'INERA du Tanganyika ZR-MINAGRI-199487-CS- CDS / Mission d' appui à l’UNCP dans la mise en œuvre des activités du Support Services and Project 2020-10- 2020-10- 2020-10- 2020-12- 2020-10- 2021-06- PICAGL(Appui à l'élaboration IDA / 58520 Post Direct Selection Direct 75,000.00 74,450.00 Signed 2020-10-16 Management 19 26 20 30 21 28 du rapport à mi-parcours et d'activités) et l' élaboration du rapport d’achèvement du PARRSA -FA avec Monsieur ISSA DRAME ZR-MINAGRI-203023-CS- INDV / Recrutement d'un Individual Support Services and Project Under 2021-01- 2020-12- 2020-12- 2021-01- 2021-07- Responsable Provincial en IDA / 58520 Post Consultant Limited 42,000.00 0.00 2020-11-30 Management Implementation 09 05 26 30 29 sauvegarde Selection environnementale et sociale de l'UPEP Sud Kivu ZR-MINAGRI-203024-CS- INDV / Recrutement d'un Délégué à pied d'oeuvre pour Individual la surveillance et contrôle Agriculture Value Chain Pending 2020-12- 2021-01- 2021-02- 2021-08- IDA / 58520 Post Consultant Limited 12,000.00 0.00 2020-12-09 des travaux de réhabilitation Development Implementation 14 04 08 07 Selection des travaux du bâtiment du Secrétariat Général de Pêche et Elevage à Kinshasa ZR-MINAGRI-209981-CS- CDS / Contractualisation avec Monsieur MASEMBE WASIKATENDA Samy, Délégué à Pied d’Œuvre pour Support Services and Project Pending 2020-12- 2021-03- 2021-09- le contrôle et la surveillance IDA / 58520 Post Direct Selection Direct 6,000.00 0.00 2020-12-20 Management Implementation 30 05 01 des travaux de la clôture et aménagement extérieur des Bureaux du Ministère Provincial de l’Agriculture, Elevage, Pêche du Sud-Kivu ZR-MINAGRI-210123-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre pour la surveillance et le contrôle des Travaux de construction Individual Agriculture Value Chain 2021-06- 2021-03- 2021-03- 2021-04- 2021-10- de quatre (04) boutiques IDA / 58520 Post Consultant Open 12,000.00 0.00 Under Review 2021-01-15 Development 16 05 26 30 27 d'intrants agricoles dans les Selection Bassins de production de Rugumba, Lwaminwa, Kabimba et Kalemie dans la Province de Tanganyika ZR-MINAGRI-210124-CS- INDV / Recrutement d'un Délégué à Pied d'Œuvre (DPO) pour la surveillance et Individual le contrôle des Travaux de Agriculture Value Chain Pending 2021-03- 2021-04- 2021-05- 2021-11- IDA / 58520 Post Consultant Open 8,000.00 0.00 2021-01-22 construction de deux (02) Development Implementation 12 02 07 03 Selection provenderies dans les Bassins de production de Rugumba et Lwaminwa dans la Province de Tanganyika ZR-MINAGRI-210137-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et Individual surveillance des Travaux de Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-27 construction de quatre (4) Development 26 01 22 29 25 Selection Centres de Collecte et Transformation de Manioc à Bitale, Bulmbika et Mulonge, dans le territoire de Kalehe Page 12 ZR-MINAGRI-210139-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et surveillance des Travaux de Individual Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- construction de quatre (4) IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-27 Development 26 01 22 29 25 Centres de Collecte et Selection Transformation de Manioc à Mubuku, Karasi, Kitchanga et Maibano, dans le territoire de Kalehe ZR-MINAGRI-210134-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et Individual surveillance des Travaux de Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-27 construction de deux (2) Development 26 01 22 29 25 Selection Centres de Collecte et Transformation de Manioc à Katanga et Malinde, dans le territoire de Fizi ZR-MINAGRI-210133-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et Individual surveillance des Travaux de Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-27 construction de cinq (5) Development 26 01 22 29 25 Selection Centres de Collecte et Transformation de Manioc à Katana, Kavumu et Luhihi, dans le territoire de Kabare ZR-MINAGRI-210135-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et Individual surveillance des Travaux de Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-27 construction de trois (3) Development 26 01 22 29 25 Selection Centres de Collecte et Transformation de Manioc à Sange, Kiliba et Runingu, dans le territoire d’Uvira ZR-MINAGRI-210138-CS- INDV / Recrutement d'un (1) délégué à pied d'oeuvre pour la mission de controle et surveillance des Travaux de Individual Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- construction de quatre (4) IDA / 58520 Post Consultant Limited 6,000.00 0.00 Under Review 2021-01-27 Development 26 01 22 29 25 Centres de Collecte et Selection Transformation de Manioc à Kamanyola, Luvungi et Lubarika, dans la plaine de Ruzizi ZR-MINAGRI-210214-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des Travaux de construction de 2 mini Individual Support Services and Project Pending 2021-01- 2021-02- 2021-03- 2021-09- laboratoires de SENASEM à IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-01-25 Management Implementation 30 20 27 23 Bwegera et Fizi, d’1 mur de Selection clôture et aménagement paillasses salle de labo physique et phytopathologie au SENASEM Bukavu ZR-MINAGRI-210331-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la mission de contrôle et surveillance des Travaux de Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- construction des aires de IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-03 Development Implementation 08 01 05 02 sechage semi ouverts dans le Selection groupement de Bushumba (territoire de Kabare) et le groupement d'Itara (territoire d'Uvira) ZR-MINAGRI-210333-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la mission de contrôle et Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- surveillance des Travaux de IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-03 Development Implementation 08 01 05 02 construction des aires de Selection sechage non couverts à Sebele dans le territoire de Fizi et à Uvira ZR-MINAGRI-210661-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des Travaux Individual Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- de construction de 7 abris IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 Development 26 03 24 31 27 dont 6 pour mini-minoterie Selection et 1 pour mini-laiterie de type 2, et d'une provenderie, dans le territoire de Kabare ZR-MINAGRI-210658-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des Travaux Individual de construction de 16 abris Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 dont 12 pour mini- Development 26 03 24 31 27 Selection minoterie, 3 pour rizerie type 2 et 1 pour mini- laiterie de type 2, et d'une provenderie, dans la plaine de Ruzizi ZR-MINAGRI-210662-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour Individual la surveillance des Travaux Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 de construction de 4 abris Development 26 03 24 31 27 Selection dont 1 pour mini-minoterie et 3 pour mini-laiterie de type 2, dans le territoire de Kalehe ZR-MINAGRI-210659-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des Travaux Individual de construction de 10 abris Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 dont 8 pour mini-minoterie, Development 26 03 24 31 27 Selection 1 pour rizerie de type 2 (SB- 50 ou équivalent) et 1 pour mini-laiterie de type 2, dans le territoire de Fizi ZR-MINAGRI-210660-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour Individual le contrôle et la surveillance Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 des Travaux de construction Development 26 03 24 31 27 Selection de 2 abris pour mini-laiterie de type 2 et d'une provenderie, à Bukavu ZR-MINAGRI-210657-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des Travaux Individual de construction de 14 abris Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-03- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-01-29 dont 5 mini-minoteries, 2 Development 26 03 24 31 27 Selection rizerie de type 2, 1 entrepôt des intrants agricoles et 6 mini-laiteries de type 2, dans le territoire d’Uvira ZR-MINAGRI-210877-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 3 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines et d’1 entrepôt semencier à Katanga, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210874-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 3 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines à Baraka et d’1 entrepôt semencier à Nemba, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210876-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 3 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines à Sebele,Kabondonzi et Malinde et d’1 entrepôt semencier à Sebele,UPEP Sud- Kivu ZR-MINAGRI-210880-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Individual Construction de 4 entrepôts Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 des produits agricoles avec Development Implementation 10 03 07 04 Selection bureaux des préposés et latrines dont 2 à Fizi centre et 2 à Mulongwe, dans le cadre du PICAGL, UPEP Sud- Kivu Page 13 ZR-MINAGRI-210883-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 3 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines et de 2 entrepôts semenciers à Sange, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210873-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Individual Construction de 3 entrepôts Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 des produits agricoles avec Development Implementation 10 03 07 04 Selection bureaux des préposés et latrines à Kiliba et Runingu, et d’1 entrepôt semencier à Kiliba, UPEP Sud-Kivu ZR-MINAGRI-210879-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Individual Construction de 4 entrepôts Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 des produits agricoles avec Development Implementation 10 03 07 04 Selection bureaux des préposés et latrines dont 3 à Luvungi et 1 à Lubarika, dans le cadre du PICAGL, UPEP Sud-Kivu ZR-MINAGRI-210881-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 4 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines à Kagando, Kahwizi, Kigongo et Murunga, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210878-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 2 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines et d’1 entrepôt semencier à Nyangezi, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210882-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Individual Construction de 3 entrepôts Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 des produits agricoles avec Development Implementation 10 03 07 04 Selection bureaux des préposés et latrines à Kamanyola, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210875-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la surveillance des travaux de Construction de 2 entrepôts Individual Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- des produits agricoles avec IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-05 Development Implementation 10 03 07 04 bureaux des préposés et Selection latrines dont 1 à Mudaka et 1 à Bunyakiri/Bitale, dans le cadre du PICAGL, UPEP Sud- Kivu ZR-MINAGRI-210976-CS- INDV / Recrutement d’un (1) délégué à pied d’œuvre pour Individual le contrôle et la surveillance Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-04- 2021-09- IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-02-01 des Travaux de construction Development 26 06 27 03 30 Selection d’une (1) laiterie de type 3 à Cirunga, dans le territoire de Kabare ZR-MINAGRI-210978-CS- INDV / Recrutement d’un (1) délégué à pied d’œuvre pour le contrôle et la surveillance Individual Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-04- 2021-09- des Travaux de construction IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-02-01 Development 26 06 27 03 30 de trois (3) laiteries de type 3 Selection dont deux (2) à Luvungi et une (1) à Bwegera, dans le territoire d’Uvira ZR-MINAGRI-210977-CS- INDV / Recrutement d’un (1) délégué à pied d’œuvre pour le contrôle et la surveillance Individual Agriculture Value Chain 2021-05- 2021-02- 2021-02- 2021-04- 2021-09- des Travaux de construction IDA / 58520 Post Consultant Limited 8,000.00 0.00 Under Review 2021-02-01 Development 26 06 27 03 30 de quatre (4) laiteries de type Selection 3 dont 1 à Sange, 1 à Kavimvira et 2 à Uvira, dans le territoire d’Uvira ZR-MINAGRI-213742-CS- INDV / Recrutement d'un délégué à pied d'oeuvre pour la mission de contrôle et Individual surveillance des Travaux de Agriculture Value Chain Pending 2021-02- 2021-03- 2021-04- 2021-10- IDA / 58520 Post Consultant Limited 8,000.00 0.00 2021-02-08 construction de deux (2) mini Development Implementation 13 06 10 07 Selection chambres froides dont 1 à Luberezi et 1 Mutarule, dans le cadre du PICAGL, UPEP Sud- Kivu Page 14 PLAN DE PASSATION DES MARCHES AVEC INDICATION DES SEUILS DE REVUE ET DE PASSATION DES MARCHES Information sur le Projet : Togo –Projet de Filets Sociaux et de Services de Base (P157038) Agence d’exécution du Projet : Agence Nationale d’Appui au Développement à la Base (ANADEB) Date du plan de passation des marchés: 11 Septembre, 2017 Période couverte par ce plan de passation des marchés: Septembre, 2017 – 31 août, 2018 I. GENERAL 1. Informations sur le Projet : P-RAMS • Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System): Elevé II. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans l’annexe 1 des "Directives de Passation des Marchés de fournitures, de travaux et de services (autres que les services de consultants) par les Emprunteurs de la Banque mondiale dans le cadre des prêts de la BIRD et des crédits de l’AID. Catégories de Seuils de revue a Observations marchés/Méthode de priori passation des marchés Montants estimatifs des contrats en millions de dollars américains Travaux, Contrats clé en main et Contrats de >= 5 Fourniture et Montage d’Installations Fournitures, Système d’information, et Services >= 1.5 autres que les services de consultants Travaux, Les justifications de Contrats Contrats clé en l’entente directe à passer main et devront être jointes par Contrats de >= 5 et approuvées avec entente Fourniture et PPM directe Montage d’Installations Fournitures, Système d’information, et Services >= 1.5 autres que les services de consultants 2. Pré qualification : Aucune n’a été pour l’instant identifiée. Toutefois, en cas de pré-qualification, les soumissionnaires seront pré qualifiées en accord avec les dispositions des paragraphes 2.9 et 2.10 des directives. 3. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : FOURNITURES ET SERVICES AUTRE QUE LES SERVICES DE CONSULTANTS (US$ TRAVAUX (US$ équivalent) équivalent) AOI AON CF AOI AON CF < < 100.000 ≥5.000.000 <5.000.000 ≥ 500.000 < 500.000 200.000 4. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). II. Sélection des Consultants 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujet à la revue préalable de la Banquet comme indiqué dans l’annexe 1 du Guide de Sélection et d’Emploi des Consultants par les Emprunteurs de la Banque Mondiale dans le cadre des Prêts de la BIRD et des Crédits et Dons de l’AID Méthode de Seuils de revue a Observations sélection/Catégories de priori marchés Montants estimatifs des contrats en millions de dollars américains Méthode >= 0.5 compétitive/Firmes de consultants Entente directe/firmes Les justifications pour >= 0.5 de consultants l’entente directe Entente devront être jointes et directe/Consultants >= 0.2 approuvées avec le individuel PPM Méthode Compétitive >= 0.2 (Comparaison de CVs)/ Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux selon les dispositions du paragraphe 2.7 des Directives de Sélection et d’Emploi des Consultants, et l’Emprunteur ne procède pas à une publication dans UNDB. 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels prévus au paragraphe 3.7 des directives pour la sélection et l’emploi des consultants par les emprunteurs de la Banque Mondiale dans le cadre des Prêts de la BIRD et des Crédits et Dons de l’AID PROCUREMENT Togo : Safety Nets and Basic Services Project PLAN General Information Country: Togo Bank’s Approval Date of the Original Procurement Plan: 2017-09-11 2021-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157038 GPN Date: 2017-07-31 Project Name: Safety Nets and Basic Services Project Loan / Credit No: IDA / V0650, IDA / D1740 N Executing Agency(ies): ational Agency for Development Support at the Base WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 03FT-PFS / Travaux Component 3:Capacity Request for Single Stage - One 2017-11- d'aménagement des Antennes IDA / V0650 building and project Post Limited 24,167.00 38,573.20 Signed 2017-07-20 2017-09-08 2017-09-14 2018-02-02 Quotations Envelope 13 Régionales ANADEB management GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3:Capacity 01FT-PFS / Acquisition de UN Agencies IDA / V0650 building and project Post Direct 300,000.00 223,857.36 Completed 2017-04-14 2017-06-01 2017-04-21 2017-06-01 2017-06-09 2017-09-25 2017-11-06 2018-01-15 matériel roulant (Direct) management 06FT-PFS / Reproduction des Component 2: Social safety Request for Single Stage - One carnets de reçus pour IDA / D1740 Post Limited 17,000.00 4,690.48 Completed 2017-08-22 2017-09-08 2017-10-17 2017-10-09 2017-11-16 2017-10-30 nets Quotations Envelope l'opération cantine scolaire Component 3:Capacity 02FT-PFS / Acquisition de Single Stage - One IDA / V0650 building and project Post Request for Bids Open - National 129,000.00 217,653.64 Signed 2017-04-14 2018-01-20 2017-04-21 2017-05-21 2017-07-19 2017-06-20 2017-09-20 2018-02-07 2017-12-27 2018-04-08 matériels informatiques Envelope management TG-ANADEB-44865-GO-RFB Component 3:Capacity Single Stage - One / Acquisition de six (6) IDA / V0650 building and project Post Request for Bids Open - National 70,000.00 75,869.41 Signed 2017-07-11 2017-07-18 2017-08-17 2017-09-04 2017-09-16 2017-10-20 2017-10-28 2018-07-20 2017-12-27 Envelope groupes électrogènes management TG-ANADEB-46559-GO-RFQ / Tablettes: Acquisition de 50 Component 3:Capacity tablettes pour les enquêtes Request for Single Stage - One IDA / D1740 building and project Post Limited 23,334.00 24,278.90 Completed 2018-02-06 2018-09-05 2018-04-03 2018-11-14 2018-06-02 2018-11-20 (PMT, géolocalisation, Quotations Envelope management enregistrement de données de terrain) TG-ANADEB-46571-GO-RFQ Component 3:Capacity / Fournitures de Bureau: Request for Single Stage - One IDA / D1740 building and project Post Limited 16,667.00 0.00 Canceled 2018-04-04 2018-05-30 2018-11-26 Acquisition de fournitures de Quotations Envelope management bureau TG-ANADEB-101617-GO- RFQ / Consommables cartes TM: Acquisition des Component 3:Capacity Request for Single Stage - One consommables pour la IDA / D1740 building and project Post Limited 17,000.00 29,589.54 Completed 2019-03-09 2019-03-11 2019-05-04 2019-05-02 2019-07-03 2019-05-27 Quotations Envelope production des cartes des management bénéficiaires des transferts monétaires TG-ANADEB-101632-GO- RFQ / Consommables de Component 3:Capacity Request for Single Stage - One bureau: Acquisition de IDA / D1740 building and project Post Limited 25,000.00 0.00 Canceled 2019-03-05 2019-04-30 2020-02-24 Quotations Envelope consommables informatiques management et bureautiques TG-ANADEB-46558-GO-RFQ / Communication institutionnelle: Production Component 3:Capacity de supports imprimés de Request for Single Stage - One IDA / D1740 building and project Post Limited 24,167.00 0.00 Canceled 2018-02-25 2018-04-22 2018-10-19 communication Quotations Envelope management institutionnelle autour du projet (dépliants, gadgets, étrennes, kakemono etc,) TG-ANADEB-46574-GO-RFQ Component 3:Capacity Request for Single Stage - One / Fourniture de IDA / D1740 building and project Post Limited 16,667.00 0.00 Canceled 2019-09-21 2019-11-16 2019-12-16 Quotations Envelope consommables informatiques management TG-ANADEB-123497-GO- DIR / Moteurs véhicules: Component 3:Capacity Acquisition, montage et IDA / D1740 building and project Post Direct Selection Direct 75,000.00 81,236.08 Signed 2019-09-11 2019-07-01 2019-09-26 2019-07-16 2019-10-27 2019-10-31 2020-01-25 services connexes de six (6) management moteurs pour les véhicules rétrocédés du projet PDCplus TG-ANADEB-164855-GO- RFQ / Tablette pour le Component 3:Capacity personnel: Acquisition de dix Request for Single Stage - One IDA / D1740 building and project Post Limited 15,000.00 28,486.57 Completed 2020-04-04 2020-11-20 2020-05-30 2020-12-31 2020-06-29 2021-02-15 (10) tablettes pour le Quotations Envelope management personnel de l'unité de gestion du projet TG-ANADEB-180540-GO- RFQ / ACQUISITION EPI: Acquisition des équipements Component 3:Capacity de protection individuels (EPI) Request for Single Stage - One IDA / D1740 building and project Post Limited 15,000.00 24,303.99 Completed 2020-07-01 2020-07-02 2020-08-26 2020-09-15 2020-09-15 2020-10-19 pour le personnel de Quotations Envelope management l'ANADEB dans le cadre de suivi et supervision de mise en œuvre des microprojets sur le terrain Page 1 TG-ANADEB-212323-GO- RFQ / Acquisition 3 Lap top: Acquisition de trois (03) Component 3:Capacity Pending ordinateurs performants pour Request for Single Stage - One IDA / D1740 building and project Post Limited 8,000.00 0.00 Implementati 2021-01-20 2021-03-17 2021-04-16 la gestion des bases de Quotations Envelope management on données du projet Filets sociaux et services de base (FSB) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 07FT-PFS / Location de Component 3:Capacity bureau dans les antennes IDA / V0650 building and project Post Direct Selection Direct 12,000.00 0.00 Canceled 2017-09-14 2017-09-19 2017-10-24 2018-10-24 régionales ANADEB management TG-ANADEB-46584-NC-RFQ Component 3:Capacity / Assurance du personnel: Request for Single Stage - One IDA / D1740 building and project Post Limited 16,667.00 12,806.53 Signed 2018-02-05 2018-07-09 2018-04-02 2018-06-19 2019-03-28 Souscription de police Quotations Envelope management d'assurance pour le personnel TG-ANADEB-48433-NC-RFQ / Extension réseau internet: Fourniture de services Component 3:Capacity Request for Single Stage - One d'extension du réseau intranet IDA / D1740 building and project Post Limited 20,000.00 0.00 Canceled 2018-02-22 2018-04-19 2018-06-18 Quotations Envelope et internet (câblage et management connections internet ADSL) dans les bureaux de l'ANADEB TG-ANADEB-48480-NC-RFQ / Supports audio-visuels: Component 3:Capacity Production des manuels et Request for Single Stage - One IDA / D1740 building and project Post Limited 33,334.00 0.00 Canceled 2018-03-08 2018-05-03 2018-07-02 des guides illustrés du projet Quotations Envelope management sous forme de supports audio- visuels TG-ANADEB-48435-NC-RFB / Impression et multiplication Component 3:Capacity des manuels, des brochures, Single Stage - One IDA / D1740 building and project Post Request for Bids Open - National 75,000.00 0.00 Canceled 2018-03-01 2018-03-08 2018-04-19 2018-05-19 2018-06-23 2018-08-22 des guides illustrés et des Envelope management supports pédagogiques sur les activités du projet TG-ANADEB-48434-NC-RFQ Component 3:Capacity / Magasine: Production d'un Request for Single Stage - One IDA / D1740 building and project Post Limited 16,667.00 0.00 Canceled 2018-03-11 2018-05-06 2018-07-05 magasine d'information Quotations Envelope management semestriel TG-ANADEB-49332-NC-RFQ / Paiement des TM: Fourniture des services de transfert Component 2: Social safety Request for Single Stage - One IDA / D1740 Post Limited 100,000.00 79,045.10 Signed 2018-03-06 2018-10-12 2018-05-08 2018-12-24 2019-05-03 monétaires aux bénéficiaires nets Quotations Envelope de la sous composante des Transferts monétaires 05FT-PFS / Acquisition de modules complémentaires de Component 3:Capacity TOM2PRO et de IDA / V0650 building and project Post Direct Selection Direct 70,000.00 0.00 Canceled 2017-04-21 2017-04-28 2017-06-16 2017-08-15 TOMMONITORING et des clé management de connexion et fourniture de services connexes TG-ANADEB-69430-NC-DIR / LOGICIEL TOM2PRO: Acquisition de modules Component 3:Capacity complémentaires de IDA / D1740 building and project Post Direct Selection Direct 105,000.00 108,947.26 Signed 2018-07-12 2018-07-27 2018-07-17 2018-08-03 2018-08-21 2018-10-12 2018-09-20 TOM2PRO et de management TOMMONITORING et des clé de connexion et fourniture de services connexes TG-ANADEB-99919-NC-RFQ / Reproduction guides FGB: Component 3:Capacity Reproduction des guides Request for Single Stage - One IDA / D1740 building and project Post Limited 55,000.00 39,058.24 Signed 2019-03-20 2019-05-29 2019-05-22 2019-09-11 2019-11-18 illustrés de formation de Quotations Envelope management gestion à la base (FGB) du projet TG-ANADEB-101629-NC- RFQ / Carnet TM: Component 3:Capacity Request for Single Stage - One Reproduction des cartes de IDA / D1740 building and project Post Limited 30,000.00 10,191.40 Signed 2019-03-05 2019-03-14 2019-04-30 2019-05-21 2019-05-30 Quotations Envelope bénéficiaires des transferts management monétaires TG-ANADEB-101958-NC- RFQ / Extension câblage internet: Fourniture de services d'extension du Component 3:Capacity Request for Single Stage - One réseau intranet et internet IDA / D1740 building and project Post Limited 20,000.00 0.00 Canceled 2019-03-06 2019-05-01 2019-05-31 Quotations Envelope (câblage et connections management internet ADSL) dans les bureaux des Antennes régionales de l'ANADEB TG-ANADEB-197272-NC- RFQ / PLANCHES PHOTO CAUSERIES TM: Reproduction Component 3:Capacity Pending Request for Single Stage - One de planches-photo pour les IDA / D1740 building and project Post Limited 50,000.00 0.00 Implementati 2020-11-04 2021-01-06 2021-02-05 Quotations Envelope causeries socio-éducatives management on sur les transferts monétaire (TM) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 01PI-PFS / Sélection d'un Component 3:Capacity Consultant cabinet pour le recrutement IDA / V0650 building and project Post Qualification Open - National 40,000.00 16,801.42 Signed 2017-04-10 2017-05-02 2017-05-01 2017-06-14 2017-07-04 2017-07-14 2017-07-28 2017-08-18 2017-08-17 2017-10-17 du personnel du projet management Selection 06PI-PFS / Recrutement des Consultant ONG pour la mise en œuvre Component 2: Social safety IDA / D1740 Post Qualification Open - National 195,000.00 130,248.82 Signed 2017-07-05 2017-10-20 2017-07-26 2017-09-08 2017-11-14 2017-10-08 2017-12-15 2017-11-12 2017-12-26 2018-08-09 des cantines scolaires dans nets Selection les écoles bénéficiaires 02PI-PFS / Recrutement d'un Component 3:Capacity cabinet pour l'audit des Least Cost IDA / V0650 building and project Post Open - National 15,000.00 0.00 Canceled 2017-07-15 2017-08-05 2017-09-18 2017-10-16 2017-11-15 2017-12-20 2018-01-24 2018-02-23 comptes du fonds de Selection management préparation du projet TG-ANADEB-46579-CS-LCS / Audit Financier Comptable: Sélection d'un cabinet pour Component 3:Capacity Least Cost l'audit financier et comptable IDA / D1740 building and project Post Open - National 40,000.00 57,412.34 Signed 2018-05-31 2018-09-26 2018-06-21 2018-08-04 2018-12-12 2018-09-01 2018-12-31 2018-10-01 2019-01-16 2018-11-05 2019-02-05 2018-12-10 2019-04-02 2019-10-06 Selection du Projet, Exercices 2018 management (Juillet 2017 à Décembre 2018), 2019 et 2020 TG-ANADEB-101956-CS- CQS / Évaluation processus Component 3:Capacity Consultant TM: Recrutement d'un IDA / D1740 building and project Post Qualification Open - National 50,000.00 60,845.87 Completed 2019-04-15 2020-02-26 2019-04-29 2019-06-28 2020-06-19 2019-07-19 2020-08-07 2019-08-23 2020-08-26 2019-10-22 2021-02-12 consultant pour l'évaluation management Selection du processus du programme des transferts monétaires TG-ANADEB-46577-CS-CQS / Conception SIG: Sélection Consultant d'un consultant pour la Component 2: Social safety IDA / V0650 Post Qualification Open - National 58,334.00 0.00 Canceled 2018-01-31 2018-02-21 2018-04-06 2018-05-06 2018-06-10 2018-09-08 conception et l'installation du nets Selection système d'information et de gestion (SIG) des projets TG-ANADEB-143908-CS- CQS / Agence de communication: sélection Component 3:Capacity Consultant d'une agence de IDA / D1740 building and project Post Qualification Limited 25,000.00 0.00 Canceled 2019-11-20 2019-12-04 2020-01-03 2020-02-07 2020-12-03 communication pour la management Selection capitalisation des réalisations du projet FSB TG-ANADEB-101955-CS- CQS / Mise en place du RSU: Component 3:Capacity Consultant Sélection d'une firme pour la IDA / D1740 building and project Post Qualification Open - National 92,000.00 0.00 Canceled 2020-04-30 2020-05-14 2020-07-13 2020-08-03 2020-09-07 2020-12-06 mise en place du système du management Selection registre social unifié (RSU) TG-ANADEB-197245-CS- CQS / Formation en sauvegarde du personnel: Recrutement d'un cabinet Component 3:Capacity Consultant pour la formation du IDA / D1740 building and project Post Qualification Open - National 50,000.00 0.00 Canceled 2020-10-30 2020-12-07 2020-11-13 2020-12-27 2021-01-11 2021-02-15 2021-03-17 personnel de l'ANADEB sur les management Selection directives en sauvegardes environnementales et sociales des bailleurs notamment la Banque mondiale TG-ANADEB-204771-CS- CQS / Étude Financement Component 3:Capacity Consultant Cantines: Sélection d'un IDA / D1740 building and project Post Qualification Open - National 42,000.00 0.00 Canceled 2020-12-31 2021-01-21 2021-03-06 2021-04-05 2021-05-10 2021-07-09 cabinet pour l'étude sur les management Selection financements innovants des cantines scolaires TG-ANADEB-228821-CS- CQS / AUDIT TM DIGITAUX: SÉLECTION D'UN BUREAU/CABINET POUR Component 3:Capacity Consultant Pending L'AUDIT DES PAIEMENTS IDA / D1740 building and project Post Qualification Open - National 65,000.00 0.00 2021-04-20 2021-05-04 2021-06-08 2021-06-29 2021-08-03 2021-09-02 Implementation DIGITAUX DES TRANSFERTS management Selection MONÉTAIRES (TM) DU PROJET DE FILETS SOCIAUX ET SERVICES DE BASE (FSB) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 05PI-PFS / Recrutement d'un consultant national en appui Component 3:Capacity Individual au système de planification et IDA / V0650 building and project Post Consultant Open 17,000.00 0.00 Canceled 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 du suivi évaluation de management Selection l'ANADEB TG-ANADEB-36702-CS-INDV / Coordonnateur: Component 3:Capacity Individual Recrutement d'Un IDA / D1740 building and project Post Consultant Open 30,000.00 33,512.32 Signed 2017-06-01 2017-06-09 2017-07-20 2017-11-23 2017-08-10 2017-11-24 2017-09-14 2018-03-01 2018-09-09 Coordonnateur pour le management Selection compte de l'Unité de gestion du projet TG-ANADEB-46332-CS-INDV / Consultant FGB : Component 3:Capacity Individual Recrutement d'un (01) IDA / D1740 building and project Post Consultant Open 33,350.00 33,387.89 Signed 2018-01-28 2018-03-18 2018-04-05 2018-04-08 2018-06-11 2018-05-13 2018-08-10 2018-11-09 Consultant pour l'actualisation management Selection des outils de formation en gestion à la base (FGB) TG-ANADEB-46353-CS-INDV Component 3:Capacity Individual / Assistant SSE: Recrutement IDA / D1740 building and project Post Consultant Open 15,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-20 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 d'un (01) Assistant suivi- management Selection évaluation Page 3 TG-ANADEB-46355-CS-INDV / Gestionnaire SIG: Component 3:Capacity Individual Recrutement d'un (01) IDA / D1740 building and project Post Consultant Open 20,000.00 15,461.44 Signed 2018-01-31 2018-05-17 2018-03-21 2019-01-09 2018-04-11 2019-01-11 2018-05-16 2019-01-14 2019-05-11 Spécialiste en système management Selection d'information et de gestion (SIG) TG-ANADEB-46359-CS-INDV / Assistant administratif: Component 3:Capacity Individual Recrutement d'un (01) IDA / D1740 building and project Post Consultant Open 10,000.00 6,260.62 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 Assistant administratif pour le management Selection projet TG-ANADEB-46799-CS-INDV / Sauvegarde sociale: Component 3:Capacity Individual Recrutement d'un Spécialiste IDA / D1740 building and project Post Consultant Open 20,000.00 26,587.73 Signed 2017-10-15 2017-10-20 2017-12-03 2017-12-26 2017-12-24 2018-04-09 2018-01-28 2018-04-10 2019-01-23 en sauvegarde sociale pour le management Selection compte du projet TG-ANADEB-44863-CS-INDV / SGF: Recrutement d'Un Component 3:Capacity Individual Spécialiste en gestion IDA / D1740 building and project Post Consultant Open 10,000.00 22,551.84 Signed 2017-06-01 2017-06-09 2017-07-20 2017-11-24 2017-08-10 2017-12-06 2017-09-14 2018-03-01 2018-03-13 financière (SGF) pour le management Selection compte de l'Unité de gestion du projet TG-ANADEB-44864-CS-INDV / SPM: Recrutement d'un Component 3:Capacity Individual Spécialiste en passation de IDA / D1740 building and project Post Consultant Open 10,000.00 25,026.30 Signed 2017-06-01 2017-06-09 2017-07-20 2017-12-11 2017-08-10 2017-12-13 2017-09-14 2018-03-01 2018-03-13 marchés (SPM) pour le compte management Selection de l'Unité de gestion du projet TG-ANADEB-46352-CS-INDV / Filets Sociaux RM: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-20 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Maritime de l'ANADEB TG-ANADEB-46357-CS-INDV / FGB Région Maritime: Recrutement d'un(e) Component 3:Capacity Individual Formateur en gestion à la IDA / D1740 building and project Post Consultant Open 14,000.00 15,654.14 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-28 2018-04-11 2018-10-04 2018-05-16 2018-11-12 2019-05-11 base (FGB) pour le compte du management Selection projet au profit de l'antenne régionale Maritime de l'ANADEB TG-ANADEB-46365-CS-INDV / Graphiste: Recrutement d'un illustrateur (Graphiste) pour Component 3:Capacity Individual l'actualisation/adaptation des IDA / D1740 building and project Post Consultant Open 15,000.00 0.00 Canceled 2018-02-05 2018-03-26 2018-04-16 2018-05-21 2018-09-18 boîtes à images des modules management Selection de formation en gestion à la base (FGB) TG-ANADEB-48453-CS-INDV / FGB Région Plateaux: Recrutement d'un(e) Component 3:Capacity Individual Formateur en gestion à la IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-28 2018-04-11 2018-10-01 2018-05-16 2018-10-04 2019-05-11 base (FGB) pour le compte du management Selection projet au profit de l'antenne régionale Plateaux de l'ANADEB TG-ANADEB-48454-CS-INDV / FGB Région Centrale: Recrutement d'un(e) Component 3:Capacity Individual Formateur en gestion à la IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-28 2018-04-11 2018-10-04 2018-05-16 2018-10-08 2019-05-11 base (FGB) pour le compte du management Selection projet au profit de l'antenne régionale Centrale de l'ANADEB TG-ANADEB-48455-CS-INDV / FGB Région Kara: Recrutement d'un(e) Component 3:Capacity Individual Formateur en gestion à la IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-28 2018-04-11 2018-10-01 2018-05-16 2018-10-03 2019-05-11 base (FGB) pour le compte du management Selection projet au profit de l'antenne régionale Kara de l'ANADEB TG-ANADEB-48457-CS-INDV / FGB Région Savanes: Recrutement d'un(e) Component 3:Capacity Individual Formateur en gestion à la IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-28 2018-04-11 2018-10-04 2018-05-16 2018-10-04 2019-05-11 base (FGB) pour le compte du management Selection projet au profit de l'antenne régionale Savanes de l'ANADEB TG-ANADEB-48459-CS-INDV / Filets Sociaux RP: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-04-04 2018-09-26 2018-04-25 2018-09-28 2018-05-30 2018-10-01 2019-05-25 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Plateaux de l'ANADEB TG-ANADEB-48460-CS-INDV / Filets Sociaux RC: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-13 2018-04-11 2018-10-26 2018-05-16 2018-10-01 2019-05-11 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Centrale de l'ANADEB TG-ANADEB-48463-CS-INDV / Filets Sociaux RK: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-20 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Kara de l'ANADEB Page 4 TG-ANADEB-48464-CS-INDV / Filets Sociaux RS: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-20 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Savanes de l'ANADEB TG-ANADEB-46341-CS-CDS / Ciblage de bénéficiaires: Component 2: Social safety Sélection d'une firme pour le IDA / V0650 Post Direct Selection Direct 116,667.00 97,705.78 Signed 2018-01-28 2018-03-29 2018-02-09 2018-05-11 2018-04-15 2018-07-20 2018-08-13 nets ciblage des bénéficiaires du projet TG-ANADEB-48466-CS-INDV / Assistant Infra RP: Recrutement d'un Assistant régional en Infrastructures, Component 3:Capacity Individual Chargé de la passation des IDA / D1740 building and project Post Consultant Open 16,000.00 15,390.55 Signed 2018-01-31 2018-01-31 2018-03-21 2018-10-09 2018-04-11 2018-12-31 2018-05-16 2019-01-07 2019-05-11 marchés pour le compte du management Selection projet au profit de l'antenne régionale Plateaux de l'ANADEB TG-ANADEB-46802-CS-INDV / Comptable-gestionnaire: Component 3:Capacity Individual Recrutement d'un Comptable- IDA / D1740 building and project Post Consultant Direct 10,000.00 0.00 Canceled 2017-12-01 2017-12-11 2017-12-18 2018-01-01 2018-06-30 gestionnaire au niveau management Selection national pour le compte du projet TG-ANADEB-46351-CS-INDV / Assistant Infra RM: Recrutement d'un Assistant régional en Infrastructures, Component 3:Capacity Individual Chargé de la passation des IDA / D1740 building and project Post Consultant Open 16,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 marchés pour le compte du management Selection projet au profit de l'antenne régionale Maritime de l'ANADEB TG-ANADEB-46358-CS-INDV / Comptable-Gestionnaire RM: Recrutement d'un Component 3:Capacity Individual comptable-gestionnaire IDA / D1740 building and project Post Consultant Open 14,000.00 14,688.17 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-13 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 régional pour le compte du management Selection projet au profit de l'antenne régionale Maritime de l'ANADEB TG-ANADEB-46363-CS-INDV / Secrétaire-Caissier RM: Recrutement d'un(e) secrétaire Component 3:Capacity Individual caissier pour le compte du IDA / D1740 building and project Post Consultant Open 6,000.00 5,217.18 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-08 2019-05-11 projet au profit de l'antenne management Selection régionale Maritime de l'ANADEB TG-ANADEB-48450-CS-INDV / Secrétaire-Caissier RP: Recrutement d'un(e) secrétaire Component 3:Capacity Individual Under caissier pour le compte du IDA / D1740 building and project Post Consultant Open 6,000.00 0.00 2018-01-31 2018-01-31 2018-03-21 2018-04-11 2018-05-16 2019-05-11 Implementation projet au profit de l'antenne management Selection régionale Plateaux de l'ANADEB TG-ANADEB-48451-CS-INDV / Secrétaire-Caissier RC: Recrutement d'un(e) secrétaire Component 3:Capacity Individual caissier pour le compte du IDA / D1740 building and project Post Consultant Open 6,000.00 5,217.18 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 projet au profit de l'antenne management Selection régionale Centrale de l'ANADEB TG-ANADEB-48468-CS-INDV / Assistant Infra RC: Recrutement d'un Assistant régional en Infrastructures, Component 3:Capacity Individual Chargé de la passation des IDA / D1740 building and project Post Consultant Open 16,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 marchés pour le compte du management Selection projet au profit de l'antenne régionale Centrale de l'ANADEB TG-ANADEB-48469-CS-INDV / Assistant Infra RK: Recrutement d'un Assistant Component 3:Capacity Individual régional en Infrastructures, IDA / D1740 building and project Post Consultant Open 16,000.00 15,703.71 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 Chargé de la passation des management Selection marchés pour le compte du projet au profit de l'antenne régionale Kara de l'ANADEB TG-ANADEB-48470-CS-INDV / Assistant Infra RS: Recrutement d'un Assistant régional en Infrastructures, Component 3:Capacity Individual Chargé de la passation des IDA / D1740 building and project Post Consultant Open 16,000.00 15,187.47 Signed 2018-01-31 2018-01-31 2018-03-21 2018-10-30 2018-04-11 2019-10-30 2018-05-16 2018-11-12 2019-05-11 marchés pour le compte du management Selection projet au profit de l'antenne régionale Savanes de l'ANADEB TG-ANADEB-48473-CS-INDV / Comptable-Gestionnaire RP: Recrutement d'un comptable- Component 3:Capacity Individual gestionnaire régional pour le IDA / D1740 building and project Post Consultant Open 14,000.00 14,688.17 Signed 2018-01-31 2018-01-31 2018-03-21 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection l'antenne régionale Plateaux de l'ANADEB Page 5 TG-ANADEB-48474-CS-INDV / Comptable-Gestionnaire RC: Recrutement d'un comptable- Component 3:Capacity Individual gestionnaire régional pour le IDA / D1740 building and project Post Consultant Open 14,000.00 14,688.17 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-13 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection l'antenne régionale Centrale de l'ANADEB TG-ANADEB-48477-CS-INDV / Comptable-Gestionnaire RS: Recrutement d'un comptable- Component 3:Capacity Individual gestionnaire régional pour le IDA / D1740 building and project Post Consultant Open 14,000.00 14,688.17 Signed 2018-01-31 2018-06-22 2018-03-21 2018-09-13 2018-04-11 2018-09-26 2018-05-16 2018-10-15 2019-05-11 compte du projet au profit de management Selection l'antenne régionale Savanes de l'ANADEB TG-ANADEB-48476-CS-INDV / Comptable-Gestionnaire RK: Recrutement d'un comptable- Component 3:Capacity Individual gestionnaire régional pour le IDA / D1740 building and project Post Consultant Open 14,000.00 14,688.17 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-13 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection l'antenne régionale Kara de l'ANADEB TG-ANADEB-46364-CS-INDV / Chauffeur-Coursier FSB: Recrutement d'un (01) Component 3:Capacity Individual Chauffeur-Coursier pour le IDA / D1740 building and project Post Consultant Open 4,000.00 3,131.68 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-24 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection la direction générale de l'ANADEB TG-ANADEB-51929-CS-INDV / Chauffeur-Coursier RM: Recrutement d'un (01) Component 3:Capacity Individual Chauffeur-Coursier pour le IDA / D1740 building and project Post Consultant Open 4,000.00 2,712.93 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-14 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection l'Antenne régionale de l'ANADEB Maritime TG-ANADEB-51930-CS-INDV / Chauffeur-Coursier RP: Recrutement d'un (01) Component 3:Capacity Individual Under Chauffeur-Coursier pour le IDA / D1740 building and project Post Consultant Open 4,000.00 0.00 2018-01-31 2018-01-31 2018-03-21 2018-09-26 2018-04-11 2018-05-16 2019-05-11 Implementation compte du projet au profit de management Selection l'Antenne régionale de l'ANADEB Plateaux TG-ANADEB-51931-CS-INDV / Chauffeur-Coursier RC: Recrutement d'un (01) Component 3:Capacity Individual Chauffeur-Coursier pour le IDA / D1740 building and project Post Consultant Open 4,000.00 2,714.12 Signed 2018-01-31 2018-01-31 2018-03-21 2018-09-14 2018-04-11 2018-09-26 2018-05-16 2018-10-01 2019-05-11 compte du projet au profit de management Selection l'Antenne régionale de l'ANADEB Centrale TG-ANADEB-62826-CS-INDV / Formation en Passation des Component 3:Capacity Individual Marchés: Recrutement d'un IDA / D1740 building and project Post Consultant Limited 25,000.00 0.00 Canceled 2018-05-31 2018-06-05 2018-06-26 2018-07-31 2018-09-29 consultant pour la formation management Selection des acteurs sur la passation des marchés communautaires TG-ANADEB-46347-CS-INDV / FGB proximité RM: Recrutement de cinq (5) Component 3:Capacity Individual prestataires individuels IDA / D1740 building and project Post Consultant Open 5,835.00 0.00 Canceled 2018-07-31 2018-07-08 2018-09-18 2018-10-09 2018-11-13 2019-09-09 chargés de l'animation management Selection communautaire en Formation en Gestion à la Base (FGB) dans la région Maritime TG-ANADEB-74839-CS-INDV / FGB proximité RP: Recrutement de huit (8) Component 3:Capacity Individual prestataires individuels IDA / D1740 building and project Post Consultant Open 9,336.00 0.00 Canceled 2018-07-31 2018-09-18 2018-10-09 2018-11-13 2019-09-09 chargés de l'animation management Selection communautaire en Formation en Gestion à la Base (FGB) dans la région des Plateaux TG-ANADEB-74842-CS-INDV / FGB proximité RC: Recrutement de sept (7) Component 3:Capacity Individual prestataires individuels IDA / D1740 building and project Post Consultant Open 8,170.00 0.00 Canceled 2018-07-31 2018-09-18 2018-10-09 2018-11-13 2019-09-09 chargés de l'animation management Selection communautaire en Formation en Gestion à la Base (FGB) dans la région Centrale TG-ANADEB-74845-CS-INDV / FGB proximité RK: Recrutement de neuf (9) Component 3:Capacity Individual prestataires individuels IDA / D1740 building and project Post Consultant Open 10,500.00 0.00 Canceled 2018-07-31 2018-09-18 2018-10-09 2018-11-13 2019-09-09 chargés de l'animation management Selection communautaire en Formation en Gestion à la Base (FGB) dans la région de la Kara TG-ANADEB-74847-CS-INDV / FGB proximité RS: Recrutement de onze (11) Component 3:Capacity Individual prestataires individuels IDA / D1740 building and project Post Consultant Open 12,840.00 0.00 Canceled 2018-07-31 2018-01-31 2018-09-18 2018-10-09 2018-11-13 2019-09-09 chargés de l'animation management Selection communautaire en Formation en Gestion à la Base (FGB) dans la région des savanes TG-ANADEB-101639-CS- INDV / Géoréférencement: Recrutement d'un consultant Component 3:Capacity Individual pour l'appui à l'ANADEB dans IDA / D1740 building and project Post Consultant Open 25,000.00 0.00 Canceled 2019-04-30 2019-07-13 2019-08-03 2019-09-07 2019-11-06 le géoréférencement des management Selection microprojets sociocommunautaires Page 6 TG-ANADEB-101950-CS- INDV / Formation en Passation des Marchés: Component 3:Capacity Individual Recrutement d'un consultant IDA / D1740 building and project Post Consultant Open 17,000.00 20,277.86 Signed 2019-02-25 2019-03-28 2019-03-31 2019-05-20 2019-04-21 2019-07-08 2019-05-26 2019-07-15 2019-07-25 pour la formation des acteurs management Selection sur la passation des marchés communautaires TG-ANADEB-101952-CS- INDV / Evaluation sociale: Component 3:Capacity Individual Recrutement d'un (01) IDA / D1740 building and project Post Consultant Open 25,000.00 0.00 Under Review 2019-05-02 2019-07-15 2019-08-05 2019-09-09 2019-11-08 Consultant pour l'évaluation management Selection en genre et développement social sur les microprojets TG-ANADEB-101954-CS- INDV / Évaluation mi- Component 3:Capacity Individual parcours: Recrutement d'un IDA / D1740 building and project Post Consultant Open 25,000.00 24,428.28 Completed 2019-02-28 2019-02-08 2019-05-13 2019-04-11 2019-06-03 2019-04-26 2019-07-08 2019-05-07 2019-09-06 2019-06-07 (01) Consultant pour management Selection l'évaluation à mi-parcours du projet TG-ANADEB-107032-CS- INDV / Consultant screening Component 3:Capacity Individual social: Recrutement d'un Under IDA / D1740 building and project Post Consultant Limited 4,500.00 5,495.83 2019-02-15 2019-02-02 2019-03-02 2019-03-02 2019-03-09 2019-03-22 2019-03-21 2019-07-19 consultant en sauvegarde Implementation management Selection sociale pour appui au screening des microprojets TG-ANADEB-107033-CS- INDV / Consultant screening Component 3:Capacity Individual social: Recrutement d'un IDA / D1740 building and project Post Consultant Limited 4,500.00 5,406.68 Signed 2019-02-15 2019-02-02 2019-03-02 2019-03-02 2019-03-09 2019-03-22 2019-03-21 2019-03-25 2019-07-19 consultant en sauvegarde management Selection sociale pour appui au screening des microprojets TG-ANADEB-107034-CS- INDV / Consultant screening Component 3:Capacity Individual environnemental: IDA / D1740 building and project Post Consultant Limited 4,500.00 5,406.68 Signed 2019-02-15 2019-02-02 2019-03-02 2019-03-02 2019-03-09 2019-03-22 2019-03-21 2019-03-25 2019-07-19 Recrutement d'un consultant management Selection en sauvegarde environnemantale pour appui au screening des microprojets TG-ANADEB-107035-CS- INDV / Spécialiste Sauvegarde Component 3:Capacity Individual Sociale: Recrutement d'un IDA / D1740 building and project Post Consultant Open 20,000.00 25,851.36 Signed 2019-03-28 2019-03-27 2019-05-01 2019-09-17 2019-05-15 2019-09-18 2019-06-12 2019-10-03 2020-06-06 Spécialiste en sauvegarde management Selection sociale pour le compte de l'unité de gestion du projet TG-ANADEB-127084-CS- INDV / Filets Sociaux RS: Recrutement d'un(e) Assistant Component 3:Capacity Individual régional en transfert IDA / D1740 building and project Post Consultant Open 14,000.00 1,392.45 Signed 2019-08-20 2019-09-25 2019-09-15 2020-02-11 2019-09-22 2020-02-14 2019-10-02 2020-03-02 2020-09-26 monétaire/ cantines scolaires management Selection pour le compte du projet au profit de l'antenne régionale Maritime de l'ANADEB TG-ANADEB-132921-CS- INDV / Comptable RM: Recrutement d'un Comptable Component 3:Capacity Individual gestionnaire pour le compte IDA / D1740 building and project Post Consultant Open 16,000.00 15,469.15 Signed 2019-09-16 2019-10-01 2019-10-20 2020-02-10 2019-10-27 2020-02-14 2019-11-10 2020-03-02 2020-11-04 du projet au profit de management Selection l'antenne régionale Maritime de l'ANADEB TG-ANADEB-132923-CS- INDV / Audit institutionnel Component 3:Capacity Individual ANADEB: Recrutement d'un IDA / D1740 building and project Post Consultant Open 25,000.00 0.00 Canceled 2019-09-30 2019-11-03 2019-11-24 2019-12-29 2020-02-27 consultant individuel pour management Selection l’audit organisationnel et institutionnel de l’ANADEB TG-ANADEB-123267-CS- CDS / Mission de recours INSEED: Contractualisation avec l'INSEED pour la gestion Component 3:Capacity des recours liés aux listes des IDA / D1740 building and project Post Direct Selection Direct 171,500.00 0.00 Canceled 2019-07-17 2019-07-27 2019-09-30 2020-03-28 ménages bénéficiaires des management transferts monétaires et la sélection de nouveaux ménages bénéficiaires TG-ANADEB-143903-CS- INDV / Consultant social RM: Recrutement d'un consultant social junior pour le suivi de mise en œuvre des mesures Component 3:Capacity Individual de sauvegardes IDA / D1740 building and project Post Consultant Open 10,000.00 6,134.83 Signed 2019-11-15 2020-01-08 2019-12-25 2020-07-21 2020-01-15 2020-07-24 2020-02-19 2020-08-14 2021-02-13 environnementale et sociale management Selection dans le cadre des sous- projets communautaires des projets FSB et EJV dans la région maritime TG-ANADEB-143904-CS- INDV / Consultant social RP: Recrutement d'un consultant social junior pour le suivi de mise en œuvre des mesures Component 3:Capacity Individual de sauvegardes IDA / D1740 building and project Post Consultant Open 10,000.00 6,166.28 Signed 2019-11-15 2020-01-08 2019-12-25 2020-07-21 2020-01-15 2020-07-24 2020-02-19 2020-08-14 2021-02-13 environnementale et sociale management Selection dans le cadre des sous- projets communautaires des projets FSB et EJV dans la région des Plateaux TG-ANADEB-143905-CS- INDV / Consultant social RC: Recrutement d'un consultant social junior pour le suivi de mise en œuvre des mesures Component 3:Capacity Individual de sauvegardes IDA / D1740 building and project Post Consultant Open 10,000.00 6,163.01 Signed 2019-11-15 2020-01-08 2019-12-25 2020-07-21 2020-01-15 2020-07-24 2020-02-19 2020-08-14 2021-02-13 environnementale et sociale management Selection dans le cadre des sous- projets communautaires des projets FSB et EJV dans la région Centrale Page 7 TG-ANADEB-143906-CS- INDV / Consultant social RK: Recrutement d'un consultant social junior pour le suivi de mise en œuvre des mesures Component 3:Capacity Individual de sauvegardes IDA / D1740 building and project Post Consultant Open 10,000.00 6,163.01 Signed 2019-11-15 2020-01-08 2019-12-25 2020-07-21 2020-01-15 2020-07-24 2020-02-19 2020-08-14 2021-02-13 environnementale et sociale management Selection dans le cadre des sous- projets communautaires des projets FSB et EJV dans la région Kara TG-ANADEB-143907-CS- INDV / Consultant social RS: Recrutement d'un consultant social junior pour le suivi de mise en œuvre des mesures Component 3:Capacity Individual de sauvegardes IDA / D1740 building and project Post Consultant Open 10,000.00 6,163.01 Signed 2019-11-15 2020-01-08 2019-12-25 2020-07-21 2020-01-15 2020-08-07 2020-02-19 2020-08-14 2021-02-13 environnementale et sociale management Selection dans le cadre des sous- projets communautaires des projets FSB et EJV dans la région des Savanes TG-ANADEB-150059-CS- INDV / Audit institutionnel ANADEB: Recrutement d'un consultant individuel pour l'audit institutionnel t Component 3:Capacity Individual organisationnel de l'Agence IDA / D1740 building and project Post Consultant Limited 40,000.00 74,345.00 Signed 2020-01-03 2019-12-17 2020-01-18 2020-01-09 2020-02-08 2020-06-09 2020-03-07 2020-08-26 2020-05-06 nationale d'appui au management Selection développement à la base (ANADEB) en charge de la mise en œuvre des projets FSB et EJV TG-ANADEB-101636-CS- INDV / Audit marchés Component 3:Capacity Individual communautaires: IDA / D1740 building and project Post Consultant Open 35,000.00 22,778.29 Signed 2020-04-30 2020-06-23 2020-07-13 2020-11-24 2020-08-03 2021-01-25 2020-09-07 2021-03-11 2020-11-06 Recrutement d'un consultant management Selection pour l'audit des marchés communautaires TG-ANADEB-165419-CS- Component 3:Capacity Individual INDV / Gestionnaire RSU: IDA / D1740 building and project Post Consultant Open 20,000.00 0.00 Canceled 2020-04-30 2020-04-30 2020-06-18 2020-07-02 2020-08-06 2021-08-01 Recrutement d'un management Selection gestionnaire du Registre Social Unifié (RSU) TG-ANADEB-194529-CS- INDV / Collaboration élus locaux ANADEB: Recrutement Component 3:Capacity Individual d'un (01) Consultant pour IDA / D1740 building and project Post Consultant Limited 10,000.00 26,594.34 Signed 2020-09-25 2020-09-30 2020-09-30 2020-10-02 2020-10-15 2020-12-01 2020-11-19 2020-12-18 2020-12-19 l'élaboration de la stratégie de management Selection collaboration entre l'ANADEB et les élus locaux TG-ANADEB-165416-CS- INDV / Audit environnemental et social : Recrutement d'un consultant pour l'Audit Component 3:Capacity Individual Under environnemental et social des IDA / D1740 building and project Post Consultant Open 35,000.00 0.00 2020-11-30 2020-11-24 2021-01-18 2021-02-08 2021-03-15 2021-05-14 Implementation infrastructures management Selection sociocommunautaires réalisées dans le cadre du projet TG-ANADEB-165404-CS- INDV / Audit technique des INFRA: Recrutement d'un Component 3:Capacity Individual consultant pour l'audit Under IDA / D1740 building and project Post Consultant Open 35,000.00 0.00 2020-12-15 2020-10-07 2021-02-02 2021-03-24 2021-02-23 2021-03-30 2021-05-29 technique des ouvrages Implementation management Selection sociocommunauataires réalisés dans le cadre du projet TG-ANADEB-209693-CS- INDV / Financements Component 3:Capacity Individual innovants Cantines: Sélection Under IDA / D1740 building and project Post Consultant Open 42,000.00 0.00 2020-12-31 2020-12-21 2021-02-18 2021-03-11 2021-04-15 2021-07-14 d'un cabinet pour l'étude sur Implementation management Selection les financements innovants des cantines scolaires TG-ANADEB-211871-CS- INDV / PROTECTION SOCIALE: Recrutement d’un consultant Component 3:Capacity Individual Under international pour le IDA / D1740 building and project Post Consultant Limited 60,000.00 0.00 2021-01-15 2021-01-06 2021-01-22 2021-02-03 2021-02-12 2021-03-19 2021-09-15 Implementation développement du management Selection programme de protection sociale du gouvernement TG-ANADEB-224313-CS- INDV / CGES _projet Cohésion sociale :recrutement d'un consultant pour l'élaboration Component 3:Capacity Individual du Cadre de Gestion Under IDA / D1740 building and project Post Consultant Limited 35,000.00 0.00 2021-03-25 2021-06-02 2021-04-01 2021-04-22 2021-05-27 2021-06-26 Environnementale et Sociale Implementation management Selection (CGES) intégrant le Plan de Gestion des Pestes et Pesticides (PGPP) du Projet de cohésion sociale (P175043) TG-ANADEB-224318-CS- INDV / CPR_projet Cohésion sociale: Recrutement d'un consultant pour l'élaboration Component 3:Capacity Individual Under du Cadre de Politique de IDA / D1740 building and project Post Consultant Limited 25,000.00 0.00 2021-03-30 2021-06-02 2021-04-06 2021-04-27 2021-06-01 2021-06-26 Implementation Réinstallation (CPR) du Projet management Selection de cohésion sociale pour les régions défavorisées du Golfe de Guinée (P175043) TG-ANADEB-224319-CS- INDV / PGMO_projet Cohésion sociale: Recrutement d'un consultant pour l'élaboration Component 3:Capacity Individual Under du Plan de Gestion de la Main IDA / D1740 building and project Post Consultant Limited 20,000.00 0.00 2021-03-30 2021-06-02 2021-04-06 2021-04-27 2021-06-01 2021-06-26 Implementation d’œuvre (PGMO) du Projet de management Selection cohésion sociale pour les régions défavorisées du Golfe de Guinée (P175043) Page 8 ANDHRA PRADESH INTEGRATED IRRIGATION AND AGRICULTURE TRANSFORMATION PROJECT Procurement Methods Procurement Approaches and Thresholds (US$ Equivalent) Methods Open international (goods, IT, and non- >3 million consulting services) Open national (goods, IT, and non- >100,000 and up to 3 million consulting services) National request for quotation Up to 100,000 (goods/works) Open international (works) >40 million Open national (works) >100,000 and up to 40 million Direct selection No threshold; For goods/works/non-consulting services: According to paragraphs 6.8–6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Framework Agreements For goods, works, and non-consulting services: According to paragraphs 6.57–6.59 of the Regulations Shortlist of national consultants Up to 800,000 1. Procurement prior-review thresholds based on the Moderate rating. The World Bank requires its prior review of the following types of contract: (a) Works: All contracts more than US$15 million equivalent (b) Goods and IT: All contracts more than US$4 million equivalent (c) Non-consulting services: All contracts more than US$4 million equivalent (d) Consultants: All contracts more than US$2 million equivalent for firms and US$400,000 equivalent for individuals (e) Direct selection: Justification of DS for all contracts more than US$100,000 equivalent 2. National procurement procedure conditions. National competition for the procurement of goods, works, and non-consulting services will be within the thresholds and will comply with the Procurement Provisions of paragraphs 5.3–5.6 of Section V of the Regulations and the following additional provisions: (a) Only the model bidding documents agreed with the World Bank (as amended from time to time) will be used for bidding. (b) At least 30 days before the deadline for submission of bids, invitations to bid will be advertised in at least one widely circulated national daily newspaper, or on a widely-used website or electronic portal with free national and international access inan abridged version of the advertisement published in a widely circulated national daily, giving details of the electronic portal where the full invitation to bid can be downloaded. (c) No preference will be accorded to any bidder for price or for other terms when competing with foreign bidders, state-owned enterprises, small- scale enterprises, or enterprises from a given state. (d) Extension of bid validity will not be allowed for contracts subject to World Bank prior review without prior World Bank concurrence (i) for the first request for an extension longer than four weeks and (ii) for all subsequent requests for extension whatever the length; concurrence will be considered only in cases of force majeure and other circumstances beyond the control of the purchaser employer. (e) There will be no re-bidding of contracts subject to World Bank prior review without prior World Bank concurrence. In this project, bids will not be rejected for being outside a predetermined range of prices. (f) To improve the efficiency and transparency of small-value purchases in WB-financed projects, the Bank has agreed to allow the following uses of Government e-Marketplace (GeM): (i) in lieu of shopping, up to US$30,000 in catalog mode; (ii) in lieu of shopping, up to US$100,000 if there are at least three suppliers for the item on GeM and the purchaser uses the GeM Request for Quotation feature (mini-competition) to discover the final price; (iii) in both cases, borrowers will record their assessment that the price is reasonable, and (iv) GeM is not to be used in lieu of National Competitive Bidding. (g) No negotiations are to be conducted even with the lowest evaluated responsive bidders. Domestic preference. Domestic preference will be applied in evaluating bids in accordance with Annex VI of the Regulations. PROCUREMENT India : AP Integrated Irrigation & Agriculture Transformation Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2020-09-23 2021-05-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160463 GPN Date: Project Name: AP Integrated Irrigation & Agriculture Transformation Project Loan / Credit No: IBRD / 89100 Irrigation Circle, Ananthapuramu Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-ICANTPAPIIATP-194144- CW-RFB / Rehabilitation of Component A: Improving Under Sreedhargatta MI tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 97,853.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-10-20 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Envelope 31 Efficiency ion Sreedhargatta (V) in Bommanahal (M) in Ananthapuramu District IN-ICANTPAPIIATP-194155- CW-RFB / Rehabilitation of Component A: Improving Apparas Cheruvu Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 304,448.00 0.00 Canceled 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 (Independent) in Apparas Envelope 31 Efficiency Cheruvu (V) in Bathalapalli (M) in Ananthapuramu District IN-ICANTPAPIIATP-194162- CW-RFB / Rehabilitation of Component A: Improving Under Hariyani cheruvu Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 148,466.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Hariyani Envelope 31 Efficiency ion cheruvu (V) in C.K.Palli (M) in Ananthapuramu District IN-ICANTPAPIIATP-194231- CW-RFB / Rehabilitation of Component A: Improving Under Madigubba MI tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 146,166.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Madigubba Envelope 31 Efficiency ion (V) in Atmakur (M) in Ananthapuramu District IN-ICANTPAPIIATP-194267- CW-RFB / Rehabilitation of Component A: Improving Under Gunipalli tank (Independent) Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 128,374.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 in Gunipalli (V) in Envelope 31 Efficiency ion Bukkapatnam (M) in Ananthapuramu District IN-ICANTPAPIIATP-194273- CW-RFB / Rehabilitation of Component A: Improving Under Jambuladinne tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 192,178.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Envelope 31 Efficiency ion Jambuladinne (V) in Garladinne (M) in Ananthapuramu District IN-ICANTPAPIIATP-194276- CW-RFB / Rehabilitation of Component A: Improving Under Kandukuru chowti tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 168,252.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Kandukuru Envelope 31 Efficiency ion (V) in Ananthapuramu(M) & District IN-ICANTPAPIIATP-194277- CW-RFB / Rehabilitation of Component A: Improving Under Single Stage - One 2021-07- Budili MI tank (Independent) IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 88,037.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Envelope 31 in Budili (V) in Gorantla (M) Efficiency ion in Ananthapuramu District IN-ICANTPAPIIATP-194280- CW-RFB / Rehabilitation of Component A: Improving Under Single Stage - One 2021-07- Pulakunta tank (Independent) IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 89,877.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Envelope 31 in Pulakunta (V) in Hindupur Efficiency ion (M) in Ananthapuramu District IN-ICANTPAPIIATP-194282- CW-RFB / Rehabilitation of Component A: Improving Under Kasaba MI tank( Kodur MI Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 160,276.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 tank) (Independent) in Kodur Envelope 31 Efficiency ion (V) in Chilamathur (M) in Ananthapuramu District IN-ICANTPAPIIATP-194287- CW-RFB / Rehabilitation of Budidhagaddapalli tank Component A: Improving Under Single Stage - One 2021-07- (Independent) in IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 127,301.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Envelope 31 Budidhagaddapalli (V) in Efficiency ion Gorantla (M) in Ananthapuramu District IN-ICANTPAPIIATP-194290- CW-RFB / Rehabilitation of Component A: Improving Under Gorantla Big tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 180,368.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Gorantla (V) Envelope 31 Efficiency ion in Gorantla (M) in Ananthapuramu District IN-ICANTPAPIIATP-194293- CW-RFB / Rehabilitation of Component A: Improving Under Grandham vani cheruvu Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 66,258.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Cascade No.12 in Envelope 31 Efficiency ion Bandameeda palli(V) in Gandlapenta (M) in Ananthapuramu District IN-ICANTPAPIIATP-194335- CW-RFB / Rehabilitation of Component A: Improving Under Nyamaddala MI tank Single Stage - One 2021-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 217,638.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 (Independent) in Nyamaddala Envelope 31 Efficiency ion (V) in C.K.Palli (M) in Ananthapuramu District Page 1 IN-ICANTPAPIIATP-194345- CW-RFB / Rehabilitation of Component A: Improving Under Single Stage - One 2021-07- Yerra cheruvu (Independent) IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 123,160.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Envelope 31 in Kanumukkala (V) in Efficiency ion C.K.Palli (M) in Ananthapuramu District IN-ICANTPAPIIATP-194352- CW-RFB / Rehabilitation of Ammagari Cheruvu Component A: Improving Under Single Stage - One 2021-07- (Independent) in IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 112,883.00 0.00 Implementat 2020-10-12 2020-10-12 2020-10-17 2020-11-28 2020-11-19 2020-12-28 2021-03-15 2021-02-01 Envelope 31 Santhekondapuram (V) in Efficiency ion Bramhasamudram (M) in Ananthapuramu District IN-ICANTPAPIIATP-225829- CW-RFB / Rehabilitation of Santhekondapuram MI tank Component A: Improving Pending Single Stage - One 2022-01- Cascade No-32 in IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 313,804.00 0.00 Implementat 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 Envelope 29 Santhekondapuram (V) in Efficiency ion Brahmasamudram (M) in Ananthapuramu (dist) IN-ICANTPAPIIATP-225974- CW-RFB / Rehabilitation of Component A: Improving Pending Bachupalli MI tank Cascade Single Stage - One 2022-01- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 328,221.00 0.00 Implementat 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 No-29 in Bachupalli (V) in Envelope 29 Efficiency ion Gooty (M) in Ananthapuramu (dist) IN-ICANTPAPIIATP-225978- CW-RFB / Rehabilitation of Component A: Improving Pending Single Stage - One 2022-01- B.Yaleru MI tank IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 618,712.00 0.00 Implementat 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 Envelope 29 (Independent) in B.Yaleru (V) Efficiency ion in Atmakur (M) in Ananthapuramu District IN-ICANTPAPIIATP-225987- CW-RFB / Rehabilitation of Component A: Improving Pending Nidragatta MI tank Single Stage - One 2022-01- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 410,276.00 0.00 Implementat 2021-04-12 2021-04-17 2021-05-29 2021-06-28 2021-08-02 (Independent) in Nidragatta Envelope 29 Efficiency ion (V) in Amarapuram (M) in Ananthapuramu District IN-ICANTPAPIIATP-236484- National CW-RFB / Rehabilitation of Component A: Improving Procurement Pending Apparas Cheruvu Single Stage - One 2022-09- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National Document - 1 304,448.00 0.00 Implementat 2021-06-07 2021-06-12 2021-07-24 2021-08-23 2021-09-27 (Independent) in Apparas Envelope 26 Efficiency Envelope process ion Cheruvu (V) in Bathalapalli (Non Bank-SPD) (M) in Ananthapuramu District GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 RÉPUBLIQUE GABONAISE (Union-Travail-Justice) MINISTÈRE DE L’ÉCONOMIE ET DES FINANCES COMMISSION NATIONALE DES TIPPEE SECRETARIAT PERMANENT PROJET DE PREPARATION STRATEGIQUE ET DE RIPOSTE AU COVID-19 Financement : BIRD | ID : P173927 PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : P173927 - Projet de Préparation et de riposte Stratégiques au COVID-19 (PPRS) du Gabon Agence d’exécution du Projet : Commission Nationale des Travaux d’Intérêt Public pour la Promotion de l’Entreprenariat et l’Emploi (CNTIPPEE) Date du plan de passation des marchés : 07 mai 2020 Période couverte par ce plan de passation des marchés : mai 2020 à avril 2021 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) révisé en Novembre 2017 puis en Août 2018 (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans le Code des Marchés Publics, Décret n°00027/PR/MEPPDD du 17 janvier 2018, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : a. publication de l'appel d’offres/à propositions au niveau national ; b. les entreprises éligibles de tout pays peuvent concourir ; c. le dossier d'appel d'offres/à propositions oblige le Soumissionnaire/Proposant présentant une Offre/Proposition à déposer un agrément signé qui sera joint à tout contrat éventuel, pour confirmer qu'il applique et respecte les Directives de la Banque pour la lutte contre la corruption y compris sans limitation. Le droit de la Banque de sanctionner et les droits de la Banque pour l'inspection et l'audit ; d. les marchés doivent comporter une répartition appropriée des attributions, risques et responsabilités ; e. la publication des informations relatives à l'attribution du marché ; f.les droits de la Banque d’examiner le dossier et les activités de passation des marchés ; g. l'existence d'un mécanisme efficace d'examen des plaintes ; et h. la gestion et l'archivage des dossiers relatifs au Processus de la Passation des Marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. Sans objet. Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. Sans objet. Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés. Travaux ne s’applique pas/s’applique pour les contrats indiqués dans les tableaux du Plan de passation des marchés. L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés s’applique : 3.10La Banque peut accepter d'apporter une assistance directe à la mise œuvre des activités de passation des marchés lorsqu'elle juge que ('Emprunteur/le bénéficiaire ou, le cas échéant, le pays membre : a. est dans un besoin urgent d'assistance en raison d'une catastrophe d'origine naturelle ou humaine, ou d'un conflit ; ou b. se heurte à des problèmes de capacités du fait de sa fragilité ou de vulnérabilités particulières (petits Etats, par exemple). 3.11La Banque détermine, au cas par cas, le champ et la nature de cet appui. Celui-ci ne l'amène pas à exécuter les opérations de passation des marchés en lieu et place de l'Emprunteur, qui reste responsable de l'exécution du projet. Autres informations pertinentes sur la passation des marchés : Sans objet. Approche du Montant % Date de Catégorie marché/ estimé financ démarrage Numéro Compétition Méthode de Type de prévue de é par Description de passation de (Dollars revue passation la Référence marché US) (jj/mm/aaaa) de marché Banqu e Fournitures GA-CN TIPPEE-169285-GO-UN / Acquisition équipement de protection, test/équipement de laboratoire, Go-Ref 1 GO Direct UN 6 300 000,00 100 Post 2020/05/25 ambulances médicalisées, formation personnel de santé – réponse au COVID19 GA-CN TIPPEE-172487-GO-DIR / Fourniture d’internet et téléphonie Go-Ref 2 GO Direct DIR 10 000,00 100 Post 2020/06/20 mobile Services de consultants GA-CN TIPPEE-172488-CS-QCBS / Open - Auditeur comptable et financier CS-Ref 1 CS QCBS 60 000,00 100 Post 2020/12/23 International 2020,2021 et clôture GA-CN TIPPEE-172490-CS-CDS / Audit CS-Ref 2 CS Direct CDS 130 000,00 100 Post 2020/07/20 global réponse au COVID19 CS-Ref 3 CS Non-consulting Services GA-CN TIPPEE-172653-NC-RFQ / NC-Ref 3 NC CF RFQ 50 000,00 Post 2020/06/27 Logistique, transporteur et dispatching PROCUREMENT Gabon : GABON COVID-19 Strategic Preparedness and Response Project (SPRP) PLAN General Information Country: Gabon Bank’s Approval Date of the Original Procurement Plan: 2020-05-07 2021-06-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173927 GPN Date: Project Name: GABON COVID-19 Strategic Preparedness and Response Project (SPRP) Loan / Credit No: IBRD / 91240 COMMISSION NATIONALE DES TIPPEE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GA-CN TIPPEE-169285-GO- UN / Acquisition équipement de protection, test/équipement de Component 1: Emergency UN Agencies IBRD / 91240 Post Direct 6,300,000.00 6,240,052.49 Signed 2020-05-08 2020-05-17 2020-05-13 2020-05-22 2020-05-25 2020-05-25 2020-11-21 laboratoire, ambulances COVID-19 Response (Direct) médicalisées, formation personnel de santé – réponse au COVID19 GA-CN TIPPEE-172487-GO- Component 3: Project Under DIR / Fourniture d’internet et IBRD / 91240 Implementation and Post Direct Selection Direct 10,000.00 0.00 Implementati 2020-11-02 2020-11-03 2020-11-07 2020-12-12 2021-06-10 téléphonie mobile Monitoring on GA-CN TIPPEE-195897-GO- Component 2: Supporting Request for Single Stage - One RFQ / Acquisition de IBRD / 91240 National and Sub-national, Post Limited 410,000.00 355,982.96 Signed 2020-09-25 2020-09-25 2020-10-09 2020-10-15 2021-04-07 Quotations Envelope consommables médicaux Prevention and Preparedness GA-CN TIPPEE-195892-GO- Component 2: Supporting RFQ / Acquisition de Request for Single Stage - One IBRD / 91240 National and Sub-national, Post Limited 1,000,000.00 1,430,295.74 Signed 2020-09-26 2020-09-25 2020-10-17 2020-10-15 2021-04-15 médicaments et autres Quotations Envelope Prevention and Preparedness produits de santé GA-CN TIPPEE-195903-GO- Component 3: Project RFQ / Acquisition Matériel Request for Single Stage - One IBRD / 91240 Implementation and Post Limited 17,000.00 47,112.35 Signed 2020-09-30 2020-11-02 2020-10-12 2020-11-11 2020-12-11 Informatique pour la Cellule Quotations Envelope Monitoring FINEX GA-CN TIPPEE-195905-GO- RFQ / Acquisition de quatre Component 3: Project Request for Single Stage - One (4) Véhicules pour les activités IBRD / 91240 Implementation and Post Limited 150,000.00 0.00 Canceled 2020-09-25 2020-10-15 2020-12-14 Quotations Envelope de la Cellule de Suivi Monitoring Evaluation du COPIL GA-CN TIPPEE-195902-GO- Component 3: Project RFQ / Acquisition Matériel Request for Single Stage - One IBRD / 91240 Implementation and Post Limited 26,000.00 118,965.89 Signed 2020-11-08 2020-12-09 2020-11-28 2021-03-25 2021-01-27 Informatique pour la Cellule Quotations Envelope Monitoring de Suivi Evaluation du COPIL GA-CN TIPPEE-201737-GO- Component 3: Project Under DIR / Fourniture de carburant IBRD / 91240 Implementation and Post Direct Selection Direct 11,000.00 0.00 Implementati 2020-11-02 2020-11-03 2020-11-04 2020-11-12 2021-05-11 à l'UCP Monitoring on GA-CN TIPPEE-201726-GO- DIR / Acquisition de six (6) Component 3: Project Véhicules pour les activités de IBRD / 91240 Implementation and Post Direct Selection Direct 166,000.00 269,845.50 Completed 2020-11-05 2020-11-03 2020-11-07 2020-11-09 2020-11-10 2020-11-11 2021-01-09 2021-01-08 la Cellule de Suivi Evaluation Monitoring du COPIL et la Cellule FINEX GA-CN TIPPEE-238804-GO- Component 3: Project Pending DIR / Fourniture du carburant IBRD / 91240 Implementation and Post Direct Selection Direct 5,600.00 0.00 Implementati 2021-06-08 2021-06-09 2021-06-11 2021-12-08 à la Cellule Finex Monitoring on GA-CN TIPPEE-238917-GO- Component 3: Project Pending RFQ / Fourniture des outils de Request for Single Stage - One IBRD / 91240 Implementation and Post Limited 10,000.00 0.00 Implementati 2021-06-23 2021-07-14 2021-07-23 communication pour le PPRS Quotations Envelope Monitoring on COVID-19 NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GA-CN TIPPEE-172653-NC- Pending Component 1: Emergency Request for Single Stage - One RFQ / Logistique, transporteur IBRD / 91240 Post Limited 50,000.00 0.00 Implementati 2020-12-03 2021-01-03 2021-07-02 COVID-19 Response Quotations Envelope et dispatching on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GA-CN TIPPEE-172488-CS- Component 3: Project Quality And Cost- Under QCBS / Auditeur comptable et IBRD / 91240 Implementation and Post Open - National 60,000.00 0.00 2020-11-10 2021-04-10 2020-11-17 2020-12-08 2021-01-07 2021-01-14 2021-01-28 2021-02-09 2022-02-09 Based Selection Implementation financier 2020,2021 et clôture Monitoring GA-CN TIPPEE-183997-CS- Component 3: Project Quality And Cost- Pending QCBS / Audit global réponse IBRD / 91240 Implementation and Post Open - National 130,000.00 0.00 2021-08-02 2021-08-09 2021-09-22 2021-10-22 2021-10-29 2021-11-12 2021-11-24 2022-03-24 Based Selection Implementation au COVID19 Monitoring Page 1 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GA-CN TIPPEE-183699-CS- INDV / Recrutement d’un Component 3: Project Individual Consultant Individuel pour IBRD / 91240 Implementation and Post Consultant Limited 85,000.00 48,528.74 Signed 2020-07-15 2020-07-13 2020-07-18 2020-07-15 2020-07-22 2020-08-19 2020-07-26 2020-08-20 2020-09-24 l’élaboration d’un Cadre de Monitoring Selection Gestion environnementale et Sociale GA-CN TIPPEE-195898-CS- Component 3: Project Individual INDV / Recrutement d’un IBRD / 91240 Implementation and Post Consultant Open 32,000.00 0.00 Canceled 2020-11-21 2020-12-17 2020-12-19 2020-12-22 2021-12-17 Comptable pour le projet Monitoring Selection COVID-19 GA-CN TIPPEE-195900-CS- INDV / Recrutemnt d’un Component 3: Project Individual Expert pour le suivi IBRD / 91240 Implementation and Post Consultant Limited 26,000.00 22,257.24 Signed 2020-11-24 2021-01-14 2020-12-01 2021-02-04 2020-12-06 2021-05-10 2020-12-09 2021-05-10 2021-06-07 épidémiologique pour la Monitoring Selection Risposte au COVID-19 GA-CN TIPPEE-222184-CS- Component 3: Project CDS / Recrutement d’une Pending IBRD / 91240 Implementation and Post Direct Selection Direct 30,000.00 0.00 2021-12-01 2021-12-04 2021-12-07 2022-06-05 Assistante de Direction pour Implementation Monitoring le projet COVID-19 GA-CN TIPPEE-238900-CS- Component 3: Project Individual INDV / Recrutement d’un Pending IBRD / 91240 Implementation and Post Consultant Limited 35,000.00 0.00 2021-06-09 2021-06-10 2021-06-11 2021-06-13 2021-08-12 Auditeur Environnemental et Implementation Monitoring Selection Social GA-CN TIPPEE-238904-CS- Component 3: Project Individual INDV / Recrutement d’un Pending IBRD / 91240 Implementation and Post Consultant Limited 30,000.00 0.00 2021-06-10 2021-06-12 2021-06-14 2021-06-18 2021-12-15 spécialiste environnemental Implementation Monitoring Selection pour le projet GA-CN TIPPEE-238906-CS- INDV / Recrutement d’un consultant Spécialiste en Component 3: Project Individual Élaboration de la Stratégie de Pending IBRD / 91240 Implementation and Post Consultant Direct 25,000.00 0.00 2021-06-09 2021-06-11 2021-06-12 2021-06-14 2021-09-12 Passation de Marchés pour Implementation Monitoring Selection promouvoir le Développement (PPSD) pour le projet PPRS - P173927 GA-CN TIPPEE-238915-CS- Component 3: Project Individual INDV / Recrutement d’un Pending IBRD / 91240 Implementation and Post Consultant Open 65,000.00 0.00 2021-06-10 2021-06-17 2021-06-19 2021-06-21 2022-05-27 Auditeur Interne pour les Implementation Monitoring Selection projets de la CN-TIPPEE Page 2