Procurement Plan National Community Driven Development Project Department of Rural Development I. General 1. Bank’s approval Date of the procurement Plan: November 13, 2012 2. Procurement Plan Update Version: 8th Version 3. Date of General Procurement Notice: Nov 8, 2012 4. Period covered by this procurement plan: 12 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement (US $ ) Works (Including turnkey supply and installation of 2,000,000 plant and equipment and PPP) ( 2 million) Goods, information technology and non- 1,000,000 consulting services ( 1million) Consultant firms 300,000 Consultant Individuals 200,000 Type of Market Approaches Thresholds Procurement (US $ in million) Internation National- National Comments al Open RFQ (Shopping ) Works (Including 3 and Less than 3 Less than Recommended to turnkey supply above 1 advertise for 7 days and installation of for RFQ above 0.5 plant and equipment and PPP) Goods, 1 and Less than 1 Less than Recommended to information above 0.5 advertise for 7 days technology and for RFQ above 0.05 non-consulting services Consultants 0.1 and Less than Not CQS method may (Firms) above 0.1 applicable be used up to 0.5. July 9, 2010 Use of full RFP mandatory for CQS above 0.3. Limits on market approaches do not apply to individual consultants. 2. Reference to (if any) Project Operational Manual (POM): is under preparation and to be acceptable to the World Bank. 3. Any Other Special Procurement Arrangements: N/A 4. Summary of the Procurement Packages (Goods, Works and Non-Consulting Services) planned for 12 months 1 2 3 4 5 6 7 Ref. Description Estimated Pack Dome Review Commen No. Cost ages stic by Bank ts US$ Prefer (Prior / million ence Post) (yes/n o) 3 Summary of 3.5 25 No Prior and Shopping Post (Goods) 4 Summary of 0.5 5 No Prior and Direct Post Contracting (Goods) 6 Summary of 1 7 No Post Shopping (Works) 4. Summary of consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimat Packag Review Comments No. Assignment ed es by Bank Cost (Prior / US$ Post) million 1 Summary of 4.4 4 Prior number of contracts that will be let under QBS July 9, 2010 2 Summary of 3.4 20 Prior/Po CQS and number of st Individual contracts that will Consultan be let under other t methods selection 3 Summary of 13.2 12 Prior number of contracts that will be amendment of existing contract/ Single Source Selection July 9, 2010 PROCUREMENT Myanmar : Myanmar National Community Driven Development Project PLAN General Information Country: Myanmar Bank’s Approval Date of the Original Procurement Plan: 2017-09-11 2020-12-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132500 GPN Date: Project Name: Myanmar National Community Driven Development Project Loan / Credit No: IDA / H8140, IDA / 56870 Department of Rural Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Under W3 / GARAGE for NEW OFFICE Request for Single Stage - One 2019-12- IDA / H8140 Implementation Support Post Open - National 50,000.00 0.00 Implementat 2019-05-05 2019-06-30 BUILDING Quotations Envelope 27 ion Under W4 / WAREHOUSE for NEW Request for Single Stage - One 2020-01- IDA / H8140 Implementation Support Post Open - National 100,000.00 0.00 Implementat 2019-05-28 2019-07-23 OFFICE BUILDING Quotations Envelope 19 ion W7 / REHABILITATION of THE Pending Request for Single Stage - One 2019-12- YANGON WAREHOUSE IDA / H8140 Implementation Support Post Open - National 120,000.00 0.00 Implementat 2019-05-05 2019-06-30 Quotations Envelope 27 COMPLEX 2 units ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G 45 / VEHICLES and MOTORCYCLES (HGC) for IDA / H8140 Community Block Grants Prior Direct Selection Direct 1,865,000.00 2,083,297.00 Signed 2016-07-28 TOWNSHIPS and REGIONAL OFFICES G53 / COMMUNICATION Request for IDA / H8140 Community Block Grants Prior Open - International 216,615.00 152,002.77 Canceled MATERIAL: VINYL POSTERS Quotations G80 / TABLET COMPUTERS Single Stage - One IDA / H8140 Community Block Grants Prior Request for Bids Open - International 669,375.00 700,875.00 Signed 2017-04-05 2017-05-09 for 17 TOWNSHIPS (2017- Envelope 2018) G-59 / Communication Request for IDA / H8140 Community Block Grants Prior Open - International 454,080.00 405,405.30 Signed 2017-05-19 Materials: T-shirts and Caps Quotations G16(a)(b), G17(b) / Motor Vehicle: Double cabs pickup, IDA / H8140 Community Block Grants Prior Direct Selection Direct 987,500.00 1,005,521.50 Signed 2015-09-10 land cruiser double cab, Motorcycle 125 cc G95 / ELECTRIC CURRENT Request for Single Stage - One STABILIZERS for 16 new IDA / H8140 Implementation Support Post Open - National 48,000.00 41,342.22 Completed 2017-12-10 2018-02-04 2018-04-11 2018-08-03 2018-08-03 Quotations Envelope townships G96 / DESKTOP and LAPTOP COMPUTERS and HARD DISK Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 371,700.00 299,708.92 Completed 2018-01-15 2018-03-12 2018-04-03 2018-09-08 2018-07-26 DRIVES for the UNION and 16 Quotations Envelope new townships Pending G92B / 30 SEATER BUSSES IDA / H8140 Implementation Support Post Direct Selection Direct 133,475.00 0.00 Implementati 2017-12-29 2018-01-03 2018-02-07 2018-08-06 on Pending G93 / Seven BOATS for 16 Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 70,000.00 0.00 Implementati 2018-01-30 2018-03-27 2018-09-23 new townships Quotations Envelope on G97 / PRINTERS and PHOTO COPIERS and FAX-SCANNERS Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 67,650.00 62,555.10 Completed 2017-12-26 2018-02-20 2018-06-26 2018-08-19 2018-08-09 for the UNION and 16 new Quotations Envelope townships G98 / SUPPLY and INSTALLATION of a CCTV Pending Request for Single Stage - One SECURITY SYSTEM in the IDA / H8140 Implementation Support Post Open - National 30,000.00 0.00 Implementati 2018-02-23 2018-04-20 2018-10-17 Quotations Envelope YANGON and NAY PYI TAW on WAREHOUSES G99 / PROJECTOR and Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 16,000.00 14,133.86 Completed 2017-12-26 2018-02-20 2018-03-05 2018-08-19 2018-03-22 SCREEN for 16 new townships Quotations Envelope G100 / GSM PHONE HANDSET Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 12,250.00 6,850.17 Completed 2017-12-06 2018-01-31 2018-02-07 2018-07-30 2018-02-22 for 16 new townships Quotations Envelope G101 / CAMERAS and VIDEO Request for Single Stage - One CAMERAS for 16 new IDA / H8140 Implementation Support Post Open - National 32,600.00 29,527.33 Completed 2017-12-26 2018-02-20 2018-02-22 2018-08-19 2018-03-08 Quotations Envelope townships G102 / WATER COOLER and Request for Single Stage - One AIR CONDITIONERS for 16 new IDA / H8140 Implementation Support Post Open - National 29,500.00 15,245.70 Completed 2017-12-09 2018-02-03 2018-02-28 2018-08-02 2018-03-06 Quotations Envelope townships G103 / OFFICE FURNITURE Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 96,080.00 77,739.19 Completed 2017-12-09 2018-02-03 2018-02-09 2018-08-02 2018-02-16 for 16 new townships Quotations Envelope G104 / SAFETY EQUIPMENT MOTORCYCLE CRASH Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 97,920.00 92,811.80 Completed 2018-01-24 2018-03-21 2018-09-06 2018-09-17 2018-10-19 HELMETS for 16 new Quotations Envelope townships Page 1 G105 / SAFETY EQUIPMENT Request for Single Stage - One LIFE JACKETS for 16 new IDA / H8140 Implementation Support Post Open - National 60,000.00 35,202.24 Completed 2018-01-07 2018-03-04 2018-02-09 2018-08-31 2018-02-23 Quotations Envelope townships G107 / CONSUMABLES and USAGE SPARE PARTS for IDA / H8140 Implementation Support Post Direct Selection Direct 50,000.00 0.00 Canceled 2017-12-04 2017-12-09 2018-01-13 2018-07-12 PHOTOCOPIERS and PRINTERS G108 / MOTORCYCLES High Pending Ground Clerance including Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 171,478.00 0.00 Implementati 2017-12-20 2018-02-14 2018-08-13 SPARE PART KIT for 16 new Quotations Envelope on townships G110 / RAIN COATS with Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 60,900.00 24,865.47 Completed 2018-01-01 2018-02-26 2018-02-09 2018-08-25 2018-03-12 PROJECT LOGO Quotations Envelope G72 / WATER QUALITY Request for Single Stage - One TESTING KITS for 54 IDA / H8140 Implementation Support Post Open - National 270,000.00 316,797.69 Completed 2017-03-10 2017-05-05 2018-08-06 2017-11-01 2018-11-28 Quotations Envelope TOWNSHIPS G111 / NCDDP VINYL Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 265,608.00 158,872.93 Completed 2018-03-12 2018-05-07 2018-07-17 2018-11-03 2018-09-18 POSTERS Quotations Envelope G112 / TILES or PLAQUES or Request for Single Stage - One STONES with completed sub- IDA / H8140 Implementation Support Post Open - National 73,346.00 63,869.01 Completed 2018-01-24 2018-03-21 2018-05-09 2018-09-17 2018-01-01 Quotations Envelope project information G113 / T SHIRTS with NCDD Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 445,728.00 302,985.14 Completed 2018-01-24 2018-03-21 2018-06-29 2018-09-17 2018-10-19 Project Logo Quotations Envelope G114 / CAPS with NCDDP Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 166,800.00 145,434.53 Completed 2018-01-24 2018-03-21 2018-05-09 2018-09-17 2018-07-26 Logo Quotations Envelope Request for Single Stage - One G118 / GENDER BOOKLETS IDA / H8140 Implementation Support Post Open - National 43,500.00 23,673.40 Completed 2018-03-19 2018-05-14 2018-08-13 2018-11-10 2018-09-19 Quotations Envelope G119 / ENVIRONMENTAL Request for Single Stage - One CODE OF PRACTICES IDA / H8140 Implementation Support Post Open - National 4,750.00 6,905.37 Completed 2018-03-19 2018-05-14 2018-07-11 2018-11-10 2018-09-14 Quotations Envelope BOOKLETS G120 / GRIEVANCE Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 63,195.00 55,272.06 Completed 2018-04-02 2018-05-28 2018-10-10 2018-11-24 2019-01-07 SUGGESTION BOXES Quotations Envelope G121 / BROCHURES FOR Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 29,600.00 3,230.42 Completed 2018-03-19 2018-05-14 2018-07-17 2018-11-10 2018-08-31 UNION and TOWNSHIPS Quotations Envelope G109 / SPARE PARTS and Pending REPAIR KITS for IDA / H8140 Implementation Support Post Direct Selection Direct 385,000.00 0.00 Implementati 2018-02-23 2018-02-28 2018-04-04 2018-10-01 MOTORCYCLES High Ground on Clerance Pending G122 / VEHICLE SPARE PARTS IDA / H8140 Implementation Support Post Direct Selection Direct 121,380.00 0.00 Implementati 2018-02-28 2018-03-05 2018-04-09 2018-10-06 on G91B / 13 PICKUPS DOUBLE Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 468,000.00 0.00 Canceled 2018-01-03 2018-02-28 2018-08-27 CAB Quotations Envelope G 92A / G 92A Nine Pickup Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 378,000.00 311,319.00 Completed 2018-11-21 2019-01-16 2019-01-07 2019-07-15 2019-03-29 Double Cabs for NCDDP Quotations Envelope G123 / SUPPLY and INSTALLATION of a CCTV Request for Single Stage - One SECURITY SYSTEM in NEW IDA / H8140 Implementation Support Post Open - National 50,000.00 16,802.67 Completed 2019-03-06 2019-05-01 2019-10-10 2019-10-28 2020-01-30 Quotations Envelope BUILDING OF DRD HEAD OFFICE Pending Request for Single Stage - One G124 / Office Furniture IDA / H8140 Implementation Support Post Open - National 104,600.00 0.00 Implementati 2019-07-15 2019-09-09 2020-03-07 Quotations Envelope on G125 / 3HP Stand Air Pending Request for Single Stage - One Conditioner for New Project IDA / H8140 Implementation Support Post Open - National 5,000.00 0.00 Implementati 2019-07-15 2019-09-09 2020-03-07 Quotations Envelope Office and Training Hall on G126 / Photo Copieer for Request for Single Stage - One replacement and additional IDA / H8140 Implementation Support Post Open - National 105,000.00 104,040.23 Completed 2019-03-13 2019-05-08 2019-06-26 2019-11-04 2019-09-03 Quotations Envelope needs for existing townships G127 / Projector with screen Request for Single Stage - One for replacement in Township IDA / H8140 Implementation Support Post Open - National 25,000.00 22,519.53 Completed 2019-03-13 2019-04-22 2019-05-08 2019-06-03 2019-11-04 2019-08-16 Quotations Envelope and Union G128 / Still Camera for Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 7,500.00 7,588.10 Completed 2019-03-13 2019-05-14 2019-05-08 2019-07-11 2019-11-04 2019-09-20 Regional Office Quotations Envelope Pending G131 / Rehabilitation of Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 130,000.00 0.00 Implementati 2019-03-24 2019-05-19 2019-11-15 Project Vehicles Quotations Envelope on G132 / Life Jackets for Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 13,500.00 0.00 Canceled 2019-04-07 2019-06-02 2019-11-29 replacement Quotations Envelope G133 / Printing Grievance Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 33,000.00 7,106.05 Completed 2019-05-14 2019-07-09 2019-08-07 2020-01-05 2019-09-20 Envelop Quotations Envelope G134 / Tshirts with project Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 333,000.00 172,385.38 Completed 2019-05-14 2019-07-09 2019-08-30 2020-01-05 2019-08-30 logo Quotations Envelope G135 / Caps with project Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 171,000.00 59,994.26 Completed 2019-05-14 2019-07-09 2019-09-05 2020-01-05 2019-09-05 logo Quotations Envelope G136 / Project Information Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 210,000.00 205,546.95 Completed 2019-03-05 2019-04-22 2019-04-30 2019-05-31 2019-10-27 2019-09-03 Board with Project Logo Quotations Envelope Page 2 G137 / Backpack for 16 new project townships and Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 40,000.00 18,792.86 Completed 2019-03-05 2019-04-22 2019-04-30 2019-06-11 2019-10-27 2019-08-15 additional needs for other Quotations Envelope townships G138 / Operation and Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 52,000.00 18,484.86 Completed 2019-03-10 2019-05-05 2019-09-30 2019-11-01 2019-09-30 Maintenance Vinyl Poster Quotations Envelope G139 / Printing Operation Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 13,500.00 8,728.15 Completed 2019-03-10 2019-05-05 2019-09-23 2019-11-01 2019-09-23 and Maintenance Books Quotations Envelope G140 / Printing Communication Guide Book Pending Request for Single Stage - One and Printing Community IDA / H8140 Implementation Support Post Open - National 7,500.00 0.00 Implementati 2019-07-07 2019-09-01 2020-02-28 Quotations Envelope Driven Development Booklet on support by World Bank G141 / Printing Gender Manual Book and Check List Request for Single Stage - One Review and Revised Book and IDA / H8140 Implementation Support Post Open - National 9,350.00 5,126.52 Completed 2019-07-07 2019-09-01 2019-09-23 2020-02-28 2019-09-23 Quotations Envelope Printing Gender Success Stories Booklet G142 / NCDDP Sticker(Grievance Suggestion Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 65,900.00 12,999.16 Completed 2019-03-10 2019-04-22 2019-05-05 2019-06-12 2019-11-01 2019-09-05 Boxes,Motorcycles and Fie Quotations Envelope Cover) Pending G143 / Video Conference for Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 45,000.00 0.00 Implementati 2019-06-09 2019-08-04 2020-01-31 Union Quotations Envelope on G144 / Highspeed Scanner Request for Single Stage - One for Union Regional and IDA / H8140 Implementation Support Post Open - National 35,000.00 49,703.98 Completed 2019-06-09 2019-08-04 2019-08-13 2020-01-31 2019-09-23 Quotations Envelope Township Pending G145 / Printing Operation Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 189,663.00 0.00 Implementati 2019-05-14 2019-07-09 2020-01-05 Manual in 2018 Quotations Envelope on Pending G41 / GRADIENT Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 18,900.00 0.00 Implementati 2019-07-22 2019-09-16 2020-03-14 MEASUREMENT DEVICES Quotations Envelope on G117 / 60001 kits SUPPLY of Request for Single Stage - One MEDICAL KITS for the PROJECT IDA / H8140 Implementation Support Post Open - National 187,870.00 0.00 Canceled 2019-04-07 2019-04-22 2019-06-02 2019-11-29 Quotations Envelope STAFF G 130 / Maintenance and Under Request for Single Stage - One Repair Service for the NCDDP IDA / 56870 Implementation Support Post Open - National 365,635.00 0.00 Implementati 2019-10-22 2019-12-17 2020-06-14 Quotations Envelope Fleet of Motorbikes on G146 / Life Jackets for Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 13,500.00 11,492.79 Completed 2019-10-29 2019-12-24 2020-01-03 2020-06-21 2020-01-03 replacement Quotations Envelope G 147 / Supply of Medical Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 187,870.00 110,761.25 Completed 2019-10-29 2019-12-24 2020-01-30 2020-06-21 2020-01-30 Kits Quotations Envelope Pending G148 / Spare parts for UN Agencies IDA / 56870 Implementation Support Post Direct 110,000.00 0.00 Implementati 2019-11-06 2019-11-11 2019-12-16 2020-06-13 vehicles (Direct) on G162 / Protective Items For Pending Emergency Contingency COVID-19 Response for IDA / 56870 Post Direct Selection Direct 35,000.00 0.00 Implementati 2020-04-06 2020-04-11 2020-04-28 2020-05-12 Response project staff on G145 PRINTING OPERATION MANUAL 2020 / Printing of Request for Single Stage - One the Operation Manual Update IDA / 56870 Knowledge and Learning Post Open - National 49,350.00 60,801.12 Signed 2020-06-28 2020-08-23 2020-09-15 2021-02-19 Quotations Envelope Version 2020 for Union, State, Regional, Townships. G148 SPARE PARTS FOR MOTOR VEHICLES / Spare Under parts for Motor Vehicles in IDA / 56870 Implementation Support Post Direct Selection Direct 110,000.00 0.00 Implementati 2020-06-23 2020-06-28 2020-08-02 2021-01-29 State, Regional, union, on Townships G161 REPLACEMENT BATTERIES FOR TABLETS / Pending REPLACEMENT BATTERIES for Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 24,000.00 0.00 Implementati 2020-07-04 2020-08-29 2021-02-25 SAMSUNG and HUAWEI Quotations Envelope on TABLET COMPUTERS in Union, State, Regional, Towships. G 176 / Video Conferencing Pending Request for Single Stage - One Equipment for the State and IDA / 56870 Implementation Support Post Open - National 85,000.00 0.00 Implementati 2020-07-01 2020-08-26 2021-02-22 Quotations Envelope Regional Offices on Under Request for Single Stage - One G 158 / PHONE HANDSETS IDA / 56870 Implementation Support Post Open - National 6,500.00 0.00 Implementati 2020-07-08 2020-09-02 2021-03-01 Quotations Envelope on G 156 / OFFICE EQUIPMENT; COLOR PRINTER, BLACK and Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 17,700.00 20,645.37 Signed 2020-07-07 2020-09-01 2020-11-16 2021-02-28 WHITE PRINTER, ALL-IN-ONE Quotations Envelope PRINTER G 157 / OFFICE Pending EQUIPMENT;HIGH-SPEED Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 13,800.00 0.00 Implementati 2020-07-01 2020-08-26 2021-02-22 SCANNER and HARD DISK Quotations Envelope on DRIVE G 159 / COMMUNICATION Under Request for Single Stage - One MATERIAL; CAMERA and IDA / 56870 Implementation Support Post Open - National 20,350.00 0.00 Implementati 2020-07-08 2020-09-02 2021-03-01 Quotations Envelope VIDEO CAMERA on Page 3 G166 INFORMATION BOARD / Pending INFORMATION BOARDS for Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 155,100.00 0.00 Implementati 2020-09-02 2020-10-28 2021-04-26 CURRENT TOWNSHIPS and 13 Quotations Envelope on NEW TOWNSHIPS G 152 / FURNITURE for Union Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 91,650.00 51,809.17 Signed 2020-07-01 2020-08-26 2020-10-13 2021-02-22 and 13 new townships Quotations Envelope G 153 / AIR-CONDITIONERS , Request for Single Stage - One WATER COOLERS AND IDA / 56870 Implementation Support Post Open - National 23,000.00 2,614.95 Signed 2020-07-07 2020-09-01 2020-10-21 2021-02-28 Quotations Envelope REFRIGERATOR G168 VINYL POSTERS (9) ITEM Pending / Vinyl Posters (9) Item for Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 112,733.00 0.00 Implementati 2020-09-04 2020-10-30 2021-04-28 Union, Regional Office, 12 Old Quotations Envelope on TSPs and 13 new TSPs G160 RIVER BOAT FOR Pending DEDAYE TOWNSHIP / River Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 12,000.00 0.00 Implementati 2020-11-23 2021-01-18 2021-07-17 Boat for Dedaye Township Quotations Envelope on (AYEYARWADDY) G165 T-SHIRTS / T-SHIRTS Pending for REPLACEMENT in CURRENT Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 24,600.00 0.00 Implementati 2020-11-23 2021-01-04 2021-03-05 TOWNSHIPS and 13 NEW Quotations Envelope on TOWNSHIPS G167 CAPS FOR 13 NEW Pending Request for Single Stage - One TOWNSHIPS / CAPS for 13 IDA / 56870 Implementation Support Post Open - National 67,260.00 0.00 Implementati 2020-11-23 2021-01-04 2021-03-05 Quotations Envelope NEW TOWNSHIPS on G169 ECOP , O&M BOOKLET Pending & BROCHURES / PRINTING of Request for Single Stage - One IDA / 56870 Knowledge and Learning Post Open - National 9,819.00 0.00 Implementati 2020-11-23 2021-01-04 2021-03-05 ECOP , O&M BOOKLET and Quotations Envelope on PROJECT CYCLE BROCHURES G170 STICKERS / PRINTING Pending of FILE STICKERS, Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 5,046.00 0.00 Implementati 2020-11-20 2021-01-01 2021-03-02 MOTORCYCLE STICKERS and Quotations Envelope on GRIEVANCE BOX STICKERS G171 COMMUNICATION Pending MATERIALS / PRINTING of Request for Single Stage - One IDA / 56870 Knowledge and Learning Post Open - National 13,032.00 0.00 Implementati 2020-11-23 2021-01-04 2021-03-19 GENDER BOOKLET, GENDER Quotations Envelope on BROCHURES and CHECKLIST G172 GRIEVANCE Pending BROCHURES AND ENVELOPES Request for Single Stage - One IDA / 56870 Knowledge and Learning Post Open - National 14,827.00 0.00 Implementati 2020-11-21 2021-01-02 2021-03-03 / PRINTING of GRIEVANCE Quotations Envelope on BROCHURES and GRIEVANCE ENVELOPES G173 BACKPACKS FOR 13 Pending NEW TOWNSHIPS / Supply of Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 8,976.00 0.00 Implementati 2020-11-21 2021-01-16 2021-07-15 the BACKPACKS for 13 NEW Quotations Envelope on TOWNSHIPS G174 RAIN COATS FOR 13 Pending NEW TOWNSHIPS / Supply of Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 13,200.00 0.00 Implementati 2020-11-21 2021-01-02 2021-03-03 the RAIN COATS for 13 NEW Quotations Envelope on TOWNSHIPS G175 GRIEVANCE BOXES FOR Pending 13 NEW TOWNSHIP / Supply of Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 64,167.00 0.00 Implementati 2020-11-21 2021-01-16 2021-07-15 the GRIEVANCE BOXES for 13 Quotations Envelope on NEW TOWNSHIPS G176 10 KW SOLAR ON- GRID (GRID-TIE) / Supply of Pending the 10 KW Solar On- grid Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 240,000.00 0.00 Implementati 2020-11-23 2021-01-04 2021-03-05 (Grid-Tie) System for eight Quotations Envelope on new townships in 13 new townships G177 HYBRID SYSTEM FOR 5 Pending NEW TOWNSHIPS / Hybrid Request for Single Stage - One IDA / 56870 Implementation Support Post Open - National 225,000.00 0.00 Implementati 2020-11-23 2021-01-04 2021-07-03 System for 5 new townships in Quotations Envelope on the 13 new townships G178 RIVER BOAT FOR Pending Request for Single Stage - One HKAMTI TOWNSHIP / River IDA / 56870 Implementation Support Post Open - National 26,000.00 0.00 Implementati 2020-11-23 2021-01-04 2021-03-05 Quotations Envelope Boat for Hkamti Township on G164 / Reagents for the Pending Request for Single Stage - One Water Quality Testing Kits in IDA / 56870 Implementation Support Post Open - National 145,000.00 0.00 Implementati 2020-12-19 2021-01-30 2021-04-30 Quotations Envelope the Current Townships. on G163 WATER QUALITY TESTING KITS / WATER Pending Request for Single Stage - One QUALITY TESTING KITS for 13 IDA / 56870 Implementation Support Post Open - National 217,500.00 0.00 Implementati 2020-11-23 2021-01-18 2021-07-17 Quotations Envelope new townships and 17 on Clusters NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual G89 / SUPPLY and INSTALLATION and Pending CONFIGURATION of a SERVER IDA / H8140 Implementation Support Prior Direct Selection Direct 10,000.00 0.00 Implementati 2018-03-12 2018-03-17 2018-04-21 2018-10-18 for the NEW FINANCE on SOFTWARE NC82 / RENTAL of VEHICLES Pending for UNION DRD EVENTS and Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 60,000.00 0.00 Implementati 2018-01-23 2018-03-20 2018-09-16 CROSS EXCHANGE VISITS Quotations Envelope on between townships Page 4 Pending NC85 / PHOTOCOPY AND Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 9,230.00 0.00 Implementati 2017-12-17 2018-02-11 2018-08-10 PRINTING SERVICES Quotations Envelope on G129 / Rehabilitation of Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 20,000.00 0.00 Canceled 2019-03-24 2019-05-19 2019-11-15 Nissan SUV Quotations Envelope G130 / Rehabilitation of Request for Single Stage - One IDA / H8140 Implementation Support Post Open - National 232,600.00 0.00 Canceled 2019-03-24 2019-05-19 2019-11-15 Project Motorbikes Quotations Envelope G131 REPAIR SERVICE FOR PROJECT VEHICLES / Repair Under Service for the rehabilitation IDA / 56870 Implementation Support Post Direct Selection Direct 30,000.00 0.00 Implementati 2020-06-18 2020-05-19 2020-06-23 2020-05-29 2020-07-28 2021-01-24 of the project vehicles (15 on Toyota and 1 Nissan) G149 REPAIR SERVICE FOR Under THE MOTORBIKES / Repair IDA / 56870 Implementation Support Post Direct Selection Direct 150,000.00 0.00 Implementati 2020-06-23 2020-04-01 2020-06-28 2020-08-02 2021-01-29 service for the Rehabilitation on of the Motorbikes G150 SPARE PARTS FOR Under HONDA MOTORCYCLES / IDA / 56870 Implementation Support Post Direct Selection Direct 100,000.00 0.00 Implementati 2020-06-23 2020-04-01 2020-06-28 2020-08-02 2021-08-02 Spare Parts for Honda on Motorcycles G-151 SPARE PARTS FOR TVS Under MOTORCYCLES / Spare Parts IDA / 56870 Implementation Support Post Direct Selection Direct 200,000.00 0.00 Implementati 2020-06-18 2020-04-01 2020-06-23 2020-07-28 2021-07-28 (TVS Motorcycles) for Union, on Regional, and Townships. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C.4.16 / TTA Y3 Cluster 7: Quality Based IDA / H8140 Community Block Grants Prior Open - International 3,000,000.00 1,817,882.14 Signed 2015-11-12 2015-11-27 Sagaing Selection C4.13 / TTA Y3 Cluster 4: Quality Based IDA / H8140 Community Block Grants Prior Open - International 3,000,000.00 2,605,225.09 Signed 2015-11-23 2015-11-27 Magway-Chin Selection C4.12 / TTA Y3 Cluster 3: Quality Based IDA / H8140 Community Block Grants Prior Open - International 3,000,000.00 1,766,947.30 Signed 2015-12-11 2015-12-16 Kayah Selection C4.14 / TTA Y3 Cluster 5: Quality Based IDA / H8140 Community Block Grants Prior Open - International 6,000,000.00 2,932,594.57 Signed 2015-12-17 2015-12-22 Mon-Kayin-Tanintharyi Selection C4.10 / TTA Y3 Cluster 1: Quality Based IDA / H8140 Community Block Grants Prior Open - International 3,000,000.00 2,800,626.17 Signed 2015-12-16 2015-11-06 Ayeyawaddy Selection C4.15 / TTA Y3 Cluster 6: Quality Based IDA / H8140 Community Block Grants Prior Open - International 4,500,000.00 3,156,957.00 Signed 2015-12-16 2015-12-21 Naypyitaw-Mandalay Selection C.4.11 / TTA Y3 Cluster 2: Quality Based IDA / H8140 Community Block Grants Prior Open - International 4,500,000.00 2,748,468.14 Signed 2016-01-15 2016-01-15 Bago-Yangon Selection C72 / FINANCE - NEW Consultant SOFTWARE PACKAGE and IDA / H8140 Community Block Grants Prior Qualification Open - International 100,000.00 78,660.00 Canceled 2017-04-05 CUSTOMIZATION Selection C4.18 / Y4 TTA Quality Based IDA / H8140 Community Block Grants Prior Open - International 1,200,000.00 1,008,471.75 Signed 2017-01-11 2016-12-21 CONSULTANT FIRM for Selection KACHIN STATE C4.19 / Y4 TTA Quality Based IDA / H8140 Community Block Grants Prior Open - International 1,200,000.00 1,196,495.48 Signed 2017-01-23 2017-01-23 CONSULTANT FIRM for SHAN Selection STATE C 4.3/ 2014 / TTA Sidoktaya Quality And Cost- IDA / H8140 Community Block Grants Prior Open - International 425,000.00 662,209.93 Signed 2014-12-22 2015-01-07 Township, Magway Region Based Selection C 4.2/2014 / Township Level Technical Assistance for Quality Based IDA / H8140 Community Block Grants Prior Open - International 900,000.00 746,557.83 Signed 2014-12-29 2015-01-05 Pinlebu Township of Sagaing Selection Region C 4.5/ 2014 / TTA Quality Based Laymyethnor Township IDA / H8140 Community Block Grants Prior Open - International 425,000.00 883,753.00 Signed 2015-01-02 2015-01-15 Selection Ayarwaddy Region Consultant C-10/2014 / Technical IDA / H8140 Community Block Grants Prior Qualification Open - International 0.00 8,300.00 Signed 2015-02-17 2015-02-27 Auditor Selection C 4.1/2014 / TTA Nay Pyi Quality Based IDA / H8140 Community Block Grants Prior Open - International 425,000.00 1,163,384.20 Canceled 2015-10-08 2015-05-15 Taw Selection C4.4/2014 / TTA Ann Quality Based IDA / H8140 Community Block Grants Prior Open - International 425,000.00 824,816.00 Signed 2015-02-02 2015-02-18 Township Selection Quality Based C4.6/2014 / TTA Yangon IDA / H8140 Community Block Grants Prior Open - International 425,000.00 812,762.00 Signed 2015-02-02 2015-02-18 Selection C4.17 / TTA Y3 Cluster 8: Quality Based IDA / H8140 Community Block Grants Prior Open - International 1,500,000.00 1,088,927.30 Signed 2015-11-23 2015-11-27 Kayin Selection C5-03 / TOWNSHIP TECHNICAL ASSISTANCE Quality Based IDA / 56870 Community Block Grants Prior Open - International 2,200,000.00 1,196,400.71 Signed 2017-11-22 2017-12-08 2017-12-06 2018-01-03 2017-12-23 2018-02-20 2018-01-22 2018-02-05 2018-06-20 2018-03-22 2018-08-17 2018-04-09 2018-09-13 2022-04-08 (2017-2018) in RAKHINE Selection (Ponnagyun, Gwa) Page 5 C5-05 / TOWNSHIP TECHNICAL ASSISTANCE Quality Based IDA / 56870 Community Block Grants Prior Open - International 1,100,000.00 532,680.81 Signed 2017-11-22 2017-12-08 2017-12-13 2018-01-03 2018-01-26 2018-02-20 2018-02-23 2018-03-26 2018-03-25 2018-05-14 2018-04-24 2018-06-29 2018-05-29 2018-07-04 2019-05-29 (2017-2018) in SHAN Selection (Mongkhet) C 5-08 / TOWNSHIP TECHNICAL ASSISTANCE Quality Based IDA / 56870 Community Block Grants Prior Open - International 1,100,000.00 764,088.05 Signed 2017-11-22 2017-12-08 2017-12-06 2018-01-03 2017-12-23 2018-02-20 2018-01-22 2018-03-26 2018-02-05 2018-05-12 2018-03-22 2018-06-29 2018-04-09 2018-07-04 2022-04-08 (2017-2018) in BAGO Selection (Thegon) C100 / PROCUREMENT and Consultant LOGISTICS SPECIALIZED Pending IDA / H8140 Implementation Support Post Qualification Open - National 30,000.00 0.00 2019-03-25 2019-04-15 2019-05-29 2019-06-28 2019-08-02 2020-01-29 TRAINING INSTITUTE for Implementation Selection SHORT TERM TRAININGS C6.03 / Township Level Facilitation and Capacity Quality Based Under Technical Assistance in Chin IDA / 56870 Prior Open 1,090,000.00 0.00 2020-05-04 2020-07-19 2020-05-25 2020-07-31 2020-06-29 2020-10-02 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Development Selection Implementation State(Mindat Township) C6.06 / Township Level Facilitation and Capacity Quality Based Under Technical Assistance in Shan IDA / 56870 Prior Open 2,030,000.00 0.00 2020-05-04 2020-07-19 2020-05-25 2020-07-27 2020-06-29 2020-10-02 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Development Selection Implementation State(Tangyan Township) C6.08 / Township Level Technical Assistance in Facilitation and Capacity Quality Based Under IDA / 56870 Prior Open 1,000,000.00 0.00 2020-05-04 2020-07-31 2020-05-25 2020-06-29 2020-10-02 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Tanintharyi Region(Palaw Development Selection Implementation Township) C6.09 / Township Level Facilitation and Capacity Quality Based Under Technical Assistance in Bago IDA / 56870 Prior Open 1,200,000.00 0.00 2020-05-04 2020-07-19 2020-05-25 2020-07-27 2020-06-29 2020-10-02 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Development Selection Implementation Region(Oakpho Township) C6.11 / Township Level Technical Assistance in Facilitation and Capacity Quality Based Under IDA / 56870 Prior Open 1,200,000.00 0.00 2020-05-04 2020-07-31 2020-05-25 2020-06-29 2020-10-02 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Mandalay Region (Taungtha Development Selection Implementation Township) C6.12 / Township Level Technical Assistance in Facilitation and Capacity Quality Based Under IDA / 56870 Prior Open 1,020,000.00 0.00 2020-05-04 2020-07-27 2020-05-25 2020-08-13 2020-06-29 2020-10-02 2020-08-13 2020-09-12 2020-10-03 2020-11-07 2024-11-06 Yangon Region (Kayan Development Selection Implementation Township) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C42/ 2015 / National IDA / H8140 Community Block Grants Prior Direct Selection Direct 50,000.00 50,407.75 Signed 2016-01-01 Developer for MIS 2.0 (firm) Individual C12 / Finance Assistant IDA / H8140 Community Block Grants Prior Consultant Open 0.00 29,644.99 Signed 2014-07-17 2014-08-10 Selection Individual C 22/ 2014 / International IDA / H8140 Community Block Grants Prior Consultant Open 47,280.00 47,280.00 Signed 2014-09-15 2014-09-22 Procurement Specialist Selection C28 / Peachtree Financial Accounting Software, IDA / H8140 Community Block Grants Prior Direct Selection Direct 6,000.00 4,980.00 Signed 2015-02-26 Refresher Training and additional customization April Individual C 22.1/ 2014 / National IDA / H8140 Community Block Grants Prior Consultant Open 27,600.00 25,321.07 Signed 2015-05-25 2015-05-01 Senior Finance Assistant Selection C 5-01 / TOWNSHIP TECHNICAL ASSISTANCE (2017-2018) in KACHIN IDA / 56870 Community Block Grants Prior Direct Selection Direct 3,300,000.00 1,171,361.03 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-02-23 2022-02-09 (Putao, Shwegu, Mabeing (Shan)) C 5-04 / TOWNSHIP TECHNICAL ASSISTANCE IDA / 56870 Community Block Grants Prior Direct Selection Direct 1,100,000.00 436,282.83 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-05-04 2022-02-09 (2017-2018) in SHAN (Mawkmai) C 5-06 / TOWNSHIP TECHNICAL ASSISTANCE IDA / 56870 Community Block Grants Prior Direct Selection Direct 2,200,000.00 1,560,848.42 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-02-23 2022-02-09 (2017-2018) in KAYIN (Hlaingbwe, Kawkareik) C 5-07 / TOWNSHIP TECHNICAL ASSISTANCE IDA / 56870 Community Block Grants Prior Direct Selection Direct 2,200,000.00 833,562.02 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-02-23 2022-02-09 (2017-2018) in SAGAING (Kyunhla, Kani) C 5-09 / TOWNSHIP TECHNICAL ASSISTANCE Direct - IDA / 56870 Community Block Grants Prior Direct Selection 1,100,000.00 408,483.00 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-02-23 2022-02-09 (2017-2018) in BAGO International (Shwegyin) C 5-10 / TOWNSHIP TECHNICAL ASSISTANCE (2017-2018) in IDA / 56870 Community Block Grants Prior Direct Selection Direct 2,200,000.00 2,186,439.81 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-05-04 2022-02-09 AYEYARWADDY (Danubyu, Ingapu) C 5-02 / TOWNSHIP TECHNICAL ASSISTANCE IDA / 56870 Community Block Grants Prior Direct Selection Direct 1,100,000.00 564,232.00 Signed 2017-11-22 2017-12-08 2017-12-27 2018-02-10 2018-02-23 2022-02-09 (2017-2018) in CHIN (Tonzang) C67 / National Technical Under IDA / 56870 Implementation Support Post Direct Selection Direct 60,000.00 0.00 2018-01-18 2017-12-27 2018-01-24 2018-01-08 2018-02-13 2018-08-12 Auditors- 5 Experts Implementation Page 6 Individual C68 / IT CONSULTANTS for Facilitation and Capacity Pending IDA / 56870 Post Consultant Open 40,800.00 0.00 2018-01-31 2018-02-26 2018-02-28 2018-03-09 2020-03-08 UNION and TOWNSHIPS Development Implementation Selection Individual C69 / IT CONSULTANTS for Facilitation and Capacity Under IDA / 56870 Post Consultant Open 86,400.00 0.00 2018-01-31 2018-01-25 2018-02-26 2018-04-20 2018-03-01 2018-05-02 2018-03-10 2020-03-09 UNION and TOWNSHIPS Development Implementation Selection C92 / National Consultant for Individual Facilitation and Capacity Under the development of the PRA IDA / H8140 Post Consultant Open 3,200.00 0.00 2018-01-31 2018-01-25 2018-02-16 2018-02-21 2018-03-01 2018-04-10 Development Implementation MANUAL Selection Individual Facilitation and Capacity Pending C84 / GRIEVANCE ASSISTANT IDA / 56870 Post Consultant Open 35,585.00 0.00 2018-05-18 2018-06-12 2018-06-17 2018-06-22 2019-06-22 Development Implementation Selection Individual C81 / VEHICLE FLEET Facilitation and Capacity Pending IDA / 56870 Post Consultant Open 36,000.00 0.00 2018-05-17 2018-06-12 2018-06-17 2018-06-22 2020-06-21 MANAGER Development Implementation Selection Individual C65 / NATIONAL TRAINING Under IDA / H8140 Implementation Support Post Consultant Open 86,400.00 0.00 2019-03-25 2019-04-12 2019-05-13 2019-06-03 2019-07-08 2020-01-04 EXPERT Implementation Selection C93 / GENDER ASSISTANT Individual Pending replacing JUNIOR IDA / H8140 Implementation Support Post Consultant Open 18,000.00 0.00 2019-03-25 2019-05-13 2019-06-03 2019-07-08 2020-01-04 Implementation CONSULTANTS for GRIEVANCE Selection Individual C95 / NATIONAL GENDER Under IDA / H8140 Implementation Support Post Consultant Open 18,580.00 0.00 2019-03-18 2019-06-26 2019-05-06 2019-05-27 2019-07-01 2019-12-28 CONSULTANT Implementation Selection C96 / COMMUNICATIONS Individual Under CONSULTANT including IDA / H8140 Implementation Support Post Consultant Open 18,210.00 0.00 2019-02-25 2019-06-26 2019-04-15 2019-05-06 2019-06-10 2019-12-07 Implementation website mgt. & advocacy Selection C97 / FINANCE ASSISTANT Individual Under for CHECKING TOWNSHIP IDA / H8140 Implementation Support Post Consultant Open 18,000.00 0.00 2019-03-18 2019-06-26 2019-05-06 2019-05-27 2019-07-01 2019-12-28 Implementation FINANCIAL MANAGEMENT Selection Individual C99 / NATIONAL TRAINING Pending IDA / H8140 Implementation Support Post Consultant Open 28,800.00 0.00 2019-03-25 2019-05-13 2019-06-03 2019-07-08 2020-01-04 COORDINATOR Implementation Selection Individual C102 / PROJECT SECRETARY Pending IDA / H8140 Implementation Support Post Consultant Open 14,400.00 0.00 2019-03-18 2019-05-06 2019-05-27 2019-07-01 2019-12-28 AT UNION LEVEL Implementation Selection Individual C90 / NATIONAL GRIEVANCE Facilitation and Capacity Under IDA / H8140 Post Consultant Open 19,200.00 0.00 2019-03-18 2019-06-26 2019-04-21 2019-04-26 2019-05-09 2020-05-08 HANDLING EXPERT Development Implementation Selection C101 / COMMUNITY Individual Under PROCUREMENT RESOURCE IDA / H8140 Implementation Support Post Consultant Open 21,600.00 0.00 2019-03-18 2019-05-13 2019-04-16 2019-06-12 2019-04-26 2019-06-17 2019-05-06 2020-10-27 Implementation OFFICER Selection C98 / (20) PROCUREMENT Individual Under ASSISTANT for the (20) IDA / H8140 Implementation Support Post Consultant Open 198,000.00 0.00 2019-03-25 2019-05-21 2019-04-28 2019-05-05 2019-05-20 2020-11-10 Implementation TOWNSHIPS Selection Individual C53 / (15) REGIONAL OFFICE Under IDA / H8140 Implementation Support Prior Consultant Open 576,000.00 0.00 2019-03-18 2019-08-02 2019-04-16 2019-09-27 2019-04-21 2019-05-04 2020-10-25 CONSULTANTS Implementation Selection C103 / International Facilitation and Capacity Under IDA / H8140 Post Direct Selection Direct 196,040.00 0.00 2019-05-29 2019-09-05 2019-06-14 2019-07-09 2021-07-08 Procurement Consultant Development Implementation C104 / International M&E Facilitation and Capacity Under IDA / H8140 Post Direct Selection Direct 198,220.00 0.00 2019-05-29 2019-06-05 2019-06-14 2019-07-09 2021-07-08 Consultant Development Implementation C105 / International Finance Facilitation and Capacity Under IDA / H8140 Post Direct Selection Direct 196,040.00 0.00 2019-05-29 2019-09-05 2019-06-14 2019-07-09 2021-07-08 Consultant Development Implementation Individual C106 / Senior Procurement IDA / 56870 Implementation Support Post Consultant Open 21,600.00 0.00 Canceled 2019-09-27 2019-10-17 2019-11-15 2019-12-06 2020-01-10 2021-12-30 Assistant (National) Selection C4.18 EXT 01 / Ext. of the TOWNSHIP TECHNICAL Facilitation and Capacity IDA / H8140 Prior Direct Selection Direct 750,000.00 750,170.02 Signed 2020-01-22 2020-02-04 2020-02-13 2020-02-03 2020-02-22 2020-02-23 2022-02-21 ASSISTANCE (Putao, Shwegu, Development Mabein) C4.10 EXT 03 / Ext. of the TOWNSHIP TECHNICAL Facilitation and Capacity Under IDA / H8140 Prior Direct Selection Direct 700,000.00 0.00 2020-03-20 2020-04-08 2020-04-20 2020-04-08 2020-04-27 2022-04-27 ASSISTANCE (Danubyu, Development Implementation Ingapu) C4.19 EXT 01 / Ext. of the Facilitation and Capacity Under TOWNSHIP TECHNICAL IDA / H8140 Prior Direct Selection Direct 400,000.00 0.00 2020-03-20 2020-04-08 2020-04-20 2020-04-08 2020-04-27 2022-04-27 Development Implementation ASSISTANCE (Mawkmai) C4.12 EXT 03 / Ext. of the TOWNSHIP TECHNICAL Facilitation and Capacity Under IDA / H8140 Prior Direct Selection Direct 600,000.00 0.00 2020-01-22 2020-02-04 2020-02-13 2020-02-11 2020-02-22 2022-02-21 ASSISTANCE (Hlaingbwe, Development Implementation Kawkareik) C4.13 EXT 03 / Ext. of the Facilitation and Capacity TOWNSHIP TECHNICAL IDA / H8140 Prior Direct Selection Direct 400,000.00 383,348.92 Signed 2020-01-22 2020-02-04 2020-02-13 2020-02-11 2020-02-22 2020-02-23 2022-02-21 Development ASSISTANCE (Tonzan) C4.14 EXT 02 / Ext. of the Facilitation and Capacity TOWNSHIP TECHNICAL IDA / H8140 Prior Direct Selection Direct 400,000.00 222,990.00 Signed 2020-01-22 2020-02-04 2020-02-13 2020-02-11 2020-02-22 2020-02-23 2022-02-21 Development ASSISTANCE (Shwegyin) Page 7 C4.16 EXT 03 / Ext. of the Facilitation and Capacity Under TOWNSHIP TECHNICAL IDA / H8140 Prior Direct Selection Direct 500,000.00 0.00 2020-01-22 2020-02-04 2020-02-13 2020-02-11 2020-02-22 2022-02-21 Development Implementation ASSISTANCE (Kyunhla, Kani) C5.03 / Ext. of the TOWNSHIP Facilitation and Capacity Under TECHNICAL ASSISTANCE IDA / H8140 Prior Direct Selection Direct 850,000.00 0.00 2020-07-27 2020-08-05 2020-08-18 2020-08-06 2020-08-27 2022-08-27 Development Implementation (Ponnagyun, Gwa) C5.08 / Ext. of the TOWNSHIP Facilitation and Capacity Under TECHNICAL ASSISTANCE IDA / H8140 Prior Direct Selection Direct 600,000.00 0.00 2020-05-22 2020-05-18 2020-06-13 2020-06-22 2022-06-22 Development Implementation (Thegon) C5.05 / Ext. of the TOWNSHIP Facilitation and Capacity Under TECHNICAL ASSISTANCE IDA / H8140 Prior Direct Selection Direct 400,000.00 0.00 2020-05-22 2020-05-18 2020-06-13 2020-06-23 2022-06-23 Development Implementation (Mongkhet) C89 EXT-01 / MIS SUPPORT & Under IDA / H8140 Knowledge and Learning Post Direct Selection Direct 35,000.00 0.00 2020-02-25 2020-03-10 2020-03-03 2020-03-12 2022-03-12 DEVELOPMENT for Year 5 Implementation C107 / (2) Legal Advisors for Developing of Regulations and Under IDA / 56870 Knowledge and Learning Post Direct Selection Direct 30,000.00 0.00 2020-04-06 2020-06-23 2020-04-09 2020-04-26 2020-05-11 Follow Up Guidelines of the Implementation Rural Development Law C6.02 / Township Level Facilitation and Capacity Under Technical Assistance in Kayin IDA / 56870 Prior Direct Selection Direct 1,800,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-27 2020-09-20 2024-09-19 Development Implementation State(Hpa An Township) C6.07 / Township Level Technical Assistance in Facilitation and Capacity Under IDA / 56870 Prior Direct Selection Direct 1,000,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-31 2020-09-20 2024-09-19 Sagaing Region(Hkamti Development Implementation Township) C6.10 / Township Level Technical Assistance in Facilitation and Capacity Under IDA / 56870 Prior Direct Selection Direct 1,000,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-27 2020-09-20 2024-09-19 Magway Region(Ngape Development Implementation Township) C6.01 / Township Level Facilitation and Capacity Under Technical Assistance in Kachin IDA / 56870 Prior Direct Selection Direct 1,000,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-31 2020-09-20 2024-09-19 Development Implementation State (Waingmaw Township) C6.13 / Township Level Technical Assistance in Facilitation and Capacity Under IDA / 56870 Prior Direct Selection Direct 1,540,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-27 2020-09-20 2024-09-19 Ayeyarwaddy Region (Dedaye Development Implementation Township) C6.04 / Township Level Facilitation and Capacity Under Technical Assistance in Mon IDA / 56870 Prior Direct Selection Direct 1,000,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-31 2020-09-20 2024-09-19 Development Implementation State(Kyaikmaraw Township) C6.05 / Township Level Technical Assistance in Facilitation and Capacity Under IDA / 56870 Prior Direct Selection Direct 1,000,000.00 0.00 2020-06-16 2020-07-19 2020-07-26 2020-07-27 2020-09-20 2024-09-19 Rakhine State(Munaung Development Implementation Township) C108 / Individual Consultant Individual for Ponnagyun Townsip (Team Facilitation and Capacity Under IDA / H8140 Post Consultant Open 32,400.00 0.00 2020-08-14 2020-08-07 2020-09-19 2020-09-26 2020-10-15 2021-10-15 Leader, Lead CDD and Development Implementation Selection Training Expert) C109 / Individual Consultant Individual Facilitation and Capacity Under for Ponnagyun Townsip IDA / H8140 Post Consultant Open 19,800.00 0.00 2020-08-14 2020-08-07 2020-09-19 2020-09-26 2020-10-15 2021-10-15 Development Implementation (Finance Officer) Selection C110 / Individual Consultant Individual Facilitation and Capacity Under for Ponnagyun Townsip IDA / H8140 Post Consultant Open 19,800.00 0.00 2020-08-14 2020-08-07 2020-09-19 2020-09-26 2020-10-15 2021-10-15 Development Implementation (Procurement Officer) Selection C111 / Individual Consultant Individual Facilitation and Capacity Under for Ponnagyun Townsip (M&E, IDA / H8140 Post Consultant Open 19,800.00 0.00 2020-08-14 2020-08-07 2020-09-19 2020-09-26 2020-10-15 2021-10-15 Development Implementation MIS Officer) Selection C112 / Individual Consultant Individual for Ponnagyun Townsip Facilitation and Capacity Under IDA / H8140 Post Consultant Open 19,800.00 0.00 2020-08-14 2020-08-07 2020-09-19 2020-09-26 2020-10-15 2021-04-13 (Communication, Social Development Implementation Selection Accountability & Gender) Individual CFW-C01 / Key Expert at Facilitation and Capacity Pending IDA / H8140 Post Consultant Open 10,800.00 0.00 2020-10-20 2020-11-07 2020-11-12 2020-11-25 2021-11-25 Union (M&E) Development Implementation Selection CFW-C02 / Key Expert at Facilitation and Capacity Pending IDA / H8140 Post Direct Selection Direct 2,178.00 0.00 2020-10-20 2020-10-27 2020-11-14 2021-11-14 Union (Procurement) Development Implementation CFW-C03 / Key Expert at Facilitation and Capacity Pending IDA / H8140 Post Direct Selection Direct 3,465.00 0.00 2020-10-20 2020-10-27 2020-11-14 2021-11-14 Union (GHM) Development Implementation CFW-C04 / Key Expert at Facilitation and Capacity Pending IDA / H8140 Post Direct Selection Direct 4,615.00 0.00 2020-10-20 2020-10-27 2020-11-14 2021-11-14 Union (Trainer-1) Development Implementation CFW-C05 / Key Expert at Facilitation and Capacity Pending IDA / H8140 Post Direct Selection Direct 2,772.00 0.00 2020-10-20 2020-10-27 2020-11-14 2021-11-14 Union (Trainer-2) Development Implementation CFW-C06 / Key Expert at Facilitation and Capacity Pending IDA / H8140 Post Direct Selection Direct 2,079.00 0.00 2020-10-20 2020-10-27 2020-11-14 2021-11-14 Union (Finance) Development Implementation Facilitation and Capacity Pending CFW-C07 / Web Developer IDA / H8140 Post Direct Selection Direct 20,000.00 0.00 2020-10-20 2020-10-27 2020-11-14 2021-11-14 Development Implementation Individual C 113 / Fixed Asset Data Facilitation and Capacity IDA / H8140 Post Consultant Open 17,100.00 0.00 Under Review 2020-11-25 2020-12-17 2021-01-13 2021-02-03 2021-03-10 2021-09-06 Management Assistant Development Selection Page 8 C114 / Individual Consultant for Hparsaung and Bawlakhe Facilitation and Capacity Pending Township Cluster (Team IDA / H8140 Post Direct Selection Direct 20,400.00 0.00 2020-12-17 2020-12-22 2021-01-01 2022-01-01 Development Implementation Leader, Lead CDD and Training Expert) C115 / Individual Consultant for Hparsaung and Bawlakhe Facilitation and Capacity Pending IDA / H8140 Post Direct Selection Direct 13,200.00 0.00 2020-12-17 2020-12-22 2021-01-01 2022-01-01 Township Cluster (Finance Development Implementation Officer) C116 / Individual Consultant for Hparsaung and Bawlakhe Facilitation and Capacity Pending IDA / H8140 Post Direct Selection Direct 13,200.00 0.00 2020-12-17 2020-12-22 2021-01-01 2022-01-01 Township Cluster (M&E, MIS Development Implementation Officer) Page 9