PROCUREMENT PLAN (Textual Part) Project information: Uzbekistan Prosperous Villages (P168233) Project Implementation agency: PIU under the MOE Date of the Procurement Plan: October 3, 2019 Period covered by this Procurement Plan: October 2019 to March 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market, procurement under World Bank financed operations may be carried out in accordance with “Single-Stage Bidding” method set forth in the Public Procurement Law of the Republic of Uzbekistan dated April 9, 2018(the “PPL), provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. • The Bidding process shall not be cancelled sole on the reason that minimum bid price is larger than the amount allocated by procuring entity for this procurement. • There shall be no preference applied during procurement of works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. Other national procurement arrangements (other than national open competitive procurement) that may be applied by the Borrower shall be consistent with paragraphs 5.5 and 5.6 of the Procurement Regulations. E-Procurement system in Republic of Uzbekistan will be used to facilitate the e- procurement transactions for World Bank financed projects when the country’s own national procurement procedures will be used. In this regard, the e-Reverse Auction module and e-Catalog module can be used for Bank-funded procurement following national market approach for simple goods and works. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables - Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. - Not Applicable Other Relevant Procurement Information. PROCUREMENT Uzbekistan : Rural Infrastructure Development Project PLAN General Information Country: Uzbekistan Bank’s Approval Date of the Original Procurement Plan: 2019-09-05 2020-11-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168233 GPN Date: 2020-03-24 Project Name: Rural Infrastructure Development Project Loan / Credit No: TF / A9749, IDA / 65020 M Executing Agency(ies): inistry of Economy and Industry of Uzbekistan WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOEI-PVP-G-1 / Computer Project management, Pending Request for Single Stage - One and office equipment for PIU IDA / 65020 monitoring and evaluation, Post Open - National 56,796.00 0.00 Implementati 2020-01-11 2020-03-07 2020-09-03 Quotations Envelope staff and capacity building on Project management, Pending MOEI-PVP-G-2 / Purchase of Request for Single Stage - One IDA / 65020 monitoring and evaluation, Post Open - National 60,000.00 0.00 Implementati 2020-01-11 2020-03-07 2020-09-03 vehicles (3 vehicles) Quotations Envelope and capacity building on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Demand-driven investments Consultant MOEI-PVOQ-CS-1 / Financial in basic infrastructure and Under TF / A9749 Post Qualification Open - National 11,000.00 0.00 2019-10-08 2020-04-08 2019-10-29 2019-12-12 2020-01-11 2020-02-15 2020-08-13 audit services and local governance Implementation Selection capacity support Demand-driven investments Consultant MOEI-PVOQ-CS-2 / Public in basic infrastructure and Pending TF / A9749 Post Qualification Open - National 12,600.00 0.00 2019-09-05 2019-09-26 2019-11-09 2019-12-09 2020-01-13 2020-07-11 awareness campaign (PR) services and local governance Implementation Selection capacity support Demand-driven investments MOEI-PVOQ-CS-3 / ESMF Consultant in basic infrastructure and Pending and RPF Drafting and TF / A9749 Post Qualification Open - National 20,000.00 0.00 2019-09-05 2019-09-26 2019-11-09 2019-12-09 2020-01-13 2020-07-11 services and local governance Implementation Consultations Selection capacity support Demand-driven investments Consultant MOEI-PVOQ-CS-5 / MIS in basic infrastructure and Pending TF / A9749 Post Qualification Open - National 12,000.00 0.00 2019-09-05 2019-09-26 2019-11-09 2019-12-09 2020-01-13 2020-07-11 Software services and local governance Implementation Selection capacity support MOEI-PVP-CS-3 / Development of technical manual, online training Demand-driven investments modules, and mobile Consultant in basic infrastructure and Pending applications to monitor TF / A9749 Post Qualification Open - International 500,000.00 0.00 2020-01-20 2020-02-10 2020-03-25 2020-04-24 2020-05-29 2020-11-25 services and local governance Implementation infrastructure quality and Selection capacity support provision of infrastructure master trainers (multiple contracts) Demand-driven investments Consultant MOEI-PVP-CS-4 / Technical in basic infrastructure and Pending IDA / 65020 Post Qualification Open - International 200,000.00 0.00 2020-06-08 2020-06-29 2020-08-12 2020-09-11 2020-10-16 2021-04-14 Audits services and local governance Implementation Selection capacity support MOEI-PVP-CS-5 / Communication strategy and Demand-driven investments Consultant implemementation which in basic infrastructure and Pending IDA / 65020 Post Qualification Open - International 200,000.00 0.00 2020-02-03 2020-02-24 2020-04-08 2020-05-08 2020-06-12 2020-12-09 include production of services and local governance Implementation Selection informational material for capacity support local governments, and others Demand-driven investments Consultant MOEI-PVP-CS-6 / Financial in basic infrastructure and Pending IDA / 65020 Post Qualification Open - National 100,000.00 0.00 2020-09-01 2020-09-22 2020-11-05 2020-12-05 2021-01-09 2021-07-08 Audit services and local governance Implementation Selection capacity support Demand-driven investments Consultant MOEI-PVP-CS-7 / Financial in basic infrastructure and Pending IDA / 65020 Post Qualification Open - National 6,000.00 0.00 2020-01-06 2020-01-27 2020-03-11 2020-04-10 2020-05-15 2020-11-11 Management Software services and local governance Implementation Selection capacity support Demand-driven investments MOEI-PVP-CS-8 / Baseline, Consultant in basic infrastructure and Pending Midline and Endline Surveys IDA / 65020 Post Qualification Open - National 150,000.00 0.00 2020-02-02 2020-02-23 2020-04-07 2020-05-07 2020-06-11 2020-12-08 services and local governance Implementation and Impact Assesmen Selection capacity support Demand-driven investments MOEI-PVP-CS-9 / Consultant in basic infrastructure and Pending Technology for Citizen IDA / 65020 Post Qualification Open - International 400,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-05-07 services and local governance Implementation Engagement Selection capacity support Page 1 MOEI-PVP-CS-10 / Special Demand-driven investments studies for village-level Public Consultant in basic infrastructure and Pending Expenditure Tracking and IDA / 65020 Post Qualification Open - National 150,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-05-07 services and local governance Implementation Governance and Anti- Selection capacity support Corruption MOEI-PVP-CS-11 / Training Demand-driven investments for Regional Hokimiyats on Consultant in basic infrastructure and Pending Procurement, Public Financial IDA / 65020 Post Qualification Open - National 450,000.00 0.00 2020-06-01 2020-06-22 2020-08-05 2020-09-04 2020-10-09 2021-04-07 services and local governance Implementation Management and Oversight (2 Selection capacity support separate contracts) MOEI-PVP-CS-2 / Facilitating Demand-driven investments Partner(s) for activities under in basic infrastructure and Quality And Cost- IDA / 65020 Prior Open - National 11,700,000.00 0.00 Canceled 2019-12-20 2019-12-16 2020-01-10 2019-12-17 2020-02-23 2020-03-22 2020-04-21 2020-05-26 2020-06-30 2021-06-30 Component 1b (at least two services and local governance Based Selection separate contracts) capacity support MOEI-PVP-CS-2-2 / Demand-driven investments Facilitating Partner(s) for in basic infrastructure and Quality And Cost- Under IDA / 65020 Prior Open - International 2,500,000.00 0.00 2020-04-05 2020-06-17 2020-04-26 2020-06-09 2020-11-03 2020-07-07 2020-08-06 2020-09-10 2020-10-15 2023-10-15 activities under Component services and local governance Based Selection Implementation 1b from Namangan region capacity support MOEI-PVP-CS-2-1 / Demand-driven investments Facilitating Partner(s) for in basic infrastructure and Quality And Cost- Under activities under Component IDA / 65020 Prior Open - International 2,500,000.00 0.00 2020-04-05 2020-06-17 2020-04-26 2020-06-09 2020-11-04 2020-07-07 2020-08-06 2020-09-10 2020-10-15 2023-10-15 services and local governance Based Selection Implementation 1b from Andijan and capacity support Ferghana regions MOEI-PVP-CS-8-1 / Demand-driven investments Consultant CONSULTING SERVICES FOR in basic infrastructure and Pending IDA / 65020 Post Qualification Open - National 50,000.00 0.00 2020-11-24 2020-12-15 2020-12-29 2021-01-12 2021-01-15 2021-04-15 BASELINE PROJECT services and local governance Implementation Selection MONITORING SURVEY capacity support INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Demand-driven investments Individual MOEI-PVOQ-IC-2 / Social in basic infrastructure and Pending TF / A9749 Post Consultant Open 7,700.00 0.00 2019-09-05 2019-10-24 2019-11-14 2019-12-19 2020-06-16 Safeguards specialist services and local governance Implementation Selection capacity support Demand-driven investments Individual MOEI-PVOQ-IC-3 / in basic infrastructure and Pending TF / A9749 Post Consultant Open 5,500.00 0.00 2019-09-05 2019-10-24 2019-11-14 2019-12-19 2020-06-16 Environmental Specialist services and local governance Implementation Selection capacity support Demand-driven investments MOEI-PVOQ-IC-4 / Individual in basic infrastructure and Pending Community Mobilization TF / A9749 Post Consultant Open 6,000.00 0.00 2019-09-05 2019-10-24 2019-11-14 2019-12-19 2020-06-16 services and local governance Implementation Specialis Selection capacity support Demand-driven investments Individual MOEI-PVOQ-IC-5 / Financial in basic infrastructure and Pending TF / A9749 Post Consultant Open 7,700.00 0.00 2019-09-05 2019-10-24 2019-11-14 2019-12-19 2020-06-16 Management Specialist services and local governance Implementation Selection capacity support Demand-driven investments Individual MOEI-PVOQ-IC-6 / in basic infrastructure and Pending TF / A9749 Post Consultant Open 7,700.00 0.00 2019-09-05 2019-10-24 2019-11-14 2019-12-19 2020-06-16 Procurement Specialist services and local governance Implementation Selection capacity support Demand-driven investments Individual MOEI-PVOQ-IC-7 / MIS in basic infrastructure and Pending TF / A9749 Post Consultant Open 6,000.00 0.00 2019-09-05 2019-10-24 2019-11-14 2019-12-19 2020-06-16 Specialist services and local governance Implementation Selection capacity support Demand-driven investments Individual MOEI-PVOQ-IC-8 / in basic infrastructure and Pending TF / A9749 Post Consultant Open 7,000.00 0.00 2019-09-05 2019-10-24 2019-11-14 2019-12-19 2020-06-16 Translator services and local governance Implementation Selection capacity support Demand-driven investments Individual MOEI-PVOQ-IC-9 / in basic infrastructure and Pending TF / A9749 Post Consultant Open 5,500.00 0.00 2019-09-05 2019-10-24 2019-11-14 2019-12-19 2020-06-16 Infrastructure specialist services and local governance Implementation Selection capacity support Demand-driven investments Individual MOEI-PVOQ-IC-10 / HR in basic infrastructure and Pending TF / A9749 Post Consultant Open 5,000.00 0.00 2019-09-05 2019-10-24 2019-11-14 2019-12-19 2020-06-16 manager services and local governance Implementation Selection capacity support MOEI-PVOQ-CS-4 / Participatory Village Selection Demand-driven investments and Planning Pilot in basic infrastructure and TF / A9749 Prior Direct Selection Direct 30,800.00 27,768.86 Signed 2019-09-05 2019-09-30 2019-09-15 2019-10-02 2019-11-19 2019-10-03 2020-05-17 “Taraqqiyot” Center for services and local governance Development of the Well- capacity support Being of Population Page 2