Public Disclosure Copy

         The World Bank                                                                           Implementation Status & Results Report
         Integrated Solid Waste Management Project (P114515)


Integrated Solid Waste Management Project (P114515)

 EUROPE AND CENTRAL ASIA | Belarus | Global Practice |
 IBRD/IDA | Specific Investment Loan | FY 2010 | Seq No: 16 | ARCHIVED on 18-Jul-2016 | ISR24544 |


 Implementing Agencies: Ministry of Housing and Utilities




 Key Dates

   Key Project Dates

   Bank Approval Date:17-Jun-2010                                           Effectiveness Date:06-Oct-2010
   Planned Mid Term Review Date:--                                          Actual Mid-Term Review Date:26-May-2015
   Original Closing Date:30-Dec-2016                                        Revised Closing Date:30-Dec-2016




 Project Development Objectives

  Integrated Solid Waste Management Project (P114515)
  Project Development Objective (from Project Appraisal Document)
  (i) Improve environmental benefits of integrated solid waste management in Grodno through recovery and reuse of recycable materials in line
  with good international standards; (ii) Strengthen national capacity to manage hazardous wastes associated with POPs.


  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No




  Belarus POPs Stockpile Management Project (GEF) (P111110)
  Global Environmental Objective (from Project Appraisal Document)
  Reduce environmental and health risks associated with the presence and release of POPs in global and local environments.


  Has the Global Environmental Objective been changed since Board Approval of the Project Objective?
  No




Components

Name
Mechanical Materials Recovery Facility:(Cost $37.00 M)
Waste Separation Management Improvements:(Cost $4.00 M)
Persistent Organic Pollutants (POPs) stockpile Management (GEF):(Cost $26.10 M)
Project Management:(Cost $2.65 M)


7/18/2016                                                   Public Disclosure Copy                                                    Page 1 of 9
                                                           Public Disclosure Copy

        The World Bank                                                                            Implementation Status & Results Report
        Integrated Solid Waste Management Project (P114515)




Overall Ratings
Name                                                                      Previous Rating                          Current Rating

Progress towards achievement of PDO                                        Moderately Satisfactory                 Moderately Satisfactory
Overall Implementation Progress (IP)                                       Moderately Satisfactory                 Moderately Satisfactory
Overall Risk Rating                                                        Moderate                                Moderate


 Implementation Status and Key Decisions

 The contract for the construction of the Materials Recycling Facility (MRF) in Grodno was signed with the China Machinery Engineering Corporation
 on July 10, 2014 and became effective on December 18, 2014. Civil works for the construction of the MRF have advanced substantially and the facility
 is expected to be substantially completed in the summer of 2016 and become operational at the end of calendar 2016. The project remains on track to
 achieve its Development Objective to increase the environmental benefits of integrated solid waste management in Grodno through recovery and
 reuse of recyclable material. Going forward, proactive supervision will be important for timely completion of construction works and commissioning of
 the plant.




7/18/2016                                                   Public Disclosure Copy                                                     Page 2 of 9
                                                              Public Disclosure Copy

               The World Bank                                                                       Implementation Status & Results Report
               Integrated Solid Waste Management Project (P114515)




 Risks

 Systematic Operations Risk-rating Tool

 Risk Category                                                Rating at Approval              Previous Rating          Current Rating

 Political and Governance                                      --                             Moderate                Moderate
 Macroeconomic                                                 --                             Moderate                Moderate
 Sector Strategies and Policies                                --                             Moderate                Moderate
 Technical Design of Project or Program                        --                             Moderate                Moderate
 Institutional Capacity for Implementation and
 Sustainability
                                                               --                             Moderate                Moderate
 Fiduciary                                                     --                             Moderate                Moderate
 Environment and Social                                        --                             Moderate                Moderate
 Stakeholders                                                  --                             Moderate                Moderate
 Other                                                         --                             Moderate                Moderate
 Overall                                                       --                             Moderate                Moderate


 Results

 Project Development Objective Indicators
 PHINDPDOTBL




          Valuable material sold by the new facility to users (tons) (Tones/year, Custom)


                                              Baseline                    Actual (Previous)         Actual (Current)         End Target

         Value                                0.00                        0.00                      0.00                     10000.00

         Date                                 16-Nov-2009                 07-Jul-2015               07-Jul-2015              30-Dec-2016


 PHINDPDOTBL




          Tons of waste that will not be buried in the landfill due to the new facility (Tones/year, Custom)




7/18/2016                                                      Public Disclosure Copy                                               Page 3 of 9
                                                                 Public Disclosure Copy

                  The World Bank                                                                    Implementation Status & Results Report
                  Integrated Solid Waste Management Project (P114515)



                                                 Baseline                   Actual (Previous)       Actual (Current)        End Target

               Value                             0.00                       0.00                    0.00                    20000.00

               Date                              16-Nov-2009                07-Jul-2015             07-Jul-2015             30-Dec-2016


 PHINDPDOTBL




              Industrial or municipal solid waste reduced or recycled under the project (Tones/year, Core)


                                                 Baseline                   Actual (Previous)       Actual (Current)        End Target

               Value                             0.00                       0.00                    0.00                    20000.00

               Date                              18-Dec-2012                07-Jul-2015             07-Jul-2015             30-Dec-2016




 Overall Comments


 Global Environmental Objective Indicators
 PHINDGEOTBL




              Compliance with Stockholm Convention (Text, Custom)


                                                   Baseline                  Actual (Previous)        Actual (Current)   End Target

               Value                               Compliant                 Compliant                Compliant          Compliant

               Date                                16-Nov-2009               23-Jan-2015              23-Jan-2015        30-Sep-2013



 PHINDGEOTBL




              Reduced exposure of population to POPs Waste (Number, Custom)


                                                   Baseline                  Actual (Previous)        Actual (Current)   End Target

               Value                               100000.00                 127360.00                127360.00          101832.00

               Date                                16-Nov-2009               30-Sep-2013              30-Sep-2013        30-Sep-2013




7/18/2016                                                        Public Disclosure Copy                                               Page 4 of 9
                                                                 Public Disclosure Copy

                  The World Bank                                                                 Implementation Status & Results Report
                  Integrated Solid Waste Management Project (P114515)

 PHINDGEOTBL




              POPs&pops waste destroyed,disposed or contained in environmentally sound manner (Metric ton, Core)


                                                   Baseline                  Actual (Previous)    Actual (Current)   End Target

               Value                               0.00                      8340.00              8340.00            5751.00

               Date                                16-Nov-2009               11-Mar-2014          11-Mar-2014        30-Sep-2013



 PHINDGEOTBL




              Environmentally sound disposal of priority POPs stockpiles (Metric ton, Custom)


                                                   Baseline                  Actual (Previous)    Actual (Current)   End Target

               Value                               0.00                      2926.00              2926.00            1800.00

               Date                                16-Nov-2009               11-Mar-2014          11-Mar-2014        30-Sep-2013




 Overall CommentsPHGEOCMTS

 Intermediate Results Indicators
 PHINDIRITBL




              % of recycling effort coverage of the city of Grodno (Percentage, Custom)

                                                Baseline                    Actual (Previous)    Actual (Current)       End Target

               Value                            40.00                       50.00                50.00                  100.00

               Date                             16-Nov-2009                 07-Jul-2015          07-Jul-2015            30-Dec-2016




 PHINDIRITBL




              Tons of separated waste collected (Percentage, Custom)

                                                Baseline                    Actual (Previous)    Actual (Current)       End Target

               Value                            0.00                        0.00                 0.00                   14000.00

               Date                             16-Nov-2009                 07-Jul-2015          07-Jul-2015            30-Dec-2016




7/18/2016                                                        Public Disclosure Copy                                           Page 5 of 9
                                                               Public Disclosure Copy

                  The World Bank                                                                 Implementation Status & Results Report
                  Integrated Solid Waste Management Project (P114515)

 PHINDIRITBL




              Percent of population aware of Grodno's solid waste separation program (Percentage, Custom)

                                                Baseline                  Actual (Previous)      Actual (Current)      End Target

               Value                            37.00                     37.00                  37.00                 80.00

               Date                             16-Nov-2009               14-Nov-2013            14-Nov-2013           30-Dec-2016




 PHINDIRITBL




              Percent of population participating in Grodno's source separation program (Percentage, Custom)

                                                Baseline                  Actual (Previous)      Actual (Current)      End Target

               Value                            16.00                     16.00                  16.00                 80.00

               Date                             16-Nov-2009               14-Nov-2013            14-Nov-2013           30-Dec-2016




 PHINDIRITBL




              Percent of waste recycled by weight (Percentage, Custom)

                                                Baseline                  Actual (Previous)      Actual (Current)      End Target

               Value                            5.00                      5.00                   5.00                  30.00

               Date                             16-Nov-2009               14-Nov-2013            14-Nov-2013           30-Dec-2016




 PHINDIRITBL




              Operating Ratio of MWSTF (Percentage, Custom)

                                                Baseline                  Actual (Previous)      Actual (Current)      End Target

               Value                            0.00                      0.00                   0.00                  1.00

               Date                             16-Nov-2009               07-Jul-2015            07-Jul-2015           30-Dec-2016




7/18/2016                                                      Public Disclosure Copy                                          Page 6 of 9
                                                                Public Disclosure Copy

                  The World Bank                                                                    Implementation Status & Results Report
                  Integrated Solid Waste Management Project (P114515)

 PHINDIRITBL




              Mechanical waste separation facility operaitonal (Text, Custom)

                                                Baseline                    Actual (Previous)       Actual (Current)        End Target

               Value                            No                          No                      No                      Yes

               Date                             16-Nov-2009                 07-Jul-2015             07-Jul-2015             30-Dec-2016




 PHINDIRITBL




              Amounts of POPs pesticides recovered, packaged in storage or destroyed (Text, Custom)

                                                Baseline                    Actual (Previous)       Actual (Current)        End Target

               Value                            0.00                        7068                    7068                    4486

               Date                             16-Nov-2009                 30-Sep-2013             30-Sep-2013             30-Dec-2016




 PHINDIRITBL




              Amounts of Priority PCBs destroyed (Number, Custom)

                                                Baseline                    Actual (Previous)       Actual (Current)        End Target

               Value                            0.00                        823.00                  823.00                  816.00

               Date                             17-Nov-2009                 30-Sep-2013             30-Sep-2013             30-Dec-2016




 PHINDIRITBL




              Plans and inventories established, laboratories upgraded (Text, Custom)

                                                Baseline                    Actual (Previous)       Actual (Current)        End Target

                                                                            Long-term PCB           Long-term PCB
                                                                            phaseout                phaseout
                                                                                                                            Plans and
                                                No long-term plan for PCB   plan developed and      plan developed and
                                                                                                                            inventories
                                                phase out. Baseline         approved by the         approved by the
               Value                                                                                                        established and
                                                inventory of PCB            Government.             Government.
                                                                                                                            laboratories
                                                equipment                   Laboratories upgraded   Laboratories upgraded
                                                                                                                            upgraded
                                                                            using Government's      using Government's
                                                                            cofinancing.            cofinancing.

               Date                             16-Nov-2009                 30-Sep-2013             30-Sep-2013             30-Dec-2016




7/18/2016                                                       Public Disclosure Copy                                               Page 7 of 9
                                                                      Public Disclosure Copy

                  The World Bank                                                                               Implementation Status & Results Report
                  Integrated Solid Waste Management Project (P114515)

 PHINDIRITBL




              New and amended regulatory documents (Text, Custom)

                                                    Baseline                       Actual (Previous)           Actual (Current)             End Target

                                                    Gaps in national legislation                                                            New and
                                                    for control of POPs. Lack                                                               amended POPs
                                                                                   Ten educational events      Ten educational events
               Value                                of consistency and                                                                      regulatory
                                                                                   were held                   were held
                                                    coordination for POPs                                                                   documents
                                                    related information                                                                     adopted

               Date                                 16-Nov-2009                    23-Jul-2014                 23-Jul-2014                  30-Dec-2016




 Overall Comments



Data on Financial Performance

Disbursements (by loan)

Project                Loan/Credit/TF   Status        Currency        Original     Revised       Cancelled    Disbursed      Undisbursed                  Disbursed

P114515                IBRD-79320       Effective     USD                42.51       42.51             0.00         19.59           22.92                        46%

P111110                TF-96993         Closed        USD                 5.50          5.49           0.01          5.49            0.00                     100%


Key Dates (by loan)
Project                Loan/Credit/TF   Status        Approval Date       Signing Date         Effectiveness Date    Orig. Closing Date     Rev. Closing Date

P114515                IBRD-79320       Effective     17-Jun-2010         05-Jul-2010          06-Oct-2010           30-Dec-2016            30-Dec-2016
P111110                TF-96993         Closed        05-Jul-2010         05-Jul-2010          06-Oct-2010           30-Sep-2013            30-Sep-2013



Cumulative Disbursements




7/18/2016                                                             Public Disclosure Copy                                                       Page 8 of 9
                                                    Public Disclosure Copy

        The World Bank                                                        Implementation Status & Results Report
        Integrated Solid Waste Management Project (P114515)




 Restructuring History

 Level 2 Approved on 04-Nov-2015




 Related Project(s)

P111110-Belarus POPs Stockpile Management Project (GEF)




7/18/2016                                            Public Disclosure Copy                                Page 9 of 9