The World Bank Report No: ISR6198 Implementation Status & Results Indonesia ID-PCF-Indocement Cement (P084860) Public Disclosure Copy Operation Name: ID-PCF-Indocement Cement (P084860) Project Stage: Implementation Seq.No: 2 Status: ARCHIVED Archive Date: 06-Jul-2011 Country: Indonesia Approval FY: 2004 Product Line: Carbon Offset Region: EAST ASIA AND PACIFIC Lending Instrument: Rehabilitation Loan Implementing Agency(ies): Key Dates Board Approval Date 09-Jun-2004 Original Closing Date 31-Dec-2012 Last Archived ISR Date 06-Jul-2011 Effectiveness Date 23-Dec-2005 Revised Closing Date 31-Dec-2012 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Satisfactory Overall Risk Rating Implementation Status Overview Both components are commissioned and operating as expected. CERs have been issued for January 2005-July 2007 for the Alternative Fuels component. First and second issuance for Blended Cement component for the period January 05-October 2006 and November 2006-July 2007 took place in summer 2011 and March 2012 respectively. Third issuance for Alternative Fuels component is expected before the end of FY12. For third issuance of Blended Cement, site visit will be done in June 2012. Locations Country First Administrative Division Location Planned Actual Indonesia Not Entered Citeureup Indonesia Not Entered Cirebon Public Disclosure Copy Indonesia Not Entered Tarjun Key Decisions Regarding Implementation No key decisions for disclosure Related Projects There are no related projects. Page 1 of 1