Procurement Plan (Using Procurement Guidelines) I. General 1. Project Information: Modern Food Storage Facilities Project [P120583] 2. Project Implementation agency: Directorate General of Food, Ministry of Food 3. Bank’s approval Date of the procurement Plan [Original: August 2015]: Revision of Updated Procurement Plan, January 2018] 2. Date of General Procurement Notice: January 06, 2015 3. Period covered by this procurement plan: The procurement period of project covered from year July 2014 to June 2020 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement Prior Review Threshold (Above US$ million) Sl Procurement Type High Risk Substantial Moderate Low Risk and Method Risk Risk 1. ICB and LIB (Goods) 1.5 2 4 6 2. NCB (Goods) 0.5 3. ICB (Works) 5 10 15 20 4. NCB (Works) 2 5. (Non-Consultant 1.5 2 4 6 Services) 2. Pre-qualification. 3 packages  W -3 / Construction of the Rice Silos in Madhupur (48,000 MT), Mymensingh (48,000 MT) and Ashuganj (105,000 MT) with all ancillary facilities, public toilet, vehicle parking, water supply, sewerage, surface drain, equipment, machineries and firefighting.  W1 / Construction of Wheat Silos in Chittagong (114,300 MT) and Maheshwarpasha (76,200 MT) with all ancilary facilities, public toilet, vehicle parking, water supply, sewerage, surface drain, equipment, machineries and firefighting.  W-2 / Construction of Rice Silos at Barial (48,000MT), Dhaka (48,000) and Narayangonj (48,000) with all ancillary facilities, public toilet, vehicle parking, water supply, sewerage, surface drain, equipment, machineries and firefighting. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Not applicable February 1, 2018 5. Any Other Special Procurement Arrangements: Not applicable 6. Summary of the Procurement Packages planned during the first 18 months* after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Description Estimated Pac Domesti Review Commen . Cost kag c by ts No. US$ es Prefere Bank million nce (Prior / (yes/no) Post) 1 Summary of the ICB (Works) 354* 3 No Prior 2 Summary of the ICB (Goods) 69.4 3 No Prior 3 Summary of the NCB (Works) 20.5 5 No Prior= 3, Post =2 4 Summary of the NCB (Goods) 1.8 7 No Prior= 1, Post =6 5 Summary of the ICB (Non-Consultant Services) *Based on Revised procurement plan. There are two works packages (W1 and W2) that are processed in the Procurement Plan but implementation will depend on the availability of fund. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Threshold (Above US$ million) Sl Selection Type and High Risk Substantial Moderate Low Risk Method Risk Risk 1. Competitive 0.5 1 2 4 Methods (Firms) 2. Individual 0.2 0.3 0.4 0.5 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 0.5 million equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule February 1, 2018 1 2 3 4 5 6 Ref Description of Assignment Estimated Packag Review Comment . Cost es by Bank s No. US$ million (Prior / Post) 1 Summary of number of contracts that 4.75 2 Prior will be let under QCBS 2 Summary of number of contracts that 29.65 24 Prior= 21, will be let under other methods (QBS, Post=3 CDS, and individual consultants) *Based on Revised procurement plan February 1, 2018 PROCUREMENT Bangladesh : Bangladesh Modern Food Storage Facilities Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2017-07-14 2021-11-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P120583 GPN Date: Project Name: Bangladesh Modern Food Storage Facilities Project Loan / Credit No: IDA / 52650, IDA / 67260 Directorate General of Food Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned W -3 / Construction of the Rice Silos in Madhupur (48,000 MT), Mymensingh (48,000 MT) and Ashuganj Component A – Construction (105,000 MT) with all ancillary Single Stage - One 125,594,137. 115,659,68 2020-03- IDA / 52650 of Modern Grain Storage Silo Prior Request for Bids Open - International Signed 2017-08-08 2017-08-09 2017-08-09 2017-08-08 2017-11-17 2017-05-31 2018-01-16 2018-03-13 2018-03-08 2018-04-04 facilities, public toilet, vehicle Envelope 50 7.64 07 Facilities parking, water supply, sewerage, surface drain, equipment, machineries and fire fighting. W1 / Construction of Wheat Silos in Chittagong (114,300 MT) and Maheshwarpasha (76,200 MT) with all ancilary Component A – Construction Single Stage - One 103,452,250. 2020-02- facilities, public toilet, vehicle IDA / 52650 of Modern Grain Storage Silo Prior Request for Bids Open - International 0.00 Canceled 2017-08-09 2017-08-09 2017-08-09 2017-08-09 2017-10-18 2017-11-12 2018-07-19 2020-09-17 2018-08-30 Envelope 00 21 parking, water supply, Facilities sewerage, surface drain, equipment, machineries and fire fighting. W-17 / Construction of Component C - Project Laboratory Buildings at management, Construction Single Stage - One 2019-03- Khulna, Barisal, Rajshahi, IDA / 52650 Supervision, Technical Post Request for Bids Open - National 637,500.00 0.00 Canceled 2017-10-19 2017-10-24 2017-11-23 2017-12-23 2018-02-03 Envelope 13 Rangpur, Sylhet and Assistance, Training and Chittagang. Strategic Studies W-4 / Construction of a Component B – Support for building for establishment of Single Stage - One 11,875,000.0 2021-07- IDA / 52650 Food and Market Planning Prior Request for Bids Open - National 0.00 Canceled 2018-08-06 2018-09-04 2018-08-11 2018-09-22 2019-04-10 2019-05-22 food monitoring, research & Envelope 0 30 and Monitoring Program training center W-11 / Site/Land Component A – Construction development, site office, Single Stage - One 2018-01- IDA / 52650 of Modern Grain Storage Silo Prior Request for Bids Open - National 5,215,233.50 0.00 Canceled 2018-01-25 2018-01-25 2018-01-25 2018-01-25 2018-01-25 boundary wall, river training Envelope 25 Facilities etc of Ashugonj Silo W-9 / Site/Land Component A – Construction development, site office, Single Stage - One 2018-01- IDA / 52650 of Modern Grain Storage Silo Prior Request for Bids Open - National 2,173,065.36 0.00 Canceled 2018-01-25 2018-01-25 2018-01-25 2018-01-25 2018-01-25 boundary wall, river training Envelope 25 Facilities etc of Narayangong Silo Component C - Project management, Construction W-19 / Construction of Single Stage - One 2021-10- IDA / 52650 Supervision, Technical Post Request for Bids Open - National 625,000.00 0.00 Canceled 2019-10-17 2019-10-22 2019-11-19 2020-01-18 2020-02-22 Laboratory Buildings Phase-2 Envelope 14 Assistance, Training and Strategic Studies W-2 / CONSTRUCTION OF RICE SILOS AT BARISAL (48,000 MT), DHAKA (48,000 MT) AND NARAYANGONJ (48,000 MT) WITH ALL Component A – Construction Single Stage - One 125,551,662. 2021-08- ANCILLARY FACILITIES, PUBLIC IDA / 52650 of Modern Grain Storage Silo Prior Request for Bids Open - International 0.00 Canceled 2017-08-08 2017-08-08 2018-08-08 2019-06-18 2017-08-08 2018-12-03 2019-06-21 2019-08-02 Envelope 50 11 TOILET, VEHICLE PARKING, Facilities WATER SUPPLY, SEWERAGE, SURFACE DRAIN, EQUIPMENT, MACHINERIES AND FIREFIGHTING. Component A – Construction MFSP/W-21 / Construction of Single Stage - One 40,034,000.0 39,016,948. 2023-09- IDA / 52650 of Modern Grain Storage Silo Prior Request for Bids Open - International Signed 2020-07-15 2020-11-16 2020-09-23 2020-11-19 2020-11-07 2021-01-26 2021-01-06 2021-04-16 2021-02-10 2021-07-22 steel silo for rice at Barishal Envelope 0 43 20 Facilities Component A – Construction Pending MFSP/W-22 / Construction of Single Stage - One 18,363,770.0 2023-09- IDA / 52650 of Modern Grain Storage Silo Prior Request for Bids Open - International 0.00 Implementat 2020-10-21 2020-12-30 2021-02-13 2021-04-14 2021-05-19 steel silo for rice at Dhaka Envelope 0 20 Facilities ion MFSP/W-23 / Construction of Component A – Construction Single Stage - One 34,173,200.0 36,865,378. 2023-09- steel silo for rice at IDA / 52650 of Modern Grain Storage Silo Prior Request for Bids Open - International Signed 2020-07-21 2021-01-27 2020-09-29 2021-02-07 2020-11-13 2021-04-05 2021-01-12 2021-07-13 2021-02-16 2021-09-14 Envelope 0 03 30 Narayanganj Facilities Component C - Project MFSP/W-19/1 / Construction management, Construction Single Stage - One 2022-05- of Laboratory Buildings at IDA / 52650 Supervision, Technical Post Request for Bids Open - National 154,208.36 130,149.06 Signed 2020-04-19 2020-06-01 2020-04-24 2021-09-23 2020-05-16 2020-06-24 2020-06-15 2020-08-16 2020-07-20 2020-09-03 Envelope 31 Khulna Assistance, Training and Strategic Studies Component C - Project MFSP/W-19/2 / Construction management, Construction Single Stage - One 2022-05- of Laboratory Buildings at IDA / 52650 Supervision, Technical Post Request for Bids Open - National 353,148.91 221,643.58 Signed 2020-04-15 2020-07-09 2020-04-20 2021-09-20 2020-05-12 2020-07-27 2020-06-11 2020-08-27 2020-07-16 2020-09-10 Envelope 27 Rajshahi Assistance, Training and Strategic Studies Component C - Project MFSP/W-19/3 / Construction management, Construction Single Stage - One 2022-06- of Laboratory Buildings at IDA / 52650 Supervision, Technical Post Request for Bids Open - National 182,460.27 150,011.09 Signed 2020-04-21 2020-06-01 2020-04-26 2021-09-29 2020-05-18 2020-06-24 2020-06-17 2020-07-29 2020-07-22 2020-09-02 Envelope 02 Barisal Assistance, Training and Strategic Studies Component C - Project MFSP/W-19/4 / Construction management, Construction Single Stage - One 2022-06- of Laboratory Buildings at IDA / 52650 Supervision, Technical Post Request for Bids Open - National 157,739.85 122,394.79 Signed 2020-04-27 2020-06-01 2020-05-02 2021-09-29 2020-05-24 2020-06-24 2020-06-23 2020-07-09 2020-07-28 2020-07-19 Envelope 08 Sylhet Assistance, Training and Strategic Studies Page 1 Component C - Project MFSP/W-19/5 / Construction management, Construction Single Stage - One 2022-06- of Laboratory Buildings at IDA / 52650 Supervision, Technical Post Request for Bids Open - National 164,802.83 164,454.55 Signed 2020-04-30 2020-06-01 2020-05-05 2021-09-29 2020-05-27 2020-06-23 2020-06-26 2020-07-09 2020-07-31 2020-07-27 Envelope 11 Chittagang Assistance, Training and Strategic Studies Component C - Project MFSP/W-19/6 / Construction management, Construction Single Stage - One 2022-06- of Laboratory Buildings at IDA / 52650 Supervision, Technical Post Request for Bids Open - National 185,991.76 125,080.41 Signed 2020-05-11 2020-06-01 2020-05-16 2021-09-29 2020-06-07 2020-06-23 2020-07-07 2020-06-23 2020-08-11 2020-07-27 Envelope 22 Rangpur Assistance, Training and Strategic Studies Component A – Construction Under W-24 / Construction of steel Single Stage - One 56,000,000.0 2022-01- IDA / 67260 of Modern Grain Storage Silo Prior Request for Bids Open - International 0.00 Implementat 2020-12-15 2020-12-30 2021-01-10 2021-01-17 2021-03-01 2021-03-16 2021-06-09 2021-09-26 2021-07-14 silo for wheat at Chattogram Envelope 0 10 Facilities ion Component A – Construction Under W-25 / Construction of steel Single Stage - One 47,000,000.0 2022-02- IDA / 67260 of Modern Grain Storage Silo Prior Request for Bids Open - International 0.00 Implementat 2021-01-14 2021-03-15 2021-02-13 2021-03-27 2021-04-04 2021-05-27 2021-07-13 2021-10-18 2021-08-17 silo for wheat at Khulna Envelope 0 13 Facilities ion Component C - Project National W-20 / Construction of management, Construction Procurement Pending Single Stage - One 2022-04- Consultants office spaces and IDA / 52650 Supervision, Technical Post Request for Bids Open - National Document - 1 72,000.00 0.00 Implementat 2021-07-08 2021-07-13 2021-08-10 2021-09-09 2021-10-23 Envelope 21 Physical Services at PMU office Assistance, Training and Envelope process ion Strategic Studies (Non Bank-SPD) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component C - Project management, Construction GD-3 / Procurement of Pick- Single Stage - One IDA / 52650 Supervision, Technical Prior Request for Bids Open - National 587,500.00 492,908.16 Signed 2015-03-23 2015-04-19 up Vehicles Envelope Assistance, Training and Strategic Studies MFSP GD- 14 / Procurement Component A – Construction Single Stage - One of Household Silo (food grade IDA / 52650 of Modern Grain Storage Silo Prior Request for Bids Open - International 10,709,285.00 8,775,226.56 Signed 2016-02-28 2016-08-02 Envelope plastic container) Facilities Component B – Support for GD-8 / Procurement of Single Stage - One IDA / 52650 Food and Market Planning Prior Request for Bids Limited 1,125,000.00 827,591.63 Signed 2017-08-08 2017-09-03 2017-10-21 2017-10-04 2017-11-20 2018-04-26 2018-01-03 2017-11-28 2018-08-31 Digital Weigh Bridge Scale Envelope and Monitoring Program GD-4 / Purchase of office Component C - Project equipment including LAN management, Construction Under Single Stage - One infrastructure, AC, VC and IT IDA / 52650 Supervision, Technical Post Request for Bids Open - National 105,250.00 0.00 Implementati 2018-08-12 2018-08-17 2018-09-14 2018-10-14 2018-11-25 2019-05-24 Envelope equipment for PMU and 8 Site Assistance, Training and on offices Strategic Studies Component C - Project GD-25 / Procurement of management, Construction Under Single Stage - One Furniture for PMU and Silo IDA / 52650 Supervision, Technical Post Request for Bids Open - National 42,612.50 0.00 Implementati 2018-10-07 2018-10-12 2018-11-14 2018-12-14 2019-01-25 2019-06-24 Envelope offices Assistance, Training and on Strategic Studies GD-5 / Procurement of Component B – Support for Single Stage - One Furniture for food monitoring, IDA / 52650 Food and Market Planning Post Request for Bids Open - National 625,000.00 0.00 Canceled 2019-08-12 2019-08-17 2019-10-06 2019-12-05 2020-01-16 2020-07-14 Envelope research and training center and Monitoring Program GD-6 / Procurement of Component B – Support for specialized equipment for Single Stage - One IDA / 52650 Food and Market Planning Prior Request for Bids Limited 3,500,000.00 0.00 Canceled 2019-06-06 2019-06-11 2019-07-23 2020-02-08 2020-03-21 2020-09-17 strengthening of Food Testing Envelope and Monitoring Program Laboratories GD-7 / Procurement of Laboratory Apparatus and Component B – Support for Single Stage - One office equipment (AC, IDA / 52650 Food and Market Planning Post Request for Bids Open - National 250,000.00 0.00 Canceled 2019-08-08 2019-08-13 2019-09-12 2019-11-11 2019-12-25 2020-06-22 Envelope computer, printer, scanner, and Monitoring Program fridge etc) Component C - Project GD-23 / Supply of Laptop, management, Construction Under Single Stage - One Computer, Printer, IDA / 52650 Supervision, Technical Post Request for Bids Open - National 34,562.50 0.00 Implementati 2018-08-05 2018-08-10 2018-09-09 2018-10-09 2018-11-13 2019-01-12 Envelope Photocopier etc. Assistance, Training and on Strategic Studies Component C - Project management, Construction GD-22 / Procurement of Single Stage - One IDA / 52650 Supervision, Technical Post Request for Bids Open - National 163,375.00 0.00 Canceled 2019-04-10 2019-04-22 2019-05-22 2019-07-01 2019-08-05 2019-10-04 vehicle for PMU Envelope Assistance, Training and Strategic Studies GD-26 / Supply, Installation and Commissioning of Component B – Support for Single Stage - One Desktop PCs, Accessories and IDA / 52650 Food and Market Planning Prior Request for Bids Open - International 4,500,000.00 5,272,553.13 Signed 2018-04-30 2018-05-30 2018-05-16 2018-08-14 2018-07-05 2018-08-14 2019-01-21 2019-04-15 2019-03-06 2019-06-13 2020-07-18 Envelope their maintenance support and Monitoring Program including computer training GD-27 / Supply, Installation and Commissioning of Software with customization, development, integration, Component B – Support for rollout and training including Single Stage - One IDA / 52650 Food and Market Planning Prior Request for Bids Open - International 56,664,687.50 0.00 Canceled 2018-07-12 2018-07-17 2018-09-05 2019-03-24 2019-05-07 2022-01-31 Data Centre and DR site Envelope and Monitoring Program equipment, networking and data connectivity with 3 years support and maintenance for Food Stock and Mar GD-24 / Procurement of Component B – Support for Single Stage - One Digital Weigh Bridge for LSD IDA / 52650 Food and Market Planning Post Request for Bids Limited 1,387,187.50 0.00 Canceled 2019-08-04 2019-08-09 2019-09-30 2020-04-17 2020-05-22 2020-11-18 Envelope and CSD and Monitoring Program Component C - Project management, Construction Pending GD-06 / Procurement of Single Stage - One IDA / 52650 Supervision, Technical Post Request for Bids Open - National 200,120.00 0.00 Implementati 2021-12-12 2021-12-17 2022-01-10 2022-02-09 2022-03-16 2022-09-12 Vehicle Envelope Assistance, Training and on Strategic Studies Page 2 Component C - Project management, Construction Pending GD-21 / Supply of food Single Stage - One IDA / 52650 Supervision, Technical Post Request for Bids Open - National 1,177,160.00 0.00 Implementati 2022-08-01 2022-08-06 2022-09-20 2022-10-20 2022-11-24 2023-05-23 testing laboratory equipment Envelope Assistance, Training and on Strategic Studies GD-27A / Supply, Installation and Commissioning of Online Component B – Support for food stock and market Single Stage - One IDA / 52650 Food and Market Planning Prior Request for Bids Open - International 31,000,000.00 30,861,918.56 Signed 2020-06-18 2020-09-01 2020-06-23 2020-09-17 2020-08-10 2020-12-10 2020-11-08 2021-04-28 2020-12-17 2021-07-28 2023-09-25 monitoring system of DG Envelope and Monitoring Program Food including data center, software etc Component C - Project management, Construction Pending GD-07 / Laptop, Computer, Single Stage - One IDA / 52650 Supervision, Technical Post Request for Bids Open - National 48,000.00 0.00 Implementati 2021-07-11 2021-07-16 2021-08-06 2021-09-05 2021-10-10 2022-04-08 Printer, Photocopier etc. Envelope Assistance, Training and on Strategic Studies Component C - Project GD-09 / Procurement of management, Construction Pending Single Stage - One Furniture for PMU and Silo IDA / 52650 Supervision, Technical Post Request for Bids Open - National 41,000.00 0.00 Implementati 2021-06-13 2021-06-18 2021-07-09 2021-08-08 2021-09-12 2022-03-11 Envelope offices Assistance, Training and on Strategic Studies NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component C - Project NCS-01 / Outsourcing of management, Construction Pending Manpower through a Service Single Stage - One IDA / 52650 Supervision, Technical Post Request for Bids Open - National 317,830.00 0.00 Implementati 2021-02-02 2021-02-07 2021-03-01 2021-03-31 2021-05-05 2023-10-31 provider (Non Consulting Envelope Assistance, Training and on Service)-GD-05 Strategic Studies CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-26 / CA Firm for Component A – Construction Quality Based Independent Internal Audit of IDA / 52650 of Modern Grain Storage Silo Prior Open - International 210,000.00 94,604.19 Signed 2015-11-27 2015-11-09 Selection MFSFP Facilities MFSP/SD-1: Design and Component A – Construction Supervision Consul / MFSP/SD- Quality Based IDA / 52650 of Modern Grain Storage Silo Prior Open - International 8,000,000.00 8,502,853.38 Signed 2015-11-23 2015-12-21 1: Design and Supervision Selection Facilities Consultants (DSC) Component A – Construction SD-21 / Integrated Food Quality Based IDA / 52650 of Modern Grain Storage Silo Prior Open - International 8,000,000.00 11,019,316.28 Signed 2016-03-03 2016-07-28 Policy Research Program Selection Facilities Component A – Construction SD-3 / Monitoring and Quality Based IDA / 52650 of Modern Grain Storage Silo Prior Open - International 8,750,000.00 587,140.50 Signed 2015-11-27 2015-12-28 Impact Evaluation of MFSFP Selection Facilities Component C - Project MFSP/SD-1 Assignment-B management, Construction (Supervision) / Design and Quality Based IDA / 52650 Supervision, Technical Prior Open - International 3,000,000.00 5,293,080.04 Signed 2015-11-23 2015-10-21 Supervision Consultants- Selection Assistance, Training and Construction Supervision Strategic Studies MFSP-138-SBC-CF-SD-4 / Component A – Construction Service Provider for the Quality Based IDA / 52650 of Modern Grain Storage Silo Prior Open - International 1,250,000.00 2,188,700.18 Signed 2016-07-19 2016-07-17 Distribution of Household Selection Facilities silos and Related Service SD-2 / ICT Consulting Firm(s) Component B – Support for Quality Based for Online Food Stock and IDA / 52650 Food and Market Planning Prior Open - International 0.00 1,862,500.00 Signed 2016-10-12 2016-11-30 Selection Market Monitoring System and Monitoring Program Component C - Project SD-40 / Strategic management, Construction Quality And Cost- Studies/Survey for Future IDA / 52650 Supervision, Technical Prior Open - International 3,750,000.00 0.00 Canceled 2019-06-09 2019-06-30 2019-08-13 2019-09-10 2019-10-10 2020-02-21 2020-04-05 2021-04-05 Based Selection Project Preparation Assistance, Training and Strategic Studies Component C - Project SD-42 / Feasibility study for management, Construction Quality And Cost- the construction of a concrete IDA / 52650 Supervision, Technical Prior Open - International 1,250,000.00 0.00 Canceled 2018-09-12 2019-03-26 2018-10-03 2019-04-05 2018-12-02 2019-09-04 2018-12-30 2019-10-28 2019-01-29 2020-01-29 2019-03-05 2019-04-18 2020-04-17 Based Selection grain silo at Paira Sea Port Assistance, Training and Strategic Studies Component C - Project SD-41 / Feasibility Study for management, Construction Quality And Cost- the BMRE of Ashuganj Wheat IDA / 52650 Supervision, Technical Post Open - International 300,000.00 476,515.20 Signed 2018-09-18 2018-10-25 2018-10-09 2019-05-21 2018-12-08 2019-07-10 2019-01-05 2019-08-29 2019-02-04 2020-01-29 2019-03-11 2020-01-29 2019-04-24 2020-07-22 2020-04-23 Based Selection Silo Assistance, Training and Strategic Studies Component C - Project SD-30 / Consulting Firm for management, Construction Quality And Cost- Overseas Study Tour and IDA / 52650 Supervision, Technical Prior Open - International 1,000,000.00 0.00 Canceled 2019-01-02 2019-02-01 2019-04-26 2019-05-26 2019-07-25 2019-11-06 2019-12-11 2023-01-24 Based Selection Training Program Assistance, Training and Strategic Studies Component C - Project MFSP/SD-32 / Supervision management, Construction Quality And Cost- Under consultant for silo IDA / 52650 Supervision, Technical Prior Open - International 4,709,000.00 0.00 2020-07-08 2020-07-12 2020-07-29 2020-07-13 2020-09-11 2021-01-17 2020-10-09 2021-03-25 2020-11-08 2021-07-16 2020-12-13 2021-09-23 2021-01-17 2023-10-26 Based Selection Implementation construction Assistance, Training and Strategic Studies INDIVIDUAL CONSULTANTS Page 3 Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Senior Procurement Specialist Component A – Construction Individual / Senior Procurement IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 200,000.00 202,083.66 Signed 2014-07-13 2014-09-14 Specialist Facilities Selection MFSP-75-SBPF-CI-SD-13 / Component A – Construction Individual Senior Financial Management IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 0.00 194,791.58 Signed 2014-09-03 2014-08-21 Specialist Facilities Selection SD-28 / International Component A – Construction Individual Consultant for Food Policy IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 811,600.00 539,405.38 Signed 2016-12-28 2017-01-03 Research Program. Facilities Selection Draft Netotiated Contract / Component A – Construction Individual Senior Outreach and Public IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 138,000.00 136,582.89 Signed 2014-07-16 2014-08-06 Awareness Specialist Facilities Selection Draft Negotiated Contract / Contract for Consulting Component A – Construction Individual Services for Senior Social IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 150,000.00 151,767.93 Signed 2014-07-17 2014-08-06 Specialist (Individual Facilities Selection Consultant) Senior Environmental Component A – Construction Individual Specialist / Contract for IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 153,000.00 155,197.76 Signed 2014-07-28 2014-08-27 Consultancy Services Facilities Selection MFSP-85-SBCC-CI-SD-16 / Component A – Construction Individual International Procurement IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 625,000.00 568,522.00 Signed 2014-12-03 2015-01-14 Expert Facilities Selection MFSP-74-SCC-CI-SD-5 / Component A – Construction Individual Senior Technical Specialist IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 200,000.00 171,703.84 Signed 2015-02-02 2015-02-03 (Mechanical) Facilities Selection Component A – Construction Individual SD-9 / Procurement Analyst IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 150,000.00 133,119.01 Signed 2015-02-02 2015-02-03 Facilities Selection Component A – Construction Individual SD-6 / Senior Technical IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 200,000.00 133,119.01 Signed 2015-02-02 2015-02-03 Specialist (Civil) Facilities Selection Component A – Construction Individual SD-16 / International IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 625,000.00 644,711.36 Signed 2015-06-22 2015-06-30 Technical Expert of IPP Facilities Selection SD- 29 / Senior National Component A – Construction Individual Individual Consultant for Food IDA / 52650 of Modern Grain Storage Silo Prior Consultant Open 0.00 221,882.19 Canceled 2016-08-11 Policy Research Program Facilities Selection Component C - Project SD-12B / Senior Outreach management, Construction Individual and Public Awareness IDA / 52650 Supervision, Technical Post Consultant Open 132,400.00 40,300.35 Completed 2017-07-27 2019-03-25 2017-10-23 2019-04-21 2017-11-06 2019-04-24 2017-12-25 2019-05-02 2019-04-19 2020-06-30 Specialist Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-18B / Technical Site Under IDA / 52650 Supervision, Technical Post Consultant Open 22,500.00 0.00 2017-09-11 2017-08-27 2017-10-30 2017-11-20 2018-01-01 2020-03-11 Specialist (Civil) Implementation Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-13B / Senior Financial IDA / 52650 Supervision, Technical Post Consultant Open 50,000.00 90,587.18 Signed 2018-01-29 2017-12-28 2018-02-18 2018-03-20 2018-03-11 2018-03-07 2018-04-15 2018-05-03 2019-04-15 Management Specialist Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-10B / Senior IDA / 52650 Supervision, Technical Prior Consultant Open 121,000.00 0.00 Canceled 2018-01-29 2018-01-29 2018-01-29 2018-01-29 2018-10-06 Environmental Specialist Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-9/B / Procurement IDA / 52650 Supervision, Technical Post Consultant Open 118,125.00 242,362.40 Signed 2018-02-18 2018-02-19 2018-03-19 2018-03-29 2018-03-29 2018-03-29 2018-05-03 2018-05-10 2020-06-30 Analyst Assistance, Training and Selection Strategic Studies Component C - Project SD-29/1 / Senior National management, Construction Individual Consultant for Food Policy IDA / 52650 Supervision, Technical Prior Consultant Open 328,863.80 153,677.07 Signed 2018-04-26 2018-05-08 2018-04-26 2017-04-11 2018-04-26 2018-05-14 2018-04-26 2017-05-23 2020-06-30 Research Program Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-36 / Senior DPP Specialist IDA / 52650 Supervision, Technical Post Consultant Open 30,000.00 28,141.34 Completed 2018-06-17 2018-05-29 2018-08-05 2019-06-10 2018-08-26 2019-06-12 2018-09-30 2019-06-17 2019-03-29 2019-12-15 Assistance, Training and Selection Strategic Studies Component B – Support for SD-38 / Institution for IDA / 52650 Food and Market Planning Prior Direct Selection Direct 362,500.00 0.00 Canceled 2018-02-05 2018-02-15 2018-02-19 2018-04-06 2020-12-31 Technical Review and Monitoring Program Component C - Project management, Construction Individual SD-11A / Senior Social IDA / 52650 Supervision, Technical Post Consultant Open 235,000.00 80,309.34 Signed 2018-06-25 2018-07-02 2018-08-13 2018-08-12 2018-09-03 2018-08-13 2018-10-08 2018-08-29 2020-06-30 Specialist Assistance, Training and Selection Strategic Studies Page 4 Component C - Project management, Construction Individual SD-6A / Senior Technical IDA / 52650 Supervision, Technical Post Consultant Open 250,000.00 101,143.88 Signed 2018-07-02 2018-07-02 2018-08-27 2018-09-03 2018-09-17 2018-09-04 2018-10-22 2018-10-08 2020-07-08 Specialist (Civil) Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-5A / Senior Technical IDA / 52650 Supervision, Technical Post Consultant Open 220,000.00 0.00 Canceled 2018-07-05 2018-10-04 2018-08-31 2018-09-30 2018-11-13 2020-07-17 Specialist (Mechanical) Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-8A / Senior Procurement IDA / 52650 Supervision, Technical Post Consultant Open 281,250.00 106,174.05 Completed 2018-07-05 2018-07-02 2018-08-31 2018-09-03 2018-09-30 2018-09-04 2018-11-13 2019-01-16 2020-07-17 2021-01-14 Specialist Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-10A / Senior IDA / 52650 Supervision, Technical Post Consultant Open 157,500.00 69,879.71 Signed 2018-07-11 2018-07-02 2018-09-06 2018-09-03 2018-10-06 2018-09-04 2018-11-19 2018-10-01 2020-07-23 Environmental Specialist Assistance, Training and Selection Strategic Studies Component C - Project management, Construction SD-38/1 / Institution for IDA / 52650 Supervision, Technical Post Direct Selection Direct 362,500.00 269,601.77 Signed 2018-07-12 2018-07-25 2018-08-01 2018-07-04 2018-10-05 2018-08-30 2019-04-03 Technical Review Assistance, Training and Strategic Studies Component C - Project management, Construction Individual MFSP/SD-49 / Senior Gender IDA / 52650 Supervision, Technical Post Consultant Open 84,755.74 83,783.45 Signed 2020-11-18 2021-03-09 2021-01-06 2021-06-23 2021-01-27 2021-06-21 2021-03-03 2021-08-01 2023-08-30 Specialist Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-33 / Senior Technical Under IDA / 52650 Supervision, Technical Post Consultant Open 145,100.00 116,538.25 2020-11-26 2020-12-06 2021-01-30 2021-09-14 2021-02-20 2021-09-14 2021-03-27 2021-09-23 Specialist (Mechanical) Implementation Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-51 / Senior Procurement IDA / 52650 Supervision, Technical Post Consultant Open 125,760.00 92,656.63 Signed 2020-11-26 2020-12-06 2021-01-30 2021-03-15 2021-02-20 2021-03-16 2021-03-27 2021-04-19 2021-09-23 Specialist Assistance, Training and Selection Strategic Studies Component C - Project SD-45 / Senior National management, Construction Individual Consultant for Food Policy IDA / 52650 Supervision, Technical Post Consultant Open 24,650.00 23,897.42 Signed 2020-12-06 2020-12-14 2021-02-09 2021-06-06 2021-03-02 2021-06-06 2021-04-06 2021-07-11 2021-10-03 Research Program Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-35 / Senior Technical Pending IDA / 52650 Supervision, Technical Post Consultant Open 43,530.00 0.00 2021-12-28 2022-08-20 2022-09-10 2022-10-15 2023-10-15 Specialist (Electrical) Implementation Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-37 / Senior Financial Pending IDA / 52650 Supervision, Technical Post Consultant Open 106,410.00 0.00 2021-06-07 2021-07-26 2021-08-16 2021-09-20 2023-07-22 Management Specialist Implementation Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual MFSP-SD-40 / Senior Social IDA / 52650 Supervision, Technical Post Consultant Open 21,770.00 25,189.22 Signed 2021-06-03 2016-05-30 2021-07-22 2021-09-08 2021-08-12 2021-09-14 2021-09-16 2021-10-05 2022-03-15 Specialist (Intermittent) Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-46 / Accountant cum IDA / 52650 Supervision, Technical Post Consultant Open 41,270.00 39,059.59 Signed 2021-06-03 2014-08-19 2021-07-22 2021-07-11 2021-08-12 2021-07-11 2021-09-16 2021-07-19 2024-01-04 Cashier Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-47 / Accounts Officer IDA / 52650 Supervision, Technical Post Consultant Open 77,390.00 74,696.16 Signed 2021-06-03 2014-08-20 2021-07-22 2021-07-11 2021-08-12 2021-07-11 2021-09-16 2021-07-19 2024-01-04 Assistance, Training and Selection Strategic Studies Component C - Project SD-48/1 / Technical Site management, Construction Individual Under Specialist- IDA / 52650 Supervision, Technical Post Consultant Open 66,700.00 0.00 2021-06-17 2021-08-31 2021-09-20 2021-10-11 2021-11-15 2023-10-16 Implementation Civil/Mechanical/Electrical Assistance, Training and Selection Strategic Studies Component C - Project SD-48/2 / Technical Site management, Construction Individual Pending Specialist- IDA / 52650 Supervision, Technical Post Consultant Open 66,700.00 0.00 2021-06-17 2021-09-20 2021-10-11 2021-11-15 2023-10-16 Implementation Civil/Mechanical/Electrical Assistance, Training and Selection Strategic Studies Component C - Project SD-48/3 / Technical Site management, Construction Individual Pending Specialist- IDA / 52650 Supervision, Technical Post Consultant Open 66,700.00 0.00 2021-07-22 2021-09-16 2021-10-07 2021-11-11 2023-10-12 Implementation Civil/Mechanical/Electrical Assistance, Training and Selection Strategic Studies Component C - Project SD-48/4 / Technical Site management, Construction Individual Pending Specialist- IDA / 52650 Supervision, Technical Post Consultant Open 66,700.00 0.00 2021-07-21 2021-09-15 2021-10-06 2021-11-10 2023-10-11 Implementation Civil/Mechanical/Electrical Assistance, Training and Selection Strategic Studies Component C - Project management, Construction Individual SD-49/1 / Senior Gender Pending IDA / 52650 Supervision, Technical Post Consultant Open 80,000.00 0.00 2021-10-25 2021-12-13 2022-01-03 2022-02-07 2022-08-06 Specialist Implementation Assistance, Training and Selection Strategic Studies Page 5 Component C - Project SD-48/5 / Technical Site management, Construction Individual Pending Specialist- IDA / 52650 Supervision, Technical Post Consultant Open 66,700.00 0.00 2021-10-26 2021-12-21 2022-01-11 2022-02-15 2024-01-16 Implementation Civil/Mechanical/Electrical Assistance, Training and Selection Strategic Studies Component C - Project SD-48/6 / Technical Site management, Construction Individual Pending Specialist- IDA / 52650 Supervision, Technical Post Consultant Open 66,700.00 0.00 2021-10-27 2021-12-22 2022-01-12 2022-02-16 2024-01-17 Implementation Civil/Mechanical/Electrical Assistance, Training and Selection Strategic Studies Component C - Project SD-48/7 / Technical Site management, Construction Individual Pending Specialist- IDA / 52650 Supervision, Technical Post Consultant Open 66,700.00 0.00 2021-10-26 2021-12-21 2022-01-11 2022-02-15 2024-01-16 Implementation Civil/Mechanical/Electrical Assistance, Training and Selection Strategic Studies Component C - Project SD-48/8 / Technical Site management, Construction Individual Pending Specialist IDA / 52650 Supervision, Technical Post Consultant Open 66,700.00 0.00 2021-10-26 2021-12-21 2022-01-11 2022-02-15 2024-01-16 Implementation Civil/Electrical/Mechanical Assistance, Training and Selection Strategic Studies Page 6