The World Bank Dili Water Supply Project (P176687) Note to Task Teams: The following sections are system generated and can only be edited online in the Portal. Please delete this note when finalizing the document. Project Information Document (PID) Concept Stage | Date Prepared/Updated: 31-Aug-2021 | Report No: PIDC31839 Aug 31, 2021 Page 1 of 5 The World Bank Dili Water Supply Project (P176687) BASIC INFORMATION A. Basic Project Data OPS TABLE Country Project ID Parent Project ID (if any) Project Name Timor-Leste P176687 Dili Water Supply Project (P176687) Region Estimated Appraisal Date Estimated Board Date Practice Area (Lead) EAST ASIA AND PACIFIC Apr 04, 2022 May 11, 2022 Water Financing Instrument Borrower(s) Implementing Agency Investment Project Financing Ministry of Public BTL Empresa Publica Works,Ministry of Finance Proposed Development Objective(s) To increase the usage of cleaner and more reliable piped water supported and to improve the operational performance of the water utility in the project area. PROJECT FINANCING DATA (US$, Millions) SUMMARY-NewFin1 Total Project Cost 95.00 Total Financing 95.00 of which IBRD/IDA 95.00 Financing Gap 0.00 DETAILS -NewFinEnh1 World Bank Group Financing International Development Association (IDA) 95.00 IDA Grant 95.00 Environmental and Social Risk Classification Concept Review Decision Substantial Track II-The review did authorize the preparation to continue Aug 31, 2021 Page 2 of 5 The World Bank Dili Water Supply Project (P176687) Note to Task Teams: End of system generated content, document is editable from here. Please delete this note when finalizing the document. Other Decision (as needed) B. Introduction and Context Country Context Sectoral and Institutional Context Relationship to CPF C. Proposed Development Objective(s) Note to Task Teams: The PDO has been pre-populated from the datasheet for the first time for your convenience. Please keep it up to date whenever it is changed in the datasheet. Please delete this note when finalizing the document. to increase piped water access and improve the operational performance of the water utility in the project area. Key Results (From PCN) D. Concept Description Note to Task Teams: The following sections are system generated and can only be edited online in the Portal. Please delete this note when finalizing the document. Aug 31, 2021 Page 3 of 5 The World Bank Dili Water Supply Project (P176687) Legal Operational Policies Triggered? Projects on International Waterways OP 7.50 No Projects in Disputed Areas OP 7.60 No Summary of Screening of Environmental and Social Risks and Impacts . Note to Task Teams: This summary section is downloaded from the PCN data sheet and is editable. It should match the text provided by E&S specialist. If it is revised after the initial download the task team must manually update the summary in this section. Please delete this note when finalizing the document. Note: To view the Environmental and Social Risks and Impacts, please refer to the Concept Stage ESRS Document. Please delete this note when finalizing the document. . CONTACT POINT World Bank IJsbrand Harko de Jong, Christophe Prevost Lead Water Resources Management Specialist Borrower/Client/Recipient Ministry of Public Works Salvador Eugénio Soares Minister of Public Works info@mof.gov.tl Ministry of Finance Rui Augusto Gomes Minister of Finance info@mof.gov.tl Implementing Agencies Aug 31, 2021 Page 4 of 5 The World Bank Dili Water Supply Project (P176687) BTL Empresa Publica Carlos Peloi Dos Reis President of BTL carlos.dosreis@btl.tl Aleixo dos Santos Project Director aleixo.santos@btl.tl FOR MORE INFORMATION CONTACT The World Bank 1818 H Street, NW Washington, D.C. 20433 Telephone: (202) 473-1000 Web: http://www.worldbank.org/projects APPROVAL Task Team Leader(s): IJsbrand Harko de Jong, Christophe Prevost Approved By APPROVALTBL Country Director: Bolormaa Amgaabazar 22-Sep-2021 Note to Task Teams: End of system generated content, document is editable from here. Please delete this note when finalizing the document. Aug 31, 2021 Page 5 of 5