Procurement Plan
  I.        General

       1.     Project Information
              Country: Malawi
              Project Name:      Malawi Agricultural Sector Wide Approach Project II (ASWAP II)
              Project ID: P164445

       2.     Project Implementation Agency: Ministry of Agriculture, Irrigation and Water Development (MoAIWD)

       3.     Date of the Procurement Plan: January, 2018

       4.     Period Covered by this procurement plan: January, 2018 -31st December,2018

 II.        Preamble

       In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement
       Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear
       and update Procurement Plans and conduct all procurement transactions for the Project.

       This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The
       following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan
       as required under paragraph 4.4 of the Procurement Regulations as set forth in STEP.

III.        Bank’s Standard Procurement Documents:

       The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement
       and those contracts as specified in the Procurement Plan tables in STEP.

IV.         National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when
            approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement
            procedures may be used.
            When the Borrower uses its own national open competitive procurement arrangements as set forth in The Public
            Procurement Act, 2003 and The Public Procurement Regulations, 2004, such arrangements shall be subject to paragraph
            5.4 of the Procurement Regulations under the following conditions:

                   o    Provision of “set-asides” contracts for small enterprises shall not be applied.

                   o    Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific
                        & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the
                        Bank on case to case basis.


            When other national procurement arrangements other than national open competitive procurement arrangements are
            applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations.

            In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for
            proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations
            present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application
            of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to
            sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1.

 V.          Prequalification : N/A

 VI.         Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable.

VII.          Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not
              Applicable.


                                                                     1
VIII.    Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works).
           (a)    Goods: N/A

           (b)       Works: N/A

           Domestic preference is not applicable for National Open Competitive Procurement

 IX.       Other Relevant Procurement Information

           Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations
           of Urgent Need of Assistance or Capacity Constraints etc.--NONE

  X.       Procurement Prior Review Thresholds (US$ millions): The overall Project procurement Risk is Substantial. The
           project being a non-emergency project, there would be generally prior reviews of cases unless specifically indicated
           in the Procurement Plan as a special measure.

       Post Review: All contracts not subject to prior review shall be subject to post review.

 XI.       Procurement Prior Review Thresholds Based on High Risk Rating (US$ millions)



                           Works                      Goods, IT and Non-Consulting Services           Shortlist of National
                                                                                                         Consultants

            Open            Open         Request          Open          Open         Request      Consulting     Engineering
        International      National        for        International    National        for         Services           &
                                        Quotation                                   Quotation                    Construction
                 <                ≥                         <              >                           ≤         Supervision
                                            ≥                                            <
                                                                                                                       ≤


                 7                7        0.2             1.0            1.0           0.1           0.2             0.3




                                                                 2
                   PROCUREMENT PACKAGES WITH METHODS AND TIME SCHEDULES OF GOOD AND NON CONSULTANCY AS PER COMPONET

Sr. No   Contract           QTY      Unit   Est. Cost        Review    Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                        (US$)            by Bank   Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                             (Prior/   h                                                (Yes/ No)    e           opening            Signature
                                                             Post)                                                                   (Yes/No)
                                                      Component 1: Sustainable Agriculture Productivity and Diversification

                                                                        (a) GOODS
G.1.01   Motor               2                               Post                             Qualifying                No           No          01- 02 -18         01 -03 -018
         Vehicles for                No     200,000                    Open       RFB         criteria     Single
         Zomba and                                                     National                            stage one
         Chitipa                                                                                           Envelope
         districts
G.1.02   Field             Various   No     15,0000          Post                 RFQ         Qualifying                No           No          01- 02 -18         01 -03 -018
         Equipment                                                     Open                   criteria     Single
         For soil                                                      National                            stage one
         sampling -                                                                                        Envelope
         DLRC
G.1.03   IT Equipment      Various   No     75,000.00        Post      Open       RFQ         Qualifying   Single       No           No          01- 02 -18         01 -03 -018
         (Laptops,                                                     National               criteria     stage one
         Communicatio                                                                                      Envelope
         n equipment)
         DLRC
G.1.04      Supply and                                                            RFB                                                            Already opened     RAF
            delivery of
              Pinting        2       Each                               Open                  Qualifying      Single         No           No
             Machines                                          Post    National                Criteria     stage one
                                             432,869.03
            (Colour to                                                                                      Envelope
             Plate and
              Folding
             Machine)
G.1.05      Supply and                                                               RFB                                                         Already opened     RAF
            delivery of
             Printing        1       Each                      Post     Open                  Qualifying      Single         No           No
             Machines                        147,360.38                National                Criteria     stage one
         (Book Binding                                                                                      Envelope
             Machine
             Machine)
G.1.06      Laboratory                                                               RFQ                                                         Already opened     RAF
            Equipment        1       Each                      Post     Open                  Qualifying      Single         No           No
           (Plant tissue                      23,292.61                National                Criteria     stage one
          Homogenizer)                                                                                      Envelope



                                                                                        3
Sr. No   Contract           QTY      Unit   Est. Cost     Review    Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                        (US$)         by Bank   Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                          (Prior/   h                                                (Yes/ No)    e           opening            Signature
                                                          Post)                                                                   (Yes/No)
G.1.07      Laboratory                                                            RFQ                                                         Already opened     RAF
            Equipment        1       Each                   Post     Open                  Qualifying      Single       No           No
           (Nano Drop                                               National                Criteria     stage one
               One                            16,297.46                                                  Envelope
         Spectophotom
               eter)
G.1.08      Laboratory                                                            RFQ                                                         Already opened     RAF
            Equipment        1       Each                   Post     Open                  Qualifying      Single       No           No
            (Ultra Low                                              National                Criteria     stage one
           Temperature                                                                                   Envelope
           Freezer and                        45,165.40
              Bench
         Microcentrifug
                 e)
G.1.09       Procure       Various    No                    Post                  RFQ                                                         Already opened     RAF
             Artificial                       20,108.57              Open                  Qualifying      Single       No           No
          Inseminations                                             National                Criteria     stage one
          Kits (Procure                                                                                  Envelope
         liquid nitrogen
              tanks)

G.1.10   Procurement                  No                    Post                  RFQ                                                         Already opened     RAF
           of training     Various            14,057.14             Limited                Qualifying      Single       No           No
          materials for                                                                     Criteria     stage one
          farmers (for                                                                                   Envelope
         goats, rabbits,
            pigs and
             chicken
           production)

G.1.11                     Various    No                    Post                  RFQ                                                           Already opened         RAF
          Procurement
                                                                    Limited                Qualifying      Single       No           No
            of office                          1,414.29
                                                                                            Criteria     stage one
           stationary
                                                                                                         Envelope
G.1.12    Procurement      Various    No                    Post                  RFQ                                                           Already opened         RAF
         of Herbicides                                              Limited                Qualifying      Single       No           No
         and Fertilizers                                                                    Criteria     stage one
                                               1,414.29
           (Inputs for                                                                                   Envelope
              cattle
            breeding)



                                                                                     4
Sr. No   Contract          QTY      Unit   Est. Cost     Review    Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                       (US$)         by Bank   Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                         (Prior/   h                                                (Yes/ No)    e           opening            Signature
                                                         Post)                                                                   (Yes/No)
G.1.13       Procure      Various    No                    Post                  RFQ                                                           Already opened        RAF
           protective                                              Limited                Qualifying      Single       No           No
                                              4,921.44
            clothings                                                                      Criteria     stage one
          (safeguards)                                                                                  Envelope
G.1.20   Tissue Culture                                                       RFQ                                                            01- 02 -18         01 -03 -018
           Laboratory
          Reagents for    Various    No                            Limited                Qualifying      Single       No           No
                                             24,310.33
             banana                                        Post                            Criteria     stage one
         microprogation                                                                                 Envelope
             -DARS
G.1.21   Tissue Culture                                                          RFQ                                                         01- 02 -18         01 -03 -018
           Laboratory
         Consumables      Various    No                    Post    Limited                Qualifying      Single       No           No
                                             12,413.79
           for banana                                                                      Criteria     stage one
         microprogation                                                                                 Envelope
             -DARS
G.1.22    Farm inputs                                                            RFQ                                                         01- 02 -18         01 -03 -018
               for        Various    No                    Post    Limited                Qualifying      Single       No           No
         maintenance of                                                                    Criteria     stage one
             banana                                                                                     Envelope
            orchards-                         5,176.55
             DARS


G.1.23     Laboratory                                                            RFQ                                                         01- 02 -18         01 -03 -018
           Equipment        3       Each                   Post     Open                  Qualifying      Single       No           No
         (Autoclaves) –                                            National                Criteria     stage one
              for                                                                                       Envelope
          Lunyangwa,                         31,034.48
          LUANAR &
           Bvumbwe
             DARS
G.1.24                                                                           RFQ                                                         01- 02 -18         01 -03 -018
          Procurement
                          Various    No                    Post    Limited                Qualifying      Single       No           No
           of planting
                                                                                           Criteria     stage one
          pots, manure
                                                                                                        Envelope
         and river sand                       5,213.79
         for hardening
           of bananas-
              DARS




                                                                                    5
Sr. No   Contract          QTY      Unit    Est. Cost     Review    Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                        (US$)         by Bank   Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                          (Prior/   h                                                (Yes/ No)    e           opening            Signature
                                                          Post)                                                                   (Yes/No)
G.1.25      Procure       Various    No                     Post    Limited       RFQ      Qualifying      Single       No           No       01- 02 -18         01 -03 -018
           Protective                           25,700                                      Criteria     stage one
          clothing for                                                                                   Envelope
           labs a and
          operations -
             DARS

G.1.26     Laboratory     Various    No                     Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
           reagents for                                             National                Criteria     stage one
              indexing                                                                                   Envelope
                                                23,943
           cassava and
         sweet potato-
                DARS
G.1.27        Planting    19,000    Bundl                   Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
          materials for              es                             National                Criteria     stage one
           cassava and                                                                                   Envelope
          sweet potato
                                                42,000
               seed for
            secondary
             nurseries-
                DARS
G.1.28   Equipment for      2        No                     Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
             collecting                                             National                Criteria     stage one
             yams and                             5,715                                                  Envelope
             cocoyams
         (GPS)-DARS
G.1.29      In puts for   Various    No                     Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         production of                                              National                Criteria     stage one
               legume                                                                                    Envelope
                                                39,800
           breeder and
            foundation
           seed-DARS
G.1.30   IT Equipment     Various    No                     Post    Limited    RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
                 and                                                                        Criteria     stage one
          accessories –                                                                                  Envelope
                DARS
                                                13,500




                                                                                     6
Sr. No   Contract            QTY      Unit   Est. Cost    Review    Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                         (US$)        by Bank   Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                          (Prior/   h                                                (Yes/ No)    e           opening            Signature
                                                          Post)                                                                   (Yes/No)
G.1.31     Accelerated        2        No                   Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
              aging                                                 National                Criteria     stage one
          chambers for                                                                                   Envelope
           seed vigor                            5,000
         testing-DARS


G.1.32   Analytical and       2        No                   Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
           prescision                                               National                Criteria     stage one
          balances for                           5,000                                                   Envelope
         satellite labs -
             DARS
G.1.33                      Various    No                   Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
          Germination
                                                 3,600              National                Criteria     stage one
          paper-DARS
                                                                                                         Envelope
G.1.34   Seed quality         5        No                   Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         equipment and                                              National                Criteria     stage one
         soil analysis                                                                                   Envelope
                                                 10,000
         tools( meters-
         PH and EC
         meters)-DARS
G.1.35   Sampling and         10       No                   Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         pest detection                          2,500              National                Criteria     stage one
         tools-DARS                                                                                      Envelope
G.1.36   Glassware for      Various    No                   Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         soil analysis-                          5,500              National                Criteria     stage one
         DARS                                                                                            Envelope
G.1.37                       2,000     No                   Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         Pheromone
                                                 4,500              National                Criteria     stage one
         traps - DARS
                                                                                                         Envelope
G.1.38   Temperature          1        No                   Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         controlled                                                 National                Criteria     stage one
                                                 4,000
         water bath-                                                                                     Envelope
         DARS
G.1.39   Automated            3        No                   Post     Open      RFQ         Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         heater and                                                 National                Criteria     stage one
         humidifies-                                                                                     Envelope
                                                 3,500
         DARS




                                                                                     7
Sr. No   Contract             QTY      Unit   Est. Cost    Review    Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                          (US$)        by Bank   Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                           (Prior/   h                                                (Yes/ No)    e           opening            Signature
                                                           Post)                                                                   (Yes/No)
G.1.39   Inputs for area     Various    No                   Post     Open      RFQ         Qualifying      Single         No         No       01- 02 -18         01 -03 -018
         specific                                                    National                Criteria     stage one
         fertilizer                               51,000                                                  Envelope
         demonstrations
         -DARS
G.1.39   Production of       Variuos    No                   Post     Open      RFQ         Qualifying      Single         No           No     01- 02 -18         01 -03 -018
         maps for area                                               National                Criteria     stage one
         specific fert.                           15,000                                                  Envelope
         Recommendati
         ons-DARS
G.1.40   Freezers in           3        No                   Post     Open      RFQ         Qualifying      Single         No           No     01- 02 -18         01 -03 -018
         genebank-                                12,000             National                Criteria     stage one
         DARS                                                                                             Envelope
G.1.41   Drier for             1        No                   Post     Open      RFQ         Qualifying      Single         No           No     01- 02 -18         01 -03 -018
         drying                                                      National                Criteria     stage one
                                                  20,000
         germplasm-                                                                                       Envelope
         DARS
G.1.42   IT Equipment        Various   No     6,000        Post      Limited    RFQ         Qualifying   Single       No           No          01- 02 -18         01 -03 -018
         (Laptop,                                                                           criteria     stage one
         design                                                                                          Envelope
         software and
         scanner) -
         DAES

G.1.43   Protective           200      No     15,000       Post                 RFQ         Qualifying                No           No          01- 02 -18         01 -03 -018
         wear for                                                    Limited                criteria     Single
         frontline staff -                                                                               stage one
         DAES                                                                                            Envelope
G.1.44   Procurement          1000      No        43200                            RFQ                                                         01- 02 -18         01 -03 -018
         of pheromone                                        Post     Open                  Qualifying      Single         No           No
         traps for                                                   National                Criteria     stage one
         trapping                                                                                         Envelope
         insects in the
         field –DCD




                                                                                      8
Sr. No   Contract            QTY      Unit     Est. Cost       Review    Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                           (US$)           by Bank   Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                               (Prior/   h                                                (Yes/ No)    e           opening            Signature
                                                               Post)                                                                   (Yes/No)
G.1.45   Start- up          Various    No         230,100                              RFB                                                         01- 02 -18         01 -03 -018
         construction                                            Post     Open                  Qualifying      Single       No           No
         materials for                                                   National                Criteria     stage one
         simple green                                                                                         Envelope
         house facilities
         for the
         propagation of
         bananas

         DCD

G.1.46   Procurement                                                                   RFQ                                                         01- 02 -18         01 -03 -018
         of seed to be                                           Post     Open                  Qualifying      Single       No           No
         used for                                                        National                Criteria     stage one
         mounting                                                                                             Envelope
         demonstrations
         of various
         technologies in
         order to
         increase
         adoption of the
         technologies:       3,400    Kg           83,049
                             3,400    kg
         (i). zinc rich      7,200    bundle
         bean                4,000    s (50)
         (ii) iron rich     23,220    8 kg r
         bean                3,400    Kgs
         (iii). Cassava
         (iv).
         Sweetpotato
         (v) banana
         (v!) QPM
         maize
         DCD

                                                   a.
                                                   b.      Z
                                                           i
                                                           n
                                                           c




                                                                                          9
Sr. No   Contract          QTY      Unit   Est. Cost       Review    Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                       (US$)           by Bank   Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                           (Prior/   h                                                (Yes/ No)    e           opening            Signature
                                                           Post)                                                                   (Yes/No)
                                                       r
                                                       i
                                                       c
                                                       h
                                                                                   RFQ                                                         01- 02 -18         01 -03 -018
                                                             Post    Limited                Qualifying      Single       No           No
         Office                                                                              Criteria     stage one
         equipment                                                                                        Envelope
         (i). laptop
         (ii) Desktop                          6032
         (iii) Tablets       3       No
         (iv) Printers       3       No
         (v) Scanners        5       No
         DCD                 2       No
                             2       No
G.1.48   Procure          Various    No        12,740                              RFQ                                                         01- 02 -18         01 -03 -018
         protective                                          Post    Limited                Qualifying      Single       No           No
         clothing                                                                            Criteria     stage one
         (safeguards)                                                                                     Envelope
         for the
         Department of
         Crop
         Development
         (DCD)
G.1.49   Procurement      1000-1     No        43200                               RFQ                                                         01- 02 -18         01 -03 -018
         of pheromone                                        Post     Open                  Qualifying      Single       No           No
         traps for                                                   National                Criteria     stage one
         trapping                                                                                         Envelope
         insects in the
         field -DCD
                                             1,941,629




                                                                                     10
Sr. No   Contract          QTY   Unit   Est. Cost     Review      Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                    (US$)         by Bank     Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                      (Prior/     h                                                (Yes/ No)    e           opening            Signature
                                                      Post)                                                                     (Yes/No)
                                                                (b) WORKS


W.1.2    Water pump         1    No                   Post        Limited    RFQ         Qualifying   Single
         and solar                      10,854.60                                        criteria     stage one
         installation at                                                                              Envelope
         Kandiyani -
         DARS
                                        10,854.60




                                                                               (c) CONSULTANCY
C.1.01    Resettlement      1    No                   Post        Open       CQS        Rated         Single            No           No       Already opened       RAF
              Policy                                              National                            Stage Two
           Framework                      28,490.00                                                   Envelope
              (RPF)
C.1.02   Environmental      1    No                   Post        Open       CQS         Rated        Single            No           No       Already opened       RAF
           and Social                                             National                            Stage Two
          Management                                                                                  Envelope
                                          32,000.00
           Framework
             (ESMF)
C.1.03     Review of        1    No     12,000.00     Post        Open       CQS         Rated        Single            No           No       Already opened       RAF
          cooperatives                                            National                            Stage Two
           policy and                                                                                 Envelope
         implementatio
            n strategy
C.1.04     Design and       1    No                   Post        Open       CQBS        Rated        Single       No           No            Already opened       RAF
         Supervision of                                           National                            stage Two
               Land                                                                                   envelopes
          Information                    114,300.00
          Management
              System
C.1.05    Development       1    No                   Post        Open       CQS         Rated        Single       No           No            Already opened       RAF
             of Land                                              National                            stage Two
                                          99,689.00
          Information                                                                                 envelopes




                                                                                   11
Sr. No    Contract            QTY      Unit   Est. Cost      Review    Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
          Description                         (US$)          by Bank   Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                             (Prior/   h                                                (Yes/ No)    e           opening            Signature
                                                             Post)                                                                   (Yes/No)
           Management
               System
C.1.06    Livestock            1       No                    Post      Open       CQS         Rated        Single       No           No            Already opened         RAF
          Policy and                          21,413.11                National                            stage Two
          strategic plan                                                                                   envelopes
          review

                                              307,893.00




                                                                                  (d) NON CONSULTANCY
NC.1.01   Production and     Various   No     25,000.00      Post      Open       RFB        Qualifying Single                                   Already opened     RAF
          Dissemination                                                National              criteria   stage one            No           No
          of messages in                                                                                Envelope
          print, radio and
          video
NC.1.02                        20       No                     Prior                 RFQ
                                                15,624.83               Direct                               Not             No           No
                                                                                                           Applicable
          Force account
          for hardening
          bananas

                                              40,624.83

Total Component 1:                            2,301,001.43




                                                                                        12
Sr. No   Contract       QTY   Unit   Est. Cost     Review    Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                 (US$)         by Bank   Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                   (Prior/   h                                                (Yes/ No)    e           opening            Signature
                                                   Post)                                                                   (Yes/No)



                                     Component 2: Improvement of Rural Road Infrastructure for Market Access

                                                                        (a) GOODS
G.1.50   Double Cabin                                Post                           Qualifying                   No           No       01- 02 -18         01 -03 -018
         for MoTPW       1     No      70,000.00              Open         RFQ       criteria       Single
                                                             National                             stage one
                                                                                                  Envelope
G.1.51   Single Cabin   12     No     520,000.00     Post     Open         RFB      Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         4x4 Vehicles                                        National                criteria     stage one
         for District                                                                             Envelope
         Councils

G.1.52   Laptops for     5     No.      6,000.00     Post    Limited       RFQ      Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         RA                                                                          criteria     stage one
         Coordinator                                                                              Envelope
         and 4
         Engineers
G.1.53   Printers and    5     No        12,500      Post    Limited       RFQ      Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         Scanners for                                                                criteria     stage one
         RA                                                                                       Envelope



G.1.54   Computer       12     No       4,800.00     Post    Limited       RFQ      Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         desktops for                                                                criteria     stage one
         District                                                                                 Envelope
         Councils

G.1.55   Printers and                  30,000.00             Limited                Qualifying      Single                             01- 02 -18         01 -03 -018
         Scanners for   12     No                    Post                  RFQ       criteria     stage one      No           No
         District                                                                                 Envelope
         Councils




                                                                             13
Sr. No   Contract           QTY      Unit   Est. Cost       Review    Market     Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                        (US$)           by Bank   Approac    Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                            (Prior/   h                                                (Yes/ No)    e           opening            Signature
                                                            Post)                                                                   (Yes/No)
G.1.56   Geographic          12       No.      4,800.00       Post    Limited       RFQ      Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         Positioning                                                                          criteria     stage one
         System (GPS)                                                                                      Envelope
         Equipment for
         District
         Councils
G.1.57   Procurement       Various    No        48,629        Post     Open         RFQ      Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         of Protective                                                National                criteria     stage one
         clothing                                                                                          Envelope
         (Helmets,
         Masks,
         Gloves,
         Gumboots,
         Stoage
         Containers and
         work suits
G.1.58   Procurement       Various    No      28,572.00       Post    Limited       RFQ      Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         of stationary                                                                        criteria     stage one
         for soil                                                                                          Envelope
         mapping
         exercise
         (Toners, Paper,
         printing)
G.1.59   Procurement       Various    No     100,000.00       Post     Open         RFB      Qualifying      Single       No           No       01- 02 -18         01 -03 -018
         of CSA Inputs                                                National                criteria     stage one
         (Agroforestry                                                                                     Envelope
         germ plasm
         and
         equipment)
                                             1,002,502.00




                                                                                      14
Sr. No   Contract          QTY      Unit   Est. Cost      Review      Market      Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                       (US$)          by Bank     Approac     Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                          (Prior/     h                                                 (Yes/ No)    e           opening            Signature
                                                          Post)                                                                      (Yes/No)
                                                                                         (b) WORKS

W.1.3    Rehabilitation    558      Km     2,800,000      Post        Open-       RFB         Qualifying   Single
         of unpaved                                       except      National                Criteria     stage one         No           No     15-02-18           10-04-18
         roads using                                      for two                                          Envelope
         labour                                           contracts
         intensive                                        per batch
         method
         including
         bridge
         construction

W.1.01                    Various   No     1,613,701.33   Post        Open        RFB         Qualifying   Single                                  Already opened       RAF
                                                                      National                criteria     stage one    No           No
                                                                                                           Envelope

         Works-Roads




W.1.4    Upgrading of       84      km     16,800,000     Post        National-   RFB         Qualifying   Single            No           No
         unpaved roads                                    except      Open                    Criteria     stage one                                  14-02-18        25-04-18
         using Low                                        for two                                          Envelope
         Volume                                           contracts
         Sealing                                          per batch
         Methods
         including
         bridge
         construction
                                           21,213,701




                                                                                        15
Sr. No   Contract          QTY   Unit   Est. Cost      Review    Market      Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date of   Expected date
         Description                    (US$)          by Bank   Approac     Method      Options      nt Process   cation       Preferenc   bid/ proposal      of Contract
                                                       (Prior/   h                                                 (Yes/ No)    e           opening            Signature
                                                       Post)                                                                    (Yes/No)


                                                                                (c) CONSULTANCY


C.1.07   Consultancy        1    No     1,200,000.00   Prior     Open        QCBS        Rated        Single
         services for                                            Internati                            Stage Two    No           No               16-07-17        30-09-17
         Road Selection                                          onal                                 Envelope
         and Design of
         Labour
         Intensive and
         Upgrading
         Works
C.1.08   Consultancy to     1    No     120,000.00     Post      Open                                 Single       No           No               30-07-17        15-09-17
         prepare                                                 National    CQS         Rated        Stage Two
         ESMPs and                                                                                    Envelope
         RAP

C.1.09   Technical          4    No     120,000.00     Post      Opne                    Rated        Short        No           No               01-07-17        30-08-17
         Assistance for                                          National    INDV                     listing
         backstopping
         services to the
         RA for
         monitoring of
         projects (4
         Individual
         Consultants –
         Engineers)
                                        1,440,000.00




                                                                                   16
   Sr. No      Contract        QTY      Unit   Est. Cost     Review    Market      Selection    Evaluation   Procureme    Prequalifi   Domestic    Expected date of      Expected date
               Description                     (US$)         by Bank   Approac     Method       Options      nt Process   cation       Preferenc   bid/ proposal         of Contract
                                                             (Prior/   h                                                  (Yes/ No)    e           opening               Signature
                                                             Post)                                                                     (Yes/No)



                                                                                  (d) TRAINING
  CB .1.01     District       Various   No
               Councils
               ,RA,RFA                           1200,000
               ,MoTPW stff




                                                200,000.00


  Total Component 2

                                               23,501,701




Sr. No       Contract         QTY       Unit   Est. Cost     Review    Market       Selection   Evaluation   Procureme    Prequalifi   Domestic    Expected date      Expected date of
             Description                       (US$)         by Bank   Approach     Method      Options      nt Process   cation       Preferenc   of bid/ proposal   Contract
                                                             (Prior/                                                      (Yes/ No)    e           opening            Signature
                                                             Post)                                                                     (Yes/No)
                                                       Component 3: Institutional Capacity Development for NAIP

                                                                                  (a) GOODS
G.1.60                                                                              RFQ                                                            01- 02 -18         01 -03 -018
                 Laptop
               Computers -      15       No        10,274               Limited                 Qualifying      Single       No           No
                 DAPS                                          Post                              Criteria     stage one
                                                                                                              Envelope
G.1.61          Desktop                                                Limited        RFQ                                                          01- 02 -18         01 -03 -018
             Computers-DAPS                        4,384
                                20       No                    Post                                                          No           No



                                                                                        17
                                                                                           Qualifying      Single
                                                                                            Criteria     stage one
                                                                                                         Envelope
G.1.62                                                                               RFQ                                       01- 02 -18       01 -03 -018
                                                               Post     Open               Qualifying      Single    No   No
          Tablets -DAPS          200    No      82,192                 National             Criteria     stage one
                                                                                                         Envelope
G.1.63                                                                               RFQ                Single                 01- 02 -18       01 -03 -018
         National Servers-
                                  2     No     54,795          Post     Open               Qualifying   stage one    No   No
              DAPS
                                                                       National             Criteria    Envelope
                                             151,645.00
                                                                                   (b) CONSULTANCY
C.1.10       Review of       1         No    15,771.43       Post     Open         CQS     Rated        Single       No   No   Already opened          RAF
              National                                                National                          Stage Two
         Investment Policy                                                                              Envelope
C.1.11                       1         No                    Prior    Open         QCBS    Rated        Single       No   No   Already opened          RAF
                                             795,000.00               Internatio                        Stage Two
                                                                      nal                               Envelope
         Digitization of
         Old Records,
         Supply, Delivery,
         Installation of
         Hardware and
         Software as
         designed, Test
         run and
         commissioning of
         E-Permit
         Issuance System
C.1.12   Analysis of Gaps    1         No                    Post     Open         CQS     Rated        Single       No   No   Already opened          RAF
         in the Existing                                              National                          Stage Two
         Value Chains                                                                                   Envelope
         Supporting
         Agricultural
         Industrialization
         in Malawi                               15,000.00
C.1.13   Situational         1         No                    Post     Open         CQS     Rated        Single       No   No   Already opened          RAF
         Analysis of 18                                               National                          Stage Two
         Malawi’s Export                                                                                Envelope
         markets-Existing
         and New                                 13,000.00




                                                                                     18
C.1.14     Development of       1         No                      Post      Open       CQS     Rated        Single      No   No   Already opened         RAF
           food safety policy                                               National                        Stage Two
           and                                                                                              Envelope
           implementation
           strategy                                  18,000.00
C.1.15     Development of       1         No                      Post      Open       CQS     Rated        Single      No   No   Already opened         RAF
           the National                                                     National                        Stage Two
           Agriculture                                                                                      Envelope
           Management
           Information
           System                                     300,000
                                                1,156,772.00
                                                                                       (c) TRAINING
CB .1.02   AEDOs Training       200       No    696,480.82
CB.1.03    Masters Training     20        No      400,000.00
                                                 1,096,481.00
Total Component 3                               2,404,898.00
                                                               Component 4: Project Coordination and Management

                                                                         (a) NON CONSULTANCY SERVICES
NC.1.03    Insurance of         46 and    No    23,000.00         Post      Open       RFQ     Qualifying   Single                Already opened   RAF
           Motor Vehicles       120                                         National           criteria     stage one   No   No
           and Motor Cycles                                                                                 Envelope
NC.1.04    Maintenance of       46 and    No    29,000.00         Post      Open       RFQ     Qualifying   Single                Already opened   RAF
           Motor vehicles       120                                         National           criteria     stage one   No   No
           and Motor Cycles                                                                                 Envelope
NC.1.05    Provision of         Various   No    129,066           Post      Open       RFB     Qualifying   Single      No   No   Already          RAF
           Internet Services                                                National           criteria     stage one
                                                                                                            Envelope
                                                181,066.00


                                                                          (b) CONSULTANCY SERVICES
C.1.15     Project              1          No   31,592.00         Post      Open        INDV   Rated        Single      No   No   Already opened         RAF
           Coordination Ass.                                                National                        Stage One
                                                                                                            Envelope
C.1.16     Procurement of       1          No   44,249.00         Post      Open        INDV   Rated        Single      No   No   Already opened         RAF
           FMS                                                              National                        Stage One
                                                                                                            Envelope




                                                                                         19
C.1.17   Procurement of    2    No   39,370.00       Post   Open       INDV   Rated   Single      No   No   Already opened   RAF
         AFMS                                               National                  Stage One
                                                                                      Envelope
C.1.18   Procurement of    2    No   53,079.00       Post   Open       INDV   Rated   Single      No   No   Already opened   RAF
         Proc.Specialist                                    National                  Stage One
                                                                                      Envelope
C.1.20   Procurement of    1    No   15,502.00       Post   Open       INDV   Rated   Single      No   No   Already opened   RAF
         M&E Assistant                                      National                  Stage One
                                                                                      Envelope
C.1.21   Procurement of    1    No   7,095.00        Post   Open       INDV   Rated   Single      No   No   Already opened   RAF
         Documentation                                      National                  Stage One
         Officer                                                                      Envelope
C.1.22   Procurement of    1    No   29,118.00       Post   Open       INDV   Rated   Single      No   No   Already opened   RAF
         PFT TWG                                            National                  Stage One
         Assistant                                                                    Envelope
C.1.23   Procurement of    6    No   55,556.00       Post   Open       INDV   Rated   Single      No   No   Already opened   RAF
         PFT - JAs                                          National                  Stage One
                                                                                      Envelope
C.1.24   Procurement of    1    No   15,502.00       Post   Open       INDV   Rated   Single      No   No   Already opened   RAF
         PFT-                                               National                  Stage One
         Communication                                                                Envelope
         Specialist
C.1.16    Implementation   1   No                    Post   Open       INDV   Rated   Single      No   No   Already opened   RAF
            Completion               119,533.33             National                  Stage One
              Report                                                                  Envelope
                                     410,576.33
        Total                        591,642.33
        Component 4
TOTAL ALL COMPONENTS                 28,799,242.76




                                                                        20
SUMMARY

Component /Category   Value (US$)       Component Project Cost
                                               Allocation
Component 1: Total    2,301,001.43    17,210,000
Goods                 1,941,629
Works                 10,854.60
Consultancy           307,893
Non-Consultancy       40,624.83
Training              0

Component 2: Total    23,501,701      30,640,000

Goods                 1,002,502.00
Works                 21,213,701.00
Consultancy           1,440,000
Non Consultancy       0
Training              200,000

Component 3 Total     2,404,898.00    4,490,000
 Goods                151,645
Works                 0
Consultancy           1,156,772
Non Consultancy       0
Training              1,096,481.00

Component 4 Total     591,642.33      2,660,000
Consultancy           410,576.33
Non Consultancy       181,066

Grand Total           28,799,242.76   55,000,000.00



                                                   21
PROCUREMENT
                               Malawi : Second Agriculture Sector Wide Approach Support Project
PLAN
General Information
Country:                       Malawi                                     Bank’s Approval Date of the Original Procurement Plan:                    2018-02-19
                                                                                                                                     2020-03-06
                                                                          Revised Plan Date(s): (comma delineated, leave blank if none)
Project ID:                    P164445                                    GPN Date:
Project Name:                  Second Agriculture Sector Wide Approach Support Project
Loan / Credit No:              TF / A7167,     / , TF / A7166
Executing Agency(ies): Agriculture Sector Wide Support Project




WORKS
                                                                                                                                                                                                                                                                                                                                                                             Bid Evaluation
Activity Reference No. /                                                                                                                                                                                                                                                    Draft Bidding
                               Loan / Credit                                                                      Market         Procurement        Prequalification    Estimated       Actual Amount           Process   Draft Pre-qualification    Prequalification                             Specific Procurement      Bidding Documents   Proposal Submission /          Report and
        Description                                    Component            Review Type       Method                                                                                                                                                                         Document /                                                                                                               Signed Contract         Contract Completion
                                     No.                                                                         Approach           Process              (Y/N)         Amount (US$)         (US$)               Status         Documents            Evaluation Report                              Notice / Invitation          as Issued        Opening / Minutes        Recommendation for
                                                                                                                                                                                                                                                                            Justification
                                                                                                                                                                                                                                                                                                                                                                                  Award
                                                                                                                                                                                                                           Planned      Actual      Planned    Actual   Planned       Actual      Planned       Actual      Planned    Actual    Planned      Actual      Planned       Actual      Planned       Actual      Planned       Actual


 MW-ASWAP II-82927-CW-
RFQ / Establishment of a 6                     Sustainable Agricultural
                                                                                          Request for                          Single Stage - One
hacres solar powered           TF / A7167      Productivity and           Post                               Limited                                                        76,712.00               0.00   Canceled                                                                               2018-12-02                                                                                        2018-12-12                2019-01-26
                                                                                          Quotations                           Envelope
irrigation plot at Chitedze                    Diversification
Research Station




 MW-ASWAP II-153368-CW-
                                               Sustainable Agricultural                                                                                                                                    Pending
RFB / Procurement of                                                                                                           Single Stage - One
                               TF / A7166      Productivity and           Post            Request for Bids   Open - National                                               202,000.00               0.00   Implementati                                                 2020-02-28                2020-03-13                                    2020-04-24                2020-05-10                2020-06-14                2020-10-12
irrigation scheme                                                                                                              Envelope
                                               Diversification                                                                                                                                             on
construction works




GOODS
                                                                                                                                                                                                                                                                                                                                                                             Bid Evaluation
Activity Reference No. /                                                                                                                                                                                                                                                    Draft Bidding
                               Loan / Credit                                                                      Market         Procurement        Prequalification    Estimated       Actual Amount           Process   Draft Pre-qualification    Prequalification                             Specific Procurement      Bidding Documents   Proposal Submission /          Report and
        Description                                    Component            Review Type       Method                                                                                                                                                                         Document /                                                                                                               Signed Contract         Contract Completion
                                     No.                                                                         Approach           Process              (Y/N)         Amount (US$)         (US$)               Status         Documents            Evaluation Report                              Notice / Invitation          as Issued        Opening / Minutes        Recommendation for
                                                                                                                                                                                                                                                                            Justification
                                                                                                                                                                                                                                                                                                                                                                                  Award
                                                                                                                                                                                                                           Planned      Actual      Planned    Actual   Planned       Actual      Planned       Actual      Planned    Actual    Planned      Actual      Planned       Actual      Planned       Actual      Planned       Actual


 MW-ASWAP II-52531-GO-
RFB / Procurement and                          Sustainable Agricultural
                                                                                                                               Single Stage - One
Supply of Printing Machines     /              Productivity and           Post            Request for Bids   Open - National                                               432,869.00        894,974.04    Signed                                                       2018-03-10   2016-10-01   2018-03-10                                    2018-03-10   2016-10-21   2018-03-10   2016-12-05   2018-03-10   2017-02-05   2018-03-15
                                                                                                                               Envelope
(Colour to Plate and Folding                   Diversification
Machine)




 MW-ASWAP II-52563-GO-
                                               Sustainable Agricultural                                                                                                                                    Pending
RFQ / Procure Artificial                                                                  Request for                          Single Stage - One
                                /              Productivity and           Post                               Limited                                                        20,109.00               0.00   Implementati                                                                           2018-03-10                                                                                        2018-03-10                2018-03-15
Inseminations Kits (Procure                                                               Quotations                           Envelope
                                               Diversification                                                                                                                                             on
liquid nitrogen tanks)




 MW-ASWAP II-52591-GO-                         Sustainable Agricultural
                                                                                          Request for                          Single Stage - One
RFQ / Procurement of            /              Productivity and           Post                               Limited                                                        14,057.00         13,666.68    Signed                                                                                 2018-03-10   2016-12-12                                                                           2018-03-10   2017-04-10   2018-03-15
                                                                                          Quotations                           Envelope
Training Materials for Goats                   Diversification




 MW-ASWAP II-52572-GO-
                                               Sustainable Agricultural
RFQ / Procurement of                                                                      Request for                          Single Stage - One
                                /              Productivity and           Post                               Limited                                                         1,414.00          1,375.00    Signed                                                                                 2018-03-10   2016-10-10                                                                           2018-03-10   2016-12-21   2018-03-15
Herbicides and Fertilizers                                                                Quotations                           Envelope
                                               Diversification
(Inputs for cattle breeding)




 MW-ASWAP II-52546-GO-                         Sustainable Agricultural
                                                                                          Request for                          Single Stage - One
RFQ / Procure protective        /              Productivity and           Post                               Limited                                                         4,921.00          4,705.04    Completed                                                                              2018-03-10   2016-12-05                                                                           2018-03-10   2017-04-10   2018-03-15   2018-07-31
                                                                                          Quotations                           Envelope
clothing (safeguards)                          Diversification




 MW-ASWAP II-57287-GO-
RFB / Motor Vehicles                           Project Coordination and                                                        Single Stage - One
                                /                                         Post            Request for Bids   Open - National                                               208,333.00               0.00   Canceled                                                     2018-04-13   2018-04-27   2018-04-18                                    2018-05-17                2018-05-22                2018-06-03                2018-06-18
(Double Cabin Vehicles for                     Management                                                                      Envelope
Roads x3)




                                                                                                                                                                                                                               Page 1
 MW-ASWAP II-57397-GO-
RFQ / Procure Office
equipment ( 10 Laptops, 1                   Project Coordination and          Request for                          Single Stage - One
                                /                                      Post                      Limited                                 48,611.00    15,744.00   Completed                                      2018-04-23   2018-05-08                                                       2018-05-25   2018-06-18   2018-05-31   2018-07-31
Desktop, 1 Digital Camera                   Management                        Quotations                           Envelope
and 10 Smart phones) and
various stationary




 MW-ASWAP II-61975-GO-
RFB / Motor Vehicles
                                            Project Coordination and                                               Single Stage - One
(Double Cabin Vehicles for      /                                      Post   Request for Bids   Limited                                208,333.00   195,357.13   Signed               2018-05-09   2018-05-19   2018-05-14   2018-05-22   2018-05-28   2019-03-14   2018-06-11   2019-04-08   2018-06-28   2019-05-29   2018-08-23
                                            Management                                                             Envelope
Chitipa, Dedza and Zomba
x3)




 MW-ASWAP II-82123-GO-                      Sustainable Agricultural
                                                                              Request for                          Single Stage - One
RFQ / Procurement of farm      TF / A7167   Productivity and           Post                      Limited                                 13,698.00    22,125.31   Completed                                      2018-10-28   2019-01-25                                                       2018-11-07   2019-02-13   2018-12-05   2019-06-19
                                                                              Quotations                           Envelope
inputs for demonstrations                   Diversification




 MW-ASWAP II-82137-GO-                      Sustainable Agricultural
                                                                              Request for                          Single Stage - One
RFQ / Procurement of           TF / A7167   Productivity and           Post                      Limited                                 27,397.00    53,313.09   Signed                                         2018-11-02   2019-04-05                                                       2018-12-01   2019-05-23   2018-12-29
                                                                              Quotations                           Envelope
protective wear                             Diversification




 MW-ASWAP II-82868-GO-                      Sustainable Agricultural
                                                                              Request for                          Single Stage - One
RFQ / Procurement of 1         TF / A7167   Productivity and           Post                      Limited                                  2,466.00         0.00   Canceled                                       2018-10-21                                                                    2018-10-31                2018-11-28
                                                                              Quotations                           Envelope
desktop Computer for DARS                   Diversification




 MW-ASWAP II-82886-GO-
                                            Project Coordination and          Request for                          Single Stage - One
RFQ / Procurement of Office    TF / A7167                              Post                      Limited                                 20,548.00    17,823.00   Completed                                      2018-12-02   2019-02-08                                                       2018-12-12   2019-02-21   2019-01-09   2019-03-29
                                            Management                        Quotations                           Envelope
Furniture




 MW-ASWAP II-82908-GO-
                                            Project Coordination and          Request for                          Single Stage - One
RFQ / Procurement of Video     TF / A7167                              Post                      Limited                                  1,986.00         0.00   Canceled                                       2018-11-02                                                                    2018-11-12                2018-12-10
                                            Management                        Quotations                           Envelope
Camera




                                            Institutional Capacity
 MW-ASWAP II-82926-GO-                      Building for the
                                                                              Request for                          Single Stage - One
RFQ / Procurement of APES TF / A7167        Implementation of the      Post                      Limited                                 92,191.00   856,967.43   Completed                                      2018-11-02   2018-11-02                                                       2018-11-12   2018-12-17   2018-12-10   2019-06-28
                                                                              Quotations                           Envelope
Equipment                                   National Agricultural
                                            Investment Plan (NAIP)




 MW-ASWAP II-82929-GO-                      Sustainable Agricultural
                                                                              Request for                          Single Stage - One
RFQ / Procurement of re        TF / A7167   Productivity and           Post                      Limited                                 79,702.00    67,058.82   Completed                                      2018-12-02   2018-12-03                                                       2018-12-12   2018-12-10   2019-01-09   2018-12-20
                                                                              Quotations                           Envelope
agents for micro propagation                Diversification




 MW-ASWAP II-82952-GO-                      Sustainable Agricultural
                                                                                                                   Single Stage - One
RFB / Procurement of book      TF / A7167   Productivity and           Post   Request for Bids   Open - National                        178,000.00   173,402.90   Completed            2018-10-31   2019-01-14   2018-11-05                2018-12-05   2019-02-18   2018-12-15   2019-03-01   2019-01-04   2019-05-07   2019-03-05   2019-08-16
                                                                                                                   Envelope
binding machine                             Diversification




 MW-ASWAP II-82958-GO-                      Sustainable Agricultural
                                                                              Request for                          Single Stage - One
RFQ / Procurement of IEC       TF / A7167   Productivity and           Post                      Limited                                 14,384.00     2,816.27   Completed                                      2019-01-20   2018-12-04                                                       2019-01-30   2018-12-14   2019-02-27   2019-02-28
                                                                              Quotations                           Envelope
materials                                   Diversification




 MW-ASWAP II-82907-GO-
                                            Project Coordination and          Request for                          Single Stage - One
RFQ / Procurement of           TF / A7167                              Post                      Limited                                  8,000.00    12,148.07   Completed                                      2018-11-16   2018-10-18                                                       2018-11-26   2018-10-30   2018-12-24   2019-02-15
                                            Management                        Quotations                           Envelope
Diaries




 MW-ASWAP II-82911-GO-
                                            Project Coordination and          Request for                          Single Stage - One
RFQ / Procurement of Pull      TF / A7167                              Post                      Limited                                  2,000.00      431.70    Completed                                      2018-11-24   2018-11-14                                                       2018-12-04   2018-12-05   2019-01-01   2019-01-14
                                            Management                        Quotations                           Envelope
up Banners in quarter 2




                                            Institutional Capacity
 MW-ASWAP II-82920-GO-                      Building for the
                                                                              Request for                          Single Stage - One
RFQ / Procurement of           TF / A7167   Implementation of the      Post                      Limited                                523,332.00         0.00   Canceled                                       2018-11-02                                                                    2018-11-12                2018-12-10
                                                                              Quotations                           Envelope
NAMIS Equipment                             National Agricultural
                                            Investment Plan (NAIP)




                                                                                                                                                                              Page 2
 MW-ASWAP II-82876-GO-
                                             Project Coordination and          Request for                          Single Stage - One
RFQ / Procurement of heavy TF / A7167                                   Post                      Limited                                 50,000.00    22,841.87   Completed                                         2018-12-02   2018-11-22                                                       2018-12-12   2018-12-03   2019-01-09   2019-01-16
                                             Management                        Quotations                           Envelope
duty photocopiers




                                             Institutional Capacity
 MW-ASWAP II-85974-GO-                       Building for the
                                                                                                                    Single Stage - One
RFB / Procurement of            TF / A7167   Implementation of the      Post   Request for Bids   Open - National                        523,332.00   453,100.51   Signed                  2018-12-13   2019-01-17   2018-12-18                2019-01-17   2019-02-18   2019-01-27   2019-02-28   2019-02-06   2019-05-15   2019-03-06   2019-09-11
                                                                                                                    Envelope
NAMIS Equipment                              National Agricultural
                                             Investment Plan (NAIP)




 MW-ASWAP II-85951-GO-
RFQ / Procurement of                         Project Coordination and          Request for                          Single Stage - One
                                TF / A7167                              Post                      Limited                                 14,297.00     3,500.44   Completed                                         2018-11-27   2018-11-05                                                       2019-01-22   2018-11-28   2019-02-19   2018-12-14
materials for printing of                    Management                        Quotations                           Envelope
calendars




 MW-ASWAP II-85968-GO-                       Sustainable Agricultural
                                                                               Request for                          Single Stage - One
RFQ / Procurement of ICT        TF / A7167   Productivity and           Post                      Limited                                 52,740.00    15,862.41   Completed                                         2018-12-01   2018-11-14                                                       2018-12-11   2018-11-22   2019-01-08   2019-01-16
                                                                               Quotations                           Envelope
Equipment                                    Diversification




 MW-ASWAP II-85990-GO-                       Sustainable Agricultural
                                                                               Request for                          Single Stage - One
RFQ / Procurement of            TF / A7167   Productivity and           Post                      Limited                                  5,597.00     8,948.87   Completed                                         2018-11-18   2018-11-02                                                       2018-11-28   2018-12-07   2018-12-26   2019-01-17
                                                                               Quotations                           Envelope
digital and video camera                     Diversification




 MW-ASWAP II-85961-GO-
                                             Project Coordination and          Request for                          Single Stage - One
RFQ / Procurement of            TF / A7167                              Post                      Limited                                  3,000.00     2,694.55   Completed                                         2018-12-02   2019-01-16                                                       2018-12-12   2019-01-24   2019-01-09   2019-02-19
                                             Management                        Quotations                           Envelope
stickers, brochures and cards




 MW-ASWAP II-102635-GO-                      Sustainable Agricultural
                                                                               Request for                          Single Stage - One
RFQ / Procurement of            TF / A7167   Productivity and           Post                      Limited                                 17,000.00     7,674.59   Completed                                         2019-04-02   2019-01-16                                                       2019-04-19   2019-01-25   2019-05-04   2019-03-29
                                                                               Quotations                           Envelope
hardware materials                           Diversification




 MW-ASWAP II-82960-GO-                       Sustainable Agricultural
                                                                               Request for                          Single Stage - One
RFQ / Procurement of inputs TF / A7167       Productivity and           Post                      Limited                                 20,547.00         0.00   Canceled                                          2019-01-19                                                                    2019-01-29                2019-02-26
                                                                               Quotations                           Envelope
for agroforestry nurseries                   Diversification




 MW-ASWAP II-82089-GO-
                                             Sustainable Agricultural
RFQ / Procurement of                                                           Request for                          Single Stage - One
                                TF / A7167   Productivity and           Post                      Limited                                  3,287.00         0.00   Canceled                                          2018-10-28                                                                    2018-11-07                2018-12-05
chemicals to control aphids                                                    Quotations                           Envelope
                                             Diversification
and screen houses




 MW-ASWAP II-85958-GO-                       Sustainable Agricultural                                                                                              Pending
                                                                               Request for                          Single Stage - One
RFQ / Procurement of pull       TF / A7167   Productivity and           Post                      Limited                                  2,500.00         0.00   Implementati                                      2019-12-20                                                                    2019-12-30                2020-01-27
                                                                               Quotations                           Envelope
up banners in quarter 3                      Diversification                                                                                                       on




 MW-ASWAP II-85964-GO-                       Sustainable Agricultural
                                                                               Request for                          Single Stage - One
RFQ / Procurement of golf       TF / A7167   Productivity and           Post                      Limited                                  9,500.00     9,115.87   Signed                                            2020-01-18   2020-02-04                                                       2020-01-28   2020-02-17   2020-02-25
                                                                               Quotations                           Envelope
shirts                                       Diversification




 MW-ASWAP II-82964-GO-
                                             Sustainable Agricultural
RFQ / Procurement of inputs                                                    Request for                          Single Stage - One
                                TF / A7167   Productivity and           Post                      Limited                                 26,997.00         0.00   Canceled                                          2018-12-08                                                                    2018-12-18                2019-01-15
for various CSA                                                                Quotations                           Envelope
                                             Diversification
Demonstrations




 MW-ASWAP II-128404-GO-                      Sustainable Agricultural                                                                                              Pending
                                                                               Request for                          Single Stage - One
RFQ / Procurement of ICT        TF / A7166   Productivity and           Post                      Limited                                 96,000.00         0.00   Implementati                                      2020-03-01                                                                    2020-03-19                2020-04-16
                                                                               Quotations                           Envelope
Equipment                                    Diversification                                                                                                       on




 MW-ASWAP II-128460-GO-                      Project Coordination and          Request for                          Single Stage - One
                                TF / A7166                              Post                      Limited                                 14,865.00    17,404.18   Signed                                            2019-11-02   2019-10-28                                                       2019-11-20   2019-11-22   2019-12-19
RFQ / Procure 2020 Diaries                   Management                        Quotations                           Envelope




                                             Institutional Capacity
 MW-ASWAP II-128476-GO-                      Building for the
                                                                               Request for                          Single Stage - One
RFQ / Procure Scales for        TF / A7166   Implementation of the      Post                      Limited                                 93,000.00    92,740.22   Signed                                            2019-10-05   2019-09-19                                                       2019-11-17   2019-10-31   2019-12-15
                                                                               Quotations                           Envelope
APES                                         National Agricultural
                                             Investment Plan (NAIP)




                                                                                                                                                                                  Page 3
 MW-ASWAP II-114672-GO-
                                                Sustainable Agricultural
RFB / Procurement of                                                                                                             Single Stage - One
                                TF / A7167      Productivity and            Post            Request for Bids   Open - National                                               198,000.00               0.00   Canceled                                                     2019-05-31                2019-06-05                                    2019-07-06              2019-07-16            2019-08-13                2019-10-22
certified seed of rice and                                                                                                       Envelope
                                                Diversification
legumes




                                                Institutional Capacity
 MW-ASWAP II-107209-GO-                         Building for the
                                                                                            Request for                          Single Stage - One
RFQ / Procurement of            TF / A7167      Implementation of the       Post                               Limited                                                        80,222.00               0.00   Canceled                                                                               2019-04-05                                                                                  2019-04-26                2019-05-30
                                                                                            Quotations                           Envelope
NAMIS Equipment                                 National Agricultural
                                                Investment Plan (NAIP)




 MW-ASWAP II-141947-GO-
RFQ / Procurement of                            Improvement of Roads
Inputs to Micropropagate        TF / A7166      Infrastructure for Market   Post            Direct Selection   Direct                                                         81,000.00         77,412.27    Signed                                                       2019-11-01   2019-11-06   2019-11-06   2019-11-07                                                                     2019-11-19   2019-11-29   2019-12-21
and harden off banana                           Access
plantlets-private sector




 MW-ASWAP II-128376-GO-                         Sustainable Agricultural
                                                                                            Request for                          Single Stage - One
RFQ / Procurement of            TF / A7166      Productivity and            Post                               Limited                                                        80,000.00         90,073.44    Signed                                                                                 2019-11-05   2019-09-23                                                                     2019-11-23   2019-10-31   2019-12-23
                                                                                            Quotations                           Envelope
Banana Suckers                                  Diversification




 MW-ASWAP II-128409-GO-                         Sustainable Agricultural
                                                                                            Request for                          Single Stage - One
RFQ / Procure certified         TF / A7166      Productivity and            Post                               Limited                                                        50,000.00         81,296.46    Signed                                                                                 2019-11-05   2019-09-16                                                                     2019-11-23   2019-10-31   2019-12-29
                                                                                            Quotations                           Envelope
legume and rice seed                            Diversification




 MW-ASWAP II-128482-GO-
                                                Project Coordination and                    Request for                          Single Stage - One
RFQ / Procure 16 seater         TF / A7166                                  Post                               Limited                                                        70,973.00         48,693.50    Signed                                                                                 2019-11-06   2019-09-30                                                                     2019-11-24   2019-10-31   2019-12-15
                                                Management                                  Quotations                           Envelope
Minibus




 MW-ASWAP II-128362-GO-                         Sustainable Agricultural
                                                                                            Request for                          Single Stage - One
RFQ / Procurement of            TF / A7166      Productivity and            Post                               Limited                                                        81,081.00               0.00   Canceled                                                                               2019-11-13                                                                                  2019-12-01                2019-12-22
                                                                                            Quotations                           Envelope
foundation/basic legume seed                    Diversification




 MW-ASWAP II-141942-GO-                         Improvement of Roads
                                                                                            Request for                          Single Stage - One
RFQ / Procurement of IEC        TF / A7166      Infrastructure for Market   Post                               Limited                                                         6,756.00               0.00   Canceled                                                                               2019-11-15                                                                                  2019-12-04                2019-12-28
                                                                                            Quotations                           Envelope
Materials                                       Access




 MW-ASWAP II-141943-GO-
                                                Improvement of Roads
RFQ / Procurement of road                                                                   Request for                          Single Stage - One
                                TF / A7166      Infrastructure for Market   Post                               Limited                                                         6,500.00         10,822.24    Signed                                                                                 2019-11-26   2019-11-04                                                                     2019-12-11   2019-11-22   2019-12-29
sign posts for roads in                                                                     Quotations                           Envelope
                                                Access
ASWAP 12 districts




 MW-ASWAP II-161199-GO-                                                                                                                                                                                      Pending
                                                Project Coordination and                    Request for                          Single Stage - One
RFQ / Procurement of Office     TF / A7166                                  Post                               Limited                                                        34,000.00               0.00   Implementati                                                                           2020-03-16                                                                                  2020-04-28                2020-05-30
                                                Management                                  Quotations                           Envelope
Furniture                                                                                                                                                                                                    on




NON CONSULTING SERVICES
                                                                                                                                                                                                                                                                                                                                                                             Bid Evaluation
Activity Reference No. /                                                                                                                                                                                                                                                      Draft Bidding
                                Loan / Credit                                                                       Market         Procurement        Prequalification    Estimated       Actual Amount           Process   Draft Pre-qualification    Prequalification                             Specific Procurement      Bidding Documents   Proposal Submission /        Report and
          Description                                    Component            Review Type        Method                                                                                                                                                                        Document /                                                                                                         Signed Contract         Contract Completion
                                      No.                                                                          Approach           Process              (Y/N)         Amount (US$)         (US$)               Status         Documents            Evaluation Report                              Notice / Invitation          as Issued        Opening / Minutes      Recommendation for
                                                                                                                                                                                                                                                                              Justification
                                                                                                                                                                                                                                                                                                                                                                                  Award
                                                                                                                                                                                                                             Planned      Actual      Planned    Actual   Planned       Actual      Planned       Actual      Planned    Actual    Planned     Actual     Planned      Actual   Planned       Actual      Planned       Actual


 MW-ASWAP II-75956-NC-
DIR / Provision of logistical                   Sustainable Agricultural
support for the 2018 - 2019     TF / A7167      Productivity and            Post            Direct Selection   Direct                                                        226,027.00        172,085.76    Completed                                                    2018-09-04   2018-09-21   2018-09-07   2018-07-05                                                                     2018-09-19   2018-08-01   2019-08-20   2018-09-25
Farm Inputs Subsidy                             Diversification
Programme




 MW-ASWAP II-82870-NC-
                                                Project Coordination and                    Request for                          Single Stage - One
RFQ / Procurement of Motor TF / A7167                                       Post                               Limited                                                        68,493.00         25,236.46    Signed                                                                                 2018-10-28   2018-09-07                                                                     2018-11-07   2018-11-01   2019-11-07
                                                Management                                  Quotations                           Envelope
Vehicle Insurance Services




 MW-ASWAP II-82905-NC-
                                                Project Coordination and                    Request for                          Single Stage - One
RFQ / Procurement of            TF / A7167                                  Post                               Limited                                                        13,699.00         11,137.77    Completed                                                                              2018-12-04   2019-05-07                                                                     2018-12-14   2019-05-23   2019-01-11   2019-06-28
                                                Management                                  Quotations                           Envelope
magazine printing services




                                                                                                                                                                                                                                 Page 4
 MW-ASWAP II-101370-NC-
                                              Project Coordination and           Request for                          Single Stage - One
RFQ / Procurement of             TF / A7167                               Post                      Limited                                  5,000.00    3,261.78   Completed                                         2019-02-27   2018-11-02                             2019-03-15   2018-11-28   2019-09-27   2018-12-14
                                              Management                         Quotations                           Envelope
Binding Services




 MW-ASWAP II-114938-NC-
DIR / Consultancy services
                                              Project Coordination and
to renew Audit Command           TF / A7167                               Post   Direct Selection   Direct                                   5,360.00    5,360.00   Completed               2019-05-24   2019-03-14   2019-05-29   2019-03-18                             2019-06-28   2019-05-31   2019-08-03   2019-07-11
                                              Management
Language (ACL) Software
license




 MW-ASWAP II-82888-NC-
                                              Project Coordination and                                                Single Stage - One
RFB / Procurement of             TF / A7167                               Post   Request for Bids   Open - National                        308,219.00        0.00   Canceled                2018-10-31                2018-11-05                2018-12-05   2019-01-17   2019-02-01                2020-02-01
                                              Management                                                              Envelope
Internet Services




 MW-ASWAP II-82904-NC-
RFQ / Procurement of                          Project Coordination and           Request for                          Single Stage - One
                                 TF / A7167                               Post                      Limited                                 18,808.00        0.00   Canceled                                          2020-01-25                                          2020-02-04                2020-03-03
Result Handbook Printing                      Management                         Quotations                           Envelope
Services




 MW-ASWAP II-128455-NC-
                                                                                                                                                                    Pending
RFQ / Procure printing                        Project Coordination and           Request for                          Single Stage - One
                                 TF / A7166                               Post                      Limited                                 10,811.00        0.00   Implementati                                      2020-06-03                                          2020-06-21                2020-07-20
services to print quarterly                   Management                         Quotations                           Envelope
                                                                                                                                                                    on
project magazine




                                              Institutional Capacity
 MW-ASWAP II-128473-NC-                       Building for the
                                                                                 Request for                          Single Stage - One
RFQ / Procure Cloud Server       TF / A7166   Implementation of the       Post                      Limited                                 13,500.00        0.00   Canceled                                          2019-12-04                                          2020-01-12                2021-01-11
                                                                                 Quotations                           Envelope
for NAMIS                                     National Agricultural
                                              Investment Plan (NAIP)




 MW-ASWAP II-128413-CS-
CDS / Provision of Logistical                 Sustainable Agricultural                                                                                              Pending
support to Logistics Unit for    TF / A7166   Productivity and            Post   Direct Selection   Direct                                 135,135.00        0.00   Implementati            2019-10-31                2019-11-05                                          2019-11-18                2019-12-30
2019-2020 Farm Input                          Diversification                                                                                                       on
Subsidy Programme (FISP)




 MW-ASWAP II-141941-NC-                       Improvement of Roads
                                                                                 Request for                          Single Stage - One
RFQ / Procurement of             TF / A7166   Infrastructure for Market   Post                      Limited                                  8,785.00        0.00   Canceled                                          2019-11-06                                          2019-11-24                2019-12-16
                                                                                 Quotations                           Envelope
Billboard advertising services                Access




 MW-ASWAP II-128462-CS-
INDV / Procure services to                    Project Coordination and           Request for                          Single Stage - One
                                 TF / A7166                               Post                      Limited                                  4,054.00    3,922.78   Signed                                            2020-01-22   2019-11-20                             2020-02-07   2020-01-21   2020-03-14
develop and host ASWAP SP                     Management                         Quotations                           Envelope
II Website




 MW-ASWAP II-153369-NC-
                                              Project Coordination and           Request for                          Single Stage - One
RFQ / Procurement of             TF / A7166                               Post                      Limited                                 30,000.00   22,068.74   Signed                                            2020-02-04   2019-12-20                             2020-03-08   2020-01-10   2021-03-08
                                              Management                         Quotations                           Envelope
Insurance Services




 MW-ASWAP II-150749-NC-
                                              Sustainable Agricultural
RFQ / Procurement of                                                             Request for                          Single Stage - One
                                 TF / A7166   Productivity and            Post                      Limited                                 80,000.00        0.00   Canceled                                          2020-01-15                                          2020-03-11                2020-06-09
Laboratory services for seed                                                     Quotations                           Envelope
                                              Diversification
testing




 MW-ASWAP II-156919-NC-                       Sustainable Agricultural                                                                                              Pending
DIR / Procurement of             TF / A7166   Productivity and            Post   Direct Selection   Direct                                  80,000.00        0.00   Implementati            2020-03-06                2020-03-13                                          2020-05-01                2020-06-30
Laboratory services                           Diversification                                                                                                       on




 MW-ASWAP II-161200-NC-
RFQ / Procurement of
                                              Sustainable Agricultural                                                                                              Pending
printing services to print                                                       Request for                          Single Stage - One
                                 TF / A7166   Productivity and            Post                      Limited                                  3,000.00        0.00   Implementati                                      2020-03-18                                          2020-04-28                2020-05-26
booklets of Success stories,                                                     Quotations                           Envelope
                                              Diversification                                                                                                       on
Communication strategy and
Quarterly Magazine




CONSULTING FIRMS




                                                                                                                                                                                   Page 5
Activity Reference No. /                                                                                                                                                                                                                                                                                                                                  Combined Evaluation
                                Loan / Credit                                                                       Market       Contract Type    Estimated           Actual                                                      Expression of Interest Short List and Draft Request for Proposals Opening of Technical            Evaluation of
         Description                                    Component            Review Type        Method                                                                                Process Status   Terms of Reference                                                                                                                                  Report and Draft           Signed Contract         Contract Completion
                                      No.                                                                          Approach                      Amount (US$)      Amount (US$)                                                           Notice        Request for Proposals         as Issued       Proposals / Minutes        Technical Proposal
                                                                                                                                                                                                                                                                                                                                                          Negotiated Contract
                                                                                                                                                                                                       Planned       Actual        Planned     Actual    Planned      Actual      Planned    Actual   Planned       Actual      Planned       Actual      Planned       Actual      Planned       Actual      Planned       Actual


                                                Institutional Capacity
 MW-ASWAP II-52401-CS-
                                                Building for the
QCBS / Agriculture                                                                         Quality And Cost-
                                 /              Implementation of the      Post                                Open - National                         77,143.00        87,761.83     Signed           2018-03-07   2018-03-22    2018-03-07            2018-03-07   2017-01-25                       2018-03-07   2017-02-28   2018-03-07   2017-03-31   2018-03-07   2018-03-22   2018-03-07   2017-12-22   2018-06-05
Development and Marketing                                                                  Based Selection
                                                National Agricultural
Corporation Review Study
                                                Investment Plan (NAIP)




 MW-ASWAP II-52547-CS-
QCBS / Digitization of Old                      Institutional Capacity
Records, Supply, Delivery,                      Building for the
                                                                                           Quality And Cost- Open -                                                                   Under
Installation of Hardware and TF / A7167         Implementation of the      Prior                                                                      795,000.00               0.00                    2018-03-10                 2018-03-10            2018-03-10                                    2018-03-10                2018-03-10                2018-03-20                2018-03-30                2018-06-28
                                                                                           Based Selection     International                                                          Implementation
Software as designed, Test                      National Agricultural
run and commissioning of E-                     Investment Plan (NAIP)
Permit Issuance System




 MW-ASWAP II-82897-CS-
                                                Project Coordination and                   Least Cost
LCS / Procurement of            TF / A7167                                 Post                                Open - National                         82,192.00        67,955.41     Signed           2018-10-31   2019-02-01    2018-11-05            2018-11-29   2019-03-20                       2018-12-29   2019-04-23   2019-01-03   2019-06-07   2019-01-18   2019-07-19   2019-01-28   2019-07-23   2019-03-14
                                                Management                                 Selection
external audit services




 MW-ASWAP II-85937-CS-                                                                     Consultant
                                                Project Coordination and
CQS / Consultancy services      TF / A7167                                 Post            Qualification       Limited                                 69,444.00        93,879.09     Completed        2018-11-15   2018-11-16                          2018-11-20   2018-11-29                                                                           2018-12-20   2019-02-01   2019-02-14   2019-02-08   2019-04-15   2019-07-31
                                                Management
to conduct baseline survey                                                                 Selection




                                                Institutional Capacity
 MW-ASWAP II-85941-CS-
                                                Building for the
QCBS / Consultancy services                                                                Quality And Cost-
                                TF / A7167      Implementation of the      Post                                Open - National                         68,493.00               0.00   Canceled         2019-02-21                 2019-02-26            2019-03-22                                    2019-04-21                2019-04-26                2019-05-16                2019-05-26                2019-07-25
to pretest NAMIS in one of                                                                 Based Selection
                                                National Agricultural
the project districts
                                                Investment Plan (NAIP)




                                                Institutional Capacity
 MW-ASWAP II-82947-CS-
                                                Building for the
QCBS / Consultancy services                                                                Quality And Cost-
                                TF / A7167      Implementation of the      Post                                Open - National                        178,082.00               0.00   Canceled         2019-01-31                 2019-02-05            2019-03-01                                    2019-03-31                2019-04-10                2019-04-25                2019-05-10                2019-07-09
for upscaling of NAMIS to                                                                  Based Selection
                                                National Agricultural
all project districts
                                                Investment Plan (NAIP)




 MW-ASWAP II-85936-CS-
                                                Institutional Capacity
QCBS / Consultancy services
                                                Building for the
to train councilors and staff                                                              Quality And Cost-
                                TF / A7167      Implementation of the      Post                                Open - National                         27,397.00               0.00   Canceled         2019-02-14                 2019-02-19            2019-03-15                                    2019-04-14                2019-04-19                2019-04-29                2019-05-14                2019-07-13
in decentralized M & E                                                                     Based Selection
                                                National Agricultural
using Social Accountability
                                                Investment Plan (NAIP)
Framework




 MW-ASWAP II-82950-CS-                          Institutional Capacity
QCBS / Consultancy services                     Building for the
                                                                                           Quality And Cost-
to conduct a study on carry     TF / A7167      Implementation of the      Post                                Open - National                        109,589.00               0.00   Canceled         2019-01-11                 2019-01-16            2019-02-09                                    2019-03-11                2019-03-21                2019-04-05                2019-04-25                2019-06-24
                                                                                           Based Selection
over and on farm stocks for                     National Agricultural
2018-2019 FY                                    Investment Plan (NAIP)




 MW-ASWAP II-85935-CS-                          Institutional Capacity
QCBS / Consultancy services                     Building for the
                                                                                           Quality And Cost-
to develop additional           TF / A7167      Implementation of the      Post                                Open - National                         68,493.00               0.00   Canceled         2019-01-24                 2019-01-29            2019-02-22                                    2019-03-24                2019-03-29                2019-04-08                2019-04-23                2019-06-22
                                                                                           Based Selection
modules and dashboards for                      National Agricultural
NAMIS                                           Investment Plan (NAIP)




                                                Institutional Capacity
 MW-ASWAP II-107210-CS-                         Building for the
                                                                                           Quality And Cost-
QCBS / Consultancy Services TF / A7167          Implementation of the      Post                                Open - National                         30,137.00               0.00   Canceled         2019-04-19                 2019-04-25            2019-05-15                                    2019-06-17                2019-06-24                2019-07-10                2019-07-26                2019-09-30
                                                                                           Based Selection
to develop NAIP Handbook                        National Agricultural
                                                Investment Plan (NAIP)




 MW-ASWAP II-82910-CS-
CQS / Engagement of
                                                                                           Consultant
consultant to update                            Project Coordination and
                                TF / A7167                                 Post            Qualification       Open - National                         26,027.00               0.00   Canceled         2020-05-20                 2020-05-25            2020-06-18                                                                                        2020-07-18                2020-08-02                2020-10-01
Ministry Website and                            Management
                                                                                           Selection
conduct training in website
management




                                                                                                                                                                                                                         Page 6
 MW-ASWAP II-107206-CS-
QCBS / Consultancy services                   Sustainable Agricultural
                                                                                         Quality And Cost-
for independent evaluation of TF / A7167      Productivity and           Post                                Open - National                        109,589.00               0.00   Canceled         2020-03-30                 2020-04-20                2020-05-25                                          2020-06-22            2020-07-05   2020-07-26   2020-09-06   2020-11-05
                                                                                         Based Selection
2018-2019 Farm Input                          Diversification
Subsidy Programme (FISP)




 MW-ASWAP II-153363-CS-
                                                                                         Consultant
CQS / Procurement of                          Project Coordination and                                                                                                              Pending
                              TF / A7166                                 Post            Qualification       Open - National                         70,000.00               0.00                    2020-02-28                 2020-03-20                2020-05-03                                                                             2020-06-02   2020-07-07   2020-10-05
consultancy services to                       Management                                                                                                                            Implementation
                                                                                         Selection
conduct an adoption study




 MW-ASWAP II-153365-CS-
                                              Sustainable Agricultural                   Consultant
CQS / Procurement of                                                                                                                                                                Pending
                              TF / A7166      Productivity and           Post            Qualification       Open - National                         70,000.00               0.00                    2020-03-31                 2020-04-21                2020-06-04                                                                             2020-07-04   2020-08-08   2020-12-06
supervision services for                                                                                                                                                            Implementation
                                              Diversification                            Selection
irrigation scheme works




INDIVIDUAL CONSULTANTS
Activity Reference No. /                                                                                                                                                                                                            Invitation to
                              Loan / Credit                                                                       Market       Contract Type    Estimated           Actual                                                                                  Draft Negotiated
         Description                                  Component            Review Type        Method                                                                                Process Status   Terms of Reference          Identified/Selected                                  Signed Contract         Contract Completion
                                    No.                                                                          Approach                      Amount (US$)      Amount (US$)                                                                                   Contract
                                                                                                                                                                                                                                     Consultant
                                                                                                                                                                                                     Planned       Actual       Planned       Actual      Planned       Actual      Planned       Actual      Planned      Actual


 MW-ASWAP II-47206-CS-
CDS / Consultancy Services
to lead Adjudication.                         Project Coordination and
                              TF / A7167                                 Prior           Direct Selection    Direct                                 250,000.00       250,000.00     Signed           2018-02-01   2018-04-27    2018-02-03   2018-02-13                             2018-02-21   2018-04-09   2018-07-21
Demarcation and                               Management
Registration of Traditional
Land Management Areas




 MW-ASWAP II-52604-CS-                                                                   Individual
                                              Project Coordination and
INDV / Resettlement Policy     /                                         Post            Consultant          Limited                                 28,490.00        29,452.11     Signed           2018-03-10   2016-12-07    2018-03-10   2016-04-12   2018-03-10   2017-02-01   2018-03-10   2017-02-01   2018-03-10
                                              Management
Framework (RPF                                                                           Selection




 MW-ASWAP II-52582-CS-
                                                                                         Individual
INDV / Environmental and                      Project Coordination and
                               /                                         Post            Consultant          Limited                                 32,000.00        32,600.00     Signed           2018-03-10   2016-11-24    2018-03-10   2016-04-12   2018-03-10   2017-02-01   2018-03-10   2017-02-01   2018-03-15
Social Management                             Management
                                                                                         Selection
Framework (ESMF)




 MW-ASWAP II-52555-CS-                                                                   Individual
                                              Project Coordination and                                                                                                              Pending
INDV / Implementation          /                                         Post            Consultant          Limited                                119,533.00               0.00                    2018-03-10                 2018-03-10                2018-03-10                2018-03-10                2018-03-15
                                              Management                                                                                                                            Implementation
Completion Report                                                                        Selection




                                              Institutional Capacity
 MW-ASWAP II-52587-CS-                        Building for the                           Individual
                                                                                                                                                                                    Under
INDV / Review of National      /              Implementation of the      Post            Consultant          Limited                                 15,771.00               0.00                    2018-03-10   2017-02-03    2018-03-10                2018-03-10                2018-03-10                2018-03-15
                                                                                                                                                                                    Implementation
Investment Policy                             National Agricultural                      Selection
                                              Investment Plan (NAIP)




                                              Institutional Capacity
 MW-ASWAP II-52540-CS-
                                              Building for the                           Individual
INDV / Recruitment of
                               /              Implementation of the      Post            Consultant          Limited                                 62,294.00         2,458.34     Signed           2018-03-10   2015-07-10    2018-03-10   2016-11-17   2018-03-10   2015-08-18   2018-03-10   2017-11-22   2018-03-15
Technical Assistant
                                              National Agricultural                      Selection
–MOLHUD
                                              Investment Plan (NAIP)




 MW-ASWAP II-52597-CS-                        Institutional Capacity
INDV / Design and                             Building for the                           Individual
Supervision of Land            /              Implementation of the      Post            Consultant          Limited                                 35,000.00       114,300.00     Signed           2018-03-10   2016-04-25    2018-03-10   2016-07-27   2018-03-10   2016-11-10   2018-03-10   2016-12-12   2018-03-15
Information Management                        National Agricultural                      Selection
System                                        Investment Plan (NAIP)




                                              Institutional Capacity
 MW-ASWAP II-52570-CS-
                                              Building for the                           Individual
INDV / Development of
                               /              Implementation of the      Post            Consultant          Limited                                 30,000.00        99,690.00     Signed           2018-03-10   2016-04-27    2018-03-10   2016-07-27   2018-03-10   2016-12-12   2018-03-10   2016-12-12   2018-03-15
Land Information
                                              National Agricultural                      Selection
Management System
                                              Investment Plan (NAIP)




                                                                                                                                                                                                                       Page 7
 MW-ASWAP II-52590-CS-                     Sustainable Agricultural           Individual
INDV / Livestock Policy and    /           Productivity and           Post    Consultant         Limited    17,850.00   27,503.80   Signed           2018-03-10   2016-04-12    2018-03-10   2016-06-20   2018-03-10   2016-10-10   2018-03-10   2016-10-14   2018-03-15
strategic plan review                      Diversification                    Selection




 MW-ASWAP II-57403-CS-                                                        Individual
                                           Project Coordination and
INDV / Project Coordination   TF / A7167                              Prior   Consultant         Open       51,000.00   46,038.05   Completed        2018-04-09   2018-05-03    2018-05-12   2018-09-21   2018-05-17   2018-10-01   2018-05-25   2018-09-01   2019-05-25   2019-09-02
                                           Management
Assistant                                                                     Selection




 MW-ASWAP II-57405-CS-                                                        Individual
                                           Project Coordination and
INDV / Procurement            TF / A7167                              Prior   Consultant         Open       45,000.00   41,105.40   Completed        2018-04-09   2018-05-02    2018-05-12   2018-10-03   2018-05-17   2018-10-05   2018-05-25   2018-09-01   2019-05-25   2019-09-02
                                           Management
Specialist                                                                    Selection




 MW-ASWAP II-57346-CS-                                                        Individual
                                           Project Coordination and
INDV / Documentation          TF / A7167                              Prior   Consultant         Open       12,857.00    9,865.30   Completed        2018-04-09   2018-05-03    2018-05-12   2018-09-20   2018-05-17   2018-10-01   2018-05-25   2018-09-01   2019-05-25   2019-09-02
                                           Management
Officer                                                                       Selection




 MW-ASWAP II-57398-CS-                                                        Individual
                                           Project Coordination and
INDV / Financial              TF / A7167                              Prior   Consultant         Open       60,000.00   46,038.05   Signed           2018-04-09   2018-05-02    2018-05-12   2018-09-20   2018-05-17   2018-10-01   2018-05-25   2018-09-01   2019-05-25
                                           Management
Management Specialist,                                                        Selection




 MW-ASWAP II-57345-CS-                                                        Individual
                                           Project Coordination and
INDV / Monitoring and         TF / A7167                              Prior   Consultant         Open       30,000.00   42,749.62   Completed        2018-04-09   2018-05-02    2018-05-12   2018-10-09   2018-05-17   2018-10-18   2018-05-25   2018-09-01   2019-05-25   2019-08-30
                                           Management
Evaluation Specialist                                                         Selection




 MW-ASWAP II-57394-CS-                                                        Individual
                                           Project Coordination and
INDV / Assistant Financial    TF / A7167                              Post    Consultant         Open       36,000.00   32,884.32   Completed        2018-02-09   2018-04-29    2018-05-12   2018-09-20   2018-05-17   2018-09-21   2018-05-25   2018-09-01   2019-05-25   2019-08-01
                                           Management
Management Specialist                                                         Selection




 MW-ASWAP II-57401-CS-                                                        Individual
                                           Project Coordination and
INDV / Communication          TF / A7167                              Prior   Consultant         Open       48,000.00   41,105.40   Completed        2018-04-09   2018-05-02    2018-05-12   2018-09-17   2018-05-17   2018-10-01   2018-05-25   2018-09-01   2019-05-25   2019-09-02
                                           Management
Specialist                                                                    Selection




                                                                              Individual
 MW-ASWAP II-57396-CS-                     Project Coordination and
                              TF / A7167                              Post    Consultant         Open       48,000.00   41,105.40   Signed           2018-04-09   2018-04-29    2018-05-12   2019-02-15   2018-05-17   2019-02-15   2018-05-25   2019-01-01   2019-05-25
INDV / TWG Assistant                       Management
                                                                              Selection




 MW-ASWAP II-57400-CS-                                                        Individual
                                           Project Coordination and
INDV / Justification          TF / A7167                              Prior   Consultant         Open       22,500.00   69,057.06   Signed           2018-04-09   2018-05-02    2018-05-12   2018-10-19   2018-05-17   2018-10-26   2018-05-25   2018-09-01   2019-05-25   2019-09-02
                                           Management
Assistants                                                                    Selection




 MW-ASWAP II-63367-CS-                                                        Individual
                                           Project Coordination and
INDV / Conduct Baseline       TF / A7167                              Post    Consultant         Limited    69,444.00        0.00   Canceled         2018-05-23   2018-09-04    2018-05-28                2018-06-11                2018-06-24                2018-07-24
                                           Management
Survey for the Project                                                        Selection




 MW-ASWAP II-85938-CS-
INDV / Procurement of
                                           Sustainable Agricultural           Individual
consultancy services to
                              TF / A7167   Productivity and           Post    Consultant         Limited    20,547.00   20,843.20   Signed           2018-11-09   2018-11-09    2018-11-25   2018-11-05   2018-11-27   2019-02-01   2018-12-05   2019-02-08   2019-02-03
conduct a survey to
                                           Diversification                    Selection
establish demand for basic
and breeder seed




 MW-ASWAP II-107216-CS-                    Institutional Capacity
CDS / Consultancy services                 Building for the
                                                                                                                                    Under
to develop additional         TF / A7166   Implementation of the      Post    Direct Selection   Direct    182,432.00        0.00                    2019-11-29   2019-11-25    2019-12-09                                          2020-01-09                2020-03-14
                                                                                                                                    Implementation
modules and dashboards for                 National Agricultural
NAMIS                                      Investment Plan (NAIP)




                                           Institutional Capacity
 MW-ASWAP II-52577-CS-
                                           Building for the                   Individual
INDV / Review of
                               /           Implementation of the      Post    Consultant         Limited    12,000.00        0.00   Canceled         2018-03-10                 2018-03-10                2018-03-10                2018-03-10                2018-03-15
cooperatives policy and
                                           National Agricultural              Selection
implementation strategy
                                           Investment Plan (NAIP)




 MW-ASWAP II-128490-CS-
INDV / Procurement of                                                         Individual
                                           Project Coordination and
consultancy services as       TF / A7166                              Post    Consultant         Direct     56,100.00   21,753.92   Signed           2019-11-01   2019-07-31    2019-11-10   2019-08-14   2019-11-14   2019-08-22   2019-11-24   2019-08-26   2019-12-30
                                           Management
Project Coordination                                                          Selection
Assistant




                                                                                                                                                                       Page 8
 MW-ASWAP II-128503-CS-
                                                                               Individual
INDV / Procure Consultancy                   Project Coordination and
                                TF / A7166                              Post   Consultant   Direct    14,300.00    4,887.86   Signed           2019-10-31   2019-08-30    2019-11-09   2019-08-30   2019-11-13   2019-10-29   2019-11-23   2019-10-29   2019-12-30
Services as Documentation                    Management
                                                                               Selection
Officer




 MW-ASWAP II-128507-CS-
                                                                               Individual
INDV / Procure Consultancy                   Project Coordination and
                                TF / A7166                              Post   Consultant   Direct    77,550.00   24,439.30   Signed           2019-10-31   2019-08-30    2019-11-09   2019-10-07   2019-11-13   2019-10-18   2019-11-23   2019-11-18   2019-12-30
Services as Justification                    Management
                                                                               Selection
Assistants




 MW-ASWAP II-128494-CS-
                                                                               Individual
INDV / Procure Consultancy                   Project Coordination and
                                TF / A7166                              Post   Consultant   Direct    48,400.00   16,292.88   Signed           2019-10-31   2019-08-30    2019-11-09   2019-10-07   2019-11-13   2019-10-18   2019-11-23   2019-10-29   2019-12-29
services as Monitoring and                   Management
                                                                               Selection
Evaluation Specialist




 MW-ASWAP II-128492-CS-
                                                                               Individual
INDV / Procure Consultancy                   Project Coordination and
                                TF / A7166                              Post   Consultant   Direct    52,800.00   16,422.84   Signed           2019-10-31   2019-08-30    2019-11-09   2019-08-30   2019-11-13   2019-10-18   2019-11-23   2019-10-29   2019-12-30
services as Communication                    Management
                                                                               Selection
Specialist




 MW-ASWAP II-128485-CS-
                                                                               Individual
INDV / Procure Consultancy                   Project Coordination and
                                TF / A7166                              Post   Consultant   Direct    56,100.00   21,044.97   Signed           2019-10-31   2019-07-31    2019-11-09   2019-10-07   2019-11-13   2019-10-18   2019-11-23   2019-10-29   2019-12-30
services as Financial                        Management
                                                                               Selection
Management Specialist




 MW-ASWAP II-128504-CS-
                                                                               Individual
INDV / Procure Consultancy                   Project Coordination and
                                TF / A7166                              Post   Consultant   Direct    49,500.00   16,292.88   Signed           2019-10-31   2019-08-30    2019-11-09   2019-10-07   2019-11-13   2019-10-18   2019-11-23   2019-10-29   2019-12-29
services as Procurement                      Management
                                                                               Selection
Specialist




 MW-ASWAP II-128468-CS-                      Institutional Capacity
INDV / Procure consultancy                   Building for the                  Individual
                                                                                                                              Under
services to develop             TF / A7166   Implementation of the      Post   Consultant   Limited   16,216.00        0.00                    2019-11-22   2019-11-27    2019-11-27                2019-12-02                2019-12-08                2019-12-29
                                                                                                                              Implementation
Agriculture Handbook of                      National Agricultural             Selection
Indicators                                   Investment Plan (NAIP)




 MW-ASWAP II-153358-CS-                                                        Individual
                                             Project Coordination and                                                         Under
INDV / Procurement of           TF / A7166                              Post   Consultant   Open      45,000.00        0.00                    2020-03-06   2020-01-31    2020-04-12                2020-04-24                2020-05-20                2021-05-20
                                             Management                                                                       Implementation
Safeguards Specialist                                                          Selection




 MW-ASWAP II-153360-CS-
                                                                               Individual
INDV / Procurement of                        Project Coordination and                                                         Under
                                TF / A7166                              Post   Consultant   Open      35,000.00        0.00                    2020-03-13   2020-02-19    2020-05-09                2020-05-23                2020-06-22                2021-06-22
Justification Assistant for                  Management                                                                       Implementation
                                                                               Selection
Machinga ADD




 MW-ASWAP II-153362-CS-
                                                                               Individual
INDV / Procurement of                        Project Coordination and                                                         Under
                                TF / A7166                              Post   Consultant   Open      39,600.00        0.00                    2020-03-10   2020-02-19    2020-04-28                2020-05-19                2020-06-23                2021-06-23
Assistant Financial                          Management                                                                       Implementation
                                                                               Selection
Management Specialist




 MW-ASWAP II-153371-CS-                      Institutional Capacity
INDV / Procurement of                        Building for the                  Individual
                                                                                                                              Pending
consultancy services to         TF / A7166   Implementation of the      Post   Consultant   Open      20,270.00        0.00                    2020-03-27                 2020-05-15                2020-06-05                2020-07-10                2020-09-10
                                                                                                                              Implementation
develop NAIP                                 National Agricultural             Selection
Communication Strategy                       Investment Plan (NAIP)




 MW-ASWAP II-156115-CS-
INDV / Procurement of
                                             Sustainable Agricultural          Individual
consultancy services to                                                                                                       Pending
                                TF / A7166   Productivity and           Post   Consultant   Open      40,540.00        0.00                    2020-03-17                 2020-05-02                2020-05-14                2020-06-18                2020-09-18
develop national Agricultural                                                                                                 Implementation
                                             Diversification                   Selection
research and development
policy