Public Disclosure Copy The World Bank Implementation Status & Results Report Infrastructure and Local Development Project II (P151077) Infrastructure and Local Development Project II (P151077) AFRICA | Gabon | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 4 | ARCHIVED on 04-Dec-2017 | ISR30379 | Implementing Agencies: GABONESE REPUBLIC, National Commission for Public Infras. Works and Promotion of Small-Scale Enterprises (CN- TIPPEE) Key Dates Key Project Dates Bank Approval Date:10-Dec-2015 Effectiveness Date:25-Apr-2016 Planned Mid Term Review Date:27-May-2019 Actual Mid-Term Review Date:-- Original Closing Date:31-Jan-2021 Revised Closing Date:31-Jan-2021 Project Development Objectives Project Development Objective (from Project Appraisal Document)
The project development objective is to improve access to urban infrastructure and services in selected underserviced neighborhoods and to build basic capacities for municipal management in target cities.
Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component 1: Improving urban infrastructure to increase access to services:(Cost $85.50 M) Component 2: Building institutional development to strengthen the capacity of the urban sector:(Cost $10.00 M) Component 3: Project management, coordination, monitoring and evaluation of the project:(Cost $4.25 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial 12/4/2017 Page 1 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Infrastructure and Local Development Project II (P151077) Implementation Status and Key Decisions Project implementation has progressed to a stage of construction of the first batch of civil works and launch of consultancy assignments. The procurement activities are ongoing for next batch of civil works and consultancies. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating 12/4/2017 Page 2 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Infrastructure and Local Development Project II (P151077) Political and Governance Moderate Moderate Moderate Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Sustainability Substantial Substantial Substantial Fiduciary Moderate Moderate Substantial Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Other -- -- -- Overall Substantial Substantial Substantial Results Project Development Objective Indicators PHINDPDOTBL Number of people in urban areas provided with access to all-season roads within a 500 meter range under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 21,000.00 Date 01-Oct-2015 17-Oct-2016 01-Nov-2017 31-Jan-2021 PHINDPDOTBL Additional population provided with access to other infrastructure and services (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 23,000.00 Date 01-Oct-2015 -- 01-Nov-2017 31-Jan-2021 PHINDPDOTBL Cities that implement asset management plan as specified in the City Contracts (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 8.00 Date 01-Oct-2015 17-Oct-2016 01-Nov-2017 31-Jan-2021 12/4/2017 Page 3 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Infrastructure and Local Development Project II (P151077) PHINDPDOTBL Sub-projects with post-project community engagement or O&M arrangements (%) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 85.00 Date 01-Oct-2015 17-Oct-2016 01-Nov-2017 31-Jan-2021 PHINDPDOTBL Sub-projects that are expected to have a mechanism for post-completion operation (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 36.00 PHINDPDOTBL Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 44,000.00 Date 01-Oct-2015 17-Oct-2016 01-Nov-2017 31-Jan-2021 PHINDPDOTBL Female beneficiaries (Percentage, Custom Supplement) 12/4/2017 Page 4 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Infrastructure and Local Development Project II (P151077) Baseline Actual (Previous) Actual (Current) End Target Value 48.00 48.00 48.00 48.00 Overall Comments Intermediate Results Indicators PHINDIRITBL Roads rehabilitated, Non-rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 8.80 Date 01-Oct-2015 -- 01-Nov-2017 31-Jan-2021 PHINDIRITBL Person-days of employment created (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 902,000.00 Date 01-Oct-2015 17-Oct-2016 01-Nov-2017 31-Jan-2021 PHINDIRITBL Neighborhood Development Plans for which activities adopted for funding by ILDP2 are implemented at least 80 percent (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 18.00 Date 01-Oct-2015 -- 01-Nov-2017 31-Jan-2021 12/4/2017 Page 5 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Infrastructure and Local Development Project II (P151077) PHINDIRITBL Cities developing and implementing capacity building plans for staff (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 8.00 Date 01-Oct-2015 17-Oct-2016 01-Nov-2017 31-Jan-2021 PHINDIRITBL New urban sector strategy developed (Number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 01-Oct-2015 -- 01-Nov-2017 31-Jan-2021 PHINDIRITBL Municipalities that increase municipal own source revenue as specified in the City Contracts (Number) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 8.00 Date 01-Oct-2015 17-Oct-2016 01-Nov-2017 31-Jan-2021 PHINDIRITBL Recruiting at least 40 percent of community facilitators from female members of community (Percentage) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 40.00 Date 01-Oct-2015 17-Oct-2016 01-Nov-2017 31-Jan-2021 12/4/2017 Page 6 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Infrastructure and Local Development Project II (P151077) PHINDIRITBL Grievances registered related to delivery of project benefits addressed (%) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 90.00 Date 01-Oct-2015 17-Oct-2016 01-Nov-2017 31-Jan-2021 Overall Comments The project is at early stage where physical works and institutional strengthening activities have not generated results yet. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P151077 IBRD-85640 Effective USD 100.00 100.00 0.00 11.13 88.79 11% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P151077 IBRD-85640 Effective 10-Dec-2015 14-Jan-2016 25-Apr-2016 31-Jan-2021 31-Jan-2021 Cumulative Disbursements 12/4/2017 Page 7 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Infrastructure and Local Development Project II (P151077) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/4/2017 Page 8 of 8 Public Disclosure Copy