BF-YOUTH EMPLOYMENT & SKILLS DEVELOPMENT (P130735) I. General 1. Bank’s approval Date of the procurement Plan Original: 2013, version 2: 18/07/2014), version 3: 22/02/2015; version 4: 20/03/2015; version 5: 11/04/2016, version 6 : 16/12/2016 2. Date of General Procurement Notice: Dec 7, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year JANUARY 2017 to December 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) ≥ US$ 1.000,000 All 2. NCB (Goods) POST REVIEW POST REVIEW 3. ICB (Works) ≥ US$ 5 million All 4. NCB (Works) POST REVIEW POST REVIEW 5. ICB (Non-Consultant Services) ≥ US$ 1.5 million All 6. NCB (Non-Consultant Services) POST REVIEW POST REVIEW 7. Shopping POST REVIEW POST REVIEW 8. Direct Contracting (Works) ≥ US$ 5 million All 9. Direct Contracting (Goods) ≥ US$ 1.5 million All 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Refer to the relevant CDD project implementation document approved by the Bank 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P130735 issued by PCU 5. Any Other Special Procurement Arrangements: Not applicable 6. Summary of the Procurement Packages planned during the first 18 months [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 July 9, 2010 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 0.19 1 Yes Prior the RFQ (Works) Summary of 0.95 14 Yes Post the RFQ (Goods) Summary of 0.18 2 Yes Post the RFQ (Non- Consultant Services) Summary of NA 0 NA the Direct (Works) Summary of 0.58 8 NA Post the Direct (Goods) Summary of 0.27 5 NA Post the Direct (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank (Prior / Post) July 9, 2010 US$ million Summary of 0.53 4 2 post, 2 All 4 number of prior packages contracts that have been will be let returned under QCBS Summary of 1.78 12 Post CQS number of contracts that will be let under CQS Summary of 1.37 5 Post Only number of approved contracts that 0.22m will be let immediately under Direct Contracting Summary of 0.01 1 Post Returned number of contracts that will be let under INDV July 9, 2010 PROCUREMENT Burkina Faso : BF-Youth Employment & Skills Development PLAN General Information Country: Burkina Faso Banks Approval Date of the Original Procurement Plan: 2017-04-03 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-05-15 Project ID: P130735 GPN Date: Project Name: BF-Youth Employment & Skills Development Loan / Credit No: IDA / 52560 Executing Agency(ies): Project Coordination Unit Employment and Youth Development of Competences WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PEJDC-48871-CW-RFQ / cloisonnement de 04 bureaux à Component 3: Institutional Request for Single Stage - One Pending l'UCP/PEJDC et câblage IDA / 52560 Capacity Strengthening and Post Limited 40,000.00 0.00 2018-03-03 2018-04-28 2018-07-23 Quotations Envelope Implementation é ectrique , informatique l Project Management é honique, pause de Splits télp BF-PEJDC-48917-CW-RFQ / Réhabilitation du CAOJ de la Component 1: Labor Intensive Request for Single Stage - One Pending IDA / 52560 Post Open - National 160,000.00 0.00 2018-03-02 2018-04-08 2018-08-06 commune de Ouahigouya dans Public Works Quotations Envelope Implementation le cadre des THIMO/PEJDC BF-PEJDC-48922-CW-RFQ / Réhabilitation du CAOJ de la Component 1: Labor Intensive Request for Single Stage - One Pending IDA / 52560 Post Open - National 195,000.00 0.00 2018-03-10 2018-04-10 2018-08-08 commune de Ouagadougou dans Public Works Quotations Envelope Implementation le cadre des THIMO/PEJDC BF-PEJDC-48923-CW-RFQ / Réhabilitation du CAOJ de la Component 1: Labor Intensive Request for Single Stage - One Pending IDA / 52560 Post Open - National 190,000.00 0.00 2018-02-25 2018-04-02 2018-07-31 commune de Bobo-Dioulasso Public Works Quotations Envelope Implementation dans le cadre des THIMO/PEJDC BF-PEJDC-48926-CW-RFQ / Réhabilitation du CAOJ de la Component 1: Labor Intensive Request for Single Stage - One Pending IDA / 52560 Post Open - National 140,000.00 0.00 2018-03-06 2018-04-11 2018-08-09 commune de Manga dans le Public Works Quotations Envelope Implementation cadre des THIMO/PEJDC BF-PEJDC-10635-CW-RFQ / Réhabilitation de quatre (04) centres d'accueil et d'Orientation Professionnelle des Jeunes Component 1: Labor Intensive Request for Single Stage - One IDA / 52560 Post Limited 190,000.00 0.00 Canceled 2017-06-25 2017-08-17 2017-10-16 (CAOJ) au profit des communes Public Works Quotations Envelope de Ouagadougou, de Bobo- Dioulasso, de Ouahigouya et Manga GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PEJDC-10548-GO-RFQ / Acquisition de 250 kits d'apprentissage pour les métiers Component 2: Skills Request for Single Stage - One Pending de la restauration (Pâtisserie, IDA / 52560 Post Limited 75,000.00 0.00 2017-04-09 2017-05-29 2017-06-28 development Quotations Envelope Implementation Boulangerie, Cuisine, laiterie, agroalimentaire) etc...de la CMA- BF BF-PEJDC-10552-GO-RFQ / Acquisition de kits 324 kits Component 2: Skills Request for Single Stage - One Pending d'apprentissage pour les métiers IDA / 52560 Post Limited 97,500.00 0.00 2017-04-09 2017-05-29 2017-06-28 development Quotations Envelope Implementation de coiffure, broderie, couture et tissage de la CMA-BF BF-PEJDC-10564-GO-RFQ / Acquisition d'affiche dans le Component 1: Labor Intensive Request for Single Stage - One IDA / 52560 Post Limited 2,500.00 2,745.00 Completed 2017-04-09 2017-04-20 2017-05-13 2017-04-27 2017-05-28 2017-05-02 cadre de recrutement des Public Works Quotations Envelope brigadiers des cohortes 4 et 5 BF-PEJDC-10565-GO-RFQ / Acquisition de cartables Component 1: Labor Intensive Request for Single Stage - One IDA / 52560 Post Limited 45,000.00 45,492.41 Completed 2017-04-13 2017-05-03 2017-06-01 2017-07-11 2017-06-22 2017-07-17 minimum pour les trois (03) Public Works Quotations Envelope cohortes (3-4-5) BF-PEJDC-10568-GO-RFQ / Acquisition de Boites à Component 1: Labor Intensive Request for Single Stage - One IDA / 52560 Post Limited 24,000.00 25,547.23 Signed 2017-04-18 2017-05-02 2017-06-09 2017-07-11 2017-06-24 2017-08-21 pharmacie pour les deux (02) Public Works Quotations Envelope prochaines cohortes (4-5) BF-PEJDC-10569-GO-RFQ / Acquisition de 327 kits Component 2: Skills Request for Single Stage - One Pending d'apprentissage pour les métiers IDA / 52560 Post Limited 98,000.00 0.00 2017-04-15 2017-06-08 2017-07-08 development Quotations Envelope Implementation du BTP, automobile etc. de la CMA-BF BF-PEJDC-10570-GO-RFQ / Acquisition des qé uipements de Component 2: Skills Request for Single Stage - One Pending IDA / 52560 Post Limited 90,000.00 0.00 2017-04-10 2017-06-01 2017-07-01 protection individuelle pour les development Quotations Envelope Implementation apprentis de la CMA-BF Component 1: Labor Intensive BF-PEJDC-10571-GO-RFQ / Public Works Acquisition de matériel Component 3: Institutional Request for Single Stage - One Pending informatique et péri- informatique IDA / 52560 Capacity Strengthening and Post Limited 95,000.00 0.00 2017-05-15 2017-07-10 2017-08-09 Quotations Envelope Implementation au profit du PTR-HIMO, de la Project Management CMA-BF et de l'UCP Component 2: Skills development BF-PEJDC-10611-GO-DIR / Acquisition de quincaillerie au Component 1: Labor Intensive Pending profit d'une cohorte (1 800 IDA / 52560 Post Direct Selection Direct 144,000.00 0.00 2017-05-07 2017-05-17 2017-07-01 2017-08-30 Public Works Implementation jeunes) de l'année 2018 de la commune d'Ouagadougou Page 1 BF-PEJDC-10614-GO-DIR / Acquisition d'effet d'habillement Component 1: Labor Intensive Pending au profit d'une cohorte (700 IDA / 52560 Post Direct Selection Direct 84,000.00 0.00 2017-05-07 2017-05-17 2017-07-01 2017-08-30 Public Works Implementation jeunes) de l'année 2018 de la commune de Bobo-Dioulasso BF-PEJDC-10615-GO-DIR / Acquisition de quincaillerie au Component 1: Labor Intensive Pending profit d'une cohorte (700 jeunes) IDA / 52560 Post Direct Selection Direct 56,000.00 0.00 2017-05-14 2017-05-24 2017-07-08 2017-09-06 Public Works Implementation de l'année 2018 de la commune de Bobo-Dioulasso Component 1: Labor Intensive BF-PEJDC-10595-GO-RFQ / Public Works Acquisition des fournitures de Component 3: Institutional bureau-consommables Request for Single Stage - One Under IDA / 52560 Capacity Strengthening and Post Limited 95,000.00 143.71 2017-10-07 2017-10-02 2017-11-28 2017-12-28 informatique au profit du PTR- Quotations Envelope Implementation Project Management HIMO, de la CCI-BF, de la CMA- Component 2: Skills BF et de l'UCP development BF-PEJDC-10616-GO-DIR / Acquisition d'effet d'habillement Component 1: Labor Intensive Pending au profit d'une cohorte (375 IDA / 52560 Post Direct Selection Direct 45,000.00 0.00 2017-05-17 2017-05-27 2017-07-11 2017-09-09 Public Works Implementation jeunes) de l'année 2018 de la commune d'Ouahigouya BF-PEJDC-10618-GO-DIR / Acquisition de quincaillerie au Component 1: Labor Intensive Pending profit d'une cohorte (375 jeunes) IDA / 52560 Post Direct Selection Direct 30,000.00 0.00 2017-05-19 2017-05-29 2017-07-13 2017-09-11 Public Works Implementation de l'année 2018 de la commune de Ouahigouya BF-PEJDC-10622-GO-DIR / Acquisition de mobilier pour l'équipement des centres Component 1: Labor Intensive d'orientation et d'accueil des Public Works Request for Single Stage - One jeunes dans les 4 communes et IDA / 52560 Post Limited 94,000.00 84,848.40 Signed 2017-07-26 2017-11-17 2017-09-14 2017-12-15 2017-10-14 Component 2: Skills Quotations Envelope le mobilier pour le mobilier pour development le nouveau personnel de la Chambre des Métiers de l'Artisanat BF-PEJDC-10626-GO-DIR / Acquisition de quincaillerie au Component 1: Labor Intensive Pending profit d'une cohorte (125 jeunes) IDA / 52560 Post Direct Selection Direct 10,000.00 0.00 2017-05-19 2017-05-29 2017-07-13 2017-09-11 Public Works Implementation de l'année 2018 de la commune de Manga Component 1: Labor Intensive BF-PEJDC-10620-GO-RFQ / Public Works Acquisition des fournitures de Component 3: Institutional bureau-consommables Request for Single Stage - One Under IDA / 52560 Capacity Strengthening and Post Limited 95,000.00 72,120.44 2017-06-17 2017-10-04 2017-08-06 2017-09-05 informatique au profit du PTR- Quotations Envelope Implementation Project Management HIMO, de la CCI-BF, de la CMA- Component 2: Skills BF et de l'UCP development BF-PEJDC-11551-GO-RFQ / acquisition d'équipements de Component 1: Labor Intensive protection individuelles pour les Public Works métiers à risques des jeunes Component 3: Institutional Request for Single Stage - One Under apprenants en mécanique et IDA / 52560 Capacity Strengthening and Post Limited 79,060.00 0.00 2017-04-07 2017-01-26 2017-04-28 2017-10-25 Quotations Envelope Implementation conducteurs de produits Project Management dangereux en formation au Component 2: Skills centre de formation en transport development routier et activités auxiliaires BF-PEJDC-11576-GO-DIR / fourniture et administration de Component 1: Labor Intensive vaccins contre les risques du Public Works métier aux apprenants en Component 3: Institutional formation de mécanique et Under IDA / 52560 Capacity Strengthening and Post Direct Selection Direct 600.00 0.00 2017-04-13 2017-04-03 2017-04-18 2017-04-05 2017-05-23 2017-11-19 conduite de produits dangereux, Implementation Project Management au centre de formation en Component 2: Skills transport routier et auxiliaires development par la Direction de la santé des communs BF-PEJDC-10604-GO-RFQ / Component 1: Labor Intensive Request for Single Stage - One Acquisition de 4 matériels roulant IDA / 52560 Post Limited 8,000.00 7,422.49 Completed 2017-04-15 2017-05-05 2017-06-06 2017-05-31 2017-06-21 2017-06-19 Public Works Quotations Envelope (vélomoteurs hommes) BF-PEJDC-10625-GO-DIR / Acquisition d'effet d'habillement Component 1: Labor Intensive Pending au profit d'une cohorte (125 IDA / 52560 Post Direct Selection Direct 15,000.00 0.00 2017-05-21 2017-05-31 2017-07-15 2017-09-13 Public Works Implementation jeunes) de l'année 2018 de la commune de Manga BF-PEJDC-10606-GO-RFQ / Acquisition d'effet d'habillement Component 1: Labor Intensive Single Stage - One IDA / 52560 Post Request for Bids Open - National 196,000.00 239,928.21 Signed 2017-05-15 2017-06-06 2017-05-20 2017-07-01 2017-07-12 2017-07-31 2017-07-14 2017-09-04 2017-11-15 2018-03-03 au profit d'une cohorte de la Public Works Envelope commune d'Ouagadougou BF-PEJDC-11573-GO-RFB / acquisition des q é uipements par Component 2: Skills Request for Single Stage - One Pending une demande de prix afin IDA / 52560 Post Limited 1,000,000.00 0.00 2017-07-05 2017-08-30 2018-02-26 development Quotations Envelope Implementation é uiper le centre de formation en q tourisme et hôtellerie BF-PEJDC-16615-GO-RFQ / Acquisition de petits matériels et consommable pour Component 1: Labor Intensive Request for Single Stage - One Pending IDA / 52560 Post Limited 8,000.00 0.00 2017-06-08 2017-06-15 2017-06-17 l'expérimentation des crèches Public Works Quotations Envelope Implementation mobiles dans le cadre des THIMO BF-PEJDC-18173-GO-RFQ / Acquisition de mobiliers et Component 3: Institutional é uipements de bureau pour les q Request for Single Stage - One Under IDA / 52560 Capacity Strengthening and Post Limited 20,000.00 0.00 2017-06-30 2017-09-05 2017-08-21 2018-02-17 services de la Direction des Quotations Envelope Implementation Project Management Marchés Publics du Ministère de la jeunesse (DMP/MJFIP) Page 2 BF-PEJDC-24817-GO-RFQ / fourniture d equipememts de protection individuels pour 50 Component 2: Skills Request for Single Stage - One Pending IDA / 52560 Post Limited 8,000.00 0.00 2017-08-29 2017-10-24 2018-04-22 jeunes a former en aviculture development Quotations Envelope Implementation dans le cadre de la formation a la demande BF-PEJDC-24843-GO-RFQ / acquisition d outils de Component 2: Skills Request for Single Stage - One Under communication pour ouverture IDA / 52560 Post Limited 12,000.00 19.91 2017-08-30 2017-09-18 2017-10-25 2018-04-23 development Quotations Envelope Implementation des métiers prioritaires des 2 centres BF-PEJDC-27126-GO-RFQ / Acquisition de matériel Component 1: Labor Intensive Request for Single Stage - One Pending IDA / 52560 Post Limited 10,000.00 0.00 2017-09-25 2017-11-20 2017-12-10 complémentaire pour la phase Public Works Quotations Envelope Implementation pilote des crèches mobiles BF-PEJDC-24675-GO-DIR / Acquisition des effets d'habillement supplémentaires au Component 1: Labor Intensive Request for Single Stage - One IDA / 52560 Post Open - National 37,368.00 41,263.36 Signed 2017-09-20 2017-10-16 2017-11-15 2017-11-15 profit des brigadiers Public Works Quotations Envelope THIMO/PEJDC de la commune de Ouagadougou BF-PEJDC-24820-GO-DIR / fourniture et administration de Component 2: Skills Request for Single Stage - One Pending vaccins a des jeunes dans le IDA / 52560 Post Limited 2,500.00 0.00 2017-09-19 2017-10-30 2018-04-28 development Quotations Envelope Implementation cadre de la formation a la demande BF-PEJDC-33085-GO-RFQ / acquisition des qé uipements de Component 2: Skills Request for Single Stage - One Under protection individuelles dans le IDA / 52560 Post Limited 10,000.00 25.73 2017-11-19 2017-11-09 2017-12-21 2018-01-15 development Quotations Envelope Implementation cadre de la formation des jeunes dans le domaine de l'apiculture BF-PEJDC-35148-GO-RFB / é uipements fourniture des q légers et outillages, du mobilier Component 2: Skills Single Stage - Two Under et matériel informatique et IDA / 52560 Post Request for Bids Open - National 700,000.00 0.00 2017-11-17 2017-12-07 2017-11-22 2018-01-18 2017-12-27 2018-01-24 2018-02-13 2018-03-17 development Envelope Implementation bureautique pour l'ouverture de 04 filières en BTP et 02 filières en TH BF-PEJDC-38602-GO-RFQ / acquisition de matériel Component 1: Labor Intensive Request for Single Stage - One Pending IDA / 52560 Post Limited 35,000.00 0.00 2017-12-23 2018-02-17 2018-08-16 complémentaire pour les crèches Public Works Quotations Envelope Implementation mobiles halte garderie de Manga BF-PEJDC-38606-GO-RFQ / Component 3: Institutional Request for Single Stage - One Pending acquisition d'un antivirus réseau IDA / 52560 Capacity Strengthening and Post Limited 5,000.00 0.00 2017-12-05 2018-01-30 2018-07-29 Quotations Envelope Implementation et de clés USB Project Management BF-PEJDC-38617-GO-RFQ / Acquisition d'équipements de Component 2: Skills Request for Single Stage - One Pending protections individuelles pour les IDA / 52560 Post Limited 80,000.00 0.00 2018-01-13 2018-03-10 2018-09-06 development Quotations Envelope Implementation apprenants dans le cadre de la formation à la demande BF-PEJDC-38922-GO-RFQ / fourniture de dépliants, flyers, affiches, prospectus de Component 2: Skills Request for Single Stage - One Pending IDA / 52560 Post Limited 25,000.00 0.00 2018-02-10 2018-04-07 2018-10-04 présentation et promotion des development Quotations Envelope Implementation formations aux métiers de l'ANPE BF-PEJDC-38900-GO-RFB / Component 2: Skills Single Stage - Two Pending é uipements acquisition des q IDA / 52560 Post Request for Bids Open - International 1,800,000.00 0.00 2018-01-10 2018-01-15 2018-02-26 2018-05-11 2018-06-15 2018-12-12 development Envelope Implementation lourds du CFBTP BF-PEJDC-38619-GO-RFB / Component 2: Skills Single Stage - Two Pending é uipements acquisition des q IDA / 52560 Post Request for Bids Open - International 1,500,000.00 0.00 2018-01-08 2018-01-13 2018-02-24 2018-05-09 2018-06-13 2018-12-10 development Envelope Implementation lourds du CFTH BF-PEJDC-38911-GO-RFB / acquisition de matière d'oeuvre Component 2: Skills Single Stage - One Pending pour la formation des apprentis IDA / 52560 Post Request for Bids Open - National 350,000.00 0.00 2018-01-18 2018-01-23 2018-03-06 2018-04-05 2018-05-10 2018-11-06 development Envelope Implementation CMABF auprès des maître d'apprentissage BF-PEJDC-47332-GO-RFP / Lot 1: Service de pause café, pause Component 3: Institutional déjeuner et de location salle Request for Single Stage - One Pending IDA / 52560 Capacity Strengthening and Post Limited 95,000.00 0.00 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2019-01-05 Lot 2: fournitures et Proposals Envelope Implementation Project Management consommables de bureau Lot 3: gestion de la logistique BF-PEJDC-48911-GO-RFQ / Acquisition d'équipements de Component 1: Labor Intensive Request for Single Stage - One Pending IDA / 52560 Post Open - National 10,000.00 0.00 2018-02-25 2018-03-14 2018-03-24 sécurité pour les membres de la Public Works Quotations Envelope Implementation cellule PEJDC NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PEJDC-10631-NC-RFQ / Location de quatre (04) pelles chargeuses pour les deux (02) Component 1: Labor Intensive Request for Single Stage - One Pending cohortes (4-5) au profit des IDA / 52560 Post Limited 96,000.00 0.00 2017-04-04 2017-05-15 2018-05-15 Public Works Quotations Envelope Implementation communes de Ouagadougou , de Bobo-Dioulasso, de Ouahigouya et Manga BF-PEJDC-10634-NC-DIR / Acquisition de service d- Assurance individuelle accident Component 1: Labor Intensive IDA / 52560 Post Direct Selection Direct 84,000.00 92,495.59 Signed 2017-04-20 2017-04-10 2017-04-30 2017-05-04 2017-06-14 2017-07-11 2018-06-14 au profit des jeunes brigadiers Public Works THIMO/PEJDC pour les cohortes 4 et 5 Page 3 BF-PEJDC-10661-NC-DIR / Component 2: Skills Pending Assurance individuelle accident IDA / 52560 Post Direct Selection Direct 40,000.00 0.00 2017-04-03 2017-04-08 2017-05-09 2018-05-04 development Implementation pour les apprentis de la CMA-BF BF-PEJDC-10664-NC-DIR / Component 3: Institutional Assurance maladie du personnel Pending IDA / 52560 Capacity Strengthening and Post Direct Selection Direct 90,000.00 0.00 2017-07-06 2017-07-11 2017-08-15 2018-08-10 de l'UCP pour la période 2017- Implementation Project Management 2018 BF-PEJDC-10666-NC-DIR / Component 2: Skills Assurances des véhicules et development Pending motos acquis dans le cadre du IDA / 52560 Component 3: Institutional Post Direct Selection Direct 7,000.00 0.00 2017-07-19 2017-07-24 2017-08-28 2018-08-23 Implementation projet (UCP+A.E) pour la période Capacity Strengthening and 2017-2018 Project Management BF-PEJDC-10667-NC-DIR / Component 2: Skills Under Assurance individuelle accident IDA / 52560 Post Direct Selection Direct 48,000.00 0.00 2017-10-30 2016-11-10 2017-11-04 2016-11-10 2017-12-09 2018-12-04 development Implementation pour les apprentis de la CCI-BF BF-PEJDC-10627-NC-RFQ / Location de quatre (04) Component 1: Labor Intensive Request for Single Stage - One IDA / 52560 Post Limited 84,400.00 0.00 Canceled 2017-04-08 2017-05-28 2018-05-28 camionnettes pour les deux (02) Public Works Quotations Envelope prochaines cohortes (4-5) BF-PEJDC-13211-NC-RFB / Location de camion bennes dans le cadre des travaux Component 1: Labor Intensive Request for Single Stage - One Pending IDA / 52560 Post Limited 93,600.00 0.00 2017-05-20 2017-07-15 2018-01-11 HIMO/PEJDC au profit des Public Works Quotations Envelope Implementation communes de Ouahigouya et de Manga BF-PEJDC-13210-NC-RFB / Location de camion bennes basculantes dans le cadre des Component 1: Labor Intensive Single Stage - One IDA / 52560 Post Request for Bids Open - National 262,080.00 213,490.67 Signed 2017-05-11 2017-06-06 2017-05-16 2017-06-27 2017-07-12 2017-07-27 2017-07-13 2017-08-31 2017-11-15 2018-02-27 travaux HIMO/PEJDC au profit Public Works Envelope des communes de Ouagadougou et de Bobo-Dioulasso. BF-PEJDC-10629-NC-RFB / Location des camions lève conteneurs dans le cadre des Component 1: Labor Intensive Single Stage - One IDA / 52560 Post Request for Bids Open - National 149,760.00 243,738.59 Signed 2017-05-11 2017-06-06 2017-05-16 2017-06-27 2017-07-12 2017-07-27 2017-07-12 2017-08-31 2017-11-15 2018-02-27 Travaux HIMO/PEJDC au profit Public Works Envelope des communes de Ouagadougou et de Bobo-Dioulasso BF-PEJDC-18181-NC-RFQ / Component 3: Institutional connexion internet auprès d'un Request for Single Stage - One IDA / 52560 Capacity Strengthening and Post Limited 8,000.00 4,427.88 Signed 2017-08-21 2017-09-18 2017-10-16 2017-10-04 2018-04-14 fournisseur d'accès privé et Quotations Envelope Project Management remplacement du routeur VPN BF-PEJDC-33092-NC-DIR / renouvellement du contrat Component 3: Institutional d'hébergement du serveur dédié Pending IDA / 52560 Capacity Strengthening and Post Direct Selection Direct 7,000.00 0.00 2017-10-26 2017-10-31 2017-11-22 2018-05-21 PEJDC en ligne (site web du Implementation Project Management projet ) auprès de BENIT pour une durée d'un an BF-PEJDC-38611-NC-DIR / Component 3: Institutional renouvellement de la police Pending IDA / 52560 Capacity Strengthening and Post Direct Selection Direct 50,000.00 0.00 2018-05-31 2018-06-05 2018-07-10 2019-01-06 d'assurance santé contractée Implementation Project Management auprès de ALLIANZ BF-PEJDC-38613-NC-DIR / Component 3: Institutional Pending renouvellement de l'assurance IDA / 52560 Capacity Strengthening and Post Direct Selection Direct 15,000.00 0.00 2018-05-31 2018-06-05 2018-07-10 2019-01-06 Implementation auto auprès de la SONAR Project Management BF-PEJDC-38614-NC-DIR / renouvellement de l'assurance individuelle risque accident pour Component 2: Skills Pending les apprenants de la CCIBF dans IDA / 52560 Post Direct Selection Direct 30,000.00 0.00 2017-12-20 2017-12-25 2018-01-29 2018-07-28 development Implementation le cadre des formations à la demande avec JACKSONS ASSURANCE BF-PEJDC-39075-NC-DIR / COPA- contrat de gré à gré avec Component 2: Skills Pending la MEBF pour organisation de la IDA / 52560 Post Direct Selection Direct 400,000.00 0.00 2017-12-08 2017-12-13 2018-01-17 2018-07-16 development Implementation compétition des plans d'affaires des jeunes BF-PEJDC-56499-NC-DIR / police assurance risque individuel accident dans le cadre Component 2: Skills Pending IDA / 52560 Post Direct Selection Direct 1,600.00 0.00 2018-03-30 2018-04-04 2018-05-09 2018-11-05 de l'énumération des apprentis development Implementation dans les 13 régions par gré à gré avec jackson assurance BF-PEJDC-56501-NC-DIR / marché de gré à gré pour la fourniture de divers services par é honie la compagnie de télp Component 2: Skills Pending mobile orange dont la connexion IDA / 52560 Post Direct Selection Direct 100,000.00 0.00 2018-04-03 2018-04-08 2018-05-10 2018-11-06 development Implementation internet,le paiement par orange money chaque quinzaine des enquêteurs dans les 13 régions ... BF-PEJDC-55812-NC-DIR / contrat par entente directe pour visite médicale, examen sanguin et cardiaque obligatoire par l'Office de santé des Component 2: Skills Pending IDA / 52560 Post Direct Selection Direct 20,000.00 0.00 2018-04-13 2018-04-18 2018-05-15 2018-06-22 travailleurs,structure publique development Implementation habilité à délivrer des certificats pour 500 agents de sécurité dans le cadre de la formation à la demande BF-PEJDC-61744-NC-RFQ / Location de 38 salles d- Component 1: Labor Intensive Request for Single Stage - One Pending é iciaires alphabétisation des bénf IDA / 52560 Post Limited 50,920.00 0.00 2018-05-20 2018-06-17 2018-10-15 Public Works Quotations Envelope Implementation THIMO/PEJDC dans la Zone A de Ouagadougou Page 4 BF-PEJDC-61745-NC-RFQ / Location de 32 salles Component 1: Labor Intensive Request for Single Stage - One Pending d'alphabétisation des IDA / 52560 Post Limited 42,880.00 0.00 2018-05-20 2018-06-17 2018-10-15 Public Works Quotations Envelope Implementation é iciaires THIMO/PEJDC bénf dans la Zone B de Ouagadougou BF-PEJDC-61747-NC-RFQ / Location de 30 salles Component 1: Labor Intensive Request for Single Stage - One Pending d'alphabétisation des IDA / 52560 Post Limited 40,200.00 0.00 2018-05-20 2018-06-17 2018-10-15 Public Works Quotations Envelope Implementation é iciaires THIMO/PEJDC bénf dans la Zone C de Ouagadougou BF-PEJDC-61748-NC-RFQ / Location de 20 salles d- Component 1: Labor Intensive Request for Single Stage - One Pending é iciaires alphabétisation des bénf IDA / 52560 Post Limited 26,800.00 0.00 2018-05-20 2018-06-17 2018-10-15 Public Works Quotations Envelope Implementation THIMO/PEJDC dans la Zone D de Ouagadougou BF-PEJDC-61751-NC-RFQ / Location de 25 salles d- Component 1: Labor Intensive Request for Single Stage - One Pending é iciaires alphabétisation des bénf IDA / 52560 Post Limited 33,500.00 0.00 2018-05-20 2018-06-17 2018-10-15 Public Works Quotations Envelope Implementation THIMO/PEJDC dans la Zone B de Bobo-Dioulasso BF-PEJDC-61752-NC-RFQ / Location de 15 salles d'alphabétisation des Component 1: Labor Intensive Request for Single Stage - One Pending IDA / 52560 Post Limited 20,100.00 0.00 2018-05-20 2018-06-17 2018-10-15 é iciaires THIMO/PEJDC bénf Public Works Quotations Envelope Implementation dans la Zone C de Bobo- Dioulasso BF-PEJDC-61753-NC-RFQ / Location de 22 salles d- Component 1: Labor Intensive Request for Single Stage - One Pending é iciaires alphabétisation des bénf IDA / 52560 Post Limited 29,480.00 0.00 2018-05-20 2018-06-17 2018-10-15 Public Works Quotations Envelope Implementation THIMO/PEJDC dans la Zone A de Ouagahigouya BF-PEJDC-61754-NC-RFQ / Location de 13 salles d- Component 1: Labor Intensive Request for Single Stage - One Pending é iciaires alphabétisation des bénf IDA / 52560 Post Limited 17,420.00 0.00 2018-05-20 2018-06-17 2018-10-15 Public Works Quotations Envelope Implementation THIMO/PEJDC dans la Zone B de Ouagahigouya BF-PEJDC-61755-NC-RFQ / Location de 11 salles d- Component 1: Labor Intensive Request for Single Stage - One Pending é iciaires alphabétisation des bénf IDA / 52560 Post Limited 14,740.00 0.00 2018-05-20 2018-06-17 2018-10-15 Public Works Quotations Envelope Implementation THIMO/PEJDC dans la ville de Manga CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PEJDC-10672-CS-CQS / Recrutement de cabinet de Consultant Component 2: Skills formation chargé de la formation IDA / 52560 Post Qualification Open - National 21,150.00 18,501.33 Completed 2017-04-04 2017-05-04 2017-04-25 2017-06-08 2017-08-07 2017-07-08 2017-09-13 2017-08-12 2017-09-20 2017-09-26 2017-11-11 development de 25 formateurs en Selection entreprenariat BF-PEJDC-10677-CS-CQS / ENTRE: Recrutement de cabinet de formation chargé de la réalisation de Formation à l'esprit Consultant d'entreprise et au management Component 2: Skills Under IDA / 52560 Post Qualification Open - National 113,292.00 105,232.60 2017-04-04 2017-05-04 2017-04-25 2017-06-08 2017-08-07 2017-07-08 2017-09-12 2017-08-12 2017-11-10 de la nouvelle entreprise de 500 development Implementation Selection jeunes non scolarisés et déscolarisés et le coaching de 250 jeunes pour le montage de leur projet BF-PEJDC-10679-CS-CQS / NORD ZONE A: Recrutement de cabinet de formation chargé de la réalisation de Formation à Consultant l'esprit d'entreprise et au Component 2: Skills Under IDA / 52560 Post Qualification Open - National 147,280.00 0.00 2017-04-03 2017-04-19 2017-04-24 2017-06-07 2017-08-07 2017-07-07 2017-09-12 2017-08-11 2017-11-28 management de la nouvelle development Implementation Selection entreprise de 650 jeunes non scolarisés et déscolarisés et le coaching de 325 jeunes pour le montage de leur p BF-PEJDC-10680-CS-CQS / NORD ZONE B: Recrutement de cabinet de formation de la réalisation de Formation à l'esprit Consultant d'entreprise et au management Component 2: Skills IDA / 52560 Post Qualification Open - National 147,280.00 132,731.20 Signed 2017-04-03 2017-04-19 2017-04-24 2017-06-07 2017-08-07 2017-07-07 2017-09-12 2017-08-11 2017-09-25 2017-11-28 de la nouvelle entreprise de 650 development Selection jeunes non scolarisés et déscolarisés et le coaching de 325 jeunes pour le montage de leur projet BF-PEJDC-10681-CS-CQS / CENTRE SUD: Recrutement de de cabinet de formation chargé de la réalisation de Formation à Consultant l'esprit d'entreprise et au Component 2: Skills Under IDA / 52560 Post Qualification Open - National 67,975.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-07 2017-08-11 2017-10-31 management de la nouvelle development Implementation Selection entreprise de 300 jeunes non scolarisés et déscolarisés et le coaching de 150 jeunes pour le montage de leur BF-PEJDC-10682-CS-CQS / CENTRE ZONE A : Recrutement de cabinet de formation chargé de la réalisation de Formation en Consultant sur l'identification d'idée de Component 2: Skills Under IDA / 52560 Post Qualification Open - National 174,955.00 0.00 2017-04-03 2017-04-19 2017-04-24 2017-06-12 2017-07-12 2017-08-16 2017-12-07 projet, la création et la gestion development Implementation Selection d'entreprise au profit de 200 jeunes diplômes de la Région du Centre Zone A et le coaching de 1 Page 5 BF-PEJDC-10684-CS-CQS / CENTRE ZONE B: Recrutement de cabinet de formation chargé de la réalisation de Formation Consultant sur l'identification d'idée de Component 2: Skills Under IDA / 52560 Post Qualification Open - National 174,955.00 0.00 2017-04-06 2017-04-19 2017-04-27 2017-06-10 2017-07-10 2017-08-14 2017-12-05 projet, la création et la gestion development Implementation Selection d'entreprise au profit de 200 jeunes diplômes de la Région du Centre Zone B et le coaching de 100 j BF-PEJDC-10685-CS-CQS / CENTRE ZONE C: Recrutement de cabinet de formation chargé de la réalisation de Formation Consultant sur l'identification d'idée de Component 2: Skills Under IDA / 52560 Post Qualification Open - National 174,955.00 0.00 2017-04-24 2017-04-19 2017-05-15 2017-06-28 2017-07-28 2017-09-01 2017-12-23 projet, la création et la gestion development Implementation Selection d'entreprise au profit de 200 jeunes diplômes de la Région du Centre Zone C et le coaching de 100 j BF-PEJDC-10686-CS-CQS / HAUTS BASSINS: Recrutement de cabinet de formation de la réalisation de formations sur Consultant l'identification d'idée de projet, la Component 2: Skills Under IDA / 52560 Post Qualification Open - National 87,478.00 0.00 2017-04-21 2017-04-19 2017-05-12 2017-06-25 2017-07-25 2017-08-29 2017-11-25 création et la gestion development Implementation Selection d'entreprise au profit de 100 jeunes diplôms é et coaching de 50 jeunes diplôms é pour le montage de leur p BF-PEJDC-10687-CS-CQS / NORD: Recrutement de cabinet de formation chargé de la réalisation de Formations sur Consultant l'identification d'idée de projet, la Component 2: Skills Under IDA / 52560 Post Qualification Open - National 43,739.00 0.00 2017-04-14 2017-05-05 2017-06-18 2017-07-18 2017-08-22 2017-10-25 création et la gestion development Implementation Selection d'entreprise au profit de 50 jeunes diplôms é et coaching de 25 jeunes diplôms é pour le montage de leur pro BF-PEJDC-10688-CS-CQS / CENTRE OUEST : Recrutement de cabinet de formation chargé de la réalisation de formations Consultant sur l'identification d'idée de Component 2: Skills Under IDA / 52560 Post Qualification Open - National 65,608.00 0.00 2017-04-25 2017-04-19 2017-05-16 2017-06-29 2017-07-29 2017-09-02 2017-11-29 projet, la création et la gestion development Implementation Selection d'entreprise au profit de 75 jeunes diplôms é et coaching de 38 jeunes diplôms é pour le montage de BF-PEJDC-10712-CS-CDS / Recrutement de consultant pour la sensibilisation aux métiers au Consultant profit des brigadiers Component 1: Labor Intensive Under IDA / 52560 Post Qualification Open - National 292,000.00 0.00 2017-04-16 2017-05-01 2017-06-04 2017-06-19 2017-07-20 2018-01-16 THIMO/PEJDC) des communes Public Works Implementation Selection de Ouagadougou , de Bobo- Dioulasso, de Ouahigouya et Manga BF-PEJDC-10953-CS-QCBS / Component 3: Institutional Recrutement d'un cabinet de Quality And Cost- Pending IDA / 52560 Capacity Strengthening and Post Open - National 200,000.00 0.00 2017-01-20 2017-02-10 2017-03-26 2017-04-23 2017-05-23 2017-06-27 2017-08-01 2018-08-01 é aluation du contrôle et suivi v Based Selection Implementation Project Management projet BF-PEJDC-12876-CS-CQS / Recrutement d'un centre pour la formation de 20 jeunes dans le domaine de l'Agro-pastoral à la Consultant Component 2: Skills Under demande de la Fédr é ation des IDA / 52560 Post Qualification Open - National 15,000.00 0.00 2017-05-10 2017-05-10 2017-05-31 2017-06-22 2017-07-03 2017-08-01 2017-10-30 development Implementation organisations professionnelles Selection agricoles de Bagré (FOPACB), besoins exprimés par leurs membres BF-PEJDC-13084-CS-CQS / recrutement d'un centre pour la formation de 30 techniciens endogènes en techniques Consultant Component 2: Skills Under d'apiculture avancée à la IDA / 52560 Post Qualification Open - National 20,000.00 0.00 2017-04-28 2017-04-19 2017-05-19 2017-07-02 2017-07-12 2017-08-16 2017-11-15 development Implementation demande de l'Union Nationale Selection des Apiculteurs pour ses membres pour un prix unitaire de 330 000 FCFA BF-PEJDC-10678-CS-CQS / HAUTS BASSINS: Recrutement de cabinet de formation de la réalisation de Formation à l'esprit Consultant d'entreprise et au management Component 2: Skills IDA / 52560 Post Qualification Open - National 135,950.00 123,250.40 Signed 2017-04-21 2017-04-19 2017-05-12 2017-06-25 2017-08-07 2017-07-25 2017-09-12 2017-08-29 2017-09-26 2017-12-14 de la nouvelle entreprise de 600 development Selection jeunes non scolarisés et déscolarisés et le coaching de 300 jeunes pour le montage de leur projet BF-PEJDC-10956-CS-QCBS / recrutement d'un cabinet pour la réalisation des Etudes Component 2: Skills Quality And Cost- Pending architecturales techniques suivi IDA / 52560 Post Open - International 260,000.00 0.00 2017-05-02 2017-05-02 2017-05-02 2017-05-02 2017-05-02 2017-05-02 2017-05-02 development Based Selection Implementation contrôle des travaux du Centre de Formation en Bâtiment et Travaux Publics BF-PEJDC-13062-CS-QCBS / Component 2: Skills Quality And Cost- Pending é ude sur le cadre règlementaire t IDA / 52560 Post Open - National 50,000.00 0.00 2017-05-21 2017-06-11 2017-07-25 2017-08-22 2017-09-21 2017-10-26 2017-11-30 2019-07-23 development Based Selection Implementation de l'apprentissage BF-PEJDC-16413-CS-LCS / audit financier et comptable des Component 3: Institutional Pending comptes de l'exercice 2017 du IDA / 52560 Capacity Strengthening and Post Least Cost Selection Open - National 20,000.00 0.00 2017-06-20 2017-07-11 2017-08-24 2017-09-21 2017-10-21 2017-11-25 2017-12-30 2018-02-28 Implementation PEJDC et de ses agences Project Management d'exécution Page 6 BF-PEJDC-16595-CS-CQS / Consultant Formation de 28 apprentis de la Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 8,400.00 0.00 2017-06-14 2017-07-05 2017-08-18 2017-09-17 2017-10-22 2017-12-21 CMA-BF dans la ville de Bobo- development Implementation Selection é evage Dioulasso en l BF-PEJDC-16617-CS-CQS / Consultant Formation de 13 apprentis de la Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 3,900.00 0.00 2017-06-14 2017-07-05 2017-08-18 2017-09-17 2017-10-22 2017-12-21 CMA-BF de la ville de development Implementation Selection Ouagadougou en l é evage BF-PEJDC-16618-CS-CQS / Consultant Formation de 20 jeunes apprentis Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 6,000.00 0.00 2017-06-14 2017-07-05 2017-08-18 2017-09-17 2017-10-22 2018-01-20 CMA-BFde la ville de Ziniaré en development Implementation Selection restauration BF-PEJDC-16619-CS-CQS / Consultant Formation de 07 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 2,100.00 0.00 2017-06-14 2017-07-05 2017-08-18 2017-09-17 2017-10-22 2018-01-20 BF de la ville de Bobo-Dioulasso development Implementation Selection en restauration BF-PEJDC-16620-CS-CQS / Consultant formation de 03 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 900.00 0.00 2017-06-14 2017-07-05 2017-08-18 2017-09-17 2017-10-22 2018-01-20 BF de la ville de Ouagadougou development Implementation Selection en restauration BF-PEJDC-16621-CS-CQS / Consultant formation des 08 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 2,400.00 0.00 2017-06-14 2017-07-05 2017-08-18 2017-09-17 2017-10-22 2018-01-20 BF de la ville de Dori en development Implementation Selection restauration BF-PEJDC-20202-CS-CQS / Consultant formation de 12 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 4,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en construction métallique development Implementation Selection dans la ville de Dédougou BF-PEJDC-20186-CS-CQS / Consultant formation de 12 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 4,000.00 0.00 2017-08-01 2017-08-22 2017-10-05 2017-11-04 2017-12-09 2018-06-07 BF en coupe couture dans la ville development Implementation Selection de Dédougou BF-PEJDC-20332-CS-CQS / Consultant formation de 29 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 9,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en mécanique 2 roues dans development Implementation Selection la ville de Dédougou BF-PEJDC-20322-CS-CQS / Consultant Formation de 16 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 5,000.00 0.00 2017-08-01 2017-08-22 2017-10-05 2017-11-04 2017-12-09 2018-06-07 BF en coiffure de la ville de development Implementation Selection Ouagadougou BF-PEJDC-20325-CS-CQS / Consultant Formation de 65 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 20,000.00 0.00 2017-08-03 2017-08-24 2017-10-07 2017-11-06 2017-12-11 2018-06-09 BF en coiffure de la ville de development Implementation Selection Koudougou BF-PEJDC-20044-CS-CQS / Consultant Formation de 153 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 46,000.00 0.00 2017-10-15 2017-11-05 2017-12-19 2018-01-18 2018-02-22 2018-08-21 BF en coupe couture de la ville development Implementation Selection de Koudougou BF-PEJDC-20040-CS-CQS / Consultant Formation de 7 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 2,100.00 0.00 2017-10-27 2017-11-17 2017-12-31 2018-01-30 2018-03-06 2018-09-02 BF en elevage de la ville de development Implementation Selection Koudougou BF-PEJDC-20042-CS-CQS / Consultant Formation de 20 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 6,000.00 0.00 2017-07-27 2017-08-17 2017-09-30 2017-10-30 2017-12-04 2018-06-02 BF en mécanique automobile de development Implementation Selection la ville de Koudougou BF-PEJDC-20190-CS-CQS / Consultant Formation de 55 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 17,000.00 0.00 2017-08-02 2017-08-23 2017-10-06 2017-11-05 2017-12-10 2018-06-08 BF en mécanique cyclomoteur development Implementation Selection de la ville de Koudougou BF-PEJDC-20323-CS-CQS / Consultant Formation de 34 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 11,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en construction métallique de development Implementation Selection la ville de Manga BF-PEJDC-20335-CS-CQS / Consultant Formation de 56 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 17,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en coupe couture de la ville development Implementation Selection de Manga BF-PEJDC-20337-CS-CQS / Consultant Formation de 8 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 2,500.00 0.00 2017-08-02 2017-08-23 2017-10-06 2017-11-05 2017-12-10 2018-06-08 BF en mécanique automobile de development Implementation Selection la ville de Manga BF-PEJDC-20314-CS-CQS / Consultant Formation de 62 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 19,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en coiffure de la ville de Bobo- development Implementation Selection Dioulasso BF-PEJDC-20336-CS-CQS / Consultant Formation de 139 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 42,500.00 0.00 2017-08-01 2017-08-22 2017-10-05 2017-11-04 2017-12-09 2018-06-07 BF en construction métallique de development Implementation Selection la ville de Bobo-Dioulasso BF-PEJDC-20038-CS-CQS / Consultant Formation de 299 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 89,700.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en coupe couture de la ville development Implementation Selection de Bobo-Dioulasso BF-PEJDC-20185-CS-CQS / Consultant Formation de 28 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 8,500.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en l é ectricité bâtiment de la development Implementation Selection ville de Bobo-Dioulasso Page 7 BF-PEJDC-20191-CS-CQS / Consultant Formation de 54 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 16,200.00 0.00 2017-08-02 2017-08-23 2017-10-06 2017-11-05 2017-12-10 2018-06-08 BF en mécanique automobile de development Implementation Selection la ville de Bobo-Dioulasso BF-PEJDC-20328-CS-CQS / Consultant Formation de 90 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 27,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en mécanique cyclo de la development Implementation Selection ville de Bobo-Dioulasso BF-PEJDC-20029-CS-CQS / Consultant Formation de 38 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 11,500.00 0.00 2017-07-31 2017-08-21 2017-09-23 2017-10-08 2017-11-05 2018-05-04 BF en menuiserie bois de la ville development Implementation Selection de Bobo-Dioulasso BF-PEJDC-20334-CS-CQS / Consultant Formation de 16 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 4,800.00 0.00 2017-08-04 2017-08-25 2017-10-08 2017-11-07 2017-12-12 2018-06-10 BF en construction métallique de development Implementation Selection la ville de Ouayigouya BF-PEJDC-20043-CS-CQS / Consultant Formation de 15 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 4,600.00 0.00 2017-08-01 2017-08-22 2017-10-05 2017-11-04 2017-12-09 2018-06-07 BF en coiffure de la ville de development Implementation Selection Boussé BF-PEJDC-20046-CS-CQS / Consultant Formation de 53 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 16,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en mécanique cyclo de la development Implementation Selection ville de Boussé BF-PEJDC-20333-CS-CQS / Consultant Formation de 08 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 2,500.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en construction métallique de development Implementation Selection la ville de Zorgho BF-PEJDC-20313-CS-CQS / Consultant Formation de 23 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 7,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en coiffure de la ville de development Implementation Selection Zorgho BF-PEJDC-20324-CS-CQS / Consultant Formation de 16 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 4,800.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en agriculture de la ville de development Implementation Selection Zorgho BF-PEJDC-20198-CS-CQS / Consultant Formation de 30 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 9,000.00 0.00 2017-08-01 2017-08-22 2017-09-25 2017-10-25 2017-11-29 2018-05-28 BF en coiffure de la ville de development Implementation Selection Ziniaré BF-PEJDC-20188-CS-CQS / Consultant Formation de 10 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 3,000.00 0.00 2017-08-02 2017-08-23 2017-10-06 2017-11-05 2017-12-10 2018-06-08 BF en mécanique auto de la ville development Implementation Selection de Ziniaré BF-PEJDC-20321-CS-CQS / Consultant Formation de 34 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 11,000.00 0.00 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en mécanique cyclomoteur development Implementation Selection de la ville de Ziniaré BF-PEJDC-20203-CS-CQS / Consultant Formation de 08 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 2,500.00 0.00 2017-10-15 2017-11-05 2017-12-19 2018-01-18 2018-02-22 2018-08-21 BF en menuiserie bois de la ville development Implementation Selection de Ziniaré BF-PEJDC-20199-CS-CQS / Consultant Formation de 54 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 17,000.00 0.00 2017-10-15 2017-11-05 2017-12-19 2018-01-18 2018-02-22 2018-08-21 BF en construction métallique de development Implementation Selection la ville de Ziniaré BF-PEJDC-20183-CS-CQS / Recrutement de prestataires Consultant privés pour la formation de 08 Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 2,500.00 0.00 2017-08-01 2017-08-22 2017-10-05 2017-11-04 2017-12-09 2018-06-07 apprentis CMA-BF en development Implementation Selection construction métallique dans le sud-ouest BF-PEJDC-20037-CS-CQS / Consultant Formation de 18 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 5,500.00 0.00 2017-07-30 2017-08-20 2017-10-03 2017-11-02 2017-12-07 2018-06-05 BF en coupe couture dans le sud- development Implementation Selection ouest BF-PEJDC-24794-CS-CQS / Recrutement de consultant pour la sensibilisation aux thèmes Consultant sociétaux (VIH, l'environnement Component 1: Labor Intensive Under IDA / 52560 Post Qualification Open - National 120,000.00 0.00 2017-09-15 2017-05-10 2017-09-30 2017-10-30 2017-11-14 2017-12-14 2018-06-12 et le civisme) au profit des Public Works Implementation Selection brigadiers de la cohorte 5 des THIMO/PEJDC de la commune de Ouagadougou. BF-PEJDC-10965-CS-CDS / recrutement de centre pour la Consultant Formation à la demande de Component 2: Skills IDA / 52560 Post Qualification Open - National 78,860.00 0.00 Canceled 2017-05-12 2017-05-10 2017-06-02 2017-07-16 2017-08-15 2017-09-19 2018-03-18 l'Association des Auto-écoles development Selection pour assurer la formation de 50 jeunes moniteurs d'auto-écoles BF-PEJDC-24981-CS-CQS / Recrutement de consultant pour la sensibilisation aux thèmes Consultant sociétaux (VIH,environnement et Component 1: Labor Intensive Pending IDA / 52560 Post Qualification Open - National 75,000.00 0.00 2017-09-15 2017-09-30 2017-10-29 2017-11-13 2017-12-12 2018-06-10 civisme) au profit des brigadiers Public Works Implementation Selection de la cohorte 5 des THIMO/PEJDC de la commune de Bobo-Dioulasso BF-PEJDC-25009-CS-CQS / Recrutement de consultant pour la sensibilisation aux thèmes Consultant Component 1: Labor Intensive Pending sociétaux (VIH, l'environnement IDA / 52560 Post Qualification Open - National 50,000.00 0.00 2017-08-30 2017-09-20 2017-10-19 2017-11-03 2017-12-02 2018-05-31 Public Works Implementation et le civisme) des brigadiers de la Selection cohorte 5 des THIMO/PEJDC de la commune de Ouahigouya. Page 8 BF-PEJDC-25013-CS-CQS / Recrutement de consultant pour la sensibilisation aux thèmes Consultant Component 1: Labor Intensive Pending sociétaux (VIH, environnement et IDA / 52560 Post Qualification Open - National 14,000.00 0.00 2017-09-15 2017-09-30 2017-10-29 2017-11-13 2017-12-12 2018-06-10 Public Works Implementation civisme) des brigadiers de la Selection cohorte 5 des THIMO/PEJDC de la commune de Manga. BF-PEJDC-25126-CS-CQS / Recrutement de bureaux d'études chargé de la réalisation Consultant de formation sur l'esprit de Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 182,600.00 0.00 2017-08-30 2017-09-14 2017-10-13 2017-10-28 2017-12-11 2018-01-25 création et de gestion d'AGR et development Implementation Selection d'entreprise au profit de 2200 jeunes brigadiers des cohortes 1 et 2 du Centre BF-PEJDC-25131-CS-CQS / Recrutement de bureaux d'études chargé de la réalisation Consultant de formation sur l'esprit de Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 149,400.00 0.00 2017-08-30 2017-09-20 2017-10-19 2017-11-03 2017-12-02 2018-03-02 création et de gestion d'AGR et development Implementation Selection d'entreprise au profit de 1800 jeunes brigadiers de la cohortes 3 du Centre BF-PEJDC-25142-CS-CQS / Recrutement de bureaux d'études chargé de la réalisation Consultant de formation sur l'esprit de Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 132,800.00 0.00 2017-08-30 2017-09-20 2017-10-19 2017-11-03 2017-12-08 2018-03-08 création et de gestion d'AGR et development Implementation Selection d'entreprise au profit de 1600 jeunes brigadiers de la cohortes 4 du Centre BF-PEJDC-25147-CS-CQS / Recrutement de bureaux d'études chargé de la réalisation Consultant de formation sur l'esprit de Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 83,000.00 0.00 2017-08-30 2017-09-20 2017-10-19 2017-11-03 2017-12-02 2018-03-02 création et de gestion d'AGR et development Implementation Selection d'entreprise au profit de 1000 jeunes brigadiers de la cohortes 1 et 2 des Hauts Bassins BF-PEJDC-25240-CS-CQS / Recrutement de bureaux d'études chargé de la réalisation Consultant de formation sur l'esprit de Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 124,500.00 0.00 2017-08-30 2017-09-20 2017-10-19 2017-11-03 2017-12-02 2018-03-02 création et de gestion d'AGR et development Implementation Selection d'entreprise au profit de 1500 jeunes brigadiers de la cohortes 3 et 4 des Hauts Bassins BF-PEJDC-25250-CS-CQS / Recrutement de bureaux d'études chargé de la réalisation Consultant de formation sur l'esprit de Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 114,855.00 0.00 2017-08-30 2017-09-20 2017-10-19 2017-11-03 2017-12-02 2018-03-02 création et de gestion d'AGR et development Implementation Selection d'entreprise au profit de 1425 jeunes brigadiers de la cohortes 1, 2,3 et 4 du Nord BF-PEJDC-25253-CS-CQS / Recrutement de bureaux d'études chargé de la réalisation Consultant de formation sur l'esprit de Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 38,285.00 0.00 2017-08-30 2017-09-20 2017-10-19 2017-11-03 2017-12-02 2018-03-02 création et de gestion d'AGR et development Implementation Selection d'entreprise au profit de 475 jeunes brigadiers de la cohortes 1, 2,3 et 4 du Centre Sud BF-PEJDC-25255-CS-CQS / Recrutement de bureaux d'études chargé de la réalisation Consultant de formation sur l'esprit de Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 166,000.00 0.00 2017-08-30 2017-09-20 2017-10-19 2017-11-03 2017-12-02 2018-03-02 création et de gestion d'AGR et development Implementation Selection d'entreprise au profit de 2200 jeunes brigadiers des cohortes 5 du Centre BF-PEJDC-25256-CS-CQS / Recrutement de bureaux d'études chargé de la réalisation Consultant de formation sur l'esprit de Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 83,000.00 0.00 2017-08-30 2017-09-20 2017-10-19 2017-11-03 2017-12-02 2018-03-02 création et de gestion d'AGR et development Implementation Selection d'entreprise au profit de 1000 jeunes brigadiers de la cohortes 5 des Hauts Bassins BF-PEJDC-25421-CS-CQS / Recrutement de bureaux d'études chargé de la réalisation Consultant de formation sur l'esprit de Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 48,360.00 0.00 2017-08-30 2017-09-20 2017-10-19 2017-11-03 2017-12-02 2018-03-02 création et de gestion d'AGR et development Implementation Selection d'entreprise au profit de 600 jeunes brigadiers de la cohortes 5 du Nord BF-PEJDC-25429-CS-CQS / Recrutement de bureaux d'études chargé de la réalisation Consultant de formation sur l'esprit de Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 32,240.00 0.00 2017-08-30 2017-09-20 2017-10-19 2017-11-03 2017-12-02 2018-03-02 création et de gestion d'AGR et development Implementation Selection d'entreprise au profit de 200 jeunes brigadiers de la cohortes 5 du Centre Sud BF-PEJDC-25496-CS-CQS / Recrutement d'un prestataire Consultant Component 2: Skills Pending privé pour la formation de 80 IDA / 52560 Post Qualification Open - National 24,000.00 0.00 2017-09-07 2017-09-28 2017-11-11 2017-12-11 2018-01-15 2018-03-16 development Implementation apprentis CMA-BF en l é evage de Selection la ville de Bobo-Dioulasso BF-PEJDC-25497-CS-CQS / Consultant Formation de 148 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 45,000.00 0.00 2017-09-07 2017-09-28 2017-11-11 2017-12-11 2018-01-15 2018-07-14 BF de la ville de Houndé en development Implementation Selection coupe couture Page 9 BF-PEJDC-25498-CS-QCBS / Formation de 31 apprentis CMA- Component 2: Skills Quality And Cost- Pending IDA / 52560 Post Open - National 9,500.00 0.00 2017-09-10 2017-10-01 2017-11-14 2017-12-12 2018-01-11 2018-02-15 2018-03-22 2019-03-22 BF de la ville de Houndé en development Based Selection Implementation construction métallique BF-PEJDC-25499-CS-CQS / Consultant Formation de 53 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 16,000.00 0.00 2017-09-12 2017-10-03 2017-11-16 2017-12-16 2018-01-20 2018-07-19 BF de la ville de Houndé en development Implementation Selection mécanique cyclomoteur BF-PEJDC-25500-CS-CQS / Consultant formation de 11 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 4,000.00 0.00 2017-09-11 2017-10-02 2017-11-15 2017-12-15 2018-01-19 2018-07-18 BF de la ville de Houndé en development Implementation Selection mécanique automobile BF-PEJDC-25502-CS-CQS / Consultant formation de 20 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 6,000.00 0.00 2017-09-14 2017-10-05 2017-11-18 2017-12-18 2018-01-22 2018-07-21 BF en menuiserie bois de la ville development Implementation Selection de Houndé BF-PEJDC-25503-CS-CQS / Consultant Formation de 18 apprentis CMA- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 5,600.00 0.00 2017-09-07 2017-09-28 2017-11-11 2017-12-11 2018-01-15 2018-07-14 BF de la ville de Houndé en development Implementation Selection coiffure BF-PEJDC-20039-CS-CQS / Consultant Formation de 45 apprentis CMA- Component 2: Skills IDA / 52560 Post Qualification Open - National 14,000.00 0.00 Canceled 2017-07-27 2017-08-17 2017-09-30 2017-10-30 2017-12-04 2018-06-02 BF en coupe couture de la ville development Selection de Dori BF-PEJDC-20041-CS-CQS / Consultant Formation de 57 apprentis CMA- Component 2: Skills IDA / 52560 Post Qualification Open - National 17,500.00 0.00 Canceled 2017-10-27 2017-11-17 2017-12-31 2018-01-30 2018-03-06 2018-09-02 BF en mécanique cyclo de la development Selection ville de Dori BF-PEJDC-20315-CS-CQS / Consultant Formation de 34 apprentis CMA- Component 2: Skills IDA / 52560 Post Qualification Open - National 10,200.00 0.00 Canceled 2017-08-01 2017-08-22 2017-10-05 2017-11-04 2017-12-09 2018-06-07 BF en construction metallique de development Selection la ville de Dori BF-PEJDC-20330-CS-CQS / Consultant Formation de 33 apprentis CMA- Component 2: Skills IDA / 52560 Post Qualification Open - National 10,000.00 0.00 Canceled 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en menuiserie bois de la ville development Selection de Dori BF-PEJDC-20331-CS-CQS / Consultant formation de 43 apprentis CMA- Component 2: Skills IDA / 52560 Post Qualification Open - National 12,900.00 0.00 Canceled 2017-08-02 2017-08-23 2017-10-06 2017-11-05 2017-12-10 2018-06-08 BF en coupe couture dans la ville development Selection de Banfora BF-PEJDC-20204-CS-CQS / Consultant formation de 14 apprentis CMA- Component 2: Skills IDA / 52560 Post Qualification Open - National 4,500.00 0.00 Canceled 2017-08-03 2017-08-24 2017-10-07 2017-11-06 2017-12-11 2018-06-09 BF en mécanique cyclo dans la development Selection ville de Banfora BF-PEJDC-20201-CS-CQS / Consultant formation de 11 apprentis CMA- Component 2: Skills IDA / 52560 Post Qualification Open - National 3,500.00 0.00 Canceled 2017-07-28 2017-08-18 2017-10-01 2017-10-31 2017-12-05 2018-06-03 BF en mécanique auto dans la development Selection ville de Banfora BF-PEJDC-29860-CS-INDV / sélection d'un cabinet pour le Component 3: Institutional Consultant Pending recrutement du Coordonnateur et IDA / 52560 Capacity Strengthening and Post Qualification Open - National 10,000.00 0.00 2017-09-27 2017-10-02 2017-10-10 2017-10-17 2017-10-23 2017-11-22 Implementation le spécialiste en gestion Project Management Selection financière de l'UCP BF-PEJDC-33144-CS-CQS / formation à la demande de 50 Consultant Component 2: Skills Pending assistante maternelles et 50 IDA / 52560 Post Qualification Open - National 40,000.00 0.00 2017-11-10 2017-11-24 2017-12-20 2017-12-29 2018-01-22 2018-03-30 development Implementation moniteurs en dé ucation de Selection jeunes enfants BF-PEJDC-33142-CS-CQS / formation à la demande de 285 Consultant Component 2: Skills Pending agents de sécurité pour le IDA / 52560 Post Qualification Open - National 80,000.00 0.00 2017-10-30 2017-11-20 2017-12-10 2017-12-22 2018-01-18 2018-04-18 development Implementation compte d'une société de Selection placement BF-PEJDC-38608-CS-CQS / Component 3: Institutional Consultant sélection d'un cabinet pour le Pending IDA / 52560 Capacity Strengthening and Post Qualification Open - National 12,000.00 0.00 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-11-21 recrutement du personnel Implementation Project Management Selection complémentaire du PEJDC BF-PEJDC-38930-CS-CQS / sélection d'une agence de Consultant communication pour publi- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 99,000.00 0.00 2018-01-22 2018-02-12 2018-03-28 2018-04-27 2018-06-01 2018-11-28 reportage COPA, production et development Implementation Selection diffusion d'un film sur la COPA, médiatisation remise prix COPA BF-PEJDC-39067-CS-CQS / COPA- sélection de structure Consultant Component 2: Skills Pending locale pour suivi- IDA / 52560 Post Qualification Open - National 120,000.00 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-04 2018-12-01 development Implementation accompagnement des lauréats Selection COPA de la région du centre BF-PEJDC-39068-CS-CQS / COPA- sélection de structure Consultant Component 2: Skills Pending locale privée pour suivi- IDA / 52560 Post Qualification Open - National 85,000.00 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-04 2018-12-01 development Implementation accompagnement des lauréats Selection COPA de la région du nord BF-PEJDC-39071-CS-CQS / COPA- sélection de stucture Consultant privée locale pour suivi- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 65,000.00 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-04 2018-12-01 accompagnement des jeunes development Implementation Selection lauréats COPA dans la région des hauts-bassins Page 10 BF-PEJDC-39072-CS-CQS / COPA- sélection de structure Consultant privée local pour suivi - Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 8,500.00 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-04 2018-12-01 accompagnement des lauréats development Implementation Selection COPA de la région du centre- ouest BF-PEJDC-39073-CS-CQS / COPA - sélection de structure Consultant locale privé pour suivi- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 16,500.00 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-04 2018-12-01 accompagnement des lauréats development Implementation Selection COPA dans la région du centre- sud BF-PEJDC-39074-CS-CQS / COPA- sélection de structure Consultant privé locale pour un suivi- Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 27,000.00 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-04 2018-12-01 accompagnement des lauréats development Implementation Selection COPA dans la région du plateau central BF-PEJDC-39386-CS-CQS / sélection de centre pour la Consultant formation de 140 jeunes à la Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 99,000.00 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-04 2018-12-01 demande dans les métiers de development Implementation Selection carreleurs, charpentiers, aide topo, maçons, lé ectriciens BF-PEJDC-39391-CS-CQS / sélection de centre privé pour la Consultant Component 2: Skills Pending formation de 40 jeunes en IDA / 52560 Post Qualification Open - National 30,000.00 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-04 2018-12-01 development Implementation maraîchaiculture à la demande Selection de la faîtière BF-PEJDC-39397-CS-CQS / sélection de centre pour la formation de 70 conducteurs Consultant Component 2: Skills Pending d'engins lourds de chantiers et IDA / 52560 Post Qualification Open - National 180,000.00 0.00 2018-01-25 2018-02-15 2018-03-31 2018-04-30 2018-06-04 2018-12-01 development Implementation 30 mécaniciens d'engins lourds Selection de chantiers à la demande de la faîtière BF-PEJDC-38601-CS-CDS / Consultant sélection de centre pour la Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 60,000.00 0.00 2018-01-22 2018-02-12 2018-03-28 2018-04-27 2018-06-01 2018-11-28 formation à la demande de 80 development Implementation Selection fermiers agricoles BF-PEJDC-38363-CS-CQS / Consultant sélection de centre privé pour Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 35,000.00 0.00 2018-01-24 2018-02-14 2018-03-30 2018-04-29 2018-06-03 2018-11-30 formation à la demande de 40 development Implementation Selection brigadiers phytosanitaires BF-PEJDC-42933-CS-CQS / sélection de centre pour la formation de 200 jeunes dans les Consultant métiers d' aide familiale, Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 140,000.00 0.00 2018-01-30 2018-02-20 2018-04-05 2018-05-05 2018-06-09 2018-12-06 gouvernante d'enfants, development Implementation Selection gouvernante d'étage, hôtesse... dans le cadre de la formation à la demande BF-PEJDC-48780-CS-CQS / formation à la demande de Consultant Component 2: Skills Pending NZAKA et CDPG pour 215 IDA / 52560 Post Qualification Open - National 130,000.00 0.00 2018-02-26 2018-03-19 2018-04-18 2018-05-04 2018-06-08 2018-08-30 development Implementation agents de sécurité par la Selection consultation de trois centres BF-PEJDC-48859-CS-CQS / formation à la demande de 117 Consultant Component 2: Skills Pending jeunes dans le domaine de IDA / 52560 Post Qualification Open - National 80,000.00 0.00 2018-02-28 2018-03-21 2018-05-04 2018-06-03 2018-07-08 2019-01-04 development Implementation l'agroalimentaire par la mise en Selection concurrence de 3 centres privés BF-PEJDC-48930-CS-CQS / Formation de brigadiers THIMO/PEJDC au metier de Consultant Component 1: Labor Intensive Pending CONSTRUCTEUR DE BIO- IDA / 52560 Post Qualification Open - National 22,000.00 0.00 2018-02-20 2018-03-06 2018-03-26 2018-04-05 2018-04-29 2018-06-13 Public Works Implementation DIGESTEUR dans les Selection communes de Ouagadougou et Bobo-Dioulasso BF-PEJDC-48935-CS-CQS / Formation de brigadiers Consultant THIMO/PEJDC au metier de Component 1: Labor Intensive Pending IDA / 52560 Post Qualification Open - National 40,000.00 0.00 2018-02-20 2018-03-06 2018-03-26 2018-04-05 2018-05-01 2018-06-15 BRIQUETIER dans les Public Works Implementation Selection communes de Ouagadougou, Bobo-dioulasso et Ouahigouya BF-PEJDC-48938-CS-CQS / Formation de brigadiers THIMO/PEJDC au métier de Consultant COUTURIER- REPARATEUR DE Component 1: Labor Intensive Pending IDA / 52560 Post Qualification Open - National 70,000.00 0.00 2018-02-20 2018-03-06 2018-03-26 2018-04-05 2018-05-01 2018-06-15 VETEMENTS dans les Public Works Implementation Selection communes de Ouagadougou, Bobo-dioulasso, Ouahigouya et Manga BF-PEJDC-48939-CS-CQS / Formation de brigadiers Consultant THIMO/PEJDC au metier de Component 1: Labor Intensive Pending IDA / 52560 Post Qualification Open - National 32,000.00 0.00 2018-02-20 2018-03-06 2018-03-26 2018-04-05 2018-05-01 2018-06-15 FERRAILLEUR dans les Public Works Implementation Selection communes de Ouagadougou et Bobo-dioulasso BF-PEJDC-48941-CS-CQS / Formation de brigadiers Consultant THIMO/PEJDC au metier de Component 1: Labor Intensive Pending IDA / 52560 Post Qualification Open - National 64,000.00 0.00 2018-02-20 2018-03-06 2018-03-26 2018-04-05 2018-05-01 2018-06-15 FABRICANT DE SAVON dans Public Works Implementation Selection les communes de Ouagadougou, Bobo-dioulasso, Ouahigouya Page 11 BF-PEJDC-48943-CS-CQS / Formation de brigadiers THIMO/PEJDC au metier de Consultant Component 1: Labor Intensive Pending TISSERAND - TEINTURIER IDA / 52560 Post Qualification Open - National 84,000.00 0.00 2018-02-20 2018-03-06 2018-03-26 2018-04-05 2018-05-01 2018-06-15 Public Works Implementation dans les communes de Selection Ouagadougou, Bobo-dioulasso, Ouahigouya et Manga BF-PEJDC-48944-CS-CQS / Formation de brigadiers THIMO/PEJDC au metier de Consultant Component 1: Labor Intensive Pending CORDONNIER dans les IDA / 52560 Post Qualification Open - National 64,000.00 0.00 2018-02-20 2018-03-06 2018-03-26 2018-04-05 2018-05-01 2018-06-15 Public Works Implementation communes de Ouagadougou, Selection Bobo-dioulasso, Ouahigouya et Manga BF-PEJDC-56730-CS-CQS / sélection de cabinet pour fournir au projet des enquêteurs, Consultant Component 2: Skills Pending superviseurs, secrétaire IDA / 52560 Post Qualification Open - National 150,000.00 0.00 2018-04-03 2018-04-10 2018-04-20 2018-04-24 2018-05-10 2018-07-10 development Implementation assistante et informaticien pour Selection une n é umération des apprentis dans 13 régions du Burkina Faso BF-PEJDC-56731-CS-CQS / sélection de cabinet pour fournir Component 3: Institutional Consultant Pending é aluation deux cadres en suivi v IDA / 52560 Capacity Strengthening and Post Qualification Open - National 40,000.00 0.00 2018-04-10 2018-04-17 2018-05-06 2018-05-15 2018-06-19 2018-12-16 Implementation et deux chauffeurs au projet pour Project Management Selection une durée de 8 mois BF-PEJDC-48786-CS-INDV / Consultant formation à la demande pour 16 Component 2: Skills Pending IDA / 52560 Post Qualification Open - National 15,000.00 0.00 2018-05-21 2018-05-22 2018-06-14 2018-07-06 2018-08-10 2018-10-31 jeunes dans le domaine de la development Implementation Selection microfinance INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PEJDC-10668-CS-CDS / Recrutement d'un consultant individuel pour l'assistance technique pour assurer la mise Component 2: Skills Pending en Suvre de la formation à la IDA / 52560 Post Direct Selection Direct 98,025.00 0.00 2017-04-20 2017-04-30 2017-07-04 2017-12-31 development Implementation demande à la CCI-BF et pour la mise en Suvre du système de formation par apprentissage à l'a CMA-BF BF-PEJDC-10711-CS-CDS / Recrutement de consultant pour la sensibilisation sur les thèmes Component 1: Labor Intensive Under sociétaux (VIH, l'environnement IDA / 52560 Post Direct Selection Direct 26,964.00 0.00 2017-04-20 2017-05-10 2017-06-20 2017-12-20 Public Works Implementation et le civisme) au profit des brigadiers THIMO/PEJDC de la commune de Manga BF-PEJDC-10745-CS-CDS / NORD: Recrutement de bureaux d'études chargé de la réalisation Component 2: Skills Under IDA / 52560 Post Direct Selection Direct 57,112.00 0.00 2018-02-20 2017-04-19 2018-03-02 2018-05-06 2018-07-09 de Coaching de 240 jeunes non development Implementation scolarisés et déscolarisés pour le montage de leur projet BF-PEJDC-10746-CS-CDS / CENTRE SUD: Recrutement de bureaux d'études chargé de la Component 2: Skills Under réalisation de Coaching de 80 IDA / 52560 Post Direct Selection Direct 19,335.00 0.00 2018-02-15 2018-02-25 2018-05-01 2018-06-30 development Implementation jeunes non scolarisés et déscolarisés pour le montage de leur projet BF-PEJDC-10751-CS-CDS / Etudes de sols du CF-TH et Component 2: Skills Under CFBTP par le Laboratoire IDA / 52560 Post Direct Selection Direct 20,000.00 0.00 2017-04-05 2017-04-15 2017-04-07 2017-06-19 2017-09-17 development Implementation National des Travaux Publics (LNBTP) BF-PEJDC-10710-CS-CDS / Recrutement de consultant pour la sensibilisation sur les thèmes Component 1: Labor Intensive Under sociétaux (VIH, l'environnement IDA / 52560 Post Direct Selection Direct 76,329.00 0.00 2017-04-20 2017-05-10 2017-06-15 2017-12-15 Public Works Implementation et le civisme) au profit des brigadiers THIMO/PEJDC de la commune de Ouahigouya BF-PEJDC-10691-CS-CDS / CENTRE ZONE B: Recrutement de cabinet de formation chargé Component 2: Skills Under de la réalisation de Coaching de IDA / 52560 Post Direct Selection Direct 190,374.00 0.00 2018-02-16 2017-04-19 2018-02-26 2018-05-02 2018-07-01 development Implementation 800 jeunes non scolarisés et déscolarisés pour le montage de leur projet BF-PEJDC-10693-CS-CDS / HAUTS BASSINS: Recrutement de bureaux d'études chargé de la Component 2: Skills Under réalisation de Coaching de 400 IDA / 52560 Post Direct Selection Direct 95,187.00 0.00 2018-02-19 2018-02-19 2018-03-12 2018-05-11 development Implementation jeunes non scolarisés et déscolarisés pour le montage de leur projet BF-PEJDC-10954-CS-CQS / recrutement de centre pour assurer une formation à la Component 2: Skills Under demande de l'Association des IDA / 52560 Post Direct Selection Direct 149,688.00 0.00 2017-04-25 2017-04-19 2017-05-05 2017-05-11 2017-06-19 2017-12-16 development Implementation Boulangers Pâtissiers pour des jeunes par le centre de formation é ence de Ziniaré de réfr Page 12 BF-PEJDC-10949-CS-CDS / Formation des superviseurs THIMO/PEJDC en secourisme au Component 1: Labor Intensive Under profit des communes de IDA / 52560 Post Direct Selection Direct 4,000.00 0.00 2017-04-10 2017-04-20 2017-06-08 2017-06-23 Public Works Implementation Ouagadougou, de Bobo- Dioulasso, de Ouahigouya et Manga BF-PEJDC-10984-CS-CDS / recrutement d'un centre pour une Formation à la demande des Component 2: Skills Under IDA / 52560 Post Direct Selection Direct 64,885.00 0.00 2017-04-23 2017-04-19 2017-05-08 2017-04-20 2017-06-15 2017-12-12 entreprises , de 80 jeunes pour development Implementation une formation en maintenance et exploitation de Biodigesteurs BF-PEJDC-10985-CS-CDS / recrutement d'un centre pour la Component 2: Skills Under formation à la demande de l' IDA / 52560 Post Direct Selection Direct 88,125.00 0.00 2017-04-24 2017-04-19 2017-05-09 2017-04-20 2017-06-22 2017-12-19 development Implementation Association des Aviculteurs pour former des jeunes en aviculture BF-PEJDC-10708-CS-CDS / Recrutement de consultant pour la sensibilisation sur les thèmes Component 1: Labor Intensive Under sociétaux (VIH, l'environnement IDA / 52560 Post Direct Selection Direct 149,446.00 0.00 2017-04-20 2017-05-10 2017-06-15 2017-12-15 Public Works Implementation et le civisme) au profit des brigadiers THIMO/PEJDC de la commune de Ouagadougou BF-PEJDC-10709-CS-CDS / Recrutement de consultant pour la sensibilisation sur les thèmes Component 1: Labor Intensive Under sociétaux (VIH, l'environnement IDA / 52560 Post Direct Selection Direct 100,290.00 0.00 2017-04-20 2017-05-10 2017-06-19 2017-12-18 Public Works Implementation et le civisme) au profit des brigadiers THIMO/PEJDC de la commune de Bobo-Dioulasso BF-PEJDC-10689-CS-CQS / CENTRE : Recrutement de cabinet de formation chargé de la réalisation de Formation à l'esprit Component 2: Skills Pending d'entreprise et au management IDA / 52560 Post Direct Selection Direct 90,634.00 0.00 2018-02-12 2018-02-22 2018-04-28 2018-06-27 development Implementation de la nouvelle entreprise de 400 jeunes apprenants et le coaching de 200 jeunes pour le montage de leur projet BF-PEJDC-12873-CS-CQS / recrutement d'un centre de formation en vue d'assurer la formation de 70 jeunes dans les Component 2: Skills Individual Consultant Under IDA / 52560 Post Limited 50,000.00 146.17 2017-05-12 2017-05-10 2017-05-12 2017-05-11 2017-05-12 2017-06-12 2017-06-02 2017-11-29 filières du BTP( à la demande de development Selection Implementation l'association des professionnels du bâtiments sur besoins exprimés par leur membres BF-PEJDC-13088-CS-CDS / entente directe avec le CENAFIFF centre de formation Component 2: Skills Under IDA / 52560 Prior Direct Selection Direct 450,000.00 0.00 2017-04-28 2017-05-08 2017-07-12 2018-01-30 Tunisien pour la formation des29 development Implementation formateurs et des gestionnaires du CFTH et du CFBTP BF-PEJDC-11531-CS-INDV / Recrutement de consultant individuel pour vérification liste Component 2: Skills Individual Consultant Under des qé uipements, précision des IDA / 52560 Post Limited 40,000.00 0.00 2017-05-11 2017-05-05 2017-05-19 2017-05-09 2017-05-24 2017-05-15 2017-06-09 2017-08-18 development Selection Implementation spécifications techniques et réception des qé uipements du CFTH et du CFBTP BF-PEJDC-14345-CS-INDV / Recrutement d'un consultant Component 3: Institutional Individual Consultant Pending individuel chargé du suivi- IDA / 52560 Capacity Strengthening and Post Limited 36,000.00 0.00 2017-05-30 2017-06-04 2017-06-25 2017-07-30 2018-07-25 Selection Implementation é aluation de la composante v Project Management apprentissage du Projet BF-PEJDC-16421-CS-CDS / Formation de 190 jeunes de la Component 2: Skills Pending IDA / 52560 Post Direct Selection Direct 56,800.00 0.00 2017-06-14 2017-06-24 2017-08-28 2017-10-27 ville de Ziniaré, boussé et Zorgho development Implementation en elevage avec l'ONG APIL BF-PEJDC-16585-CS-CDS / Formation de 189 jeunes Component 2: Skills Pending apprentis des villes de Ziniaré, IDA / 52560 Post Direct Selection Direct 58,000.00 0.00 2017-06-14 2017-06-24 2017-08-28 2017-10-27 development Implementation Zorgho et Boussé en elavage par l'ONG Wend yam BF-PEJDC-25455-CS-INDV / RECRUTEMENT D'UN CONSULTANT INDIVIDUEL Component 3: Institutional NATIONAL POUR UN APPUI Individual Consultant Pending IDA / 52560 Capacity Strengthening and Post Limited 30,000.00 0.00 2017-08-30 2017-09-04 2017-09-25 2017-10-30 2018-04-28 TECHNIQUE DE PROXIMITE AU Selection Implementation Project Management PROJET EMPLOIS DES JEUNES ET DEVELOPPEMENT DES COMPETENCES BF-PEJDC-25492-CS-CDS / Convention avec le Centre de Formation Professionnelle de é ence de ZINIARE (CFPRZ) Réfr pour la formation de 106 Component 2: Skills Pending IDA / 52560 Post Direct Selection Direct 50,000.00 0.00 2017-09-06 2017-09-16 2017-11-20 2018-05-19 apprentis CMA-BF dont 10 en development Implementation mécanique auto, 34 en mécanique cyclo, 8 en menuiserie bois, 54 en construction métallique BF-PEJDC-25494-CS-CDS / Convention avec le centre de formation de l'Action Sociale pour Component 2: Skills Pending la formation de 29 apprentis IDA / 52560 Post Direct Selection Direct 10,000.00 0.00 2017-09-04 2017-09-14 2017-11-18 2018-05-17 development Implementation CMA-BF à Seba dont 19 en coupe couture et 10 en mécanique auto Page 13 BF-PEJDC-25495-CS-CDS / Convention pour la formation de Component 2: Skills Pending 30 apprentis CMA-BF de la ville IDA / 52560 Post Direct Selection Direct 10,000.00 0.00 2017-09-12 2017-09-22 2017-11-26 2018-05-25 development Implementation de Djibo dont 20 en coupe couture et 10 en mécanique auto BF-PEJDC-18170-CS-INDV / recrutement de consultant individuel pour un Component 1: Labor Intensive Individual Consultant accompagnement à la mise en IDA / 52560 Post Limited 10,000.00 0.00 Canceled 2017-06-30 2017-07-05 2017-07-26 2017-08-30 2018-02-26 Public Works Selection oeuvre de la phase pré pilote des crèches mobiles dans le cadre des THIMO BF-PEJDC-27885-CS-INDV / formation à la demande de Component 2: Skills Individual Consultant Pending ABRDP/PF de 50 jeunes pour IDA / 52560 Post Limited 4,500.00 0.00 2017-09-25 2017-09-30 2017-10-21 2017-11-25 2018-05-24 development Selection Implementation les métiers de tisserands teinturiers BF-PEJDC-24857-CS-CDS / recruter le CFTRA de gré a gré Component 2: Skills Pending IDA / 52560 Post Direct Selection Direct 79,000.00 0.00 2017-10-12 2017-10-22 2017-12-26 2018-06-24 pour assurer la formation de 50 development Implementation moniteurs d auto cé ole BF-PEJDC-27887-CS-CDS / formation à la demande des Component 2: Skills Pending associations de 70 jeunes dans IDA / 52560 Post Direct Selection Direct 40,000.00 0.00 2017-10-15 2017-10-25 2017-12-29 2018-06-27 development Implementation le domaine agro sylvo pastoral par le centre public bagrépole BF-PEJDC-33143-CS-INDV / formation à la demande, de Component 2: Skills Individual Consultant Under séances de perfectionnement et IDA / 52560 Post Limited 20,000.00 27.50 2017-11-20 2017-03-05 2017-11-25 2017-11-17 2017-12-16 2017-11-24 2018-01-20 2018-07-19 development Selection Implementation sensibilisation des chauffeurs routiers à la sécurité routière BF-PEJDC-30013-CS-INDV / sélection d'enquêteurs pour la collecte de données sur la Component 1: Labor Intensive Individual Consultant Under situation des femmes et des IDA / 52560 Post Limited 5,000.00 4.78 2017-11-15 2017-11-03 2017-11-20 2017-11-06 2017-12-01 2017-11-13 2017-12-20 2018-03-30 Public Works Selection Implementation enfants avant, pendant et après les THIMO et sur les crèches mobiles BF-PEJDC-34184-CS-INDV / sélection enquêteur pour collecte de données sur situation femmes Component 1: Labor Intensive Individual Consultant Under IDA / 52560 Post Limited 5,000.00 0.00 2017-11-15 2017-11-03 2017-11-20 2017-11-06 2017-12-11 2017-11-13 2018-01-15 2018-07-14 et enfants avant pendant et après Public Works Selection Implementation THIMO et sur les crèches mobiles BF-PEJDC-34188-CS-INDV / sélection enquêteurs pour collecte de données sur situation Component 1: Labor Intensive Individual Consultant Under IDA / 52560 Post Limited 5,000.00 4.78 2017-11-15 2017-11-05 2017-11-20 2017-11-13 2017-12-11 2017-11-14 2018-01-15 2018-07-14 des femmes et enfants avant Public Works Selection Implementation pendant et après les THIMO et sur les crèches mobiles BF-PEJDC-38597-CS-CDS / entente directe avec l' ENESA Component 2: Skills Under IDA / 52560 Post Direct Selection Direct 30,000.00 32,437.58 2017-12-12 2017-03-06 2017-12-22 2017-03-23 2018-02-25 2018-08-24 pour la formation à la demande development Implementation é inaires pour 40 aides-vétr BF-PEJDC-39214-CS-CDS / Convention de partenariat entre le PTR-HIMO et la MEBF pour la formation des bénf é iciaires des Component 1: Labor Intensive Pending IDA / 52560 Prior Direct Selection Direct 240,000.00 0.00 2017-12-20 2017-12-30 2018-03-05 2018-09-01 Travaux à Haute Intensité de Public Works Implementation Main d'Suvre (THIMO) sur l'esprit de création et de gestion d'AGR et d'entreprises BF-PEJDC-42931-CS-INDV / sélection de consultant pour le perfectionnement de 100 acteurs du secteur des transports dans Component 2: Skills Individual Consultant Pending IDA / 52560 Post Limited 70,000.00 0.00 2018-02-12 2018-02-17 2018-03-10 2018-04-14 2018-10-11 le cadre de la formation à la development Selection Implementation demande (guichetiers, messagers de transport, convoyeurs de transport) BF-PEJDC-42938-CS-CDS / passation d'un avenant au contrat Component 2: Skills Pending du cabinet HUMAN PROJECT IDA / 52560 Post Direct Selection Direct 1,426.00 0.00 2018-01-19 2018-01-29 2018-04-04 2018-10-01 development Implementation pour le recrutement d'un spécialiste TIC du projet BF-PEJDC-47327-CS-INDV / Recrutement d'un consultant Component 3: Institutional Individual Consultant Pending individuel d'un Spécialiste en IDA / 52560 Capacity Strengthening and Post Limited 18,000.00 0.00 2018-02-07 2018-02-12 2018-03-05 2018-04-09 2018-10-06 Selection Implementation Gestion Financière au sein de Project Management l'UCP BF-PEJDC-47330-CS-INDV / Recrutement d'enquêteurs pour Component 3: Institutional Individual Consultant Pending l'énumération et l'identification IDA / 52560 Capacity Strengthening and Post Limited 95,000.00 0.00 2018-03-12 2018-03-17 2018-04-07 2018-05-12 2018-11-08 Selection Implementation des apprentis dans le cadres du Project Management PEJDC BF-PEJDC-47329-CS-CDS / Recrutement du consultant Component 3: Institutional JEKINNOU Pierre Mahougnon Pending IDA / 52560 Capacity Strengthening and Post Direct Selection Direct 35,000.00 0.00 2018-02-19 2018-03-01 2018-05-05 2018-11-01 pour l'énumération et Implementation Project Management l'identification des apprentis dans le cadre du PEJDC BF-PEJDC-47658-CS-CDS / recrutement du consultant Component 3: Institutional Pending OUEDRAOGO Boubacar pour IDA / 52560 Capacity Strengthening and Post Direct Selection Direct 35,000.00 0.00 2018-02-07 2018-02-17 2018-04-23 2018-10-20 Implementation l'énumération et l'identification Project Management des apprentis du PEJDC Page 14 BF-PEJDC-48788-CS-INDV / formation à la demande de 100 Component 2: Skills Individual Consultant Pending IDA / 52560 Post Limited 60,000.00 0.00 2018-02-28 2018-03-05 2018-03-26 2018-04-30 2018-08-30 aides opticiens pour une durée development Selection Implementation de 4 mois BF-PEJDC-48863-CS-CDS / formation à la demande - passation de contrat par entente Component 2: Skills Pending directe avec GABRIEL TABORIN IDA / 52560 Post Direct Selection Direct 50,000.00 0.00 2018-02-28 2018-03-10 2018-05-14 2018-09-25 development Implementation pour la formation de 50 jeunes dans le domaine des biodigesteurs pendant 4 mois BF-PEJDC-51351-CS-INDV / sélection de consultant expert en THIMO pour la capitalisation des acquis de la composante Component 1: Labor Intensive Individual Consultant Pending IDA / 52560 Post Limited 28,000.00 0.00 2018-04-20 2018-04-25 2018-05-16 2018-06-20 2018-12-17 Travaux à Haute Intensité de Public Works Selection Implementation Main d'Suvre (THIMO), interface entre l'unité de coordination et la composante THIMO. BF-PEJDC-56492-CS-INDV / sélection d'un consultant Component 2: Skills Individual Consultant Pending individuel informaticien dans le IDA / 52560 Post Limited 15,000.00 0.00 2018-04-02 2018-04-07 2018-04-28 2018-06-02 2018-11-29 development Selection Implementation cadre de l'énumération des apprentis dans 13 régions BF-PEJDC-47324-CS-INDV / Recrutement d'un consultant Component 3: Institutional Individual Consultant Pending individuel pour appui à la IDA / 52560 Capacity Strengthening and Post Limited 18,000.00 0.00 2018-02-07 2018-02-12 2018-03-05 2018-04-09 2018-10-06 Selection Implementation passation des marchés au sein Project Management de l'UCP BF-PEJDC-57237-CS-INDV / contrat par entente directe avec le consultant GANOU pour un Component 2: Skills Pending IDA / 52560 Post Direct Selection Direct 41,000.00 0.00 2018-04-13 2018-04-23 2018-06-27 2018-12-24 appui technique de proximité development Implementation jusqu'à la fin du projet en décembre. BF-PEJDC-29999-CS-CDS / réalisation NIES complémentaire Component 2: Skills Pending sur le site qui doit abriter le IDA / 52560 Post Direct Selection Direct 24,000.00 0.00 2018-05-24 2018-06-03 2018-06-26 2018-07-27 development Implementation CFBTP et le CFTH à Ouagarinter BF-PEJDC-62034-CS-CDS / formation à la demande de Component 2: Skills Pending jeunes maraîcheculteurs au profit IDA / 52560 Post Direct Selection Direct 30,000.00 0.00 2018-05-10 2018-05-20 2018-07-04 2018-09-30 development Implementation de la faîtiére avec le centre public de kodougou Page 15