The World Bank                                                                                                                                             Report No: ISR7131


                                                                                                  Implementation Status & Results
                                                                                                                 Peru
                                                                                                   PE Rural Electrification (P090116)
Public Disclosure Copy




                         Operation Name: PE Rural Electrification (P090116)                                Project Stage:   Implementation         Seq.No: 13      Status: ARCHIVED    Archive Date:    28-Oct-2012
                                                                              Country: Peru                                         Approval FY:        2006
                         Product Line: IBRD/IDA                               Region: LATIN AMERICA AND CARIBBEAN                   Lending Instrument: Specific Investment Loan
                         Implementing Agency(ies):

                         Key Dates
                         Board Approval Date      07-Mar-2006          Original Closing Date 31-Dec-2011            Planned Mid Term Review Date 31-Jan-2009               Last Archived ISR Date 01-Mar-2012
                         Effectiveness Date       10-Aug-2006          Revised Closing Date 30-Jun-2013             Actual Mid Term Review Date     11-May-2009

                         Project Development Objectives
                         PE Rural Electrification (P090116)
                         Project Development Objective (from Project Appraisal Document)
                         The objective of the proposed Project is to increase access to efficient and sustainable electricity services in rural areas of Peru.

                         Has the Project Development Objective been changed since Board Approval of the Program?

                            Yes           No

                         PE Rural Electrification (P090110)
                         Global Environmental Objective (from Project Appraisal Document)
                         The Project's global environmental objective is to achieve reduction of greenhouse gas emissions through use of renewable energy inrural areas for provision of
                         electricity.
                         Has the Global Environmental Objective been changed since Board Approval of the Program?

                            Yes           No


                         Component(s)
Public Disclosure Copy




                         Component Name                                                                                                           Component Cost
                         Rural Electrification Sub-projects                                                                                               44.37
                         TA for Rural Electrification                                                                                                      3.25
                         Pilot Program to Increase Productive Uses of Electricity                                                                          3.50
                         Project Management                                                                                                                3.75

                         Overall Ratings
                                                                  Previous Rating                      Current Rating



                                                                                                                                                                                                          Page 1 of 5
                             The World Bank                                                                                                                                             Report No: ISR7131



                                                                Previous Rating                           Current Rating
                         Progress towards achievement of PDO    Satisfactory                              Unsatisfactory
                         Progress towards achievement of GEO    Moderately Unsatisfactory                 Moderately Satisfactory
Public Disclosure Copy




                         Overall Implementation Progress (IP)   Moderately Satisfactory                   Unsatisfactory
                         Overall Risk Rating


                         Implementation Status Overview
                         The Project continues to make progress toward meeting its objectives, albeit facing implementation delays. Project results include: (a) electricity distribution companies have
                         completed grid extension projects to serve 78,200 rural households and the installation of 1,772 PV systems, (b) ten electricity distribution companies are participating in the Project,
                         co-financing projects based on grid extension and PV systems;and (c) five contracts under the productive uses promotion component have assisted more than 4,700 rural producers
                         to improve their productivity and incomes through electricity using equipment in Cuzco, Junin and Lima Provinces, while an additional 9 contracts are underway in these and other
                         areas. The Project is facing implementation delays, mostly related to: (i) the right-of-way payments, and (ii) the number of grid extension connections and installed PV systems.


                         Locations
                         Country                                                  First Administrative Division                       Location                                Planned                Actual
                         Peru                                                     Not Entered                                         Departamento de Loreto


                         Results
                         Project Development Objective Indicators
                         Indicator Name                                    Core Unit of Measure                            Baseline                     Current                         End Target
                         Number of new connections outside existing                 Text                     Value         0                            78,273                          160,000
                         concession areas                                                                    Date          07-Feb-2006                  31-Jul-2012                     30-Sep-2012
                                                                                                             Comments                                   Please note that the Value of
                                                                                                                                                        92000, registered on Dec 31,
                                                                                                                                                        2011, is a mistake. The real
                                                                                                                                                        value was around 65,000
                         Increase in MWh/year of electricity consumed               Text                     Value         0                            1,230                           18,000
                         for productive uses in target areas (MWh/Year)
Public Disclosure Copy




                                                                                                             Date          07-Feb-2006                  31-Jul-2012                     30-Sep-2012
                                                                                                             Comments


                         Global Environmental Objective Indicators




                                                                                                                                                                                                              Page 2 of 5
                             The World Bank                                                                                                                 Report No: ISR7131



                         Indicator Name                                     Core Unit of Measure              Baseline      Current                         End Target
                         Number of new connections served by                      Text             Value      0             0                               20,000
                         renewable energy                                                          Date       07-Feb-2006   31-Jul-2012                     30-Sep-2012
Public Disclosure Copy




                                                                                                   Comments                 7,062 connections using PV
                                                                                                                            systems are under
                                                                                                                            installation.

                         Intermediate Results Indicators
                         Indicator Name                                     Core Unit of Measure              Baseline      Current                         End Target
                         Investments by service providers in rural                Text             Value      0             27.61                           23
                         electrification outside concession (USD million)                          Date       07-Feb-2006   31-Jul-2012                     30-Sep-2012
                                                                                                   Comments
                         Issuance of norms, regulations and guidelines            Text             Value      None          --conventional 75%              100%
                         and their adoption for all rural electrification                                                   renewable systyems 100%
                         projects                                                                  Date       07-Feb-2006   31-Jul-2012                     30-Sep-2012
                         - for conventional grids
                                                                                                   Comments                 The Project was key in
                         - for renewable systems
                                                                                                                            obtaining regulatory approval
                                                                                                                            for: (a) national tariffs for
                                                                                                                            regulated service using PV
                                                                                                                            systems; (b) access to FOSE
                                                                                                                            for regulated customers using
                                                                                                                            PV systems: (c) Specific
                                                                                                                            modifications to norms for
                                                                                                                            rural grid extension.
                         Increase in number of enterprises adopting               Text             Value      0             4,970                           9,000
                         electricity using equipment                                               Date       07-Feb-2006   31-Jul-2012                     12-Sep-2012
                                                                                                   Comments
                         Number of proposals approved for financing               Text             Value      0             Total: 63                       Total: 81
                         - Conventional grids                                                                               Conventional: 54                Conventional: 67
                         - Renewable systems                                                                                                                Renewable: 14
Public Disclosure Copy




                                                                                                   Date       07-Feb-2006   30-Apr-2012                     30-Sep-2012
                                                                                                   Comments
                         Increase in investment in electricity using              Text             Value      0             0.92                            1.81
                         equipment (US$ millions)                                                  Date       07-Feb-2006   30-Apr-2012                     30-Sep-2012
                                                                                                   Comments                 11 other contracts still
                                                                                                                            underway.




                                                                                                                                                                               Page 3 of 5
                             The World Bank                                                                                                                                                 Report No: ISR7131



                         Investments by service providers in rural                  Text              Value          0                                  27.23                               23
                         electrification outside concession (USD million)                             Date           07-Feb-2006                        30-Apr-2012                         31-Dec-2011
                                                                                                      Comments
Public Disclosure Copy




                         Data on Financial Performance (as of 08-Oct-2012)
                         Financial Agreement(s) Key Dates
                         Project               Ln/Cr/Tf                 Status             Approval Date                 Signing Date           Effectiveness Date        Original Closing Date      Revised Closing Date
                         P090116               IBRD-73660               Effective          07-Mar-2006                   19-Jul-2006            10-Aug-2006               31-Dec-2011                30-Jun-2013
                         P090110               TF-56023                 Effective          19-Jul-2006                   19-Jul-2006            10-Aug-2006               31-Dec-2011                30-Jun-2013

                         Disbursements (in Millions)
                         Project               Ln/Cr/Tf                 Status             Currency           Original             Revised           Cancelled          Disbursed            Undisbursed          % Disbursed
                         P090116               IBRD-73660               Effective          USD                             50.00             49.39               0.61               49.39                  0.00        100.00
                         P090110               TF-56023                 Effective          USD                             10.00             10.00               0.00                3.84                  6.16         38.00


                         Disbursement Graph
Public Disclosure Copy




                         Key Decisions Regarding Implementation
                         None




                                                                                                                                                                                                                  Page 4 of 5
                             The World Bank                                                                                                                          Report No: ISR7131



                         Restructuring History
                         Level two Approved on 26-Mar-2010, Level two Approved on 30-Sep-2010, Level two Approved on 24-Jan-2011, Level two Approved on 20-Mar-2012, Level two Approved on 26-
                         Sep-2012
Public Disclosure Copy




                         Related Projects
                         P090110-PE Rural Electrification
Public Disclosure Copy




                                                                                                                                                                                      Page 5 of 5