The World Bank Report No: ISR7131 Implementation Status & Results Peru PE Rural Electrification (P090116) Public Disclosure Copy Operation Name: PE Rural Electrification (P090116) Project Stage: Implementation Seq.No: 13 Status: ARCHIVED Archive Date: 28-Oct-2012 Country: Peru Approval FY: 2006 Product Line: IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 07-Mar-2006 Original Closing Date 31-Dec-2011 Planned Mid Term Review Date 31-Jan-2009 Last Archived ISR Date 01-Mar-2012 Effectiveness Date 10-Aug-2006 Revised Closing Date 30-Jun-2013 Actual Mid Term Review Date 11-May-2009 Project Development Objectives PE Rural Electrification (P090116) Project Development Objective (from Project Appraisal Document) The objective of the proposed Project is to increase access to efficient and sustainable electricity services in rural areas of Peru. Has the Project Development Objective been changed since Board Approval of the Program? Yes No PE Rural Electrification (P090110) Global Environmental Objective (from Project Appraisal Document) The Project's global environmental objective is to achieve reduction of greenhouse gas emissions through use of renewable energy inrural areas for provision of electricity. Has the Global Environmental Objective been changed since Board Approval of the Program? Yes No Component(s) Public Disclosure Copy Component Name Component Cost Rural Electrification Sub-projects 44.37 TA for Rural Electrification 3.25 Pilot Program to Increase Productive Uses of Electricity 3.50 Project Management 3.75 Overall Ratings Previous Rating Current Rating Page 1 of 5 The World Bank Report No: ISR7131 Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Unsatisfactory Progress towards achievement of GEO Moderately Unsatisfactory Moderately Satisfactory Public Disclosure Copy Overall Implementation Progress (IP) Moderately Satisfactory Unsatisfactory Overall Risk Rating Implementation Status Overview The Project continues to make progress toward meeting its objectives, albeit facing implementation delays. Project results include: (a) electricity distribution companies have completed grid extension projects to serve 78,200 rural households and the installation of 1,772 PV systems, (b) ten electricity distribution companies are participating in the Project, co-financing projects based on grid extension and PV systems;and (c) five contracts under the productive uses promotion component have assisted more than 4,700 rural producers to improve their productivity and incomes through electricity using equipment in Cuzco, Junin and Lima Provinces, while an additional 9 contracts are underway in these and other areas. The Project is facing implementation delays, mostly related to: (i) the right-of-way payments, and (ii) the number of grid extension connections and installed PV systems. Locations Country First Administrative Division Location Planned Actual Peru Not Entered Departamento de Loreto Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of new connections outside existing Text Value 0 78,273 160,000 concession areas Date 07-Feb-2006 31-Jul-2012 30-Sep-2012 Comments Please note that the Value of 92000, registered on Dec 31, 2011, is a mistake. The real value was around 65,000 Increase in MWh/year of electricity consumed Text Value 0 1,230 18,000 for productive uses in target areas (MWh/Year) Public Disclosure Copy Date 07-Feb-2006 31-Jul-2012 30-Sep-2012 Comments Global Environmental Objective Indicators Page 2 of 5 The World Bank Report No: ISR7131 Indicator Name Core Unit of Measure Baseline Current End Target Number of new connections served by Text Value 0 0 20,000 renewable energy Date 07-Feb-2006 31-Jul-2012 30-Sep-2012 Public Disclosure Copy Comments 7,062 connections using PV systems are under installation. Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Investments by service providers in rural Text Value 0 27.61 23 electrification outside concession (USD million) Date 07-Feb-2006 31-Jul-2012 30-Sep-2012 Comments Issuance of norms, regulations and guidelines Text Value None --conventional 75% 100% and their adoption for all rural electrification renewable systyems 100% projects Date 07-Feb-2006 31-Jul-2012 30-Sep-2012 - for conventional grids Comments The Project was key in - for renewable systems obtaining regulatory approval for: (a) national tariffs for regulated service using PV systems; (b) access to FOSE for regulated customers using PV systems: (c) Specific modifications to norms for rural grid extension. Increase in number of enterprises adopting Text Value 0 4,970 9,000 electricity using equipment Date 07-Feb-2006 31-Jul-2012 12-Sep-2012 Comments Number of proposals approved for financing Text Value 0 Total: 63 Total: 81 - Conventional grids Conventional: 54 Conventional: 67 - Renewable systems Renewable: 14 Public Disclosure Copy Date 07-Feb-2006 30-Apr-2012 30-Sep-2012 Comments Increase in investment in electricity using Text Value 0 0.92 1.81 equipment (US$ millions) Date 07-Feb-2006 30-Apr-2012 30-Sep-2012 Comments 11 other contracts still underway. Page 3 of 5 The World Bank Report No: ISR7131 Investments by service providers in rural Text Value 0 27.23 23 electrification outside concession (USD million) Date 07-Feb-2006 30-Apr-2012 31-Dec-2011 Comments Public Disclosure Copy Data on Financial Performance (as of 08-Oct-2012) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P090116 IBRD-73660 Effective 07-Mar-2006 19-Jul-2006 10-Aug-2006 31-Dec-2011 30-Jun-2013 P090110 TF-56023 Effective 19-Jul-2006 19-Jul-2006 10-Aug-2006 31-Dec-2011 30-Jun-2013 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P090116 IBRD-73660 Effective USD 50.00 49.39 0.61 49.39 0.00 100.00 P090110 TF-56023 Effective USD 10.00 10.00 0.00 3.84 6.16 38.00 Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation None Page 4 of 5 The World Bank Report No: ISR7131 Restructuring History Level two Approved on 26-Mar-2010, Level two Approved on 30-Sep-2010, Level two Approved on 24-Jan-2011, Level two Approved on 20-Mar-2012, Level two Approved on 26- Sep-2012 Public Disclosure Copy Related Projects P090110-PE Rural Electrification Public Disclosure Copy Page 5 of 5