The World Bank Report No: ISR3065 Implementation Status & Results India Public Disclosure Copy Bihar Kosi Flood Recovery Project (P122096) Operation Name: Bihar Kosi Flood Recovery Project (P122096) Project Stage: Implementation Seq.No: 1 Status: ARCHIVED Last Modified Date: 20-Jun-2011 Country: India Approval FY: 2011 Product Line: IBRD/IDA Region: SOUTH ASIA Lending Instrument: Emergency Recovery Loan Implementing Agency(ies): Bihar Aapda Purniwas and Punarnirman Society Key Dates Board Approval Date 09-Sep-2010 Original Closing Date 14-Sep-2014 Planned Mid Term Review Date 14-Jan-2013 Last Archived ISR Date Effectiveness Date 08-Mar-2011 Revised Closing Date 14-Sep-2014 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost A. Housing Reconstruction 60.00 B. Roads and Bridges 70.00 C. Strengthening Flood Management Capacity 30.00 D. Livelihood Support and Enhancement 30.00 E. Contingency Fund 20.00 Public Disclosure Copy F. Project Management and Implementation Support 10.00 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Overall Implementation Progress (IP) Satisfactory Overall Risk Rating Substantial Implementation Status Overview The credit was approved on September 09, 2010 and became effective on March 08, 2011. The Project Management Unit in the form of Bihar Aapada Puarwas Evam Punarnirman Society (BAPEPS) has been created and Project Director has been appointed. Page 1 of 4 The World Bank Report No: ISR3065 Process for selection of consultants: Third party Quality Audit and Procurement and Financial Management Support has been initiated. Other staff recruitment and preparation of the Public Disclosure Copy Project MIS has also been initiated. First installment for reconstruction of houses for about 30,000 beneficiaries has been approved released by BAPEPS. About 330 houses are now complete and 11400 are at various stages of construction. First ISR Mission now in the field (June 13-17, 2011). Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of flood affected households having Percentage Value 0.00 new houses in project area Date 14-Jun-2011 Comments Number of flood affected households having Percentage Value new houses in project area Date 00000000 Comments Communities with increased access to finance Percentage Value 0.00 through SHGs and improved employment opportunities in farm and non-farm sectors Date 14-Jun-2011 Comments Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Effective disbursement of contingent Amount(USD) Value emergency response financing in case of future disasters Date Public Disclosure Copy Comments Completion of technical studies and Text Value establishment of center of excellence to better understand the flood and sediment Date management Comments Completion of structural investments to Text Value strenghten existing embankments Date Comments Page 2 of 4 The World Bank Report No: ISR3065 Indicator Name Core Unit of Measure Baseline Current End Target Completion of structural investments to Text Value Public Disclosure Copy strenghten existing embankments Date 00000000 Comments Km of roads constructed Number Value Date Comments Number of bridges constructed Number Value Date Comments Increased income by at least 30% of the Percentage Value baseline Date Comments Reduced hight cost debt of SHG members Percentage Value Date Comments Number of precipitation and river flow gauge Number Value stations set up Date Comments Flood Risk Managment Plan prepared Text Value Date Public Disclosure Copy Comments Asset Management Plan prepared Text Value Date Comments Amount of funds disbursed in a future Amount(USD) Value emergency (if triggered) Date Comments Data on Financial Performance (as of 24-Mar-2011) Page 3 of 4 The World Bank Report No: ISR3065 Financial Agreement(s) Key Dates Public Disclosure Copy Project Loan No. Status Approval Date Signing Date Effectiveness Date Closing Date P122096 IDA-48020 Effective 09-Sep-2010 12-Jan-2011 08-Mar-2011 14-Sep-2014 Disbursements (in Millions) Project Loan No. Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P122096 IDA-48020 Effective XDR 148.80 148.80 0.00 12.60 136.20 8.00 Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation 1) Selection of Third Party Quality Audit Consultants and Procurement and Financial Management Support Consultancy has been initiated. 2) First installment for reconstruction of houses for about 30,000 beneficiaries has been approved and released by BAPEPS. 3) BAPEPS has initiated the process of appointment of staff and creation of the project MIS. Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Page 4 of 4