Public Disclosure Copy The World Bank Implementation Status & Results Report Naghlu Hydropower Rehabilitation Project (P132944) Naghlu Hydropower Rehabilitation Project (P132944) SOUTH ASIA | Afghanistan | Energy & Extractives Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2016 | Seq No: 4 | ARCHIVED on 10-Nov-2017 | ISR29862 | Implementing Agencies: Islamic Republic of Afghanistan, Da Afghanistan Breshna Sherkat Key Dates Key Project Dates Bank Approval Date:14-Dec-2015 Effectiveness Date:19-Jan-2016 Planned Mid Term Review Date:31-Dec-2018 Actual Mid-Term Review Date:-- Original Closing Date:30-Sep-2022 Revised Closing Date:30-Sep-2022 Project Development Objectives Project Development Objective (from Project Appraisal Document)
The Project Development Objective (PDO) is to improve dam safety and to increase the supply of electricity at the Naghlu Hydropower Plant.
Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component 1: Mechanical, Electrical, and Electromechanical Works:(Cost $30.00 M) Component 2: Dam Safety and Power Generation Capacity Improvement:(Cost $33.00 M) Component 3: Environmental and Social Sustainability, Project Management Support, and Future Project Preparation:(Cost $20.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating High High 11/10/2017 Page 1 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Naghlu Hydropower Rehabilitation Project (P132944) Implementation Status and Key Decisions The Naghlu Hydropower Rehabilitation Project (NHRP) has been effective since January 24, 2016. Key rehabilitation work of units 1 and 3 of the hydropower plant has been making steady progress. It is expected that both units will be operational during the first half of 2018. Progress on the dam safety component is slower than expected due to the lack of interest of qualified consultants to work in Afghanistan. The electrification of 18 villages near Naghlu, which is part of the benefit sharing program under the project for the hydropower plant, is well underway. The hard work by the power utility DABS to make this project a success is commended. Overall the project is on track. 11/10/2017 Page 2 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Naghlu Hydropower Rehabilitation Project (P132944) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Substantial Macroeconomic High High High Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Sustainability High High High Fiduciary Substantial Substantial Substantial Environment and Social High High High Stakeholders Substantial Substantial Substantial Other -- -- -- Overall High High High Results Project Development Objective Indicators PHINDPDOTBL Installed Capacity of Unit-1 Ready for Utilization (Megawatt, Custom) Baseline Actual (Previous) Actual (Current) End Target 11/10/2017 Page 3 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Naghlu Hydropower Rehabilitation Project (P132944) Value 0.00 0.00 0.00 25.00 Date 31-Dec-2015 25-Apr-2017 25-Apr-2017 30-Sep-2022 PHINDPDOTBL Total Number of Un-planned Power Outages due to Deficiency of NHPP (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 100.00 130.00 130.00 20.00 Date 31-Dec-2015 25-Apr-2017 25-Apr-2017 30-Sep-2022 PHINDPDOTBL Dam Safety Procedures Developed and Maintained (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 31-Dec-2015 25-Apr-2017 25-Apr-2017 30-Sep-2022 PHINDPDOTBL Number of Villages in the Immediate Vicinity of the Dam Provided with Access to Electricity by the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 8.00 Date 31-Dec-2015 -- 25-Apr-2017 30-Sep-2022 Overall Comments Intermediate Results Indicators 11/10/2017 Page 4 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Naghlu Hydropower Rehabilitation Project (P132944) PHINDIRITBL Overhaul of Unit-3 Completed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 31-Dec-2015 -- 25-Apr-2017 30-Sep-2022 PHINDIRITBL Dam Safety Audit in Place (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N -- N Y Date 31-Dec-2015 -- 25-Apr-2017 30-Sep-2022 PHINDIRITBL Number of Staff Trained in Hydropower Operation and Maintenance under the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 130.00 Date 31-Dec-2015 25-Apr-2017 25-Apr-2017 30-Sep-2022 PHINDIRITBL Feasibility Study of Options to Increase Power Generation at NHPP Completed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 31-Dec-2015 25-Apr-2017 25-Apr-2017 30-Sep-2022 11/10/2017 Page 5 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Naghlu Hydropower Rehabilitation Project (P132944) PHINDIRITBL Number of Local People Receiving Vocational Training through the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 60.00 Date 31-Dec-2015 25-Apr-2017 25-Apr-2017 30-Sep-2022 PHINDIRITBL Out of which the percentage of women trained (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 PHINDIRITBL Grievances reported related to delivery of project benefits that are addressed (Percent) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 75.00 50.00 Date 31-Dec-2015 25-Apr-2017 25-Apr-2017 30-Sep-2022 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P132944 TF-A1691 Effective USD 83.00 83.00 0.00 8.89 74.11 11% Key Dates (by loan) 11/10/2017 Page 6 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Naghlu Hydropower Rehabilitation Project (P132944) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P132944 TF-A1691 Effective 14-Dec-2015 19-Jan-2016 19-Jan-2016 30-Sep-2022 30-Sep-2022 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 11/10/2017 Page 7 of 7 Public Disclosure Copy