PROCUREMENT PLAN (Textual Part) Project information: Preparation of Proposed Sustainable Forests and Livelihood Project Project Implementation agency: Forest Department of Ministry of Environment and Forest, Bangladesh Date of the Procurement Plan: September 13, 2017 Period covered by this Procurement Plan: September 2017 to June 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules 2008, as amended in August 2009) , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions : a) e-GP system of the country for national competitive bidding (NCB) shall be followed using Standard/Model Procurement documents satisfactory to the Bank b) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; c) Bids should be submitted and opened in public in one location immediately after the deadline for submission; d) Lottery in award of contracts shall not be allowed; e) Bidders’ qualification/experience requirement shall be mandatory f) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). “Not Applicable” PROCUREMENT Bangladesh : Sustainable Forests & Livelihoods (SUFAL) Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2017-09-13 2021-09-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161996 GPN Date: 2019-02-26 Project Name: Sustainable Forests & Livelihoods (SUFAL) Project Loan / Credit No: IDA / V1280, / , IDA / 63250 F Executing Agency(ies): orest Department WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned WD 2-A / Repair and Renovation works of PMU Project Management, Request for Single Stage - One 2020-04- IDA / 63250 Post Limited 11,500.00 0.00 Canceled 2019-09-07 2019-11-02 Office at Ban Bhaban, Monitoring and Reporting Quotations Envelope 30 Agargaon, Dhaka. WD 2-1 / Renovation of Ban Project Management, Single Stage - One 2019-11- Bhaban for PMU of SUFAL IDA / 63250 Post Request for Bids Open - National 48,000.00 0.00 Canceled 2019-05-30 2019-06-04 2019-07-02 2019-07-30 2019-09-03 Monitoring and Reporting Envelope 02 Project WD-2/A / Repair and renovation works of Project Project Management, Single Stage - One 2021-03- Management Unit of SUFAL IDA / 63250 Post Request for Bids Open - National 43,500.00 33,204.96 Signed 2020-09-14 2020-11-08 2020-09-19 2020-10-04 2020-11-26 2020-11-03 2021-01-07 2020-12-01 2021-02-11 Monitoring and Reporting Envelope 31 Project at Ban Bhaban, Agargaon, Dhaka. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Collaborative GD1 / Procurement of Digital Request for Single Stage - One IDA / V1280 Forest and Protected Areas Post Limited 2,500.00 2,357.85 Completed 2017-10-19 2018-06-11 2017-11-01 2018-06-21 2017-11-06 2018-06-25 Cameras (4 nos) Quotations Envelope Management GD5 / Procurement of Printer Request for Single Stage - One / Post Limited 4,500.00 0.00 Canceled 2017-10-02 2017-10-21 2017-10-26 (Heavy Duty) Quotations Envelope Strengthening Institutions, GD11 / Procurement of Air Request for Single Stage - One IDA / V1280 Information Systems and Post Limited 5,625.00 4,910.06 Completed 2017-10-25 2018-05-10 2017-11-15 2018-05-21 2017-11-22 2018-05-30 conditioner for PMU (3 nos) Quotations Envelope Training Strengthening Collaborative GD12 / Procurement of GPS Request for Single Stage - One IDA / V1280 Forest and Protected Areas Post Limited 5,000.00 3,770.66 Completed 2017-10-18 2018-06-11 2017-11-05 2018-06-21 2017-11-12 2018-06-25 (8 nos) Quotations Envelope Management GD3 / Procurement of Desktop Computer with UPS Strengthening Institutions, Single Stage - One ,Laptop ,Printer, Photocopier, IDA / V1280 Information Systems and Post Request for Bids Open - National 48,500.00 40,439.92 Completed 2018-02-25 2018-05-15 2018-02-28 2018-03-14 2018-05-30 2018-03-22 2018-05-31 2018-03-28 2018-06-12 2018-04-04 2018-06-24 Envelope Multimedia Projector and Training Scanner ( 10+17+6+3+1+10) GD2 / Procurement of Single Stage - One / Post Request for Bids Open - National 7,500.00 0.00 Canceled 2017-10-05 2017-10-12 2017-10-30 2017-11-20 2017-12-07 2017-12-14 Desktop Computer with UPS Envelope GD4 / Procurement of Printer Request for Single Stage - One / Post Limited 3,000.00 0.00 Canceled 2017-11-05 2017-11-19 2017-11-22 (Regular) Quotations Envelope GD8 / Procurement of Request for Single Stage - One / Post Limited 1,250.00 0.00 Canceled 2017-11-08 2017-11-25 2017-11-30 Multimedia Projector (1 no) Quotations Envelope GD7 / Procurement of Single Stage - One / Post Request for Bids Open - National 16,875.00 0.00 Canceled 2017-10-05 2017-10-12 2017-10-30 2017-11-20 2017-12-09 2017-12-19 Photocopier (3 nos) Envelope GD9 / Procurement of Request for Single Stage - One / Post Limited 2,500.00 0.00 Canceled 2017-10-19 2017-11-02 2017-11-05 Scanner ( 10 Nos) Quotations Envelope GD-13 / Procurement of Desktop Computer with UPS Project Management, Request for Single Stage - One ,Laptop ,Printer, Photocopier, IDA / V1280 Post Limited 6,000.00 5,948.33 Completed 2018-01-31 2018-02-22 2018-02-14 2018-03-08 2018-02-20 2018-03-20 Monitoring and Reporting Quotations Envelope Multimedia Projector and Scanner GD-14 / Procurement of Project Management, Request for Single Stage - One IDA / V1280 Post Limited 6,000.00 5,299.46 Completed 2018-01-31 2018-03-25 2018-02-14 2018-04-02 2018-02-20 2018-04-17 Office Furniture Monitoring and Reporting Quotations Envelope GD10 / Procurement of Office Project Management, Single Stage - One IDA / V1280 Post Request for Bids Open - National 16,500.00 13,693.01 Completed 2018-02-18 2018-05-22 2018-02-22 2018-03-08 2018-06-07 2018-03-15 2018-06-07 2018-03-25 2018-06-12 2018-04-01 2018-06-24 Furniture Monitoring and Reporting Envelope GD-15 / Desktop Computer Project Management, Request for Single Stage - One IDA / V1280 Post Limited 3,250.00 0.00 Canceled 2018-09-20 2018-10-04 2018-10-15 and Laptop Monitoring and Reporting Quotations Envelope GD6 / Procurement of Request for Single Stage - One / Post Limited 1,875.00 0.00 Canceled 2017-09-28 2017-10-16 2017-10-30 Accounting Software for PMU Quotations Envelope GD 8-1 / Supply and Strengthening Institutions, Single Stage - One Installation of Photocopiers IDA / 63250 Information Systems and Post Request for Bids Open - National 166,670.00 0.00 Canceled 2019-05-11 2019-05-15 2019-05-16 2019-06-08 2019-06-13 2019-06-22 2019-07-10 2019-07-09 2019-08-24 Envelope for PMU, MOFFCC, FIU and Training BFD GD 18-1 / Supply and Installation of Printer, Strengthening Institutions, Single Stage - One Scanner, Multimedia, LED IDA / 63250 Information Systems and Post Request for Bids Open - National 98,220.00 0.00 Canceled 2019-05-11 2019-05-15 2019-05-16 2019-06-08 2019-06-13 2019-06-22 2019-07-10 2019-07-09 2019-08-24 Envelope screen etc for PMU, MOFFCC, Training FIU and BFD. Page 1 GD 2-1 / Supply, Fitting and Project Management, Single Stage - One Fixing of Furniture for PMU of IDA / 63250 Post Request for Bids Open - National 30,000.00 17,301.86 Signed 2019-05-30 2019-06-03 2019-06-04 2019-07-02 2019-06-24 2019-07-30 2019-07-28 2019-09-03 2019-08-25 2019-10-18 Monitoring and Reporting Envelope SUFAL Project GD – 19.1 / Supply and Installation of Air Conditioner Project Management, Request for Single Stage - One IDA / 63250 Post Limited 5,060.00 4,950.76 Signed 2019-07-05 2019-06-24 2019-07-25 2019-07-02 2019-08-15 for the conference room of Monitoring and Reporting Quotations Envelope Bangladesh Forest Department GD-36 / Procurement of 85 Strengthening Institutions, Single Stage - One Nos. Laptop for RIMS & Field IDA / 63250 Information Systems and Post Request for Bids Open - National 126,488.00 0.00 Canceled 2019-03-03 2019-03-08 2019-03-31 2019-04-14 2019-05-01 2019-06-16 Envelope Office. Training GD 1-1 / Supply of Laptop Strengthening Institutions, and Desktop Computer and Single Stage - One IDA / 63250 Information Systems and Post Request for Bids Open - National 224,108.00 0.00 Canceled 2019-05-12 2019-05-15 2019-05-17 2019-06-09 2019-06-23 2019-07-10 2019-08-25 related accessories for PMU, Envelope Training MOFFCC, FIU and BFD. GD-6 / Computer operating Licence software (Like Project Management, Request for Single Stage - One IDA / 63250 Post Limited 5,952.00 0.00 Canceled 2018-12-11 2018-12-25 2019-01-08 Windows,MS Office,Adobe Monitoring and Reporting Quotations Envelope etc.) GD 15 / Procurement of Project Management, Request for Single Stage - One Desktop Computer-2, Laptop- IDA / 63250 Post Limited 5,190.00 0.00 Canceled 2018-12-17 2019-01-01 2019-01-12 Monitoring and Reporting Quotations Envelope 1& Printer- 1 GD-16 / Office Furniture with Project Management, Request for Single Stage - One Work Station for New office of IDA / 63250 Post Limited 17,238.00 0.00 Canceled 2018-12-10 2018-12-20 2019-01-20 Monitoring and Reporting Quotations Envelope SUFAL Project GD 17 / Procurement of Project Management, Request for Single Stage - One Photocopier Machine (Heavy IDA / 63250 Post Limited 5,357.00 0.00 Canceled 2018-12-09 2018-12-23 2019-01-06 Monitoring and Reporting Quotations Envelope duty) GD 1 / Supply and Installation of Laptop, Strengthening Institutions, Single Stage - One Desktop Computer and IDA / 63250 Information Systems and Post Request for Bids Open - National 383,095.00 302,700.64 Signed 2019-08-22 2019-08-20 2019-08-27 2019-09-24 2019-09-16 2019-10-22 2019-11-03 2019-11-26 2019-12-02 2020-02-24 Envelope Related Accessories for PMU, Training MoEFCC, FIU and BFD GD 5-1 / Supply and Project Management, Request for Single Stage - One Installation Two (2) heavy duty IDA / 63250 Post Limited 3,571.00 0.00 Canceled 2020-02-07 2020-04-03 2020-09-30 Monitoring and Reporting Quotations Envelope IPS for PMU GD 8 / Supply and Strengthening Institutions, Single Stage - One Installation of Photocopiers IDA / 63250 Information Systems and Post Request for Bids Open - National 228,571.00 170,044.97 Signed 2019-08-19 2019-08-22 2019-08-24 2019-09-14 2019-09-16 2019-10-26 2019-10-20 2019-11-30 2019-10-30 2020-02-28 Envelope for PMU, MOFFCC, FIU and Training BFD GD 15-1 / Supply and Strengthening Institutions, Installation of Laptop, Single Stage - One IDA / 63250 Information Systems and Post Request for Bids Open - National 459,821.00 351,326.79 Signed 2019-08-19 2019-08-19 2019-08-24 2019-09-14 2019-09-18 2019-10-26 2019-10-31 2019-11-30 2019-11-27 2020-02-28 Desktop Computer, Printer, Envelope Training UPS and Scanner for RIMS GD 16 / Supply and Strengthening Institutions, Installation of Plotter/Wide Single Stage - One IDA / 63250 Information Systems and Post Request for Bids Open - National 38,095.00 25,817.53 Signed 2019-08-19 2019-08-20 2019-08-24 2019-09-14 2019-09-18 2019-10-14 2019-11-03 2019-11-18 2019-11-27 2020-02-16 Format Printer for RIMS & S K Envelope Training Wild Life Center GD 18-2 / Supply and Strengthening Institutions, Installation of Printer, Single Stage - One IDA / 63250 Information Systems and Post Request for Bids Open - National 92,262.00 54,851.00 Signed 2019-09-08 2019-11-06 2019-09-13 2019-10-04 2019-11-25 2019-11-03 2019-12-26 2019-12-08 2020-01-26 2019-12-17 Scanner, LED screen etc for Envelope Training PMU, MOFFCC, FIU and BFD GD 19-2 / Supply and Strengthening Institutions, Single Stage - One Installation of Air Condition IDA / 63250 Information Systems and Post Request for Bids Open - National 101,131.00 14,810.45 Signed 2019-09-01 2020-06-10 2019-09-06 2019-09-27 2020-07-01 2019-10-27 2020-08-13 2019-12-01 2020-08-20 2020-02-29 Envelope for PMU, FIUs, MoEFCC Training GD -35 / Supply of Rescue Strengthening Collaborative Boat (Fiber) - In-Board-Diesel Single Stage - One IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 333,333.00 0.00 Canceled 2020-01-05 2020-01-10 2020-01-31 2020-03-01 2020-04-05 2020-07-04 Engine for four Coastal Envelope Management Division GD 15-2 / Supply and Installation of Server, Strengthening Institutions, Single Stage - One Networking, IF Modem, IF IDA / 63250 Information Systems and Post Request for Bids Open - National 72,143.00 0.00 Canceled 2020-01-05 2020-01-10 2020-01-31 2020-03-01 2020-04-05 2020-07-04 Envelope Router etc. and Related Training Accessories for RIMS GD 15-3 / Supply of GPS Strengthening Institutions, Regular, GPS Trimble Juno, Single Stage - One IDA / 63250 Information Systems and Post Request for Bids Open - National 393,452.00 235,692.29 Signed 2020-01-05 2020-02-24 2020-01-10 2020-01-31 2020-03-16 2020-03-01 2020-04-27 2020-04-05 2020-05-20 2020-07-04 Binocular and Cyber Tracker Envelope Training for RIMS and Wild Life Center Strengthening Collaborative GD 37 / Supply of Backpacks Single Stage - One IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 15,357.00 0.00 Canceled 2019-09-08 2019-09-13 2019-10-04 2019-11-03 2019-12-08 2020-03-07 for SSP and Survey Envelope Management GD 5-2 / Supply and Project Management, Request for Single Stage - One Installation of Refrigerator IDA / 63250 Post Limited 5,952.00 2,121.89 Signed 2020-02-14 2020-02-26 2020-03-19 2020-03-22 2020-04-18 Monitoring and Reporting Quotations Envelope and Water Purifier for PMU GD 7 / Supply and Installation of Interactive Flat Panel including Video Strengthening Institutions, Conferencing System , LED Single Stage - One IDA / 63250 Information Systems and Post Request for Bids Open - National 53,571.00 41,668.31 Signed 2020-04-29 2021-02-09 2020-05-04 2020-05-25 2021-02-25 2020-06-29 2021-04-24 2020-08-03 2021-05-04 2020-11-01 Monitor for making large Envelope Training screen video wall and Floor Stand Digital Signage (Kiosk) for PMU GD 15-4 / Supply of Smart Strengthening Institutions, Single Stage - One phone , Mobile phone and IDA / 63250 Information Systems and Post Request for Bids Open - National 80,833.00 0.00 Canceled 2020-05-18 2020-05-23 2020-06-13 2020-07-13 2020-08-17 2020-11-15 Envelope TABS for RIMS, MP, CF, DFO Training NON CONSULTING SERVICES Page 2 Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NS-1 / Study Tour (International): Best Practices of Sustainable Forest Management/Restoring Degraded Forest Ecosystems/ Forest Dependent Livelihoods Single Stage - One / Post Request for Bids Open - National 150,000.00 0.00 Canceled 2017-11-09 2017-11-14 2017-11-29 2017-12-21 2018-01-25 2018-06-30 (Example of Tentative Envelope Country: Equador/Mexico/South Korea/Combodia or The World Bank funded similar countries. NS-2 / Study Tour (International): Best Practices Single Stage - One / Post Request for Bids Open - National 180,000.00 0.00 Canceled 2017-11-09 2017-11-14 2017-11-29 2017-12-22 2018-01-19 2018-06-30 of Wildlife Management: Safari Envelope Park Management NS-10 / Hiring Charge: Rent- Project Management, Request for Single Stage - One IDA / V1280 Post Limited 6,000.00 13,780.60 Completed 2018-01-31 2018-02-22 2018-02-18 2018-03-14 2018-06-30 2019-01-31 a-car Monitoring and Reporting Quotations Envelope Strengthening Institutions, NS-5 / One Policy Dialogue IDA / V1280 Information Systems and Post Direct Selection Direct 15,000.00 14,197.49 Completed 2018-04-30 2018-04-11 2018-05-05 2018-04-11 2018-05-19 2018-04-17 2018-06-30 2018-04-18 Training NS-9 / Hiring Charge:Rent- a- Single Stage - One IDA / V1280 Post Request for Bids Limited 29,000.00 0.00 Canceled 2018-02-20 2018-02-25 2018-03-11 2018-03-18 2018-03-29 2018-06-30 car Envelope NS-11 / Hiring of Two Project Management, Request for Single Stage - One IDA / V1280 Post Limited 6,250.00 4,708.55 Terminated 2018-04-27 2018-04-30 2018-05-08 2018-05-06 2018-06-30 2018-06-30 Vehicle . Monitoring and Reporting Quotations Envelope NS-11A / Vehicle Rental Project Management, Request for Single Stage - One IDA / V1280 Post Limited 18,750.00 18,714.01 Completed 2018-09-04 2018-07-01 2018-09-18 2018-07-09 2019-01-31 2019-01-31 Service Monitoring and Reporting Quotations Envelope NS 6 / Non-Consulting Firm: Strengthening Collaborative Request for Single Stage - One For Taking 10 Surveyor for IDA / 63250 Forest and Protected Areas Post Limited 3,572.00 3,515.04 Completed 2019-01-06 2018-12-12 2019-01-13 2018-12-26 2019-01-31 2019-01-31 Quotations Envelope SSP. Management NS 2 / Non Consulting (Outsourcing) Firm for PMU Project Management, Single Stage - One (Training Coordinator, IDA / 63250 Post Request for Bids Open - National 173,833.00 0.00 Canceled 2019-01-31 2019-02-05 2019-03-19 2019-04-18 2019-05-23 2023-06-30 Monitoring and Reporting Envelope Accountant, IT Assistant, Office Assistant). NS6 / Non-Consulting Service for engaging 20 GIS Surveyors (30 Man Days each) for conducting GIS Based Strengthening Collaborative Survey for Site Specific Request for Single Stage - One IDA / 63250 Forest and Protected Areas Post Limited 19,286.00 19,080.23 Completed 2019-05-09 2019-05-07 2019-07-04 2019-05-19 2019-12-31 2019-06-19 Planning (using ODK platfrom) Quotations Envelope Management of 2018-2019 Nursery Raising for 2019-2020 Plantation (10,075 ha.) of different categories. NS 3 / Non Consulting Firm Project Management, Single Stage - One for vehicle (05 Car) rental IDA / 63250 Post Request for Bids Open - National 302,143.00 0.00 Canceled 2019-01-20 2019-01-25 2019-03-08 2019-04-07 2019-05-12 2023-06-30 Monitoring and Reporting Envelope service of PMU. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD7 / Service Procurement Consultant Project Management, From Firm-Consulting Firm IDA / V1280 Post Qualification Open - National 60,000.00 0.00 Canceled 2017-10-04 2017-12-07 2017-10-05 2017-10-19 2017-12-07 2017-10-26 2017-10-31 2018-02-28 Monitoring and Reporting for Project Feasibility Study . Selection SD8 / Service Procurement From Firm /Consulting Firm Consultant for Sustainable Livelihood / Post Qualification Open - National 56,250.00 0.00 Canceled 2017-10-04 2017-10-05 2017-10-19 2017-10-26 2017-10-31 2018-02-28 Framework Including Base Selection Line Survey of Forest Dependent . SD9 / Service Procurement From Engineering Firm/ Consulting Firm for Plan, Design, Cost Estimate etc. Consultant Preparation for Civil Works / Post Qualification Open - National 46,250.00 0.00 Canceled 2017-10-04 2017-10-05 2017-10-19 2017-10-26 2017-10-31 2018-02-28 under the DPP of SUFAL Selection Project: (a) Senior Architect Engineer-4MM (b) Civil Engineer - 4MM and others as needed SD10 / Short Training (Local): Procurement Management, Strengthening Institutions, Consultant Project Financial Management, IDA / V1280 Information Systems and Post Qualification Limited 31,250.00 23,420.26 Signed 2018-04-30 2018-05-15 2018-05-07 2018-05-17 2018-05-14 2018-05-29 2018-05-20 2018-06-24 2018-06-30 Project Monitoring and Training Selection Evaluation etc. SD-9 / Consulting Firm for Strengthening Institutions, Consultant Plan, Design, Cost Estimate IDA / V1280 Information Systems and Post Qualification Limited 46,250.00 40,426.15 Signed 2018-11-08 2018-01-09 2018-11-08 2018-01-09 2018-11-15 2018-01-25 2018-11-22 2018-01-25 2018-12-31 etc. for Civil Works under Training Selection SUFAL Project. SD-7 / Consulting Firm for Consultant Project Management, Project Feasibility Study of IDA / V1280 Post Qualification Limited 60,000.00 52,330.54 Signed 2018-11-08 2018-01-09 2018-11-08 2018-01-09 2018-11-15 2018-01-25 2018-11-22 2018-01-25 2018-12-31 Monitoring and Reporting SUFAL Project. Selection SD-8 / Consulting Firm for Sustainable Livelihood Consultant Project Management, Framework Including Base IDA / V1280 Post Qualification Limited 56,250.00 42,337.10 Signed 2018-11-08 2018-01-09 2018-11-08 2018-01-09 2018-11-15 2018-01-25 2018-11-22 2018-01-25 2018-12-31 Monitoring and Reporting Line Survey for SUFAL Project Selection of Forest Dependent. Page 3 Increasing Access to SD 14 / Consulting firm for Alternative Income Consultant Preparation of (i) Community IDA / V1280 Generating Activities (AIGAs), Post Qualification Limited 89,286.00 81,596.27 Signed 2018-11-29 2018-11-08 2018-11-29 2018-11-08 2018-12-13 2018-11-27 2018-12-18 2018-11-29 2019-01-31 Operations Manual and (ii) Forest Extension Services & Selection Innovation Grant Manual Trees outside Fores ts (TOF) SD13 / Workshop, Seminar, Conference & Policy Dialogue/National Workshops Consultant on 7th FYP/SDG/Sustainable IDA / V1280 Post Qualification Limited 98,700.00 0.00 Canceled 2018-04-30 2018-05-05 2018-05-10 2018-05-16 2018-06-30 Forest Management etc. Selection (Capacity Development) at National Level. SD-51 / Consulting Firm for : (a) Customized database of financial management, (b) for land management (c) for real Strengthening Institutions, time survey and monitoring Quality And Cost- IDA / 63250 Information Systems and Prior Open - National 726,190.00 0.00 Canceled 2019-02-25 2019-03-18 2019-05-01 2019-05-29 2019-06-28 2019-08-02 2019-09-06 2023-07-25 and (d) for Based Selection Training beneficiary/community/AIGAs database etc. and Purchage of: Arc GIS Software, Envy Software, e-Cognition Soft SD-57 / Consulting Firm Increasing Access to (NGO): Activity includes- Alternative Income Collaborative Forest Quality And Cost- IDA / 63250 Generating Activities (AIGAs), Prior Open - International 714,286.00 0.00 Canceled 2019-03-03 2019-03-24 2019-05-07 2019-06-04 2019-07-04 2019-08-08 2019-09-12 2023-06-30 Management group formation, Based Selection Forest Extension Services & data entry, training, etc. (For Trees outside Fores ts (TOF) Hill Area) SD11 / Short Training (Local): IT Application in Office Consultant Management- IDA / V1280 Post Qualification Limited 6,250.00 0.00 Canceled 2018-04-30 2018-05-07 2018-05-14 2018-05-20 2018-06-30 Presentation,Web Selection Management etc. SD-13 / Consulting Firm for Strengthening Collaborative Consultant Organizing Various Types of IDA / 63250 Forest and Protected Areas Post Qualification Limited 15,476.00 0.00 Canceled 2018-12-02 2018-12-02 2018-12-11 2018-12-17 2019-01-31 National Policy Dialogue /SDG Management Selection Workshops. SD-19 / Consulting Firm for Strengthening Institutions, Consultant Organizing SUFAL Project IDA / V1280 Information Systems and Post Qualification Limited 41,667.00 0.00 Canceled 2018-12-13 2018-12-13 2018-12-20 2019-01-01 2019-01-31 Inauguration Ceremony. Training Selection SD 33 / Selection of Increasing Access to Consulting Firm for Market Alternative Income study for wood chips, saw Quality And Cost- Under IDA / 63250 Generating Activities (AIGAs), Post Open - National 148,810.00 0.00 2019-10-07 2021-07-26 2019-10-28 2019-12-11 2020-01-22 2020-02-21 2020-03-27 2020-05-08 2021-05-08 dust and other wood products Based Selection Implementation Forest Extension Services & including furniture - (demand Trees outside Fores ts (TOF) and supply) SD 44 / Selection of Consulting Firm for Strengthening Collaborative Quality And Cost- Pending Implementation of PA IDA / 63250 Forest and Protected Areas Post Open - National 131,548.00 0.00 2019-09-10 2019-10-08 2019-11-26 2020-01-07 2020-02-06 2020-03-12 2020-04-23 2023-05-31 Based Selection Implementation Management Rules including Management Smart Patrolling SD 37 / Selection of Strengthening Institutions, Consulting Firm for Ecosystem Quality And Cost- Under IDA / 63250 Information Systems and Post Open - National 430,714.00 0.00 2019-12-22 2021-08-12 2020-01-12 2020-02-25 2020-04-07 2020-05-07 2020-06-11 2020-07-23 2021-07-23 Service Valuation 12mm (One Based Selection Implementation Training Expert International for 3 mm) SD32 / Third Party Monitoring By Conducting Baseline Survey, Independent Half-Yearly Process Monitoring, Mid Term Review Project Management, Quality And Cost- IDA / 63250 Prior Open - National 1,080,952.00 0.00 Canceled 2019-04-07 2019-04-28 2019-06-11 2019-07-09 2019-07-24 2019-08-07 2019-09-02 2023-09-01 and Final Impact Assessment Monitoring and Reporting Based Selection of Sustainable Forests and Livelihoods (SUFAL) Project activities under all the four components SD 56-A / Selection of NGO Increasing Access to for Collaborative Forest Alternative Income Quality And Cost- Management Group IDA / 63250 Generating Activities (AIGAs), Prior Open - International 1,066,667.00 723,308.62 Signed 2019-10-30 2020-01-29 2019-11-20 2020-02-05 2020-01-24 2020-12-15 2020-03-06 2021-02-07 2020-04-10 2021-03-31 2020-05-15 2021-06-14 2020-06-26 2021-06-30 2023-06-29 Based Selection formation, data entry, training Forest Extension Services & etc.(Hill Chattragram North & Trees outside Fores ts (TOF) South) SD-56 / Consulting Firm (NGO): Activity includes- Increasing Access to Baseline Survey, Collaborative Alternative Income Quality And Cost- Forest Management group IDA / 63250 Generating Activities (AIGAs), Prior Open - International 1,066,667.00 0.00 Canceled 2019-03-10 2019-03-31 2019-05-14 2019-06-11 2019-07-11 2019-08-15 2019-09-19 2023-07-07 Based Selection formation, data entry, Forest Extension Services & training, etc. (For Chattogram Trees outside Fores ts (TOF) Hill Forest Area) SD 57-B / Selection of NGO Increasing Access to for Collaborative Forest Alternative Income Quality And Cost- Management Group IDA / 63250 Generating Activities (AIGAs), Prior Open - International 1,066,667.00 432,161.39 Signed 2019-10-30 2020-01-29 2019-11-20 2020-02-05 2020-01-24 2020-12-15 2020-03-06 2021-02-07 2020-04-10 2021-03-31 2020-05-15 2021-06-15 2020-06-26 2021-06-30 2023-06-29 Based Selection formation, data entry, training Forest Extension Services & etc.(Hill Cox's Bazar North and Trees outside Fores ts (TOF) South) SD57A / Consulting Firm (NGO): Activity includes- Increasing Access to Baseline Survey, Collaborative Alternative Income Quality And Cost- Forest Management group IDA / 63250 Generating Activities (AIGAs), Prior Open - International 1,066,667.00 0.00 Canceled 2019-03-25 2019-04-15 2019-05-29 2019-06-26 2019-07-26 2019-08-30 2019-10-04 2023-07-22 Based Selection formation, data entry, Forest Extension Services & training, etc. (For Cox's Bazar Trees outside Fores ts (TOF) Hill Forest Area) SD 58-A / Selection of NGO Increasing Access to for Collaborative Forest Alternative Income Quality And Cost- Management Group IDA / 63250 Generating Activities (AIGAs), Prior Open - International 716,667.00 616,105.47 Under Review 2019-10-30 2020-01-29 2019-11-20 2020-02-05 2020-01-14 2020-09-21 2020-02-25 2020-11-12 2020-03-31 2021-01-06 2020-05-05 2021-04-17 2020-06-16 2021-05-23 2023-06-29 Based Selection formation, data entry, training Forest Extension Services & etc. (Hill Sylhet) Trees outside Fores ts (TOF) Page 4 SD-58 / Consulting Firm (NGO): Activity includes- Increasing Access to Baseline Survey, Collaborative Alternative Income Quality And Cost- Forest Management group IDA / 63250 Generating Activities (AIGAs), Prior Open - International 716,666.00 0.00 Canceled 2019-03-03 2019-03-24 2019-05-07 2019-06-04 2019-07-04 2019-08-08 2019-09-12 2023-06-30 Based Selection formation, data entry, Forest Extension Services & training, etc. (For Hill Area of Trees outside Fores ts (TOF) Sylhet Forest Division) SD 59-A / Selection of NGO Increasing Access to for Collaborative Forest Alternative Income Quality And Cost- Management Group IDA / 63250 Generating Activities (AIGAs), Prior Open - International 716,667.00 692,800.20 Signed 2019-10-30 2020-01-29 2019-11-20 2020-02-05 2020-01-24 2020-10-07 2020-03-06 2020-11-24 2020-04-10 2021-01-06 2020-05-15 2021-04-17 2020-06-26 2021-05-27 2023-06-29 Based Selection formation, data entry, training Forest Extension Services & etc. (Plain Land Dhaka and Trees outside Fores ts (TOF) Tangail) SD-59 / Consulting Firm (NGO): Activity includes- Increasing Access to Collaborative Forest Alternative Income Management group formation, Quality And Cost- IDA / 63250 Generating Activities (AIGAs), Prior Open - International 716,667.00 0.00 Canceled 2019-03-03 2019-03-24 2019-05-07 2019-06-04 2019-07-04 2019-08-08 2019-09-12 2023-06-30 data entry, training, etc.(For Based Selection Forest Extension Services & Plain land forest area of Trees outside Fores ts (TOF) Dhaka Forest Division and Tangail Forest Division) SD 60-A / Selection of NGO Increasing Access to for Collaborative Forest Alternative Income Quality And Cost- Management Group IDA / 63250 Generating Activities (AIGAs), Post Open - International 333,333.00 282,104.44 Signed 2019-10-30 2020-01-30 2019-11-20 2020-02-05 2020-01-24 2020-10-13 2020-03-06 2020-11-30 2020-04-10 2021-01-13 2020-05-15 2021-02-14 2020-06-26 2021-04-01 2023-06-29 Based Selection formation, data entry, training Forest Extension Services & etc. (Plain Land Mymensingh) Trees outside Fores ts (TOF) SD-60 / Consulting Firm (NGO): Activity includes- Increasing Access to Baseline Survey, Collaborative Alternative Income Forest Management group Quality And Cost- IDA / 63250 Generating Activities (AIGAs), Post Open - International 333,333.00 0.00 Canceled 2019-03-26 2019-04-16 2019-05-18 2019-06-08 2019-06-29 2019-07-21 2019-08-25 2023-08-04 formation, data entry, Based Selection Forest Extension Services & training, etc. (For Plain land Trees outside Fores ts (TOF) Sal forest area of Mymensingh Forest Division) SD-61 / Consulting Firm (NGO): Activity includes- Baseline Survey, Collaborative Increasing Access to Forest Management group Alternative Income Quality And Cost- formation, data entry, IDA / 63250 Generating Activities (AIGAs), Prior Open - International 516,667.00 0.00 Canceled 2019-03-03 2019-03-24 2019-05-07 2019-06-04 2019-07-04 2019-08-08 2019-09-12 2023-06-30 Based Selection training, etc. (For Coastal Forest Extension Services & forest of Patuakhali Coastal Trees outside Fores ts (TOF) Forest Division and Bhola Coastal Forest Division ) SD-62 / Consulting Firm (NGO): Activity includes- Baseline Survey, Collaborative Increasing Access to Forest Management group Alternative Income formation, data entry, Quality And Cost- IDA / 63250 Generating Activities (AIGAs), Prior Open - International 583,333.00 0.00 Canceled 2019-03-03 2019-03-24 2019-05-07 2019-06-04 2019-07-04 2019-08-08 2019-09-12 2023-06-30 training, etc. (For Coastal Based Selection Forest Extension Services & forest of Noakhali Coastal Trees outside Fores ts (TOF) Forest Division and Chattoram Coastal Forest Division covering Cox's Bazar)) SD 62-A / Selection of NGO Increasing Access to for Collaborative Forest Alternative Income Management Group Quality And Cost- IDA / 63250 Generating Activities (AIGAs), Prior Open - International 583,333.00 487,435.01 Signed 2019-11-05 2020-01-29 2019-11-26 2020-02-05 2020-01-30 2020-10-02 2020-03-12 2020-11-25 2020-04-16 2021-04-17 2020-05-21 2021-05-25 2020-07-02 2021-06-10 2023-06-29 formation, data entry, training Based Selection Forest Extension Services & etc. (Coastal Chattrogram and Trees outside Fores ts (TOF) Noakhali) SD 54 / Selection of Consulting firm for Wildlife Strengthening Institutions, Quality And Cost- Pending Olympiad for school & College IDA / 63250 Information Systems and Post Open - National 228,571.00 0.00 2019-11-14 2019-12-05 2020-02-08 2020-03-21 2020-04-25 2020-05-30 2020-07-11 2023-08-16 Based Selection Implementation level student throughout the Training country SD 61-A / Selection of NGO Increasing Access to for Collaborative Forest Alternative Income Quality And Cost- Management Group IDA / 63250 Generating Activities (AIGAs), Prior Open - International 516,667.00 277,461.83 Signed 2019-11-05 2020-01-29 2019-11-26 2020-02-05 2020-01-30 2020-09-21 2020-03-12 2020-11-12 2020-04-16 2020-12-07 2020-05-21 2021-06-07 2020-07-02 2021-06-30 2023-06-29 Based Selection formation, data entry, training Forest Extension Services & etc. (Coastal Bhola and Trees outside Fores ts (TOF) Patuakhali) SD 32-A / Selection of Consulting Firm for Project Management, Quality And Cost- IDA / 63250 Prior Open - International 604,762.00 0.00 Canceled 2020-02-02 2020-02-23 2020-04-07 2020-05-22 2020-06-21 2020-07-26 2020-09-06 2023-05-31 Independent Third Party Monitoring and Reporting Based Selection Monitoring SD 32-B / Selection of Consulting Firm for Baseline, Project Management, Quality And Cost- IDA / 63250 Post Open - National 476,190.00 0.00 Canceled 2020-02-02 2020-10-08 2020-03-01 2020-04-14 2020-05-12 2020-06-11 2020-07-16 2020-08-20 2023-05-31 Midterm and End of Project Monitoring and Reporting Based Selection Evaluation SD36 / Selection of Consulting Firm for Social Project Management, Quality And Cost- Under IDA / 63250 Post Open - National 95,300.00 0.00 2020-04-01 2021-07-26 2020-04-22 2020-06-05 2020-07-03 2020-08-02 2020-09-06 2020-10-11 2021-10-11 Satisfaction Survey - Baseline Monitoring and Reporting Based Selection Implementation and Endline survey SD 63-A / Selection of Strengthening Collaborative Consultant Consulting Firm for Site IDA / 63250 Forest and Protected Areas Post Qualification Open - National 297,620.00 294,828.75 Signed 2019-11-28 2019-12-03 2019-12-19 2020-01-05 2020-10-12 2020-01-19 2020-12-15 2020-02-19 2021-01-21 2020-08-17 Specific Plan (SSP) and ODK Management Selection Development SD 63 / Selection of Strengthening Collaborative consulting firm for Site Quality And Cost- IDA / 63250 Forest and Protected Areas Post Open - National 297,620.00 0.00 Canceled 2019-11-10 2019-12-01 2020-02-04 2020-03-17 2020-04-21 2020-05-26 2020-07-07 2021-01-03 Specific Plan (SSP) and ODK Based Selection Management interface Development SD 38 / Selection of Consulting Firm for Avifauna Strengthening Collaborative Consultant Conservation (a. Birds of Prey; IDA / 63250 Forest and Protected Areas Post Qualification Open - National 315,714.00 305,657.22 Signed 2019-12-22 2020-02-11 2020-01-26 2020-03-15 2020-09-27 2020-04-19 2021-01-05 2020-06-07 2021-02-11 2022-05-28 b. Asian Flyway of Migratory Management Selection Birds Survey; c. Bird census and Ringing etc.) SD-39 / Selection of Strengthening Collaborative Consultant Consulting Firm for Shark and IDA / 63250 Forest and Protected Areas Post Qualification Open - National 297,619.00 294,828.75 Signed 2019-12-31 2020-03-10 2020-01-28 2020-03-19 2020-08-27 2020-05-03 2020-11-26 2020-06-28 2021-01-13 2022-03-20 Rey Conservation Strategy- Management Selection NDF Completion Page 5 SD 46 / Selection of Strengthening Collaborative Consultant Consulting Firm for Vulture IDA / 63250 Forest and Protected Areas Post Qualification Open - National 178,571.00 163,495.82 Signed 2019-12-23 2020-09-24 2020-01-27 2020-03-16 2021-01-10 2020-04-20 2021-03-14 2020-06-08 2021-04-12 2023-05-24 Conservation Program Management Selection SD 47 / Selection of Strengthening Collaborative Consultant Consulting Firm for SB IDA / 63250 Forest and Protected Areas Post Qualification Open - National 59,524.00 0.00 Canceled 2019-12-30 2020-02-03 2020-03-23 2020-04-27 2020-06-15 2022-06-05 Sandpiper- Conservation Management Selection Program SD 40 / Selection of Consulting Firm for Elephant Strengthening Collaborative Consultant Conservation & Human Under IDA / 63250 Forest and Protected Areas Post Qualification Open - National 119,048.00 0.00 2019-12-19 2020-09-16 2020-01-23 2020-03-12 2020-04-16 2020-06-04 2021-05-30 Elephant Conflict Resolution Implementation Management Selection (including conservation activities) SD 35 / Selection of Consulting Firm for Strengthening Institutions, Communication & Outreach - Quality And Cost- IDA / 63250 Information Systems and Post Open - National 190,476.00 0.00 Canceled 2019-10-22 2019-11-12 2019-12-26 2020-02-06 2020-03-07 2020-04-11 2020-05-23 2021-05-23 (including Design & Based Selection Training Publication) - PA (Protected Area) & Wild Life SD 53 / Selection of Strengthening Institutions, Quality And Cost- Consulting firm for Audio- IDA / 63250 Information Systems and Post Open - National 238,095.00 0.00 Canceled 2019-11-14 2019-12-05 2020-02-08 2020-03-21 2020-04-25 2020-05-30 2020-07-11 2023-06-29 Based Selection video (Spot) Training SD 50 / Selection of Audit Project Management, Least Cost IDA / 63250 Post Open - National 273,810.00 0.00 Canceled 2019-09-19 2019-10-22 2019-10-10 2019-11-23 2019-12-29 2020-01-04 2020-02-03 2020-03-09 2020-04-20 2023-06-30 Firm for Internal Audit Monitoring and Reporting Selection SD 50A / Selection of Internal Project Management, Fixed Budget IDA / 63250 Post Open - National 273,810.00 239,179.92 Signed 2020-04-02 2020-03-20 2020-05-14 2020-07-09 2020-08-23 2020-08-27 2020-10-07 2020-10-08 2020-10-25 2020-11-26 2020-11-12 2021-01-14 2020-12-09 2023-06-30 Audit Firm for SUFAL Project Monitoring and Reporting Selection SD 34 / Selection of Consulting Firm for Communication & Outreach Strengthening Institutions, Quality And Cost- Activities for Collaborative IDA / 63250 Information Systems and Prior Open - National 571,428.00 482,647.38 Signed 2020-10-15 2020-09-21 2020-11-12 2020-10-26 2021-01-09 2021-02-09 2021-02-08 2021-04-13 2021-03-20 2021-06-07 2021-05-29 2021-08-01 2021-07-10 2021-08-25 2023-06-30 Based Selection Forest Management, Wildlife Training and Protected Area Management SD-32 / Selection of Project Management, Quality And Cost- Under Consulting Firm for Third IDA / 63250 Prior Open - International 604,762.00 0.00 2021-01-31 2021-03-11 2021-02-21 2021-04-05 2021-04-06 2021-06-20 2021-05-26 2021-08-05 2021-07-07 2021-08-18 2021-09-29 2023-06-30 Monitoring and Reporting Based Selection Implementation Party Monitoring(Plantation). SD 51A / Consulting Services Increasing Access to for Development of database Alternative Income for beneficiary/community Quality And Cost- Under IDA / 63250 Generating Activities (AIGAs), Post Open - National 297,619.00 0.00 2021-06-10 2021-08-10 2021-07-01 2021-08-07 2021-09-18 2021-10-18 2021-11-13 2021-12-25 2023-06-25 profiling and AIGAs, and real Based Selection Implementation Forest Extension Services & time survey and monitoring Trees outside Fores ts (TOF) for community tracking INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD1 / Procurement of Individual Project Management, Services for the position of IDA / V1280 Post Consultant Limited 50,000.00 28,641.34 Completed 2017-09-21 2017-11-20 2017-09-24 2017-11-21 2017-10-08 2017-12-27 2017-10-15 2017-12-27 2018-06-30 2018-06-30 Monitoring and Reporting Team Leader for the project Selection SD2 / Selection of Individual Individual Consultant : Procurement Project Management, IDA / V1280 Post Consultant Limited 33,750.00 31,459.15 Completed 2017-09-21 2018-02-19 2017-09-24 2018-02-19 2017-10-08 2018-03-11 2017-10-15 2018-03-14 2018-06-30 2019-01-31 Specialist ( Selection through Monitoring and Reporting Selection 3 CV) SD3 / Selection of Individual Consultant : Financial Individual Project Management, Management Specialist (FMS) : IDA / V1280 Post Consultant Limited 33,750.00 46,414.22 Completed 2017-09-21 2017-11-20 2017-09-24 2017-11-21 2017-10-08 2017-12-24 2017-10-15 2017-12-24 2018-06-30 2019-01-31 Monitoring and Reporting Selection through 3 CV Selection method SD4 / Selection of Individual Consultant : Financial Individual Project Management, Management Specialist -Junior IDA / V1280 Post Consultant Limited 10,000.00 19,307.31 Completed 2017-10-15 2017-11-20 2017-10-17 2017-11-21 2017-10-31 2017-12-24 2017-11-12 2017-12-24 2018-06-30 2019-01-31 Monitoring and Reporting Consultant - Selection Selection through 3 CV method SD5 / Selection of Individual Sustainable Forest Project Management, IDA / V1280 Post Consultant Limited 11,250.00 22,433.53 Completed 2017-09-21 2017-11-20 2017-09-24 2017-11-21 2017-10-08 2017-12-24 2017-10-15 2017-12-24 2018-05-13 2019-01-31 Management Planning Monitoring and Reporting Selection Specialist SD6 / Institutional Specialist Individual for Collaborative Management Project Management, IDA / V1280 Post Consultant Limited 14,062.50 14,320.67 Completed 2017-09-21 2017-11-20 2017-09-24 2017-11-21 2017-10-08 2017-12-24 2017-10-15 2017-12-24 2018-02-12 2018-04-30 and Organizational Monitoring and Reporting Selection Development Strengthening Institutions, SD12 / International Study IDA / V1280 Information Systems and Post Direct Selection Direct 19,700.00 18,790.04 Signed 2018-04-30 2018-05-07 2018-05-10 2018-05-07 2018-05-20 2018-06-24 2018-06-30 Tour Training SD-18 / Junior Consultant Project Management, IDA / V1280 Post Direct Selection Direct 5,250.00 704.85 Completed 2018-09-03 2018-08-27 2018-09-05 2018-08-27 2018-09-24 2018-10-09 2019-01-31 2019-01-31 (Accounts) Monitoring and Reporting SD-15 / Consultant for RIMS Strengthening Collaborative Individual to support the processing of IDA / V1280 Forest and Protected Areas Post Consultant Limited 11,250.00 14,248.09 Completed 2018-09-26 2018-08-27 2018-09-26 2018-08-27 2018-10-10 2018-09-19 2018-10-22 2018-10-09 2019-01-22 2019-01-31 incoming field data. Management Selection SD-16 / Junior Consultant for Strengthening Collaborative Individual RIMS to support the IDA / V1280 Forest and Protected Areas Post Consultant Limited 9,000.00 1,430.44 Completed 2018-09-26 2018-08-27 2018-09-26 2018-08-27 2018-10-10 2018-09-19 2018-10-22 2018-10-09 2019-01-31 2019-01-31 processing of incoming field Management Selection data. Strengthening Collaborative Individual SD-17 / Consultant for IDA / V1280 Forest and Protected Areas Post Consultant Limited 3,750.00 3,524.23 Completed 2018-09-26 2018-08-27 2018-09-26 2018-08-27 2018-10-10 2018-09-19 2018-10-15 2018-10-09 2018-11-15 2018-10-31 Safeguard Management Selection Page 6 Increasing Access to SD-14 / Consultant for Alternative Income Individual Community Operational and IDA / V1280 Generating Activities (AIGAs), Post Consultant Limited 11,250.00 0.00 Canceled 2018-09-26 2018-09-26 2018-10-08 2018-10-22 2019-01-22 Disbursement Manual Forest Extension Services & Selection Preparation Trees outside Fores ts (TOF) SD -7 / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 86,667.00 77,131.63 Signed 2018-12-09 2018-12-28 2019-01-04 2019-04-21 2019-01-10 2019-04-23 2019-02-01 2019-05-05 2023-06-30 Monitoring and Reporting Consultant (Accounts) (01) Selection SD -14 / Selection of Individual Individual Consultant: Project Management, IDA / 63250 Post Consultant Open 200,000.00 228,493.80 Signed 2018-12-09 2019-01-16 2019-01-04 2019-04-24 2019-01-10 2019-04-25 2019-02-01 2019-05-02 2022-12-31 Monitoring & Evaluation Monitoring and Reporting Selection Specialist SD -16 / Selection of Individual Individual Consultant: Project Management, IDA / 63250 Post Consultant Open 64,286.00 73,235.46 Signed 2018-12-09 2020-10-07 2019-01-04 2021-02-02 2019-01-10 2021-02-08 2019-02-01 2021-03-07 2020-07-31 Regulation & Organizational Monitoring and Reporting Selection Specialist SD-26 / Selection of Strengthening Collaborative Individual Individual Consultant: Senior IDA / 63250 Forest and Protected Areas Post Consultant Open 142,857.00 130,196.38 Signed 2018-12-09 2019-01-16 2019-01-04 2020-08-26 2019-01-10 2020-08-31 2019-02-01 2020-09-29 2021-01-31 Collaborative Forest Management Selection Management Specialist SD-28 / Selection of Strengthening Collaborative Individual Individual Consultant: Social IDA / 63250 Forest and Protected Areas Post Consultant Open 42,857.00 42,313.82 Signed 2018-12-09 2019-01-16 2019-01-04 2020-01-06 2019-01-10 2020-01-08 2019-02-01 2020-02-06 2020-01-31 Safeguard Specialist Management Selection SD-29 / Selection of Strengthening Collaborative Individual Individual Consultant: Gender IDA / 63250 Forest and Protected Areas Post Consultant Open 64,286.00 72,125.89 Signed 2018-12-09 2019-01-16 2019-01-04 2019-09-22 2019-01-10 2020-01-08 2019-02-01 2020-02-12 2020-07-31 Specialist Management Selection SD-1 / Selection of Individual Individual Project Management, Consultant: Project IDA / 63250 Prior Consultant Open 273,214.00 259,759.85 Signed 2019-01-01 2019-01-21 2019-01-27 2019-09-22 2019-02-02 2019-10-09 2019-02-27 2019-10-20 2023-06-30 Monitoring and Reporting Management Specialist/CTA Selection SD -8 / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 87,876.93 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-23 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD -9 / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 88,238.48 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-3 / Selection of Individual Individual Project Management, Consultant: Procurement IDA / 63250 Prior Consultant Open 250,715.00 0.00 Canceled 2019-01-01 2019-01-17 2019-01-27 2019-05-09 2019-02-02 2019-07-15 2019-02-24 2023-06-30 Monitoring and Reporting Specialist Selection SD-12 / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 80,000.00 90,231.72 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-24 2019-02-02 2019-04-25 2019-02-24 2019-05-21 2022-12-31 Monitoring and Reporting Procurement Specialist Selection SD -13 / Selection of Individual Individual Consultant: Senior Project Management, IDA / 63250 Prior Consultant Open 228,571.00 0.00 Canceled 2019-01-01 2019-01-28 2019-01-27 2019-02-02 2019-02-24 2023-01-31 Monitoring & Evaluation Monitoring and Reporting Selection Specialist SD-22 / Selection of Strengthening Collaborative Individual Individual Consultant: IDA / 63250 Forest and Protected Areas Post Consultant Open 96,429.00 61,029.55 Signed 2019-01-01 2019-01-16 2019-01-27 2020-09-28 2019-02-02 2020-10-04 2019-02-24 2020-11-01 2023-06-30 Community Mobilization Management Selection Officer SD-2 / Selection of Individual Individual Project Management, Consultant: Senior Financial IDA / 63250 Prior Consultant Open 285,714.00 271,842.53 Signed 2019-01-01 2019-03-21 2019-01-27 2019-04-30 2019-02-02 2019-05-14 2019-02-24 2019-05-16 2023-06-30 Monitoring and Reporting Management Specialist Selection SD-5 / Selection of Individual Individual Consultant: Consultant- Project Management, Under IDA / 63250 Post Consultant Open 128,572.00 120,717.20 2019-01-01 2018-12-28 2019-01-27 2019-03-19 2019-02-02 2019-03-24 2019-02-24 2019-04-28 2023-06-30 2020-02-16 Accounts and Financial Monitoring and Reporting Implementation Selection Management SD-6 / Selection of Individual Individual Project Management, Consultant:Program Co- IDA / 63250 Prior Consultant Open 233,333.00 0.00 Canceled 2019-01-01 2019-01-21 2019-01-27 2019-02-02 2019-02-24 2023-06-30 Monitoring and Reporting coordinator Selection SD-10 / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 49,769.69 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-28 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-5A / Selection of Individual Individual Consultant: Project Management, IDA / 63250 Post Consultant Open 128,572.00 134,873.41 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-07 2019-02-02 2019-04-09 2019-02-24 2019-05-15 2023-06-30 Consultant-Accounts and Monitoring and Reporting Selection Financial Management SD-5B / Selection of Individual Individual Consultant: Project Management, IDA / 63250 Post Consultant Open 128,572.00 136,374.94 Signed 2019-01-01 2018-12-28 2019-01-27 2019-03-19 2019-02-02 2019-03-24 2019-02-24 2019-04-28 2023-06-30 Consultant-Accounts and Monitoring and Reporting Selection Financial Management SD-8A / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 88,238.48 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-8B / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 0.00 Canceled 2019-01-01 2018-12-28 2019-01-27 2019-02-02 2019-02-24 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-8C / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 88,238.48 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-8D / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 87,033.97 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-26 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection Page 7 SD-8E / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 87,033.97 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-26 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-8F / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 87,610.64 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-16 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-9A / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 53,992.50 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-9B / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 87,724.79 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-14 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-9C / Selection of Individual Project Management, Individual Consultant through: IDA / 63250 Post Consultant Open 83,572.00 77,131.63 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2023-06-30 Monitoring and Reporting Junior Consultant (Accounts) Selection SD-9D / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 88,238.48 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-9E / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 87,838.94 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-12 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-9F / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 83,572.00 88,238.48 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2023-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10A / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 51,082.43 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10B / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 43,254.13 Signed 2019-01-01 2018-12-28 2019-01-27 2019-09-08 2019-02-02 2019-09-15 2019-02-24 2019-10-10 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10C / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 51,310.73 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-06-30 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10D / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 51,322.87 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-06-30 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10E / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 0.00 Canceled 2019-01-01 2018-12-28 2019-01-27 2019-02-02 2019-02-24 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10F / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 51,322.87 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-06-30 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10G / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 51,082.43 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10H / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 51,322.87 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-06-30 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10I / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 51,082.43 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10J / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 0.00 Canceled 2019-01-01 2018-12-28 2019-01-27 2019-02-02 2019-02-24 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10K / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 51,082.43 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10L / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 51,322.87 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-06-30 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10M / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 51,082.43 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-21 2019-02-02 2019-04-23 2019-02-24 2019-05-05 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-10N / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 46,429.00 51,189.55 Signed 2019-01-01 2018-12-28 2019-01-27 2019-05-09 2019-02-02 2019-05-13 2019-02-24 2019-06-30 2021-06-30 Monitoring and Reporting Consultant (Accounts) Selection SD-12A / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 80,000.00 87,650.16 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-24 2019-02-02 2019-04-25 2019-02-24 2019-06-30 2022-12-31 Monitoring and Reporting Procurement Specialist Selection SD-12B / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 80,000.00 90,539.04 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-30 2019-02-02 2019-05-02 2019-02-24 2019-05-16 2022-12-31 Monitoring and Reporting Procurement Specialist Selection SD-12C / Selection of Individual Project Management, Individual Consultant: Junior IDA / 63250 Post Consultant Open 80,000.00 90,108.78 Signed 2019-01-01 2018-12-28 2019-01-27 2019-04-24 2019-02-02 2019-04-25 2019-02-24 2019-05-23 2022-12-31 Monitoring and Reporting Procurement Specialist Selection SD-22A / Selection of Strengthening Collaborative Individual Individual Consultant: IDA / 63250 Forest and Protected Areas Post Consultant Open 96,429.00 53,095.71 Signed 2019-01-01 2019-01-16 2019-01-27 2020-09-28 2019-02-02 2020-10-04 2019-02-24 2020-11-01 2023-06-30 Community Mobilization Management Selection Officer Page 8 SD-22B / Selection of Strengthening Collaborative Individual Individual Consultant: IDA / 63250 Forest and Protected Areas Post Consultant Open 96,429.00 61,029.55 Signed 2019-01-01 2019-01-16 2019-01-27 2020-09-28 2019-02-02 2020-10-04 2019-02-24 2020-11-01 2023-06-30 Community Mobilization Management Selection Officer SD-22C / Selection of Strengthening Collaborative Individual Individual Consultant: IDA / 63250 Forest and Protected Areas Post Consultant Open 96,429.00 61,029.55 Signed 2019-01-01 2019-01-16 2019-01-27 2020-09-28 2019-02-02 2020-10-04 2019-02-24 2020-11-01 2023-06-30 Community Mobilization Management Selection Officer SD-22D / Selection of Strengthening Collaborative Individual Individual Consultant: IDA / 63250 Forest and Protected Areas Post Consultant Open 96,429.00 61,029.55 Signed 2019-01-01 2019-01-16 2019-01-27 2020-09-28 2019-02-02 2020-10-04 2019-02-24 2020-11-01 2023-06-30 Community Mobilization Management Selection Officer SD-22E / Selection of Strengthening Collaborative Individual Individual Consultant: IDA / 63250 Forest and Protected Areas Post Consultant Open 96,429.00 58,965.75 Signed 2019-01-01 2019-01-16 2019-01-27 2020-09-28 2019-02-02 2020-10-04 2019-02-24 2020-11-01 2023-06-30 Community Mobilization Management Selection Officer SD-22F / Selection of Strengthening Collaborative Individual Individual Consultant: IDA / 63250 Forest and Protected Areas Post Consultant Open 96,429.00 5,596.53 Signed 2019-01-01 2019-01-16 2019-01-27 2020-09-28 2019-02-02 2020-10-04 2019-02-24 2020-11-01 2023-06-30 Community Mobilization Management Selection Officer SD-4A / Selection of Individual Project Management, Individual Consultant: IDA / 63250 Post Consultant Open 195,000.00 191,088.23 Signed 2019-01-01 2019-01-02 2019-01-27 2019-03-19 2019-02-02 2019-03-24 2019-02-24 2019-06-30 2022-06-30 Monitoring and Reporting Procurement Specialist Selection SD-4B / Selection of Individual Project Management, Individual Consultant: IDA / 63250 Post Consultant Open 195,000.00 196,909.91 Signed 2019-01-01 2019-01-02 2019-01-27 2019-03-19 2019-02-02 2019-03-24 2019-02-24 2019-05-29 2022-06-30 Monitoring and Reporting Procurement Specialist Selection SD-4C / Selection of Individual Project Management, Individual Consultant: IDA / 63250 Post Consultant Open 139,286.00 137,152.03 Signed 2019-01-01 2019-01-02 2019-01-27 2019-03-19 2019-02-02 2019-03-24 2019-02-24 2019-05-06 2021-06-30 Monitoring and Reporting Procurement Specialist Selection SD-4E / Selection of Individual Project Management, Individual Consultant: IDA / 63250 Post Consultant Open 139,286.00 134,754.86 Signed 2019-01-01 2019-01-02 2019-01-27 2019-03-19 2019-02-02 2019-03-24 2019-02-24 2019-05-20 2021-06-30 Monitoring and Reporting Procurement Specialist Selection SD-4D / Selection of Individual Project Management, Individual Consultant: IDA / 63250 Post Consultant Open 139,286.00 137,152.03 Signed 2019-01-01 2019-01-02 2019-01-27 2019-03-19 2019-02-02 2019-03-24 2019-02-24 2019-05-06 2021-06-30 Monitoring and Reporting Procurement Specialist Selection SD-63 / Individual Individual Project Management, Consultant: Procurement IDA / 63250 Post Consultant Direct 13,929.00 0.00 Canceled 2019-01-10 2019-01-15 2019-01-20 2019-01-31 2019-04-30 Monitoring and Reporting Specialist Selection SD-64 / Individual Individual Project Management, Consultant: Financial IDA / 63250 Post Consultant Direct 13,929.00 0.00 Canceled 2019-01-10 2019-01-15 2019-01-20 2019-01-31 2019-04-30 Monitoring and Reporting Management Specialist Selection SD-65 / Individual Individual Project Management, Consultant: Junior Consultant- IDA / 63250 Post Consultant Direct 4,643.00 0.00 Canceled 2019-01-10 2019-01-15 2019-01-20 2019-01-31 2019-04-30 Monitoring and Reporting Accounts Selection SD-66 / Individual Individual Project Management, Consultant: Junior Consultant- IDA / 63250 Post Consultant Direct 4,643.00 0.00 Canceled 2019-01-10 2019-01-15 2019-01-20 2019-01-31 2019-04-30 Monitoring and Reporting Accounts Selection Strengthening Institutions, Individual SD 21 / Selection of Remote IDA / 63250 Information Systems and Post Consultant Open 72,857.00 0.00 Canceled 2020-09-16 2020-11-04 2020-11-25 2021-01-06 2023-01-06 Sensing & GIS Specialist Training Selection Strengthening Institutions, Individual SD-24 / Selection of Junior IT IDA / 63250 Information Systems and Post Consultant Open 18,571.00 14,463.81 Signed 2019-09-30 2019-10-21 2019-11-18 2020-08-31 2019-12-09 2020-08-31 2020-01-20 2020-09-30 2021-01-19 Networking Consultant Training Selection Strengthening Institutions, Individual SD-25 / Selection of Junior IDA / 63250 Information Systems and Post Consultant Open 18,571.00 18,083.00 Signed 2019-09-30 2019-10-08 2019-11-18 2020-10-01 2019-12-09 2020-10-04 2020-01-20 2020-10-11 2021-01-19 Consultant GIS Training Selection Increasing Access to Alternative Income Individual SUFAL/SD-11 / Selection of IDA / 63250 Generating Activities (AIGAs), Post Consultant Open 171,429.00 130,181.03 Signed 2019-09-16 2019-12-04 2019-11-04 2021-04-20 2019-11-25 2021-05-04 2019-12-30 2021-06-13 2022-12-29 Senior Livelihood Specialist Forest Extension Services & Selection Trees outside Fores ts (TOF) SD 27 / Selection of Strengthening Collaborative Individual Integrated Forest Management IDA / 63250 Forest and Protected Areas Post Consultant Open 42,857.00 0.00 Canceled 2019-09-15 2019-11-07 2019-11-10 2019-12-01 2020-01-12 2020-07-10 Planning Consultant (Aquatic Management Selection 3 Dolphin Sanctuary) SUFAL/SD-17 / Selection of Strengthening Institutions, Individual Sustainable Forest Financing IDA / 63250 Information Systems and Post Consultant Open 40,714.00 39,673.88 Signed 2019-09-30 2020-11-24 2019-11-18 2021-02-15 2019-12-09 2021-02-22 2020-01-13 2021-04-01 2020-10-09 Specialist Training Selection SD 27A / Selection of Strengthening Collaborative Individual Integrated Forest Management IDA / 63250 Forest and Protected Areas Post Consultant Open 42,857.00 0.00 Canceled 2019-09-22 2019-11-21 2019-11-10 2019-12-01 2020-01-05 2024-01-04 Planning Consultant Management Selection (Terrestrial Plain Land) Increasing Access to SUFAL/SD-18 / Selection of Alternative Income Individual Pending Community Development IDA / 63250 Generating Activities (AIGAs), Post Consultant Open 14,286.00 0.00 2019-10-01 2019-11-19 2019-12-10 2020-01-14 2020-04-13 Implementation Specialist Forest Extension Services & Selection Trees outside Fores ts (TOF) SD 27B / Selection of Strengthening Collaborative Individual Integrated Forest Management IDA / 63250 Forest and Protected Areas Post Consultant Open 42,857.00 0.00 Canceled 2019-09-29 2019-11-07 2019-11-17 2019-12-08 2020-01-12 2024-01-11 Planning Consultant (Hill) Management Selection Strengthening Institutions, Individual SUFAL/SD-19 / Selection of IDA / 63250 Information Systems and Post Consultant Open 109,286.00 88,474.73 Signed 2019-09-16 2019-11-11 2019-11-04 2020-07-20 2019-11-25 2020-07-22 2019-12-30 2020-08-20 2022-12-29 Database Expert Training Selection Page 9 Strengthening Institutions, Individual SD-20 / Selection of IDA / 63250 Information Systems and Post Consultant Open 130,536.00 103,780.85 Signed 2019-09-16 2019-11-11 2019-11-04 2020-08-05 2019-11-25 2020-08-06 2019-12-30 2020-08-20 2023-06-30 Maintenance Engineer (for IT) Training Selection SD 64-A / Selection of Junior Strengthening Collaborative Individual Consultant for Index Mapping IDA / 63250 Forest and Protected Areas Post Consultant Limited 7,500.00 6,795.54 Signed 2019-09-18 2019-11-21 2019-10-02 2020-06-21 2019-10-30 2020-09-10 2019-12-11 2020-09-17 2020-06-08 (GIS Surveyor) Management Selection SD 64-B / Selection of Junior Strengthening Collaborative Individual Consultant for Index Mapping IDA / 63250 Forest and Protected Areas Post Consultant Limited 7,500.00 6,795.54 Signed 2019-09-08 2019-10-21 2019-09-22 2020-06-21 2019-10-20 2020-09-10 2019-12-01 2020-09-17 2020-05-29 (GIS Surveyor) Management Selection SD 65 / Selection of Design, Individual Monitoring and Supervision Project Management, IDA / 63250 Post Consultant Limited 7,150.00 0.00 Canceled 2019-11-18 2019-11-25 2019-12-02 2019-12-16 2020-01-27 2020-10-23 Consultant for water transport Monitoring and Reporting Selection (Rescue boat) under SUFAL. Individual SD-12D / Junior Procurement Project Management, IDA / 63250 Post Consultant Direct 66,000.00 74,062.25 Terminated 2019-12-01 2019-12-05 2019-12-11 2020-01-06 2020-01-01 2020-01-08 2020-02-12 2020-02-04 2023-04-30 Specialist Monitoring and Reporting Selection SD 6 / Selection of Individual Individual Project Management, Consultant:Program Co- IDA / 63250 Post Consultant Open 233,333.00 215,880.45 Signed 2019-11-24 2018-12-24 2019-12-16 2019-09-08 2019-12-22 2019-09-15 2020-01-13 2019-11-03 2023-06-30 Monitoring and Reporting coordinator Selection Individual SD 12E / Selection of Junior Project Management, Under IDA / 63250 Post Consultant Open 40,000.00 45,568.73 2019-12-10 2019-12-31 2020-02-21 2020-09-27 2020-03-22 2020-09-29 2020-05-03 2022-05-03 Procurement Specialist Monitoring and Reporting Implementation Selection Individual SD 12F / Selection of Junior Project Management, Under IDA / 63250 Post Consultant Open 40,000.00 45,590.22 2019-12-10 2019-12-31 2020-02-21 2020-09-27 2020-03-22 2020-09-29 2020-05-03 2022-05-03 Procurement Specialist Monitoring and Reporting Implementation Selection Individual SD 12G / Selection of Junior Project Management, IDA / 63250 Post Consultant Open 40,000.00 45,579.47 Signed 2019-12-10 2019-12-31 2020-02-21 2020-09-27 2020-03-22 2020-09-29 2020-05-03 2020-10-12 2022-05-03 Procurement Specialist Monitoring and Reporting Selection SD 67 / Forestry Specialist for Strengthening Collaborative Individual Restoration Planning under IDA / 63250 Forest and Protected Areas Post Consultant Open 12,500.00 12,381.35 Signed 2019-12-22 2020-02-19 2020-03-11 2020-12-01 2020-04-10 2020-12-10 2020-05-22 2020-12-27 2020-08-20 PIP. Management Selection Strengthening Collaborative Individual SD 66 / selection of Forest IDA / 63250 Forest and Protected Areas Post Consultant Open 100,000.00 127,433.63 Signed 2020-04-16 2020-02-19 2020-07-05 2020-07-20 2020-08-04 2020-07-22 2020-09-15 2020-08-20 2022-09-05 Management Specialist for SSP Management Selection SD 15A / Selection of Senior Individual Project Management, Organizational Specialist for IDA / 63250 Post Consultant Open 71,429.00 79,745.28 Signed 2020-03-18 2020-10-07 2020-05-27 2021-02-02 2020-06-26 2021-02-08 2020-08-07 2021-03-07 2021-08-02 Monitoring and Reporting SUFAL PMU Selection SD -15 / Selection of Individual Project Management, Individual Consultant: Senior IDA / 63250 Post Consultant Open 71,429.00 0.00 Canceled 2018-12-09 2019-01-16 2019-01-04 2019-09-26 2019-01-10 2019-10-30 2019-02-01 2020-01-31 Monitoring and Reporting Organizational Specialist Selection Increasing Access to SD-11 / Selection of Alternative Income Individual Individual Consultant: Senior IDA / 63250 Generating Activities (AIGAs), Post Consultant Open 171,429.00 0.00 Canceled 2019-02-03 2019-03-01 2019-03-07 2019-03-29 2022-03-31 Livelihoods Specialist Forest Extension Services & Selection Trees outside Fores ts (TOF) SD 13 / Selection of Senior Individual Project Management, Monitoring & Evaluation IDA / 63250 Post Consultant Open 171,429.00 135,621.23 Signed 2020-03-30 2020-03-25 2020-06-15 2021-05-02 2020-07-27 2021-05-04 2020-08-31 2021-06-01 2023-06-21 Monitoring and Reporting Specialist Selection SD-5C / Consultant- Individual Project Management, Accounts and Financial IDA / 63250 Post Consultant Open 96,314.00 76,060.01 Signed 2020-04-06 2020-09-09 2020-07-27 2021-01-04 2020-08-17 2021-01-10 2020-09-28 2021-03-16 2023-07-21 Monitoring and Reporting Management Selection Individual SD 12H / Junior Procurement Project Management, IDA / 63250 Post Consultant Open 60,000.00 45,378.74 Signed 2020-04-08 2021-02-08 2020-07-22 2021-04-19 2020-08-21 2021-05-24 2020-10-16 2021-06-29 2023-05-31 Specialist Monitoring and Reporting Selection Individual SD 12I / Selection of Junior Project Management, IDA / 63250 Post Consultant Open 40,000.00 45,563.36 Signed 2021-01-14 2021-02-08 2021-03-14 2021-05-19 2021-04-04 2021-05-24 2021-05-09 2021-06-16 2023-05-09 Procurement Specialist Monitoring and Reporting Selection Individual SD 12J / Selection of Junior Project Management, IDA / 63250 Post Consultant Open 40,000.00 0.00 Canceled 2021-01-14 2021-02-08 2021-03-14 2021-04-04 2021-05-09 2023-05-09 Procurement Specialist Monitoring and Reporting Selection SD-10O / Selection of Individual Project Management, Under Individual Consultant: Junior IDA / 63250 Post Consultant Open 12,380.95 0.00 2021-01-31 2021-02-08 2021-03-28 2021-04-18 2021-05-04 2021-12-30 Monitoring and Reporting Implementation Consultant (Accounts) Selection SD-3A / Selection of Individual Project Management, Under Individual Consultant: IDA / 63250 Prior Consultant Open 112,125.00 0.00 2021-07-15 2021-07-26 2021-09-02 2021-09-07 2021-10-12 2023-06-30 Monitoring and Reporting Implementation Procurement Specialist Selection SD-4AA / Selection of Individual Project Management, Under Individual Consultant: IDA / 63250 Prior Consultant Open 64,071.00 0.00 2021-07-15 2021-07-27 2021-09-02 2021-09-07 2021-10-12 2022-10-07 Monitoring and Reporting Implementation Procurement Specialist Selection SD-10-1 / Selection of Individual Project Management, Pending Individual Consultant: Junior IDA / 63250 Post Consultant Direct 21,358.00 0.00 2021-09-29 2021-10-01 2021-10-02 2021-10-04 2022-10-04 Monitoring and Reporting Implementation Consultant (Accounts) Selection SD-10H-1 / Selection of Individual Project Management, Pending Individual Consultant: Junior IDA / 63250 Post Consultant Direct 21,358.00 0.00 2021-09-29 2021-10-01 2021-10-02 2021-10-04 2022-12-01 Monitoring and Reporting Implementation Consultant (Accounts) Selection SD-10L-1 / Selection of Individual Project Management, Pending Individual Consultant: Junior IDA / 63250 Post Consultant Direct 21,358.00 0.00 2021-09-29 2021-10-01 2021-10-02 2021-10-04 2022-12-01 Monitoring and Reporting Implementation Consultant (Accounts) Selection Individual SD-12K / Selection of Junior Project Management, Pending IDA / 63250 Post Consultant Open 35,000.00 0.00 2021-09-30 2021-11-06 2021-11-13 2021-12-04 2023-05-28 Procurement Specialist Monitoring and Reporting Implementation Selection Page 10