Procurement Plan Programme Régional d’infrastructure de communications de l’Afrique de l’Ouest– Projet du Burkina Faso (PRICAO-BF) Don IDA N°H 712-BF I. General 1. Bank’s approval Date of the procurement Plan: February 9, 2017 2. Date of General Procurement Notice: March 27, 2012 3. Period covered by this procurement plan: The procurement period of project covers the calendar year 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 2 million All 2. NCB (Goods) Above US$ 2 million All 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 10 million All 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Manuel des procédures administratives, financières et comptables du SP/PST version révisée d’avril 2016 5. Any Other Special Procurement Arrangements: Not applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Packages Review Ref. Descripti Estimat Dome by Bank Comme No. on ed stic (Prior / nts Cost Prefe Post) US$ rence million (yes/ no) Summary 4 1 No Prior of the ICB (Works) Summary 0 0 N/A N/A of the ICB (Goods) Summary 0 0 N/A N/A of the NCB (Works) Summary 0.5 1 No Post of the NCB (Goods) Summary 0 0 N/A N/A of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 1 million 2. Single Source (Firms) Above US$ 1 million 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Cost Assignmen US$ (Prior / t million Post) Summary 0 0 N/A of number of contracts that will be let under QCBS Summary 0.14 3 Post of number of contracts that will be let under other methods PROCUREMENT Western Africa : West Africa Regional Communications Infrastructure Project - APL-1B PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2017-05-11 2021-05-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P122402 GPN Date: 2017-04-17 Project Name: West Africa Regional Communications Infrastructure Project - APL-1B Loan / Credit No: IDA / H7120, IDA / 62220 D Executing Agency(ies): euxieme Programme Sectoriel des Transports et du Tourisme WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BF-PST2-12985-CW-DIR / Avenant aux travaux de construction d'une liaison sur Burkina Faso: Component 1- 2017-06- fibre optique entre IDA / H7120 Prior Direct Selection Direct 250,000.00 0.00 Canceled 2017-05-04 2017-05-22 2017-05-09 2017-06-22 Supporting Connectivity 22 Ouagadougou et Pô jusqu'à la frontière du Ghana + la bretelle Bagré Pôle BF-PST2-43925-CW-RFQ / Burkina Faso: Component 1- Request for Single Stage - One 2016-05- Travaux d'aménagement IDA / H7120 Post Limited 80,000.00 84,815.81 Completed 2015-10-18 2015-08-27 2016-02-15 2015-11-26 Supporting Connectivity Quotations Envelope 15 d'une salle Datacenter BF-PST2-43923-CW-RFB / Construction d’une liaison sur fibre optique entre Burkina Faso: Component 1- Single Stage - One 7,984,185.0 2017-02- IDA / H7120 Post Request for Bids Open - International 8,000,000.00 Signed 2016-01-20 2015-12-12 2016-02-04 2016-03-17 2016-01-26 2016-05-01 2016-02-08 2016-08-14 2016-08-29 Ouagadougou et Pô jusqu’à la Supporting Connectivity Envelope 0 10 frontière du Ghana + Bretelle Bagré Pôle BF-PST2-65237-CW-RFB / Pose de la fibre optique vers Burkina Faso: Component 1- Single Stage - One 2020-11- IDA / 62220 Post Request for Bids Open - International 6,320,000.00 0.00 Canceled 2019-06-19 2019-10-08 2019-11-22 2019-07-10 2019-12-22 2020-01-21 2020-04-05 la frontière avec le Bénin et Supporting Connectivity Envelope 01 pose de la fibre optique vers Zabré BF-PST2-171989-CW-RFB / Burkina Faso: Component 1- Single Stage - One 2021-01- Pose de la fibre optique IDA / 62220 Post Request for Bids Open - National 599,000.00 852,964.17 Signed 2020-07-20 2020-12-31 2020-08-04 2020-09-03 2021-02-08 2020-10-03 2021-02-17 2020-11-07 2021-04-13 Supporting Connectivity Envelope 21 Dindéogo - Zabré GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-12981-GO-RFB / Burkina Faso: Component 1- Single Stage - One Acquisition de la bande IDA / H7120 Prior Request for Bids Open - International 4,000,000.00 4,585,670.68 Signed 2016-10-03 2016-10-08 2016-12-12 2017-02-10 2017-05-17 2017-04-09 2018-02-21 2017-08-07 Supporting Connectivity Envelope passante internationale BF-PST2-12983-GO-RFB / Acquisition, installation et Burkina Faso: Component 1- Single Stage - One IDA / H7120 Post Request for Bids Open - National 500,000.00 450,056.37 Signed 2017-03-12 2017-07-06 2017-03-17 2017-04-28 2017-07-06 2017-05-13 2017-08-25 2017-06-26 2017-09-27 2017-09-24 configuration d’équipements Supporting Connectivity Envelope pour le PAV BF-PST2-65255-GO-RFB / Burkina Faso: Component 1- Single Stage - One Acquisition capacité bande IDA / 62220 Prior Request for Bids Open - International 6,000,000.00 4,351,200.00 Signed 2019-01-30 2019-08-30 2019-02-09 2019-09-13 2019-04-10 2019-10-25 2019-04-14 2020-01-14 2019-06-13 2020-06-23 2019-09-11 Supporting Connectivity Envelope passante internationale BF-PST2-66342-GO-RFB / Acquisition d'un modèle de Burkina Faso: Component 2- Single Stage - One comptabilité analytique pour IDA / 62220 Enabling Environment for Post Request for Bids Open - International 300,000.00 0.00 Canceled 2019-03-12 2019-04-01 2019-05-13 2019-06-12 2019-08-26 2019-11-24 Envelope la détermination des couts Connectivity des services BF-PST2-73104-GO-RFQ / Burkina Faso: Component 3- Matériels et consommables Request for Single Stage - One IDA / 62220 Project implementation and Post Limited 60,000.00 10,610.27 Completed 2019-01-11 2019-06-28 2019-03-03 2019-11-22 2019-06-01 2020-01-27 informatiques au profit du SP Quotations Envelope Contingency PST BF-PST2-87338-GO-RFB / Acquisition d'équipements, installation, configuration et Burkina Faso: Component 1- Single Stage - One IDA / 62220 Post Request for Bids Open - International 800,000.00 816,585.56 Signed 2019-04-16 2019-06-05 2019-05-06 2019-06-19 2019-06-17 2019-07-22 2019-07-17 2019-09-13 2019-09-04 2019-09-30 2019-12-03 formation pour la mise en Supporting Connectivity Envelope place du PAV, IXP de Bobo Dioulasso BF-PST2-87319-GO-RFB / Acquisition d'équipements Burkina Faso: Component 1- Single Stage - One IDA / 62220 Post Request for Bids Open - National 500,000.00 817,649.15 Signed 2019-09-05 2019-08-01 2019-09-10 2019-10-22 2019-10-04 2019-11-21 2019-09-13 2019-12-26 2019-09-30 2020-06-23 pour le renforcement du PAV, Supporting Connectivity Envelope IXP de Ouagadougou BF-PST2-114702-GO-RFQ / Acquisition d'équipements et Burkina Faso: Component 1- Request for Single Stage - One de systèmes pour le Centre IDA / 62220 Post Limited 80,000.00 0.00 Canceled 2019-07-15 2019-10-06 2020-01-04 Supporting Connectivity Quotations Envelope d'Opérations du Réseau (NOC) de FasoREN BF-PST2-114703-GO-RFQ / Acquisition et installation d'équipements d'énergie de Burkina Faso: Component 1- Request for Single Stage - One IDA / 62220 Post Limited 90,909.00 0.00 Canceled 2019-07-15 2019-10-06 2020-01-04 sécurité et d'environnement Supporting Connectivity Quotations Envelope technique pour le nœud de FasoREN BF-PST2-153093-GO-RFB / Acquisition, installation, configuration d’équipements pour le renforcement du point Burkina Faso: Component 1- Single Stage - One IDA / 62220 Post Request for Bids Open - National 500,000.00 536,609.35 Signed 2020-01-08 2019-08-01 2020-01-13 2020-02-12 2019-10-04 2020-02-17 2019-11-06 2020-03-03 2020-01-09 2020-06-01 d’atterrissement virtuel (PAV) Supporting Connectivity Envelope et le point d’échange internet (IXP) de Ouagadougou (Burkina Faso) Page 1 BF-PST2-159127-GO-RFQ / Burkina Faso: Component 3- MAtériels et consommables Request for Single Stage - One IDA / 62220 Project implementation and Post Limited 27,881.00 33,277.02 Terminated 2020-04-10 2020-09-16 2020-06-12 2020-11-30 2020-07-12 informatiques au profit du SP- Quotations Envelope Contingency PST 2020 BF-PST2-159243-GO-RFB / Acquisition, installation, configuration des Burkina Faso: Component 1- Single Stage - One IDA / 62220 Post Request for Bids Open - National 190,000.00 201,815.91 Signed 2020-03-16 2020-03-16 2020-03-21 2020-04-20 2020-04-23 2020-05-20 2020-05-08 2020-07-03 2020-09-07 2020-10-31 équipements pour une salle Supporting Connectivity Envelope NOC de type datacenter au profit de FasoREN BF-PST2-195447-GO-RFQ / Acquisition de Matériels Burkina Faso: Component 1- Request for Single Stage - One IDA / 62220 Post Limited 99,000.00 63,218.10 Completed 2020-10-10 2020-10-08 2020-12-17 2020-11-30 2021-01-16 2021-03-29 informatiques au profit de la Supporting Connectivity Quotations Envelope DGICE BF-PST2-212938-GO-RFB / Acquisition et la mise en Under Burkina Faso: Component 1- Single Stage - One service d’un outil de gestion IDA / 62220 Post Request for Bids Open - National 1,208,178.00 0.00 Implementati 2021-01-20 2021-02-05 2021-01-30 2021-02-12 2021-03-01 2021-03-11 2021-03-31 2021-06-29 Supporting Connectivity Envelope et d’optimisation de la bande on passante internet du RESINA BF-PST2-224179-GO-RFQ / Equipements et matériel Burkina Faso: Component 3- Under Request for Single Stage - One informatique au profit du SP IDA / 62220 Project implementation and Post Limited 53,903.00 45,829.25 Implementati 2021-03-22 2021-04-12 2021-04-18 2021-06-02 Quotations Envelope PST et de la cellule Contingency on environnementale du MDENP BF-PST2-231166-GO-RFQ / Pending Acquisition de matériel Burkina Faso: Component 1- Request for Single Stage - One IDA / 62220 Post Limited 37,174.00 0.00 Implementati 2021-06-07 2021-06-20 2021-07-20 informatique pour le compte Supporting Connectivity Quotations Envelope on du BUNEE NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-224166-NC-DIR / Mise à disposition de bande Burkina Faso: Component 1- IDA / 62220 Prior Direct Selection Direct 5,390,334.00 5,399,829.00 Signed 2021-03-12 2021-03-19 2021-03-22 2021-03-19 2021-03-30 2021-05-20 2021-04-29 passante internationale pour Supporting Connectivity l’administration publique BF-PST2-226435-CS-CQS / Pending Réalisation d'un film Burkina Faso: Component 1- Request for Single Stage - One IDA / 62220 Post Limited 18,587.00 0.00 Implementati 2021-05-08 2021-05-28 2021-06-17 documentaire sur les Supporting Connectivity Quotations Envelope on réalisations du PRICAO CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-79390-CS-QCBS / Etudes techniques pour la Burkina Faso: Component 1- Quality And Cost- réalisation de la liaison fibre IDA / 62220 Post Open - International 200,000.00 0.00 Canceled 2018-10-24 2018-11-27 2018-11-14 2018-11-27 2019-01-13 2019-02-25 2019-02-10 2019-03-12 2019-05-02 2019-07-11 2019-10-09 Supporting Connectivity Based Selection optique fada Pama frontière Benin BF-PST2-79400-CS-QCBS / Burkina Faso: Component 3- Assistance technique pour la Quality And Cost- IDA / 62220 Project implementation and Post Open - International 200,000.00 0.00 Canceled 2019-05-21 2019-06-25 2019-08-24 2019-09-21 2019-10-21 2019-12-25 2020-02-12 2020-08-10 conduite d'une étude sur la Based Selection Contingency fiscalité du secteur des TIC BF-PST2-79533-CS-QCBS / Réalisation des Avant-Projet Sommaire (APS) et Avant- Burkina Faso: Component 1- Quality And Cost- IDA / 62220 Post Open - International 100,000.00 0.00 Canceled 2018-10-23 2018-11-27 2018-11-13 2018-11-27 2019-01-12 2019-02-25 2019-02-09 2019-03-11 2019-04-21 2019-06-25 2019-08-24 Projet Détaillé (APD) de la Supporting Connectivity Based Selection liaison fibre optique Dindéogo Zabré BF-PST2-87380-CS-QCBS / Assistance technique à la mise Burkina Faso: Component 3- Quality And Cost- en place d'une structure PPP IDA / 62220 Project implementation and Post Open - International 363,636.00 0.00 Canceled 2018-12-27 2019-01-31 2019-04-01 2019-04-29 2019-05-29 2019-08-02 2019-09-15 2019-12-14 Based Selection pour l'exploitation des Contingency infrastructures nationales BF-PST2-114669-CS-QCBS / Réalisation des Avant-Projet Sommaire (APS) et Avant- Burkina Faso: Component 1- Quality And Cost- IDA / 62220 Post Open - International 54,545.00 41,518.48 Signed 2019-05-13 2018-06-25 2019-06-03 2019-08-02 2019-06-21 2019-08-30 2019-08-01 2019-09-29 2019-10-07 2019-11-09 2019-11-25 2020-01-13 2020-01-09 2020-03-13 Projet Détaillé (APD) de la Supporting Connectivity Based Selection liaison fibre optique Dindéogo - Zabré BF-PST2-114675-CS-QCBS / Etudes techniques pour la Burkina Faso: Component 1- Quality And Cost- réalisation de la liaison fibre IDA / 62220 Post Open - International 545,455.00 0.00 Canceled 2019-05-13 2019-05-28 2019-06-03 2019-08-02 2019-03-02 2019-08-30 2019-07-24 2019-09-29 2019-10-29 2019-11-19 2020-01-06 2020-01-28 2020-04-27 Supporting Connectivity Based Selection optique fada - Pama - frontière Benin BF-PST2-73092-CS-QCBS / Mise en place d'un Burkina Faso: Component 2- Quality And Cost- observatoire des IDA / 62220 Enabling Environment for Post Open - International 600,000.00 506,068.29 Signed 2019-07-31 2019-07-19 2019-08-30 2019-10-13 2019-11-11 2019-11-10 2020-01-23 2019-12-10 2020-02-05 2020-01-30 2020-03-31 2020-03-29 2020-09-15 2020-10-15 Based Selection infrastructures haut débit du Connectivity Burkina Faso BF-PST2-114706-CS-QCBS / Élaboration des règlements et des guides techniques pour Burkina Faso: Component 2- la mutualisation des travaux Quality And Cost- Under IDA / 62220 Enabling Environment for Post Open - International 454,545.00 0.00 2019-06-30 2019-11-29 2019-07-30 2019-12-19 2019-09-12 2020-04-08 2019-10-10 2019-11-09 2019-12-30 2020-03-13 2020-07-11 d'infrastructures publiques et Based Selection Implementation Connectivity les règles de partage d'infrastructures de communications électroniques Page 2 BF-PST2-114714-CS-CQS / Études techniques et estimation financière de la Consultant Burkina Faso: Component 1- construction du centre de IDA / 62220 Post Qualification Open - National 90,900.00 86,736.20 Signed 2019-06-20 2019-07-19 2019-07-11 2019-08-24 2019-09-26 2019-09-23 2019-12-24 2019-10-28 2020-12-08 2019-12-27 Supporting Connectivity gestion des infrastructures Selection numériques d'initiatives publiques BF-PST2-152821-CS-QCBS / Assistance technique pour Burkina Faso: Component 2- Quality And Cost- mettre en place le PPP pour la IDA / 62220 Enabling Environment for Post Open - International 500,000.00 516,479.77 Signed 2020-01-31 2020-02-26 2020-03-06 2020-04-20 2020-05-05 2020-06-26 2020-06-02 2020-09-16 2020-07-02 2020-10-08 2020-08-22 2020-11-16 2020-10-20 2020-12-29 2021-04-18 Based Selection gestion des infrastructures Connectivity nationale BF-PST2-73093-CS-QCBS / Assistance technique pour Burkina Faso: Component 2- Quality And Cost- mettre en place du PPP pour la IDA / 62220 Enabling Environment for Post Open - International 500,000.00 0.00 Canceled 2019-01-16 2019-02-20 2019-04-21 2019-05-19 2019-06-18 2019-08-08 2019-08-26 2020-02-22 Based Selection gestion des infrastructures Connectivity nationales BF-PST2-114712-CS-QCBS / Burkina Faso: Component 2- Quality And Cost- Suivi-contrôle de la liaison IDA / 62220 Enabling Environment for Post Open - International 545,455.00 0.00 Canceled 2019-12-16 2019-12-19 2020-01-15 2020-02-28 2020-03-27 2020-04-26 2020-06-16 2020-08-29 2021-04-26 Based Selection fibre optique Fada - Pama Connectivity BF-PST2-207505-CS-CQS / Recrutement du cabinet de l’atelier sur la communication Burkina Faso: Component 3- Consultant interne du personnel du IDA / 62220 Project implementation and Post Qualification Open - National 9,433.00 8,531.71 Signed 2020-12-03 2020-12-16 2020-12-05 2020-12-07 2020-12-07 2020-12-08 2020-12-17 2020-12-10 2020-12-21 2020-12-12 Secrétariat Permanent du Contingency Selection Programme Sectoriel des Transports (PS/PST) BF-PST2-212941-CS-CQS / Réaliser une étude de Consultant délimitation des zones Burkina Faso: Component 1- IDA / 62220 Post Qualification Open - International 278,810.00 0.00 Under Review 2021-01-20 2021-01-25 2021-01-30 2021-02-09 2021-02-10 2021-03-04 2021-06-02 d’intervention pour le Supporting Connectivity Selection déploiement des réseaux d’accès fibre optique (FTTx) BF-PST2-212944-CS-CQS / Élaborer la stratégie de Consultant développement des réseaux Burkina Faso: Component 1- IDA / 62220 Post Qualification Open - International 278,810.00 0.00 Under Review 2021-01-21 2021-01-29 2021-02-04 2021-02-16 2021-02-23 2021-03-12 2021-05-11 hauts débit mobiles en tirant Supporting Connectivity Selection profit des IMT 2020 au Burkina Faso BF-PST2-212946-CS-CQS / Réaliser une étude sur les Consultant Burkina Faso: Component 1- infrastructures d’accueil des IDA / 62220 Post Qualification Open - International 259,321.00 0.00 Under Review 2021-01-20 2021-01-25 2021-02-03 2021-02-17 2021-02-27 2021-03-25 2021-05-24 Supporting Connectivity réseaux haut débits fixes Selection résidentiels BF-PST2-212942-CS-CQS / Étude de faisabilité relative à la mise en place de la société Consultant Burkina Faso: Component 1- Under de gestion du patrimoine des IDA / 62220 Post Qualification Open - National 91,078.00 0.00 2021-02-01 2021-02-27 2021-02-15 2021-03-06 2021-03-21 2021-04-16 2021-06-15 Supporting Connectivity Implementation infrastructures de Selection communications électroniques de l’État INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PST2-12877-CS-INDV / Recrutement d’un consultant Individual pour l’actualisation du Cadre Burkina Faso: Component 1- IDA / H7120 Post Consultant Limited 23,840.00 21,817.18 Signed 2017-02-22 2017-02-22 2017-02-27 2017-03-21 2017-03-20 2017-04-07 2017-04-24 2017-05-26 2017-05-24 de Politique de Réinstallation Supporting Connectivity Selection des Populations du PRICAO- BF (CPRP) BF-PST2-12980-CS-INDV / Recrutement d’un consultant Individual pour l’actualisation du Cadre Burkina Faso: Component 1- IDA / H7120 Post Consultant Limited 26,300.00 24,068.45 Signed 2017-02-15 2017-02-22 2017-02-20 2017-02-21 2017-03-13 2017-03-15 2017-05-01 2017-03-29 2017-05-31 de Gestion Environnementale Supporting Connectivity Selection et Sociale (CGES) du PRICAO- BF BF-PST2-43515-CS-CDS / Contrôle et suivi de la construction d’une liaison sur Burkina Faso: Component 1- fibre optique entre IDA / H7120 Post Direct Selection Direct 62,000.00 663,576.01 Signed 2015-10-30 2012-09-26 2016-01-08 2016-01-18 2016-05-17 2016-08-08 2017-01-12 Supporting Connectivity Ouagadougou et Pô jusqu’à la frontière du Ghana + Bretelle Bagré Pôle BF-PST2-60353-CS-INDV / Individual Burkina Faso: Component 1- Audit environnemental et IDA / H7120 Post Consultant Limited 50,000.00 27,342.08 Signed 2018-04-23 2018-04-12 2018-04-30 2018-05-07 2018-05-14 2018-06-01 2018-06-08 2018-09-18 2018-07-23 Supporting Connectivity social du PRICAO Selection BF-PST2-73100-CS-INDV / Recrutement d'un consultant Burkina Faso: Component 3- Individual Individuel pour former les IDA / 62220 Project implementation and Post Consultant Limited 40,000.00 34,722.24 Completed 2018-11-12 2019-01-09 2018-12-02 2019-06-06 2018-12-23 2019-07-31 2019-02-21 2019-10-24 2019-03-07 2019-11-29 acteurs sur les procédures de Contingency Selection la Banque mondiale en matière de passation des marchés BF-PST2-62149-CS-CDS / Burkina Faso: Component 1- Elaboration d'avis juridique au IDA / H7120 Post Direct Selection Direct 24,000.00 0.00 Canceled 2018-05-21 2018-05-31 2018-06-30 2018-07-02 Supporting Connectivity profit du PRICAO BF-PST2-87339-CS-INDV / Étude et suivi contrôle de la Individual Burkina Faso: Component 1- mise à niveau de l'énergie et IDA / 62220 Post Consultant Limited 18,181.00 11,044.80 Signed 2018-11-28 2018-12-21 2018-12-13 2019-01-09 2019-01-03 2019-02-27 2019-02-12 2019-04-25 2019-05-13 Supporting Connectivity de la climatisation de la salle Selection datacenter à Ouaga 2000 BF-PST2-87341-CS-INDV / Individual Elaboration de Plan d'affaires Burkina Faso: Component 1- IDA / 62220 Post Consultant Limited 36,363.00 0.00 Under Review 2018-11-30 2019-10-16 2018-12-20 2019-01-10 2019-02-24 2019-05-25 pour le IXP (incluant celui de Supporting Connectivity Selection Bobo) Page 3 BF-PST2-87342-CS-INDV / Individual Elaboration d'un Plan Burkina Faso: Component 1- IDA / 62220 Post Consultant Limited 45,450.00 20,332.93 Signed 2018-11-29 2019-10-16 2018-12-19 2019-11-21 2019-01-18 2019-03-03 2020-06-08 2019-06-01 d'affaires pour le PAV Supporting Connectivity Selection (incluant celui de Bobo) BF-PST2-81344-CS-INDV / ÉLABORATION DU PLAN D'ACTIONS DE RÉINSTALLATION DES Burkina Faso: Component 2- Individual TRAVAUX DE CONSTRUCTION IDA / 62220 Enabling Environment for Post Consultant Limited 127,272.00 111,658.80 Signed 2019-05-30 2019-07-01 2019-06-19 2019-07-11 2019-07-10 2019-12-09 2019-08-14 2019-12-09 2019-11-12 DE LA LIAISON FIBRE OPTIQUE Connectivity Selection FADA - PAMA - KOUROU/KOUALA et DINDEOGO-ZABRE BF-PST2-114711-CS-INDV / Élaboration d'un Plan Burkina Faso: Component 2- Individual d'Affaires de FasoREN IDA / 62220 Enabling Environment for Post Consultant Limited 72,727.00 58,050.71 Signed 2019-08-30 2020-02-19 2019-09-19 2020-04-14 2019-10-10 2021-02-03 2019-11-23 2021-04-12 2020-01-22 (organisationnels, Connectivity Selection infrastructures, équipements et ressources humaines) BF-PST2-114717-CS-INDV / Notice d'impact environnemental et social des Burkina Faso: Component 2- Individual travaux de construction de la IDA / 62220 Enabling Environment for Post Consultant Limited 127,272.00 99,068.59 Signed 2019-05-30 2019-07-17 2019-06-19 2019-07-23 2019-07-10 2019-09-06 2019-08-23 2019-10-28 2019-11-21 liaison fibre optique FADA - Connectivity Selection PAMA - KOUROU/KOUALA et DINDEOGO-ZABRE BF-PST2-117849-CS-INDV / recrutement d'un Commissaire aux apports en Burkina Faso: Component 3- Individual vue de l'évaluation des biens IDA / 62220 Project implementation and Post Consultant Limited 80,000.00 32,349.97 Completed 2019-08-30 2019-07-15 2019-09-19 2019-08-06 2019-10-10 2019-08-27 2019-12-09 2019-10-28 2019-12-23 2020-01-22 en nature que l'Etat du Contingency Selection Burkina Faso doit apporter à la SCOOPS PAV Burkina BF-PST2-156903-CS-INDV / Burkina Faso: Component 3- Individual Recrutement d'un spécialiste IDA / 62220 Project implementation and Post Consultant Open 28,000.00 1,911.28 Signed 2020-04-15 2020-05-06 2020-06-03 2020-07-06 2020-06-24 2020-07-22 2020-07-29 2020-08-24 2020-08-01 en suivi-évaluation du FA- Contingency Selection PRICAO BF-PST2-171994-CS-INDV / Individual Burkina Faso: Component 1- Under Suivi-contrôle de la pose de la IDA / 62220 Post Consultant Limited 40,000.00 43,845.08 2020-06-01 2021-01-11 2020-06-06 2021-01-14 2020-06-27 2020-11-07 2021-01-21 Supporting Connectivity Implementation fibre optique Dindéogo-Zabré Selection BF-PST2-174175-CS-INDV / Individual Burkina Faso: Component 1- Recrutement d'un expert en IDA / 62220 Post Consultant Limited 37,000.00 33,214.40 Signed 2020-05-25 2020-05-18 2020-05-30 2020-06-19 2020-06-20 2020-07-29 2020-07-25 2020-08-24 2020-08-24 Supporting Connectivity sécurité Selection BF-PST2-212940-CS-INDV / Recrutement D’un Individual Commissaire Aux Burkina Faso: Component 1- IDA / 62220 Post Consultant Limited 37,175.00 35,841.21 Signed 2021-02-24 2021-01-13 2021-03-01 2021-03-12 2021-03-22 2021-04-09 2021-04-26 2021-05-12 2021-05-26 Apports Pour L’évaluation Des Supporting Connectivity Selection Équipements Du Pav Et De L’ixp De Bobo-Dioulasso BF-PST2-213294-CS-INDV / Burkina Faso: Component 3- Individual Recrutement d'un Assistant en IDA / 62220 Project implementation and Post Consultant Direct 7,800.00 4,658.46 Signed 2021-01-12 2021-01-12 2021-01-19 2021-01-05 2021-01-22 2021-01-11 2021-01-28 2021-01-22 2021-07-27 passation des marchés au Contingency Selection profit du FA-PRICAO BF-PST2-210038-CS-INDV / Burkina Faso: Component 3- Individual Recrutement d'un Assistant en IDA / 62220 Project implementation and Post Consultant Limited 7,924.00 0.00 Canceled 2020-12-21 2020-12-26 2021-01-02 2021-01-06 2021-05-06 passation des marchés au Contingency Selection profit du FA-PRICAO BF-PST2-224184-CS-INDV / Burkina Faso: Component 3- Individual Under Elaboration du Rapport IDA / 62220 Project implementation and Post Consultant Limited 74,349.00 0.00 2021-03-30 2021-03-23 2021-04-14 2021-05-05 2021-05-22 2021-06-21 Implementation d'achèvement du PRICAO Contingency Selection BF-PST2-224200-CS-INDV / Burkina Faso: Component 3- Individual Under Audit environnemental et IDA / 62220 Project implementation and Post Consultant Limited 37,174.00 0.00 2021-03-19 2021-04-26 2021-03-24 2021-04-14 2021-05-19 2021-06-18 Implementation social Contingency Selection BF-PST2-226052-CS-INDV / Enquête de satisfactions des Burkina Faso: Component 2- Individual bénéficiaires du Projet Pending IDA / 62220 Enabling Environment for Post Consultant Limited 74,349.00 0.00 2021-05-28 2021-05-30 2021-06-01 2021-06-13 2021-07-13 Régional d’Infrastructures de Implementation Connectivity Selection Communications en Afrique de l’Ouest (PRICAO) BF-PST2-224195-CS-INDV / Individual Burkina Faso: Component 1- Etude environnementale du IDA / 62220 Post Consultant Limited 46,468.00 0.00 Canceled 2021-03-17 2021-03-22 2021-04-12 2021-05-17 2021-06-16 Supporting Connectivity NOC Selection Page 4