Department of Water Supply & Sanitation, Punjab Website: www.pbdwss.gov.in 75470 v6 Procurement Report 2 Procurement Plan For Services Other than Consultancy Contract Status: All As on : 16-Nov-2012 Contract Contarct WBR incurred to date (in case of prior Estimated cost contract award Bids Preparation of Completion of bid Document review) (Date) review) (Date) Document (in Procurement case of prior Contract No. Package No. Expenditure Award signed No. (in objection to Plan/Actual Contractor Method of Banks no Banks no objection (RS lacs) Contract (In Lacs) Name of bidding decided (Date/Val case of Date of (Date) Opened on Sr. Description of Invitation Date ue/Curre prior (Date) (Date) No. Services ncy) review) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Zone: South Zone, Circle: Chandigarh Circle, District: SAS Nagar PRWSS/ Watch & Ward and SPMC/S SHOPPI 05-Apr- 05-May- 20-May- 05-06- 04-Jun- 1 ervices-1 P maintainance of 2.50 NG 2010 N/A 2010 2010 N/A 2010 N/A N/A N/A 2011 N/A Lawn Services M/s Enterclim PRWSS/ Watch & Ward and 05-JUN- ac SPMC/S SHOPPI 05-May- 20-May- 04-Jun- 2 ervices-1 A maintainence of 2.50 NG N/A 2010 2010 05-JUN-2010 N/A 2010/2.21/ Security 2011 0.16 Lawn Services INR Pvt. Ltd / 0 / Indian PRWSS/ Dedicated Leased SPMC/S Line of 1 Mbps with SHOPPI 20-Dec- 01-Jan- 17-Jan- 17-02- 22-Mar- 3 ervices-2 P minimum 2 static IP 0.70 NG 2010 N/A 2011 2011 N/A 2011 N/A N/A N/A 2011 N/A address M/s Airtel PRWSS/ I Mbps Dedicated 17-FEB- 1812 Bharti / 0 SPMC/S leased line with 8 SHOPPI 01-Jan- 18-Jan- 25-Jan- 22-Mar- 4 ervices-2 A static IPs from Airtel 7.50 NG 2011 N/A 2011 2011 17-FEB-2011 N/A 2011/0.70/ (SPMC / Indian 2011 7.00 INR Service ISP PRWSS/ SPMC/S Implementation of SHOPPI 20-Jan- 08-Feb- 10-Feb- 23-02- 11-Mar- 5 ervices-3 P Antivirus 0.51 NG 2011 N/A 2011 2011 N/A 2011 N/A N/A N/A 2011 N/A M/s H&H Technolo gies Pvt. Ltd SCO PRWSS/ Centralised No. 198- 23-FEB- 1980 SPMC/S Symantec Antivirus/ SHOPPI 01-Jan- 18-Jan- 25-Jan- 200 3rd 30-Jun- 6 ervices-3 A End Protection 5.10 NG 2011 N/A 2011 2011 23-FEB-2011 N/A 2011/0.51/ (SPMC/ Floor 2011 0.50 INR Service Sector 34A Chandiga rh / 0 / Indian Page 1 of 2 Procurement Plan For Services/ Non- 16/11/2012 Contract Contarct WBR incurred to date (in case of prior Estimated cost contract award Bids Preparation of Completion of bid Document review) (Date) review) (Date) Document (in Procurement case of prior Contract No. Package No. Expenditure Award signed No. (in objection to Plan/Actual Contractor Method of Banks no Banks no objection (RS lacs) Contract (In Lacs) Name of bidding decided (Date/Val case of Date of (Date) Opened on Sr. Description of Invitation Date ue/Curre prior (Date) (Date) No. Services ncy) review) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 PRWSS/ Implementation of SPMC/S SHOPPI 20-Jan- 01-Feb- 10-Feb- 23-02- 30-Apr- 7 ervices-4 P Various IT Service in 1.20 NG 2011 N/A 2011 2011 N/A 2011 N/A N/A N/A 2011 N/A Data Center Implementation of Microsoft Exchange Server*, M/s Implementation of Diakon backup software*, Tech PRWSS/ Microsoft Active 23-FEB- Solution SPMC/S SHOPPI 01-Jan- 18-Jan- 25-Jan- 31-Dec- 8 ervices-4 A directory 12.00 NG 2011 N/A 2011 2011 23-FEB-2011 N/A 2011/1.20/ & 2012 1.20 implementation, INR integrator implementation of s Pvt. Ltd virtualization, /0/ installation of Indian windows and linux operating system Electric cabling &allied works for PRWSS/ installation of 30 SPMC/S SHOPPI 01-Jan- 10-Jan- 10-Jan- 25-01- 14-Feb- 9 ervices-6 P KVA online UPS 2.55 NG 2011 N/A 2011 2011 N/A 2011 N/A N/A N/A 2011 N/A server in the Server room and other extension Electric cabling &allied works for Trackon PRWSS/ installation of 30 09-OCT- Courier SPMC/S SHOPPI 01-Jan- 14-Jan- 21-Jan- 09-OCT-2010 14-Feb- 10 ervices-6 A KVA online UPS 2.55 NG 2011 N/A 2011 2011 N/A 2010/2.10/ Pvt. Ltd. / 2011 2.54 server in the Server INR 0 / Indian room and other extension Selection of HR PRWSS- agency for S- 06-Nov- 16-Nov- 16-Dec- 01-01- 31-Dec- 11 SPMC- P outsoudring the 500.00 NCB 2012 15-11-2012 2012 2012 23-DEC-2012 15-11-2012 2013 N/A N/A N/A 2013 N/A recruitment of 2243 professionals Grand Total: 6 537.11 11.40 Page 2 of 2 Procurement Plan For Services/ Non- 16/11/2012