The World Bank                                                                                        Implementation Status & Results Report
         Punjab Skills Development (P130193)



Punjab Skills Development (P130193)


 SOUTH ASIA | Pakistan | Education Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2015 | Seq No: 11 | ARCHIVED on 10-Nov-2020 | ISR43977 |


 Implementing Agencies: Industries, Commerce & Investment Dep., Govt. of Punjab, Islamic Republic of Pakistan



 Key Dates


  Key Project Dates

   Bank Approval Date: 30-Apr-2015                                             Effectiveness Date: 03-Jul-2015
   Planned Mid Term Review Date: 02-Apr-2018                                   Actual Mid-Term Review Date: 14-May-2018
   Original Closing Date: 30-Jun-2020                                          Revised Closing Date: 31-Dec-2020
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The Project Development Objective (PDO) is to to improve the quality, labor market relevance of, and access to skills training programs in priority
  sectors in the Punjab.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Component One: Improving and Expanding Market-Relevant Skills Training:(Cost $46.00 M)
 Component Two: Project Management, M&E, and Technical Assistance:(Cost $4.00 M)

 Overall Ratings

 Name                                                                        Previous Rating                           Current Rating

 Progress towards achievement of PDO                                         Moderately Satisfactory                  Moderately Satisfactory
 Overall Implementation Progress (IP)                                        Moderately Satisfactory                  Moderately Satisfactory
 Overall Risk Rating                                                         Substantial                              Substantial


 Implementation Status and Key Decisions

  The project closing date was extended by 6 months from the original June 30, 2020 to December 31, 2020 to cope with the global spread of
  COVID-19 pandemic. Despite the disruptions due to the COVID-19, the mission observed a positive progress towards achieving its Project
  Development Objectives (PDO).
  PDO Indicator 1, percentage of graduates employed 6 months after completing training showed a stable trend over time, according to the recent
  tracer study of graduates. Cumulative employment rate as of December 2019 was 57.4% for all the cohorts. PDO Indicator 2, established and
  functioning testing quality standard, has been achieved by approval and notification of the new testing quality standards by three testing agencies.
  PDO Indicator 3, number of students passed out from market-relevant courses, reached 44,030 (of which 13,264 female), exceeding the target
  number of 40,000 (of which 7,200 female). Implementation progress is also steady, with two remaining DLI targets to be achieved.




11/10/2020                                                                                                                     Page 1 of 8
            The World Bank                                                                                            Implementation Status & Results Report
            Punjab Skills Development (P130193)




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                                   Rating at Approval                Previous Rating               Current Rating

  Political and Governance                                        --                                Moderate                     Moderate
  Macroeconomic                                                   --                                Substantial                  Substantial
  Sector Strategies and Policies                                  --                                Moderate                     Moderate
  Technical Design of Project or Program                          --                                Moderate                     Moderate
  Institutional Capacity for Implementation and
                                                                  --                                Substantial                  Substantial
  Sustainability
  Fiduciary                                                       --                                Substantial                  Substantial
  Environment and Social                                          --                                Low                          Low
  Stakeholders                                                    --                                Substantial                  Substantial
  Other                                                           --                                High                         High
  Overall                                                         --                                Substantial                  Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   Improve the quality of skills training

    IN00909071
    ►Established and functioning PSA (Text, Custom, PBC)

                                            Baseline                    Actual (Previous)             Actual (Current)            End Target
                                                                                                      Testing quality
                                                                        Testing quality standards
                                            PSA does not exist at the                                 standards approved         Testing quality
    Value                                                               approved by one testing
                                            moment                                                    and notified by all        standards established
                                                                        agency.
                                                                                                      testing agencies.
    Date                                    31-Dec-2014                 05-Mar-2020                   29-Oct-2020                30-Jun-2020



   Improve labor market relevance of skills training

    IN00909072
    ►Percentage of graduates employed 6 months after completing training in market-relevant courses (Text, Custom)

                                            Baseline                    Actual (Previous)             Actual (Current)            End Target
                                            Male: 42                    For all batches               For all batches             Male: 46
    Value
                                            Female: 28                  T: 41.7%                      T: 41.7%                    Female: 32


11/10/2020                                                                                                                           Page 2 of 8
           The World Bank                                                                                     Implementation Status & Results Report
           Punjab Skills Development (P130193)



                                                                   M: 43.0%                     M: 43.0%
                                                                   F: 36.0%                     F: 36.0%

                                                                   (As of Dec 2019)             (As of Dec 2019)
                                                                   T: 57.4                      T: 57.4
                                                                   M: 60.9                      M: 60.9
                                                                   F: 41.8                      F: 41.8


    Date                                31-Dec-2014                05-Mar-2020                  29-Oct-2020               31-Dec-2020



   Improve access to skills training

    IN00909073
    ►Number of students passed out from market-relevant courses (Number, Custom, PBC)

                                        Baseline                   Actual (Previous)            Actual (Current)           End Target

    Value                               0.00                       30,664.00                    44,030.00                  40,000.00

    Date                                31-Jul-2014                02-Jun-2019                  29-Oct-2020               30-Jun-2020

     IN00909074
     Male (Number, Custom Breakdown)

                                       Baseline                   Actual (Previous)            Actual (Current)           End Target

     Value                             0.00                      21,374.00                     30,766.00                  32,800.00

     Date                              31-Jul-2014               02-Jun-2019                   29-Oct-2020                31-Jan-2021

     IN00909075
     Female (Number, Custom Breakdown)

                                       Baseline                   Actual (Previous)            Actual (Current)           End Target

     Value                             0.00                      9,290.00                      13,264.00                  7,200.00

     Date                              31-Jul-2014               02-Jun-2019                   29-Oct-2020                31-Jan-2021


 Overall Comments PDO

  Final year data for all the PDO indicators have been reported, and these are expected to be final. Due to the timing of the survey, "Percentage
  of graduates employed 6 months after completing training in market-relevant courses" reports the graduate cohorts of 2019 and before. The
  study reported the overall placement rate was 57.4 percent for all the cohort as of December 2019. Other two PDO indicators also met and
  surpassed the targets.




 Intermediate Results Indicators by Components



   Component One: Improving and Expanding Market-Relevant Skills Training

    IN00909076
    ►P-TEVTA Institutional Development Plan Targets approved (Text, Custom)

                                        Baseline                   Actual (Previous)            Actual (Current)           End Target

11/10/2020                                                                                                                    Page 3 of 8
           The World Bank                                                                            Implementation Status & Results Report
           Punjab Skills Development (P130193)



                                                                                                                P-TEVTA Institutional
                                                                                       P-TEVTA IDP
    Value                            Plan does not exist      P-TEVTA IDP approved.                             Development Plan
                                                                                       approved.
                                                                                                                approved
    Date                             31-Dec-2014              05-Mar-2020              29-Oct-2020              31-Dec-2020

    IN00909077
    ►Number of CBTA curricula introduced (Text, Custom)

                                     Baseline                 Actual (Previous)        Actual (Current)          End Target

    Value                            0.00                     25.00                    25.00                     30.00

    Date                             31-Dec-2014              05-Mar-2020              29-Oct-2020              31-Dec-2020

    IN00909078
    ►Number of institutions offering CBTA courses (Number, Custom, PBC)

                                     Baseline                 Actual (Previous)        Actual (Current)          End Target

    Value                            0.00                     84.00                    84.00                     80.00

    Date                             31-Dec-2014              05-Mar-2020              29-Oct-2020              31-Dec-2020

    IN00909079
    ►Number of students passed-out from CBTA courses (Number, Custom)

                                     Baseline                 Actual (Previous)        Actual (Current)          End Target

    Value                            0.00                     2,317.00                 5,440.00                  6,800.00

    Date                             31-Dec-2014              05-Mar-2020              29-Oct-2020              31-Dec-2020

     IN00909080
     Male (Number, Custom Breakdown)

                                    Baseline                Actual (Previous)         Actual (Current)          End Target

     Value                          0.00                    2,164.00                  4,486.00                  6,300.00

     Date                           31-Jul-2014             05-Mar-2020               29-Oct-2020               30-Jun-2020

     IN00909081
     Female (Number, Custom Breakdown)

                                    Baseline                Actual (Previous)         Actual (Current)          End Target

     Value                          0.00                    153.00                    954.00                    500.00

     Date                           31-Jul-2014             05-Mar-2020               29-Oct-2020               30-Jun-2020

    IN00909082
    ►Number of industry Partnership Agreements signed (Number, Custom, PBC)

                                     Baseline                 Actual (Previous)        Actual (Current)          End Target

    Value                            0.00                     36.00                    52.00                     52.00

    Date                             31-Dec-2014              05-Mar-2020              29-Oct-2020              30-Jun-2020


11/10/2020                                                                                                          Page 4 of 8
           The World Bank                                                                                         Implementation Status & Results Report
           Punjab Skills Development (P130193)



    IN00909083
    ►Number of students benefited from industry partnership agreement (Number, Custom)

                                        Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                               0.00                         2,513.00                       2,639.00                   2,000.00

    Date                                31-Dec-2014                  05-Mar-2020                    29-Oct-2020                31-Dec-2020

    IN00909084
    ►Employment rate of students benefited from industry partnership agreement (after 6 months) (Percentage, Custom)

                                        Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                               0.00                         57.30                          71.80                      55.00

    Date                                31-Dec-2014                  05-Mar-2020                    29-Oct-2020                30-Jun-2020

    IN00909085
    ►Employer satisfaction with graduates from programs which benefitted from CBTA packages and Partnership Agreements (Yes/No, Custom)

                                        Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                               No                           Yes                            Yes                        Yes

    Date                                31-Dec-2014                  23-Aug-2019                    29-Oct-2020                31-Dec-2020

    IN00909086
    ►Number of students enrolled in market-relevant courses (Number, Custom)

                                        Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                               0.00                         54,818.00                      54,879.00                  51,000.00

    Date                                31-Dec-2014                  05-Mar-2020                    29-Oct-2020                30-Jun-2020


 Overall Comments IR

  As of October 2019, two IO indicators have not been achieved the final targets, which are: Number of CBTA curricula introduced and Number
  of students passed-out from CBTA courses. Number of CBTA curricula introduced is the DLI3 indicator, and the GoPb is prioritizing to achieve
  the final target 30 by commencing training in 5 more new CBTA programs. The number of students passed out from these courses may not be
  achieved by the time of project closing, provided that the current cohort is still in training, but the number of beneficiaries during the final year
  and the anticipated graduates could be updated during the ICR.




 Performance-Based Conditions




   IN00909087
    ►PBC 1 Established and functioning PSA (Text, Output, 4.00, 50.00%)


                                   Baseline                        Actual (Previous)             Actual (Current)               June 30, 2020


11/10/2020                                                                                                                        Page 5 of 8
           The World Bank                                                                                   Implementation Status & Results Report
           Punjab Skills Development (P130193)



                                                               Testing quality standards    Testing quality standards
                                 PSA does not exist at the
    Value                                                      prepared for                 approved and notified by     --
                                 moment
                                                               endorsement.                 all testing agencies.
    Date                         --                            05-Mar-2020                  29-Oct-2020                  --




   IN00909088
    ►PBC 2 Improving training provision by the public sector (Text, Output, 6.00, 33.33%)


                                 Baseline                      Actual (Previous)            Actual (Current)             June 30, 2020
                                                                                                                         2a. P-TEVTA Board
                                                                                                                         of Management has
                                                                                                                         approved its
                                                                                            2a. P-TEVTA Board of         institutional
                                                                                            Management has               development plan
                                                                                            approved its institutional   (IDP).
                                                                                            development plan (IDP).
                                                               Functional review has
    Value                        N/A                                                        2b. A new job placement      2b. A new job
                                                               been completed.
                                                                                            mechanism is approved        placement
                                                                                            and piloted in Project       mechanism is
                                                                                            supported P-TEVTA            approved and
                                                                                            institutes.                  piloted in Project
                                                                                                                         supported P-TEVTA
                                                                                                                         institutes.


    Date                         --                            30-Jun-2019                  29-Oct-2020                  --




   IN00909089
    ►PBC 3 Number of institutions offering CBTA courses (Number, Intermediate Outcome, 10.00, 60.00%)


                                 Baseline                      Actual (Previous)            Actual (Current)             June 30, 2020

    Value                        0.00                          84.00                        84.00                        --

    Date                         --                            05-Mar-2020                  29-Oct-2020                  --




   IN00909090
    ►PBC 4 Number of industry Partnership Agreements signed (Number, Intermediate Outcome, 12.00, 50.00%)


                                 Baseline                      Actual (Previous)            Actual (Current)             June 30, 2020

    Value                        0.00                          36.00                        52.00                        --

    Date                         --                            05-Mar-2020                  29-Oct-2020                  --




11/10/2020                                                                                                                    Page 6 of 8
           The World Bank                                                                                      Implementation Status & Results Report
           Punjab Skills Development (P130193)



   IN00909091
    ►PBC 5 Number of students passed out from market-relevant courses (Number, Outcome, 14.00, 42.86%)


                                 Baseline                        Actual (Previous)             Actual (Current)              June 30, 2020

    Value                        0.00                            0.00                          44,030.00                     --

    Date                         --                              30-Jun-2019                   29-Oct-2020                   --



 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF    Status       Currency        Original   Revised       Cancelled     Disbursed       Undisbursed                % Disbursed


 P130193       IDA-56300         Effective    USD               50.00      50.00             0.00          38.04           12.42                       75%


 Key Dates (by loan)

 Project        Loan/Credit/TF    Status      Approval Date       Signing Date       Effectiveness Date      Orig. Closing Date      Rev. Closing Date

 P130193        IDA-56300         Effective   30-Apr-2015         04-Jun-2015        03-Jul-2015             30-Jun-2020             31-Dec-2020


Cumulative Disbursements




11/10/2020                                                                                                                        Page 7 of 8
          The World Bank                                                                           Implementation Status & Results Report
          Punjab Skills Development (P130193)



 PBC Disbursement

                                                                                  Achievement   Disbursed amount in     Disbursement %
 PBC ID                   PBC Type    Description         Coc        PBC Amount
                                                                                  Status        Coc                     for PBC




  Restructuring History


  Level 2 Approved on 12-Jul-2019 ,Level 2 Approved on 26-Jun-2020


  Related Project(s)


 There are no related projects.




11/10/2020                                                                                                        Page 8 of 8