64732 v2 Restructuring Status: Archived Restructuring Type: Level two Last modified on date : 10/06/2011 1. Basic Information Project ID & Name P095114: Rampur Hydropower Project Country India Task Team Leader Rohit Mittal Sector Manager/Director Jyoti Shukla Country Director N. Roberto Zagha Original Board Approval Date 09/13/2007 Original Closing Date: 03/31/2013 Current Closing Date 03/31/2013 Proposed Closing Date [if applicable] 12/31/2014 EA Category A-Full Assessment Revised EA Category A-Full Assessment-Full Assessment EA Completion Date 10/17/2006 Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 270.00 297.00 IBRD 400.00 400.00 Total 670.00 697.00 3. Borrower Organization Department Location SJVN Limited India 4. Implementing Agency Organization Department Location SJVN Limited India ii 5. Disbursement Estimates (US$m) Actual amount disbursed as of 10/14/2011 210.20 Fiscal Year Annual Cumulative 2012 59.80 270.00 2013 70.00 340.00 2014 52.50 392.50 2015 7.50 400.00 Total 400.00 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select N from the checklist below and update ISDS accordingly before submitting the package. 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes The development objective of the project is (a) to improve the reliability of India's Northern Electricity Grid through the addition of renewable, low carbon energy from the Rampur hydropower project; and (b) to improve the effectiveness of Satluj Jal Vidyut Nigam Limited (SJVN) with respect to the preparation and safe implementation of economically, environmentally, and socially sustainable hydropower projects. 7b. Revised Project Development Objectives/Outcomes [if applicable] iii