Public Disclosure Copy The World Bank Implementation Status & Results Report Hwange-Sanyati Biological Corridor Project (P124625) Hwange-Sanyati Biological Corridor Project (P124625) AFRICA | Zimbabwe | Environment & Natural Resources Global Practice | Global Environment Project | Investment Project Financing | FY 2014 | Seq No: 7 | ARCHIVED on 29-Dec-2017 | ISR30670 | Implementing Agencies: Government of Zimbabwe, World Wide Fund for Nature Key Dates Key Project Dates Bank Approval Date:16-May-2014 Effectiveness Date:22-Jan-2015 Planned Mid Term Review Date:22-Jan-2018 Actual Mid-Term Review Date:-- Original Closing Date:30-Jun-2019 Revised Closing Date:30-Jun-2019 Global Development Objectives Global Environmental Objective (from Project Appraisal Document) To develop land use and resource management capacity of managers and communities in the Hwange-Sanyati Biological Corridor (HSBC). Has the Global Environmental Objective been changed since Board Approval of the Project Objective? No Components Name Protected area management and community livelihoods:(Cost $1.80 M) Land and forest management:(Cost $3.24 M) Corridor sustainability:(Cost $0.33 M) Project coordination:(Cost $0.27 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  Substantial  Substantial Implementation Status and Key Decisions 12/29/2017 Public Disclosure Copy Page 1 of 7 Public Disclosure Copy The World Bank Implementation Status & Results Report Hwange-Sanyati Biological Corridor Project (P124625) Overall project implementation and activities under the project are progressing well, disbursements are essentially on track, and progress toward achievement of the PDO is considered satisfactory. A comprehensive mid-term review of the project, between the Government, WWF, and the World Bank, will be carried out in January 2018. This will consider the accomplishments of the project at its mid-way point and whether or not any changes will be needed to achieve the project objectives. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  Moderate  Moderate Macroeconomic  --  Moderate  Moderate Sector Strategies and Policies  --  Moderate  Moderate Technical Design of Project or Program  --  Low  Low Institutional Capacity for Implementation and  --  Substantial  Substantial 12/29/2017 Public Disclosure Copy Page 2 of 7 Public Disclosure Copy The World Bank Implementation Status & Results Report Hwange-Sanyati Biological Corridor Project (P124625) Sustainability Fiduciary  --  Low  Low Environment and Social  --  Low  Moderate Stakeholders  --  Moderate  Moderate Other  --  --  -- Overall  --  Substantial  Substantial Results Global Environmental Objective Indicators PHINDGEOTBL  Improved management of Hwange National Park(Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 51.00 -- -- 68.00 Date 15-Jan-2014 -- -- 30-Jun-2019 PHINDGEOTBL  Stable carbon sequestration in project forest reserves.(Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 0.00 Date 01-Jul-2014 -- -- 30-Jun-2019 PHINDGEOTBL  Land area under sustainable landscape management practices(Hectare(Ha), Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 500.00 Date 01-Jul-2014 -- -- 30-Jun-2019 12/29/2017 Public Disclosure Copy Page 3 of 7 Public Disclosure Copy The World Bank Implementation Status & Results Report Hwange-Sanyati Biological Corridor Project (P124625) PHINDGEOTBL  Direct project beneficiaries(Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 20,000.00 Date 01-Jul-2014 -- -- 30-Jun-2019 PHINDGEOTBL  Female beneficiaries(Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 50.00 Overall Comments No new information on indicators is entered in this ISR as no progress report has been received since the last ISR. A full set of new data will be entered in the February 2018 ISR, following the mid-term review mission. Intermediate Results Indicators PHINDIRITBL  Areas brought under enhanced biodiversity protection (ha) (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 0.00 Date 01-Jul-2014 -- -- 30-Jun-2019 12/29/2017 Public Disclosure Copy Page 4 of 7 Public Disclosure Copy The World Bank Implementation Status & Results Report Hwange-Sanyati Biological Corridor Project (P124625) PHINDIRITBL  Reduced poaching incidents (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 858.00 -- -- 400.00 Date 01-Jul-2014 -- -- 30-Jun-2019 PHINDIRITBL  New areas outside protected areas managed as biodiversity-friendly (ha) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 10,000.00 Date 01-Jul-2014 -- -- 30-Jun-2019 PHINDIRITBL  Reduced human-wildlife conflict (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 100.00 -- -- 30.00 Date 01-Jul-2014 -- -- 30-Jun-2019 PHINDIRITBL  Forest area brought under management plans (Hectare(Ha), Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 157,300.00 Date 01-Jul-2014 -- -- 30-Jun-2019 12/29/2017 Public Disclosure Copy Page 5 of 7 Public Disclosure Copy The World Bank Implementation Status & Results Report Hwange-Sanyati Biological Corridor Project (P124625) PHINDIRITBL  Capacity building of beneficiaries (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 80.00 Date 01-Jul-2014 -- -- 30-Jun-2019 Overall Comments No new information on indicators is entered in this ISR as no progress report has been received since the last ISR. A full set of new data will be entered in the February 2018 ISR, following the mid-term review mission. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P124625 TF-17713 Effective USD 5.65 5.65 0.00 3.55 2.10 63% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P124625 TF-17713 Effective 24-Jul-2014 24-Jul-2014 22-Jan-2015 30-Jun-2019 30-Jun-2019 Cumulative Disbursements 12/29/2017 Public Disclosure Copy Page 6 of 7 Public Disclosure Copy The World Bank Implementation Status & Results Report Hwange-Sanyati Biological Corridor Project (P124625) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/29/2017 Public Disclosure Copy Page 7 of 7