The World Bank Implementation Status & Results Report Guizhou Tongren Rural Transport Project (P148071) Guizhou Tongren Rural Transport Project (P148071) EAST ASIA AND PACIFIC | China | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 7 | ARCHIVED on 07-Dec-2018 | ISR34700 | Implementing Agencies: People's Republic of China, Tongren World Bank Project Management Office, Tongren Transport Bureau Key Dates Key Project Dates Bank Approval Date: 25-Sep-2015 Effectiveness Date: 27-Jan-2016 Planned Mid Term Review Date: 01-Sep-2018 Actual Mid-Term Review Date: 25-Oct-2018 Original Closing Date: 30-Jun-2021 Revised Closing Date: 30-Jun-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to improve rural transport connectivity in Dejiang and Sinan counties. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name A. Dejiang Rural Transport:(Cost $150.02 M) B. Sinan Rural Transport:(Cost $80.77 M) C. Technical Assistance:(Cost $1.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions Progress on road works in both Dejiang and Sinan counties continues to proceed ahead of schedule. As a result, the PDO is on track to be fully achieved. 12/7/2018 Page 1 of 5 The World Bank Implementation Status & Results Report Guizhou Tongren Rural Transport Project (P148071) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Low Low Macroeconomic -- Low Moderate Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and Sustainability -- Substantial Substantial Fiduciary -- Moderate Moderate Environment and Social -- Substantial Moderate Stakeholders -- Moderate Moderate Other -- -- -- Overall -- Moderate Moderate Results PDO Indicators by Objectives / Outcomes Improve rural transport connectivity in Dejiang and Sinan Counties. IN00597594 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 9,388.00 143,916.00 262,000.00 12/7/2018 Page 2 of 5 The World Bank Implementation Status & Results Report Guizhou Tongren Rural Transport Project (P148071) Date 01-Apr-2015 13-Apr-2018 25-Oct-2018 30-Jun-2021 IN00597647 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 35.00 56.00 48.00 IN00597641 ►Travel Time Savings on Upgraded / Improved Roads (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 01-Apr-2015 13-Apr-2018 25-Oct-2018 30-Jun-2021 Intermediate Results Indicators by Components A and B. Dejiang and Sinan Rural Transport IN00597595 ►Roads rehabilitated, Rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 115.75 312.75 646.00 Date 01-Apr-2015 13-Apr-2018 25-Oct-2018 30-Jun-2021 IN00597642 ►Number of Bridges Improved / Constructed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 5.00 7.00 30.00 Date 01-Apr-2015 13-Apr-2018 25-Oct-2018 30-Jun-2021 IN00597643 ►Number of Villages with New Road Safety Measures (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 32.00 103.00 147.00 Date 01-Apr-2015 13-Apr-2018 25-Oct-2018 30-Jun-2021 IN00597646 ►Direct Project Consultations with Beneficiaries Undertaken (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Yes Yes Yes Yes Date 01-Apr-2015 13-Apr-2018 25-Oct-2018 30-Jun-2021 12/7/2018 Page 3 of 5 The World Bank Implementation Status & Results Report Guizhou Tongren Rural Transport Project (P148071) C. Technical Assistance IN00597645 ►Technical Assistance: Studies and Plans Completed (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 01-Apr-2015 13-Apr-2018 25-Oct-2018 30-Jun-2021 IN00597644 ►Number of Trainees who Attended Training and Study Tours (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 226.00 344.00 300.00 Date 01-Apr-2015 13-Apr-2018 25-Oct-2018 30-Jun-2021 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P148071 IBRD-85340 Effective USD 150.00 150.00 0.00 83.96 66.04 56% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P148071 IBRD-85340 Effective 25-Sep-2015 29-Oct-2015 27-Jan-2016 30-Jun-2021 30-Jun-2021 Cumulative Disbursements 12/7/2018 Page 4 of 5 The World Bank Implementation Status & Results Report Guizhou Tongren Rural Transport Project (P148071) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/7/2018 Page 5 of 5