PROCUREMENT PLAN (Textual Part) Project information: Bangladesh: Exports Competitiveness for Jobs (EC4J), P156113 Project Implementation agency: Ministry of Commerce (MoC) Date of the Procurement Plan: September 18, 2017 Period covered by this Procurement Plan: from September 2017 to June 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules 2008, as amended in August 2009), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a) e-GP system of the country for national competitive bidding (NCB) shall be followed using Standard/Model Procurement documents satisfactory to the Bank b) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; c) Bids should be submitted and opened in public in one location immediately after the deadline for submission; d) Lottery in award of contracts shall not be allowed; e) Bidders’ qualification/experience requirement shall be mandatory f) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Bangladesh : Export Competitiveness for Jobs PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2017-09-18 2021-10-13 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156113 GPN Date: 2017-09-17 Project Name: Export Competitiveness for Jobs Loan / Credit No: IDA / 60420 Ministry of Commerce Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned W6-1 / Construction of Boundary Wall and Gates for General Engineering Pending 3. Public Investment Facility Single Stage - One 2022-05- Technology Center-1 (GETC- IDA / 60420 Post Request for Bids Open - National 750,000.00 0.00 Implementat 2021-04-19 2021-04-24 2021-05-22 2021-06-05 2021-07-10 for Infrastructure Constraints Envelope 06 1) at Bangabandhu Sheikh ion Mujib Industrial City, Mirsarai, Chattogram. W6-2 / Construction of Boundary Wall and Gates for Pending General Engineering 3. Public Investment Facility Single Stage - One 2022-02- IDA / 60420 Post Request for Bids Open - National 300,000.00 0.00 Implementat 2021-04-20 2021-04-25 2021-05-16 2021-05-30 2021-06-27 Technology Center-2 (GETC- for Infrastructure Constraints Envelope 22 ion 2) at Bangabandhu Hi-Tech City, Kaliakoir, Gazipur. W6-3 / Construction of Pending Boundary Wall and Gates for 3. Public Investment Facility Single Stage - One 2022-04- IDA / 60420 Post Request for Bids Open - National 500,000.00 0.00 Implementat 2021-04-19 2021-04-24 2021-05-15 2021-05-29 2021-07-03 Design and Technology for Infrastructure Constraints Envelope 29 ion Center (DTC) at Kashimpur, Gazipur. GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GD8 / Office furniture, 4. Project Management, Single Stage - One IDA / 60420 Post Request for Bids Open - National 190,000.00 161,304.61 Signed 2018-01-04 2018-05-15 2018-01-09 2018-02-20 2018-05-31 2018-03-22 2018-06-21 2018-04-26 2018-07-19 2018-07-25 equipment and decoration Monitoring & Evaluation Envelope GD4 / Stationaries for Project 4. Project Management, Single Stage - One IDA / 60420 Post Request for Bids Open - National 19,000.00 0.00 Canceled 2017-11-30 2017-12-05 2017-12-19 2017-12-29 2018-02-02 2019-02-02 Office Monitoring & Evaluation Envelope GD-09 / Procurement of 4. Project Management, Request for Single Stage - One Four(04) Laptop Computer & IDA / 60420 Post Limited 6,330.00 5,857.52 Signed 2018-03-16 2018-04-05 2018-05-11 2018-04-19 2018-11-07 Monitoring & Evaluation Quotations Envelope One(01) Multi Function Printer GD-10 / Supply and 4. Project Management, Request for Single Stage - One Installation of office Furniture IDA / 60420 Post Limited 6,330.00 5,655.99 Signed 2018-05-11 2018-05-10 2018-06-15 2018-05-17 2018-12-12 Monitoring & Evaluation Quotations Envelope for the Project Office GD-11 / Supply and Installation of Office 4. Project Management, Request for Single Stage - One IDA / 60420 Post Limited 6,330.00 0.00 Canceled 2018-05-12 2018-06-16 2018-12-13 Equipment for the Office of Monitoring & Evaluation Quotations Envelope PIU GD-12 / Supply and Installation of Split Type Air 4. Project Management, Request for Single Stage - One IDA / 60420 Post Limited 6,330.00 5,918.50 Signed 2018-05-11 2018-05-10 2018-06-15 2018-05-17 2018-12-12 conditioner (AC) for the PIU Monitoring & Evaluation Quotations Envelope Office NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GD1 / Hiring of office space 4. Project Management, Single Stage - One IDA / 60420 Post Request for Bids Open - National 270,000.00 211,321.01 Signed 2017-10-15 2018-01-22 2017-10-20 2018-02-13 2017-11-19 2018-02-20 2018-01-03 2018-03-22 2018-02-07 2018-04-19 2023-06-30 for PIU Monitoring & Evaluation Envelope GD2-3 / Hiring three 4. Project Management, Single Stage - Two Vehicles-SUV-01nos and IDA / 60420 Post Request for Bids Open - National 278,481.00 246,459.41 Signed 2017-12-07 2018-10-14 2017-12-14 2018-01-08 2018-11-08 2018-04-20 2018-11-14 2018-05-14 2018-12-12 2023-06-30 Monitoring & Evaluation Envelope Microbus-02nos. NCS-01 / Hiring a Passenger Vehicle ( 8 Seated) for Short- 4. Project Management, Request for Single Stage - One IDA / 60420 Post Limited 6,330.00 5,527.35 Signed 2018-03-16 2018-03-18 2018-05-11 2018-03-27 2018-11-07 term (3/4 Months) on monthly Monitoring & Evaluation Quotations Envelope rental basis S-27 / Video awareness 1. Market Access Support IDA / 60420 Post Direct Selection Direct 36,000.00 26,255.75 Signed 2018-07-05 2018-07-01 2018-07-10 2018-07-02 2018-08-21 2018-07-10 2019-02-17 Campaign for Leather Sector Program S-30 / TV Broadcasting of Video Documentary and 1. Market Access Support IDA / 60420 Post Direct Selection Direct 50,000.00 40,556.58 Signed 2018-07-26 2018-08-01 2018-07-29 2018-08-06 2018-08-12 2018-08-09 2018-12-10 Scrolling of Key Messages to Program Reduce Flay-cuts CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S15 / Selection of ERF 1. Market Access Support Quality And Cost- IDA / 60420 Prior Open - International 1,645,570.00 0.00 Canceled 2018-01-11 2018-03-02 2018-03-30 2018-04-27 2018-05-27 2018-07-01 2018-08-05 2023-06-30 Management Firm Program Based Selection Page 1 S24 / Export Readiness Fund 1. Market Access Support Quality And Cost- (ERF) Manger for matching IDA / 60420 Prior Open - International 2,000,000.00 3,284,390.73 Signed 2018-05-14 2018-05-09 2018-06-08 2018-06-04 2018-07-30 2018-08-16 2018-08-27 2018-10-02 2018-09-26 2018-12-03 2018-10-31 2019-08-09 2018-12-05 2019-09-26 2022-05-18 Program Based Selection grant program S17 / Market Prioritization, Engineering Design and 3. Public Investment Facility Quality And Cost- IDA / 60420 Prior Open - International 4,400,000.00 5,070,462.24 Signed 2018-05-30 2018-05-15 2018-06-20 2018-05-21 2018-08-08 2018-08-13 2018-09-09 2018-10-03 2018-10-14 2018-12-03 2018-11-22 2019-08-09 2018-12-27 2019-11-27 2022-12-31 Supervision of Cluster for Infrastructure Constraints Based Selection Infrastructure S29 / Feasibility Study of Technology Centres for Light 2. Productivity Enhancement Quality And Cost- IDA / 60420 Post Open - International 215,000.00 258,325.50 Signed 2018-07-18 2018-07-28 2018-08-15 2018-09-05 2018-09-12 2018-11-04 2018-10-10 2018-12-18 2018-10-17 2019-01-15 2018-10-31 2019-05-02 2018-12-05 2019-09-12 2019-12-05 (General) Engineering Sector Program Based Selection in Bangladesh S33 / Production of 'Project Consultant 1. Market Access Support Introduction Video IDA / 60420 Post Qualification Limited 25,000.00 21,769.28 Signed 2018-09-26 2018-10-04 2018-10-10 2018-10-22 2018-11-09 2018-11-21 2018-12-14 2019-01-17 2019-06-12 Program Documentary' for EC4J Project Selection Consultant S51 / Selection of Consultant 4. Project Management, IDA / 60420 Post Qualification Limited 55,000.00 66,101.72 Signed 2018-12-04 2018-12-09 2018-12-04 2019-01-03 2019-01-01 2019-01-23 2019-01-15 2019-02-06 2020-01-15 for ICT Solutions Monitoring & Evaluation Selection S50 / Staging Theater, Gamvira and Folksongs for Consultant 1. Market Access Support Industry Level Awareness on IDA / 60420 Post Qualification Limited 40,000.00 35,384.38 Signed 2019-02-03 2019-01-10 2019-02-17 2019-01-29 2019-03-03 2019-02-13 2019-03-17 2019-02-20 2019-07-15 Program Environment, Social and Selection Quality Compliances (ESQ) S45 / TV Broadcasting of Video Documentary and Scrolling of Key Messages Consultant before Eid-ul-Adha 2019 to 1. Market Access Support IDA / 60420 Post Qualification Limited 52,000.00 50,810.17 Signed 2019-06-03 2019-06-13 2019-06-17 2019-07-07 2019-06-24 2019-07-16 2019-07-15 2019-07-18 2019-09-13 Reduce Flay-cuts of the Raw Program Selection Hides and Waste Management of Leather, Leather Goods and Footwear Sector. S53 / Consultancy Services for Design and Supervision (D&S) for the Establishment of 2. Productivity Enhancement Quality And Cost- IDA / 60420 Prior Open - International 1,700,000.00 1,616,573.25 Signed 2019-11-11 2019-12-05 2019-12-02 2019-12-09 2020-01-15 2020-04-17 2020-02-12 2020-06-29 2020-03-13 2020-09-02 2020-04-17 2020-11-26 2020-05-22 2020-12-17 2023-05-22 Technology Centers under Program Based Selection Export Competitiveness for Jobs (EC4J) Project S46 / Consulting Services to Develop Environmental, Social and Quality (ESQ) Training Modules, Conduct ToT and 1. Market Access Support Quality And Cost- IDA / 60420 Post Open - National 205,000.00 204,477.62 Signed 2020-04-16 2020-05-07 2020-05-06 2020-06-19 2020-08-31 2020-07-17 2020-09-29 2020-08-16 2020-11-30 2020-09-20 2020-12-07 2020-10-25 2020-12-27 2021-10-25 Certification for Leather, Program Based Selection Leather Goods, Footwear, Plastics and Light Engineering Sectors in Bangladesh S47 / Consulting Services to Conduct Specialized Training on Environmental, Social and 1. Market Access Support Fixed Budget Quality (ESQ) for Leather, IDA / 60420 Post Open - National 230,000.00 234,374.15 Signed 2020-04-16 2020-05-07 2020-05-07 2020-06-20 2020-08-31 2020-07-18 2020-09-30 2020-08-17 2020-11-30 2020-09-21 2020-12-09 2020-10-26 2020-12-27 2022-04-19 Program Selection Leather Goods, Footwear, Plastics and Light Engineering sectors in Bangladesh S48 / Consulting Services to design and establish Market Intelligence System (Research, 1. Market Access Support Quality And Cost- Under IDA / 60420 Prior Open - International 700,000.00 0.00 2020-05-05 2020-07-07 2020-05-26 2020-07-08 2020-07-09 2021-03-23 2020-08-06 2021-05-12 2020-09-05 2021-08-24 2020-10-10 2020-11-14 2023-05-03 Database, Maintenance) for Program Based Selection Implementation the four targeted sectors under EC4J Project S49 / Consulting Services of Market Development & 1. Market Access Support Quality And Cost- IDA / 60420 Post Open - National 425,000.00 431,952.62 Signed 2020-05-05 2020-06-25 2020-05-18 2020-07-01 2020-11-30 2020-07-29 2020-12-30 2020-08-28 2021-01-28 2020-10-02 2021-03-04 2020-11-06 2021-03-28 2023-04-25 Branding for the four targeted Program Based Selection sectors under EC4J Project S52 / Consulting Services to showcase Bangladesh at the international sourcing 1. Market Access Support Quality And Cost- IDA / 60420 Post Open - National 465,000.00 471,324.75 Signed 2020-05-05 2020-06-24 2020-05-20 2020-07-03 2020-11-30 2020-07-31 2020-12-30 2020-08-30 2021-01-28 2020-10-04 2021-03-04 2020-11-08 2021-03-28 2023-04-27 show/trade events for the Program Based Selection four targeted sectors under EC4J Project S50-1 / Broadcasting of TVC through Television Channels and Social Media Campaign on Key Messages before the Consultant 1. Market Access Support Eid-ul-Adha 2020 to ensure IDA / 60420 Post Qualification Limited 50,000.00 51,481.06 Signed 2020-07-09 2020-07-10 2020-07-16 2020-07-21 2020-07-19 2020-07-23 2020-07-24 2020-07-24 2020-10-22 Program health safety measures, Selection reduce flay-cut of the raw hides and environment friendly waste management S50-2 / Broadcasting of TVC through Television Channels and Social Media Campaign on Key Messages before the Consultant 1. Market Access Support Eid-ul-Adha 2021 to ensure IDA / 60420 Post Qualification Limited 55,000.00 50,693.44 Signed 2021-05-05 2021-05-16 2021-05-19 2021-06-16 2021-06-03 2021-06-27 2021-07-01 2021-06-29 2021-10-29 Program health safety measures, Selection reduce flay-cut of the raw hides and environment friendly waste management. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual S1 / Financial management 4. Project Management, IDA / 60420 Post Consultant Open 280,000.00 238,140.62 Signed 2017-09-10 2018-01-24 2017-11-27 2018-04-23 2017-12-14 2018-05-30 2018-01-18 2018-06-07 2021-01-17 Specialist (FMS) Monitoring & Evaluation Selection Individual S2 / Procurement Specialist 4. Project Management, IDA / 60420 Post Consultant Open 275,000.00 238,140.62 Signed 2017-09-30 2018-01-29 2017-12-18 2018-04-23 2018-01-08 2018-05-30 2018-02-12 2018-06-07 2021-02-11 (PS) Monitoring & Evaluation Selection Page 2 Individual S3 / Monitoring and 4. Project Management, IDA / 60420 Post Consultant Open 265,900.00 232,419.53 Signed 2017-09-30 2018-01-08 2017-11-23 2018-04-23 2017-12-08 2018-05-30 2018-01-08 2018-06-05 2023-06-30 Evaluation Specialist Monitoring & Evaluation Selection Individual S5 / Environmental 4. Project Management, IDA / 60420 Post Consultant Open 53,000.00 47,628.12 Signed 2018-02-18 2018-02-22 2018-04-08 2018-05-07 2018-04-29 2018-06-07 2018-06-03 2018-06-12 2018-11-30 Management Specialist Monitoring & Evaluation Selection Individual S6 / Social Management 4. Project Management, IDA / 60420 Post Consultant Open 50,000.00 44,338.49 Signed 2018-02-18 2018-02-22 2018-04-08 2018-04-23 2018-04-29 2018-06-07 2018-06-03 2018-06-11 2018-11-30 Specialist Monitoring & Evaluation Selection S4 / Technical Individual 4. Project Management, Specialist(Mechanical/Electrica IDA / 60420 Post Consultant Open 215,000.00 141,785.91 Signed 2018-03-28 2019-03-27 2018-05-16 2019-05-29 2018-06-06 2019-05-30 2018-07-11 2019-07-01 2019-01-07 Monitoring & Evaluation l/Chemical Engineer) Selection Individual 1. Market Access Support S21 / Project Manager IDA / 60420 Post Consultant Limited 266,000.00 149,112.43 Signed 2018-04-15 2018-04-19 2018-04-20 2018-04-20 2018-05-04 2018-04-24 2018-06-01 2018-04-30 2023-07-15 Program Selection Individual S22 / Component 1. Market Access Support IDA / 60420 Post Consultant Limited 213,000.00 80,186.13 Signed 2018-04-15 2018-03-22 2018-04-20 2018-06-20 2018-05-04 2018-06-20 2018-06-01 2018-07-01 2023-07-07 Coordinator (Market Access) Program Selection S23 / Component Individual 2. Productivity Enhancement Coordinator (Productivity IDA / 60420 Post Consultant Limited 213,000.00 79,479.59 Signed 2018-04-15 2018-09-13 2018-04-20 2018-09-19 2018-05-04 2018-10-10 2018-06-02 2018-10-25 2023-07-17 Program Enhancement) Selection Individual S-25 / Land Management 4. Project Management, IDA / 60420 Post Consultant Limited 80,000.00 0.00 Canceled 2018-07-08 2018-07-13 2018-08-03 2018-09-07 2019-03-06 Specialist Monitoring & Evaluation Selection Individual S-26 / Short Term Consultant 4. Project Management, IDA / 60420 Post Consultant Limited 7,300.00 0.00 Canceled 2018-07-03 2018-07-08 2018-07-29 2018-09-02 2019-03-01 DPP Revision Monitoring & Evaluation Selection S28 / Industry wise Awareness building Plan and 1. Market Access Support IDA / 60420 Post Direct Selection Direct 83,133.00 80,850.94 Signed 2018-08-29 2018-09-20 2018-09-08 2018-09-26 2018-11-12 2018-10-17 2019-05-11 Training Need Assessment Program (GAP analysis) by BFTI S30 / Coordination and Communication Consultation 1. Market Access Support for Leather , leather goods & IDA / 60420 Post Direct Selection Direct 149,909.64 137,708.07 Signed 2018-08-29 2020-06-02 2018-09-08 2020-07-23 2018-11-12 2020-11-03 2022-06-30 Program Footwear Sector by Leather Sector BPC S31 / Coordination and Communication Consultation 1. Market Access Support for Light Engineering and IDA / 60420 Post Direct Selection Direct 171,325.30 152,800.57 Signed 2018-08-29 2020-06-02 2018-09-08 2020-06-07 2018-11-12 2020-11-03 2022-06-30 Program Electronics Sector by Light Engineering Sector BPC S32 / Coordination and Communication Consultation 1. Market Access Support IDA / 60420 Post Direct Selection Direct 107,078.31 99,464.52 Signed 2018-08-29 2020-06-02 2018-09-08 2020-07-23 2018-11-12 2020-11-03 2022-06-30 for Plastics Sector by Plastics Program Sector BPC Individual S43 / Component 4. Project Management, IDA / 60420 Post Consultant Open 150,000.00 79,479.59 Signed 2019-04-04 2019-04-01 2019-05-07 2019-05-23 2019-05-21 2019-05-29 2019-06-25 2019-06-16 2022-06-09 Coordinator-3 Monitoring & Evaluation Selection Individual S44 / Monitoring and 4. Project Management, IDA / 60420 Post Consultant Open 190,000.00 172,974.56 Signed 2019-05-09 2019-05-06 2019-06-11 2019-07-25 2019-06-25 2019-07-28 2019-07-23 2019-08-14 2023-03-22 Evaluation (M&E) Specialist Monitoring & Evaluation Selection Individual S5-1 / Environmental 4. Project Management, IDA / 60420 Post Consultant Direct 100,000.00 94,635.91 Signed 2019-05-28 2019-05-29 2019-06-07 2019-06-13 2019-06-14 2019-06-13 2019-06-28 2019-08-28 2021-06-27 Management Specialist Monitoring & Evaluation Selection Individual S6-1 / Social Management 4. Project Management, IDA / 60420 Post Consultant Direct 100,000.00 94,635.91 Signed 2019-05-28 2019-05-29 2019-06-07 2019-06-13 2019-06-14 2019-06-13 2019-06-28 2019-08-28 2021-06-27 Specialist Monitoring & Evaluation Selection Individual S54 / Land Management 4. Project Management, IDA / 60420 Post Consultant Open 40,000.00 39,613.29 Signed 2019-08-31 2019-09-01 2019-10-19 2019-10-09 2019-11-09 2019-10-10 2019-12-14 2019-11-20 2020-12-13 Specialist Monitoring & Evaluation Selection Individual 4. Project Management, S55 / Procurement Specialist IDA / 60420 Post Consultant Open 60,000.00 54,634.60 Signed 2019-08-30 2020-08-17 2019-10-18 2020-12-22 2019-11-08 2020-12-22 2019-12-13 2020-12-27 2021-12-12 Monitoring & Evaluation Selection Individual S56 / Executive Officer 4. Project Management, IDA / 60420 Post Consultant Open 60,000.00 56,024.51 Signed 2019-08-31 2019-09-01 2019-10-19 2019-10-14 2019-11-09 2019-11-26 2019-12-14 2019-12-24 2021-12-13 (Admin & Finance) Monitoring & Evaluation Selection Individual S57 / Executive Officer (ICT & 4. Project Management, IDA / 60420 Post Consultant Open 60,000.00 56,590.42 Signed 2019-08-31 2019-09-01 2019-10-19 2019-10-09 2019-11-09 2019-10-10 2019-12-14 2019-10-14 2021-12-13 Logistics) Monitoring & Evaluation Selection S58 / Executive Officer Individual 4. Project Management, (Communications & Public IDA / 60420 Post Consultant Open 60,000.00 55,175.66 Signed 2019-08-31 2019-09-01 2019-10-19 2019-10-14 2019-11-09 2019-10-15 2019-12-14 2019-10-28 2021-12-13 Monitoring & Evaluation Relations) Selection Individual S65 / Short Term M&E 4. Project Management, IDA / 60420 Post Consultant Limited 20,000.00 17,686.59 Signed 2020-04-26 2020-06-14 2020-05-05 2020-06-21 2020-05-26 2020-06-22 2020-06-30 2020-07-15 2021-06-30 Consultant Monitoring & Evaluation Selection S22-1 / Component Individual 4. Project Management, Coordinator-1 (Market IDA / 60420 Post Consultant Direct 95,000.00 89,140.41 Signed 2020-06-28 2020-06-25 2020-07-02 2020-07-07 2020-07-04 2020-07-14 2020-07-14 2020-07-15 2022-07-04 Monitoring & Evaluation Access) Selection S23-1 / Component Individual 4. Project Management, Coordinator-2 (Productivity IDA / 60420 Post Consultant Direct 95,000.00 89,140.41 Signed 2020-06-28 2020-07-07 2020-07-02 2020-07-12 2020-07-07 2020-07-14 2020-07-21 2020-07-15 2022-07-11 Monitoring & Evaluation Enhancement Program) Selection Page 3 Individual 4. Project Management, Under S4-1 / Technical Specialist IDA / 60420 Post Consultant Open 90,000.00 0.00 2020-08-12 2020-08-17 2020-09-30 2020-10-21 2020-11-25 2022-09-16 Monitoring & Evaluation Implementation Selection Individual S43-1 / Component 4. Project Management, Pending IDA / 60420 Post Consultant Direct 90,000.00 0.00 2021-08-05 2021-08-15 2021-08-19 2021-08-29 2023-06-30 Coodinator-3 Monitoring & Evaluation Implementation Selection Individual 4. Project Management, Pending S21-1 / Project Manager IDA / 60420 Post Consultant Open 95,000.00 0.00 2021-08-05 2021-09-07 2021-09-14 2021-09-28 2023-07-01 Monitoring & Evaluation Implementation Selection Page 4