Public Disclosure Copy The World Bank Implementation Status & Results Report COMMUNITY RESILIENCE TO CLIMATE AND DISASTER RISK IN SOLOMON ISLANDS PROJECT (P112613) COMMUNITY RESILIENCE TO CLIMATE AND DISASTER RISK IN SOLOMON ISLANDS PROJECT (P112613) EAST ASIA AND PACIFIC | Solomon Islands | Social, Urban, Rural and Resilience Global Practice Global Practice | Global Environment Project | Investment Project Financing | FY 2014 | Seq No: 11 | ARCHIVED on 16-Apr-2019 | ISR36449 | Implementing Agencies: Solomon Islands, Ministry of Environment, Climate Change, Disaster Management and Meteorology Key Dates Key Project Dates Bank Approval Date: 06-Mar-2014 Effectiveness Date: 01-Apr-2014 Planned Mid Term Review Date: 14-Jun-2017 Actual Mid-Term Review Date: 19-Jun-2017 Original Closing Date: 31-May-2019 Revised Closing Date: 31-May-2019 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To increase the resilience of selected rural communities to the impacts of natural hazards and climate change. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name A – Integration of risk resilience for the management of disaster and climate risk into the Recipient’s policy frameworks and practices:(Cost $1.01 M) B – Strengthening of climate and disaster risk information and communication:(Cost $1.39 M) C – Climate change adaptation and disaster risk reduction investments:(Cost $6.28 M) D - Project management and monitoring & evaluation:(Cost $0.45 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions Implementation of all planned activities has been completed except for 20 community-led and 4 provincial-led subprojects which are ongoing. Severe weather events in mid-January leading to Tropical Cyclone Oma on 12 February delayed implementation progress in some communities but it is hoped the project can be completed on schedule. When completed, the subprojects will benefit a total of 57,976 people, exceeding the revised PDO results indicator of 53,400, while the completed seismic and volcano warning system directly benefit at least 60,000 people who are vulnerable 4/16/2019 Page 1 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report COMMUNITY RESILIENCE TO CLIMATE AND DISASTER RISK IN SOLOMON ISLANDS PROJECT (P112613) to volcanic eruptions in the targeted sites. The network is also used to monitor and disseminate early warnings for other natural hazards such as tropical cyclone and tsunami thereby reaching the whole country’s population of 623,000 people. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Substantial Substantial Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Substantial Substantial Institutional Capacity for Implementation and Sustainability -- High High Fiduciary -- High High Environment and Social -- Moderate Moderate Stakeholders -- Moderate Moderate Other -- Substantial Substantial Overall -- Substantial Substantial Results PDO Indicators by Objectives / Outcomes Number of beneficiaries in areas targeted under the program that benefit from CCA and/or DRR IN00684941 ►Number of beneficiaries in areas targeted under the program that benefit from CCA and/or DRR investments (with a target of at least 48% of the total beneficiaries being female) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1,000.00 52,500.00 52,500.00 53,400.00 Date 01-Jun-2014 18-Oct-2018 28-Feb-2019 31-Mar-2019 The current subprojects are on track to serve 58000 beneficiaries by closing date. The volcano-seismic equipment that have been installed in 7 sites (more than 2 stations planned originally) also allows the project to reach a direct beneficiary of at least 60000 people that are vulnerable to the current active Comments: volcanos. The overall population of Solomon Islands (projected to be 620,000) will also benefit from the system through the dissemination of early warning messages for natural hazards such as cyclones and tsunami. Percentage of targeted communities which demonstrate capacity to implement CBDRM/V&A plans IN00684942 ►Percentage of targeted communities which demonstrate capacity to implement CBDRM/V&A plans to manage the impact of natural hazards and climate change. (Percentage, Custom) 4/16/2019 Page 2 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report COMMUNITY RESILIENCE TO CLIMATE AND DISASTER RISK IN SOLOMON ISLANDS PROJECT (P112613) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 60.00 60.00 70.00 Date 01-Jun-2014 18-Oct-2018 28-Feb-2019 31-May-2019 Number of ministries with activities in their annual work programs including resilience measures IN00684943 ►Number of ministries with activities in their annual work programs including resilience measures for climate and disaster risk (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2.00 2.00 3.00 Date 01-Jun-2014 18-Oct-2018 28-Feb-2019 31-May-2019 Activities are ongoing to mainstream climate and disaster resilience into the work program of the Ministry of Environment, Climate Change, Disaster Management and Meteorology (MECDM) and Ministry of Comments: Health and Medical Services (MHMS). A work program has also been developed to work together with the Ministry of Culture and Tourism in mainstreaming activities. Intermediate Results Indicators by Components Component A – Integration of climate change adaptation and disaster risk reduction in government policies and operations IN00684944 ►The NDC and the NDC Committees are operating and are effective (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Committees exists in The NDC continues to Committees work NDRMP but not meet and have met in Value -- effectively and meet at operational April 2018 to approve least once per year the NDM Plan Date 01-Jun-2014 18-Oct-2018 28-Feb-2019 31-May-2019 IN00684951 ►National Disaster Council adopts the Framework for Resilient Development outlined in the 2017 NDM Plan for integration of climate and disaster risk (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target The revision of the NDM Plan has been completed and approved by the Cabinet and the government has separate DRM and CCA Value -- agreed to continue Framework adopted strategies/ plans lead the national dialogue and consultation on the integrated framework for resilience development. Date 01-Jun-2014 18-Oct-2018 28-Feb-2019 31-May-2019 The revision of the NDM Plan has been completed and approved by the Cabinet. The Plan provide Comments: guidance on the national and provincial institutional arrangements for disaster response activities and makes provisions for community based response activities, the establishment of national emergency 4/16/2019 Page 3 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report COMMUNITY RESILIENCE TO CLIMATE AND DISASTER RISK IN SOLOMON ISLANDS PROJECT (P112613) operation centers and an integrated approach to disaster risk management. Therefore, the indicator can be considered achieved. For the draft integrated framework for resilience development, the government has agreed to continue lead the national dialogue and consultation under its own resources. Component B – Strengthening of climate and disaster risk information and communication IN00684945 ►Volcano/Seismic early warning systems are installed and operating. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 7.00 7.00 7.00 Date 01-Jun-2014 18-Oct-2018 28-Feb-2019 31-May-2019 Results indicator achieved Comments: IN00684948 ►MECDM data base for Risk Information Management system strengthened (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Achieved- The database for climate and risk information management system in MECDM have been strengthened and the NDMO and the Climate Division are now connected to the database. The national climate change adaptation and Risk information Some data is being disaster risk database system is Value -- assembled into MapInfo management data strengthened and portal is now available oeprational and in operation. The government is now using the remaining time in the project to take the system to the next level by uploading more climate and disaster risk data into the portal to be able to undertake risk analysis. Date 01-Jun-2014 18-Oct-2018 28-Feb-2019 31-May-2019 Component C – Climate change adaptation and disaster risk reduction investments IN00684946 ►Number of subprojects completed under the community-led DRR/CCA investments (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 20.00 28.00 59.00 Date 01-Jun-2014 18-Oct-2018 28-Feb-2019 31-May-2019 IN00684949 ►Number of sub-projects completed under Provincial Government led DRM/CCA investments. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 4/16/2019 Page 4 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report COMMUNITY RESILIENCE TO CLIMATE AND DISASTER RISK IN SOLOMON ISLANDS PROJECT (P112613) Value 0.00 1.00 1.00 4.00 Date 01-Jun-2014 18-May-2018 28-Feb-2019 31-May-2019 IN00684952 ►Number of Community Based Disaster Risk Management (CBDRM) Plans developed. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 79.00 79.00 59.00 Date 01-Jun-2014 18-May-2018 28-Feb-2019 31-May-2019 IN00684953 ►Percentage of women involved in decisions during preparation and implementation of community-led projects (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 21.00 21.00 35.00 Date 01-Jun-2014 18-Oct-2018 28-Feb-2019 31-May-2019 Component D - Project management and monitoring & evaluation IN00684947 ►The PCC is meeting at least once per year and provides oversight on the project. (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target 5 Annual meetings The PCC had its fifth that define clear Value 0.00 -- annual meeting on 21 actions for CRISP November 2018. and/or SIG. Date 01-Jun-2014 18-Oct-2018 28-Feb-2019 31-May-2019 IN00684950 ►Program components are managed and monitored effectively. (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Project implementation rating has remained as Moderately Satisfactory or better Value Nil -- Satisfactory since it rating was upgraded from MU at the last ISR in November 2018. Date 01-Jun-2014 18-Oct-2018 28-Feb-2019 31-May-2019 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P112613 TF-16425 Closed USD 1.80 1.80 0.00 1.80 0.00 100% P112613 TF-16614 Effective USD 7.30 7.30 0.00 5.49 1.81 75% 4/16/2019 Page 5 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report COMMUNITY RESILIENCE TO CLIMATE AND DISASTER RISK IN SOLOMON ISLANDS PROJECT (P112613) Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P112613 TF-16425 Closed 01-Apr-2014 01-Apr-2014 01-Apr-2014 31-Dec-2016 30-Oct-2018 P112613 TF-16614 Effective 01-Apr-2014 01-Apr-2014 01-Apr-2014 31-May-2019 31-May-2019 Cumulative Disbursements Restructuring History Level 2 Approved on 14-May-2018 Related Project(s) There are no related projects. 4/16/2019 Page 6 of 6