Summarized Procurement Plan Ministry of Environment, Natural Resources and Physical Development Sudan Sustainable Natural Resources Management Project I. General 1. March Bank’s approval Date of the procurement Plan [Original: 2017]: Revision of Updated Procurement Plan, July and September 2017] 2. Date of General Procurement Notice: June, 2014 3. period Period covered by this procurement plan: The procurement of project covered from 1 December 2017 to 31 December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement Procurement Method Prior Review Comments Threshold US$ 1. Shopping (Goods) US$ 37,000 All 2. Shopping (Works) US$ 205,000 All 3. Trainings US$ 264,500 All 4. Consultancy US$ 17,500 5. Non-consulting - - services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by December, 2017 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable]5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the last month of 2017 (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Package Domestic Review Comment No. Cost s Preferenc by Bank s US$ e (Prior / (yes/no) Post) 1 Summary of 205,000 2 No Post shopping (Works) 2 Summary of 37,000 3 No Post shopping (Goods) 3 Trainings 109,500 7 Post (Locally) 4 Trainings 155,000 5 Post or (Internationally) Prior III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods - (Firms) 2. Single Source (Firms) - 3. Individual US$ 17,500 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_5,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. December, 2017 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estima Packa Review Comments No. Assignment ted ges by Bank Cost (Prior / US$ Post) 1 Summary of 17,50 5 Post number of 0 contracts that will be let under Individual Consultant (IC ) December, 2017 PROCUREMENT Sudan : Sudan Sustainable Natural Resources Management Project PLAN General Information Country: Sudan Bank’s Approval Date of the Original Procurement Plan: 2018-03-22 2021-03-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P129156 GPN Date: Project Name: Sudan Sustainable Natural Resources Management Project Loan / Credit No: TF / 16134, TF / A7607, TF / B3244 Sustainable Natural Resources Management Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 2: Community SD-SSNRMP-39606-CW-RFQ based sustainable / Installation of two water management of rangelands Request for Single Stage - One 2018-08- station in Elitaut & Maman TF / 16134 Post Limited 85,000.00 0.00 Canceled 2017-12-22 2018-02-16 and forests and biodiversity Quotations Envelope 15 villages in Talkuk Locality conservation activities in Kassala State targeted s tates Component 2: Community SD-SSNRMP-46418-CW-RFQ based sustainable / Construction of range management of rangelands Request for Single Stage - One 2018-11- TF / 16134 Post Limited 36,000.00 0.00 Canceled 2018-04-03 2018-05-29 seedling store in white Nile and forests and biodiversity Quotations Envelope 25 state conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46420-CW-RFQ management of rangelands Request for Single Stage - One 2018-07- / Construction of Enclosure to TF / 16134 Post Limited 20,000.00 35,555.56 Completed 2018-04-15 2018-07-15 2018-05-03 2018-08-07 and forests and biodiversity Quotations Envelope 02 produce pasture (legume) conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46422-CW-RFQ management of rangelands Request for Single Stage - One 2018-06- / Seeds Broadcasting for 3180 TF / 16134 Post Limited 17,000.00 0.00 Canceled 2018-05-17 2018-06-05 and forests and biodiversity Quotations Envelope 25 ha. conservation activities in targeted s tates Component 2: Community SD-SSNRMP-46423-CW-RFQ based sustainable / Fire Lines for Range and management of rangelands Request for Single Stage - One 2018-12- TF / 16134 Post Limited 38,000.00 0.00 Canceled 2018-10-07 2018-10-28 forest 347 km and forests and biodiversity Quotations Envelope 27 (integration) conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46458-CW-RFQ management of rangelands Request for Single Stage - One 2018-05- / Rehabilitation of Eldowiem TF / 16134 Post Limited 4,375.00 8,082.27 Completed 2018-03-20 2018-08-26 2018-04-15 2018-09-10 and forests and biodiversity Quotations Envelope 31 Nursery conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46473-CW-RFQ management of rangelands Request for Single Stage - One 2018-05- / Rehabilitation of Elsafory TF / 16134 Post Limited 1,875.00 0.00 Canceled 2018-03-20 2018-04-15 and forests and biodiversity Quotations Envelope 31 Nursery conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-48510-CW-RFQ management of rangelands Request for Single Stage - One 2018-08- TF / 16134 Post Limited 40,000.00 0.00 Canceled 2018-06-17 2018-07-05 / Afforestation of 840 ha. and forests and biodiversity Quotations Envelope 23 conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46523-CW-RFQ management of rangelands Request for Single Stage - One 2018-06- / Rehabilitation of Eldowiem TF / 16134 Post Limited 30,000.00 46,910.42 Completed 2018-04-08 2018-08-26 2018-04-27 2018-09-10 and forests and biodiversity Quotations Envelope 01 Office conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46538-CW-RFQ management of rangelands Request for Single Stage - One 2018-06- / Rehabilitation of Captive TF / 16134 Post Limited 12,500.00 9,847.39 Completed 2018-05-06 2018-10-17 2018-05-24 2018-11-07 and forests and biodiversity Quotations Envelope 21 Breeding in Kassala conservation activities in targeted s tates Component 2: Community SD-SSNRMP-46650-CW-RFQ based sustainable / Construction & management of rangelands Request for Single Stage - One 2018-05- TF / 16134 Post Limited 60,000.00 0.00 Canceled 2018-04-08 2018-04-26 Establishment of community and forests and biodiversity Quotations Envelope 31 wildlife farm conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46667-CW-RFQ management of rangelands Request for Single Stage - One 2018-12- / Construction of wet basins TF / 16134 Post Limited 80,000.00 0.00 Canceled 2018-03-25 2018-04-15 and forests and biodiversity Quotations Envelope 02 (210 ha) conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46902-CW-RFQ management of rangelands Request for Single Stage - One 2018-05- TF / 16134 Post Limited 14,005.00 0.00 Canceled 2018-03-27 2018-04-15 / Rehabilitation of Camps and forests and biodiversity Quotations Envelope 07 conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46906-CW-RFQ management of rangelands Request for Single Stage - One 2018-06- / Rehabilitation Kassala TF / 16134 Post Limited 1,875.00 1,831.14 Completed 2018-03-25 2018-10-17 2018-04-19 2018-11-07 and forests and biodiversity Quotations Envelope 05 central nursery conservation activities in targeted s tates Page 1 Component 2: Community based sustainable SD-SSNRMP-46920-CW-RFQ management of rangelands Request for Single Stage - One 2018-06- / Rehabilitation & TF / 16134 Post Limited 4,375.00 14,888.45 Completed 2018-04-08 2018-10-17 2018-05-24 2018-11-07 and forests and biodiversity Quotations Envelope 24 Maintenance of camps conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-47077-CW-RFQ management of rangelands Request for Single Stage - One 2018-06- / Construction three shallow TF / 16134 Post Limited 45,000.00 9,361.86 Completed 2018-04-01 2018-12-16 2018-04-18 2018-12-30 and forests and biodiversity Quotations Envelope 30 wells at Alhamaria Village conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-47401-CW-RFQ management of rangelands Request for Single Stage - One 2018-05- / Construction of Women TF / 16134 Post Limited 15,235.00 13,922.66 Completed 2018-04-07 2018-10-17 2018-04-22 2018-11-07 and forests and biodiversity Quotations Envelope 22 vegetable farm conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-47402-CW-RFQ management of rangelands Request for Single Stage - One 2018-07- / Construction of community TF / 16134 Post Limited 18,750.00 16,491.18 Completed 2018-05-20 2018-10-17 2018-06-07 2018-11-07 and forests and biodiversity Quotations Envelope 08 nursery in Maman village conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-48456-CW-RFQ management of rangelands Request for Single Stage - One 2018-06- / Construction of Enclosure TF / 16134 Post Limited 90,000.00 40,248.00 Completed 2018-04-22 2018-06-20 2018-05-10 2018-07-08 and forests and biodiversity Quotations Envelope 30 for seed production conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-48484-CW-RFQ management of rangelands Request for Single Stage - One 2018-05- / Construction of RANGE TF / 16134 Post Limited 36,000.00 47,739.15 Completed 2018-03-31 2018-08-26 2018-04-19 2018-09-10 and forests and biodiversity Quotations Envelope 31 Seeds Store conservation activities in targeted s tates Component 2: Community SD-SSNRMP-100505-CW- based sustainable RFQ / Installation of Solar management of rangelands Request for Single Stage - One 2019-05- TF / 16134 Post Limited 38,297.87 10,776.70 Completed 2019-04-12 2019-04-18 2019-04-25 2019-04-29 energy for Surface wells @ and forests and biodiversity Quotations Envelope 19 Alhamaria Village conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-100509-CW- Pending management of rangelands Request for Single Stage - One 2019-05- RFQ / Construction of field TF / 16134 Post Limited 16,595.74 0.00 Implementat 2019-03-08 2019-03-21 and forests and biodiversity Quotations Envelope 05 camp in Wad Bugul Forest ion conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-100510-CW- management of rangelands Request for Single Stage - One 2019-05- RFQ / Rehabilitation of F.N.C TF / 16134 Post Limited 5,319.15 0.00 Canceled 2019-04-06 2019-04-21 and forests and biodiversity Quotations Envelope 26 office - Rufaa conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-100512-CW- management of rangelands Request for Single Stage - One 2019-05- RFQ / Construction of seeds TF / 16134 Post Limited 5,106.38 0.00 Canceled 2019-04-06 2019-04-21 and forests and biodiversity Quotations Envelope 26 store - F.N.C office - Medani conservation activities in targeted s tates Component 2: Community SD-SSNRMP-100687-CW- based sustainable RFQ / Construction of fence management of rangelands Request for Single Stage - One 2019-04- TF / 16134 Post Limited 5,000.00 0.00 Canceled 2019-03-05 2019-03-21 for Taiba M. Alamin water and forests and biodiversity Quotations Envelope 20 yard conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-100689-CW- management of rangelands Request for Single Stage - One 2019-04- RFQ / Construction camp and TF / 16134 Post Limited 10,638.30 0.00 Canceled 2019-03-08 2019-03-24 and forests and biodiversity Quotations Envelope 23 Guarding for rangeland conservation activities in targeted s tates Component 2: Community SD-SSNRMP-47407-CW-RFQ based sustainable / construction of two management of rangelands Request for Single Stage - One 2019-05- TF / 16134 Post Limited 14,893.62 0.00 Canceled 2019-03-24 2019-04-11 Demonstration farms in and forests and biodiversity Quotations Envelope 31 Talkouk locality conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46652-CW-RFQ management of rangelands Request for Single Stage - One 2019-06- / construction of breeding TF / 16134 Post Limited 53,191.49 0.00 Canceled 2019-04-14 2019-04-25 and forests and biodiversity Quotations Envelope 09 Center conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-100727-CW- management of rangelands Request for Single Stage - One 2019-06- RFQ / Rehabilitation of F.N.C TF / 16134 Post Limited 10,638.30 0.00 Canceled 2019-05-03 2019-05-19 and forests and biodiversity Quotations Envelope 18 office - Kassala conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-100731-CW- management of rangelands Request for Single Stage - One 2019-06- RFQ / Rehabilitation of TF / 16134 Post Limited 4,255.32 0.00 Canceled 2019-05-03 2019-05-19 and forests and biodiversity Quotations Envelope 18 wildlife office - Kassala conservation activities in targeted s tates Page 2 Component 2: Community based sustainable SD-SSNRMP-46489-CW-RFQ management of rangelands Request for Single Stage - One 2019-05- / Construction of forest camp TF / 16134 Post Limited 10,638.30 0.00 Canceled 2019-03-10 2019-03-21 and forests and biodiversity Quotations Envelope 05 and Guarding conservation activities in targeted s tates SD-SSNRMP-141004-CW- Component 3: Project Request for Single Stage - One 2020-02- RFQ / Rehabilitation of North TF / A7607 management, Monitoring and Post Limited 10,000.00 0.00 Canceled 2019-12-08 2019-12-24 Quotations Envelope 06 Kordufan state offices (SPIU) Evaluation SD-SSNRMP-141013-CW- Component 3: Project Request for Single Stage - One 2020-02- RFQ / Rehabilitation of River TF / A7607 management, Monitoring and Post Limited 10,000.00 0.00 Canceled 2019-12-08 2019-12-24 Quotations Envelope 06 Nile state offices (SPIU) Evaluation SD-SSNRMP-140997-CW- Component 3: Project Request for Single Stage - One 2020-02- RFQ / Rehabilitation of TF / A7607 management, Monitoring and Post Limited 10,000.00 0.00 Canceled 2019-12-08 2019-12-24 Quotations Envelope 06 Northern state offices (SPIU) Evaluation Component 2: Community SD-SSNRMP-166638-CW- based sustainable RFQ / Rehabilitaion of management of rangelands Request for 2020-07- TF / A7607 Post Limited 30,000.00 0.00 Canceled 2020-04-06 2020-04-20 existing institutions nurseries and forests and biodiversity Quotations 19 at NK conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-191719-CW- management of rangelands Request for Single Stage - One 2020-12- RFQ / Drilling of 2 wells at TF / A7607 Post Limited 83,818.00 91,242.69 Signed 2020-10-06 2020-11-15 2020-10-22 2020-12-09 and forests and biodiversity Quotations Envelope 31 North Kordafan conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166627-CW- based sustainable Under RFQ / Irrigation system management of rangelands Single Stage - One 2020-12- TF / A7607 Post Request for Bids Open - National 262,836.00 0.00 Implementat 2020-05-20 2020-12-06 2020-05-25 2020-06-24 2020-07-01 2020-07-11 installation for (2) green belts and forests and biodiversity Envelope 31 ion rehabilitation - Northern state conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166633-CW- based sustainable RFQ / Construction of (2) management of rangelands Single Stage - One 2020-12- TF / A7607 Post Request for Bids Open - National 527,280.00 448,960.84 Signed 2020-10-01 2020-11-04 2020-10-06 2020-11-04 2020-10-21 2020-11-19 2020-10-26 2020-11-19 2020-11-01 2020-12-06 Haffirs (water reservoiur) at and forests and biodiversity Envelope 31 RN SPIUs conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166622-CW- management of rangelands Request for Single Stage - One 2020-11- RFQ / Digging 2 wells in TF / A7607 Post Limited 80,000.00 48,189.52 Signed 2020-09-25 2020-11-16 2020-10-11 2020-12-14 and forests and biodiversity Quotations Envelope 26 Northern state conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166761-CW- based sustainable Pending RFQ / Rehabilitation of (2) management of rangelands Request for Single Stage - One 2021-04- TF / 16134 Post Limited 5,500.00 0.00 Implementat 2020-09-17 2020-10-03 rangeland Enclosures at and forests and biodiversity Quotations Envelope 01 ion Kassala state conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166652-CW- based sustainable RFQ / Rehabilitation of management of rangelands Request for Single Stage - One 2020-12- TF / A7607 Post Limited 66,821.00 26,614.21 Signed 2020-09-20 2020-10-15 2020-10-04 2020-11-02 existing institutions nurseries and forests and biodiversity Quotations Envelope 31 at RN state conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166765-CW- Pending management of rangelands Request for Single Stage - One 2020-12- RFQ / Rehabilitation of TF / 16134 Post Limited 8,909.00 0.00 Implementat 2020-09-18 2020-09-27 and forests and biodiversity Quotations Envelope 26 nureseries at Kassala state ion conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166762-CW- based sustainable Pending RFQ / Rehabilitation of (3) management of rangelands Request for Single Stage - One 2021-04- TF / 16134 Post Limited 4,000.00 0.00 Implementat 2020-09-17 2020-10-03 rangeland Enclosures at White and forests and biodiversity Quotations Envelope 01 ion Nile state conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166766-CW- Pending management of rangelands Request for Single Stage - One 2020-12- RFQ / Rehabilitation of TF / 16134 Post Limited 8,909.00 0.00 Implementat 2020-09-18 2020-09-27 and forests and biodiversity Quotations Envelope 26 nureseries at White Nile ion conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166771-CW- Pending management of rangelands Request for Single Stage - One 2020-11- RFQ / Construction of White TF / 16134 Post Limited 14,477.00 0.00 Implementat 2020-09-29 2020-10-13 and forests and biodiversity Quotations Envelope 30 Nile Zoo lanterns (6) ion conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166764-CW- Pending management of rangelands Request for Single Stage - One 2020-12- RFQ / Rehabilitation of TF / 16134 Post Limited 8,909.00 0.00 Implementat 2020-09-18 2020-09-27 and forests and biodiversity Quotations Envelope 26 nureseries at Geziera ion conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166763-CW- Pending management of rangelands Request for Single Stage - One 2021-01- RFQ / Maintenance of Kassala TF / 16134 Post Limited 6,682.00 0.00 Implementat 2020-10-15 2020-10-31 and forests and biodiversity Quotations Envelope 29 Wildlife Enclosure ion conservation activities in targeted s tates Page 3 Component 2: Community SD-SSNRMP-166656-CW- based sustainable RFQ / Rehabilitation of management of rangelands Request for Single Stage - One 2021-01- TF / A7607 Post Limited 66,821.00 21,414.46 Signed 2020-09-25 2020-10-22 2020-10-09 2020-11-09 existing institutions nurseries and forests and biodiversity Quotations Envelope 07 at NR conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166760-CW- based sustainable Pending RFQ / Rehabilitation of (3) management of rangelands Request for Single Stage - One 2020-12- TF / 16134 Post Limited 16,000.00 0.00 Implementat 2020-09-15 2020-10-01 rangeland Enclosures at and forests and biodiversity Quotations Envelope 31 ion Geziera state conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166674-CW- Pending management of rangelands Request for Single Stage - One 2021-07- RFQ / Construction of TF / A7607 Post Limited 20,000.00 0.00 Implementat 2021-01-06 2021-01-22 and forests and biodiversity Quotations Envelope 21 Enclosure for Range at NR ion conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166637-CW- based sustainable Pending RFQ / Construction of two management of rangelands Request for Single Stage - One 2021-07- TF / A7607 Post Limited 100,000.00 0.00 Implementat 2021-01-06 2021-01-22 Community Development and forests and biodiversity Quotations Envelope 21 ion Centers at Northern state conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166636-CW- based sustainable Pending RFQ / Construction of two management of rangelands Request for Single Stage - One 2021-07- TF / A7607 Post Limited 100,000.00 0.00 Implementat 2021-01-06 2021-01-22 Community Development and forests and biodiversity Quotations Envelope 21 ion Centers at RN state conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166634-CW- based sustainable Pending RFQ / Construction of two management of rangelands Request for Single Stage - One 2021-07- TF / A7607 Post Limited 100,000.00 0.00 Implementat 2021-01-06 2021-01-22 Community Development and forests and biodiversity Quotations Envelope 21 ion Centers at NK state conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166769-CW- based sustainable Pending RFQ / Maintenance of (2) management of rangelands Request for Single Stage - One 2020-12- TF / 16134 Post Limited 7,400.00 0.00 Implementat 2020-10-15 2020-10-29 Water Stations /Hafir units - and forests and biodiversity Quotations Envelope 13 ion Kassala conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166770-CW- based sustainable Pending RFQ / Maintenance of (2) management of rangelands Request for Single Stage - One 2020-12- TF / 16134 Post Limited 7,400.00 0.00 Implementat 2020-10-15 2020-10-29 Water Stations /Hafir units - and forests and biodiversity Quotations Envelope 13 ion White Nile conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166767-CW- based sustainable Pending RFQ / Maintenance of (2) management of rangelands Request for Single Stage - One 2020-12- TF / 16134 Post Limited 7,400.00 0.00 Implementat 2020-10-15 2020-10-29 Water Stations /Hafir units- and forests and biodiversity Quotations Envelope 13 ion Geziera conservation activities in targeted s tates Component 2: Community SD-SSNRMP-192942-CW- based sustainable Pending RFQ / Rehabilitaion of management of rangelands Request for Single Stage - One 2020-12- TF / A7607 Post Limited 66,821.00 0.00 Implementat 2020-10-06 2020-10-24 existing institution nursery at and forests and biodiversity Quotations Envelope 13 ion NK conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166785-CW- based sustainable RFQ / Construction of management of rangelands Request for Single Stage - One 2020-11- TF / 16134 Post Limited 131,780.00 123,761.36 Signed 2020-04-20 2020-11-09 2020-05-08 2020-11-29 breeding Center at Geziera and forests and biodiversity Quotations Envelope 04 state conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-192968-CW- Pending management of rangelands Request for Single Stage - One 2021-06- RFQ / Rehabilitation of (1) TF / A7607 Post Limited 40,000.00 0.00 Implementat 2021-04-06 2021-05-05 and forests and biodiversity Quotations Envelope 19 nursery -GD ion conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166673-CW- Pending management of rangelands Request for Single Stage - One 2021-06- RFQ / Construction of TF / A7607 Post Limited 50,915.00 0.00 Implementat 2021-04-06 2021-05-05 and forests and biodiversity Quotations Envelope 19 Community Nursery in NK ion conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166672-CW- Pending management of rangelands Request for Single Stage - One 2021-08- RFQ / Construction of TF / A7607 Post Limited 50,915.00 0.00 Implementat 2021-04-06 2021-05-05 and forests and biodiversity Quotations Envelope 01 Community Nursery in RN ion conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166670-CW- based sustainable Pending RFQ / Construction of management of rangelands Request for Single Stage - One 2021-08- TF / A7607 Post Limited 50,915.00 0.00 Implementat 2021-04-06 2021-05-05 Community Nursery in and forests and biodiversity Quotations Envelope 03 ion Northern state conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166631-CW- Pending management of rangelands Request for Single Stage - One 2021-08- RFQ / Installation of (2) water TF / A7607 Post Limited 53,457.00 0.00 Implementat 2021-06-06 2021-07-03 and forests and biodiversity Quotations Envelope 17 station units at RN state ion conservation activities in targeted s tates Page 4 Component 2: Community SD-SSNRMP-191705-CW- based sustainable Pending RFQ / Installation of water management of rangelands Request for Single Stage - One 2021-06- TF / A7607 Post Limited 125,600.00 0.00 Implementat 2021-03-26 2021-04-24 stations for 2 wells at North and forests and biodiversity Quotations Envelope 23 ion Kordafan conservation activities in targeted s tates Component 2: Community SD-SSNRMP-222538-CW-RFB based sustainable Pending / Establishment of Khartoum management of rangelands Single Stage - One 2021-12- TF / A7607 Post Request for Bids Open - National 687,000.00 0.00 Implementat 2021-04-18 2021-04-25 2021-05-20 2021-06-03 2021-06-20 Green Belt (6 kilometers on and forests and biodiversity Envelope 17 ion both Eastern & Western part) conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166755-CW- Pending management of rangelands Request for Single Stage - One 2021-06- RFQ / construction of forest TF / A7607 Post Limited 20,000.00 0.00 Implementat 2021-03-25 2021-04-22 and forests and biodiversity Quotations Envelope 21 camp at NK state ion conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166737-CW- Pending management of rangelands Request for Single Stage - One 2021-06- RFQ / construction of range TF / A7607 Post Limited 20,000.00 0.00 Implementat 2021-03-25 2021-04-22 and forests and biodiversity Quotations Envelope 21 camps at RN state ion conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166757-CW- Pending management of rangelands Request for Single Stage - One 2021-06- RFQ / construction of forest TF / A7607 Post Limited 20,000.00 0.00 Implementat 2021-03-25 2021-04-22 and forests and biodiversity Quotations Envelope 06 camp at Northern state ion conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166676-CW- based sustainable Pending RFQ / Construction of (2) management of rangelands Request for Single Stage - One 2021-12- TF / B3244 Post Limited 196,400.00 0.00 Implementat 2021-06-06 2021-07-06 Enclosures for Range - RN & and forests and biodiversity Quotations Envelope 30 ion NK state conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166675-CW- based sustainable Pending RFQ / Construction of (2) management of rangelands Request for Single Stage - One 2021-12- TF / A7607 Post Limited 196,400.00 0.00 Implementat 2021-06-06 2021-07-06 Enclosures for Range at GD & and forests and biodiversity Quotations Envelope 30 ion KH conservation activities in targeted s tates Component 2: Community SD-SSNRMP-223492-CW- based sustainable RFQ / Irrigation system Pending management of rangelands Request for Single Stage - One 2021-10- installation for (2) green belts TF / B3244 Post Limited 85,000.00 0.00 Implementat 2021-03-18 2021-04-05 and forests and biodiversity Quotations Envelope 02 rehabilitation - Northern state ion conservation activities in (cost extension) targeted s tates GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Community based sustainable SD-SSNRMP-39595-GO-RFQ management of rangelands Request for Single Stage - One / Supply of plauger, Harrow TF / 16134 Post Limited 20,000.00 8,766.67 Completed 2018-01-05 2017-12-21 2018-03-02 2017-12-28 2018-08-29 2017-12-28 and forests and biodiversity Quotations Envelope ,Chezle conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-39599-GO-RFQ management of rangelands Request for Single Stage - One / Supply of fodder packaging TF / 16134 Post Limited 12,000.00 0.00 Canceled 2017-12-19 2018-02-13 2018-08-12 and forests and biodiversity Quotations Envelope machine conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-39601-GO-RFQ management of rangelands Request for Single Stage - One TF / 16134 Post Limited 500.00 0.00 Canceled 2017-12-25 2018-02-19 2018-08-18 / Supply of forage Seeds and forests and biodiversity Quotations Envelope conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46424-GO-RFQ management of rangelands Request for Single Stage - One / Supply of seeds ( tree seeds TF / 16134 Post Limited 6,250.00 0.00 Canceled 2018-03-27 2018-05-22 2018-11-18 and forests and biodiversity Quotations Envelope ) conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46456-GO-RFQ management of rangelands Request for Single Stage - One / Purchase plastic bags TF / 16134 Post Limited 3,125.00 3,289.58 Completed 2018-03-27 2018-04-09 2018-04-16 2018-04-18 2018-05-06 2018-05-03 and forests and biodiversity Quotations Envelope (polythine tubes) conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46478-GO-RFQ management of rangelands Request for Single Stage - One / Production of Seedling Costs TF / 16134 Post Limited 3,750.00 320.10 Completed 2018-03-22 2018-04-12 2018-04-05 2018-04-26 2018-05-27 2018-06-27 and forests and biodiversity Quotations Envelope Eldowiem Nursery for houses conservation activities in targeted s tates Component 2: Community SD-SSNRMP-46480-GO-RFQ based sustainable / Supply of plastic bags and management of rangelands Request for Single Stage - One TF / 16134 Post Limited 6,250.00 3,289.58 Completed 2018-03-22 2018-04-09 2018-04-05 2018-04-18 2018-05-27 2018-05-03 seedlings for Wad Elsafory and forests and biodiversity Quotations Envelope Nursery at Umrimta Locality conservation activities in targeted s tates Page 5 Component 2: Community based sustainable SD-SSNRMP-46481-GO-RFQ management of rangelands Request for Single Stage - One / Production of Seedling Costs TF / 16134 Post Limited 6,250.00 320.10 Completed 2018-03-22 2018-04-12 2018-04-05 2018-04-26 2018-05-27 2018-06-27 and forests and biodiversity Quotations Envelope Wad Nimir Nursery conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46512-GO-RFQ management of rangelands Request for Single Stage - One / Supply of Energy TF / 16134 Post Limited 5,625.00 1,984.83 Completed 2018-10-07 2018-06-10 2018-10-25 2018-07-30 2018-12-02 2018-08-20 and forests and biodiversity Quotations Envelope alternatives conservation activities in targeted s tates Component 2: Community SD-SSNRMP-48511-GO-RFQ based sustainable / Supply of fruit seedlings & management of rangelands Request for Single Stage - One TF / 16134 Post Limited 3,125.00 0.00 Canceled 2018-06-17 2018-07-05 2018-08-09 improved vegetable seeds for and forests and biodiversity Quotations Envelope Productive homes conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46529-GO-RFQ management of rangelands Request for Single Stage - One / Supply of Wireless TF / 16134 Post Limited 32,887.50 18,426.34 Completed 2018-06-24 2018-09-23 2018-07-12 2018-10-16 2018-07-31 2019-12-04 and forests and biodiversity Quotations Envelope communication system (Solar) conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46530-GO-RFQ management of rangelands Request for Single Stage - One / Supply of Solar system for TF / 16134 Post Limited 15,000.00 7,373.47 Signed 2018-06-24 2018-09-23 2018-07-12 2018-10-16 2018-07-31 and forests and biodiversity Quotations Envelope enclosure building conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46533-GO-RFQ management of rangelands Request for Single Stage - One TF / 16134 Post Limited 10,625.00 9,003.05 Completed 2018-04-01 2018-04-15 2018-04-16 2018-04-26 2018-04-25 2018-05-03 / Supply of office Equipment and forests and biodiversity Quotations Envelope conservation activities in targeted s tates Component 2: Community SD-SSNRMP-46534-GO-RFQ based sustainable / Supply of Motorcycle for management of rangelands Request for Single Stage - One TF / 16134 Post Limited 6,250.00 6,500.00 Completed 2018-06-24 2018-04-19 2018-07-12 2018-04-26 2018-07-31 2018-05-06 Monitoring of wildlife and forests and biodiversity Quotations Envelope enclosure conservation activities in targeted s tates Component 2: Community SD-SSNRMP-46623-GO-RFQ based sustainable / Supply of Monitoring management of rangelands Request for Single Stage - One TF / 16134 Post Limited 34,375.00 0.00 Canceled 2018-05-06 2018-09-23 2018-05-24 2018-06-21 Equipment for Animal inside and forests and biodiversity Quotations Envelope Enclosure conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46633-GO-RFQ management of rangelands Request for Single Stage - One / Supply of wild Animal for TF / 16134 Post Limited 35,000.00 0.00 Canceled 2018-03-20 2018-05-15 2018-11-11 and forests and biodiversity Quotations Envelope Tahdai wildlife enclosure conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46896-GO-RFQ management of rangelands Request for Single Stage - One / Supply of Marikh and TF / 16134 Post Limited 7,500.00 0.00 Canceled 2018-03-16 2018-04-05 2018-05-31 and forests and biodiversity Quotations Envelope Tomam Seedling conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-46898-GO-RFQ management of rangelands Request for Single Stage - One TF / 16134 Post Limited 75,000.00 8,853.55 Completed 2018-03-20 2018-04-09 2018-04-08 2018-04-22 2018-05-31 2018-07-15 / Supply of Tree seeds and forests and biodiversity Quotations Envelope conservation activities in targeted s tates Component 2: Community SD-SSNRMP-46924-GO-RFQ based sustainable / Supply & Collection of management of rangelands Request for Single Stage - One TF / 16134 Post Limited 12,500.00 8,853.55 Completed 2018-03-30 2018-04-09 2018-04-21 2018-04-22 2018-05-31 2018-07-15 Forests Seeds (840 ha.= 2 and forests and biodiversity Quotations Envelope tons) conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-47085-GO-RFQ management of rangelands Request for Single Stage - One / Supply of 6 tons improved TF / 16134 Post Limited 48,000.00 26,730.56 Completed 2018-05-13 2018-07-04 2018-05-31 2018-08-17 2018-07-31 2018-08-17 and forests and biodiversity Quotations Envelope seeds for 1,000 household conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-47088-GO-RFQ management of rangelands Request for Single Stage - One / Supply of Equipments for TF / 16134 Post Limited 11,250.00 9,666.67 Completed 2018-04-08 2018-04-15 2018-04-26 2018-04-26 2018-05-10 2018-05-06 and forests and biodiversity Quotations Envelope youth centers conservation activities in targeted s tates Component 2: Community SD-SSNRMP-47134-GO-RFQ based sustainable / Supply of 2,000 seedlings to management of rangelands Request for Single Stage - One TF / 16134 Post Limited 2,250.00 0.00 Canceled 2018-06-10 2018-07-01 2018-08-30 Improve the school and forests and biodiversity Quotations Envelope Environment conservation activities in targeted s tates Component 2: Community SD-SSNRMP-47156-GO-RFQ based sustainable / Supply of variety seedlings management of rangelands Request for Single Stage - One TF / 16134 Post Limited 7,500.00 0.00 Canceled 2018-06-10 2018-07-01 2018-08-30 to protected the environment and forests and biodiversity Quotations Envelope of the hospital conservation activities in targeted s tates Page 6 Component 2: Community SD-SSNRMP-47173-GO-RFQ based sustainable / Supply of fruit Seedling and management of rangelands Request for Single Stage - One TF / 16134 Post Limited 3,375.00 0.00 Canceled 2018-05-20 2018-06-10 2018-07-31 shade trees for women and forests and biodiversity Quotations Envelope societies conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-47399-GO-RFQ management of rangelands Request for Single Stage - One TF / 16134 Post Limited 10,000.00 3,780.02 Signed 2018-05-07 2018-08-26 2018-05-24 2018-10-16 2018-11-20 / Supply of Improved Stoves and forests and biodiversity Quotations Envelope conservation activities in targeted s tates Component 2: Community SD-SSNRMP-47400-GO-RFQ based sustainable / Supply of home Nursery management of rangelands Request for Single Stage - One TF / 16134 Post Limited 6,250.00 3,289.58 Completed 2018-03-27 2018-04-24 2018-04-15 2018-04-18 2018-05-31 2018-05-03 inputs for Wad araki & Wad and forests and biodiversity Quotations Envelope musa (poly bags & Seeds) conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-47403-GO-RFQ management of rangelands Request for Single Stage - One / Supply of variety vegetable TF / 16134 Post Limited 1,875.00 770.70 Signed 2018-03-18 2018-07-24 2018-04-05 2018-07-31 2018-05-20 and forests and biodiversity Quotations Envelope improved seeds conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-47404-GO-RFQ management of rangelands Request for Single Stage - One TF / 16134 Post Limited 3,000.00 504.00 Signed 2018-07-15 2018-10-15 2018-08-02 2018-10-21 2018-09-02 / Supply of Sewing machines and forests and biodiversity Quotations Envelope conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-47768-GO-RFQ management of rangelands Request for Single Stage - One / Supply of range seeds for TF / 16134 Post Limited 13,125.00 7,650.51 Completed 2018-06-10 2018-04-12 2018-06-28 2018-04-22 2018-07-30 2018-05-16 and forests and biodiversity Quotations Envelope (GA mix+Klatoria+ safar) conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-48461-GO-RFQ management of rangelands Request for Single Stage - One / Purchase and collect of tree TF / 16134 Post Limited 6,250.00 8,853.55 Completed 2018-03-18 2018-04-09 2018-04-05 2018-04-22 2018-05-06 2018-07-15 and forests and biodiversity Quotations Envelope seeds conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-48462-GO-RFQ management of rangelands Request for Single Stage - One / Supply of macaroni TF / 16134 Post Limited 500.00 67.23 Signed 2018-03-18 2018-11-04 2018-04-05 2018-11-07 2018-05-06 and forests and biodiversity Quotations Envelope machines conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-48483-GO-RFQ management of rangelands Request for Single Stage - One / Supply of 6 tons range TF / 16134 Post Limited 22,000.00 16,027.78 Completed 2018-03-20 2018-04-12 2018-04-08 2018-04-22 2018-05-31 2018-05-16 and forests and biodiversity Quotations Envelope Seeds conservation activities in targeted s tates Component 2: Community SD-SSNRMP-100450-GO- based sustainable RFQ / Supply of Forests Seeds management of rangelands Request for Single Stage - One TF / 16134 Post Limited 29,787.23 36,053.12 Completed 2019-03-03 2019-03-17 2019-03-20 2019-04-04 2019-04-21 2019-04-25 for 4600 ha. ( GA=3000, KA= and forests and biodiversity Quotations Envelope 600 and WN= 1000) conservation activities in targeted s tates Component 2: Community SD-SSNRMP-100464-GO- based sustainable RFQ / Supply of Pasture Seeds management of rangelands Request for Single Stage - One TF / 16134 Post Limited 17,021.28 30,933.78 Signed 2019-03-03 2019-03-17 2019-03-20 2019-04-04 2019-04-21 2019-06-20 for 4000 ha ( GA=1500, and forests and biodiversity Quotations Envelope KA=200 and WN=2,300) conservation activities in targeted s tates Component 2: Community SD-SSNRMP-100477-GO- based sustainable RFQ / Supply of plastic bags management of rangelands Request for Single Stage - One TF / 16134 Post Limited 4,000.00 0.00 Canceled 2019-03-03 2019-03-20 2019-04-21 for nursery (Wad Nimir & Wad and forests and biodiversity Quotations Envelope Alsafoury) conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-100481-GO- management of rangelands Request for Single Stage - One RFQ / Supply of Improved TF / 16134 Post Limited 18,723.40 0.00 Canceled 2019-03-03 2019-03-21 2019-04-21 and forests and biodiversity Quotations Envelope seeds for communities conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-100482-GO- management of rangelands Request for Single Stage - One RFQ / Supply of Equipment & TF / 16134 Post Limited 3,191.49 0.00 Canceled 2019-03-18 2019-03-28 2019-04-27 and forests and biodiversity Quotations Envelope fittings for Elsihaiba Haffir conservation activities in targeted s tates Component 2: Community SD-SSNRMP-100514-GO- based sustainable RFQ / Construction of Water management of rangelands Request for Single Stage - One TF / 16134 Post Limited 14,276.60 0.00 Canceled 2019-03-08 2019-03-23 2019-04-25 pipe line for shenateer village and forests and biodiversity Quotations Envelope (3 Km) conservation activities in targeted s tates SD-SSNRMP-101213-GO- Component 3: Project RFQ / supply of Request for Single Stage - One TF / 16134 management, Monitoring and Post Limited 2,000.00 1,276.82 Completed 2019-03-18 2019-12-23 2019-04-03 2019-12-26 2019-04-30 2019-12-30 Communication equipments Quotations Envelope Evaluation (laptop and accessories) Component 2: Community SD-SSNRMP-47405-GO-RFQ based sustainable / Supply of Solar energy cells management of rangelands Request for Single Stage - One for four targeted villages TF / 16134 Post Limited 10,638.30 21,849.12 Signed 2019-03-25 2019-04-18 2019-04-15 2019-04-29 2019-05-16 and forests and biodiversity Quotations Envelope (Mosques and the youth conservation activities in centers) targeted s tates Page 7 SD-SSNRMP-140974-GO- Component 3: Project Request for Single Stage - One RFQ / supply of furniture for TF / A7607 management, Monitoring and Post Limited 17,500.00 12,931.31 Completed 2019-11-14 2020-07-22 2019-12-05 2020-09-03 2019-12-22 2020-09-05 Quotations Envelope North Kordufan state Evaluation SD-SSNRMP-140967-GO- Component 3: Project Request for Single Stage - One RFQ / supply of furniture for TF / A7607 management, Monitoring and Post Limited 17,500.00 12,278.40 Signed 2019-11-14 2020-07-22 2019-12-05 2020-09-03 2019-12-22 Quotations Envelope River Nile state Evaluation SD-SSNRMP-140357-CS- QCBS / Supply of 6 vehicles Component 3: Project UN Agencies for 3 new states (4 Double TF / A7607 management, Monitoring and Post Direct 300,000.00 272,520.06 Signed 2019-11-10 2019-12-01 2019-11-15 2019-12-22 2019-12-12 2020-02-18 2020-03-15 (Direct) Cap pickup 4WD and 2 Land Evaluation cruiser station) SD-SSNRMP-140969-GO- Component 3: Project Request for Single Stage - One RFQ / supply of furniture for TF / A7607 management, Monitoring and Post Limited 17,500.00 12,280.58 Signed 2019-11-14 2020-07-20 2019-12-05 2020-09-03 2019-12-22 Quotations Envelope Northern state Evaluation SD-SSNRMP-140976-GO- Component 3: Project RFQ / supply of IT equipment Request for Single Stage - One TF / A7607 management, Monitoring and Post Limited 30,000.00 54,446.31 Completed 2019-11-14 2020-07-20 2019-11-30 2020-09-01 2019-12-12 2020-09-07 and internet technical Quotations Envelope Evaluation equipment for 3 new states Component 2: Community based sustainable SD-SSNRMP-166427-GO- management of rangelands Request for Single Stage - One RFQ / Supply of water plastic TF / A7607 Post Limited 10,000.00 27,663.04 Signed 2020-06-20 2020-12-02 2020-07-06 2020-12-15 2020-07-31 and forests and biodiversity Quotations Envelope tanks for RN state conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166486-GO- based sustainable Pending RFQ / Supply of Equipment for management of rangelands Request for Single Stage - One TF / 16134 Post Limited 10,000.00 0.00 Implementati 2020-09-18 2020-10-03 2020-10-15 Community Development and forests and biodiversity Quotations Envelope on Center - White Nile state conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166485-GO- based sustainable Pending RFQ / Supply of Equipment for management of rangelands Request for Single Stage - One TF / 16134 Post Limited 10,000.00 0.00 Implementati 2020-09-18 2020-10-03 2020-10-15 Community Development and forests and biodiversity Quotations Envelope on Center - kassala conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166473-GO- based sustainable RFQ / Plastic Bags for women management of rangelands Request for Single Stage - One TF / A7607 Post Limited 8,000.00 46,074.84 Signed 2020-09-12 2020-11-09 2020-09-27 2020-11-17 2020-10-25 home nurseries at the 3 SPIUs and forests and biodiversity Quotations Envelope and for other nurseries conservation activities in targeted s tates SD-SSNRMP-166404-GO- Component 1: Institutional Request for Single Stage - One RFQ / Purchase of devices for TF / A7607 Post Limited 60,000.00 44,079.47 Completed 2020-09-11 2020-11-08 2020-09-25 2020-11-29 2020-10-13 2020-12-07 and Policy Framework Quotations Envelope Geo-portal project Component 2: Community SD-SSNRMP-166474-GO- based sustainable Pending RFQ / Supply of equipment for management of rangelands Request for Single Stage - One TF / 16134 Post Limited 10,000.00 0.00 Implementati 2020-09-18 2020-10-03 2020-10-15 Community Development and forests and biodiversity Quotations Envelope on Center - Geziera conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-166422-GO- management of rangelands Request for Single Stage - One RFQ / Supply of water plastic TF / A7607 Post Limited 10,000.00 27,663.04 Completed 2020-09-18 2020-12-02 2020-10-04 2020-12-15 2020-10-29 2020-12-22 and forests and biodiversity Quotations Envelope tanks for NK conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166786-GO- based sustainable RFQ / Supply of monitoring management of rangelands Request for Single Stage - One TF / 16134 Post Limited 36,000.00 0.00 Canceled 2020-09-20 2020-10-07 2020-11-21 devices for animals - Kassala and forests and biodiversity Quotations Envelope Wildlife conservation activities in targeted s tates Component 2: Community SD-SSNRMP-100485-GO- based sustainable RFQ / Supply of Technical Pending management of rangelands Request for Single Stage - One work requirements for wildlife TF / 16134 Post Limited 8,510.64 0.00 Implementati 2020-11-05 2020-11-22 2020-12-22 and forests and biodiversity Quotations Envelope breeding centre in Geziera on conservation activities in state targeted s tates Component 2: Community SD-SSNRMP-166472-GO- based sustainable Pending RFQ / Fodder packing device management of rangelands Request for Single Stage - One TF / A7607 Post Limited 10,000.00 0.00 Implementati 2020-04-06 2020-04-20 2020-05-10 (fodder packing machine and forests and biodiversity Quotations Envelope on linked with tractor) - RN & NK conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166432-GO- based sustainable Pending RFQ / Purchase of agricultural management of rangelands Request for Single Stage - One TF / A7607 Post Limited 85,000.00 0.00 Implementati 2021-01-06 2021-01-20 2021-02-16 equipment (plaugher, harrow and forests and biodiversity Quotations Envelope on and chezle) for 3 SPIUs conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166429-GO- based sustainable RFQ / Procurement of management of rangelands Request for Single Stage - One TF / A7607 Post Limited 10,000.00 14,367.55 Signed 2020-09-18 2020-11-26 2020-10-05 2020-12-07 2020-11-15 improved seeds, vegetable and forests and biodiversity Quotations Envelope seeds and others for NR state conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166409-GO- based sustainable RFQ / Supply of tree Seeds for management of rangelands Request for Single Stage - One TF / A7607 Post Limited 80,000.00 84,334.63 Completed 2020-04-03 2020-07-02 2020-04-20 2020-08-03 2020-05-31 2020-09-07 forests at 3 new states (15 and forests and biodiversity Quotations Envelope tons) conservation activities in targeted s tates Page 8 Component 2: Community based sustainable SD-SSNRMP-166421-GO- management of rangelands Request for Single Stage - One RFQ / Supply of range Seeds TF / A7607 Post Limited 67,000.00 36,505.08 Completed 2020-04-03 2020-07-02 2020-04-20 2020-08-03 2020-05-31 2020-08-31 and forests and biodiversity Quotations Envelope for 3 new SPIUS; (15 tons) conservation activities in targeted s tates SD-SSNRMP-140985-GO- Component 3: Project Request for Single Stage - One RFQ / purchase Office TF / A7607 management, Monitoring and Post Limited 3,000.00 868.89 Completed 2020-09-21 2020-11-03 2020-10-04 2020-11-09 2020-10-17 2020-11-10 Quotations Envelope Stationery for Northern state Evaluation SD-SSNRMP-140989-GO- Component 3: Project RFQ / purchase Office Request for Single Stage - One TF / A7607 management, Monitoring and Post Limited 3,000.00 983.17 Completed 2020-09-21 2020-11-04 2020-10-05 2020-11-10 2020-10-20 2020-11-10 Stationery for North Kordufan Quotations Envelope Evaluation state office (SPIU) SD-SSNRMP-140996-GO- Component 3: Project RFQ / purchase Office Request for Single Stage - One TF / A7607 management, Monitoring and Post Limited 3,000.00 2,693.75 Completed 2020-09-21 2020-10-13 2020-10-05 2020-10-22 2020-10-20 2020-11-01 Stationery for River Nile state Quotations Envelope Evaluation office (SPIU) SD-SSNRMP-202520-GO- RFQ / Supply and installation Component 3: Project Under Request for Single Stage - One of communication system TF / A7607 management, Monitoring and Post Limited 100,000.00 0.00 Implementati 2020-11-10 2020-11-05 2020-11-29 2020-12-31 Quotations Envelope (video conference system) for Evaluation on PCU & SPIUs Component 2: Community SD-SSNRMP-222353-GO- based sustainable Pending RFQ / Plastic Bags for women management of rangelands Request for Single Stage - One TF / A7607 Post Limited 7,000.00 0.00 Implementati 2021-03-23 2021-04-18 2021-05-18 home nurseries and other and forests and biodiversity Quotations Envelope on nurseries at the 5 SPIUs conservation activities in targeted s tates SD-SSNRMP-222355-GO- Pending RFQ / Supply of Component 1: Institutional Request for Single Stage - One TF / A7607 Post Limited 14,000.00 0.00 Implementati 2021-04-06 2021-05-04 2021-06-03 communication and IT and Policy Framework Quotations Envelope on equipment for Phase III states Component 2: Community based sustainable SD-SSNRMP-222495-GO-RFB Pending management of rangelands Single Stage - One / Rehabilitation of (2) Haffirs TF / A7607 Post Request for Bids Open - National 500,000.00 0.00 Implementati 2021-03-20 2021-03-25 2021-05-06 2021-05-20 2021-06-10 2021-12-07 and forests and biodiversity Envelope (water reservoir)- GD on conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166428-GO- based sustainable RFQ / Procurement of Pending management of rangelands Request for Single Stage - One improved Seeds, vegetable TF / B3244 Post Limited 60,000.00 0.00 Implementati 2021-03-20 2021-04-15 2021-05-31 and forests and biodiversity Quotations Envelope seeds and others for phase II on conservation activities in states targeted s tates Component 2: Community SD-SSNRMP-166430-GO- based sustainable RFQ / Procurement of Pending management of rangelands Request for Single Stage - One improved Seeds, vegetable TF / A7607 Post Limited 40,000.00 0.00 Implementati 2021-03-20 2021-04-15 2021-05-31 and forests and biodiversity Quotations Envelope seeds and others for phase III on conservation activities in states targeted s tates Component 2: Community based sustainable SD-SSNRMP-192962-GO- Pending management of rangelands Request for Single Stage - One RFQ / Supply of (6) vehicles TF / A7607 Post Limited 200,000.00 0.00 Implementati 2021-03-23 2021-04-27 2021-05-31 and forests and biodiversity Quotations Envelope for 2 new states- kH & GD on conservation activities in targeted s tates SD-SSNRMP-223500-GO- Component 3: Project Pending Request for Single Stage - One RFQ / Supply of furniture for TF / A7607 management, Monitoring and Post Limited 30,000.00 0.00 Implementati 2021-04-06 2021-05-04 2021-06-05 Quotations Envelope GD & KH SPIUs Evaluation on SD-SSNRMP-223777-GO- Pending RFQ / Procurement of Component 1: Institutional Request for Single Stage - One TF / A7607 Post Limited 20,000.00 0.00 Implementati 2021-04-16 2021-05-15 2021-06-15 Geoportal equipment for and Policy Framework Quotations Envelope on phase III states NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Community based sustainable SD-SSNRMP-47737-NC-FCA management of rangelands / Rehabilitation of Alshigage TF / 16134 Prior Force Account Direct 8,000.00 0.00 Canceled 2018-05-13 2018-05-20 2018-06-05 2018-07-31 and forests and biodiversity tree Belt conservation activities in targeted s tates CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD-SSNRMP-39577-CS-INDV Individual / Training on Leadership Component 1: Institutional TF / 16134 Post Consultant Limited 3,000.00 1,666.67 Completed 2017-12-10 2017-11-19 2017-12-15 2017-11-19 2018-01-05 2017-12-10 2018-02-09 2017-12-10 2018-08-08 2017-12-14 Development and VDC and Policy Framework Selection Management Page 9 SD-SSNRMP-39583-CS-INDV / Forest Reserved Status Individual Component 1: Institutional encroachment and illegal TF / 16134 Post Consultant Limited 3,000.00 0.00 Canceled 2017-12-14 2017-12-19 2018-01-09 2018-02-13 2018-08-12 and Policy Framework cutting participatory Selection Management SD-SSNRMP-39587-CS-INDV Individual Component 1: Institutional / Training on Types of TF / 16134 Post Consultant Limited 3,000.00 1,383.80 Completed 2017-12-17 2017-12-13 2017-12-22 2017-12-13 2018-01-12 2017-12-18 2018-02-16 2017-12-18 2018-08-15 2017-12-24 and Policy Framework Communication Selection SD-SSNRMP-39589-CS-INDV Individual / Training of 18 members on Component 1: Institutional TF / 16134 Post Consultant Limited 4,000.00 2,048.02 Signed 2017-12-20 2017-12-10 2017-12-25 2017-12-14 2018-01-15 2017-12-25 2018-02-19 2017-12-26 2018-08-18 Community plans for and Policy Framework Selection Environmental protection SD-SSNRMP-39590-CS-INDV Individual / Awareness training of Component 1: Institutional TF / 16134 Post Consultant Limited 4,500.00 4,428.16 Signed 2017-12-25 2017-12-24 2017-12-30 2017-12-31 2018-01-20 2018-01-15 2018-02-24 2018-04-05 2018-08-23 environmental education and and Policy Framework Selection voluntary work ,literacy SD-SSNRMP-47424-CS-INDV Individual / Training Assessment and Component 1: Institutional TF / 16134 Post Consultant Limited 5,000.00 2,520.52 Completed 2018-06-03 2019-01-27 2018-06-08 2019-02-03 2018-06-29 2019-02-07 2018-08-03 2019-02-07 2019-01-30 2019-02-17 capacity Building for Range and Policy Framework Selection and Pasture 15 Inspector SD-SSNRMP-47425-CS-INDV Individual / Training in GPS and GIS( Component 1: Institutional TF / 16134 Post Consultant Limited 6,000.00 2,731.02 Completed 2018-06-17 2018-12-23 2018-06-22 2019-01-01 2018-07-13 2019-01-27 2018-08-17 2019-01-28 2019-02-13 2019-02-14 Range and Pasture 15 and Policy Framework Selection Inspector& Technicians) SD-SSNRMP-47426-CS-INDV Individual Component 1: Institutional / Training on integrated TF / 16134 Post Consultant Limited 4,000.00 2,730.91 Completed 2018-06-24 2019-01-15 2018-06-29 2019-01-20 2018-07-20 2018-08-24 2019-02-13 2019-02-20 2019-02-21 and Policy Framework NRM (Workshop). Selection SD-SSNRMP-47501-CS-INDV Individual Component 1: Institutional / Training on TF / 16134 Post Consultant Limited 4,000.00 2,216.74 Completed 2018-07-01 2019-02-27 2018-07-06 2019-03-03 2018-07-27 2019-03-20 2018-08-31 2019-03-21 2019-02-27 2019-03-31 and Policy Framework Leadership(Workshop) Selection SD-SSNRMP-47505-CS-INDV Individual / Advanced training on Component 1: Institutional TF / 16134 Post Consultant Limited 4,000.00 2,660.09 Completed 2018-07-15 2019-02-03 2018-07-20 2019-02-17 2018-08-10 2019-03-04 2018-09-14 2019-03-07 2019-03-13 2019-03-21 monitoring and EIA (enviro- and Policy Framework Selection impact Assessment). SD-SSNRMP-47507-CS-INDV / Awareness sessions for Individual Component 1: Institutional state stakeholders TF / 16134 Post Consultant Limited 4,500.00 1,680.28 Completed 2018-08-01 2019-01-29 2018-08-06 2019-02-03 2018-08-27 2019-02-11 2018-10-01 2019-02-12 2019-03-30 2019-02-20 and Policy Framework communities on NR Selection sustainability SD-SSNRMP-47510-CS-INDV Individual Component 1: Institutional / Safeguards training for TF / 16134 Post Consultant Limited 3,125.00 0.00 Canceled 2018-08-12 2018-08-17 2018-09-07 2018-10-12 2019-04-10 and Policy Framework communities and partners Selection SD-SSNRMP-47519-CS-INDV Individual Component 1: Institutional / State-of- art on forest TF / 16134 Post Consultant Limited 4,000.00 0.00 Canceled 2018-08-19 2018-08-24 2018-09-14 2018-10-19 2019-04-17 and Policy Framework reserves Selection SD-SSNRMP-47715-CS-INDV Individual Component 1: Institutional / Review of wildlife policy and TF / 16134 Post Consultant Limited 3,000.00 0.00 Canceled 2018-08-23 2018-08-28 2018-09-18 2018-10-23 2019-04-21 and Policy Framework law (Workshop) Selection SD-SSNRMP-47716-CS-INDV Individual Component 1: Institutional / Review and of rangeland law TF / 16134 Post Consultant Limited 3,000.00 0.00 Canceled 2018-09-02 2018-09-07 2018-09-28 2018-11-02 2019-05-01 and Policy Framework (Workshop) Selection SD-SSNRMP-47717-CS-INDV Individual Component 1: Institutional / Solicit the success stories of TF / 16134 Post Consultant Limited 3,000.00 1,050.22 Completed 2018-09-09 2019-02-03 2018-09-14 2019-02-06 2018-10-05 2019-02-21 2018-11-09 2019-02-21 2019-05-08 2019-02-28 and Policy Framework NRM in Africa. Workshop Selection Individual SD-SSNRMP-47719-CS-INDV Component 1: Institutional TF / 16134 Post Consultant Limited 3,000.00 0.00 Canceled 2018-10-01 2018-10-06 2018-10-27 2018-12-01 2019-05-30 / Media campaign on NRM and Policy Framework Selection SD-SSNRMP-47725-CS-INDV Individual Component 1: Institutional / National workshop on TF / 16134 Post Consultant Limited 4,000.00 1,680.35 Completed 2018-06-03 2019-01-06 2018-06-08 2019-01-20 2018-06-29 2019-02-10 2018-08-03 2019-02-10 2019-01-30 2019-02-17 and Policy Framework communication Selection SD-SSNRMP-47726-CS-INDV Individual / Project Geo-Portal (GIS&RS) Component 1: Institutional TF / 16134 Post Consultant Limited 15,000.00 15,628.05 Signed 2018-06-17 2019-02-03 2018-06-22 2019-03-10 2018-07-13 2019-03-31 2018-08-17 2019-04-01 2019-02-13 for M&E (regional, natioal and and Policy Framework Selection local) SD-SSNRMP-47733-CS-INDV Individual / Training women's Component 1: Institutional TF / 16134 Post Consultant Limited 2,000.00 2,520.84 Completed 2018-04-01 2019-01-27 2018-04-08 2019-02-03 2018-04-15 2018-04-22 2019-02-10 2018-05-31 2019-02-17 associations on the value and Policy Framework Selection chain SD-SSNRMP-47764-CS-INDV Individual / Training 90 farms on Component 1: Institutional TF / 16134 Post Consultant Limited 2,000.00 0.00 Canceled 2018-05-20 2018-05-27 2018-06-03 2018-06-10 2018-07-08 technical beams and Water and Policy Framework Selection harvesting Component 3: Project Individual SD-SSNRMP-48503-CS-INDV TF / 16134 management, Monitoring and Post Consultant Limited 48,000.00 4,000.00 Signed 2018-02-11 2014-05-01 2018-02-16 2014-05-01 2018-03-09 2014-05-12 2018-04-13 2017-05-25 2018-10-10 / National Project Coordinator Evaluation Selection SD-SSNRMP-48504-CS-INDV Component 3: Project Individual / Financial Management TF / 16134 management, Monitoring and Post Consultant Limited 30,000.00 2,500.00 Signed 2018-02-11 2014-04-13 2018-02-16 2014-05-01 2018-03-09 2014-05-21 2018-04-13 2017-05-25 2018-10-10 Specialist Evaluation Selection SD-SSNRMP-48506-CS-INDV Component 3: Project Individual / Monitoring&Evaluation TF / 16134 management, Monitoring and Post Consultant Limited 30,000.00 30,000.00 Signed 2018-02-11 2014-12-28 2018-02-16 2015-04-05 2018-03-09 2015-05-21 2018-04-13 2017-05-25 2018-10-10 Specialist Evaluation Selection SD-SSNRMP-48505-CS-INDV Component 3: Project Individual / Procurement &Contracts TF / 16134 management, Monitoring and Post Consultant Limited 30,000.00 30,000.00 Signed 2018-02-20 2016-03-27 2018-02-25 2016-04-01 2018-03-18 2016-04-24 2018-04-22 2017-04-24 2018-10-19 Specialist Evaluation Selection Page 10 SD-SSNRMP-48507-CS-INDV Component 3: Project Individual / Safeguards &community TF / 16134 management, Monitoring and Post Consultant Limited 30,000.00 138.89 Signed 2018-02-20 2018-04-21 2018-02-25 2018-04-22 2018-03-18 2018-09-10 2018-04-22 2018-09-15 2018-10-19 Development Specialist Evaluation Selection Component 2: Community based sustainable SD-SSNRMP-100739-CS- Individual management of rangelands INDV / Educate 9 literacy TF / 16134 Post Consultant Limited 2,000.00 0.00 Canceled 2019-03-24 2019-03-29 2019-04-16 2019-04-25 2019-05-15 and forests and biodiversity classes Selection conservation activities in targeted s tates Component 2: Community SD-SSNRMP-100742-CS- based sustainable Individual INDV / Educational seminars management of rangelands TF / 16134 Post Consultant Limited 2,000.00 0.00 Canceled 2019-04-30 2019-05-05 2019-05-19 2019-05-23 2019-06-16 on the importance of and forests and biodiversity Selection voluntary work and conservation activities in targeted s tates Component 2: Community SD-SSNRMP-100744-CS- based sustainable INDV / Policy Workshop based Individual management of rangelands on Support Policy and TF / 16134 Post Consultant Limited 2,000.00 0.00 Canceled 2019-04-28 2019-05-03 2019-05-16 2019-05-21 2019-06-23 and forests and biodiversity Framework Study Selection conservation activities in recommendations targeted s tates Component 2: Community SD-SSNRMP-101201-CS- based sustainable Individual INDV / Translation of management of rangelands TF / 16134 Post Consultant Limited 4,515.00 0.00 Canceled 2019-04-11 2019-04-16 2019-05-02 2019-05-07 2019-06-21 Monographs into ARABIC and and forests and biodiversity Selection Distribution to Stakeholders conservation activities in targeted s tates Component 2: Community based sustainable SD-SSNRMP-101202-CS- Individual management of rangelands INDV / Production of TF / 16134 Post Consultant Limited 4,680.85 0.00 Canceled 2019-04-11 2019-04-16 2019-05-02 2019-05-07 2019-06-21 and forests and biodiversity Documentary Film Selection conservation activities in targeted s tates Component 2: Community SD-SSNRMP-101203-CS- based sustainable INDV / Organize training Individual management of rangelands programs for specialized user TF / 16134 Post Consultant Limited 6,000.00 0.00 Canceled 2019-05-12 2019-05-17 2019-06-01 2019-06-09 2019-06-30 and forests and biodiversity groups (stakeholders & Selection conservation activities in Communities) targeted s tates SD-SSNRMP-101204-CS- Individual INDV / Capacity Building Component 1: Institutional TF / 16134 Post Consultant Limited 1,500.00 0.00 Canceled 2019-04-08 2019-04-13 2019-04-27 2019-05-04 2019-06-13 Program for wildlife staff - and Policy Framework Selection one workshop SD-SSNRMP-101216-CS- INDV / Environmental and Individual Component 1: Institutional natural resources policy and TF / 16134 Post Consultant Limited 10,000.00 0.00 Canceled 2019-03-31 2019-04-05 2019-04-20 2019-04-24 2019-05-23 and Policy Framework legislative framework (study + Selection validation workshop) SD-SSNRMP-101218-CS- Individual Component 1: Institutional INDV / Advanced TF / 16134 Post Consultant Limited 3,000.00 0.00 Canceled 2019-04-01 2019-04-06 2019-04-21 2019-04-25 2019-05-26 and Policy Framework communication workshop Selection SD-SSNRMP-101221-CS- INDV / Communication study Individual assessment and evaluation Component 1: Institutional TF / 16134 Post Consultant Limited 3,000.00 0.00 Canceled 2019-05-05 2019-05-10 2019-05-24 2019-05-28 2019-06-30 the link between SPIUs and and Policy Framework Selection local communication departments SD-SSNRMP-166780-CS- Individual INDV / consultant to prepare Component 1: Institutional TF / A7607 Post Consultant Limited 3,000.00 0.00 Canceled 2020-10-04 2020-10-09 2020-10-19 2020-10-24 2020-12-31 and Produce short videos on and Policy Framework Selection selected project activities Component 2: Community based sustainable SD-SSNRMP-166783-CS- Individual management of rangelands INDV / Sustainable Land TF / A7607 Post Consultant Limited 30,000.00 30,000.00 Signed 2020-04-01 2020-03-05 2020-04-06 2020-03-15 2020-04-16 2020-07-19 2020-04-22 2020-08-01 2021-04-22 and forests and biodiversity Management (SLM) Consultant Selection conservation activities in targeted s tates SD-SSNRMP-141029-CS- INDV / Prepare specifications Component 3: Project Individual and tender documents for TF / A7607 management, Monitoring and Post Consultant Limited 15,000.00 15,000.00 Signed 2019-11-02 2019-12-08 2019-11-05 2019-12-12 2019-11-17 2019-12-26 2019-11-23 2020-02-09 2020-09-30 construction works (civil Evaluation Selection Engineer consultant) SD-SSNRMP-141036-CS- INDV / prepare training plan, Individual Component 1: Institutional capacity needs assessment TF / A7607 Post Consultant Limited 11,000.00 12,951.75 Signed 2020-04-01 2020-01-19 2020-04-06 2020-02-02 2020-04-18 2020-02-09 2020-04-24 2020-02-10 2020-05-24 and Policy Framework and the schedule of Selection implementation for new states SD-SSNRMP-141016-CS- Individual INDV / Baseline survey study Component 1: Institutional TF / A7607 Post Consultant Limited 14,000.00 0.00 Canceled 2019-11-02 2019-11-28 2019-11-04 2019-12-18 2019-11-16 2019-11-20 2020-01-29 included data collection for and Policy Framework Selection the three new states (SPIUs) SD-SSNRMP-141034-CS- INDV / Prepare specifications Component 3: Project Individual and tender documents for TF / A7607 management, Monitoring and Post Consultant Limited 2,000.00 0.00 Canceled 2019-10-26 2019-11-02 2019-11-09 2019-11-19 2019-12-15 goods (vehicles and Evaluation Selection equipment Engineer and office IT works) SD-SSNRMP-166813-CS- Individual INDV / Baseline survey study Component 1: Institutional TF / A7607 Post Consultant Limited 36,000.00 36,854.00 Signed 2020-03-29 2019-10-27 2020-04-03 2019-12-18 2020-04-17 2020-01-30 2020-04-25 2020-06-17 2020-10-22 included data collection for and Policy Framework Selection the three new states (SPIUs) Component 3: Project Individual SD-SSNRMP-192145-CS- Under TF / A7607 management, Monitoring and Post Consultant Limited 3,600.00 0.00 2020-09-13 2021-01-14 2020-09-18 2021-02-18 2020-09-28 2021-03-09 2020-10-03 2020-12-31 INDV / Procurement Assistant Implementation Evaluation Selection Page 11 SD-SSNRMP-192149-CS- Component 3: Project Individual Under INDV / Communication TF / A7607 management, Monitoring and Post Consultant Limited 3,000.00 0.00 2020-09-13 2021-01-31 2020-09-18 2021-02-18 2020-09-28 2021-03-09 2020-10-02 2020-12-31 Implementation Assistant Evaluation Selection Component 2: Community SD-SSNRMP-166778-CS- based sustainable Individual INDV / Community/Business management of rangelands Pending TF / A7607 Post Consultant Limited 5,000.00 0.00 2020-10-01 2020-10-06 2020-10-16 2020-10-21 2020-12-01 Development Consultant for and forests and biodiversity Implementation Selection 3SPIUs - PI conservation activities in targeted s tates Component 2: Community SD-SSNRMP-166781-CS- based sustainable Individual INDV / Impact assessment management of rangelands Under TF / A7607 Post Consultant Limited 15,000.00 0.00 2020-09-20 2020-09-13 2020-09-25 2020-10-09 2020-10-14 2020-11-23 consultant and environmental and forests and biodiversity Implementation Selection review conservation activities in targeted s tates SD-SSNRMP-141027-CS- INDV / workshops on the Individual Component 1: Institutional Pending results framework and project TF / A7607 Post Consultant Limited 1,500.00 0.00 2021-01-01 2021-01-04 2021-01-16 2021-01-22 2021-02-08 and Policy Framework Implementation logical framework for the new Selection states Component 2: Community SD-SSNRMP-166779-CS- based sustainable INDV / Consultant for Individual management of rangelands Pending Designing of Community TF / A7607 Post Consultant Limited 6,000.00 0.00 2020-09-27 2020-10-02 2020-10-12 2020-10-17 2020-11-27 and forests and biodiversity Implementation integrated Natural Resources Selection conservation activities in plans for 3 SPIUs PI targeted s tates Component 2: Community based sustainable SD-SSNRMP-166782-CS- Individual management of rangelands INDV / Gender assessment TF / A7607 Post Consultant Limited 20,000.00 30,000.00 Signed 2020-09-20 2020-07-05 2020-09-25 2020-07-12 2020-10-07 2020-09-10 2020-10-12 2020-11-01 2020-11-11 and forests and biodiversity study for phase II&III Selection conservation activities in targeted s tates SD-SSNRMP-141025-CS- Individual Component 1: Institutional Pending INDV / Communication TF / A7607 Post Consultant Limited 5,000.00 0.00 2020-10-01 2020-10-04 2020-10-16 2020-10-22 2020-12-22 and Policy Framework Implementation network design Selection SD-SSNRMP-202538-CS- INDV / Consultancy services Individual Component 1: Institutional to conduct Project TF / A7607 Post Consultant Limited 5,000.00 5,000.00 Signed 2020-11-05 2020-09-01 2020-11-10 2020-09-10 2020-12-01 2020-09-26 2020-12-08 2020-10-01 2020-12-31 and Policy Framework Implementation Manual (PIM) Selection update SD-SSNRMP-192969-CS- Component 3: Project Individual Pending INDV / Baseline survey for TF / A7607 management, Monitoring and Post Consultant Limited 50,000.00 0.00 2021-03-14 2021-03-19 2021-04-09 2021-04-18 2021-07-17 Implementation Phase III states Evaluation Selection SD-SSNRMP-223403-CS- Individual Component 1: Institutional Pending INDV / Undertake the capacity TF / A7607 Post Consultant Limited 12,000.00 0.00 2021-03-14 2021-03-19 2021-04-10 2021-04-20 2021-06-19 and Policy Framework Implementation need assessment Phase III Selection SD-SSNRMP-166776-CS- Component 2: Community INDV / Water Harvesting based sustainable Individual techniques training management of rangelands Pending TF / A7607 Post Consultant Limited 6,000.00 0.00 2020-06-13 2020-06-18 2020-06-28 2020-07-04 2020-12-01 programme and and forests and biodiversity Implementation Selection implementation at 5 new conservation activities in SPIUs targeted s tates SD-SSNRMP-223405-CS- Individual INDV / consultant to prepare Component 1: Institutional Pending TF / A7607 Post Consultant Limited 8,000.00 0.00 2021-04-01 2021-04-06 2021-04-27 2021-05-08 2021-11-04 and Produce short videos on and Policy Framework Implementation Selection selected project activities SD-SSNRMP-166775-CS- Individual INDV / Consultant to conduct Component 1: Institutional Pending TF / A7607 Post Consultant Limited 3,000.00 0.00 2021-10-09 2021-10-14 2021-10-28 2021-11-07 2021-12-07 national workshop on and Policy Framework Implementation Selection communication SD-SSNRMP-223406-CS- Component 2: Community INDV / Consultant to conduct based sustainable Individual training of women on management of rangelands Pending TF / A7607 Post Consultant Limited 5,000.00 0.00 2021-03-15 2021-03-20 2021-04-10 2021-04-20 2021-12-30 income-generating activities and forests and biodiversity Implementation Selection one group per each village as conservation activities in the available potentials targeted s tates Component 2: Community SD-SSNRMP-192142-CS- based sustainable INDV / consultant to conduct Individual management of rangelands Pending Awareness Raising & TF / A7607 Post Consultant Limited 3,000.00 0.00 2021-03-25 2021-03-30 2021-04-20 2021-05-01 2021-06-01 and forests and biodiversity Implementation orentation workshops - Kh & Selection conservation activities in GD targeted s tates Component 2: Community SD-SSNRMP-223408-CS- based sustainable Individual INDV / Consultant to conduct management of rangelands Pending TF / A7607 Post Consultant Limited 5,000.00 0.00 2021-09-26 2021-10-01 2021-10-22 2021-11-01 2021-12-31 Environmental Education and forests and biodiversity Implementation Selection Training conservation activities in targeted s tates SD-SSNRMP-223410-CS- Individual INDV / Community Component 1: Institutional Pending TF / A7607 Post Consultant Limited 5,000.00 0.00 2021-03-21 2021-03-26 2021-04-16 2021-04-26 2021-06-30 Procurement Manual and Policy Framework Implementation Selection consultant Component 2: Community SD-SSNRMP-166777-CS- based sustainable INDV / Community plans for Individual management of rangelands Pending environmental protection and TF / A7607 Post Consultant Limited 5,000.00 0.00 2021-03-18 2021-03-23 2021-04-06 2021-04-17 2021-05-31 and forests and biodiversity Implementation the training of 32 members of Selection conservation activities in project committees targeted s tates SD-SSNRMP-223412-CS- INDV / Consultant to conduct Individual Component 1: Institutional Pending capacity building in activate TF / A7607 Post Consultant Limited 5,000.00 0.00 2021-05-09 2021-05-14 2021-06-04 2021-06-14 2021-12-11 and Policy Framework Implementation inter-agency collaboration on Selection NRM at the State level Page 12 SD-SSNRMP-223413-CS- INDV / consultant to Develop training/implementation Individual manuals on topical issues Component 1: Institutional Pending TF / A7607 Post Consultant Limited 5,000.00 0.00 2021-03-25 2021-03-30 2021-04-20 2021-05-01 2021-10-28 (e.g. SWC, water harvesting, and Policy Framework Implementation Selection small scale irrigation, managing of forests, managing of Mayas etc.) SD-SSNRMP-166772-CS- INDV / consultant to produce manuals for SLWM and Individual biodiversity conservation and Component 1: Institutional Pending TF / A7607 Post Consultant Limited 4,000.00 0.00 2021-03-25 2021-03-30 2021-04-13 2021-04-24 2021-06-23 related policies and and Policy Framework Implementation Selection regulations in NRM with special reference to landscape approach SD-SSNRMP-223417-CS- INDV / Consultant to conduct Individual Component 1: Institutional Pending a workshop to assess the TF / B3244 Post Consultant Limited 2,500.00 0.00 2021-03-25 2021-03-30 2021-04-20 2021-05-01 2021-06-01 and Policy Framework Implementation previous Policy Framework Selection Study SD-SSNRMP-166773-CS- INDV / consultant for formulate an effective comprehensive environmental and natural resources policy Individual Component 1: Institutional Pending and legislative framework that TF / A7607 Post Consultant Limited 4,000.00 0.00 2021-03-21 2021-03-26 2021-04-09 2021-04-19 2021-06-19 and Policy Framework Implementation deals with land use and Selection management in an integrated, multi-sector way for the protection and conservation of the NR base SD-SSNRMP-166774-CS- INDV / consultant to conduct workshop for Support the HCENR & NRM Admin of Individual MoANR to strengthen policy Component 1: Institutional Pending TF / A7607 Post Consultant Limited 6,000.00 0.00 2021-04-01 2021-04-06 2021-04-20 2021-05-01 2021-11-30 framework and legislation for and Policy Framework Implementation Selection SLWM and biodiversity conservation on the basis of the assessment and the recommendations SD-SSNRMP-166784-CS- Individual Component 1: Institutional Pending INDV / Consultant to prepare TF / A7607 Post Consultant Limited 4,000.00 0.00 2021-03-28 2021-04-02 2021-04-15 2021-04-25 2021-06-30 and Policy Framework Implementation the policy manuals Selection SD-SSNRMP-223421-CS- INDV / Consultant to conduct Individual training programs for Component 1: Institutional Pending TF / B3244 Post Consultant Limited 5,000.00 0.00 2021-05-01 2021-05-06 2021-05-27 2021-06-06 2021-12-03 specialized user groups: water and Policy Framework Implementation Selection user groups (Mayas, streams, and irrigation water) SD-SSNRMP-223423-CS- INDV / Consultant to conduct Individual training programs for Component 1: Institutional Pending TF / B3244 Post Consultant Limited 5,000.00 0.00 2021-05-01 2021-05-06 2021-05-27 2021-06-06 2021-12-03 specialized user groups: and Policy Framework Implementation Selection livestock & range (communal grazing area) SD-SSNRMP-223427-CS- INDV / Consultant to conduct Individual Component 1: Institutional Pending training programs for TF / B3244 Post Consultant Limited 5,000.00 0.00 2021-05-01 2021-05-06 2021-05-27 2021-06-06 2021-12-03 and Policy Framework Implementation specialized user groups: Selection forestry (fuel wood charcoal) SD-SSNRMP-223433-CS- INDV / Consultant to conduct Individual Component 1: Institutional Pending training programs for TF / B3244 Post Consultant Limited 5,000.00 0.00 2021-05-01 2021-05-06 2021-05-27 2021-06-06 2021-12-03 and Policy Framework Implementation specialized user groups: small Selection business entrepreneurs SD-SSNRMP-223434-CS- Component 2: Community INDV / Consultant to conduct based sustainable Individual Participatory methods to management of rangelands Pending TF / B3244 Post Consultant Limited 5,000.00 0.00 2021-03-15 2021-03-20 2021-04-10 2021-04-20 2021-10-17 identify community needs and and forests and biodiversity Implementation Selection prepare CEAP to produce conservation activities in CAPs’ targeted s tates SD-SSNRMP-223436-CS- Component 2: Community INDV / Consultant for CEAP based sustainable Individual training to support in the management of rangelands Pending TF / A7607 Post Consultant Limited 5,000.00 0.00 2021-05-23 2021-05-30 2021-06-13 2021-06-23 2021-07-31 development and and forests and biodiversity Implementation Selection implementation of Community conservation activities in Action Plans (CAPs) targeted s tates SD-SSNRMP-223437-CS- Individual Component 1: Institutional Pending INDV / IT consultant for PCU TF / B3244 Post Consultant Limited 9,000.00 0.00 2021-03-14 2021-03-19 2021-04-09 2021-04-19 2021-12-30 and Policy Framework Implementation & SPIUs Selection SD-SSNRMP-223440-CS- Component 3: Project Individual Pending INDV / Civil Engineer (Water TF / B3244 management, Monitoring and Post Consultant Limited 8,400.00 0.00 2021-03-17 2021-03-22 2021-04-12 2021-04-22 2021-10-19 Implementation Engineer) for 6 months Evaluation Selection Component 2: Community SD-SSNRMP-223510-CS- based sustainable Individual INDV / Consultant to conduct management of rangelands Pending TF / A7607 Post Consultant Limited 2,000.00 0.00 2021-03-28 2021-04-02 2021-04-20 2021-05-02 2021-12-30 food processing trainings for and forests and biodiversity Implementation Selection (5) states conservation activities in targeted s tates Component 2: Community SD-SSNRMP-223519-CS- based sustainable Individual INDV / Consultant to conduct management of rangelands Pending TF / A7607 Post Consultant Limited 2,000.00 0.00 2021-03-28 2021-04-02 2021-04-20 2021-05-02 2021-12-30 handicraft training at (5) and forests and biodiversity Implementation Selection states conservation activities in targeted s tates Page 13 SD-SSNRMP-223775-CS- Individual INDV / Consultancy services Component 1: Institutional Pending TF / A7607 Post Consultant Limited 10,000.00 0.00 2021-04-01 2021-04-06 2021-04-27 2021-05-08 2021-11-04 of Geoportal project- phase III and Policy Framework Implementation Selection states SD-SSNRMP-223780-CS- Component 3: Project Individual Pending INDV / Civil Engineer TF / A7607 management, Monitoring and Post Consultant Limited 14,400.00 0.00 2021-03-15 2021-03-20 2021-04-10 2021-04-20 2021-12-30 Implementation consultant Evaluation Selection Page 14