The World Bank                                                                                          Implementation Status & Results Report
         Uttarakhand Decentralized Watershed Development II Project (P131235)



Uttarakhand Decentralized Watershed Development II Project (P131235)


 SOUTH ASIA | India | Agriculture and Food Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 15 | ARCHIVED on 16-Dec-2020 | ISR44190 |


 Implementing Agencies: Watershed Management Directorate (WMD), Republic of India, Watershed Management Directorate



 Key Dates


  Key Project Dates

   Bank Approval Date: 31-Mar-2014                                              Effectiveness Date: 15-Jul-2014
   Planned Mid Term Review Date: 18-Feb-2019                                    Actual Mid-Term Review Date: 23-Sep-2019
   Original Closing Date: 30-Sep-2021                                           Revised Closing Date: 30-Sep-2021
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  The objective of the Project is to increase the efficiency of natural resource use and productivity of rainfed agriculture by participating communities
  in selected microwatersheds of the State of Uttarakhand.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Social Mobilization and Participatory Watershed Planning:(Cost $30.00 M)
 Watershed Treatment and Rainfed Area Development:(Cost $90.30 M)
 Enhancing Livelihood Opportunities:(Cost $18.70 M)
 Knowledge Management and Project Coordination:(Cost $31.00 M)

 Overall Ratings

 Name                                                                          Previous Rating                           Current Rating

 Progress towards achievement of PDO                                           Satisfactory                             Satisfactory
 Overall Implementation Progress (IP)                                          Satisfactory                             Moderately Satisfactory
 Overall Risk Rating                                                           Moderate                                 Moderate


 Implementation Status and Key Decisions

  The Project has disbursed US$ 74.40 million (68%) of the Bank’s financing against an original estimation of US$ 109.0 million to be utilized by
  September 30, 2021. The project has performed satisfactorily and could have disbursed more but for the rapid expansion of COVID cases. The
  project is left with 11 months of implementation period, and given the evolving COVID scenario it may require extension to disburse the remaining
  32 per cent of the project budget. To this effect, the project need to expedite implementation pace and execute all planned activities towards
  meeting its outcome targets within the project closure schedule.




12/16/2020                                                                                                                       Page 1 of 9
        The World Bank                                                         Implementation Status & Results Report
        Uttarakhand Decentralized Watershed Development II Project (P131235)




12/16/2020                                                                                    Page 2 of 9
            The World Bank                                                                                        Implementation Status & Results Report
            Uttarakhand Decentralized Watershed Development II Project (P131235)




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                               Rating at Approval                Previous Rating               Current Rating

  Political and Governance                                    --                                Moderate                     Moderate
  Macroeconomic                                               --                                Low                          Low
  Sector Strategies and Policies                              --                                Low                          Low
  Technical Design of Project or Program                      --                                Moderate                     Moderate
  Institutional Capacity for Implementation and
                                                              --                                Moderate                     Moderate
  Sustainability
  Fiduciary                                                   --                                Moderate                     Moderate
  Environment and Social                                      --                                Moderate                     Moderate
  Stakeholders                                                --                                Moderate                     Moderate
  Other                                                       --                                Moderate                     Moderate
  Overall                                                     --                                Moderate                     Moderate



  Results


 PDO Indicators by Objectives / Outcomes



   To increase the efficiency of natural resource use and productivity of rainfed agriculture

    IN00915348
    ►Increase in water discharge (Percentage, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)            End Target

    Value                              0.00                         18.50                         27.00                       25.00

    Date                               01-Apr-2014                  08-May-2020                   30-Sep-2020                30-Sep-2021

                                       Sample sources have already achieved the end target.
   Comments:



12/16/2020                                                                                                                       Page 3 of 9
           The World Bank                                                                                     Implementation Status & Results Report
           Uttarakhand Decentralized Watershed Development II Project (P131235)



    IN00915456
    ►Increase in Biomass (Percentage, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                             0.00                        --                            13.90                      20.00

    Date                              01-Apr-2014                 --                            30-Sep-2020                30-Sep-2021
                                      10% increase in overall dry biomass productivity (above the ground) is estimated in 10,177 Ha of land
                                      under vegetative cover (horticulture and plantation and catchment treatment). This estimation was done in
   Comments:
                                      selected sample packets within the parcel of 10, 177 Ha.

    IN00915457
    ►Increase Ha of rainfed area under irrigation (Number (Thousand), Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                             0.00                        --                            9,102.60                   5,400.00

    Date                              01-Apr-2014                 --                            30-Sep-2020                30-Sep-2021
                                      The gross irrigated area has increased to 3785 Ha with the increase in water availability of 35,713 cum
   Comments:                          through various storate structures as mentioned in the AM

    IN00915458
    ►Increase in productivity in irrigated and rainfed crops (Percentage, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                             0.00                        --                            52.30                      50.00

    Date                              01-Apr-2014                 --                            30-Sep-2020                30-Sep-2021
                                      This indicator measures productivity enhancement of 9 crops (4 Rainfed Crops + 5 Irrigated crops). The
                                      30% increase in productivity stated here as the current value is the average increase in productivity of all
                                      9 crops.
                                      The details of individual crop's productivity increase are stated in AM - Annex -3.
   Comments:
                                      Crop wise increase in productivity (in percentage) is also stated in Annex-3
                                      4 Rainfed Crops - Paddy, Finger Millet, Barnyard Millet and Soya bean.
                                      5 Irrigated Crops - Pea, Tomato, French Beans, Capsicum and Cabbage

    IN00915459
    ►Farmers reached with agricultural assets or services (Number, Corporate)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                             0.00                        49,822.00                     49,822.00                  45,000.00

    Date                              01-Apr-2014                 08-May-2020                   08-May-2020                30-Sep-2021

                                      Value stated below represents households directly benefited through project interventions.
   Comments:

     IN00915460
     Farmers reached with agricultural assets or services - Female (Number, Corporate Supplement)

                                    Baseline                     Actual (Previous)             Actual (Current)            End Target

     Value                          0.00                         28,086.00                     54,984.00                   45,000.00


12/16/2020                                                                                                                     Page 4 of 9
           The World Bank                                                                                       Implementation Status & Results Report
           Uttarakhand Decentralized Watershed Development II Project (P131235)




   Increase in Biomass

    IN00915456
    ►Increase in Biomass (Percentage, Custom)

                                        Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         --                            13.90                      20.00

    Date                               01-Apr-2014                  --                            30-Sep-2020                30-Sep-2021
                                        10% increase in overall dry biomass productivity (above the ground) is estimated in 10,177 Ha of land
                                        under vegetative cover (horticulture and plantation and catchment treatment). This estimation was done in
   Comments:
                                        selected sample packets within the parcel of 10, 177 Ha.



   Increased Ha of rainfed area under irrigation

    IN00915457
    ►Increase Ha of rainfed area under irrigation (Number (Thousand), Custom)

                                        Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         --                            9,102.60                   5,400.00

    Date                               01-Apr-2014                  --                            30-Sep-2020                30-Sep-2021
                                        The gross irrigated area has increased to 3785 Ha with the increase in water availability of 35,713 cum
   Comments:                            through various storate structures as mentioned in the AM



   Increase in productivity in irrigated and rainfed crops

    IN00915458
    ►Increase in productivity in irrigated and rainfed crops (Percentage, Custom)

                                        Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         --                            52.30                      50.00

    Date                               01-Apr-2014                  --                            30-Sep-2020                30-Sep-2021
                                        This indicator measures productivity enhancement of 9 crops (4 Rainfed Crops + 5 Irrigated crops). The
                                        30% increase in productivity stated here as the current value is the average increase in productivity of all
                                        9 crops.
                                        The details of individual crop's productivity increase are stated in AM - Annex -3.
   Comments:
                                        Crop wise increase in productivity (in percentage) is also stated in Annex-3
                                        4 Rainfed Crops - Paddy, Finger Millet, Barnyard Millet and Soya bean.
                                        5 Irrigated Crops - Pea, Tomato, French Beans, Capsicum and Cabbage


 Overall Comments PDO

  COVID crisis did pose few challenges in collecting field data from the sample villages. Yet, third party monitoring agency could manage to get
  most of it. We will further assess these data base once covid situation improves.




12/16/2020                                                                                                                       Page 5 of 9
           The World Bank                                                                                     Implementation Status & Results Report
           Uttarakhand Decentralized Watershed Development II Project (P131235)



 Intermediate Results Indicators by Components



   Social Mobilization and Participatory Watershed Planning

    IN00915461
    ►Percent of participating HHs in the Gram Sabha meetings (Percentage, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                            0.00                         88.50                         88.00                     80.00

    Date                             01-Apr-2014                  08-May-2020                   30-Sep-2020              31-Mar-2021

     IN00915468
     % of which are female (Percentage, Custom Breakdown)

                                    Baseline                     Actual (Previous)            Actual (Current)           End Target

     Value                          0.00                         43.50                        63.40                      50.00

     Date                           01-Apr-2014                  08-May-2020                  30-Sep-2020                31-Mar-2021


   Watershed Treatment and Rainfed Area Development

    IN00915462
    ►Hydrological monitoring systems fully installed and functional in sample MWS (Number, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                            0.00                         8.00                          8.00                      8.00

    Date                             01-Apr-2014                  08-May-2020                   30-Sep-2020              31-Mar-2021

                                      8 units are already installed and functional in selected micro-watersheds.
   Comments:

    IN00915465
    ►Targeted traditional natural water sources rejuvenated (Percentage, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                            0.00                         78.90                         97.00                     30.00

    Date                             01-Apr-2014                  08-May-2020                   30-Sep-2020              31-Mar-2021

    IN00915469
    ►Natural resource conservation techniques adopted in the targeted areas (Percentage, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                            0.00                         35.00                         37.50                     70.00

    Date                             01-Apr-2014                  08-May-2020                   30-Sep-2020              31-Mar-2021

                                      Rate of adoption is sustained despite covid crisis.
   Comments:

    IN00915471


12/16/2020                                                                                                                   Page 6 of 9
           The World Bank                                                                                      Implementation Status & Results Report
           Uttarakhand Decentralized Watershed Development II Project (P131235)




    ►Targeted farmers adopting soil moisture conservation practices and crop production technologies (Percentage, Custom)

                                      Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                           43.62                        62.00                     60.00

    Date                             01-Apr-2014                    08-May-2020                  30-Sep-2020               31-Mar-2021

                                        FIGs have played a major role in helping farmers in increasing rate of adoption.
   Comments:



   Enhancing Livelihood Opportunities

    IN00915463
    ►Farmers organized into (FIGs) (Number, Custom)

                                      Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                           15,161.00                    16,521.00                 10,660.00

    Date                             01-Apr-2014                    08-May-2020                  30-Sep-2020               31-Mar-2021

    IN00915466
    ►Self sustainable FFs (Percentage, Custom)

                                      Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                           50.00                        57.00                     30.00

    Date                             01-Apr-2014                    08-May-2020                  30-Sep-2020               31-Mar-2021

    IN00915470
    ►Vulnerable HHs covered by the vulnerable group activities under GPWDPs. (Number, Custom)

                                      Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                           7,040.00                     9,266.00                  8,895.00

    Date                             01-Apr-2014                    08-May-2020                  30-Sep-2020               31-Mar-2021



   Knowledge Management and Project Coordination

    IN00915464
    ►Target GPs with satisfactory Social Audit using PME regularly (Percentage, Custom)

                                      Baseline                      Actual (Previous)            Actual (Current)          End Target

    Value                            0.00                           100.00                       100.00                    80.00

    Date                             01-Apr-2014                    08-May-2020                  30-Sep-2020               31-Mar-2021
                                        As part of the PME, all targeted GPs have undergone a social audit and such accountability process
   Comments:                            continuing as planned.

    IN00915467




12/16/2020                                                                                                                    Page 7 of 9
           The World Bank                                                                                         Implementation Status & Results Report
           Uttarakhand Decentralized Watershed Development II Project (P131235)




    ►Target GPs with satisfactory financial audit report (Percentage, Custom)

                                      Baseline                      Actual (Previous)               Actual (Current)          End Target

    Value                             0.00                         100.00                           100.00                    100.00

    Date                              01-Apr-2014                  08-May-2020                      30-Sep-2020               31-Mar-2021

                                      All audit reports were reviewed during the recent mission and no discrepancies were reported.
   Comments:


 Overall Comments IR

  Despite the pandemic setback, all four components indicators are showing progressing trends.

  This was a virtual mission and we will undertake an actual mission sometime during the month of February 2021 - with an assumption that the
  covid crisis will me normalized by then.




 Performance-Based Conditions



 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF    Status       Currency        Original   Revised        Cancelled      Disbursed       Undisbursed                % Disbursed


 P131235       IDA-53690         Effective    USD             121.20        121.20           0.00            74.14           36.33                       67%


 Key Dates (by loan)

 Project        Loan/Credit/TF    Status      Approval Date       Signing Date       Effectiveness Date        Orig. Closing Date      Rev. Closing Date

 P131235        IDA-53690         Effective   31-Mar-2014         30-May-2014        15-Jul-2014               30-Sep-2021             30-Sep-2021


Cumulative Disbursements




12/16/2020                                                                                                                          Page 8 of 9
          The World Bank                                                                          Implementation Status & Results Report
          Uttarakhand Decentralized Watershed Development II Project (P131235)




 PBC Disbursement

                                                                                 Achievement   Disbursed amount in     Disbursement %
 PBC ID                   PBC Type     Description         Coc      PBC Amount
                                                                                 Status        Coc                     for PBC




  Restructuring History


  There has been no restructuring to date.


  Related Project(s)


 There are no related projects.




12/16/2020                                                                                                       Page 9 of 9