The World Bank Implementation Status & Results Report Uttarakhand Decentralized Watershed Development II Project (P131235) Uttarakhand Decentralized Watershed Development II Project (P131235) SOUTH ASIA | India | Agriculture and Food Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 15 | ARCHIVED on 16-Dec-2020 | ISR44190 | Implementing Agencies: Watershed Management Directorate (WMD), Republic of India, Watershed Management Directorate Key Dates Key Project Dates Bank Approval Date: 31-Mar-2014 Effectiveness Date: 15-Jul-2014 Planned Mid Term Review Date: 18-Feb-2019 Actual Mid-Term Review Date: 23-Sep-2019 Original Closing Date: 30-Sep-2021 Revised Closing Date: 30-Sep-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the Project is to increase the efficiency of natural resource use and productivity of rainfed agriculture by participating communities in selected microwatersheds of the State of Uttarakhand. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Social Mobilization and Participatory Watershed Planning:(Cost $30.00 M) Watershed Treatment and Rainfed Area Development:(Cost $90.30 M) Enhancing Livelihood Opportunities:(Cost $18.70 M) Knowledge Management and Project Coordination:(Cost $31.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The Project has disbursed US$ 74.40 million (68%) of the Bank’s financing against an original estimation of US$ 109.0 million to be utilized by September 30, 2021. The project has performed satisfactorily and could have disbursed more but for the rapid expansion of COVID cases. The project is left with 11 months of implementation period, and given the evolving COVID scenario it may require extension to disburse the remaining 32 per cent of the project budget. To this effect, the project need to expedite implementation pace and execute all planned activities towards meeting its outcome targets within the project closure schedule. 12/16/2020 Page 1 of 9 The World Bank Implementation Status & Results Report Uttarakhand Decentralized Watershed Development II Project (P131235) 12/16/2020 Page 2 of 9 The World Bank Implementation Status & Results Report Uttarakhand Decentralized Watershed Development II Project (P131235) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Moderate Moderate Macroeconomic -- Low Low Sector Strategies and Policies -- Low Low Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and -- Moderate Moderate Sustainability Fiduciary -- Moderate Moderate Environment and Social -- Moderate Moderate Stakeholders -- Moderate Moderate Other -- Moderate Moderate Overall -- Moderate Moderate Results PDO Indicators by Objectives / Outcomes To increase the efficiency of natural resource use and productivity of rainfed agriculture IN00915348 ►Increase in water discharge (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 18.50 27.00 25.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 30-Sep-2021 Sample sources have already achieved the end target. Comments: 12/16/2020 Page 3 of 9 The World Bank Implementation Status & Results Report Uttarakhand Decentralized Watershed Development II Project (P131235) IN00915456 ►Increase in Biomass (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 13.90 20.00 Date 01-Apr-2014 -- 30-Sep-2020 30-Sep-2021 10% increase in overall dry biomass productivity (above the ground) is estimated in 10,177 Ha of land under vegetative cover (horticulture and plantation and catchment treatment). This estimation was done in Comments: selected sample packets within the parcel of 10, 177 Ha. IN00915457 ►Increase Ha of rainfed area under irrigation (Number (Thousand), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 9,102.60 5,400.00 Date 01-Apr-2014 -- 30-Sep-2020 30-Sep-2021 The gross irrigated area has increased to 3785 Ha with the increase in water availability of 35,713 cum Comments: through various storate structures as mentioned in the AM IN00915458 ►Increase in productivity in irrigated and rainfed crops (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 52.30 50.00 Date 01-Apr-2014 -- 30-Sep-2020 30-Sep-2021 This indicator measures productivity enhancement of 9 crops (4 Rainfed Crops + 5 Irrigated crops). The 30% increase in productivity stated here as the current value is the average increase in productivity of all 9 crops. The details of individual crop's productivity increase are stated in AM - Annex -3. Comments: Crop wise increase in productivity (in percentage) is also stated in Annex-3 4 Rainfed Crops - Paddy, Finger Millet, Barnyard Millet and Soya bean. 5 Irrigated Crops - Pea, Tomato, French Beans, Capsicum and Cabbage IN00915459 ►Farmers reached with agricultural assets or services (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 49,822.00 49,822.00 45,000.00 Date 01-Apr-2014 08-May-2020 08-May-2020 30-Sep-2021 Value stated below represents households directly benefited through project interventions. Comments: IN00915460 Farmers reached with agricultural assets or services - Female (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 28,086.00 54,984.00 45,000.00 12/16/2020 Page 4 of 9 The World Bank Implementation Status & Results Report Uttarakhand Decentralized Watershed Development II Project (P131235) Increase in Biomass IN00915456 ►Increase in Biomass (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 13.90 20.00 Date 01-Apr-2014 -- 30-Sep-2020 30-Sep-2021 10% increase in overall dry biomass productivity (above the ground) is estimated in 10,177 Ha of land under vegetative cover (horticulture and plantation and catchment treatment). This estimation was done in Comments: selected sample packets within the parcel of 10, 177 Ha. Increased Ha of rainfed area under irrigation IN00915457 ►Increase Ha of rainfed area under irrigation (Number (Thousand), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 9,102.60 5,400.00 Date 01-Apr-2014 -- 30-Sep-2020 30-Sep-2021 The gross irrigated area has increased to 3785 Ha with the increase in water availability of 35,713 cum Comments: through various storate structures as mentioned in the AM Increase in productivity in irrigated and rainfed crops IN00915458 ►Increase in productivity in irrigated and rainfed crops (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 52.30 50.00 Date 01-Apr-2014 -- 30-Sep-2020 30-Sep-2021 This indicator measures productivity enhancement of 9 crops (4 Rainfed Crops + 5 Irrigated crops). The 30% increase in productivity stated here as the current value is the average increase in productivity of all 9 crops. The details of individual crop's productivity increase are stated in AM - Annex -3. Comments: Crop wise increase in productivity (in percentage) is also stated in Annex-3 4 Rainfed Crops - Paddy, Finger Millet, Barnyard Millet and Soya bean. 5 Irrigated Crops - Pea, Tomato, French Beans, Capsicum and Cabbage Overall Comments PDO COVID crisis did pose few challenges in collecting field data from the sample villages. Yet, third party monitoring agency could manage to get most of it. We will further assess these data base once covid situation improves. 12/16/2020 Page 5 of 9 The World Bank Implementation Status & Results Report Uttarakhand Decentralized Watershed Development II Project (P131235) Intermediate Results Indicators by Components Social Mobilization and Participatory Watershed Planning IN00915461 ►Percent of participating HHs in the Gram Sabha meetings (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 88.50 88.00 80.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 31-Mar-2021 IN00915468 % of which are female (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 43.50 63.40 50.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 31-Mar-2021 Watershed Treatment and Rainfed Area Development IN00915462 ►Hydrological monitoring systems fully installed and functional in sample MWS (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 8.00 8.00 8.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 31-Mar-2021 8 units are already installed and functional in selected micro-watersheds. Comments: IN00915465 ►Targeted traditional natural water sources rejuvenated (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 78.90 97.00 30.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 31-Mar-2021 IN00915469 ►Natural resource conservation techniques adopted in the targeted areas (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 35.00 37.50 70.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 31-Mar-2021 Rate of adoption is sustained despite covid crisis. Comments: IN00915471 12/16/2020 Page 6 of 9 The World Bank Implementation Status & Results Report Uttarakhand Decentralized Watershed Development II Project (P131235) ►Targeted farmers adopting soil moisture conservation practices and crop production technologies (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 43.62 62.00 60.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 31-Mar-2021 FIGs have played a major role in helping farmers in increasing rate of adoption. Comments: Enhancing Livelihood Opportunities IN00915463 ►Farmers organized into (FIGs) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 15,161.00 16,521.00 10,660.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 31-Mar-2021 IN00915466 ►Self sustainable FFs (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 50.00 57.00 30.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 31-Mar-2021 IN00915470 ►Vulnerable HHs covered by the vulnerable group activities under GPWDPs. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 7,040.00 9,266.00 8,895.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 31-Mar-2021 Knowledge Management and Project Coordination IN00915464 ►Target GPs with satisfactory Social Audit using PME regularly (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 80.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 31-Mar-2021 As part of the PME, all targeted GPs have undergone a social audit and such accountability process Comments: continuing as planned. IN00915467 12/16/2020 Page 7 of 9 The World Bank Implementation Status & Results Report Uttarakhand Decentralized Watershed Development II Project (P131235) ►Target GPs with satisfactory financial audit report (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 100.00 Date 01-Apr-2014 08-May-2020 30-Sep-2020 31-Mar-2021 All audit reports were reviewed during the recent mission and no discrepancies were reported. Comments: Overall Comments IR Despite the pandemic setback, all four components indicators are showing progressing trends. This was a virtual mission and we will undertake an actual mission sometime during the month of February 2021 - with an assumption that the covid crisis will me normalized by then. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P131235 IDA-53690 Effective USD 121.20 121.20 0.00 74.14 36.33 67% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P131235 IDA-53690 Effective 31-Mar-2014 30-May-2014 15-Jul-2014 30-Sep-2021 30-Sep-2021 Cumulative Disbursements 12/16/2020 Page 8 of 9 The World Bank Implementation Status & Results Report Uttarakhand Decentralized Watershed Development II Project (P131235) PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/16/2020 Page 9 of 9