Document of
                                           The World Bank

                                        FOR OFFICIAL USE ONLY
                                                                                   Report No: PAD5010

                            INTERNATIONAL DEVELOPMENT ASSOCIATION

                                             PROJECT PAPER
                                                  ON A
                                    PROPOSED ADDITIONAL GRANT
                                       AND RESTRUCTURING

              IN THE AMOUNT OF SDR 7.5 MILLION FROM CRISIS RESPONSE WINDOW
                               (US$10 MILLION EQUIVALENT)

                              AND A TRUST FUND GRANT
  IN THE AMOUNT OF US$4.53 MILLION FROM THE PAPUA NEW GUINEA AND PACIFIC ISLANDS
                                 UMBRELLA FACILITY

                                     TO THE KINGDOM OF TONGA

                                                FOR THE

                           TONGA SAFE AND RESILIENT SCHOOLS PROJECT


                                              June 2, 2022




 Urban, Resilience And Land Global Practice
 East Asia And Pacific Region


This document has a restricted distribution and may be used by recipients only in the performance of their
official duties. Its contents may not otherwise be disclosed without World Bank authorization.
                   CURRENCY EQUIVALENTS

             Exchange Rate Effective April 30, 2022

                            Currency Unit = Pa’anga (TOP)
                                  TOP 2.3 = US$ 1
                              US$ 1.3443 = SDR 1

                         FISCAL YEAR
                   January 1 - December 31




Regional Vice President: Manuela V. Ferro
      Country Director: Stephen N. Ndegwa
     Regional Director: Benoit Bosquet
     Practice Manager: Ming Zhang
                         Simone Lillian Esler, Andrew James Hurley,
    Task Team Leaders:
                         Janssen Nunes Teixeira
                        ABBREVIATIONS AND ACRONYMS

CERC    Contingent Emergency Response Component
CESMP   Construction Environmental and Social Management Plan
CRW     Crisis Response Window
CSU     Central Services Unit
DA      Designated Account
ESCOP   Environmental and Social Code of Practice
ESCP    Environmental and Social Commitment Plan
ESF     Environment and Social Framework
ESIA    Environment and Social Impact Assessment
ESMP    Environmental and Social Management Plan
FM      Financial Management
GDP     Gross Domestic Product
GoT     Government of Tonga
GRID    Green, Resilient, and Inclusive Development
IRR     Internal Rate of Return
MET     Ministry of Education and Training
MOF     Ministry of Finance
PDO     Project Development Objective
PMU     Project Management Unit
PPIUF   Papua New Guinea and Pacific Islands Umbrella Facility
PREP    Pacific Resilience Program
WASH    Water and Sanitation Hygiene
                                                     TABLE OF CONTENTS



I.    BACKGROUND AND RATIONALE FOR ADDITIONAL FINANCING ........................................ 7
II.   DESCRIPTION OF ADDITIONAL FINANCING ...................................................................... 9
III. KEY RISKS ..................................................................................................................... 12
IV. APPRAISAL SUMMARY .................................................................................................. 12
V. WORLD BANK GRIEVANCE REDRESS .............................................................................. 17
VI SUMMARY TABLE OF CHANGES ..................................................................................... 18
VII DETAILED CHANGE(S) .................................................................................................... 18
VIII. RESULTS FRAMEWORK AND MONITORING ................................................................... 26
      The World Bank
      Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)




BASIC INFORMATION – PARENT (Tonga Safe and Resilient Schools Project - P174434)


 Country                       Product Line             Team Leader(s)
 Tonga                         IBRD/IDA                 Simone Lillian Esler

 Project ID                    Financing Instrument     Resp CC             Req CC         Practice Area (Lead)
 P174434                       Investment Project       SEAU1 (9349)        EACNF (6680)   Urban, Resilience and Land
                               Financing

Implementing Agency: Ministry of Education and Training
 ADD_FIN_TBL1
 Is this a regionally tagged
 project?

 No

 Bank/IFC Collaboration

 No
                                                    Expected
 Approval Date                      Closing Date    Guarantee       Environmental and Social Risk Classification
                                                    Expiration Date
 10-Dec-2021                        30-Sep-2027                      Moderate


Financing & Implementation Modalities     Parent




[ ] Multiphase Programmatic Approach [MPA]                   [✓] Contingent Emergency Response Component (CERC)
[ ] Series of Projects (SOP)                                 [ ] Fragile State(s)
[ ] Performance-Based Conditions (PBCs)                      [✓] Small State(s)
[ ] Financial Intermediaries (FI)                            [ ] Fragile within a Non-fragile Country

[ ] Project-Based Guarantee                                  [ ] Conflict
[ ] Deferred Drawdown                                        [ ] Responding to Natural or Man-made disaster

[ ] Alternate Procurement Arrangements (APA)                 [ ] Hands-on Expanded Implementation Support (HEIS)

Development Objective(s)



                                                                                                                  Page 1 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



i) to enhance the safety and resilience of selected education facilities; and (ii) to improve the quality of data-driven
education management, curricula and assessments in the selected educational programs.


Ratings (from Parent ISR)
                  RATING_DRAFT_NO
                                                                                        Latest ISR

                                                                                       14-Mar-2022

Progress towards achievement of PDO                                                         S

Overall Implementation Progress (IP)                                                        S

Overall ESS Performance                                                                     S

Overall Risk                                                                                M

Financial Management                                                                        S

Project Management                                                                          S

Procurement                                                                                 S

Monitoring and Evaluation                                                                   S




BASIC INFORMATION – ADDITIONAL FINANCING (Additional Financing to the Tonga Safe and Resilient Schools
Project - P178849)
ADDFIN_TABLE
                                                                                           Urgent Need or Capacity
Project ID                   Project Name                  Additional Financing Type
                                                                                           Constraints
P178849                      Additional Financing to the Scale Up                          No
                             Tonga Safe and Resilient
                             Schools Project
Financing instrument         Product line                  Approval Date
Investment Project           IBRD/IDA                      24-Jun-2022
Financing
Projected Date of Full       Bank/IFC Collaboration
Disbursement
30-Sep-2027                  No

Is this a regionally tagged project?
No



                                                                                                                 Page 2 of 38
                         The World Bank
                         Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)




   Financing & Implementation Modalities                     Child




   [ ] Series of Projects (SOP)                                                   [ ] Fragile State(s)

   [ ] Performance-Based Conditions (PBCs)                                        [✓] Small State(s)
   [ ] Financial Intermediaries (FI)                                              [ ] Fragile within a Non-fragile Country

   [ ] Project-Based Guarantee                                                    [ ] Conflict

   [ ] Deferred Drawdown                                                          [✓] Responding to Natural or Man-made disaster
   [ ] Alternate Procurement Arrangements (APA)                                   [ ] Hands-on Expanded Implementation Support (HEIS)

   [ ] Contingent Emergency Response Component (CERC)

Disbursement Summary (from Parent ISR)

                                                           Net
          Source of Funds                                            Total Disbursed     Remaining Balance               Disbursed
                                                   Commitments

          IBRD                                                                                                               %
          IDA                                            15.00                 1.33                      13.21               9.1 %
          Grants                                                                                                             %


          PROJECT FINANCING DATA – ADDITIONAL FINANCING (Additional Financing to the Tonga Safe and Resilient
          Schools Project - P178849)



PROJECT   FINANCING DATA (US$, Millions)
     SUMMARY -NewFi n1




     SUMMARY (Total Financing)

                                                                                                 Proposed Additional         Total Proposed
                                                                         Current Financing
                                                                                                      Financing                Financing
          Total Project Cost                                                           15.00                     14.53                  29.53

          Total Financing                                                              15.00                     14.53                  29.53

                                   of which IBRD/IDA                                   15.00                     10.00                  25.00

          Financing Gap                                                                 0.00                      0.00                    0.00

      DETAILS - Additional Financing
                            NewFinEnh1




                                                                                                                                      Page 3 of 38
    The World Bank
    Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



World Bank Group Financing

   International Development Association (IDA)                                                      10.00
        IDA Grant                                                                                   10.00
Non-World Bank Group Financing

   Trust Funds                                                                                        4.53
        Papua New Guinea and Pacific Islands Umbrella Facility MDTF                                   4.53

IDA Resources (in US$, Millions)

                                   Credit Amount         Grant Amount     Guarantee Amount   Total Amount
Tonga                                        0.00                 10.00               0.00          10.00
  Crisis Response Window
                                             0.00                 10.00               0.00          10.00
  (CRW)
Total                                        0.00                 10.00               0.00          10.00


COMPLIANCE

Policy

Does the project depart from the CPF in content or in other significant respects?
[ ] Yes [ ✔ ] No

Does the project require any other Policy waiver(s)?
[ ] Yes [ ✔ ] No




                                                                                                  Page 4 of 38
                  The World Bank
                  Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



ESStandards




Environmental and Social Standards Relevance Given its Context at the Time of Appraisal
 E & S Standards                                                             Relevance
              Assessment and Management of Environmental and Social Risks and Impacts Relevant

              Stakeholder Engagement and Information Disclosure                             Relevant

              Labor and Working Conditions                                                  Relevant

              Resource Efficiency and Pollution Prevention and Management                   Relevant

              Community Health and Safety                                                   Relevant

              Land Acquisition, Restrictions on Land Use and Involuntary Resettlement       Relevant

              Biodiversity Conservation and Sustainable Management of Living Natural      Relevant
              Resources
              Indigenous Peoples/Sub-Saharan African Historically Underserved Traditional Not Currently Relevant
              Local Communities
              Cultural Heritage                                                           Not Currently Relevant

              Financial Intermediaries                                                      Not Currently Relevant
ESStandardsNote




NOTE: For further information regarding the World Bank’s due diligence assessment of the Project’s potential
environmental and social risks and impacts, please refer to the Project’s Appraisal Environmental and Social Review
Summary (ESRS).

INSTITUTIONAL DATA

Practice Area (Lead)
Urban, Resilience and Land

Contributing Practice Areas
Education

Climate Change and Disaster Screening
This operation has been screened for short and long-term climate change and disaster risks




                                                                                                                     Page 5 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



PROJECT TEAM

Bank Staff
Name                         Role                              Specialization             Unit
                             Team Leader (ADM
Simone Lillian Esler                                           Disaster Risk Management   SEAU1
                             Responsible)
Andrew James Hurley          Team Leader                       Disaster Risk Management   SEAU1
Janssen Edelweiss Nunes
                             Team Leader                       Education                  HEAED
Fernandes Teixeira
Cristiano Costa e Silva      Procurement Specialist (ADM
                                                               Procurement                EEAR2
Nunes                        Responsible)
                             Financial Management
Ha Thuy Tran                                                   Financial Management       EEAG2
                             Specialist (ADM Responsible)
                             Environmental Specialist (ADM
Bonnie Frances Cavanough                                       Environmental Safeguards   SEAE1
                             Responsible)
Georgina Elizabeth
                             Team Member                       DRM                        SEAU1
McArthur
Michelle Marie Dooley        Social Specialist                 Social Safeguards          SEAS1
Miguel Payawal Ferido        Team Member                       ACS Support                EACNF
Minghe Zheng                 Team Member                       Disbursement               WFACS
Nicholas Gerard Williams     Procurement Team                                             EACNF
Zoe Kolovou                  Team Member                       Legal                      LEGAS

Extended Team
Name                         Title                             Organization               Location




                                                                                                     Page 6 of 38
   The World Bank
   Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



I. BACKGROUND AND RATIONALE FOR ADDITIONAL FINANCING

  1. This Project Paper seeks the approval of the Executive Directors to provide an Additional Financing (AF)
     on standard grant terms to the Tonga Safe and Resilient Schools Project (P178849, TSRSP, the Parent
     Project) in the amount of SDR 7.5 million (equivalent to US$10 million) from the International
     Development Association (IDA) Crisis Response Window (CRW), and US$4.53 million from the Papua New
     Guinea and Pacific Islands Umbrella Facility (PPIUF). The proposed Additional Financing (AF) will support
     the Government of Tonga (GoT) in responding to the impact of the Hunga-Tonga-Hunga-Ha’apai (HT-HH)
     volcanic eruption and tsunami of January 15, 2022, and scale up investments to build resilience to climate
     and disaster hazards of school infrastructure in Tonga.

  2. The project will also require a Level II restructuring to: (i) revise the targets of the Results Framework
     indicators for Component 1 to measure the enhanced development impact of the AF; and (ii) revise the
     Financing Agreement to enable the relocation of schools and facilities impacted by the HT-HH disaster
     from high hazard exposure levels to safer locations with reduced exposure to hazards, as under the Parent
     Project, investment eligibility criteria stipulates there are no plans for relocating the facilities outside of
     the existing site boundaries. However, the GoT has requested that the AF supports financing for two
     schools that were significantly impacted by the HT-HH disaster, that will be relocated to areas of less risk,
     and likely incorporated into existing school sites. Therefore, this restructuring will modify the Financing
     Agreement and project description to allow for such relocations, with the applicable eligibility criteria to
     be documented in the Project Operations Manual. The eligibility criteria will include, among others, that
     for any schools which are relocated, their students must have adequate residential proximity to relocated
     or other suitable facilities, or there must be an adequate provision of transport to ensure affected pupils
     have reliable access to relocated or other suitable schools at all times.

  3. Background. Tonga consists of 169 islands in the South Pacific with a total population of around
     104,000. In recent years, Tonga has been hard-hit by several economic and natural shocks, which have
     eroded its fiscal buffers and capacity to respond to further shocks. Tropical Cyclone Gita struck Tonga on
     February 12, 2018 as a Category 4 Tropical Cyclone, and caused equivalent to around 38 percent of
     Tonga’s gross domestic product (GDP). Tropical Cyclone Harold struck on April 9, 2020, resulting in
     significant damages and losses totaling at least 12 percent of GDP. More recently, the January 15, 2022
     HT-HH volcanic eruption and subsequent ashfall and tsunami waves had a devastating impact on the
     country. The tsunami caused widespread damage to buildings, schools, roads, power and water supply
     networks, tourism infrastructure, and agricultural crops, livestock, and fisheries resulting in post-disaster
     recovery and reconstruction needs that significantly exceed the capacity of the GoT to respond.

  4. The HT-HH disaster is estimated to have caused physical damages and economic losses of at least US$182
     million (36.4 percent of GDP). Post-disaster recovery and reconstruction needs significantly exceed the
     capacity of the GoT to respond, with the GoT’s preliminary Recovery and Resilience Building Plan
     estimating that public sector needs are likely to be at least US$165.7 million (33.1 percent of GDP) from
     FY22-FY25. The GoT has elected to draw on a range of financing streams to respond to the disaster,
     including the full drawdown of US$8 million in Catastrophe Draw Down Option financing, and has
     requested US$35 million from the CRW, to be delivered via Additional Financing for two ongoing



                                                                                                                Page 7 of 38
 The World Bank
 Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



   Investment Project Financing operations (including the TSRSP and the Pacific Resilience Project - PREP)
   and Supplemental Financing for a Development Policy Operation. Though there is a Contingent
   Emergency Response Component (CERC) in the Parent Project, the government elected not to trigger this
   instrument, due to the availability of other instruments which would not result in modification or
   reprioritization of the development objective and planned activities of the newly approved Parent Project.
   The GoT is also utilizing over US$21 million in domestic resources, and has accessed over US$24 million in
   support from other development partners. To help close the remaining unmet public financing gap, the
   GoT has requested a US$10 million disbursement from the International Monetary Fund’s Rapid Credit
   Facility, with further support from other development partners (particularly the Asian Development Bank,
   Australia, New Zealand, and the European Union) expected to cover around US$44 million of the unmet
   financing needs in FY23-FY25.

5. Parent Project Status. The Parent Project, TSRSP, financed by an IDA Grant (D927-TO) of SDR10.60 million
   (US$15 million equivalent) was approved on December 9, 2021, and was declared effective on March 8,
   2022. The Project Development Objectives (PDOs) are to: (i) enhance the safety and resilience of selected
   education facilities; and (ii) improve the quality of data-driven education management, curricula and
   assessments in the selected educational programs. The TSRSP has four components: (i) Improving Safety
   and Resilience of Education Facilities; (ii) Establishment of an Education Management Information System
   (“EMIS”) and improved quality of curricula and assessments; (iii) Contingent Emergency Response; and
   (iv) Project Management. The Ministry of Education and Training (MET) is responsible for the overall
   implementation of the project, and is the implementing agency for Components 1, 2 and 4. The Ministry
   of Finance (MoF) is the implementing agency responsible for Component 3.

6. Early implementation activities have been negatively impacted by the HT-HH eruptions and tsunami, and
   Tonga’s first COVID 19 outbreak. Despite these challenges, the Project Management Unit (PMU) has
   completed the recruitments of the Project Manager, Project Engineer, Environmental and Social Officer,
   Procurement Officer and the Finance Officer. Key progress under Component 1 includes preparation of
   the Design and Supervision terms of reference, with bidding for this critical consultancy imminent. For
   Component 2, bidding documents for the procurement of the EMIS and Terms of reference for the
   curriculum and assessment consultants are well advanced. Dated legal Covenants that were due to be
   completed within one month of effectiveness are on track to be delivered with a brief delay, due to the
   impacts of the disaster event and government’s associated diverted resources as they have responded to
   the immediate recovery needs. Though no results have been seen (nor were expected to be seen) thus
   far due to the early stage of implementation, it is envisaged that targets will be met as agreed. US$1.33
   million (9.1 percent) of the Parent Project funds have been disbursed. All Project ratings are currently
   Satisfactory.

7. Rationale of Additional Financing. The impact of HT-HH eruption and tsunami, as well as Tropical Cyclone
   Gita in 2018, have highlighted the vulnerability of school infrastructure in Tonga and the need to improve
   the resilience of the building stock in Tonga to avoid similar impacts to education facilities in the
   future. Twelve schools have been damaged or destroyed by the HT-HH disaster (particularly due to the
   tsunami). All these schools are located on Tongatapu and Ha’apai and their damages range from minor




                                                                                                         Page 8 of 38
   The World Bank
   Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



     to total destruction. The GoT has requested support to repair or rebuild up to 12 of these school facilities
     under the proposed AF.

  8. The proposed AF will support the scale up of Component 1 activities of the Parent Project to enhance
     its development impact through: (i) the climate and disaster resilient recovery of school facilities
     impacted by the HT-HH eruption and tsunami; and (ii) resilient investments in the broader education
     infrastructure portfolio to reduce disaster and climate vulnerabilities from future hazards and more
     frequent adverse weather events.

  9. Higher Level Objectives to which the Project Contributes. The proposed AF is aligned with the GoTs
     Strategic Development Framework (TSDFII) and associated policies and plans for more inclusive and
     sustainable: (i) infrastructure resilient to climate change and extreme events; and (ii) human development
     with gender equality. The proposed AF is also aligned with the World Bank Group’s framework for
     supporting green, resilient, and inclusive development (GRID) in IDA and IBRD countries, and supports the
     three pillars of GRID: (i) Green Development, through sustainable infrastructure investments in education
     facilities; (ii) Resilient Development, through support for risk identification, reduction and residual
     management of risk, along with supporting vulnerable groups (children); and (iii) Inclusive Development,
     through the boosting of human capital through gender and accessibility sensitive investments in water,
     sanitation and hygiene (WASH). The proposed AF is consistent with the World Bank Group’s Pacific Islands
     Regional Partnership Framework (FY17-FY23)1 covering nine Pacific Island countries: Kiribati, the Republic
     of the Marshall Islands (RMI), Federated States of Micronesia (FSM), Republic of Nauru, Republic of Palau,
     Independent State of Samoa, Kingdom of Tonga, Tuvalu, and Vanuatu. It is in line with Focus Area 3 of
     the Regional Partnership Framework: Protecting incomes and livelihoods, through its contribution to the
     achievement of Objective 3.1: Strengthened resilience to natural disasters and climate change. The
     project also aims to ensure strong liaison with other development partners, thus avoiding duplication of
     ongoing efforts and collaborating where possible.

II. DESCRIPTION OF ADDITIONAL FINANCING

 10. The AF will scale up Component 1: Improving Safety and Resilience of Education Facilities activities. This
     will require a corresponding scale up of Component 4: Project Management of the Parent Project. The
     PDO will be amended to reflect the objectives of the Contingent Emergency Response Component (CERC).
     No changes are required to the results chain or indicator descriptions. The targets of the Results
     Framework indicators for Component 1 will be revised upwards to measure the increased development
     impact as a result of the AF.

 11. Project Development Objective: The PDO will be revised to include the CERC related objective as follows:

           (i) to enhance the safety and resilience of selected education facilities; (ii) to improve the quality of
           data-driven education management, curricula and assessments in the selected educational
           programs; and (iii) in case of an Eligible Crisis or Emergency, respond promptly and effectively to it.

     1“World Bank Group. 2017. Regional Partnership Framework: For Kiribati, Republic of Nauru, Republic of The Marshall Islands,
     Federated States of Micronesia, Republic of Palau, Independent State of Samoa, Kingdom of Tonga, Tuvalu, and Vanuatu, FY17-
     FY21. Report Number 100997-EAP.



                                                                                                                              Page 9 of 38
  The World Bank
  Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)




12. Component 1. Improving Safety and Resilience of Education Facilities. The AF will support activities
    under both subcomponents of the Parent Project.

13. Under the AF, Sub-Component 1.1: Resilient Infrastructure Investments will finance:

       a. The carrying out of a program of civil works to repair, retrofit and or reconstruct Approved
          Education Facilities2 damaged or destroyed by the January 15, 2022, tsunami; and (ii) for the
          operations of the Approved Education Facilities including through, inter alia, the purchase and
          distribution of teaching and learning materials, equipment and furniture.

       b. The carrying out of a program of civil works to: (i) construct new Approved Education Facilities; (ii)
          retrofit and strengthen existing Approved Education Facilities; and (iii) undertake minor repair and
          maintenance works.

       c. The carrying out, inter alia, of detailed building-level structural condition assessments,
          geotechnical and other site investigations, feasibility design studies, investment planning, detailed
          engineering designs (incorporating multi-hazard resilience measures as appropriate to site-specific
          exposures), construction supervision and quality assurance, and monitoring of the contractors’
          environmental and social management plans.

14. Under the AF, Sub-component 1.2: Strengthening Education Infrastructure Planning and Maintenance
    will finance a scale up of technical assistance and support to implement the Operation and Maintenance
    program and improved asset management practices in an increased number of schools.

15. Under the AF, Component 4: Project Management will finance the additional Project Management costs
    associated with the scale up of activities under Component 1.

16. Results Framework. Table 1 set summarizes the indicators which will be amended, to reflect the
    increased financing allocated to Component 1.

                                             Table 1: Revisions to Project Indicators

   Indicator                                          Indicator         Original       Revised     Rationale for Change
                                                      Type              Target         Target
   Targeted education facilities constructed or       PDO               30             60          Additional financing allows
   strengthened to improved performance                                                            for more schools to be
   levels to one or more natural hazards                                                           reached.
   (including climate related impacts) (Number)
   Direct beneficiaries with increased safety         PDO               3,000          6,000       Additional financing allows
   from new and strengthened education                                                             for more beneficiaries to be
   facilities (Number, disaggregated by gender)                                                    reached.


   2“Approved Education Facilities” means Education Facilities selected, prioritized, and approved for the purposes of Sub-
   component 1.1 of the Project either in accordance with the Project Operations Manual or as agreed with IDA, if such approval is
   requested prior to the adoption of the Project Operations Manual. As with the Parent Project, these facilities may include both
   government or non-government schools.



                                                                                                                             Page 10 of 38
  The World Bank
  Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



   Detailed engineering designs incorporating    Intermediate   30           60           Additional financing allows
   relevant hazard resilience measures are                                                for more schools to be
   developed (Number)                                                                     reached, necessitating more
                                                                                          designs to be developed.

17. Implementation Arrangements. Since the approval of the parent project, the GoT has advised that the
    Project Steering Committee (PSC) will now be chaired by MET, rather than MOF. The arrangements for
    the PSC will be set out in the Project Operations Manual.

18. Financing. Section VII: Detailed Changes indicates the current and revised component costs as a result of
    the proposed AF which are further broken down below in Table 2. The AF will result in the increase in the
    costs of Component 1 and Component 4 from US$9 million to US$22.56 million and US$1.5 million to
    US$2.5 million respectively.

                                   Table 2: Project Costs and Financing by Component


                              TSRSP Original
                                                      TSRSP Additional Finance (US$M)                TSRSP Total
        Component No.           Financing
                                  (US$M)            CRW              PPIUF             AF Total        (US$M)
               1                     9               9.0             4.53               13.53           22.53
              1.1                   8.8              8.7             4.53               13.23           22.03
              1.2                   0.2              0.3               -                 0.3              0.5
               2                    4.5               -                -                  -              4.5
               3                     0                -                -                  -               0
               4                    1.5              1.0              0.0                1.0             2.5
             Totals                 15               10              4.53               14.53           29.53


19. Closing Date. The closing date will remain unchanged, on September 30, 2027

20. Climate Change. The Additional Financing will further reduce the vulnerability of school infrastructure
    from the impact of increased climate change-induced frequent adverse weather events (including changes
    in precipitation, increased flooding, more intense storm events and tropical cyclones). It will contribute
    to climate resilience and adaptation through the construction and retrofitting of more resilient education
    facilities. It will also provide support to GoT for climate and disaster resilient investment planning,
    improved maintenance, and management of education infrastructure to help better withstand future
    climate change exacerbated weather events. The scale up will also contribute to climate mitigation
    through the use, where feasible, of contextually appropriate renewable energy sources, passive cooling
    options, and energy efficiency for the construction and retrofitting of selected education facilities.

21. Gender. In line with the Parent Project design, the Additional Financing will respond to the specific gender
    needs of beneficiaries under Component 1 by targeting gaps in gender, inclusive of WASH facilities.

22. Climate Co-Benefits. The Parent Project has been screened for short-and-long term climate and disaster
    risks, and was assessed for its contribution to climate change adaptation and mitigation. The scale up of


                                                                                                                Page 11 of 38
       The World Bank
       Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



        Component 1 investments under the AF will further reduce disaster and climate vulnerabilities from more
        frequent adverse weather events and contribute to climate resilience through adaptation and mitigation.
        Additional climate co-benefits will therefore be generated under the AF.

  23. Citizen Engagement. The activities, mechanisms for citizen engagement and beneficiary feedback
      indicators related to Citizen engagement under the Parent Project remain unchanged and will continue to
      apply under the AF.

III.      KEY RISKS

  24. As shown in Section VII: Detailed Changes, the overall risk to achieving the PDO will remain Moderate
      and the ratings of each risk category in the Parent Project’s Systematic Operations Risk Rating Tool table
      will remain unchanged. Institutional capacity for implementation and sustainability, fiduciary, and
      “Other” risks (including COVID-19) continue to be rated Substantial due to ongoing international border
      closures in Tonga and across the Pacific Region. The added risk factors since approval of the parent project
      are the recent COVID-19 outbreak in Tonga, interruptions to global and regional supply chains and the
      evolving risk of further price escalation due to the war in Ukraine. Mitigation measures proposed include
      strengthening of the Project Management Unit, support from the Central Services Unit established under
      the Ministry of Finance, and utilization of local contractors for works contracts, where feasible. The
      remaining risk ratings are unchanged from the parent project. The details of the risks and the
      corresponding risk management measures described in the PAD of the Parent Project continue to apply.

IV.       APPRAISAL SUMMARY

  A. Economic and Financial Analysis

  25. The development impact of the AF can broadly be classified according to the first dividend of the World
      Bank’s Triple Dividend of Resilience Framework, namely avoided losses and saving lives. Additionally, it
      will support the improved operation, maintenance and investment planning for education facilities,
      thereby strengthening the sustainability of project investments.

  26. The proposed AF will extend the total number of educational facilities meeting standards of safety and
      resilience to climatic disasters. As strengthened educational facilities last longer, and the number of
      beneficiaries rise, the monetized value of benefits is expected to significantly rise and outpace projected
      maintenance costs in the future.3 In addition, potential building damage is likely to be reduced in the
      future and the beneficiaries of these school facilities are also likely to bear lower threats to their health
      and life. Furthermore, more schools are expected to be safer and more resilient, implying lower disruption
      to schooling for a larger number of students.

  27. The updated cost-benefit analysis for Component 1-related interventions forecasts a positive Net Present
      Value (NPV) of US$7.46 million, with an associated Internal Rate of Return (IRR) and Benefit-to-Cost Ratio
      of 11.6 percent, and 1.5, respectively. A sensitivity analysis scenario with a 10-percent increase in the

        3Estimates made on a 25 and 50-year time horizon with a 6 percent discount rate, suggest that expected benefits exceed costs of interventions
        (in present value).



                                                                                                                                                Page 12 of 38
  The World Bank
  Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



    Project’s costs and a 10-percent decrease in the Project’s forecasted benefits (i.e., pessimistic scenario)
    stemming from climatic risks (earthquake, flood, etc.) which could be higher than those estimated under
    the base scenario, and other unforeseen or unquantified negative externalities associated with the
    proposed AF Project. As shown in Table 3, the proposed AF Project is economically sound and justifiable
    under both the base and pessimistic case scenarios.

           Table 3. Economic and Financial Analysis of Component 1 Investments (AF and Original budgets)

                                         Budget with AF                          Original Budget
                                                          Total (Over 25 Years)
                               Base Case Scenario      Pessimistic     Base Case Scenario     Pessimistic
                                                        Scenario                               Scenario
               IRR (percent)                 11.6                  8.7               10.5                 6.4
            Discounted cost      US$ 14.82 million   US$ 16.30 million    US$ 5.45 million   US$ 5.99 million
    (present value of costs)
            Present value of     US$ 22.28 million   US$ 20.05 million     US$ 7.59 million     US$ 6.19 million
       incremental benefits
          Net Present Value       US$ 7.46 million    US$ 3.75 million     US$ 2.14 million      US$ 0.2 million
          Benefit/cost ratio                   1.5                1.23                 1.39                1.03
 Source: World Bank estimations based on HIES 2015, Disbursement estimates and vulnerability estimates

B. Technical

28. As per the Parent Project, the nine standard classroom and six cubicle WASH designs developed under
    PREP will generally be used for new construction supported under the AF to minimize risks associated
    with design, supervision, and construction of new buildings. These designs have been updated to: (i)
    consider the local climate; (ii) provide improved ventilation and natural lighting; (iii) provide flexible and
    improved learning environments; and (iv) enhanced seismic and cyclone resilient standards to reduce
    disaster and climate vulnerabilities from more frequent adverse weather events and contribute to climate
    resilience and adaptation. Sub-component 1.2 of the Parent Project will contribute to creating the
    enabling environment for safer and more resilient schools in Tonga by empowering MET and the school
    community to undertake maintenance work through enhanced systems, tools (guidelines/physical tools)
    and capacity building. The AF will enable more schools and community members to be reached by the
    maintenance pilot which will further strengthen the sustainability of the project investments.

C. Financial Management

29. A financial management (FM) assessment of the Parent Project had identified the principal FM risk to be
    the risk of errors and misuse of funds due to the extensive use of spreadsheets to record and report
    project transactions, as well as the limited FM experience of MET. To mitigate the FM risks, the PMU has
    engaged a finance officer and will update the FM instructions in the Project Operations Manual to provide
    step-by-step instructions for project FM functions. The MOF Central Services Unit (CSU) will provide close
    support and training to the Finance Officer, particularly during the early stages of the project. An
    accounting software package (approved by MoF) is expected to be used for all project reporting and
    reconciliations, and to reduce the use of spreadsheets. MET, PMU, CSU, and MoF will meet regularly to



                                                                                                              Page 13 of 38
  The World Bank
  Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



    identify opportunities to integrate the project FM arrangements in the existing GoT systems and
    processes, such for budgeting, contract management, asset management, and reporting. The current
    Designated Account (DA) already opened in Fiji dollars in HFC Bank under the original financing of the
    project will be converted from a ‘segregated’ DA into a ‘pooled’ one for receipts of IDA funds from both
    the original financing and AF only. Such change in classification of DA type has no impact on the project
    and is only for IDA’s disbursement purposes. However, a revised Authorized Signatory Letter covering
    both original financing and AF will be required.

30. Project Disbursement and Fund Flow arrangement. There is no change in the Project Fund Flow and
    Disbursement arrangement for the proposed AF. Following MOF requirement, the AF funds will flow to a
    Project DA in local currency opened in National Reserve Bank of Tonga (NRBT) and then to Project
    Operating Accounts opened in local currency at commercial bank acceptable to the association. The
    Current DA which was already opened in TOP in NBRT for original grant will be converted from a
    ‘segregated’ DA into a ‘pooled’ one for receipts of IDA funds from both the original financing and AF, and
    the PPIUF4 trust fund from the AF only. Such change in the classification of DA type has no impact on the
    project and is only for IDA’s disbursement purposes. The ceiling of the pooled DA will be determined and
    documented in the Disbursement Letter. The Project funds will be disbursed against eligible expenditures
    as set out in the legal agreements. The following four disbursement methods are all available for the
    proposed AF Project: (i) advance; (ii) reimbursement; (iii) direct payment; and (iv) special commitment.
    Supporting documents required for Bank disbursement under different disbursement methods will be
    documented in the Disbursement Letter issued by the World Bank, based on Statements of Expenditures,
    Lists of Payments, and records evidencing eligible expenditures. The disbursement deadline for the
    proposed AF will be four (04) months after the Project AF closing date. IDA funds for this additional
    financing will finance 100 percent of goods, works, non-consulting services and consulting services,
    Training and Workshops and Operating Costs for Components 1 and 4 of the Project, inclusive of tax.
    PPIUF Grant for this additional financing will finance 100 percent of goods, works, non-consulting services,
    and consulting services, Training and Workshops and Operating Costs for Component 1 of the Project,
    inclusive of tax. The Project is jointly financed by IDA Grant and the PPIUF grant, given the earlier closing
    date of the PPIUF grant, to the extent practical, priority needs to be given to disburse the proceeds from
    the PPIUF grant, funds from IDA Grant D9270-TO shall be exhausted first before funds from this IDA grant
    E065-TO utilized.

D. Procurement

31. As per the Parent Project, Procurement under the proposed AF will follow the procedures specified in the
    World Bank Procurement Regulations for IPF Borrowers (November 2020). MET’s PMU will oversee all
    procurement implementation related to the AF. MET has prepared a Project Procurement Strategy for
    Development (PPSD) and the Procurement Plan (PP). The project’s largest investments will be in the
    construction and retrofitting of school buildings. Tonga’s construction industry has structural limitations,
    while foreign contractors are unlikely to be interested due to the high mobilization costs. To mitigate the
    associated risks, the PMU will take a proactive approach to promote business opportunities and ensure

    4 The Project will be co-financed by a recipient executed grant from the Papua New Guinea and Pacific Islands Umbrella Facility
    (PPIUF) in the amount of US$4.53 million (PPIUF Grant No. TF0B8671). The full amount of co-financing has been signed. The
    first tranche of US$3.2 million has been received and reflected in the PPIUF Grant Agreement. The remaining tranche is
    scheduled to be received in August 2022 and will be reflected in the PPIUF Grant Agreement through issuing of an amendment.



                                                                                                                              Page 14 of 38
       The World Bank
       Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



        that the civil works’ program is commensurable with the local contractors’ capacity. The PMU’s capacity
        will be augmented by: (i) the employment of an Engineering Firm to design (including to prepare
        procurement documents) and supervise civil works activities; and (ii) MOF’s CSU providing hands -on
        implementation support. The procurement plan contains 20 different procurement activities estimated
        at US$11.3 million and procurement of civil works represent the largest procurement category, with two
        different activities amounting to US$6.6 million. The scope of civil works activities is yet to be defined as
        the detailed assessment to be undertaken by an Engineering Firm will delineate the number of buildings
        per school site.

E. Legal Operational Policies
.
                                                                     Triggered?

    Projects on International Waterways OP 7.50                          No
    Projects in Disputed Areas OP 7.60                                   No
.

F. Environmental and Social

    32. The environmental and social risks for both the Parent Project and the Additional Financing are assessed
        to be moderate. Environmental and social risk management will be the responsibility of the PMU,
        supported by the CSU E&S Team. Risks and impacts are not likely to be significant, large or complex and
        are expected to be predictable and temporary. Risks are expected to be site specific with low probability
        of serious adverse effects to human health or the environment and easily mitigated in a predictable
        manner.

    33. The project investments will include capacity building and TA activities as well as physical works. Small-
        scale civil works will be undertaken including renovation and construction of classrooms, WASH facilities,
        teachers’ housing, and other facilities (such as halls, dormitories, laboratories, libraries, administration)
        and the construction of ramps and pathways to improve the accessibility of school. An Environmental and
        Social Management Plan (ESMP) was prepared to assess environmental and social risks for these works.
        The ESMP was disclosed on the World Bank’s website on March 31, 2022. The CSU Safeguards Team will
        work with the PMU Project Manager and PMU Environmental and Social officer to ensure that project
        activities are screened and scoped according to the requirements of the ESMP and Environmental and
        Social Commitment Plan (ESCP), which was updated for the AF and re-disclosed in country and on the
        World Bank’s website on May 4, 2022.

    34. Key risks include:

            i.   Occupational health and safety risks;
           ii.   Soil and water risk due to improper management of erosion and sediment controls;
          iii.   Risk associated with the management of hazardous materials;
          iv.    Resource efficiency risks associated with sourcing of materials;
           v.    Risk to air quality via construction dust;
          vi.    Noise impacts; and
         vii.    Construction waste management



                                                                                                                Page 15 of 38
  The World Bank
  Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)




35. The negative environmental impacts directly associated with construction activities will be minor and can
    be readily mitigated via the implementation of mitigation measures outlined in the ESMP. Once specific
    sites for works have been selected a site assessment checklist will be completed to assess site specific
    impacts for the works. This site assessment checklist will also determine the need for contractors to
    prepare a site-specific construction environmental and social management plan (CESMP) or
    environmental and social code of practice (ESCOP) based on the works to be completed at each site and
    the environmental and social risks identified. The CESMP or ESCOP will be prepared by the contractor and
    will consolidate mitigation measures for the sites based on the specific works and construction
    methodology. Operational risks associated with the school facilities include management of operational
    waste and potential fire safety risk.

36. Downstream environmental impacts of Technical Assistance activities have also been considered and the
    environmental risk for these activities is considered to be low. The school community-based operation
    and maintenance capacity building program will require management of occupational and community
    health and safety risk, waste management and hazardous materials management. These risks are
    expected to be readily mitigated through the implementation of an ESCOP for the program which will be
    developed in accordance with Environmental Health and Safety guidelines and good international industry
    practice (GIIP).

37. The overall social impact of the project is expected be positive with improved access to education,
    improved education systems and teaching standards, more resilient public sector buildings with potential
    emergency/ evacuation centers and gender informed WASH facilities included in the outcomes.

38. The key social risks and impacts associated with the project are expected to include:
        i.   Community health and safety due to interactions with construction workers and construction
             equipment;
       ii.   Exposure of workers and building occupants (including school aged children) to potentially
             hazardous materials (such as disturbed asbestos) and dangerous activities (such as machinery)
             before and during demolition and or construction/rehabilitation activities;
      iii.   Child safety and impact to the school community due to the proximity of workers to school
             children and school staff;
      iv.    Impacts of construction impacts such as noise, dust or vibration impacts to the school
             community and students due to the proximity of the buildings to construction works are to take
             place;
       v.    Minor impacts to community or livelihoods due to restricted or temporarily reduced access to
             sites and regular travel routes;
      vi.    Risks to vulnerable groups (poor, disabled, elderly, isolated or ethnic groups) and gender-based
             violence as a result of construction activities and the movement of people;
      vii.   Gender Based Violence (GBV), Sexual Exploitation and Abuse and Sexual Harassment risks during
             construction;
     viii.   The risk of COVID-19 to workers and the school community if community transmission becomes
             apparent;
      ix.    Potential impacts to land, or access to land, during construction and operation of works as a
             result of set down areas; and



                                                                                                        Page 16 of 38
   The World Bank
   Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



        x.   Failure to provide adequate information and involvement in decision-making about the impacts
             of the activities on students and families.

 39. These impacts are considered temporary and minor and will be subject to standard accepted mitigation
     measures to be implemented by the contractor. No major disruption to education services is expected,
     with a staged construction program considering exam periods and students having only minor in-situ
     relocation if at all.

 40. The project’s management of social risks will be guided by the ESMP, which provides a high level
     environmental and social impact assessment for the types of activities to be completed by the project,
     provides mitigation measures relevant to these risks and includes a site specific environmental and social
     site assessment template which must be completed during the design for each site. This approach was
     also used on the PREP Tonga project and will allow for continuity in the risk management process between
     projects and provide the opportunity to build on existing mechanisms and implement lessons learned.

 41. Labor Management Procedures for PMU and contracted workers have been prepared to ensure proper
     working conditions and management of worker relationships, Occupational Health and Safety
     management, and to prevent sexual exploitation and abuse and sexual harassment. A Project COVID
     Safety Protocol would also be developed during project preparation to address COVID-19 Safety risk.

 42. In addition, a project’s Stakeholder Engagement Plan has been prepared to ensure widespread
     engagement with communities and its more vulnerable groups including the elderly, people with
     underlying medical conditions, people with disabilities, and indigenous peoples, among others) - to
     disseminate information related to the project. The SEP was disclosed on the World Bank’s website on
     May 4, 2022.

V. WORLD BANK GRIEVANCE REDRESS

43. Communities and individuals who believe that they are adversely affected by a World Bank supported
    project may submit complaints to existing project-level grievance redress mechanisms or the World Bank’s
    Grievance Redress Service. The Grievance Redress Service ensures that complaints received are promptly
    reviewed in order to address project-related concerns. Project affected communities and individuals may
    submit their complaint to the World Bank’s independent Inspection Panel which determines whether harm
    occurred, or could occur, as a result of World Bank non-compliance with its policies and procedures.
    Complaints may be submitted at any time after concerns have been brought directly to the World Bank's
    attention, and Bank Management has been given an opportunity to respond. For information on how to
    submit complaints to the World Bank’s corporate Grievance Redress Service, please visit
    http://www.worldbank.org/en/projects-operations/products-and-services/grievance-redress-service. For
    information on how to submit complaints to the World Bank Inspection Panel, please visit
    www.inspectionpanel.org




                                                                                                          Page 17 of 38
    The World Bank
    Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)




VI SUMMARY TABLE OF CHANGES

                                                                        Changed                     Not Changed
Project's Development Objectives                                           ✔
Results Framework                                                          ✔
Components and Cost                                                        ✔
Disbursements Arrangements                                                 ✔
Legal Covenants                                                            ✔
Implementing Agency                                                                                       ✔
Loan Closing Date(s)                                                                                      ✔
Cancellations Proposed                                                                                    ✔
Reallocation between Disbursement Categories                                                              ✔
Financial Management                                                                                      ✔
Procurement                                                                                               ✔
Implementation Schedule                                                                                   ✔
Other Change(s)                                                                                           ✔



VII DETAILED CHANGE(S)

PROJECT DEVELOPMENT OBJECTIVE

Current PDO
i) to enhance the safety and resilience of selected education facilities; and (ii) to improve the quality of data-driven
education management, curricula and assessments in the selected educational programs.

Proposed New PDO
To: (i) enhance the safety and resilience of selected education facilities; (ii) improve the quality of data-driven
education management, curricula and assessments in the selected educational programs; and (iii) in case of an
Eligible Crisis or Emergency, respond promptly and effectively to it.




                                                                                                                Page 18 of 38
       The World Bank
       Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



COMPONENTS
Current Component Name              Current Cost Action          Proposed Component        Proposed Cost (US$,
                                  (US$, millions)                Name                                millions)
Component 1: Improving              9,000,000.00 Revised         Component 1:                   22,530,000.00
Safety and Resilience of                                         Improving Safety and
Education Facilities                                             Resilience of Education
                                                                 Facilities
Component 2:                       4,500,000.00 No Change        Component 2:                    4,500,000.00
Establishment of EMIS and                                        Establishment of EMIS
improved quality of                                              and improved quality of
curricula and assessments                                        curricula and
                                                                 assessments
Component 3: Contingent                    0.00 No Change        Component 3:                            0.00
Emergency Response                                               Contingent Emergency
Component                                                        Response Component
Component 4: Project               1,500,000.00 Revised          Component 4: Project            2,500,000.00
Management                                                       Management
TOTAL                             15,000,000.00                                                 29,530,000.00



DISBURSEMENT ARRANGEMENTS
Change in Disbursement Arrangements
Yes


Expected Disbursements (in US$)
DISBURSTBL
Fiscal Year                                Annual                        Cumulative

2022                                       128,840.00                     128,840.00

2023                                       632,290.00                     761,130.00

2024                                       4,845,140.00                   5,606,270.00

2025                                       9,440,790.00                   15,047,060.00

2026                                       9,514,760.00                   24,561,820.00

2027                                       4,603,240.00                   29,165,060.00

2028                                       364,940.00                     29,530,000.00




                                                                                                        Page 19 of 38
           The World Bank
           Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



SYSTEMATIC OPERATIONS RISK-RATING TOOL (SORT)
 Risk Category                                           Latest ISR Rating          Current Rating

 Political and Governance                                    ⚫ Moderate                 ⚫ Moderate
 Macroeconomic                                               ⚫ Moderate                 ⚫ Moderate
 Sector Strategies and Policies                              ⚫ Moderate                 ⚫ Moderate
 Technical Design of Project or Program                      ⚫ Moderate                 ⚫ Moderate
 Institutional Capacity for Implementation and               ⚫ Substantial              ⚫ Substantial
 Sustainability
 Fiduciary                                                   ⚫ Substantial              ⚫ Substantial
 Environment and Social                                      ⚫ Moderate                 ⚫ Moderate
 Stakeholders                                                ⚫ Moderate                 ⚫ Moderate
 Other                                                       ⚫ Substantial              ⚫ Substantial
 Overall                                                     ⚫ Moderate                 ⚫ Moderate


LEGAL COVENANTS1
 LEGAL COVENANTS – Tonga Safe and Resilient Schools Project (P174434)
 Loan/Credit/TF
LEGAL TBL1            Description                               Status                            Action
 IDA-D9270                  Without limitation to the foregoing, the      Not yet due             No Change
                            Recipient shall no later than one (1)
                            month after the Effective Date, and
                            thereafter throughout the Project
                            implementation period, maintain and
                            make available staff from MET, each
                            with skills, qualifications, and experience
                            satisfactory to the Association, for the
                            purposes of implementing Part 2 of the
                            Project in accordance with the
                            provisions of this Agreement and the
                            Project Operations Manual.
 IDA-D9270                  The Recipient shall, no later than one (1)    Not yet due             Revised
                            month after the Effective Date, establish
                            and thereafter maintain, throughout the
                            entire period of implementation of the
                            Project, the Project Steering Committee
                            with terms of reference, composition
                            and resources satisfactory to the
                            Association, which shall be responsible
                            for providing strategic oversight and



                                                                                                              Page 20 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



                      coordination for Project implementation
                      in accordance with the provisions of this
                      Agreement and the Project Operations
                      Manual. To this end, the Project Steering
                      Committee shall be chaired by the
                      Minister for Finance, and shall be
                      comprised of, inter alia, at least one (1)
                      representative of each of the Ministry of
                      Education and Training, the Ministry of
                      Infrastructure, the Ministry of
                      Meteorology, Energy, Information,
                      Disaster Management, Environment,
                      Communications and Climate Change,
                      the Ministry of Internal Affairs, and the
                      Ministry of Lands and Natural Resources.
Proposed              The Recipient shall, no later than one (1)   Complied with
                      month after the Effective Date, establish
                      and thereafter maintain, the Project
                      Steering Committee, with at least one
                      (1) representative of each of the
                      Ministry of Education and Training and
                      the Ministry of Finance, and the
                      remaining composition to be
                      satisfactory to the Association.
IDA-D9270             The Recipient shall, no later than one (1)   Not yet due        Revised
                      month after the Effective Date, establish
                      and thereafter maintain, throughout the
                      entire period of implementation of the
                      Project, the Technical Working Group
                      with terms of reference, composition
                      and resources satisfactory to the
                      Association, which shall be responsible
                      for providing technical and strategic
                      advice and guidance to the Project
                      Management Unit established under
                      Section 1.A.6 of Schedule 1 to this
                      Agreement for Project implementation
                      in accordance with the provisions of this
                      Agreement and the Project Operations
                      Manual. To this end, the Technical
                      Working Group shall be chaired by one
                      (1) representative of the Ministry of
                      Education and Training, and shall be
                      comprised of, inter alia, at least one (1)
                      representative with technical expertise



                                                                                                Page 21 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



                      relevant to the implementation of the
                      Project from each of the Ministry of
                      Finance, the Ministry of Infrastructure,
                      the Ministry of Meteorology, Energy,
                      Information, Disaster Management,
                      Environment, Communications and
                      Climate Change, the Ministry of Lands
                      and Natural Resources, and the Ministry
                      of Internal Affairs.
Proposed              The Recipient shall, no later than one (1)   Complied with
                      month after the Effective Date, establish
                      and thereafter maintain, throughout the
                      entire period of implementation of the
                      Project, the Technical Working Group
                      with terms of reference, composition
                      and resources satisfactory to the
                      Association, which shall be responsible
                      for providing technical and strategic
                      advice and guidance to the Project
                      Management Unit
IDA-D9270             The Recipient shall, no later than one (1)   Complied with      No Change
                      month after the Effective Date, establish
                      and thereafter maintain, throughout the
                      entire period of implementation of the
                      Project, a Project Management Unit
                      (“PMU”) within the Ministry of
                      Education and Training, with terms of
                      reference, composition and resources
                      satisfactory to the Association, which
                      shall be responsible for carrying out day-
                      to-day management and
                      implementation of the Project.
IDA-D9270             The Recipient shall, no later than one (1)   Not yet due        Revised
                      month after the Effective Date, recruit,
                      and thereafter maintain, within the
                      PMU, throughout the entire period of
                      implementation of the Project, at least
                      the following specialists: (i) a Project
                      manager; (ii) a finance officer; (ii) a
                      procurement officer; (iii) an
                      environmental and social officer; and (iv)
                      an engineer, each with terms of
                      reference, qualifications and experience
                      satisfactory to the Association. To this
                      end, the PMU staff shall be responsible


                                                                                                  Page 22 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



                      for, inter alia, carrying out fiduciary
                      aspects of Project management and
                      implementation, financial management,
                      procurement, contract management,
                      environmental and social risk
                      management, monitoring and
                      evaluation, and citizen engagement and
                      communications activities, in accordance
                      with the provisions of this Agreement
                      and the Project Operations Manual.
Proposed              The Recipient shall, no later than one (1) Complied with
                      month after the Effective Date, recruit,
                      and thereafter maintain, within the
                      PMU, throughout the entire period of
                      implementation of the Project, a Project
                      manager with terms of reference,
                      qualifications and experience
                      satisfactory to the Association.
IDA-D9270             The Recipient shall prepare and adopt,      Not yet due         No Change
                      by no later than one (1) month after the
                      Effective Date, a manual, in form and
                      substance acceptable to the Association,
                      setting forth the arrangements and
                      procedures for implementation of the
                      Project.
IDA-D9270             The Recipient shall prepare and furnish     Not yet due         No Change
                      to the Association, at least one (1)
                      month before the date of the Mid-Term
                      Review, a report, in scope and detail
                      satisfactory to the Association and
                      integrating the results of the monitoring
                      and evaluation activities performed
                      pursuant to Section II.2 of this Schedule
                      2 and the General Conditions, on the
                      progress achieved in the carrying out of
                      the Project during the period preceding
                      the date of such report and setting out
                      the measures recommended to ensure
                      the efficient carrying out of the Project
                      and the achievement of the objectives
                      thereof.
IDA-D9270             The Recipient shall prepare and furnish     Complied with       Revised
                      to the Association, by not later than
                      February 1 of each year during the



                                                                                                  Page 23 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



                      implementation of the Project (or such
                      later interval or date as the Association
                      may agree), for the Association’s review
                      and no-objection, an Annual Work Plan
                      and Budget, which shall, inter alia: (a) list
                      all eligible Project activities and Eligible
                      Expenditures proposed to be included in
                      the Project in the Recipient’s following
                      fiscal year; (b) provide a budget for their
                      financing (with a financial plan specifying
                      all sources of financing including the
                      Financing and any other resources
                      provided by the Recipient); and (c)
                      describe the environmental and social
                      safeguards measures taken or planned
                      to be taken in accordance with the
                      provisions of Section I.D of this Schedule
                      2.
Proposed              The Recipient shall prepare and furnish         Complied with
                      to the Association, by not later than
                      February 1 of each year during the
                      implementation of the Project (or such
                      later interval or date as the Association
                      may agree), for the Association’s review
                      and no-objection, an Annual Work Plan
                      and Budget.
IDA-D9270             The Recipient shall furnish to the              Not yet due     No Change
                      Association each Project Report not later
                      than one (1) month after the end of each
                      calendar semester, covering the
                      calendar semester. Except as may
                      otherwise be explicitly required or
                      permitted under this Agreement or as
                      may be explicitly requested by the
                      Association, in sharing any information,
                      report or document related to the
                      activities described in Schedule 1 of this
                      Agreement, the Recipient shall ensure
                      that such information, report or
                      document does not include Personal
                      Data.
IDA-D9270             The Recipient shall carry out, jointly with     Not yet due     No Change
                      the Association, not later than three (3)
                      years after the Effective Date, or such
                      other period as may be agreed with the


                                                                                                  Page 24 of 38
       The World Bank
       Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



                        Association, a mid-term review of the
                        Project (“Mid-Term Review”) to assess
                        the status of Project implementation, as
                        measured against the Project indicators
                        acceptable to the Association, and
                        compliance with the legal covenants
                        included or referred to in this
                        Agreement.
LEGAL COVENANTS2

LEGAL COVENANTS – Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)
Sections and Description
OPS_LEGAL_CONVENANT_CHILD_NODATA
No information available

Conditions
Type                             Financing source       Description
Effectiveness                    Trust Funds            The Grant Agreement has been executed and delivered
                                                        and all conditions precedent to its effectiveness (other
                                                        than the effectiveness of this Agreement) have been
                                                        fulfilled.
Type                             Financing source       Description
Effectiveness                    IBRD/IDA               The Amendment Letter has been executed and delivered
                                                        and all conditions precedent to its effectiveness (other
                                                        than the effectiveness of this Agreement) have been
                                                        fulfilled.




                                                                                                           Page 25 of 38
                          The World Bank
                          Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



                                                                          VIII. RESULTS FRAMEWORK AND MONITORING


                                                                                        Results Framework
                                                                                         COUNTRY: Tonga
 RESULT_NO_PDO                                                 Additional Financing to the Tonga Safe and Resilient Schools Project
Project Development Objective(s)
To: (i) enhance the safety and resilience of selected education facilities; (ii) improve the quality of data-driven education management, curricula and assessments in the
selected educational programs; and (iii) in case of an Eligible Crisis or Emergency, respond promptly and effectively to it.

Project Development Objective Indicators by Objectives/ Outcomes
RESULT_FRAME_TBL_ PD O




                         Indicator Name     PBC Baseline                                              Intermediate Targets                                 End Target
                                                                     1                2                    3               4           5
Targeted education facilities constructed to improved performance levels (Action: This Objective has been Revised)

Targeted education facilities
constructed or
strengthened to improved
performance levels to one                       0.00               0.00              4.00              18.00              35.00       60.00              60.00
or more natural hazards
(including climate related
impacts) (Number)
Action: This indicator has
been Revised

Direct beneficiaries with increased safety from new and strengthened education facilities (Action: This Objective has been Revised)

Direct beneficiaries with
increased safety from new
                                                0.00               0.00              400.00            1,800.00           3,500.00    6,000.00           6,000.00
and strengthened
education facilities




                                                                                                                                                                 Page 26 of 38
                          The World Bank
                          Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)


RESULT_FRAME_TBL_ PD O




                         Indicator Name     PBC Baseline                                              Intermediate Targets              End Target
                                                                     1                2                    3             4      5
(disaggregated by gender)
(Number)
Action: This indicator has
been Revised

Enhance data-driven sector management and decision making

Primary and Secondary
schools using the new EMIS
with up-to-date data in the
system according to                             0.00               0.00              0.00              40.00           60.00   70.00   80.00
established guidelines.
(Percentage)

Quality of curricula and assessments for selected subjects and class levels is improved.

Teachers delivering revised
curricula and assessments                       0.00               0.00              0.00              0.00            60.00   70.00   80.00
(Percentage)
  PDO Table SPACE

Intermediate Results Indicators by Components
RESULT_FRAME_TBL_ IO




                         Indicator Name     PBC Baseline                                              Intermediate Targets              End Target
                                                                     1                2                    3             4      5
Component 1 - Improving Safety and Resilience of Education Facilities (Action: This Component has been Revised)

Detailed engineering
designs incorporating
relevant hazard resilience                      0.00               0.00              6.00              20.00           60.00   60.00   60.00
measures are developed
(Number)




                                                                                                                                               Page 27 of 38
                        The World Bank
                        Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)


RESULT_FRAME_TBL_ IO




                       Indicator Name     PBC Baseline                                              Intermediate Targets                End Target
                                                                   1                2                    3             4       5
Action: This indicator has
been Revised
Pilot school maintenance
plans developed and
implemented for selected                      No                 No                No                Yes             Yes      Yes      Yes
schools (Yes/No)
Strategic School
Infrastructure Management
                                              No                 No                No                Yes             Yes      Yes      Yes
and Development Plan
developed (Yes/No)
Action: This indicator has
been Revised
School Infrastructure
Maintenance Manuals are
delivered and adopted by                      No                 No                No                Yes             Yes      Yes      Yes
MET (Yes/No)
WASH facilities delivered
under the project include
gender and disability                         0.00               0.00              0.00              100.00          100.00   100.00   100.00
accommodating design
(Percentage)
Beneficiaries are satisfied
with the quality of new or
                                              0.00               0.00              70.00             70.00           70.00    70.00    70.00
upgraded education
facilities (Percentage)
Action: This indicator has
been Revised

Component 2 - Establishment of EMIS and improved quality of curricula and assessments

A comprehensive EMIS is
established, and staff are                    No                 No                No                Yes             Yes      Yes      Yes
trained. (Yes/No)




                                                                                                                                                Page 28 of 38
                        The World Bank
                        Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)


RESULT_FRAME_TBL_ IO




                       Indicator Name         PBC Baseline                                          Intermediate Targets                      End Target
                                                                   1                2                    3             4          5
Curricula for the selected
subjects and class levels are                    No              No                Yes               Yes             Yes         Yes         Yes
revised. (Yes/No)
Syllabus, teachers guides,
pupils’ books are
developed, printed, and                          0.00            0.00              0.00              0.00            2.00        4.00        6.00
distributed for school years
1-6. (Number)
Primary schools recorded
sex-disaggregated results
from classroom assessment
and large-scale assessments                      0.00            0.00              0.00              0.00            60.00       80.00       90.00
(Standardized Test of
Achievement of Tonga) in
EMIS. (Percentage)
Teachers are trained to
implement revised
                                                 0.00            0.00              0.00              250.00          500.00      750.00      750.00
curriculum and assessments
(Number)
Teachers with knowledge of
gender-sensitive pedagogy,
including identifying and
referring Gender Based                           0.00            0.00              0.00              175.00          350.00      750.00      525.00
Violence (GBV) and
Violence Against Children
(VAC) (Number)
Students benefiting from
direct interventions to
                                                 0.00            0.00              0.00              5,500.00        11,000.00   17,000.00   17,000.00
enhance learning (CRI,
Number)
                   Students benefiting from
                   direct interventions to       0.00            0.00              0.00              2,600.00        5,200.00    7,800.00    7,800.00
                   enhance learning -




                                                                                                                                                      Page 29 of 38
                        The World Bank
                        Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)


RESULT_FRAME_TBL_ IO




                       Indicator Name     PBC Baseline                                              Intermediate Targets                                           End Target
                                                                   1                  2                  3                  4                           5
                   Female (CRI, Number)

Communities, parents and
students are informed
about the revision of                         No                 No                Yes                Yes                  Yes                         Yes        Yes
curricula and assessments
(Yes/No)

Component 3 - Contingent Emergency Response Component

Immediate response
mechanism established and
ready to provide access to
financial resources in case                   No                 Yes               Yes                Yes                  Yes                         Yes        Yes
of an eligible climate-
related crisis or emergency
(Yes/No)
  IO Table SPACE


                                                                          Monitoring & Evaluation Plan: PDO Indicators      Mapped




                                                                                                                                     Methodology for Data    Responsibility for Data
Indicator Name                                               Definition/Description       Frequency          Datasource
                                                                                                                                     Collection              Collection
                                           This indicator measures the
                                           combined number of new
Targeted education facilities constructed buildings constructed and
or strengthened to improved                the number of                                                     Six monthly
                                                                       Six monthly                                                   Site inspection         MET/PMU
performance levels to one or more          strengthened/retrofitted                                          report
natural hazards (including climate related buildings under sub-
impacts)                                   component 1.1. Education
                                           Facilities is defined as
                                           certain building types


                                                                                                                                                                         Page 30 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



                                             including but not limited to
                                             classrooms, water
                                             sanitation and hygiene
                                             facilities, teachers’ housing
                                             and other facilities that are
                                             essential to school function
                                             (such as halls, dormitories,
                                             laboratories, libraries, and
                                             administration buildings).
                                             These facilities may be in
                                             place at early child
                                             education centers, primary
                                             schools, middle schools,
                                             secondary schools, and
                                             technical and vocational
                                             education and training
                                             facilities located in Tonga.

                                             Delivery or results against
                                             this indicator will enhance
                                             the safety and resilience of
                                             selected education facilities

                                             This indicator measures the
                                             number of total school
                                             children who attend the
                                                                                                     Site inspection and
Direct beneficiaries with increased safety   prioritized schools who                   Six monthly
                                                                         Six monthly                 review of school      MET/PMU
from new and strengthened education          receive new or                            reports
                                                                                                     enrollement records
facilities (disaggregated by gender)         retrofitted/strengthened
                                             education facilities under
                                             sub-component 1.1.
                                             Education Facilities is



                                                                                                                                     Page 31 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



                                          defined as certain building
                                          types including but not
                                          limited to classrooms,
                                          water sanitation and
                                          hygiene facilities, teachers’
                                          housing and other facilities
                                          that are essential to school
                                          function (such as halls,
                                          dormitories, laboratories,
                                          libraries, and
                                          administration buildings).
                                          These facilities may be in
                                          place at early child
                                          education centers, primary
                                          schools, middle schools,
                                          secondary schools, and
                                          technical and vocational
                                          education and training
                                          facilities located in Tonga.
                                          Delivery or results against
                                          this indicator will measure
                                          the number of beneficiaries
                                          with increased safety from
                                          new and strengthened
                                          education facilities
                                                                                                Data collection for this
                                                                                                indicator will include a
Primary and Secondary schools using the
                                                                                                requirement for primary
new EMIS with up-to-date data in the                                      Annual      MET/PMU                              MET/PMU
                                                                                                and secondary schools
system according to established
                                                                                                prepare a short report
guidelines.
                                                                                                on how to use the EMIS
                                                                                                data to improve their



                                                                                                                                     Page 32 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



                                                                                                      performance. MET/PMU
                                                                                                      will conduct a sample-
                                                                                                      based check to see if
                                                                                                      primary and secondary
                                                                                                      schools have prepared a
                                                                                                      short report on how to
                                                                                                      use the EMIS data to
                                                                                                      improve their
                                                                                                      performance.

                                                                                                      Data will be collected for
                                                                                                      measuring the teaching
                                                                                                      of the revised curicula as
                                                                                                      follows:
                                                                                                      Delivery of the revised
                                                                                                      curricula will
                                                                                                      be measured through
                                                                                                      formal classroom
                                                                                                      observations, follow up
                                                                                                      interviews, self-report
Teachers delivering revised curricula and                              Annual         Annual report   inventory and focus        MET/PMU
assessments                                                                                           group interviews
                                                                                                      conducted at waypoints
                                                                                                      throughout the
                                                                                                      project. This will be
                                                                                                      sample based for
                                                                                                      teachers who teach
                                                                                                      Years 1-6 core subjects.
                                                                                                      delivery of the revised
                                                                                                      assessments will be
                                                                                                      measured through
                                                                                                      observation and survey



                                                                                                                                           Page 33 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



                                                                                                     to monitor the
                                                                                                     percentage of schools
                                                                                                     implementing an
                                                                                                     assessment plan, and
                                                                                                     carrying out competency
                                                                                                     based formative and
                                                                                                     summative assessments.

ME PDO Table SPACE


                                               Monitoring & Evaluation Plan: Intermediate Results Indicators   Mapped




                                                                                                    Methodology for Data       Responsibility for Data
Indicator Name                             Definition/Description      Frequency      Datasource
                                                                                                    Collection                 Collection
                                           This indicator measures the
                                           number of detailed
                                           engineering designs that
Detailed engineering designs                                                       Six monthly
                                           are developed under         Six monthly                  Review of deliverables     MET PMU
incorporating relevant hazard resilience                                           reports
                                           component 1.1,
measures are developed
                                           incorporating relevant
                                           standards and hazard
                                           resilience measures
                                                                                                    Review of
                                                                                      Six monthly
Pilot school maintenance plans developed                               Six monthly                  deliverables/trainings     MET PMU
                                                                                      reports
and implemented for selected schools                                                                delivered etc

                                           This indicator measures
                                           that a Strategic School
Strategic School Infrastructure                                                       Six monthly
                                           Infrastructure and          Six monthly                  Review of deliverables     MET PMU
Management and Development Plan                                                       report
                                           Development Plan has
developed
                                           been delivered under
                                           Component 1



                                                                                                                                            Page 34 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



School Infrastructure Maintenance                                                      Six monthly   Review of deliverables,
                                                                         Six monthly                                             MET PMU
Manuals are delivered and adopted by                                                   report        survey
MET
                                                                                                     Design firm outputs
WASH facilities delivered under the                                                    Six monthly
                                                                         Six monthly                 reviewed and reflected      MET/PMU
project include gender and disability                                                  reports
                                                                                                     in six monthly report
accommodating design
                                             This is a Citizen
                                             Engagement indicator
                                             which measures the
                                             satisfaction of Principals or
                                             Head Teachers at Project      Six         Six monthly
Beneficiaries are satisfied with the quality                                                         Surveys                     MET/PMU
                                             Schools supported under       Monthly     reports
of new or upgraded education facilities
                                             Component 1.1 that the
                                             delivered facilities meet
                                             their expectations. Target
                                             is 70% satisfaction of those
                                             surveyed
                                                                                       Six monthly   Deliverable of EMIS and
A comprehensive EMIS is established, and                                 Six monthly                                             MET PMU
                                                                                       report        trainings
staff are trained.
                                                                                       Six monthly
Curricula for the selected subjects and                                  Six monthly                 Deliverables                MET PMU
                                                                                       report
class levels are revised.
                                                                                                     Review of deliverables
Syllabus, teachers guides, pupils’ books                                               Six monthly
                                                                         Six monthly                 and proof of distribution   PMU MET
are developed, printed, and distributed                                                report
                                                                                                     to schools.
for school years 1-6.
Primary schools recorded sex-
disaggregated results from classroom                                     Six monthly EMIS            EMIS                        MET PMU
assessment and large-scale assessments
(Standardized Test of Achievement of


                                                                                                                                           Page 35 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



Tonga) in EMIS.
                                                                                      Six monthly
Teachers are trained to implement                                      Six monthly                   surveys/trainings          MET PMU
                                                                                      report
revised curriculum and assessments
Teachers with knowledge of gender-
                                                                                      Six monthly
sensitive pedagogy, including identifying                              Six monthy                    surveys/trainings          MET PMU
                                                                                      report
and referring Gender Based Violence
(GBV) and Violence Against Children (VAC)
                                                                                   This indicator
                                                                                   will measure
                                                                                   the number of     MET records on student
                                                                                   students who      numbers and those who
Students benefiting from direct                                        Six monthly receive           have received books will   MET PMU
interventions to enhance learning                                                  revised           be included in six-
                                                                                   textbooks,        monthly reporting
                                                                                   based on MET
                                                                                   Records

                                                                                   MET records
                                                                                   on student
                                                                                                     This indicator will
                                                                                   numbers and
                                                                                                     measure the number of
                                                                                   those who
    Students benefiting from direct                                                                  female students who
                                                                       Six monthly have received                                MET PMU
    interventions to enhance learning -                                                              receive revised
                                                                                   books will be
    Female                                                                                           textbooks, based on
                                                                                   included in
                                                                                                     MET Records
                                                                                   six-monthly
                                                                                   reporting

Communities, parents and students are                                                 Reporting in   MET/PMU to monitor
                                                                       Annually                                                 MET PMU
informed about the revision of curricula                                              Six monthly    and collect information
and assessments                                                                       reports        on information sharing



                                                                                                                                          Page 36 of 38
     The World Bank
     Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)



                                                                                                    initiatives and activities
                                                                                                    delivered under the
                                                                                                    project.

Immediate response mechanism
                                                                                      Six monthly
established and ready to provide access                                Six monthly                  Review of deliverable        MET PMU
                                                                                      reports
to financial resources in case of an eligible
climate-related crisis or emergency
 ME IO Table SPACE




                                                                                                                                           Page 37 of 38
The World Bank
Additional Financing to the Tonga Safe and Resilient Schools Project (P178849)




                                                                                 Page 38 of 38