Lessons of Experience | September 2006 | Number 1 38215 External Monitoring of the Chad-Cameroon Pipeline Project D riven by the emerging policy and key issues for designing, implementing requirements of lenders, and operating an external monitoring heightened public concern, and mechanism for complex projects. The the scrutiny of civil society organizations, objectivity and technical expertise of the Lessons of Experience the market is increasingly demanding that external monitor can add value to a project companies adopt responsible and by increasing trust and accountability accountable environmental and social between the sponsor and key project practices. To assist in managing these risks, stakeholders including lenders, project- lenders and project sponsors pursuing affected communities, civil society complex projects in emerging markets may organizations, and government regulators. benefit from the use of an external monitor. The role of the external monitor is to provide To highlight the practical challenges and an independent, impartial, and transparent value of the external monitoring mechanism, record of the sponsor's compliance with the the publication draws illustrative examples project's environmental and social from the experiences of IFC during the commitments. Chad-Cameroon pipeline project. In 2001, IFC required an external monitoring role for A number of challenging project investment the Chad-Cameroon project and appointed conditions may signal the need to consider D'Appolonia S.p.A., a consulting firm from use of an external monitor, including, but Italy, to form the External Compliance not limited to, projects involving: Monitoring Group (ECMG).1 While the scale » multiple public and private sector and complexity of the external monitoring partners for the Chad-Cameroon project is not » highly visible sectors such as natural necessarily indicative of the level of effort resource extraction and resources that would be needed on all » significant population resettlement complex projects, these lessons are a » indigenous peoples valuable source of practical experience with » biodiversity and sensitive habitats external monitoring. This publication has » complex project benefit sharing, revenue management, and governance systems CONTENTS » weak national regulatory regimes. This Lessons of Experience provides lenders 2 What is External Monitoring? and project sponsors with an understanding 2 What are the Benefits for Project of the business case for employing an Stakeholders? external monitor. The publication gives 3 How to Maintain the Independence of practical advice regarding the major steps the External Monitor 4 Key Components of the External Monitoring Mechanism 1 The ECMG reports are published on the following website: www.ifc.org/ecmg 15 Conclusion The client company website can be accessed at: www.essochad.com/Chad/Chad_HomePage.asp 16 Acknowledgements Project-related websites of the World Bank Group can be accessed at: www.worldbank.org/afr/ccproj/; www.ifc.org/ifcext/africa.nsf/Content/ChadCameroonVideo External Monitoring of the Chad-Cameroon Pipeline Project been produced by IFC with the extensive collaboration of specialists from D’Appolonia S.p.A. (see “Acknowledgements” page). What is External Monitoring? D'Appolonia, S.p.A. Monitoring is the sponsor's primary means for tracking and evaluating progress toward the implementation of commitments designed to avoid or mitigate the environmental and social impacts of the project. These actions are Preparation for pipeline welding. typically specified in the sponsor's Environmental and Social Management Program (ESMP). The ESMP details the procedures and actions necessary to prevent What are the Benefits for or manage the adverse impacts identified in the project's social and environmental impact Project Stakeholders? assessment. This program is commonly For lenders, the external monitor is an implemented by an “Environment and Social important tool to objectively verify and Management Unit” (hereafter referred to as the report on sponsor compliance with “E & S Unit”) within a sponsor's management environmental and social conditions of the structure. investment agreement during project development. The financial sustainability of The role of the external monitor is to provide a project can be jeopardized if agreed field-based verification of project activities environmental and social measures are not and ensure compliance by the sponsor with demonstrated to have been credibly the commitments established in the ESMP. implemented by the sponsor. Lenders with On projects with potentially significant limited in-house environmental and social environmental and social impacts that are expertise may benefit from the external diverse, irreversible, or unprecedented, IFC monitor's ability to act in part as the “eyes requires that sponsors retain qualified and and ears” of the lender, fostering a proactive experienced external experts to verify their 2 management approach to help the lender monitoring information. develop successful projects and avoid reputational damage and related liabilities. Funded and logistically supported by the sponsor, the external monitor acts as an For project sponsors, the external monitor impartial layer of monitoring that increases the sponsor's ability to document, complements the sponsor’s internal monitoring manage, and reduce their risk exposure to systems. In addition, the project may be environmental and social issues. By providing subject to additional oversight conducted additional technical expertise to supplement directly by the staff of lenders, government the sponsor's E & S Unit, the external monitor regulators, and civil society groups. increases the operational capacity of the sponsor's management to take timely actions to improve performance and comply 2 The IFC requirement for external monitoring by qualified experts is contained in Performance Standard 1, paragraph 24. Full text of with environmental and social commitments. Performance Standard 1 is available at www.ifc.org/envsocstandards. The Equator Principles II defines a broadly similar requirement as part of Principle 9: Independent Monitoring and Reporting. Full text of the Equator Principles is available at: http://www.equator-principles.com/documents/ Page Two Equator_Principles.pdf Lessons of Experience | September 2006 | Number 1 The Chad-Cameroon Pipeline Project The Chad-Cameroon project is a US$3.5 billion development of an oil field in Chad by a consortium headed by ExxonMobil, and a 1,070 km long pipeline extending through Chad and Cameroon to the Atlantic coast, constructed and operated by the Tchad Oil Transportation Company S.A. (TOTCO) and the Cameroon Oil The external Transportation Company S.A. (COTCO) monitor provides (hereafter collectively referred to as the “Consortium”). Funded and logistically an impartial and D'Appolonia S.p.A supported by the Consortium, the ECMG serves transparent record as the external monitoring team responsible for auditing the implementation of the Consortium's of the sponsor’s environmental and social commitments for the compliance with Chad-Cameroon Oil Pipeline project. Pipeline trenching in Cameroon. the project’s environmental and social The risk for sponsors whose projects are affected communities, are typically shared by commitments. associated with poor environmental and the sponsor and various levels of government. social performance extends beyond damage to the corporate brand. With respect to project affected communities Underperforming companies can lose their and civil society groups, the external monitor license to operate along with the critical provides a team of qualified technical experts support of project-affected communities. that can directly investigate and report on Their products and services may incur specific issues of concern for the local barriers to market entry from consumers and communities in the project area. It provides regulators, and their ability to raise capital reporting that can be an independent source from lenders may be constrained. The of information for local communities and technical expertise of the external NGOs, which in turn serves to foster an monitor allows sponsors to have atmosphere of trust required for effective documented, independently verified, and working relationships. publicly available reports of their actions—a critical, unbiased record which can be used to defend against potential allegations of How to Maintain the poor environmental and social performance. Independence of the The benefit of external monitoring for host External Monitor countries is the availability, at no cost, of an expert team that provides regular, objective Maintaining impartiality, objectivity, and monitoring of project compliance with transparency in the eyes of all project applicable regulations and with other stakeholders is critical to the success of the environmental and social requirements, as external monitor. However, the reliance of the agreed with the sponsor at the outset of the external monitor on the financial and logistical project. The external monitor may be support of the sponsor may create perceptions particularly useful in helping to coordinate of bias. A number of steps should be taken to joint technical solutions where responsibilities, proactively reassure project stakeholders as to such as community health issues in project the independence of the monitor, including: Page Three External Monitoring of the Chad-Cameroon Pipeline Project » establishing a robust and transparent site visit monitoring process by the external monitor that demonstrates a reliance on field-based empirical findings » creating a well defined reporting process for which the external monitor has ultimate responsibility for final content » establishing and abiding by clear D'Appolonia S.p.A operational protocols which define the relationship of the external monitor to other project stakeholders and allow the external monitor to avoid conflicts of ECMG Public Health Specialist consulting with community healers. interest. These issues, among others, are discussed in further detail below. During the project construction phase of the Chad-Cameroon project, the ECMG was composed of six permanent members, Key Components of the including a team leader, expert in pipeline External Monitoring engineering and related health and safety Mechanism issues; a team coordinator, specialist in environmental science and engineering; and individual specialists in socio-economic Structure of the External and socio-cultural issues, institutional Monitoring Team development, environmental and social capacity building, earth sciences, and Environmental and social issues on projects public health. are often interrelated, a fact reinforced by current international best practice for This varied composition of the ECMG integrated environmental and social impact created a strong internal dialogue during the assessment and management. In order to review of specific findings from the properly address the environmental and standpoint of different disciplines. In addition, social issues of complex projects, it is the multifaceted team provided technical recommended that the external monitoring expertise and credibility to a wide range of team be multidisciplinary in composition. issues when engaging with all interested parties, including IFC, the Consortium, the host governments, and civil society Visit to tree nursery. organizations. During IFC's selection of firms to act as the ECMG, the expert technical capabilities demonstrated by D'Appolonia, the firm eventually selected, was cited by the Consortium as a key factor in convincing them that the ECMG would be able to add tangible value to the project. D'Appolonia S.p.A It is important to note that during the initial planning phase the key individuals comprising the external monitoring team Page Four Lessons of Experience | September 2006 | Number 1 may not have full knowledge of all the project's technical issues. Accordingly, it may be helpful to create an understanding between lenders and the sponsor to allow the team to be complemented by additional specialized experts for unplanned issues which may arise during project development. Maintaining D'Appolonia S.p.A On the Chad-Cameroon project, this flexibility impartiality, allowed for the addition of a cultural heritage expert to the ECMG who helped identify and objectivity, and mitigate key gaps in the Consortium's Revegetation of the pipeline right-of-way in the Atlantic Littoral transparency management of impacts to cultural heritage Forest of Cameroon. in the eyes of sites during construction of the pipeline. Incidents of inadequate management of all project heritage sites along the pipeline route resulted stakeholders is in a retroactive non-compliance citation by During construction, the ECMG also added critical to the the lenders against the Consortium. Further an ecologist who provided key input into the incidents that may have resulted in costly management of invasive species and overall success of the project delays were avoided due to the bio-restoration issues along the pipeline route. external monitor. dialogue between the ECMG and the Additionally, the presence of a public health Consortium's E & S Unit, which allowed for the expert on the team played an important role identification and management of potential in facilitating joint approaches to managing cultural heritage impacts. the occupational health issues of employees and the larger community health issues faced by communities and government authorities. Operational Protocols of the Lesson 1 — “An integrated External Monitor environmental and social approach facilitates effective monitoring.” The formulation of operational protocols may » The effectiveness of the external monitor is be helpful to clearly establish the role and greatly improved by mobilizing an integrated interaction of the external monitor with and technically capable environmental and respect to other project stakeholders. On the social team. Chad-Cameroon project, the operational » This integration allows the external monitor to interact with the sponsor and provide expert protocols promoted the need for active evaluation of environmental and social issues, cooperation between the ECMG and and to foster engagement with project- Consortium's E & S Unit. The responsibility to affected communities, government, and civil provide objective, external reporting on ESMP society organizations. compliance to IFC and the lender group » Flexibility to expand the external monitor based on accurate data and empirical team to confront new, unplanned issues is findings was defined as the exclusive helpful, but should be carefully considered to responsibility of the ECMG. For host country ensure unnecessary costs for the project sponsor are avoided. governments and related agencies, the » Consulting the sponsor during the selection of protocols reinforced that the ECMG was not the external monitor provides a key meant to replace, but rather to complement, opportunity to build trust in the technical effective project monitoring by government capability of the external monitor. regulators. Page Five External Monitoring of the Chad-Cameroon Pipeline Project significant logistical resources and Lesson 2 — “Clear operational cooperation from the sponsor and protocols are critical to the all project stakeholders. The sponsor should perception of independence expect an initial period of start-up and impartiality of the external adjustments, particularly with respect to the monitor.” establishment of a working relationship between the sponsor’s E & S Unit and the » Clear operational protocols allow the external monitoring team. external monitor to avoid conflicts of interest and maintain a position of independence with project stakeholders and affected The upfront costs incurred by the sponsor communities. employing the external monitor are not » Once established, every effort should be insignificant. These costs, however, should be made to ensure that all project stakeholders weighed against the potential costs from are aware of, and abide by, the operational project delays, environmental and social protocols governing the activities of the liabilities, corporate brand damage, external monitor. potential litigation, and community upheaval that can emerge as complex projects are sited and constructed. With respect to interactions with civil society, the ECMG was defined as an independent At the end of the two year construction entity readily available to listen to civil phase of the Chad-Cameroon project, the society concerns provided they could direct ECMG cost to the Consortium was identify specific grievances or complaints approximately $US1.5 million for the labor that could be investigated in the field. In and travel expenses of quarterly site visits, practice, it proved difficult to ensure that the and an additional $US 2 million budgeted by ECMG did not become a parallel grievance the Consortium to provide technical and mechanism for the project. Early in the logistical support for the ECMG. Annual project it was therefore necessary to make ECMG site visits during the operations phase clear that the ECMG would not respond to cost approximately $US100,000 per visit. The generalities, such as “pipeline construction is total direct costs of labor, travel, technical, going to deteriorate the quality of life for the and logistical support of the ECMG are local villagers”. However, specific technical estimated at less than 5 percent of the issues such as “hydrotest discharge water Consortium’s total environmental and has damaged farmland near a specific social management costs (approximately village and the farmer has not been $US 40 million) for the project. compensated” could and would be investigated by the ECMG. Village well constructed by the Project in Chad. Funding and Logistical Arrangements for the External Monitor The resources required for the external monitoring mechanism can be expected to vary as a function of the project's complexity and the extent of potential environmental D'Appolonia S.p.A and social impacts. The relationship with the external monitoring mechanism may call for Page Six Lessons of Experience | September 2006 | Number 1 It is important to emphasize, however, that Lesson 3 — “Sponsor although project reports, monitoring data management support for the (e.g., water and air quality, noise, etc.) and external monitor is a key determinant ESMP key performance indicators (e.g. non- of success.” compliant citations, recordable spills, consultation statistics etc.), help the external » To be successful, the sponsor's management monitor to observe trends, flag potential needs to fully support the activities of the external monitoring team. The sponsor should issues, and assess data completeness and Direct field consider creating a small, focused team validity, they should not be considered monitoring is an within their E & S Unit to interface with the sufficient to replace actual site visits. Field lender and coordinate with the external verifications allow the external monitor to essential task of monitor. obtain first-hand observations of project- the external » From the beginning of the project, the lender, affected areas and communities, to the sponsor, and the external monitor should monitor. investigate issues, to explore options to establish a common vision for the correct non-compliance situations, and to constructive and positive role of the external monitor. ensure that previous corrective actions have been implemented. Site visits by the ECMG were coordinated and In addition, the Consortium provided a jointly conducted with the Consortium's E & S dedicated staff member to manage the Unit. To collect relevant information on project relationship with the ECMG, a decision that status, progress, and environmental and greatly enhanced overall performance. The social issues, the ECMG held one-day Consortium's E & S Unit facilitated the work of individual meetings with the major project the ECMG in terms of ensuring availability of stakeholders, including the Consortium's E & S key staff for meetings, assisting with the Unit, the main project contractors and sub- provision of documents, information, and contractors, project-affected communities, field data, and organizing logistical government regulators, and civil society arrangements during project site visits. organizations. These meetings allowed the ECMG to be briefed on recent project developments from all stakeholder Site Visit Activities of the External perspectives, and to establish priority issues for Monitor field verification. The World Bank office in the region played an important role early on in the project by assisting in the identification of Site visit activities of the external monitor typically involve stakeholder meetings and interviews, review of project monitoring data and records, direct field monitoring, and Community meeting with the external monitor in northern Cameroon. close-out meetings to present and discuss preliminary findings. Leading up to and during each site visit, the ECMG received ready access to the latest field reports from Consortium's E & S Unit, detailing the implementation and monitoring of the procedures and actions contained in D'Appolonia S.p.A the ESMP. These findings formed the basis of the ECMG's day-to-day interaction with the Consortium's E & S Unit during site visits. Page Seven External Monitoring of the Chad-Cameroon Pipeline Project local and national NGOs interested in the project and conducting their own project monitoring. ECMG field monitoring activities typically included on-site substantiation of environmental and social issues identified by the various project stakeholders and D'Appolonia S.p.A pertaining to the conditions of the ESMP. For example, field visits by the ECMG highlighted traffic safety and road dust as significant impacts of increased project-related transport activities, which were not fully ECMG close out meeting with officials in Cameroon. identified in the project design phase and relevant parts of the ESMP. Although the Consortium was investigating corrective actions, the increased focus on the issue acquisition (including resettlement, provided by the ECMG ensured that the compensation, and livelihood restoration), Consortium implemented a series of and community health and safety. transportation safety measures such as speed controls, community awareness Close out meetings were held at the raising, convoy management, and road by- conclusion of site visits and involved the passes, in addition to more effective dust ECMG, the Consortium's E & S Unit, suppression. government representatives, and the lenders. The meetings allowed field Other technical issues that were monitored observations, findings, and preliminary on site visits included protection of natural conclusions to be presented, and resources, waste management and pollution information gaps, additional data needs, prevention, project footprint reinstatement, and factual inaccuracies to be identified. occupational health and safety, land Site visits by the ECMG were treated as a “snapshot in time,” consistent with the periodic frequency of the monitoring schedule. Additional information received Lesson 4 — “Direct field after the site visits was set aside to be monitoring is an essential task of the investigated during the next project visit. This external monitor.” approach allowed sufficient time for the Consortium's E & S Unit to react to technical » The credibility of the external monitor is dependent on the use of direct field observations, and to evaluate the need for verification and the collection of empirical and implement corrective actions in time for observations. subsequent monitoring visits. » Sole reliance on secondary sources, such as reports provided by the sponsor's E & S Unit and project contractors, should be avoided, Frequency of Site Visits and adequate time for field verification should be planned. » Close out meetings should be held at the conclusion of site visits to allow field The frequency of visits by the external observations and conclusions to be monitor to the project site is normally presented, and factual inaccuracies to be determined by the likelihood of impacts identified. predicted to occur at different phases of the » Successful site visits require extensive logistical Page Eight support from the sponsor. Lessons of Experience | September 2006 | Number 1 project cycle. Planned schedules for site visits may also require adjustment, however, due to unexpected project specific issues. It is recommended that the precise schedule of the site visits be determined based on the prevalence of impacts in different project phases. The external D'Appolonia S.p.A For the Chad-Cameroon project, the monitor plays a frequency of ECMG site visits was significantly higher during the construction phase, key role during because the potential for adverse project transition environmental and social impacts was Pipeline stringing in the rainforest of Cameroon. from construction highest during the pipeline and permanent facility construction. The ECMG undertook to operation four project site visits per year during the phases. construction phase of the project. Once the The transition from construction to operations pipeline construction was completed in late needs to be carefully planned and 2003 and project completion was achieved implemented by both the sponsor's E & S Unit in mid-2004, the ECMG schedule changed to and the external monitor. During the last annual visits as part of the operations phase. semester of the construction phase for the Additional visits during the operational phase Chad-Cameroon project, the ECMG played are conducted only as necessary. This a key role in ensuring that transition plans and reduction in the frequency of monitoring sufficient overlapping of staff and resources reflects the relative decline in the potential within the Consortium's E & S Unit were in significance of environmental and social place to maintain satisfactory performance in issues due to end of the construction phase terms of ESMP compliance. The transition also and the consequent reduction in the project entailed commensurate changes to the workforce and related activities. structure of the ECMG including team reduction, redefinition of key team specializations, and modification of monitoring protocols during site visits. Lesson 5 — “The external monitor plays a key role during the project transition from construction Monitoring Compliance to operation.” » The frequency of visits by the external During site visits, the external monitor may monitor to the project site is normally identify a real or potential “non-compliance” determined by the likelihood of impacts situation, which occurs when either the predicted to occur at different phases of sponsor's E & S Unit or a project contractor the project cycle. fails to implement a specific environmental or » The attention and assistance of the external social commitment contained in the ESMP. monitor is critical to ensuring a smooth transition between project phases. As shown in Figure 1 on the next page, the » The shift from construction to operations phases requires restructuring of both the definition of levels of non-compliance sponsor’s E & S Unit and the external monitor developed for the Chad-Cameroon project to account for different monitoring and ranged from level 1 (least important) to level 3 implementation requirements for the ESMP (most severe), and each required a set of that are specific to the operations phase. Page Nine External Monitoring of the Chad-Cameroon Pipeline Project actions on the part of the Consortium to address the issue depending on the severity Lesson 6 — “The lender should of the potential impact. The information be the arbiter for decisions of non- provided by the ECMG was used by the compliance with the ESMP.” lenders as a direct source to assign » Definitions of non-compliance provisions significant non-compliance citations to the should be clearly established at the outset of sponsor, as needed. the project. » The lender should maintain sufficient The lender may choose whether the leverage with the sponsor to ensure the external monitor should make the official resolution of non-compliance citations. determination of non-compliant situations or instead provide information to the lenders so that they may issue the non-compliance citation as necessary. The experience of the ECMG indicates that it may be Level 3 definition is controversial because it is advantageous to leave the ultimate decision necessary to define what constitutes both to assign non-compliance with the lender. “damage” and a “specifically protected This may increase the leverage of non- sensitive resource.” This issue was particularly compliance declarations and promote a important when the findings of the ECMG positive response by the sponsor. The were used to assign a Level 3 non- external monitoring team is then afforded compliance concerning impacts to cultural the flexibility to investigate and report to the heritage sites. The ECMG was able to lenders regarding all potentially significant overcome this ambiguity by reporting any issues based on its professional judgment. situations that were considered critical issues and providing factual observations to IFC In addition to the questions of which party and other stakeholders to allow them to should issue non-compliance citations, the assess the potential non-compliance Chad-Cameroon project highlighted the situation. importance of clearly stating the definition of non-compliance provisions. For example, the Fig. 1 Example of Non-Compliance Classification System Level 3: for the Chad-Cameroon Serious Project Impact to an identified sensitive resource Level 2: Expeditious Action Required Could give rise to a serious impact to an identified sensitive resource Level 1: Source: D'Appolonia S.p.A Early Warning No significant impact, but not consistent with ESMP Repeated Level 1-type incidents can escalate to a Level 2 non-compliance situation Page Ten Lessons of Experience | September 2006 | Number 1 The External Monitor and Other Layers of responsible for implementing different Project Monitoring aspects of the project's ESMP. These contractors and sub-contractors each had a monitoring system within their management On complex projects, the monitoring of ESMP structure, and the Consortium's E & S Unit commitments typically involves internal interacted with these groups during monitoring systems of the sponsor and the monitoring activities. The Consortium's E & S main project contractors, and external Unit assumed overall responsibility for Successful project monitoring by the lender and government monitoring the social and environmental monitoring regulators. Successful project monitoring compliance of contractors and sub- requires the development and integration of contractors associated with the project. requires the these multi-layered monitoring systems. For development the Chad-Cameroon project, the ECMG was Initial site visits by the ECMG, however, and integration positioned as an additional observer to demonstrated the limited capacity of sub- oversee the sponsor’s internal monitoring contractors to implement environmental and of multi-layered systems and complement the external social commitments, which posed a risk to monitoring oversight conducted by other project overall ESMP compliance. On subsequent site systems. stakeholders. Figure 2 indicates the position of visits, the ECMG did not limit its field the ECMG in the multi-layer monitoring system monitoring to the Consortium and its main implemented for the Chad-Cameroon project contractor activities, but also project. included field verification of sub-contractor responsibilities in the ESMP. The internal layers of the monitoring system for the Chad-Cameroon project consisted of External monitoring on the Chad-Cameroon environmental and social monitoring project involved both the lenders and provided by the Consortium and their government regulators. Depending on their contractor companies. As is typical of capacity, some lenders may use in-house or complex projects, the Chad-Cameroon contracted environmental and social pipeline involved numerous contractors and specialists to monitor the implementation of sub-contractors, each of which was the ESMP. It is important to note that although Fig. 2 Multi-layer Monitoring System for the Chad-Cameroon Pipeline Project CONSTRUCTION PHASE OPERATIONS PHASE E X Layer 5 Monitoring by IFC/World Bank Staff T E R Layer 4 External Monitoring (ECMG) (Annual visits) N (Quarterly visits) A L Layer 3 Government Regulatory Monitoring I Source: D'Appolonia S.p.A N T Layer 2 Monitoring by the Sponsor’s Environment and Social Management Unit E R N Layer 1 Self-Monitoring by Contractors/Sub-Contractors A L Page Eleven External Monitoring Independent of the Monitoring onChad-Cameroon the Chad Cameroon Pipeline Pipeline Project Project and social commitments contained in the Lesson 7 — “Monitoring the ESMP. The perception of the ECMG's performance of contractors and neutrality was reinforced by its reliance on, sub-contractors is critical to project and reporting of, empirical findings. success.” The ECMG assessment reports were » Lenders should conduct regular in-country submitted to the lenders and copied to the supervision of the project. For lenders with Consortium shortly after the conclusion of limited staff resources and capacity for each site visit. The Consortium was given the these activities, the role of the external opportunity to comment one time on any monitor can be critical to successful factual inaccuracies within a fixed number implementation of the ESMP. of days following receipt of the reports. It is » The limited capacity and expertise of sub- recommended that the lender and the contractors to implement environmental sponsor have an opportunity to suggest and social commitments should be improvements to the reporting if there recognized and addressed. » The main project contractors should be appears to have been factual inaccuracies contractually obligated to comply with the in the compiled observations or sponsor's ESMP and to establish an internal interpretations, or if important information monitoring system. Although contractor was not presented to explain field compliance with the ESMP is the ultimate observations, compliance assessment and responsibility of the sponsor, their implementation strategies. However, to performance can be improved through maintain credibility, it is critical that the involvement of the external monitor. ultimate responsibility and decisions regarding the content of final reporting for public disclosure rests with the external monitor. a role of the external monitor is to be in part the objective 'eyes and ears' of the lender, Based on the experience of the Chad- this should not substitute, but rather Cameroon project, it is recommended that supplement, the regular in-country project the reports of the external monitor be supervision performed by the lender. For published on a specific and clearly lenders with limited staff resources and identifiable website. Due to limited access to capacity for supervision and monitoring the internet in Chad and Cameroon, the activities, the role of the external monitor World Bank country offices were instrumental assumes additional importance to successful in distributing paper copies to government project implementation of the ESMP. agencies, project affected communities, and civil society groups. The ECMG made efforts to confirm that sufficient dissemination Reporting the Findings of the of the previous report had taken place prior External Monitor to subsequent project site visits. A robust and transparent reporting process is Management of Change fundamental to the integrity of the external monitor. On the Chad-Cameroon project, the ECMG prepared ESMP compliance Changes are a natural feature of any assessment reports after each site visit. These complex project and do not necessarily reports were based on facts directly indicate a problem but the initiation of a observed in the field with respect to the process. Sponsors should be prepared for the Consortium's adherence to environmental Page Twelve Lessons Lessons of Experience of Experience | August 2006 | Number 1 | September significant ESMP changes; and iv) delineate Lesson 8 — “Ensuring when changes should be communicated to widespread public access to the lenders and host country governments. monitoring reports reinforces trust in the role of the external monitor.” The Chad-Cameroon ESMP focused primarily on the pipeline right-of-way. From an » To maintain the perception of neutrality, it is environmental and social standpoint, critical that the ultimate responsibility and however, other important issues related to the Ensuring decisions regarding the content of final associated infrastructure of the pipeline widespread reporting for public disclosure rests with the corridor were not given sufficient attention in external monitor. the ESMP. These included impacts from public access » External monitoring reports should be construction camps, pipe yards, access to monitoring published on a specific and clearly roads, borrow pits, and land use planning for identifiable website. Paper copies of the reports reinforces oil wells and related infrastructure. The report should be distributed and made monitoring activities of the ECMG brought trust in the role available to project affected stakeholders. » Widespread public access to monitoring these issues to the attention of the Consortium of the external reports reinforces the impartiality of the and the lenders, and management of monitor. external monitor and the responsiveness to change procedures were used to adjust the project impacts that affect stakeholders. ESMP accordingly to account for these » Credible, objective reports assist the sponsor project-related impacts. in demonstrating actions undertaken to reduce environmental and social impacts. The management of change procedure for the Chad-Cameroon project is, however, primarily an internal sponsor process with only vague procedures for external involvement by the lender or government regulators. need to add or adjust mitigation measures in While this internal company procedure may the ESMP resulting from new issues that were be sufficient for small changes to the ESMP, not previously identified or in recognition such as defining new procedures for the that despite the best planning intentions, remediation of borrow pits, it may be less mitigation measures may not be as effective effective for negotiating and addressing as originally designed and thus need to be more significant issues that may require modified. A procedural approach to substantial changes to the ESMP. managing change is essential to ensure that the project continues to consistently conform to its environmental and social commitments. It is recommended that the sponsor establish Erosion control measures on a river crossing in Cameroon. a “management of change” procedure to deal with changes in impacts from the project and with the resulting mitigation measures which need to be included in the ESMP. At a minimum, the procedure should have mechanisms which: i) identify material project scope or design changes that have not been included in the original ESMP; ii) identify, through monitoring, mitigation D'Appolonia S.p.A measures that are not achieving results and need to be altered; iii) establish criteria to differentiate between minor changes and Page Thirteen External Monitoring of the Chad-Cameroon Pipeline Project In instances where significant cultural properties, natural resources and habitats, or Lesson 9 — “A procedural sensitive species are encountered and approach to Management of potentially impacted, or where physical Change is essential to ensure that relocation or economic displacement of the project continues to conform to households are required, or changes to its environmental and social commitments.” project social and environmental standards and commitments are requested, the » A management of change procedure is management of change procedures should necessary to successfully adjust the ESMP to be established and the changes jointly deal with unexpected environmental and assessed by the sponsor, the lender, the social impacts during project external monitor, and government agencies implementation. prior to the development of further » The external monitor can be a key resource mitigation measures. During the Chad- available to the lender group and the Cameroon project, the ECMG was primarily Consortium for technical advice regarding proposed ESMP adjustments. involved as a technical counterpart » Various “classes of changes” should be available to the lender group and the established to differentiate between the Consortium for technical advice regarding degree of significance of the proposed proposed ESMP adjustments. changes with respect to the potential environmental and social impact of the By involving all key stakeholders, the project activities as defined in the ESMP. decisions regarding significant required » For significant changes, the procedure changes to the ESMP can benefit from a should involve mandatory consultation by the project with lenders and the external discussion that meets the needs of all monitor, before implementation of the stakeholders. It is important to note that in all revised mitigation and monitoring considerations of ESMP changes, a balance alternatives. is needed in the process to limit, to the extent possible, impacts to project development and unplanned costs while ensuring acceptable environmental and social outcomes. Page Fourteen Lessons of Experience | September 2006 | Number 1 Conclusion Market forces are increasingly demanding that companies take a proactive approach towards managing the environmental and social impacts of their projects. This IFC Lessons of Experience publication has demonstrated that external monitoring of D'Appolonia S.p.A environmental and social commitments can The external be a powerful resource to help lenders and monitor can be their project sponsors reduce the risks an influential tool inherent to complex projects. Completed restoration along the pipeline route. to ensure that Throughout the publication, the experiences environmental of the External Compliance Monitoring and social Group (ECMG) on the Chad-Cameroon pipeline project have highlighted the For project affected communities and civil commitments technical value of an external monitor. This society groups, the external monitor creates a are credibly value is further enhanced by the external reporting mechanism that acts as an implemented monitor's ability to increase the transparency, independent source of information helping to trust, and accountability between the key reinforce the credibility and trust in the project in the eyes of project stakeholders. While the decision to sponsor required for successful projects. Host all project employ an external monitor is related to countries, who often suffer from limited stakeholders. the particular scale and complexity of capacity to monitor the project themselves, environmental and social issues associated receive objective, technical, and publicly with a project, the business case for external disclosed assurance that the project is monitoring is based on the monitor's ability to achieving agreed environmental and social enhance the company's approach to outcomes. addressing project risk. Complex projects require companies, lenders, All project stakeholders stand to benefit from project affected communities, civil society, the involvement of an external monitoring and governments to work as part of a mechanism. Project sponsors receive an partnership based on mutual responsibility objective reporting record of their and trust. The external monitor can be an performance on environmental and social influential tool to ensure that environmental measures, which can reinforce the support of and social commitments are credibly project affected communities and defuse implemented in the eyes of all project the allegations of external critics. Lenders stakeholders, resulting in projects that are benefit from an unbiased set of “eyes and economically, socially, and environmentally ears” to assist them in ensuring project sustainable. outcomes meet their environmental and social requirements. Page Fifteen External Monitoring of the Chad-Cameroon Pipeline Project Acknowledgements “External Monitoring of the Chad-Cameroon Pipeline Project: Lessons of Experience” is the first in a new publication series prepared by the Environment and Social Development Department Lessons of Experience of the IFC for the purposes of internal learning and knowledge sharing with clients and the wider private sector. The publication was written by an IFC team comprising Christopher Frankel (Task Manager), Patty Miller and Rosa Orellana, and carried out under the general direction of Rachel Kyte (Director). Vanessa Manuel was responsible for design and layout. A special acknowledgement is due to the members of the External Compliance and Monitoring Group (ECMG) for their extensive written input and review efforts for this publication. They include Paolo Lombardo, Roberto Carpaneto, Lori Anna Conzo, and William J. Johnson, from the consulting firm D'Appolonia S.p.A, as well as private consultants Frédéric Giovannetti, Jean Le Bloas, Dr. Jorge Ossanai, and Dr. Clark A. Dobbs. The authors would also like to thank Mr. Ed Caldwell, Manager of Safety, Health and Environment for Esso Exploration and Production Chad Inc., for his review and comment on this publication. Thanks are also due to the following IFC/World Bank colleagues who reviewed earlier drafts: Rachel Kyte, Rashad Kaldany, Shahbaz Mavaddat, Richard Caines, Dennis Reyes, Debra Sequeira, Richard Wyness, Carlos Arias, John Butler, Eric Brusberg, and Eluma Obibuaku. IFC Good Practice Publications available at: www.ifc.org/enviropublications The Baku-Tbilisi-Ceyhan (BTC) Pipeline Project: Lessons of Experience For IFC as a lender, the process of capturing lessons of experience from projects in an important one. In the "BTC Pipeline Project: Lessons of Experience," IFC environmental and social staff look back on an extremely challenging process and endeavor to extract some of the key operational lessons and good practices for the benefit of colleagues, clients, and the wider institution. While it is impossible to capture all the challenges and complexities encountered during the design and construction phase of the BTC project, this publication focuses on six thematic areas where environmental and social lessons learned were thought to be most valuable and applicable to other IFC-financed projects. For more information, please contact: International Finance Corporation, Environment and Social Development Department, 2121 Pennsylvania Avenue, N.W., Washington, D.C. 20433, U.S.A. Disclaimer The views expressed in this publication are those of its authors and do not necessarily reflect the views of the wider institution. Some of the information used in this document may come from publicly available sources such as company websites and publications. The Lessons of Experience series does not represent a commitment by IFC to require projects it finances to take certain or all of the actions specified in this publication. Instead, any issues arising in an IFC-financed project will be evaluated and addressed in the context of the particular circumstances of the project. Page Sixteen