Lessons of Experience | September 2006 | Number 1


                                                                                                                38215

                                                    External Monitoring of the
                                                 Chad-Cameroon Pipeline Project



                        D
                                 riven by the emerging policy                             and key issues for designing, implementing
                                 requirements of lenders,                                 and operating an external monitoring
                                 heightened public concern, and                           mechanism for complex projects. The
                        the scrutiny of civil society organizations,                      objectivity and technical expertise of the
Lessons of Experience


                        the market is increasingly demanding that                         external monitor can add value to a project
                        companies adopt responsible and                                   by increasing trust and accountability
                        accountable environmental and social                              between the sponsor and key project
                        practices. To assist in managing these risks,                     stakeholders including lenders, project-
                        lenders and project sponsors pursuing                             affected communities, civil society
                        complex projects in emerging markets may                          organizations, and government regulators.
                        benefit from the use of an external monitor.
                        The role of the external monitor is to provide                    To highlight the practical challenges and
                        an independent, impartial, and transparent                        value of the external monitoring mechanism,
                        record of the sponsor's compliance with the                       the publication draws illustrative examples
                        project's environmental and social                                from the experiences of IFC during the
                        commitments.                                                      Chad-Cameroon pipeline project. In 2001,
                                                                                          IFC required an external monitoring role for
                        A number of challenging project investment                        the Chad-Cameroon project and appointed
                        conditions may signal the need to consider                        D'Appolonia S.p.A., a consulting firm from
                        use of an external monitor, including, but                        Italy, to form the External Compliance
                        not limited to, projects involving:                               Monitoring Group (ECMG).1 While the scale
                        » multiple public and private sector                              and complexity of the external monitoring
                              partners                                                    for the Chad-Cameroon project is not
                        » highly visible sectors such as natural                          necessarily indicative of the level of effort
                              resource extraction                                         and resources that would be needed on all
                        »     significant population resettlement                         complex projects, these lessons are a
                        »     indigenous peoples                                          valuable source of practical experience with
                        »     biodiversity and sensitive habitats                         external monitoring. This publication has
                        »     complex project benefit sharing, revenue
                          management, and governance systems
                                                                                            CONTENTS
                        » weak national regulatory regimes.

                        This Lessons of Experience provides lenders                            2   What is External Monitoring?
                        and project sponsors with an understanding                             2   What are the Benefits for Project
                        of the business case for employing an                                      Stakeholders?
                        external monitor. The publication gives                                3   How to Maintain the Independence of
                        practical advice regarding the major steps                                 the External Monitor

                                                                                               4   Key Components of the External
                                                                                                   Monitoring Mechanism
                        1
                            The ECMG reports are published on the following website:
                            www.ifc.org/ecmg                                                  15   Conclusion
                            The client company website can be accessed at:
                            www.essochad.com/Chad/Chad_HomePage.asp                           16   Acknowledgements
                            Project-related websites of the World Bank Group can be
                            accessed at: www.worldbank.org/afr/ccproj/;
                            www.ifc.org/ifcext/africa.nsf/Content/ChadCameroonVideo
External Monitoring of the Chad-Cameroon Pipeline Project




                                 been produced by IFC with the extensive
                                 collaboration of specialists from D’Appolonia
                                 S.p.A. (see “Acknowledgements” page).



                                 What is External Monitoring?




                                                                                                                                                               D'Appolonia, S.p.A.
                                 Monitoring is the sponsor's primary means for
                                 tracking and evaluating progress toward the
                                 implementation of commitments designed to
                                 avoid or mitigate the environmental and social
                                 impacts of the project. These actions are                                         Preparation for pipeline welding.
                                 typically specified in the sponsor's
                                 Environmental and Social Management
                                 Program (ESMP). The ESMP details the
                                 procedures and actions necessary to prevent                                       What are the Benefits for
                                 or manage the adverse impacts identified in
                                 the project's social and environmental impact
                                                                                                                   Project Stakeholders?
                                 assessment. This program is commonly
                                                                                                                   For lenders, the external monitor is an
                                 implemented by an “Environment and Social
                                                                                                                   important tool to objectively verify and
                                 Management Unit” (hereafter referred to as the
                                                                                                                   report on sponsor compliance with
                                 “E & S Unit”) within a sponsor's management
                                                                                                                   environmental and social conditions of the
                                 structure.
                                                                                                                   investment agreement during project
                                                                                                                   development. The financial sustainability of
                                 The role of the external monitor is to provide
                                                                                                                   a project can be jeopardized if agreed
                                 field-based verification of project activities
                                                                                                                   environmental and social measures are not
                                 and ensure compliance by the sponsor with
                                                                                                                   demonstrated to have been credibly
                                 the commitments established in the ESMP.
                                                                                                                   implemented by the sponsor. Lenders with
                                 On projects with potentially significant
                                                                                                                   limited in-house environmental and social
                                 environmental and social impacts that are
                                                                                                                   expertise may benefit from the external
                                 diverse, irreversible, or unprecedented, IFC
                                                                                                                   monitor's ability to act in part as the “eyes
                                 requires that sponsors retain qualified and
                                                                                                                   and ears” of the lender, fostering a proactive
                                 experienced external experts to verify their
                                                                           2                                       management approach to help the lender
                                 monitoring information.
                                                                                                                   develop successful projects and avoid
                                                                                                                   reputational damage and related liabilities.
                                 Funded and logistically supported by the
                                 sponsor, the external monitor acts as an
                                                                                                                   For project sponsors, the external monitor
                                 impartial layer of monitoring that
                                                                                                                   increases the sponsor's ability to document,
                                 complements the sponsor’s internal monitoring
                                                                                                                   manage, and reduce their risk exposure to
                                 systems. In addition, the project may be
                                                                                                                   environmental and social issues. By providing
                                 subject to additional oversight conducted
                                                                                                                   additional technical expertise to supplement
                                 directly by the staff of lenders, government
                                                                                                                   the sponsor's E & S Unit, the external monitor
                                 regulators, and civil society groups.
                                                                                                                   increases the operational capacity of the
                                                                                                                   sponsor's management to take timely
                                                                                                                   actions to improve performance and comply
                                 2
                                     The IFC requirement for external monitoring by qualified experts is
                                     contained in Performance Standard 1, paragraph 24. Full text of               with environmental and social commitments.
                                     Performance Standard 1 is available at www.ifc.org/envsocstandards.
                                     The Equator Principles II defines a broadly similar requirement as part of
                                     Principle 9: Independent Monitoring and Reporting. Full text of the Equator
                                     Principles is available at: http://www.equator-principles.com/documents/
Page Two                             Equator_Principles.pdf
                                                                                       Lessons of Experience | September 2006 | Number 1




  The Chad-Cameroon Pipeline Project

 The Chad-Cameroon project is a US$3.5 billion
 development of an oil field in Chad by a
 consortium headed by ExxonMobil, and a 1,070
 km long pipeline extending through Chad and
 Cameroon to the Atlantic coast, constructed
 and operated by the Tchad Oil Transportation
 Company S.A. (TOTCO) and the Cameroon Oil
                                                                                                                       The external
 Transportation Company S.A. (COTCO)                                                                                   monitor provides
 (hereafter collectively referred to as the
 “Consortium”). Funded and logistically
                                                                                                                       an impartial and




                                                                                                   D'Appolonia S.p.A
 supported by the Consortium, the ECMG serves                                                                          transparent record
 as the external monitoring team responsible for
 auditing the implementation of the Consortium's
                                                                                                                       of the sponsor’s
 environmental and social commitments for the                                                                          compliance with
 Chad-Cameroon Oil Pipeline project.                 Pipeline trenching in Cameroon.
                                                                                                                       the project’s
                                                                                                                       environmental
                                                                                                                       and social
The risk for sponsors whose projects are            affected communities, are typically shared by                      commitments.
associated with poor environmental and              the sponsor and various levels of government.
social performance extends beyond
damage to the corporate brand.                      With respect to project affected communities
Underperforming companies can lose their            and civil society groups, the external monitor
license to operate along with the critical          provides a team of qualified technical experts
support of project-affected communities.            that can directly investigate and report on
Their products and services may incur               specific issues of concern for the local
barriers to market entry from consumers and         communities in the project area. It provides
regulators, and their ability to raise capital      reporting that can be an independent source
from lenders may be constrained. The                of information for local communities and
technical expertise of the external                 NGOs, which in turn serves to foster an
monitor allows sponsors to have                     atmosphere of trust required for effective
documented, independently verified, and             working relationships.
publicly available reports of their actions—a
critical, unbiased record which can be used
to defend against potential allegations of          How to Maintain the
poor environmental and social performance.
                                                    Independence of the
The benefit of external monitoring for host         External Monitor
countries is the availability, at no cost, of an
expert team that provides regular, objective        Maintaining impartiality, objectivity, and
monitoring of project compliance with               transparency in the eyes of all project
applicable regulations and with other               stakeholders is critical to the success of the
environmental and social requirements, as           external monitor. However, the reliance of the
agreed with the sponsor at the outset of the        external monitor on the financial and logistical
project. The external monitor may be                support of the sponsor may create perceptions
particularly useful in helping to coordinate        of bias. A number of steps should be taken to
joint technical solutions where responsibilities,   proactively reassure project stakeholders as to
such as community health issues in project          the independence of the monitor, including:

                                                                                                                        Page Three
External Monitoring of the Chad-Cameroon Pipeline Project




                                 » establishing a robust and transparent site
                                   visit monitoring process by the external
                                   monitor that demonstrates a reliance on
                                   field-based empirical findings
                                 » creating a well defined reporting process
                                   for which the external monitor has ultimate
                                   responsibility for final content
                                 » establishing and abiding by clear




                                                                                                                                                                       D'Appolonia S.p.A
                                     operational protocols which define the
                                     relationship of the external monitor to
                                     other project stakeholders and allow the
                                     external monitor to avoid conflicts of
                                                                                                    ECMG Public Health Specialist consulting with community healers.
                                     interest.

                                 These issues, among others, are discussed in
                                 further detail below.
                                                                                                    During the project construction phase of the
                                                                                                    Chad-Cameroon project, the ECMG was
                                                                                                    composed of six permanent members,
                                 Key Components of the
                                                                                                    including a team leader, expert in pipeline
                                 External Monitoring                                                engineering and related health and safety
                                 Mechanism                                                          issues; a team coordinator, specialist in
                                                                                                    environmental science and engineering;
                                                                                                    and individual specialists in socio-economic
                                   Structure of the External                                        and socio-cultural issues, institutional
                                   Monitoring Team                                                  development, environmental and social
                                                                                                    capacity building, earth sciences, and
                                 Environmental and social issues on projects                        public health.
                                 are often interrelated, a fact reinforced by
                                 current international best practice for                            This varied composition of the ECMG
                                 integrated environmental and social impact                         created a strong internal dialogue during the
                                 assessment and management. In order to                             review of specific findings from the
                                 properly address the environmental and                             standpoint of different disciplines. In addition,
                                 social issues of complex projects, it is                           the multifaceted team provided technical
                                 recommended that the external monitoring                           expertise and credibility to a wide range of
                                 team be multidisciplinary in composition.                          issues when engaging with all interested
                                                                                                    parties, including IFC, the Consortium, the
                                                                                                    host governments, and civil society
                                  Visit to tree nursery.                                            organizations. During IFC's selection of firms
                                                                                                    to act as the ECMG, the expert technical
                                                                                                    capabilities demonstrated by D'Appolonia,
                                                                                                    the firm eventually selected, was cited by
                                                                                                    the Consortium as a key factor in convincing
                                                                                                    them that the ECMG would be able to add
                                                                                                    tangible value to the project.
                                                                                D'Appolonia S.p.A




                                                                                                    It is important to note that during the initial
                                                                                                    planning phase the key individuals
                                                                                                    comprising the external monitoring team


Page Four
                                                                                                      Lessons of Experience | September 2006 | Number 1




may not have full knowledge of all the
project's technical issues. Accordingly, it may
be helpful to create an understanding
between lenders and the sponsor to allow the
team to be complemented by additional
specialized experts for unplanned issues which
may arise during project development.
                                                                                                                                              Maintaining




                                                                                                                          D'Appolonia S.p.A
On the Chad-Cameroon project, this flexibility
                                                                                                                                              impartiality,
allowed for the addition of a cultural heritage
expert to the ECMG who helped identify and                                                                                                    objectivity, and
mitigate key gaps in the Consortium's
                                                     Revegetation of the pipeline right-of-way in the Atlantic Littoral                       transparency
management of impacts to cultural heritage           Forest of Cameroon.
                                                                                                                                              in the eyes of
sites during construction of the pipeline.
Incidents of inadequate management of                                                                                                         all project
heritage sites along the pipeline route resulted                                                                                              stakeholders is
in a retroactive non-compliance citation by          During construction, the ECMG also added
                                                                                                                                              critical to the
the lenders against the Consortium. Further          an ecologist who provided key input into the
incidents that may have resulted in costly           management of invasive species and overall                                               success of the
project delays were avoided due to the               bio-restoration issues along the pipeline route.                                         external monitor.
dialogue between the ECMG and the                    Additionally, the presence of a public health
Consortium's E & S Unit, which allowed for the       expert on the team played an important role
identification and management of potential           in facilitating joint approaches to managing
cultural heritage impacts.                           the occupational health issues of employees
                                                     and the larger community health issues faced
                                                     by communities and government authorities.



                                                      Operational Protocols of the
 Lesson 1 — “An integrated                            External Monitor
 environmental and social approach
 facilitates effective monitoring.”
                                                     The formulation of operational protocols may
 » The effectiveness of the external monitor is      be helpful to clearly establish the role and
   greatly improved by mobilizing an integrated      interaction of the external monitor with
   and technically capable environmental and
                                                     respect to other project stakeholders. On the
   social team.
                                                     Chad-Cameroon project, the operational
 » This integration allows the external monitor to
   interact with the sponsor and provide expert
                                                     protocols promoted the need for active
   evaluation of environmental and social issues,    cooperation between the ECMG and
   and to foster engagement with project-            Consortium's E & S Unit. The responsibility to
   affected communities, government, and civil       provide objective, external reporting on ESMP
   society organizations.                            compliance to IFC and the lender group
 » Flexibility to expand the external monitor        based on accurate data and empirical
   team to confront new, unplanned issues is
                                                     findings was defined as the exclusive
   helpful, but should be carefully considered to
                                                     responsibility of the ECMG. For host country
   ensure unnecessary costs for the project
   sponsor are avoided.
                                                     governments and related agencies, the
 » Consulting the sponsor during the selection of    protocols reinforced that the ECMG was not
   the external monitor provides a key               meant to replace, but rather to complement,
   opportunity to build trust in the technical       effective project monitoring by government
   capability of the external monitor.               regulators.

                                                                                                                                               Page Five
External Monitoring of the Chad-Cameroon Pipeline Project




                                                                                       significant logistical resources and
                                    Lesson 2 — “Clear operational                      cooperation from the sponsor and
                                    protocols are critical to the
                                                                                       all project stakeholders. The sponsor should
                                    perception of independence
                                                                                       expect an initial period of start-up
                                    and impartiality of the external
                                                                                       adjustments, particularly with respect to the
                                    monitor.”
                                                                                       establishment of a working relationship
                                                                                       between the sponsor’s E & S Unit and the
                                   » Clear operational protocols allow the
                                                                                       external monitoring team.
                                     external monitor to avoid conflicts of interest
                                     and maintain a position of independence
                                     with project stakeholders and affected            The upfront costs incurred by the sponsor
                                     communities.                                      employing the external monitor are not
                                   » Once established, every effort should be          insignificant. These costs, however, should be
                                     made to ensure that all project stakeholders      weighed against the potential costs from
                                     are aware of, and abide by, the operational       project delays, environmental and social
                                     protocols governing the activities of the
                                                                                       liabilities, corporate brand damage,
                                     external monitor.
                                                                                       potential litigation, and community
                                                                                       upheaval that can emerge as complex
                                                                                       projects are sited and constructed.
                                 With respect to interactions with civil society,
                                 the ECMG was defined as an independent                At the end of the two year construction
                                 entity readily available to listen to civil           phase of the Chad-Cameroon project, the
                                 society concerns provided they could                  direct ECMG cost to the Consortium was
                                 identify specific grievances or complaints            approximately $US1.5 million for the labor
                                 that could be investigated in the field. In           and travel expenses of quarterly site visits,
                                 practice, it proved difficult to ensure that the      and an additional $US 2 million budgeted by
                                 ECMG did not become a parallel grievance              the Consortium to provide technical and
                                 mechanism for the project. Early in the               logistical support for the ECMG. Annual
                                 project it was therefore necessary to make            ECMG site visits during the operations phase
                                 clear that the ECMG would not respond to              cost approximately $US100,000 per visit. The
                                 generalities, such as “pipeline construction is       total direct costs of labor, travel, technical,
                                 going to deteriorate the quality of life for the      and logistical support of the ECMG are
                                 local villagers”. However, specific technical         estimated at less than 5 percent of the
                                 issues such as “hydrotest discharge water             Consortium’s total environmental and
                                 has damaged farmland near a specific                  social management costs (approximately
                                 village and the farmer has not been                   $US 40 million) for the project.
                                 compensated” could and would be
                                 investigated by the ECMG.


                                                                                       Village well constructed by the Project in Chad.
                                   Funding and Logistical Arrangements
                                   for the External Monitor


                                 The resources required for the external
                                 monitoring mechanism can be expected to
                                 vary as a function of the project's complexity
                                 and the extent of potential environmental
                                                                                                                                          D'Appolonia S.p.A




                                 and social impacts. The relationship with the
                                 external monitoring mechanism may call for


Page Six
                                                                                                Lessons of Experience | September 2006 | Number 1




                                                    It is important to emphasize, however, that
 Lesson 3 — “Sponsor                                although project reports, monitoring data
 management support for the                         (e.g., water and air quality, noise, etc.) and
 external monitor is a key determinant
                                                    ESMP key performance indicators (e.g. non-
 of success.”
                                                    compliant citations, recordable spills,
                                                    consultation statistics etc.), help the external
 » To be successful, the sponsor's management
                                                    monitor to observe trends, flag potential
   needs to fully support the activities of the
   external monitoring team. The sponsor should     issues, and assess data completeness and                                           Direct field
   consider creating a small, focused team          validity, they should not be considered
                                                                                                                                       monitoring is an
   within their E & S Unit to interface with the    sufficient to replace actual site visits. Field
   lender and coordinate with the external          verifications allow the external monitor to                                        essential task of
   monitor.                                         obtain first-hand observations of project-                                         the external
 » From the beginning of the project, the lender,   affected areas and communities, to
   the sponsor, and the external monitor should                                                                                        monitor.
                                                    investigate issues, to explore options to
   establish a common vision for the
                                                    correct non-compliance situations, and to
   constructive and positive role of the external
   monitor.                                         ensure that previous corrective actions have
                                                    been implemented.

                                                    Site visits by the ECMG were coordinated and
In addition, the Consortium provided a              jointly conducted with the Consortium's E & S
dedicated staff member to manage the                Unit. To collect relevant information on project
relationship with the ECMG, a decision that         status, progress, and environmental and
greatly enhanced overall performance. The           social issues, the ECMG held one-day
Consortium's E & S Unit facilitated the work of     individual meetings with the major project
the ECMG in terms of ensuring availability of       stakeholders, including the Consortium's E & S
key staff for meetings, assisting with the          Unit, the main project contractors and sub-
provision of documents, information, and            contractors, project-affected communities,
field data, and organizing logistical               government regulators, and civil society
arrangements during project site visits.            organizations. These meetings allowed the
                                                    ECMG to be briefed on recent project
                                                    developments from all stakeholder
 Site Visit Activities of the External              perspectives, and to establish priority issues for
 Monitor                                            field verification. The World Bank office in the
                                                    region played an important role early on in
                                                    the project by assisting in the identification of
Site visit activities of the external monitor
typically involve stakeholder meetings and
interviews, review of project monitoring data
and records, direct field monitoring, and           Community meeting with the external monitor in northern Cameroon.
close-out meetings to present and discuss
preliminary findings.

Leading up to and during each site visit, the
ECMG received ready access to the latest
field reports from Consortium's E & S Unit,
detailing the implementation and monitoring
of the procedures and actions contained in
                                                                                                                   D'Appolonia S.p.A




the ESMP. These findings formed the basis of
the ECMG's day-to-day interaction with the
Consortium's E & S Unit during site visits.
                                                                                                                                       Page Seven
External Monitoring of the Chad-Cameroon Pipeline Project




                                 local and national NGOs interested in the
                                 project and conducting their own project
                                 monitoring.

                                 ECMG field monitoring activities typically
                                 included on-site substantiation of
                                 environmental and social issues identified by
                                 the various project stakeholders and




                                                                                                                                                D'Appolonia S.p.A
                                 pertaining to the conditions of the ESMP. For
                                 example, field visits by the ECMG highlighted
                                 traffic safety and road dust as significant
                                 impacts of increased project-related
                                 transport activities, which were not fully                ECMG close out meeting with officials in Cameroon.
                                 identified in the project design phase and
                                 relevant parts of the ESMP. Although the
                                 Consortium was investigating corrective
                                 actions, the increased focus on the issue                 acquisition (including resettlement,
                                 provided by the ECMG ensured that the                     compensation, and livelihood restoration),
                                 Consortium implemented a series of                        and community health and safety.
                                 transportation safety measures such as
                                 speed controls, community awareness                       Close out meetings were held at the
                                 raising, convoy management, and road by-                  conclusion of site visits and involved the
                                 passes, in addition to more effective dust                ECMG, the Consortium's E & S Unit,
                                 suppression.                                              government representatives, and the
                                                                                           lenders. The meetings allowed field
                                 Other technical issues that were monitored                observations, findings, and preliminary
                                 on site visits included protection of natural             conclusions to be presented, and
                                 resources, waste management and pollution                 information gaps, additional data needs,
                                 prevention, project footprint reinstatement,              and factual inaccuracies to be identified.
                                 occupational health and safety, land                      Site visits by the ECMG were treated as a
                                                                                           “snapshot in time,” consistent with the
                                                                                           periodic frequency of the monitoring
                                                                                           schedule. Additional information received
                                   Lesson 4 — “Direct field
                                                                                           after the site visits was set aside to be
                                   monitoring is an essential task of the
                                                                                           investigated during the next project visit. This
                                   external monitor.”
                                                                                           approach allowed sufficient time for the
                                                                                           Consortium's E & S Unit to react to technical
                                   » The credibility of the external monitor is
                                     dependent on the use of direct field
                                                                                           observations, and to evaluate the need for
                                     verification and the collection of empirical          and implement corrective actions in time for
                                     observations.                                         subsequent monitoring visits.
                                   » Sole reliance on secondary sources, such as
                                     reports provided by the sponsor's E & S Unit
                                     and project contractors, should be avoided,
                                                                                            Frequency of Site Visits
                                     and adequate time for field verification
                                     should be planned.
                                   » Close out meetings should be held at the
                                     conclusion of site visits to allow field              The frequency of visits by the external
                                     observations and conclusions to be                    monitor to the project site is normally
                                     presented, and factual inaccuracies to be             determined by the likelihood of impacts
                                     identified.                                           predicted to occur at different phases of the
                                   » Successful site visits require extensive logistical
Page Eight                           support from the sponsor.
                                                                                                  Lessons of Experience | September 2006 | Number 1




project cycle. Planned schedules for site visits
may also require adjustment, however, due
to unexpected project specific issues. It is
recommended that the precise schedule of
the site visits be determined based on the
prevalence of impacts in different project
phases.
                                                                                                                                   The external




                                                                                                               D'Appolonia S.p.A
For the Chad-Cameroon project, the
                                                                                                                                   monitor plays a
frequency of ECMG site visits was significantly
higher during the construction phase,                                                                                              key role during
because the potential for adverse                                                                                                  project transition
environmental and social impacts was               Pipeline stringing in the rainforest of Cameroon.
                                                                                                                                   from construction
highest during the pipeline and permanent
facility construction. The ECMG undertook                                                                                          to operation
four project site visits per year during the                                                                                       phases.
construction phase of the project. Once the        The transition from construction to operations
pipeline construction was completed in late        needs to be carefully planned and
2003 and project completion was achieved           implemented by both the sponsor's E & S Unit
in mid-2004, the ECMG schedule changed to          and the external monitor. During the last
annual visits as part of the operations phase.     semester of the construction phase for the
Additional visits during the operational phase     Chad-Cameroon project, the ECMG played
are conducted only as necessary. This              a key role in ensuring that transition plans and
reduction in the frequency of monitoring           sufficient overlapping of staff and resources
reflects the relative decline in the potential     within the Consortium's E & S Unit were in
significance of environmental and social           place to maintain satisfactory performance in
issues due to end of the construction phase        terms of ESMP compliance. The transition also
and the consequent reduction in the project        entailed commensurate changes to the
workforce and related activities.                  structure of the ECMG including team
                                                   reduction, redefinition of key team
                                                   specializations, and modification of
                                                   monitoring protocols during site visits.

 Lesson 5 — “The external
 monitor plays a key role during the
 project transition from construction                Monitoring Compliance
 to operation.”

 » The frequency of visits by the external         During site visits, the external monitor may
   monitor to the project site is normally         identify a real or potential “non-compliance”
   determined by the likelihood of impacts         situation, which occurs when either the
   predicted to occur at different phases of       sponsor's E & S Unit or a project contractor
   the project cycle.                              fails to implement a specific environmental or
 » The attention and assistance of the external    social commitment contained in the ESMP.
   monitor is critical to ensuring a smooth
   transition between project phases.
                                                   As shown in Figure 1 on the next page, the
 » The shift from construction to operations
   phases requires restructuring of both the       definition of levels of non-compliance
   sponsor’s E & S Unit and the external monitor   developed for the Chad-Cameroon project
   to account for different monitoring and         ranged from level 1 (least important) to level 3
   implementation requirements for the ESMP        (most severe), and each required a set of
   that are specific to the operations phase.
                                                                                                                                   Page Nine
External Monitoring of the Chad-Cameroon Pipeline Project




                                 actions on the part of the Consortium to
                                 address the issue depending on the severity                Lesson 6 — “The lender should
                                 of the potential impact. The information                   be the arbiter for decisions of non-
                                 provided by the ECMG was used by the                       compliance with the ESMP.”
                                 lenders as a direct source to assign
                                                                                            » Definitions of non-compliance provisions
                                 significant non-compliance citations to the
                                                                                               should be clearly established at the outset of
                                 sponsor, as needed.
                                                                                               the project.
                                                                                            » The lender should maintain sufficient
                                 The lender may choose whether the                             leverage with the sponsor to ensure the
                                 external monitor should make the official                     resolution of non-compliance citations.
                                 determination of non-compliant situations or
                                 instead provide information to the lenders so
                                 that they may issue the non-compliance
                                 citation as necessary. The experience of the
                                 ECMG indicates that it may be                           Level 3 definition is controversial because it is
                                 advantageous to leave the ultimate decision             necessary to define what constitutes both
                                 to assign non-compliance with the lender.               “damage” and a “specifically protected
                                 This may increase the leverage of non-                  sensitive resource.” This issue was particularly
                                 compliance declarations and promote a                   important when the findings of the ECMG
                                 positive response by the sponsor. The                   were used to assign a Level 3 non-
                                 external monitoring team is then afforded               compliance concerning impacts to cultural
                                 the flexibility to investigate and report to the        heritage sites. The ECMG was able to
                                 lenders regarding all potentially significant           overcome this ambiguity by reporting any
                                 issues based on its professional judgment.              situations that were considered critical issues
                                                                                         and providing factual observations to IFC
                                 In addition to the questions of which party             and other stakeholders to allow them to
                                 should issue non-compliance citations, the              assess the potential non-compliance
                                 Chad-Cameroon project highlighted the                   situation.
                                 importance of clearly stating the definition of
                                 non-compliance provisions. For example, the




                                          Fig. 1 Example of
                                          Non-Compliance
                                          Classification System
                                                                                     Level 3:
                                          for the Chad-Cameroon
                                                                                     Serious
                                          Project
                                                                                    Impact to an
                                                                                 identified sensitive
                                                                                      resource

                                                                                      Level 2:
                                                                              Expeditious Action
                                                                                    Required
                                                                          Could give rise to a serious impact
                                                                          to an identified sensitive resource

                                                                                    Level 1:
                                                                                                                                      Source: D'Appolonia S.p.A




                                                                                 Early Warning
                                                                   No significant impact, but not consistent with ESMP
                                                                   Repeated Level 1-type incidents can escalate to a
                                                                            Level 2 non-compliance situation
Page Ten
                                                                                          Lessons of Experience | September 2006 | Number 1




 The External Monitor and Other Layers of             responsible for implementing different
 Project Monitoring                                   aspects of the project's ESMP. These
                                                      contractors and sub-contractors each had a
                                                      monitoring system within their management
On complex projects, the monitoring of ESMP           structure, and the Consortium's E & S Unit
commitments typically involves internal               interacted with these groups during
monitoring systems of the sponsor and the             monitoring activities. The Consortium's E & S
main project contractors, and external                Unit assumed overall responsibility for                                         Successful project
monitoring by the lender and government               monitoring the social and environmental
                                                                                                                                      monitoring
regulators. Successful project monitoring             compliance of contractors and sub-
requires the development and integration of           contractors associated with the project.                                        requires the
these multi-layered monitoring systems. For                                                                                           development
the Chad-Cameroon project, the ECMG was               Initial site visits by the ECMG, however,
                                                                                                                                      and integration
positioned as an additional observer to               demonstrated the limited capacity of sub-
oversee the sponsor’s internal monitoring             contractors to implement environmental and                                      of multi-layered
systems and complement the external                   social commitments, which posed a risk to                                       monitoring
oversight conducted by other project                  overall ESMP compliance. On subsequent site
                                                                                                                                      systems.
stakeholders. Figure 2 indicates the position of      visits, the ECMG did not limit its field
the ECMG in the multi-layer monitoring system         monitoring to the Consortium and its main
implemented for the Chad-Cameroon                     project contractor activities, but also
project.                                              included field verification of sub-contractor
                                                      responsibilities in the ESMP.
The internal layers of the monitoring system for
the Chad-Cameroon project consisted of                External monitoring on the Chad-Cameroon
environmental and social monitoring                   project involved both the lenders and
provided by the Consortium and their                  government regulators. Depending on their
contractor companies. As is typical of                capacity, some lenders may use in-house or
complex projects, the Chad-Cameroon                   contracted environmental and social
pipeline involved numerous contractors and            specialists to monitor the implementation of
sub-contractors, each of which was                    the ESMP. It is important to note that although




 Fig. 2 Multi-layer Monitoring System for the Chad-Cameroon Pipeline Project

                                 CONSTRUCTION PHASE                              OPERATIONS PHASE

   E
   X       Layer 5      Monitoring by IFC/World Bank Staff
   T
   E
   R       Layer 4      External Monitoring (ECMG)                               (Annual visits)
   N                           (Quarterly visits)
   A
   L
           Layer 3      Government Regulatory Monitoring



   I
                                                                                                          Source: D'Appolonia S.p.A




   N
   T
           Layer 2      Monitoring by the Sponsor’s Environment and Social Management Unit
   E
   R
   N       Layer 1      Self-Monitoring by Contractors/Sub-Contractors
   A
   L
                                                                                                                                      Page Eleven
 External Monitoring
Independent          of the
              Monitoring  onChad-Cameroon
                             the Chad Cameroon  Pipeline
                                          Pipeline       Project
                                                   Project




                                                                                      and social commitments contained in the
                                     Lesson 7 — “Monitoring the                       ESMP. The perception of the ECMG's
                                     performance of contractors and                   neutrality was reinforced by its reliance on,
                                     sub-contractors is critical to project           and reporting of, empirical findings.
                                     success.”
                                                                                      The ECMG assessment reports were
                                     » Lenders should conduct regular in-country      submitted to the lenders and copied to the
                                       supervision of the project. For lenders with   Consortium shortly after the conclusion of
                                       limited staff resources and capacity for       each site visit. The Consortium was given the
                                       these activities, the role of the external     opportunity to comment one time on any
                                       monitor can be critical to successful          factual inaccuracies within a fixed number
                                       implementation of the ESMP.                    of days following receipt of the reports. It is
                                     » The limited capacity and expertise of sub-     recommended that the lender and the
                                       contractors to implement environmental
                                                                                      sponsor have an opportunity to suggest
                                       and social commitments should be
                                                                                      improvements to the reporting if there
                                       recognized and addressed.
                                     » The main project contractors should be         appears to have been factual inaccuracies
                                       contractually obligated to comply with the     in the compiled observations or
                                       sponsor's ESMP and to establish an internal    interpretations, or if important information
                                       monitoring system. Although contractor         was not presented to explain field
                                       compliance with the ESMP is the ultimate       observations, compliance assessment and
                                       responsibility of the sponsor, their           implementation strategies. However, to
                                       performance can be improved through
                                                                                      maintain credibility, it is critical that the
                                       involvement of the external monitor.
                                                                                      ultimate responsibility and decisions
                                                                                      regarding the content of final reporting for
                                                                                      public disclosure rests with the external
                                                                                      monitor.
                                  a role of the external monitor is to be in part
                                  the objective 'eyes and ears' of the lender,
                                                                                      Based on the experience of the Chad-
                                  this should not substitute, but rather
                                                                                      Cameroon project, it is recommended that
                                  supplement, the regular in-country project
                                                                                      the reports of the external monitor be
                                  supervision performed by the lender. For
                                                                                      published on a specific and clearly
                                  lenders with limited staff resources and
                                                                                      identifiable website. Due to limited access to
                                  capacity for supervision and monitoring
                                                                                      the internet in Chad and Cameroon, the
                                  activities, the role of the external monitor
                                                                                      World Bank country offices were instrumental
                                  assumes additional importance to successful
                                                                                      in distributing paper copies to government
                                  project implementation of the ESMP.
                                                                                      agencies, project affected communities,
                                                                                      and civil society groups. The ECMG made
                                                                                      efforts to confirm that sufficient dissemination
                                    Reporting the Findings of the                     of the previous report had taken place prior
                                    External Monitor                                  to subsequent project site visits.


                                  A robust and transparent reporting process is
                                                                                       Management of Change
                                  fundamental to the integrity of the external
                                  monitor. On the Chad-Cameroon project,
                                  the ECMG prepared ESMP compliance
                                                                                      Changes are a natural feature of any
                                  assessment reports after each site visit. These
                                                                                      complex project and do not necessarily
                                  reports were based on facts directly
                                                                                      indicate a problem but the initiation of a
                                  observed in the field with respect to the
                                                                                      process. Sponsors should be prepared for the
                                  Consortium's adherence to environmental
Page Twelve
                                                                                                     Lessons
                                                                                                 Lessons     of Experience
                                                                                                         of Experience     | August 2006 | Number 1
                                                                                                                        | September




                                                     significant ESMP changes; and iv) delineate
 Lesson 8 — “Ensuring                                when changes should be communicated to
 widespread public access to                         the lenders and host country governments.
 monitoring reports reinforces trust in
 the role of the external monitor.”                  The Chad-Cameroon ESMP focused primarily
                                                     on the pipeline right-of-way. From an
 » To maintain the perception of neutrality, it is   environmental and social standpoint,
   critical that the ultimate responsibility and     however, other important issues related to the                                  Ensuring
   decisions regarding the content of final          associated infrastructure of the pipeline
                                                                                                                                     widespread
   reporting for public disclosure rests with the    corridor were not given sufficient attention in
   external monitor.                                 the ESMP. These included impacts from                                           public access
 » External monitoring reports should be             construction camps, pipe yards, access                                          to monitoring
   published on a specific and clearly
                                                     roads, borrow pits, and land use planning for
   identifiable website. Paper copies of the                                                                                         reports reinforces
                                                     oil wells and related infrastructure. The
   report should be distributed and made
                                                     monitoring activities of the ECMG brought                                       trust in the role
   available to project affected stakeholders.
 » Widespread public access to monitoring            these issues to the attention of the Consortium                                 of the external
   reports reinforces the impartiality of the        and the lenders, and management of
                                                                                                                                     monitor.
   external monitor and the responsiveness to        change procedures were used to adjust the
   project impacts that affect stakeholders.         ESMP accordingly to account for these
 » Credible, objective reports assist the sponsor    project-related impacts.
   in demonstrating actions undertaken to
   reduce environmental and social impacts.
                                                     The management of change procedure for
                                                     the Chad-Cameroon project is, however,
                                                     primarily an internal sponsor process with only
                                                     vague procedures for external involvement
                                                     by the lender or government regulators.
need to add or adjust mitigation measures in
                                                     While this internal company procedure may
the ESMP resulting from new issues that were
                                                     be sufficient for small changes to the ESMP,
not previously identified or in recognition
                                                     such as defining new procedures for the
that despite the best planning intentions,
                                                     remediation of borrow pits, it may be less
mitigation measures may not be as effective
                                                     effective for negotiating and addressing
as originally designed and thus need to be
                                                     more significant issues that may require
modified. A procedural approach to
                                                     substantial changes to the ESMP.
managing change is essential to ensure that
the project continues to consistently conform
to its environmental and social commitments.

It is recommended that the sponsor establish
                                                     Erosion control measures on a river crossing in Cameroon.
a “management of change” procedure to
deal with changes in impacts from the
project and with the resulting mitigation
measures which need to be included in the
ESMP. At a minimum, the procedure should
have mechanisms which: i) identify material
project scope or design changes that have
not been included in the original ESMP; ii)
identify, through monitoring, mitigation
                                                                                                                 D'Appolonia S.p.A




measures that are not achieving results and
need to be altered; iii) establish criteria to
differentiate between minor changes and

                                                                                                                                     Page Thirteen
External Monitoring of the Chad-Cameroon Pipeline Project




                                 In instances where significant cultural
                                 properties, natural resources and habitats, or      Lesson 9 — “A procedural
                                 sensitive species are encountered and               approach to Management of
                                 potentially impacted, or where physical             Change is essential to ensure that
                                 relocation or economic displacement of              the project continues to conform to
                                 households are required, or changes to
                                                                                     its environmental and social
                                                                                     commitments.”
                                 project social and environmental standards
                                 and commitments are requested, the
                                                                                     » A management of change procedure is
                                 management of change procedures should
                                                                                       necessary to successfully adjust the ESMP to
                                 be established and the changes jointly
                                                                                       deal with unexpected environmental and
                                 assessed by the sponsor, the lender, the              social impacts during project
                                 external monitor, and government agencies             implementation.
                                 prior to the development of further                 » The external monitor can be a key resource
                                 mitigation measures. During the Chad-                 available to the lender group and the
                                 Cameroon project, the ECMG was primarily              Consortium for technical advice regarding
                                                                                       proposed ESMP adjustments.
                                 involved as a technical counterpart
                                                                                     » Various “classes of changes” should be
                                 available to the lender group and the
                                                                                       established to differentiate between the
                                 Consortium for technical advice regarding
                                                                                       degree of significance of the proposed
                                 proposed ESMP adjustments.                            changes with respect to the potential
                                                                                       environmental and social impact of the
                                 By involving all key stakeholders, the                project activities as defined in the ESMP.
                                 decisions regarding significant required            » For significant changes, the procedure
                                 changes to the ESMP can benefit from a                should involve mandatory consultation by
                                                                                       the project with lenders and the external
                                 discussion that meets the needs of all
                                                                                       monitor, before implementation of the
                                 stakeholders. It is important to note that in all
                                                                                       revised mitigation and monitoring
                                 considerations of ESMP changes, a balance
                                                                                       alternatives.
                                 is needed in the process to limit, to the
                                 extent possible, impacts to project
                                 development and unplanned costs while
                                 ensuring acceptable environmental and
                                 social outcomes.




Page Fourteen
                                                                                               Lessons of Experience | September 2006 | Number 1




Conclusion
Market forces are increasingly demanding
that companies take a proactive approach
towards managing the environmental and
social impacts of their projects. This IFC
Lessons of Experience publication has
demonstrated that external monitoring of




                                                                                                            D'Appolonia S.p.A
environmental and social commitments can                                                                                        The external
be a powerful resource to help lenders and                                                                                      monitor can be
their project sponsors reduce the risks
                                                                                                                                an influential tool
inherent to complex projects.
                                                  Completed restoration along the pipeline route.
                                                                                                                                to ensure that
Throughout the publication, the experiences                                                                                     environmental
of the External Compliance Monitoring
                                                                                                                                and social
Group (ECMG) on the Chad-Cameroon
pipeline project have highlighted the             For project affected communities and civil                                    commitments
technical value of an external monitor. This      society groups, the external monitor creates a                                are credibly
value is further enhanced by the external         reporting mechanism that acts as an
                                                                                                                                implemented
monitor's ability to increase the transparency,   independent source of information helping to
trust, and accountability between the key         reinforce the credibility and trust in the project                            in the eyes of
project stakeholders. While the decision to       sponsor required for successful projects. Host                                all project
employ an external monitor is related to          countries, who often suffer from limited
                                                                                                                                stakeholders.
the particular scale and complexity of            capacity to monitor the project themselves,
environmental and social issues associated        receive objective, technical, and publicly
with a project, the business case for external    disclosed assurance that the project is
monitoring is based on the monitor's ability to   achieving agreed environmental and social
enhance the company's approach to                 outcomes.
addressing project risk.
                                                  Complex projects require companies, lenders,
All project stakeholders stand to benefit from    project affected communities, civil society,
the involvement of an external monitoring         and governments to work as part of a
mechanism. Project sponsors receive an            partnership based on mutual responsibility
objective reporting record of their               and trust. The external monitor can be an
performance on environmental and social           influential tool to ensure that environmental
measures, which can reinforce the support of      and social commitments are credibly
project affected communities and defuse           implemented in the eyes of all project
the allegations of external critics. Lenders      stakeholders, resulting in projects that are
benefit from an unbiased set of “eyes and         economically, socially, and environmentally
ears” to assist them in ensuring project          sustainable.
outcomes meet their environmental and
social requirements.




                                                                                                                                 Page Fifteen
External Monitoring of the Chad-Cameroon Pipeline Project




                                         Acknowledgements

                                         “External Monitoring of the Chad-Cameroon Pipeline Project: Lessons of Experience” is the first
                                         in a new publication series prepared by the Environment and Social Development Department
         Lessons of Experience

                                         of the IFC for the purposes of internal learning and knowledge sharing with clients and the
                                         wider private sector. The publication was written by an IFC team comprising Christopher
                                         Frankel (Task Manager), Patty Miller and Rosa Orellana, and carried out under the general
                                         direction of Rachel Kyte (Director). Vanessa Manuel was responsible for design and layout.

                                         A special acknowledgement is due to the members of the External Compliance and
                                         Monitoring Group (ECMG) for their extensive written input and review efforts for this
                                         publication. They include Paolo Lombardo, Roberto Carpaneto, Lori Anna Conzo, and
                                         William J. Johnson, from the consulting firm D'Appolonia S.p.A, as well as private consultants
                                         Frédéric Giovannetti, Jean Le Bloas, Dr. Jorge Ossanai, and Dr. Clark A. Dobbs.

                                         The authors would also like to thank Mr. Ed Caldwell, Manager of Safety, Health and
                                         Environment for Esso Exploration and Production Chad Inc., for his review and comment
                                         on this publication.

                                         Thanks are also due to the following IFC/World Bank colleagues who reviewed earlier
                                         drafts: Rachel Kyte, Rashad Kaldany, Shahbaz Mavaddat, Richard Caines, Dennis Reyes,
                                         Debra Sequeira, Richard Wyness, Carlos Arias, John Butler, Eric Brusberg, and Eluma Obibuaku.




                                         IFC Good Practice Publications available at:
                                               www.ifc.org/enviropublications


                                                                                           The Baku-Tbilisi-Ceyhan (BTC) Pipeline Project:
                                                                                           Lessons of Experience

                                                                                           For IFC as a lender, the process of capturing lessons of
                                                                                           experience from projects in an important one. In the "BTC
                                                                                           Pipeline Project: Lessons of Experience," IFC environmental
                                                                                           and social staff look back on an extremely challenging
                                                                                           process and endeavor to extract some of the key
                                                                                           operational lessons and good practices for the benefit of
                                                                                           colleagues, clients, and the wider institution. While it is
                                                                                           impossible to capture all the challenges and complexities
                                                                                           encountered during the design and construction phase of
                                                                                           the BTC project, this publication focuses on six thematic
                                                                                           areas where environmental and social lessons learned
                                                                                           were thought to be most valuable and applicable to other
                                                                                           IFC-financed projects.


                                         For more information, please contact: International Finance Corporation,
                                         Environment and Social Development Department, 2121 Pennsylvania Avenue, N.W.,
                                         Washington, D.C. 20433, U.S.A.


                                   Disclaimer


                                     The views expressed in this publication are those of its authors and do not necessarily reflect the views of the wider institution.
                                     Some of the information used in this document may come from publicly available sources such as company websites and
                                     publications. The Lessons of Experience series does not represent a commitment by IFC to require projects it finances to take
                                     certain or all of the actions specified in this publication. Instead, any issues arising in an IFC-financed project will be evaluated
                                     and addressed in the context of the particular circumstances of the project.




Page Sixteen